JPH08183273A - Progress-managing book - Google Patents

Progress-managing book

Info

Publication number
JPH08183273A
JPH08183273A JP32763194A JP32763194A JPH08183273A JP H08183273 A JPH08183273 A JP H08183273A JP 32763194 A JP32763194 A JP 32763194A JP 32763194 A JP32763194 A JP 32763194A JP H08183273 A JPH08183273 A JP H08183273A
Authority
JP
Japan
Prior art keywords
sheet
construction
plan
progress management
progress
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
JP32763194A
Other languages
Japanese (ja)
Inventor
Yoshito Hoshino
嘉人 星野
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Misawa Homes Co Ltd
Original Assignee
Misawa Homes Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Misawa Homes Co Ltd filed Critical Misawa Homes Co Ltd
Priority to JP32763194A priority Critical patent/JPH08183273A/en
Publication of JPH08183273A publication Critical patent/JPH08183273A/en
Withdrawn legal-status Critical Current

Links

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

PURPOSE: To provide a progress-managing book in which the progress- management of a plan can be easily and effectively conducted and the plan can be smoothly performed without fault. CONSTITUTION: A plurality of entry sheets for describing various items (an inspection result, an approval seal, a name in charge, an inspecting date to be, a form forming date, etc.) necessary to manage the progress of a plan, and a content list 20 in which the available period of the forms and related name for the forms are indicated are bound as one progress-managing book 10. It is preferable to dispose and display the name of the fill-in forms and the related person name in the process order of the plan in the list 20. Further, it is preferable to provide a process table, an inspection sheet and a report as the fill-in form.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明は、複数のシートを束ねて
形成された各種計画の進行管理に用いられる進行管理帳
に関し、例えば、建物の建設計画の進行管理などに利用
できる。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a progress management book used for progress management of various plans formed by bundling a plurality of sheets, and can be used, for example, for progress management of building construction plans.

【0002】[0002]

【背景技術】一般に、建物の建設や土木工事等は、複数
の工程を有し、各工程内においても様々な内容の作業が
行われることに加え、計画に携わる関係者が多いため、
これらの計画の遂行には、徹底した進行管理が必要とな
る。そして、この進行管理には、通常、計画を構成する
各工程や各作業を実施する時期や時間を管理する時間的
管理、および各工程や各作業が正常に完了したか否かを
検査する内容的管理が含まれる。従来より、このような
各種計画の進行管理は、スケジュール表等を用いて時間
的管理を行ったり、あるいはチェックシート等を用いて
内容的管理を行ったりしていた。
[Background Art] In general, building construction, civil engineering work, etc. have multiple processes, and in addition to the work of various contents being performed in each process, there are many people involved in planning,
In order to carry out these plans, thorough progress management is required. The progress management usually includes a time management for managing the time and time for carrying out each process and each work constituting a plan, and a content for inspecting whether each process or each work is normally completed. Management is included. Conventionally, such progress management of various plans has been performed by time management using a schedule table or the like, or by content management using a check sheet or the like.

【0003】[0003]

【発明が解決しようとする課題】しかしながら、従来の
進行管理方法では、スケジュール表等を用いて計画の全
体的な進行管理を行ったり、あるいは各工程毎若しくは
各作業単位毎に個別に用意されたチェックシート等を用
いて計画の各部分の作業内容を各部分毎に検査すること
により部分的に詳細な進行管理を行うことはできるもの
の、これらのスケジュール表や各チェックシート等はば
らばらに存在しているため、各チェックシートを実際に
使用する時期が不明確であることから、必ずしも適切な
タイミングで各検査が行われておらず、計画の進行管理
が円滑に行われていなかった。
However, in the conventional progress management method, the overall progress management of the plan is performed by using a schedule table or the like, or it is individually prepared for each process or each work unit. Although it is possible to carry out partial detailed progress management by inspecting the work contents of each part of the plan using check sheets etc., these schedule tables and each check sheet etc. are scattered. Since it is unclear when each check sheet will actually be used, each inspection was not always performed at an appropriate timing, and the progress management of the plan was not performed smoothly.

【0004】また、これらのスケジュール表や各チェッ
クシート等に関係する者、例えば、各シートに必要事項
の記入を行って各シートを作成する者、各シートの記入
事項の確認や承認を行う者、作成された各シートの配付
を受ける者などが不明確であるため、このことも円滑な
進行管理を阻害する要因となっていた。このため、一連
の計画の全体に渡って、各工程の各作業内容に関する検
査項目が体系的に整理されかつ確実に網羅され、漏れな
く検査を行って計画を確実に遂行できるとともに、各検
査を適切なタイミングで実施でき、計画を滞りなく円滑
に遂行できる進行管理方法が望まれていた。
Further, a person related to the schedule table and each check sheet, for example, a person who fills in each sheet with necessary items to create each sheet, and a person who confirms and approves the entered items in each sheet. Since it is unclear who will receive each of the created sheets, this also hinders smooth progress management. Therefore, the inspection items related to each work content of each process are systematically organized and reliably covered throughout the series of plans, and the inspection can be performed without omission and the plan can be surely executed. There was a need for a progress management method that could be implemented at an appropriate time and that could carry out a plan smoothly and smoothly.

【0005】本発明の目的は、計画の進行管理を容易か
つ確実に行うことができ、計画を落ち度無く円滑に遂行
できる進行管理帳を提供することにある。
An object of the present invention is to provide a progress management book capable of easily and reliably managing the progress of a plan and smoothly executing the plan without failure.

【0006】[0006]

【課題を解決するための手段】本発明は、計画の進行管
理に必要な各シートを一冊に束ねて有機的に結合させる
ことにより前記目的を達成しようとするものである。具
体的には、本発明の進行管理帳は、計画の進行管理に必
要な各種事項を記入する複数の記入用紙と、これらの記
入用紙とともに綴じられて各記入用紙の使用時期および
各記入用紙に関係する関係者名が示された内容一覧と、
を備えたことを特徴とする。ここで、内容一覧には、各
記入用紙の名称および関係者名が計画の進行順に配置さ
れて表示されていることが望ましい。また、記入用紙に
は、計画の各工程の関連を示す工程表と、計画の進行管
理中に行われる検査で用いる検査シート(例えば、監理
時に用いる監理シートや立合時に用いる立合シート等)
と、計画の各工程の完了報告で用いる報告書と、が含ま
れていることが望ましい。さらに、記入用紙に記入され
る計画の進行管理に必要な各種事項とは、検査結果、承
認印、担当者名、検査予定日、用紙作成日等である。
DISCLOSURE OF THE INVENTION The present invention is intended to achieve the above object by bundling each sheet necessary for the progress management of a plan and organically binding them. Specifically, the progress management book of the present invention is composed of a plurality of entry sheets for entering various items necessary for the progress management of the plan, and the time when each entry sheet is used and each entry sheet to be bound together with these entry sheets. A list of contents showing the names of the parties concerned,
It is characterized by having. Here, it is desirable that the name of each entry form and the name of the person concerned are arranged and displayed in the order of progress of the plan in the content list. In addition, on the entry form, a process chart showing the relationship between each process of the plan and an inspection sheet used in the inspection performed during the progress management of the plan (for example, a supervision sheet used during supervision or a standing sheet used during standing)
And the report used for the completion report of each step of the plan should be included. Further, various items necessary for managing the progress of the plan to be entered on the entry form include the inspection result, the approval stamp, the name of the person in charge, the scheduled date of inspection, the date of paper preparation, and the like.

【0007】そして、本発明の進行管理帳の好適な適用
例としては、計画を建物の建設計画とし、進行管理を建
設現場の管理とし、計画に、着工、基礎、組立、造作、
および竣工の各工程が含まれるものが挙げられる。
As a preferred application example of the progress management book of the present invention, the plan is a construction plan of the building, the progress management is management of the construction site, and the start, foundation, assembly, fabrication,
And those that include each process of completion.

【0008】[0008]

【作用】このような本発明においては、内容一覧に示さ
れた各記入用紙の使用時期および各記入用紙に関係する
関係者名に従って、各記入用紙に、計画の進行管理に必
要な各種事項を記入していき、必要に応じて各記入用紙
の配付を行う。このため、各記入用紙の使用時期が明確
になることから、計画中の各作業の検査(作業が正常に
完了しているか否かのチェック)やその承認、報告等が
適切なタイミングで行われるようになり、計画が円滑に
遂行される。また、各記入用紙に関係する関係者名、例
えば、各シートに必要事項の記入を行って各シートを作
成する者、各シートの記入事項の確認や承認を行う者、
作成された各シートの配付を受ける者などが明確になる
ことから、記入、承認、配付等の進行管理に係る各処理
を迅速に行うことが可能となるうえ、間違った配付等の
不都合が生じるおそれもなくなる。そして、内容一覧お
よび各記入用紙は、ばらばらに存在するのではなく、一
冊の進行管理帳として体系的に綴じられているので、チ
ェック漏れや用紙間違い等の不都合が生じるおそれはな
く、計画が落ち度無く円滑に遂行されるようになり、こ
れらにより前記目的が達成される。
According to the present invention as described above, various items necessary for managing the progress of the plan are recorded on each entry sheet according to the use period of each entry sheet shown in the content list and the name of the person related to each entry sheet. Fill out the form and distribute each form as needed. For this reason, the timing of use of each entry form becomes clear, so inspection of each planned work (check whether the work is completed normally), its approval, and reporting are performed at appropriate timing. And the plan goes smoothly. In addition, the name of the person related to each entry form, for example, the person who fills out the required items on each sheet to create each sheet, the person who confirms and approves the entries on each sheet,
Since it becomes clear who will receive each created sheet, it will be possible to quickly perform each process related to progress management such as entry, approval, and distribution, and inconvenience such as incorrect distribution will occur. There is no fear. Since the content list and each entry form are not separated but are systematically bound as a single progress management book, there is no risk of omission of checks or incorrect forms, and there is no need to plan. The operation is smoothly performed without fail, and the above-mentioned objects are achieved by these.

【0009】また、内容一覧に、各記入用紙の名称およ
び関係者名を計画の進行順に配置表示した場合には、検
査等の順序や時期が直感的に把握しやすくなり、計画の
進行管理がより一層円滑に行われる。
Further, when the names of the respective filling sheets and the names of persons concerned are arranged and displayed in the contents list in the order of progress of the plan, it becomes easy to intuitively grasp the order and timing of the inspections, etc. It is done even more smoothly.

【0010】さらに、記入用紙として、計画の各工程の
関連を示す工程表と、計画の進行管理中に行われる検査
で用いる検査シートと、計画の各工程の完了報告で用い
る報告書とを設けた場合には、検査とその報告とを一連
の処理として扱うことができ、より一層漏れのない処理
が行われるようになるうえ、工程表に各工程の開始予定
日あるいは完了予定日等を記入することにより、計画全
体の日程の概要が容易に把握可能となる。
Further, as a form, a process chart showing the relationship between each process of the plan, an inspection sheet used in the inspection performed during the progress management of the plan, and a report used for the completion report of each process of the plan are provided. In this case, the inspection and its report can be handled as a series of processing, and more thorough processing will be performed, and the scheduled start date or scheduled completion date of each process will be entered in the process chart. By doing so, it is possible to easily grasp the outline of the schedule of the entire plan.

【0011】また、本発明の進行管理帳を、建物の建設
計画における建設現場の管理に適用した場合には、着
工、基礎、組立、造作、および竣工という多くの工程が
あることと、計画に携わる関係者が多いことから、本発
明の作用・効果が一層顕著に発揮されるようになる。
In addition, when the progress management book of the present invention is applied to management of a construction site in a building construction plan, there are many steps of construction, foundation, assembly, fabrication, and completion, and Since there are many involved persons, the action and effect of the present invention will be more remarkably exhibited.

【0012】[0012]

【実施例】以下、本発明の一実施例を図面に基づいて説
明する。図1〜図5には、本実施例に係る建物の建設計
画に用いられる進行管理帳10を構成する各シートが示
されている。進行管理帳10には、計画の進行管理に必
要な各種事項を記入する複数の記入用紙30(図2〜図
5参照)と、各記入用紙30の使用時期および各記入用
紙30に関係する関係者名が示された内容一覧20(図
1参照)とが綴じられている。通常、内容一覧20は、
各記入用紙30の前に綴じられて進行管理帳10の目次
としての役割を果たし、表紙の次若しくは表紙の近傍に
綴じられるか、あるいは表紙そのものとして綴じられて
いる。
An embodiment of the present invention will be described below with reference to the drawings. 1 to 5 show each sheet constituting the progress management book 10 used in the building construction plan according to the present embodiment. The progress management book 10 includes a plurality of entry sheets 30 (see FIGS. 2 to 5) for entering various items necessary for the progress management of the plan, a use period of each entry sheet 30, and a relationship related to each entry sheet 30. A content list 20 (see FIG. 1) showing the names of persons is bound. Normally, the content list 20 is
It is bound in front of each entry sheet 30 and serves as a table of contents of the progress management book 10, and is bound next to the cover, in the vicinity of the cover, or as the cover itself.

【0013】これらの内容一覧20および各記入用紙3
0の各々は、糊付け等されている綴じ込み部11から剥
がされて進行管理帳10から取り外し可能となってい
る。そして、各記入用紙30は、それぞれ配付先数等に
応じて複数枚ずつ用意され、各種類についての先頭のシ
ートに記入を行うと、二枚目以降のシートにも同じ内容
が複写により記入されるようになっている。また、進行
管理帳10の最終シート(うら表紙)を、厚手のボール
紙等の比較的硬質のシートとしておけば、各シートへの
記入が容易になる。
These contents list 20 and each entry form 3
Each of the numbers 0 is peeled off from the binding portion 11 that is glued or the like and is removable from the progress management book 10. A plurality of each of the filling sheets 30 is prepared according to the number of recipients, etc. When the first sheet for each type is filled, the same contents are copied and copied on the second and subsequent sheets. It has become so. If the final sheet (back cover) of the progress management book 10 is a relatively hard sheet such as thick cardboard, it is easy to fill in each sheet.

【0014】記入用紙30には、計画の各工程の関連を
示す工程表40(図2参照)と、計画の進行管理中に行
われる検査で用いる着工監理シート51(図3参照)や
着工立合シート52(図4参照)等の各種の検査シート
50と、計画の各工程の完了報告で用いる着工報告書6
1(図5参照)等の各種の報告書60とが含まれてい
る。さらに、記入用紙30には、図示はされていない
が、引渡後に用いる施工評価表や工事中に用いる指示
票、さらには監理担当者(現場管理者)から構造体検査
を行う検査員に宛てられる構造体検査依頼書や竣工検査
を行う検査員に宛てられる竣工検査依頼書も含まれてい
る。
The entry sheet 30 includes a process chart 40 (see FIG. 2) showing the relationship between each process of the plan, a construction management sheet 51 (see FIG. 3) and a construction start-up sheet used in the inspection performed during the progress management of the plan. Various inspection sheets 50 such as the sheet 52 (see FIG. 4), and the construction report 6 used for the completion report of each process of the plan
1 (see FIG. 5) and various other reports 60 are included. Further, although not shown in the form 30, the construction evaluation table used after delivery, the instruction sheet used during the construction, and the supervisor (field manager) are addressed to the inspector who conducts the structural inspection. It also includes a structural inspection request form and a completion inspection request form addressed to the inspectors who perform the completion inspection.

【0015】また、検査シート50には、前述した着工
立合時に用いる着工監理シート51や着工立合シート5
2の他に、基礎完了時に用いる基礎監理シート、組立立
合時に用いる組立監理シート、組立工事に用いる安全監
理シート(安全管理シート)、造作中に用いる造作監理
シート、工事完成時に用いる竣工監理シート、竣工立合
時に用いる竣工立合シートが用意されている。
Further, the inspection sheet 50 includes the start supervision sheet 51 and the start standing sheet 5 used at the start of the above-mentioned start.
In addition to 2, a basic supervision sheet used when completing the foundation, an assembly supervision sheet used when assembling the assembly, a safety supervision sheet used for assembly work (safety management sheet), a construction supervision sheet used during construction, a completion supervision sheet used at the completion of construction, A completion completion sheet to be used at the time of completion is prepared.

【0016】そして、報告書60には、前述した着工立
合時の報告に用いる着工報告書61の他に、組立立合時
の報告に用いる上棟報告書、竣工立合時に用いる竣工報
告書が用意されている。
In addition to the above-mentioned construction start report 61 used for the start-up status report, the report 60 includes an upper building report used for the assembly start-up report and a completion report used for the completion start-up. There is.

【0017】図1において、内容一覧20の上部には、
「現場管理シートの内容」というタイトル20Aが表示
されている。タイトル20Aの下側には、図中左側か
ら、各記入用紙30の使用時期が表示された使用時期表
示欄20B、各記入用紙30のうち現場管理者が用いる
ものに係る情報が表示された現場管理者用表示欄20C
と、各記入用紙30のうち施主への報告に用いるものに
係る情報が表示された施主報告用表示欄20Dとが設け
られている。
In FIG. 1, at the top of the content list 20,
The title 20A "contents of the site management sheet" is displayed. Below the title 20A, from the left side of the figure, a usage time display column 20B displaying the usage time of each entry sheet 30 and a site displaying information on the entry sheet 30 used by the site manager Display column for administrator 20C
And a display field 20D for the owner report, which displays information related to each of the entry forms 30 used for reporting to the owner.

【0018】現場管理者用表示欄20Cは、各記入用紙
30の名称(帳票名)が表示された名称表示欄20E
と、各記入用紙30に関係する関係者名(関係先)が表
示された関係者名表示欄20Fとに区分されている。施
主報告用表示欄20Dは、各記入用紙30の名称(帳票
名)が表示された名称表示欄20Gと、各記入用紙30
に関係する関係者名(関連先)が表示された関係者名表
示欄20Hとに区分されている。
The field manager display field 20C is a name display field 20E in which the name (form name) of each entry sheet 30 is displayed.
And a related person name display field 20F in which related person names (related parties) related to each entry sheet 30 are displayed. The owner report display column 20D includes a name display column 20G in which the name (form name) of each entry sheet 30 is displayed and each entry sheet 30.
The related person name display field 20H in which the related person name (related destination) is displayed.

【0019】そして、これらの使用時期表示欄20B、
現場管理者用表示欄20Cの各欄20E,20F、施主
報告用表示欄20Dの各欄20G,20Hは、縦方向に
並べて配置され、それぞれ上側から下側に向かって各項
目の内容が計画の進行順に表示されている。また、内容
一覧20の横方向については、同じ使用時期に係る内容
どうしが対応している。なお、内容一覧20の空欄の部
分は、ディーラー独自帳票欄として使用することができ
る。
Then, these use time display columns 20B,
The fields 20E and 20F of the field manager display field 20C and the fields 20G and 20H of the owner report display field 20D are arranged side by side in the vertical direction, and the content of each item is planned from the upper side to the lower side. They are displayed in order of progress. In the horizontal direction of the contents list 20, contents related to the same use period correspond to each other. The blank portion of the content list 20 can be used as a dealer-specific form column.

【0020】使用時期表示欄20Bには、上側から下側
に向かって、着工前打合せ時、着工工程の着工打合時、
基礎工程の基礎完了時、組立工程の組立立合時や組立工
事、造作工程の造作中、竣工工程の工事完成時や竣工立
合時、引渡後、工事中の順に各使用時期が表示されてい
る。なお、一番下の工事中は、計画の進行順に対応して
いないが、これは必要に応じて適宜用いる指示票の使用
時期を示すものだからである。
In the use time display column 20B, from the upper side to the lower side, during the pre-working meeting, the start-up meeting of the starting process,
When the foundation of the basic process is completed, at the time of assembling the assembly process, assembling work, during the creation of the manufacturing process, at the time of completion of the completion process or at the completion of construction, after delivery, during use, each usage time is displayed in order. It should be noted that the construction work at the bottom does not correspond to the order of progress of the plan, because this indicates the time of use of the instruction sheet that is appropriately used as necessary.

【0021】現場管理者用表示欄20Cの名称表示欄2
0Eには、上側から下側に向かって、着工監理シート5
1、着工立合シート52、基礎監理シート、組立監理シ
ート、安全監理シート、造作監理シート、竣工監理シー
ト、竣工立合シート、施工評価票、指示票の順に各シー
ト名称が表示されている。施主報告用表示欄20Dの名
称表示欄20Gには、上側から下側に向かって、工程表
40、着工報告書61、上棟報告書、竣工報告書の順に
各シート名称が表示されている。
Name display field 2 of the field manager display field 20C
For 0E, start-up supervision sheet 5 from top to bottom
1, each of the sheet names is displayed in the order of the start construction sheet 52, the basic supervision sheet, the assembly supervision sheet, the safety supervision sheet, the construction supervision sheet, the construction supervision sheet, the completion supervision sheet, the construction evaluation sheet, and the instruction sheet. In the name display column 20G of the owner report display column 20D, sheet names are displayed in this order from the upper side to the lower side of the process chart 40, the construction report 61, the upper building report, and the completion report.

【0022】現場管理者用表示欄20Cの関係者名表示
欄20F、および施主報告用表示欄20Dの関係者名表
示欄20Hには、(施):施主、(A):A業者、
(建):現場管理者、工務課、(総):総務・経理課
(工務課より回付する)という各関係者名が、左側に表
示されている各記入用紙30に対応して表示されてい
る。例えば、工程表40の関係者は、その右側に表示さ
れた(施)、(建)、(A)である。また、各関係者名
の略記号(施)、(A)、(建)、(総)の意味は、内
容一覧20の下部の脚注欄20Jに示されている。
In the relevant person name display column 20F of the field manager display column 20C and the relevant person name display column 20H of the owner report display column 20D, (administration): owner, (A): A trader,
(Construction): Site manager, construction section, (general): General affairs / accounting section (circulated from the construction section), the name of each person concerned is displayed in correspondence with each entry form 30 displayed on the left side. ing. For example, the persons related to the process chart 40 are (application), (construction), and (A) displayed on the right side thereof. The meanings of the abbreviations (custom character), (A), (built), and (total) of the names of the parties concerned are shown in the footnote column 20J at the bottom of the content list 20.

【0023】図2において、工程表40は、各記入用紙
30の先頭に綴じられている。工程表40の上部には、
「工程表」というタイトル40Aが表示されている。工
程表40は、着工前打合せ時に用いられて各必要事項を
記入され、工事全体の日程の概要を施主(客先)に提示
するものである。タイトル40Aの右側には、工程表4
0の作成日を記入する作成日記入欄40Bが設けられて
いる。タイトル40Aの左側には、工程表40を配付す
る配付先が表示された配付先欄40Sが設けられてい
る。この配付先欄40Sの表示内容は、複数用意された
工程表40毎に異なるものとなっている。また、タイト
ル40Aの下側には、工事名(〜様邸新築工事など)、
建設地、ディーラー名、指定工事店名、予定工期、建物
タイプ、現場管理者名およびその印、工事主任者という
工事に関する基本事項を記入する基本事項記入欄40C
が設けられている。
In FIG. 2, the process chart 40 is bound at the top of each entry sheet 30. At the top of the process chart 40,
A title 40A called "process chart" is displayed. The process chart 40 is used at the meeting before the start of construction, in which each necessary item is entered, and the summary of the schedule of the entire construction is presented to the client (customer). On the right side of the title 40A, the process chart 4
A creation date entry field 40B for entering the creation date of 0 is provided. On the left side of the title 40A, a distribution destination column 40S in which a distribution destination to distribute the process chart 40 is displayed is provided. The display content of the distribution destination column 40S is different for each of the prepared process charts 40. Also, below the title 40A, the construction name (such as new house construction work),
Basic item entry column 40C for entering basic items related to construction such as construction site, dealer name, designated construction shop name, planned construction period, building type, site manager name and its mark, construction chief
Is provided.

【0024】基本事項記入欄40Cの下側には、各工程
の完了等の計画進行の節目となる予定日を記入する複数
の予定日記入欄40Eが、進行順に従って上側から下側
に向かって設けられている。各予定日記入欄40Eに
は、上側から、着工前打合せ、本体工事着工、基礎工事
完了、組立工事完了、造作工事完了、本体工事完了、竣
工立会い、引渡しの各予定日(既に開始されている時に
は実施日)が記入されるようになっている。
Below the basic item input field 40C, a plurality of scheduled date input fields 40E for entering an expected date which becomes a milestone of the plan progress such as completion of each process are arranged from the upper side to the lower side in the order of progress. It is provided. In each scheduled date entry field 40E, from the upper side, scheduled dates for pre-construction meeting, main body construction start, foundation construction completion, assembly work completion, fabrication work completion, main body construction completion, completion witness, and delivery (already started Sometimes the implementation date) is filled in.

【0025】予定日記入欄40Eの左側には、建設計画
の進行管理中に行われる各検査事項40Fの実施時期が
矢印により表示されている。検査事項40Fには、上側
から、着工監理、基礎監理、組立監理、構造体検査、公
庫現場審査、造作監理、竣工監理、竣工検査がある。
On the left side of the planned date entry field 40E, the execution time of each inspection item 40F performed during the progress management of the construction plan is displayed by an arrow. Inspection items 40F include start-up supervision, basic supervision, assembly supervision, structural inspection, public housing site inspection, production supervision, completion supervision, and completion inspection from the top.

【0026】図3において、着工監理シート51は、工
程表40の次に綴じられている。着工監理シート51の
上部には、「着工監理シート」というタイトル51Aが
表示されている。タイトル51Aの右側には、着工監理
シート51の作成完了日を記入する作成日記入欄51B
が設けられている。タイトル51Aの左側には、着工監
理シート51を配付する配付先が表示された配付先欄5
1Sが設けられている。この配付先欄51Sの表示内容
は、複数用意された着工監理シート51毎に異なるもの
となっている。作成日記入欄51Bの下側には、建設責
任者の検印欄51C、および監理担当者(現場管理者)
の押印欄51Dが設けられている。
In FIG. 3, the construction supervision sheet 51 is bound after the process chart 40. On the upper part of the start-up supervision sheet 51, a title 51A called "start-up supervision sheet" is displayed. On the right side of the title 51A, a creation date entry field 51B for entering the completion date of creation of the construction supervision sheet 51
Is provided. On the left side of the title 51A, the distribution destination column 5 in which the distribution destination to distribute the construction supervision sheet 51 is displayed
1S is provided. The display contents of the distribution destination column 51S are different for each of the prepared construction supervision sheets 51. Below the creation date entry field 51B, a construction manager's stamp field 51C and a supervisor (field manager)
The stamp field 51D is provided.

【0027】タイトル51Aの左下側には、工事名(〜
様邸工事など)を記入する工事名記入欄51Eが設けら
れている。工事名記入欄51Eの下側には、次工程の監
理事項である基礎監理の予定日を記入する監理予定日記
入欄51Fが設けられている。基礎監理予定日記入欄5
1Fの右側には、着工工程の完了する予定日を記入する
完工予定日記入欄51Gが設けられている。
On the lower left side of the title 51A, the construction name (~
A work name entry field 51E is provided for entering the name of the house. Below the construction name entry field 51E, there is provided a scheduled management date entry field 51F for entering the scheduled date of basic supervision, which is a supervision item for the next process. Basic supervision schedule date entry field 5
On the right side of 1F, there is provided a planned completion date entry field 51G in which the expected date of completion of the construction process is entered.

【0028】基礎監理予定日記入欄51Fおよび完工予
定日記入欄51Gの下側には、左側から、監理する各項
目が表示された項目欄51H、各項目の詳細内容が表示
された内容欄51J、各内容の判定結果を記入する確認
欄51K、判定結果が不合格の際に不合格内容の指摘お
よび補修方法・取替・再施工等の指示事項を具体的に記
入する指示事項欄51L、不合格事項の処理完了後に再
確認をした旨を記入する再確認欄51Mが縦方向に並べ
て配置されている。
Below the basic supervision scheduled date entry column 51F and the completion date scheduled entry column 51G, from the left side, an item column 51H showing each item to be supervised, and a content column 51J showing detailed contents of each item. , A confirmation column 51K in which the judgment result of each content is entered, and an instruction item column 51L in which, when the judgment result is unsuccessful, the failure contents are pointed out and instructions such as a repair method, replacement, and reconstructing are specifically entered. A reconfirmation column 51M in which the reconfirmation is entered after the processing of the rejected items is completed is arranged side by side in the vertical direction.

【0029】項目欄51Hには、例えば、敷地、地縄張
り、統一看板、部材搬入、設備、遣方、打合事項他(施
主、工事主任)等の各項目が表示されている。内容欄5
1Jには、左側の各項目に付き、一つまたは複数の詳細
内容が表示されている。例えば、項目「敷地」について
は、その詳細内容として、例えば、「境界石・境界線の
確認、施主の承認」、「敷地形状・寸法・方位の確
認」、「道路・燐地との高低差・擁壁の確認」、「道路
の位置・巾員の確認」、「整地状況、障害物の確認」、
「地盤の確認」などが表示されている。また、監理項目
の中でも特に重要なものには、網掛け、色付け等による
差別化が行われ、確実に監理できるようになっている。
In the item column 51H, for example, each item such as site, territory, unified signboard, member loading, equipment, manner of use, meeting matters (owner, construction chief) and the like are displayed. Content column 5
In 1J, one or more detailed contents are displayed for each item on the left side. For example, the detailed contents of the item "Site" include "Confirmation of boundary stones / boundary lines, approval of owner", "Confirmation of site shape / dimensions / direction", "Difference in height from road / phosphorus land".・ Confirmation of retaining wall, "Confirmation of road position / width", "Confirmation of ground level, obstacles",
“Confirmation of the ground” is displayed. In addition, the most important management items are differentiated by shading, coloring, etc., so that they can be managed reliably.

【0030】確認欄51Kには、例えば、○:合格、
△:当日手直し後合格、×:不合格のいずれかを記入す
るようにする。さらに、着工監理シート51の下部に
は、各種の連絡事項を記入する連絡事項記入欄51Nが
設けられている。
In the confirmation column 51K, for example, ◯: pass,
△: After reworking on the day, pass: ×: Not pass Further, below the start-up supervision sheet 51, there is provided a contact item entry field 51N for entering various contact items.

【0031】図4において、着工立合シート52は、着
工監理シート51の次に綴じられている。着工立合シー
ト52の上部には、「着工立合シート」というタイトル
52Aが表示されている。タイトル52Aの右側には、
着工立合シート52の担当者側の作成完了日を記入する
作成日記入欄52Bが設けられている。タイトル52A
の左側には、着工立合シート52を配付する配付先が表
示された配付先欄52Sが設けられている。この配付先
欄52Sの表示内容は、複数用意された着工立合シート
52毎に異なるものとなっている。
In FIG. 4, the construction start sheet 52 is bound after the construction supervision sheet 51. On the upper part of the start-up standing sheet 52, a title 52A of "start-up standing sheet" is displayed. To the right of title 52A,
A creation date entry field 52B is provided in which the completion date of creation of the start date sheet 52 by the person in charge is entered. Title 52A
On the left side of, there is provided a distribution destination column 52S displaying a distribution destination to distribute the start-up status sheet 52. The display content of the distribution destination column 52S is different for each of the plurality of prepared starter standing sheets 52.

【0032】作成日記入欄52Bの下側には、ディーラ
ー名を記入するディーラー名記入欄52Cが設けられ、
さらにその下側には、立合検査担当者の名前を記入して
その印を押す担当者名記入欄52Dが設けられている。
タイトル52Aの左下側には、検査に立ち合った施主の
名前(客先の名称)を宛名として記入する宛名記入欄5
2Eが設けられている。
Below the creation date entry field 52B, a dealer name entry field 52C for entering a dealer name is provided.
Further, below that, there is provided a person in charge name entry field 52D for entering the name of the person in charge of the on-site inspection and pressing the mark.
On the lower left side of the title 52A, an address entry field 5 in which the name of the owner (customer name) who attended the inspection is entered as an address
2E is provided.

【0033】宛名記入欄52Eおよび担当者名記入欄5
2Dの下側には、図3の着工監理シート51の場合と同
様に、左側から、立合検査の各項目が表示された項目欄
52H、各項目の詳細内容が表示された内容欄52J、
各内容の検査結果を記入する確認欄52K、検査結果が
不合格の際に不合格内容の指摘および補修方法・取替・
再施工等の指示事項を具体的に記入する指示事項欄52
L、不合格事項の処理完了後に再確認をした旨を記入す
る再確認欄52Mが縦方向に並べて配置されている。
Address entry field 52E and person in charge name entry field 5
On the lower side of 2D, as in the case of the construction supervision sheet 51 of FIG. 3, from the left side, an item column 52H in which each item of the inspection is displayed, a content column 52J in which detailed contents of each item are displayed,
Confirmation column 52K to enter the inspection result of each content, pointing out the failure content when the inspection result fails and repairing method / replacement /
Instruction column 52 for concretely entering instructions such as re-construction
L, a reconfirmation column 52M in which the reconfirmation is entered after the processing of the rejected items is completed is arranged side by side in the vertical direction.

【0034】さらに、着工立合シート52の下部には、
着工検査に立ち合った施主の名前(客先の名称)が記入
されてその承認印が押される施主承認欄52N、および
その承認の日付を記入する承認日記入欄52Pが設けら
れている。
Further, in the lower part of the start-up standing sheet 52,
An owner approval column 52N in which the name of the owner (customer's name) who attends the start inspection is entered and an approval stamp is stamped, and an approval date entry column 52P in which the approval date is entered are provided.

【0035】図5において、着工報告書61は、着工立
合シート52の次に綴じられている。着工報告書61の
上部には、「着工報告書」というタイトル61Aが表示
されている。タイトル61Aの左側には、着工報告書6
1を配付する配付先が表示された配付先欄61Sが設け
られている。この配付先欄61Sの表示内容は、複数用
意された着工報告書61毎に異なるものとなっている。
タイトル61Aの左下側には、施主の名前(客先の名
称)を宛名として記入する施主名記入欄61Bが設けら
れている。施主名記入欄61Bの右側には、施主の承認
印が押される施主承認印欄61Cが設けられている。
In FIG. 5, the construction report 61 is bound next to the construction standing sheet 52. At the upper part of the construction report 61, a title 61A called "construction report" is displayed. On the left side of title 61A, construction report 6
A distribution destination column 61S in which a distribution destination to which 1 is distributed is displayed is provided. The display contents of the distribution destination column 61S are different for each of the plurality of prepared construction reports 61.
On the lower left side of the title 61A, a client name entry field 61B for entering the client name (customer name) as an address is provided. On the right side of the owner name entry field 61B, there is provided an owner approval stamp field 61C on which an approval stamp of the owner is stamped.

【0036】施主名記入欄61Bおよび施主承認印欄6
1Cの下側には、着工時の監理内容がチェック項目毎に
表示された報告事項表示欄61Dが設けられている。こ
の報告事項表示欄61Dには、例えば、「1、敷地形状
・境界石・方位等の確認」、「2、道路・燐地との高低
差等の確認」等のチェック項目が表示されている。
Owner name entry field 61B and owner approval stamp field 6
Below the 1C, there is provided a report item display field 61D in which the contents of supervision at the start of construction are displayed for each check item. In the report item display column 61D, for example, check items such as "1. Confirmation of site shape / boundary stone / direction", "2. Confirmation of height difference with road / phosphorus land" are displayed. .

【0037】報告事項表示欄61Dの右下側には、着工
報告書61の作成日を記入する作成日記入欄61E、デ
ィーラー名を記入するディーラー名記入欄61F、およ
び各監理内容のチェックを行った監理担当者(現場管理
者)の押印欄61Gが設けられている。
On the lower right side of the report item display field 61D, a creation date entry field 61E for entering the creation date of the construction report 61, a dealer name entry field 61F for entering the dealer name, and each supervision content are checked. A stamp field 61G for the supervising person in charge (site manager) is provided.

【0038】着工報告書61の下部は、施主宛の着工金
(契約によるもの)の請求書になっている。この請求書
には、社印を押すものとする。ディーラー名記入欄61
Fの下側には、「御請求書」というタイトル61Hが表
示されている。タイトル61Hの右側には、請求書発行
日を記入する発行日記入欄61Jが設けられている。タ
イトル61Hの下側には、請求書を発行するディーラー
名を記入するディーラー名記入欄61Kが設けられてい
る。さらに、ディーラー名記入欄61Kの下側には、着
工金の請求金額を記入する金額記入欄61L、振込銀行
やその口座番号等を記入する振込先記入欄61M、およ
び振込期限を記入する振込期限記入欄61Nが設けられ
ている。
The lower part of the construction report 61 is an invoice for the construction fee (by contract) addressed to the owner. This invoice shall bear the company seal. Dealer name entry field 61
On the lower side of F, a title 61H of "invoice" is displayed. On the right side of the title 61H, an issue date entry field 61J for entering the invoice issue date is provided. Below the title 61H, there is provided a dealer name entry field 61K for entering the name of the dealer who issues the invoice. Further, below the dealer name entry field 61K, an amount entry field 61L for entering the amount of the start-up charge, a destination entry field 61M for entering the transfer bank and its account number, and a transfer deadline for entering the transfer deadline. An entry field 61N is provided.

【0039】また、検査シート50のうち図3の着工監
理シート51以外の各監理シート、つまり基礎監理シー
ト、組立監理シート、安全監理シート、造作監理シー
ト、竣工監理シートは、着工監理シート51と同様な構
成とされ、各工程において、各監理項目のチェックを詳
細に行うことができるとともに建設責任者が監理内容を
確認して責任をもって指導できるようになっている。
The inspection sheets 50 other than the construction supervision sheet 51 shown in FIG. 3, that is, the basic supervision sheet, the assembly supervision sheet, the safety supervision sheet, the construction supervision sheet, and the completion supervision sheet are the construction supervision sheet 51. With the same configuration, each control item can be checked in detail in each process, and the construction manager can check the supervision contents and give guidance responsibly.

【0040】さらに、検査シート50のうち図4の着工
立合シート52以外の立合シートである竣工立合シート
は、着工立合シート52と同様な構成とされ、各立合検
査項目のチェックを詳細に行うことができるとともに検
査に立ち合った施主の確認・承認を得ることができるよ
うになっている。
Further, the completed standing sheets, which are the standing sheets other than the starting standing sheet 52 of FIG. 4 among the inspection sheets 50, have the same structure as the starting standing sheet 52, and each standing inspection item is checked in detail. In addition to being able to do so, it is possible to obtain confirmation and approval from the owner who attended the inspection.

【0041】そして、各検査シート50には、項目欄の
各項目毎に適宜空欄(その項目に対応する内容欄におけ
る空白部分)が設けられ、その時々の必要に応じた重点
監理事項を加えることができるようになっている。さら
に、各検査シート50には、追加・変更工事が行われる
可能性がある場合に、項目欄に新たな項目として追加・
変更工事という項目が適宜設けられている。この追加・
変更工事という項目に対応する内容欄には、事前に各監
理内容を記入しておくことが好ましい。
Each inspection sheet 50 is provided with blanks (blanks in the content column corresponding to the item) for each item in the item column, and important supervision items should be added according to the occasional need. You can do it. Furthermore, if there is a possibility that additional / change work will be performed on each inspection sheet 50, a new item will be added / added to the item column.
The item called change work is provided as appropriate. This addition
It is preferable to enter the details of each supervision in advance in the content column corresponding to the item of change work.

【0042】また、報告書60のうち図5の着工報告書
61以外の各報告書、つまり上棟報告書、竣工報告書
は、着工報告書61と同様な構成とされ、各監理内容の
チェック完了あるいは各工程完了の報告を行うことがで
きるとともに請求書(上棟報告書では中間金、竣工報告
書では最終金)を発行できるようになっている。
In the report 60, each report other than the construction report 61 shown in FIG. 5, that is, the upper building report and the completion report has the same structure as the construction report 61, and the check of each supervision content is completed. Alternatively, it is possible to report the completion of each process and issue an invoice (intermediate money for the upper building report, final money for the completion report).

【0043】施工評価表(不図示)としては、例えば、
施工の全工程における各工事の品質、単位、工期等に
ついての邸別総合施工評価を行う「現場監理シート」、
竣工時点での仕上り品質の出来栄えについての施工評
価を行う「竣工検査シート」、A業者の経営内容、工
事の出来栄え、客先の評価等についての定期的なA業者
の総合評価を行う「A業者評価表」、という三種類のシ
ートを用意しておくことができる。
As a construction evaluation table (not shown), for example,
A "site supervision sheet" that conducts a comprehensive construction evaluation by residence regarding the quality, units, construction period, etc. of each construction in all construction processes
"Completion inspection sheet" that evaluates the construction quality of finished products at the time of completion, management contents of A contractor, work completion, periodical comprehensive evaluation of A company regarding customer evaluation, etc. It is possible to prepare three types of sheets called "evaluation table".

【0044】このような本実施例においては、以下のよ
うにして進行管理帳10を用いて建設計画の進行管理を
行う。先ず、着工前打合せを行い、工程表40に必要事
項を記入した後、この工程表40を進行管理帳10から
切り離して各配付先に配付する。特に、施主に配付する
ことにより、工事全体の日程の概要の提示を行う。
In this embodiment as described above, the progress management of the construction plan is performed using the progress management book 10 as follows. First, a meeting before the start of construction is performed, necessary items are entered in the process chart 40, and then the process chart 40 is separated from the progress management book 10 and distributed to each distribution destination. In particular, by distributing it to the owner, an outline of the entire construction schedule will be presented.

【0045】次に、着工監理シート51に従って必要事
項を記入しながら着工工程における各監理項目のチェッ
クを行う。この際、監理担当者(現場管理者)は、確認
欄51Kに判定結果(○:合格、△:当日手直し後合
格、×:不合格)を記入する。不合格項目については、
その不合格内容を指摘するとともに、補修方法・取替・
再施工等の指示事項を指示事項欄51Lに具体的に記入
する。また、手直し事項については、何日までに補修で
きるかその場で確認する。さらに、不合格事項について
は、処理完了後に必ず現場で再確認し、再確認欄51M
にその旨を記入する。ここで、監理時に目視で確認でき
ないものがある場合には、口頭で工事主任より確認す
る。また、工事終了後では確認できず、しかもトラブル
が発生しやすい項目、あるいは重要な監理項目の場合
(例えば、基礎監理における「特殊基礎の確認」)に
は、工事写真(証拠写真)を撮っておく。そして、各監
理項目のチェックを完了して着工監理シート51への必
要事項の記入が終わった時点で、この着工監理シート5
1を進行管理帳10から切り離して各配付先に配付す
る。なお、A業者配付用は、監理後すぐに現場で手渡
す。
Next, while checking the necessary items according to the construction control sheet 51, each control item in the construction process is checked. At this time, the person in charge of supervision (site manager) fills in the confirmation column 51K with the judgment result (◯: pass, Δ: pass after rework on the day, x: fail). For rejected items,
In addition to pointing out the details of the failure, repair method / replacement /
Concretely enter instructions such as re-construction in the instruction column 51L. In addition, regarding repair items, confirm on the spot how many days can be repaired. In addition, regarding rejected items, be sure to reconfirm on site after the completion of processing, and reconfirm column 51M.
Fill in that. Here, if there is something that cannot be visually confirmed at the time of supervision, the construction chief verifies it. In addition, if the item cannot be confirmed after the construction is complete and troubles are likely to occur, or if it is an important supervision item (for example, "confirmation of special foundation in basic supervision"), take a construction photo (proof photo). deep. Then, when the check of each supervision item is completed and the necessary items are completed in the construction supervision sheet 51, the construction supervision sheet 5
1 is separated from the progress management book 10 and distributed to each distribution destination. In addition, as for the distribution by A company, it will be handed on site immediately after supervision.

【0046】続いて、施主(客先)の立ち合いのもと
で、着工立合シート52に従って必要事項を記入しなが
ら着工工程における各立合検査項目のチェックを行う。
この際、検査担当者は、確認欄52Kに検査結果を記入
し、必要に応じて指示事項欄52Lや再確認欄52Mへ
の記入も行う。そして、各立合検査項目のチェックを完
了して着工立合シート52への必要事項の記入が終わっ
た時点で、この着工立合シート52を進行管理帳10か
ら切り離して各配付先に配付する。
Subsequently, under the presence of the owner (customer), each establishment inspection item in the construction process is checked while filling in necessary items according to the construction start sheet 52.
At this time, the inspector fills in the inspection result in the confirmation column 52K, and also fills in the instruction item column 52L and the reconfirmation column 52M as necessary. Then, at the time when the check of each establishment inspection item is completed and the necessary items have been entered in the construction start sheet 52, the construction start sheet 52 is separated from the progress management book 10 and distributed to each distribution destination.

【0047】さらに、着工工程が完了した時点で、着工
報告書61に必要事項を記入した後、この着工報告書6
1を進行管理帳10から切り離して各配付先に配付す
る。特に、施主に配付することにより、契約による着工
金の請求を同時に行う。
Further, after the completion of the construction process, after the necessary items are entered in the construction report 61, the construction report 6
1 is separated from the progress management book 10 and distributed to each distribution destination. In particular, by distributing it to the owner, the contract start fee will be requested at the same time.

【0048】その後、基礎、組立、造作、竣工の各工程
においても、同様にして各検査シート50および各報告
書60を用いて、監理、立合検査、報告等を行う。ま
た、竣工立合後に、万一、残・駄目工事があった場合に
は、ディーラー独自の書式による帳票を用いて管理を行
い、残・駄目工事無しでの引渡しの徹底を図る。そし
て、引渡後に各施工評価表(例えば、「現場監理シー
ト」、「竣工検査シート」、「A業者評価表」など)へ
の記入を行い、建設計画の進行管理を完了する。
Thereafter, in each of the steps of foundation, assembly, fabrication, and completion, the inspection sheet 50 and the report 60 are used in the same manner for supervision, on-site inspection, reporting, and the like. In addition, in the unlikely event that there is unsuccessful or unsuccessful work after the completion of construction, we will manage it using a form in the dealer's original format, and ensure delivery without remaining and unsuccessful work. Then, after the delivery, each construction evaluation table (for example, “site supervision sheet”, “completion inspection sheet”, “A contractor evaluation table”, etc.) is filled in, and the progress management of the construction plan is completed.

【0049】このような本実施例によれば、次のような
効果がある。すなわち、進行管理帳10は、内容一覧2
0を備えているので、これが目次の役割を果たすため、
どのような種類の記入用紙30があるか、あるいは各記
入用紙30がどの辺に綴じられているかを迅速かつ容易
に認識できる。また、内容一覧20には、各記入用紙3
0の名称およびその記入用紙30に関係する関係者名が
計画の進行順に配置されて表示されているので、各記入
用紙30の使用時期および関係者名が一目で把握でき
る。
According to this embodiment, the following effects are obtained. That is, the progress management book 10 includes the content list 2
Since it has 0, it plays the role of the table of contents.
It is possible to quickly and easily recognize what kind of entry form 30 is present, or on which side each entry form 30 is bound. In addition, in the content list 20, each entry form 3
Since the name of 0 and the name of the person concerned with the entry sheet 30 are arranged and displayed in the order of progress of the plan, the use time of each entry sheet 30 and the person's name can be grasped at a glance.

【0050】さらに、進行管理帳10は、工程表40を
備えているので、工事全体の日程の概要を施主(客先)
に容易に提示することができる。そして、工程表40に
より、計画進行の節目とされる各予定日が明確かつ容易
に把握できるので、ディーラーやA業者等も各工程の段
取や監理を行いながら常に納期意識を持つことができ、
計画の進行遅延を防止できる。
Further, since the progress management book 10 is provided with the process chart 40, an outline of the schedule of the entire construction is carried out by the client (customer).
Can be easily presented to. Since the schedule table 40 clearly and easily grasps each scheduled date, which is a turning point of the plan progress, the dealer, the A dealer, and the like can always have a consciousness of the delivery date while preparing and supervising each process. ,
It is possible to prevent a delay in the progress of the plan.

【0051】また、進行管理帳10は、検査シート50
を備え、この検査シート50として、図3の着工監理シ
ート51等の各種の監理シートが着工、基礎、組立、造
作、および竣工の各工程毎に用意されているので、これ
らの監理シートにより、各工程における各監理項目のチ
ェックを詳細に行うことができるとともに、これらの監
理シートに建設責任者の検印欄51C等が設けられてい
ることから建設責任者が監理内容を確認して責任をもっ
て工事の指導を行うことができる。そして、安全監理シ
ート(安全管理シート)が用意されているため、施工現
場で働く人達の安全について気を配り、事故発生を確実
に防止できる。さらに、着工監理シート51等の各種の
監理シートには、次工程の監理予定日を記入する監理予
定日記入欄51Fおよびその工程の完了する予定日を記
入する完工予定日記入欄51Gが設けられているので、
工程表40の各予定日記入と合せ、納期意識を高めて計
画の進行遅延の防止をより一層図ることができる。
The progress management book 10 includes an inspection sheet 50.
As the inspection sheet 50, various supervision sheets such as the construction supervision sheet 51 of FIG. 3 are prepared for each process of construction, foundation, assembly, fabrication, and completion. It is possible to check each supervision item in each process in detail, and since the supervision sheet 51C for the construction manager is provided on these supervision sheets, the construction manager confirms the supervision contents and carries out the construction responsibly. Can be taught. Also, since a safety supervision sheet (safety management sheet) is prepared, it is possible to pay attention to the safety of the people who work at the construction site and prevent accidents from occurring. Further, various supervision sheets such as the construction start supervision sheet 51 are provided with a supervision scheduled date entry column 51F for entering the supervision date of the next process and a completion date entry column 51G for entering the scheduled completion date of the process. Because
Together with the entry of each scheduled date in the process chart 40, it is possible to further raise the awareness of the delivery date and further prevent the delay of the progress of the plan.

【0052】また、検査シート50として、図4の着工
立合シート52等の各種の立合シートが着工および竣工
の各工程について用意されているので、これらの立合シ
ートにより、各立合検査項目のチェックを詳細に行うこ
とができるとともに、これらの立合シートに施主承認欄
52N等が設けられていることから検査に立ち合った施
主の確認・承認を得ることができる。このため、工事に
伴う無用のトラブルを防止できる。
Further, as the inspection sheet 50, various standing sheets such as the starting standing sheet 52 shown in FIG. 4 are prepared for each process of starting and completing the construction. Therefore, each standing inspection item is checked by these standing sheets. In addition to being able to perform the details, it is possible to obtain the confirmation / approval of the owner who attended the inspection because the owner approval column 52N and the like are provided on these standing sheets. Therefore, it is possible to prevent unnecessary troubles associated with the construction.

【0053】また、進行管理帳10は、図5の着工報告
書61等の各報告書60を備えているので、各監理内容
のチェック完了あるいは各工程完了の報告を容易に行う
ことができる。そして、各報告書60の中には、請求書
が織り込まれているので、報告と同時に請求書を発行で
き、便利であるうえ、料金請求時に各報告書60の記載
により各監理項目が施主に示されることから、施主に信
頼感を与えることができ、資金回収を容易に行うことが
できる。
Further, since the progress management book 10 is provided with each report 60 such as the construction report 61 shown in FIG. 5, it is possible to easily report the completion of checking each management content or the completion of each process. In addition, since the invoice is woven into each report 60, the invoice can be issued at the same time as the report, which is convenient, and each supervising item can be provided to the owner by the description of each report 60 when billing. As shown, the owner can be given a sense of trust and the funds can be easily collected.

【0054】さらに、進行管理帳10は、構造体検査依
頼書や竣工検査依頼書を備えているので、現場管理者
は、検査予定日に合せて工程の監理に注力することがで
き、検査員は、確実で計画的な検査業務を行うことがで
きる。
Further, since the progress management book 10 is provided with a structure inspection request form and a completion inspection request form, the on-site manager can focus on process supervision according to the scheduled inspection date, and the inspector Can carry out reliable and systematic inspection work.

【0055】なお、本発明は前記実施例に限定されるも
のではなく、本発明の目的を達成できる範囲内での変形
等は本発明に含まれるものである。すなわち、本発明の
進行管理帳は、前記実施例の進行管理帳10のような各
シートが綴じられた構成に限定されるものではなく、要
するに、内容一覧および複数種類の記入用紙が綴じられ
た構成であればよい。また、進行管理帳を構成する各シ
ートのシート内における各表示や各記入欄の配置位置や
大きさ等の形態は任意である。さらに、進行管理帳を構
成する各シートを綴じる順序は、工程順となっているこ
とが好ましいが、必ずしも工程順に限定されるものでは
なく、例えば、あいうえお順などであってもよい。
The present invention is not limited to the above-mentioned embodiments, and modifications and the like within the range in which the object of the present invention can be achieved are included in the present invention. That is, the progress management book of the present invention is not limited to the configuration in which each sheet is bound like the progress management book 10 of the above-mentioned embodiment, and in short, a content list and a plurality of types of entry sheets are bound. Any configuration will do. In addition, the forms such as the position and size of each display and each entry field in each sheet constituting the progress management book are arbitrary. Further, the order of binding the sheets forming the progress management book is preferably the order of steps, but the order is not necessarily limited to the order of steps, and may be, for example, Aiueo order.

【0056】また、前記実施例では、進行管理帳10
は、建物の建設計画用のものとなっていたが、本発明の
進行管理帳は、道路、鉄道、橋梁、水道等の他の固定構
造物の建設計画、ダムや発電所の建設計画、あるいはそ
の他の土木工事の計画等に適用してもよく、さらに現場
で行われる作業の計画だけではなく、工場内での各種製
品や部品の生産計画等に適用してもよく、要するに、複
数の工程を有し、かつ進行管理が必須である計画であれ
ば、任意の計画に適用できる。
Further, in the above embodiment, the progress management book 10
Is for building construction plans, the progress management book of the present invention is for construction plans of other fixed structures such as roads, railways, bridges, waterworks, construction plans for dams and power plants, or It may be applied to other civil engineering work plans, etc., and may be applied not only to the work plans to be performed on site but also to the production plans of various products and parts in the factory. It is applicable to any plan as long as it has a plan and the progress management is essential.

【0057】[0057]

【発明の効果】以上に述べたように本発明によれば、内
容一覧に示された各記入用紙の使用時期および各記入用
紙に関係する関係者名に従って、各記入用紙に、計画の
進行管理に必要な各種事項を記入していき、必要に応じ
て各記入用紙の配付を行うので、検査やその承認、報告
等を適切なタイミングで行うことができるうえ、各記入
用紙に関係する関係者名が明確になることから、記入、
承認、配付等の進行管理に係る各処理を迅速に行うこと
ができ、かつ間違った配付等の不都合を防止できるとい
う効果がある。そして、内容一覧および各記入用紙が一
冊の進行管理帳として綴じられているので、チェック漏
れや用紙間違い等の不都合を確実に防止でき、計画を落
ち度無く円滑に遂行できるという効果がある。
As described above, according to the present invention, according to the use period of each entry sheet shown in the content list and the name of the person related to each entry sheet, the progress management of the plan is managed in each entry sheet. All necessary items will be filled in, and each form will be distributed as necessary, so inspections, approvals, reports, etc. can be performed at appropriate times, and related parties related to each form Since the name becomes clear, fill in,
Each process related to progress management such as approval and distribution can be promptly performed, and inconvenience such as incorrect distribution can be prevented. Since the content list and each entry form are bound as a single progress management book, it is possible to reliably prevent inconveniences such as omission of checks and mistakes in the forms, and it is possible to smoothly carry out the plan.

【0058】また、内容一覧に、各記入用紙の名称およ
び関係者名を計画の進行順に配置表示した場合には、検
査等の順序や時期を直感的に把握でき、計画の進行管理
をより一層円滑に行うことができるという効果がある。
Further, when the names of the respective entry forms and the names of persons concerned are arranged and displayed in the contents list in the order of progress of the plan, the order and timing of inspections and the like can be intuitively grasped, and the progress management of the plan can be further improved. The effect is that it can be carried out smoothly.

【0059】さらに、記入用紙として、計画の各工程の
関連を示す工程表と、計画の進行管理中に行われる検査
で用いる検査シートと、計画の各工程の完了報告で用い
る報告書とを設けた場合には、検査とその報告とを一連
の処理として扱うことができ、より一層漏れのない処理
を行うことができるうえ、工程表に各工程の開始予定日
あるいは完了予定日等を記入することにより、計画全体
の日程の概要を容易に把握できるという効果がある。
Further, as a form, a process chart showing the relationship between each process of the plan, an inspection sheet used in the inspection performed during the progress management of the plan, and a report used for the completion report of each process of the plan are provided. In the case of inspection, the inspection and its report can be handled as a series of processing, more complete processing can be performed, and the scheduled start date or scheduled completion date of each process is entered in the process chart. This has the effect of easily grasping the outline of the schedule for the entire plan.

【0060】また、本発明の進行管理帳を、建物の建設
計画における建設現場の管理に適用した場合には、着
工、基礎、組立、造作、および竣工という多くの工程が
あることと、計画に携わる関係者が多いことから、本発
明の作用・効果を一層顕著に発揮させることができると
いう効果がある。
Further, when the progress management book of the present invention is applied to management of a construction site in a building construction plan, there are many processes such as construction, foundation, assembly, fabrication, and completion, and Since there are many involved persons, there is an effect that the effects and advantages of the present invention can be more remarkably exhibited.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明の一実施例の進行管理帳を構成する内容
一覧の構成図。
FIG. 1 is a configuration diagram of a content list constituting a progress management book according to an embodiment of the present invention.

【図2】前記実施例の工程表の構成図。FIG. 2 is a configuration diagram of a process chart of the embodiment.

【図3】前記実施例の検査シートである着工監理シート
の構成図。
FIG. 3 is a configuration diagram of a construction supervision sheet which is an inspection sheet according to the embodiment.

【図4】前記実施例の検査シートである着工立合シート
の構成図。
FIG. 4 is a configuration diagram of a start-up standing sheet which is an inspection sheet according to the embodiment.

【図5】前記実施例の着工報告書の構成図。FIG. 5 is a configuration diagram of a construction report of the embodiment.

【符号の説明】[Explanation of symbols]

10 進行管理帳 20 内容一覧 30 記入用紙 40 工程表 50 検査シート 51 検査シートである着工監理シート 52 検査シートである着工立合シート 60 報告書 61 着工報告書 10 Progress management book 20 Contents list 30 Entry form 40 Process chart 50 Inspection sheet 51 Start-up management sheet that is an inspection sheet 52 Start-up completion sheet that is an inspection sheet 60 Report 61 Start-up report

Claims (4)

【特許請求の範囲】[Claims] 【請求項1】 計画の進行管理に必要な各種事項を記入
する複数の記入用紙と、これらの記入用紙とともに綴じ
られて各記入用紙の使用時期および各記入用紙に関係す
る関係者名が示された内容一覧とを備えたことを特徴と
する進行管理帳。
[Claim 1] A plurality of form sheets for entering various matters necessary for the progress management of the plan, and the time when each form sheet is used and the name of a person concerned with each form sheet are shown together with the form sheets. A progress management book characterized by having a list of contents.
【請求項2】 請求項1に記載した進行管理帳におい
て、前記内容一覧には、前記各記入用紙の名称および前
記関係者名が前記計画の進行順に配置されて表示されて
いることを特徴とする進行管理帳。
2. The progress management book according to claim 1, wherein the contents list displays the names of the respective entry sheets and the names of the persons concerned in the order of progress of the plan. A progress management book.
【請求項3】 請求項1または請求項2に記載した進行
管理帳において、前記記入用紙には、前記計画の各工程
の関連を示す工程表と、前記計画の進行管理中に行われ
る検査で用いる検査シートと、前記計画の各工程の完了
報告で用いる報告書とが含まれていることを特徴とする
進行管理帳。
3. The progress management book according to claim 1 or 2, wherein the entry sheet includes a process chart indicating a relationship between each process of the plan and an inspection performed during progress management of the plan. A progress management book including an inspection sheet to be used and a report to be used for a completion report of each process of the plan.
【請求項4】 請求項1から請求項3のいずれかに記載
した進行管理帳において、前記計画は建物の建設計画と
され、前記進行管理は建設現場の管理とされ、前記計画
には、着工、基礎、組立、造作、および竣工の各工程が
含まれていることを特徴とする進行管理帳。
4. The progress management book according to claim 1, wherein the plan is a building construction plan, the progress management is construction site management, and the plan is construction start. A progress management book characterized by including each process of basic, assembly, fabrication, and completion.
JP32763194A 1994-12-28 1994-12-28 Progress-managing book Withdrawn JPH08183273A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP32763194A JPH08183273A (en) 1994-12-28 1994-12-28 Progress-managing book

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP32763194A JPH08183273A (en) 1994-12-28 1994-12-28 Progress-managing book

Publications (1)

Publication Number Publication Date
JPH08183273A true JPH08183273A (en) 1996-07-16

Family

ID=18201211

Family Applications (1)

Application Number Title Priority Date Filing Date
JP32763194A Withdrawn JPH08183273A (en) 1994-12-28 1994-12-28 Progress-managing book

Country Status (1)

Country Link
JP (1) JPH08183273A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002132862A (en) * 2000-10-26 2002-05-10 Pc Network Plaza:Kk Method for controlling quality of building construction

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002132862A (en) * 2000-10-26 2002-05-10 Pc Network Plaza:Kk Method for controlling quality of building construction

Similar Documents

Publication Publication Date Title
US20130132440A1 (en) Arrangements for administrating and managing a construction project
Tang et al. Construction quality management
Brown Quality management self-assessment in Australia
AU2317901A (en) Method and system for efficiently transacting an order and for communicating order information between a construction contractor and a construction material supplier
JPH08183273A (en) Progress-managing book
Leung et al. A brief review on construction safety in some south-east Asian countries
SCHOOLS DIVISION 0-QUOTATION AND CONTRACT REQUIREMENTS
Kam Quality assurance of construction works in Hong Kong
Ng et al. Lean production system: compatible with Malaysian culture?
Al-Hazmi Toward standardization of public building maintenance contracts in Saudi Arabia
Fargo EHRM Infrastructure Upgrades
Cathey A case study on project initiation, implementation and termination in a heavy industry
Le Coze et al. Development of the ATOS concept, analysis of technical and organisational safety
Sospeter et al. 13 Construction industry development in Tanzania
Solar Learning Guide-24
GLAMA PROJECT MANAGEMENT PLAN FOR THE CONSTRUCTION OF MADANG CHRISTIAN ACADEMY PERIMETER FENCE
HUESEMANN et al. AXE LIBRARY PHASE 4 BLDG NO.: 38500-00019 PITTSBURG, KANSAS A-012950 (C)
Westerhoff et al. RENOVATIONS TO EXISTING SCIENCE LAB
SET REPAIR SITE DRAINAGE BUILDING 7
Muntean Jr Origin-DestinationTravel Surveysin the 1990s UsingMicrocomputers
Gomeseria Building Services Engineering Management
Rumane Construction Management Tools
Abdullah et al. A case study on Quality Management System in construction project
Langford et al. International projects
Middlebrook The time management and tenancy coordination of specialty retail projects: graduate project report

Legal Events

Date Code Title Description
A300 Withdrawal of application because of no request for examination

Free format text: JAPANESE INTERMEDIATE CODE: A300

Effective date: 20020305