JPH08147354A - Method and device for general schedule - Google Patents

Method and device for general schedule

Info

Publication number
JPH08147354A
JPH08147354A JP28166994A JP28166994A JPH08147354A JP H08147354 A JPH08147354 A JP H08147354A JP 28166994 A JP28166994 A JP 28166994A JP 28166994 A JP28166994 A JP 28166994A JP H08147354 A JPH08147354 A JP H08147354A
Authority
JP
Japan
Prior art keywords
schedule
work
information
cost
selecting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP28166994A
Other languages
Japanese (ja)
Inventor
Shino Takahashi
志乃 高橋
Hideaki Matoba
秀彰 的場
Kenichi Funaki
謙一 船木
Masahiro Sato
匡弘 佐藤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hitachi Ltd
Original Assignee
Hitachi Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hitachi Ltd filed Critical Hitachi Ltd
Priority to JP28166994A priority Critical patent/JPH08147354A/en
Publication of JPH08147354A publication Critical patent/JPH08147354A/en
Pending legal-status Critical Current

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/30Computing systems specially adapted for manufacturing
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/80Management or planning

Abstract

PURPOSE: To plan a schedule for operating the departments of manufacture, distribution, and service work at low cost by calculating a cost to be generated at each working department and selecting a schedule based on the generated cost from among one or plural schedule plans. CONSTITUTION: This device is provided with a cost information holding part 214 holding cost information showing a cost calculating method corresponding to working contents, working time, etc., and a schedule information holding part 215 holding schedule information showing an existent schedule. Then, the device can define the cost generated at the point of the time of schedule by a cost calculation means 224 calculating the cost to be generated from schedule information, a selected schedule and cost information and a processing for calculating the cost to be generated at each working department. In addition, the device selects the schedule based on the cost to be generated from among one or plural schedule plans by a schedule plan selecting means 225 for selecting the schedule based on the cost to be generated from among one or plural schedule plans.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明は、統括日程計画方法及び
装置に係り、特に、顧客の受注に応じて製造・物流・サ
ービスの日程計画を立案するための方法及び装置に関す
る。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a general schedule planning method and apparatus, and more particularly to a method and apparatus for planning a schedule of manufacturing, distribution and service according to an order from a customer.

【0002】[0002]

【従来の技術】従来の製造に関する日程計画方法及び装
置では、処理すべき作業と作業を処理できる作業部門
(処理工程)を関連付け、作業部門の能力(工程の処理
能力)に応じて負荷を配分し、日程を計画している。
2. Description of the Related Art In a conventional scheduling method and apparatus for manufacturing, a work to be processed and a work department (processing process) capable of processing the work are associated with each other, and a load is distributed according to the capacity of the work department (process processing capacity). I am planning a date.

【0003】この種の技術では、例えば、特開平5-2982
80号公報に記載のもの等が挙げられる。
In this type of technology, for example, Japanese Patent Laid-Open No. 5-2982
Examples include those described in Japanese Patent No. 80.

【0004】また、従来の物流・サービスに関する日程
計画方法及び装置では、予め設定された配送日、サービ
ス日等の条件の中で、作業を組合せ、配送手段、作業者
等を選択している。
Further, in the conventional schedule and method for physical distribution and service, the work is combined and the delivery means, the worker, etc. are selected within the preset conditions such as delivery date and service date.

【0005】この種の技術では、例えば、特開平5-2985
92号公報に記載のもの等が挙げられる。
In this type of technology, for example, Japanese Patent Laid-Open No. 5-2985
For example, those described in Japanese Patent Publication No. 92 are cited.

【0006】また、製造・物流・サービスに関する日程
計画方法及び装置では、通常、始めに各部門に基準日程
を指示し、各部門が個々に日程計画を立案している。
[0006] Further, in the schedule planning method and apparatus for manufacturing, distribution and service, usually, first, each department is instructed of the standard schedule, and each department makes a schedule individually.

【0007】[0007]

【発明が解決しようとする課題】製造に関する上記従来
技術では、処理すべき作業と該作業を処理できる作業部
門(処理工程)を関連付け、作業部門の能力(工程の処
理能力)に応じて、負荷のバランス、作業量を評価尺度
として日程計画を立案している。
In the above-mentioned prior art related to manufacturing, the work to be processed and the work department (processing process) capable of processing the work are associated with each other, and the load is set according to the capacity of the work department (process processing capacity). The schedule is drafted using the balance and workload of the above as evaluation criteria.

【0008】このため、能力を固定的に扱うことにな
り、固定的に一定以上の費用が発生する。また、通常残
業による費用が発生すれば、運用コストは割高になる
が、外注にだす等の作業方法変更をするか、あるいは作
業者を増加させるか、その他の手段を用いるべきか等の
判断基準がない。
For this reason, the ability is fixedly handled, and fixed costs are incurred above a certain level. Also, if overtime costs are usually incurred, operating costs will be higher, but criteria for determining whether to change the work method such as outsourcing, increase the number of workers, or use other means. There is no.

【0009】また、物流・サービスに関する上記従来技
術では、予め設定された配送日、サービス日等の条件の
中で低コスト運用を図っているが、配送日、サービス日
が予め決められた範囲内では調整できる範囲が小さい。
Further, in the above-mentioned prior art relating to physical distribution / service, low cost operation is achieved under preset delivery date, service date, etc., but the delivery date and service date are within a predetermined range. The adjustable range is small.

【0010】更に、運用コストとは無関係に、一定のル
−ル(例えば各部門の標準リ−ドタイム等)により製造
・物流・サービスの各部門に渡す基準日程を作成してい
るため、運用コストからみた最適化が図れていない。
Further, regardless of the operating cost, the operating schedule is based on a fixed schedule (for example, standard read time of each department) that creates a standard schedule to be passed to each department of manufacturing, logistics and service. The optimization seen from the perspective is not achieved.

【0011】本発明の目的は、日程計画の時点で発生す
るコストを明確にし、製造・物流・サービス作業部門を
低コストで運用するための日程計画を立案する手段を提
供することにある。
An object of the present invention is to provide means for clarifying the costs incurred at the time of scheduling and for formulating a schedule for operating the manufacturing, logistics and service work department at low cost.

【0012】本発明の第二の目的は、顧客への納期回答
時に製造・物流・サービス作業部門の運用コストを明確
にし、運用コストに基づき納期を選択する手段を提供す
ることにある。
A second object of the present invention is to provide a means for clarifying the operating cost of the manufacturing / physical distribution / service work department at the time of answering the delivery date to the customer and selecting the delivery date based on the operating cost.

【0013】本発明の第三の目的は、製造・物流・サー
ビス作業部門のト−タル運用コストを、低減するための
日程計画を立案する手段を提供することにある。
A third object of the present invention is to provide means for formulating a schedule for reducing the total operating cost of the manufacturing, logistics and service work departments.

【0014】[0014]

【課題を解決するための手段】上記目的を達成するため
に、本発明の統括日程計画方法では、各作業部門毎に発
生する費用を算出する処理と、一つまたは複数の日程計
画案の中から、発生費用に基づき日程計画を選択する処
理を行う。
In order to achieve the above object, according to the general schedule planning method of the present invention, the process of calculating the cost incurred for each work department and one or more schedule plans are performed. Then, the process of selecting the schedule based on the incurred costs is performed.

【0015】また、本発明の統括日程計画装置では、作
業内容・作業時刻等に応じた費用算出方法を示すコスト
情報を保持するコスト情報保持部、既存の日程計画を示
す日程計画情報を保持する日程計画情報保持部を有し、
日程計画情報と選択した日程及びコスト情報から、発生
する費用を算出する費用算出手段と、一つまたは複数の
日程計画案の中から、発生費用に基づき日程計画を選択
する日程計画案選択手段を備えた。
Further, in the general schedule planning apparatus of the present invention, a cost information holding section for holding cost information indicating a cost calculation method according to work content, work time, etc., and schedule planning information showing an existing schedule plan are held. It has a schedule plan information holding unit,
Cost calculation means to calculate the cost to be incurred from the schedule information and the selected schedule and cost information, and schedule plan selection means to select the schedule plan based on the generated cost from one or more schedule plans. Prepared

【0016】上記他の目的を達成するために、本発明の
統括日程計画方法では、選択された日程に基づき、顧客
への納期、あるいは引渡し日を設定する処理を有する。
In order to achieve the above-mentioned other objects, the integrated schedule planning method of the present invention has a process of setting a delivery date or a delivery date to the customer based on the selected schedule.

【0017】上記他の目的を達成するために、本発明の
統括日程計画方法では、複数の作業部門にわたり作業を
行う際に、作業部門の間の日程に関する制約条件を満足
させる作業の日程を選択する処理と、一つまたは複数の
日程計画案の中から、全作業部門で発生する費用に基づ
き日程計画を選択する処理を行う。
In order to achieve the above-mentioned other objects, in the general schedule planning method of the present invention, when performing work over a plurality of work departments, a work schedule that satisfies a constraint condition regarding a schedule between work departments is selected. And a process of selecting a schedule from one or a plurality of schedule plans based on the costs incurred by all work departments.

【0018】また、本発明の統括日程計画装置では、作
業部門の間の日程に関する制約条件である制約情報を保
持する制約情報保持部を有し、作業内容と各作業部門の
作業能力情報、日程計画情報及び制約情報から、各作業
部門における各作業の日程を選択する日程選択手段と、
日程計画情報と選択した日程及びコスト情報から、発生
する費用を算出する費用算出手段と、一つまたは複数の
日程計画案の中から、全作業部門で発生する費用に基づ
き日程計画を選択する日程計画案選択手段を備えた。
Further, the integrated schedule planning apparatus of the present invention has a constraint information holding unit for holding constraint information which is a constraint condition regarding the schedule between the work departments, and the work content, the work capability information of each work department, the schedule. A schedule selecting means for selecting a schedule of each work in each work department from the plan information and the constraint information,
A cost calculation method that calculates the costs that will be incurred from the schedule information and the selected schedule and cost information, and a schedule that selects a schedule plan based on the costs that will be incurred by all work departments from one or more schedule plans. Equipped with means for selecting a plan.

【0019】[0019]

【作用】作業内容・作業時刻等に応じた費用算出方法を
示すコスト情報を保持するコスト情報保持部、既存の日
程計画を示す日程計画情報を保持する日程計画情報保持
部を有し、日程計画情報と選択した日程及びコスト情報
から、発生する費用を算出する費用算出手段と、各作業
部門毎に発生する費用を算出する処理により、日程計画
の時点で発生するコストを明確にできる。
[Function] A cost information holding unit that holds cost information indicating a cost calculation method according to work contents, work time, and the like, and a schedule plan information holding unit that holds schedule plan information indicating an existing schedule plan The cost incurred at the time of scheduling can be clarified by the cost calculation means for calculating the cost incurred from the information and the selected schedule and cost information and the process for calculating the cost incurred for each work department.

【0020】また、一つまたは複数の日程計画案の中か
ら、発生費用に基づき日程計画を選択する日程計画案選
択手段と、一つまたは複数の日程計画案の中から、発生
費用に基づき日程計画を選択する処理により、製造・物
流・サービス作業部門を低コストで運用するための日程
計画が立案できる。
A schedule plan selecting means for selecting a schedule plan based on the generated cost from one or a plurality of schedule plans, and a schedule based on the generated cost from one or a plurality of schedule plans. By the process of selecting a plan, it is possible to make a schedule for operating the manufacturing, logistics and service work department at low cost.

【0021】また、選択された日程に基づき、顧客への
納期、あるいは引渡し日を設定する処理により、運用コ
ストに基づき納期を選択できる。
Further, the delivery date can be selected based on the operation cost by the process of setting the delivery date to the customer or the delivery date based on the selected schedule.

【0022】また、作業部門の間の日程に関する制約条
件である制約情報を保持する制約情報保持部を有し、作
業内容と各作業部門の作業能力情報、日程計画情報及び
制約情報から、各作業部門における各作業の日程を選択
する日程選択手段と、日程計画情報と前記の選択した日
程及びコスト情報から、発生する費用を算出する費用算
出手段と、一つまたは複数の日程計画案の中から、全作
業部門で発生する費用に基づき日程計画を選択する日程
計画案選択手段と、作業部門の間の日程に関する制約条
件を満足させる作業の日程を選択する処理と、一つまた
は複数の日程計画案の中から、全作業部門で発生する費
用に基づき日程計画を選択する処理により、製造・物流
・サービス作業部門のト−タル運用コストを、低減する
ための日程計画を立案することができる。
Further, it has a constraint information holding unit for holding constraint information which is a constraint condition regarding the schedule between the work departments, and each work is selected from the work content, work capability information of each work department, schedule planning information and constraint information. Schedule selection means to select the schedule of each work in the department, cost calculation means to calculate the cost incurred from the schedule plan information and the selected schedule and cost information, and from one or more schedule plans , A schedule plan selecting means for selecting a schedule based on the costs incurred by all work departments, a process for selecting a work schedule that satisfies the constraint condition regarding the schedule between the work departments, and one or more schedule plans A schedule plan to reduce the total operating cost of the manufacturing, logistics, and service work departments by selecting the schedule plan based on the costs incurred by all work departments from the plan. It is possible to draft.

【0023】[0023]

【実施例】以下、本発明の一実施例について図を用いて
説明する。
An embodiment of the present invention will be described below with reference to the drawings.

【0024】まず、図2により本発明の情報処理システ
ム構成例を説明する。
First, an example of the information processing system configuration of the present invention will be described with reference to FIG.

【0025】210はデ−タ保持部であり、更に、21
1は製品仕様・顧客情報等の受注情報を保持する受注情
報保持部、212は受注情報と作業内容の対応を示す作
業内容情報を保持する作業内容情報保持部、213は各
作業部門の作業能力情報を保持する作業能力情報保持
部、214は作業内容・作業時刻等に応じた費用算出方
法を示すコスト情報を保持するコスト情報保持部、21
5は既存の日程計画を示す日程計画情報を保持する日程
計画情報保持部、216はで作業の間の日程に関する制
約条件である制約情報を保持する制約情報保持部ある。
Reference numeral 210 is a data holding portion, and further, 21
Reference numeral 1 is an order information holding unit that holds order information such as product specifications and customer information, 212 is a work content information holding unit that holds work content information indicating correspondence between order information and work contents, and 213 is work capability of each work department. A work capability information holding unit that holds information, 214 is a cost information holding unit that holds cost information indicating a cost calculation method according to work content, work time, etc., 21
Reference numeral 5 denotes a schedule information holding unit that holds schedule information indicating an existing schedule, and reference numeral 216 denotes a constraint information holding unit that holds constraint information that is a constraint condition regarding the schedule during the work.

【0026】220は演算処理装置であり、更に、22
1は受注情報と作業内容情報から、一つまたは複数の必
要となる作業を選択する作業選択手段、222は前記作
業を実行可能な作業部門に割当てる割当て手段、223
は作業内容と各作業部門の作業能力情報及び日程計画情
報から、各作業部門における各作業の日程を選択する日
程計画立案手段、224は日程計画情報と選択した日程
及びコスト情報から、発生する費用を算出する費用算出
手段、225は一つまたは複数の日程計画案の中から、
作業内容と各作業部門の作業能力情報、日程計画情報及
び制約情報から、各作業部門における各作業の日程を選
択する日程選択手段である。
Reference numeral 220 is an arithmetic processing unit, and further, 22
Reference numeral 1 is a work selecting means for selecting one or a plurality of necessary works from the order information and work content information, 222 is an allocating means for allocating the work to an executable work section, 223
Is a schedule planning means for selecting the schedule of each work in each work department from the work content, work capability information of each work department, and schedule planning information, and 224 is an expense incurred from the schedule plan information and the selected schedule and cost information. The cost calculation means 225 for calculating 225 from one or more schedule plans,
It is a schedule selecting means for selecting a schedule of each work in each work department from the work content, work capability information of each work department, schedule planning information and constraint information.

【0027】230は磁気記録媒体、光記録媒体、マウ
ス・キーボード、プリンタ、ネットワーク等の入出力装
置である。
Reference numeral 230 denotes an input / output device such as a magnetic recording medium, an optical recording medium, a mouse / keyboard, a printer and a network.

【0028】次に、図1により本発明による統括日程計
画方法の概略処理フローを説明する。ステップ101で
顧客の受注を実現するために必要となる一つまたは複数
の作業を抽出し、ステップ102で前記作業を実行可能
な作業部門に割当てる、ステップ103で各作業部門に
おける各作業の日程計画を立案し、ステップ104で各
作業部門毎に発生する費用を算出し、ステップ105で
一つまたは複数の日程計画案の中から、発生費用に基づ
き日程計画を選択する。
Next, referring to FIG. 1, a general processing flow of the general schedule planning method according to the present invention will be described. In step 101, one or a plurality of work required to realize the customer's order is extracted, and in step 102, the work is assigned to a work department capable of executing the work. In step 103, the schedule of each work in each work department is planned. In step 104, the cost incurred for each work department is calculated, and in step 105, a schedule is selected from one or a plurality of schedule plans based on the generated cost.

【0029】以下、図3に要求モデル、及び作業部門モ
デルを示し、また、各ステップの処理内容、及びデータ
保持部で保持している情報の詳細を図4から図9により
説明する。
The request model and the work department model are shown in FIG. 3, and the details of the processing contents of each step and the information held in the data holding unit will be described with reference to FIGS. 4 to 9.

【0030】図3はワークステーションの受注時のモデ
ルである。
FIG. 3 shows a model of a workstation when receiving an order.

【0031】310は入力装置から入力され、受注情報
保持部に記録される顧客の要求及び顧客に関する情報で
ある。ここでは、要求納期範囲、納入場所、製品の機
種、台数、大形計算機と繋ぐかあるいは単体で利用する
か等の利用形態、ソフトウェアのインストールをメーカ
側で行うか、顧客自身が行うかを示すセットアップ形
態、搬入日と据付日の間の条件を示す搬入条件が設定さ
れている。
Reference numeral 310 is information about the customer's request and the customer, which is input from the input device and recorded in the order information holding unit. This section shows the required delivery date range, delivery location, product model, number of units, usage pattern such as connecting to a large computer or using it alone, whether the software is installed by the manufacturer or by the customer himself. Set-up conditions and carry-in conditions indicating conditions between the carry-in date and the installation date are set.

【0032】320は作業部門モデルであり、調達部
門、製造部門、配送部門、据付部門から構成され、特に
製造部門は、ユニット組立部門、装置組立部門、加工部
門を含む。
A work department model 320 is composed of a procurement department, a manufacturing department, a delivery department, and an installation department. In particular, the manufacturing department includes a unit assembly department, a device assembly department, and a processing department.

【0033】図4は図1のステップ101「作業の抽出
処理」の例であり、410は受注情報、420は作業内
容情報のデータ構造例を示す。
FIG. 4 shows an example of step 101 "work extraction processing" in FIG. 1, in which 410 is an order information and 420 is a data structure example of work content information.

【0034】作業を抽出する処理では、受注情報(顧客
の要求及び顧客に関する情報)に記載された項目を、検
索のキーとして作業内容情報を検索し、必要となる作業
を抽出する。例えば、利用形態が「大形計算機と接続」
であり、納入場所が横浜であるため、横浜地区を担当す
る据付け部門で、大形計算機との接続能力を持った据付
け者が必要で、かつ、ネットワーク接続、アドレス設
定、等の作業が発生する。
In the process of extracting the work, the work content information is searched using the items described in the order information (customer's request and information about the customer) as a search key, and the necessary work is extracted. For example, the usage pattern is "connect to large computer"
Since the delivery place is Yokohama, the installation department in charge of the Yokohama area needs an installer with the ability to connect to a large-scale computer, and work such as network connection and address setting occurs. .

【0035】また、製品の機種がWS1であるため、オ
プションユニットの追加作業が発生する。
Since the model of the product is WS1, the additional work of the option unit occurs.

【0036】図1のステップ102では、前記のように
抽出された作業を作業部門へ割当てる。この場合、横浜
地区を担当する据付け部門に据付け作業が、製造部門の
加工部門にオプションユニットの追加作業が割当てられ
る。
In step 102 of FIG. 1, the work extracted as described above is assigned to a work department. In this case, the installation work is assigned to the installation section in charge of the Yokohama area, and the additional work of the option unit is assigned to the processing section of the manufacturing section.

【0037】図5は図1のステップ103「作業日程立
案処理」の例であり、図6は作業能力情報のデータ構造
例、図7は日程計画情報のデータ構造例を示す。
FIG. 5 shows an example of the step 103 "work schedule planning process" in FIG. 1, FIG. 6 shows a data structure example of work capability information, and FIG. 7 shows a data structure example of schedule planning information.

【0038】「作業日程立案処理」は作業部門に応じて
各々異なるが、本例は加工部門における日程計画の例で
ある。
Although the "work schedule planning process" differs depending on the work department, this example is an example of a schedule plan in the processing department.

【0039】まず、日々の作業負荷の基準を作成する
(501)。作業負荷の基準には、1)作業量から算出
した基準、2)作業能力を基準として用いる、3)
1)、2)の組合せによる等の方法がある。
First, a daily workload standard is created (501). For the workload standard, 1) a standard calculated from the amount of work, 2) work capacity is used as a standard, 3)
There are methods such as a combination of 1) and 2).

【0040】次に、全ての作業を作業可能な日程範囲の
うち最終日に山積みする(502)。 次に、作業負荷
の基準と日々の作業量の差を算出する(503)。
Next, all the works are piled up on the last day of the workable schedule range (502). Next, the difference between the workload standard and the daily workload is calculated (503).

【0041】計画期間の初日(504)から、以下のス
テップ505から511を繰り返す。
From the first day (504) of the planning period, the following steps 505 to 511 are repeated.

【0042】その日の作業量が基準量より少なければ、
その日以降の作業の中からその日に作業可能なものを探
し、その日の作業へと変更する(505〜507)。こ
こで再び作業量の差を算出し(508)、作業量が基準
量より少なければ、更に作業日変更の処理(506〜5
08)を繰り返す。作業量が作業基準の基準に達した
ら、計画の対象日を1日ずらし、ステップ505から5
08を繰り返す。
If the amount of work on the day is less than the reference amount,
From the work after that day, a work that can be done on that day is searched for, and the work is changed to that day (505 to 507). Here, the difference in the work amount is calculated again (508), and if the work amount is less than the reference amount, the work day change process is further performed (506 to 5).
08) is repeated. When the amount of work reaches the standard of the work standard, the target date of the plan is shifted by one day, and steps 505 to 5 are performed.
Repeat 08.

【0043】また、他の工程との間に日程的な制約があ
る場合は、ステップ501、502、506、507に
おいて作業可能日として他工程との間の制約を満足でき
る日を設定する。
If there is a schedule constraint with another process, in steps 501, 502, 506 and 507, a workable date is set that satisfies the constraint with another process.

【0044】次に、図1のステップ104「費用算出処
理」の詳細を説明する。
Next, the details of step 104 "cost calculation processing" in FIG. 1 will be described.

【0045】費用は、図8に示すように、作業内容、作
業時間、作業方法、作業場所、作業者、作業時刻との関
連で設定できる。これをコスト情報として予め保持して
いる。また、コスト算出ルールには、1)作業内容ベー
スの算出ルール、2)作業時間ベースの算出ルール、
3)1)2)の組合せによる算出ルール等がある。
As shown in FIG. 8, the cost can be set in relation to the work content, work time, work method, work place, worker, and work time. This is held in advance as cost information. The cost calculation rules include 1) work content based calculation rules, 2) work time based calculation rules,
3) There are calculation rules and the like based on the combination of 1) and 2).

【0046】例えば、ホストコンピュータとのネットワ
ーク接続をレベル1の作業者が日曜日の午後7時に行う
場合、1万円が必要となる。この時の作業時間は、1時
間と見積もられる。
For example, if a level 1 worker makes a network connection with a host computer at 7:00 pm on Sunday, 10,000 yen will be required. The working time at this time is estimated to be one hour.

【0047】また、作業内容は、受注情報と他の作業の
内容から決定される。例えば、横浜地区に配送する作業
を、川崎地区に配送する作業の次に行う時には、川崎か
ら横浜へ配送する作業を作業内容とする。
The work contents are determined from the order information and the contents of other works. For example, when the work of delivering to the Yokohama area is performed after the work of delivering to the Kawasaki area, the work of delivering from Kawasaki to Yokohama is the work content.

【0048】図1のステップ105では、このようにし
て図1のステップ101から104で作成された日程計
画案の中から、費用を評価尺度に日程計画を選択する。
In step 105 of FIG. 1, the schedule is selected with the cost as an evaluation measure from the schedule plans thus prepared in steps 101 to 104 of FIG.

【0049】例えば、総費用最小の日程計画を選択す
る。あるいは、費用、負荷バランス、総作業時間のトレ
ードオフから日程計画を選択する。図9は費用、負荷バ
ランス、総作業時間から日程計画を選択するための結果
表示画面例である。
For example, a schedule plan with the minimum total cost is selected. Alternatively, select the scheduling from the trade-off of cost, load balance, and total working time. FIG. 9 is an example of a result display screen for selecting a schedule from cost, load balance, and total work time.

【0050】本発明の他の実施例は、費用を評価尺度に
して決定した日程を基に、顧客への納期回答を行うもの
であり、図10に概要処理フロー、図11に納期選択方
法の一例を示す。
In another embodiment of the present invention, the delivery date is replied to the customer based on the schedule determined by using the cost as an evaluation scale. FIG. 10 shows the outline processing flow and FIG. 11 shows the delivery date selection method. An example is shown.

【0051】まず図10から説明する。始めに、顧客の
要求と顧客に関する情報を入力する。ここでは、要求納
期範囲(最早納期、最遅納期)、納入場所、製品の機
種、台数、大形計算機と繋ぐかあるいは単体で利用する
か等の利用形態、ソフトウェアのインストールをメーカ
側で行うか、顧客自身が行うかを示すセットアップ形
態、搬入日と据付日の間の条件を示す搬入条件が設定さ
れている。
First, description will be made with reference to FIG. First, enter customer requirements and information about the customer. Here, the required delivery date range (earliest delivery date, latest delivery date), delivery location, product model, number of units, usage pattern such as connecting to large computer or using alone, software installation by manufacturer , A setup form indicating whether the customer himself or herself will perform, and a carry-in condition indicating a condition between the carry-in date and the installation date are set.

【0052】これに基づき「作業の抽出処理」、作業の
場所を割当てる「作業の割当て処理」を行った後、各作
業の作業可能日を設定する。この範囲で作業間の日程制
約を満足した上で総費用最小の日程を選択し、全ての作
業が終了し、顧客への引渡しが可能となる日を納期とし
て設定する。
Based on this, the "work extraction process" and the "work assignment process" for allocating the place of the work are performed, and then the workable dates of the respective works are set. Within this range, the schedule with the minimum total cost is selected after satisfying the schedule constraint between the works, and the date when all the works are finished and can be delivered to the customer is set as the delivery date.

【0053】次に図11によりこの日程選択・納期設定
の方法を説明する。
Next, the method of selecting the schedule and setting the delivery date will be described with reference to FIG.

【0054】この例では、1)作業1は納期当日に行わ
なければならない、2)作業2は作業1の0日前から1
日前の範囲で行う、3)作業3は作業2の1日前から3
日前の範囲で行う、4)作業4は作業3の1日前から3
日前の範囲で行う、という制約条件を持っている。顧客
の要求納期範囲は2月1日から2月5日、( )の中
は、該当日に該当作業を行った場合に発生する費用であ
る。
In this example, 1) work 1 must be performed on the same day as the delivery date, and 2) work 2 is 1 from 0 days before work 1.
3) Work 3 from 1 day before work 2
4) Work 4 from 1 day before work 3
It has a constraint condition that it is done within the range of days ago. The customer's required delivery date range is February 1st to February 5th, and the value in parentheses is the cost incurred when the corresponding work is performed on that day.

【0055】例えば、1月29日に作業4を行い、2月
1日に作業3を行い、2月4日に作業2を行い、2月5
日に作業1を行うと、総費用は20+10+10+10
0=140であり、可能な組合せの中で総費用最小の組
合せとなる。この時、納期は2月5日と回答する。この
組合せは例えばダイナミックプログラミング等の手法で
探索できる。
For example, work 4 is performed on January 29, work 3 is performed on February 1, work 2 is performed on February 4, and work is performed on February 5
If you perform work 1 on a day, the total cost is 20 + 10 + 10 + 10
0 = 140, which is the lowest total cost combination among the possible combinations. At this time, the delivery date is February 5. This combination can be searched by a technique such as dynamic programming.

【0056】[0056]

【発明の効果】本発明によれば、製造・物流・サービス
作業部門を低コストで運用するための日程計画立案、顧
客への納期回答ができる。
According to the present invention, it is possible to plan a schedule for operating the manufacturing, logistics and service work departments at a low cost, and to answer the delivery date to the customer.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明の一実施例の処理フローチャート。FIG. 1 is a processing flowchart of an embodiment of the present invention.

【図2】本発明の一実施例の情報処理システムのブロッ
ク図。
FIG. 2 is a block diagram of an information processing system according to an embodiment of the present invention.

【図3】本発明の一実施例を適用するモデルの説明図。FIG. 3 is an explanatory diagram of a model to which an embodiment of the present invention is applied.

【図4】図1のステップ101の処理例の説明図。FIG. 4 is an explanatory diagram of a processing example of step 101 in FIG.

【図5】図1のステップ103の詳細処理フローチャー
ト。
5 is a detailed processing flowchart of step 103 in FIG.

【図6】作業能力情報の一例の説明図。FIG. 6 is an explanatory diagram of an example of work capability information.

【図7】日程計画情報の一例の説明図。FIG. 7 is an explanatory diagram of an example of schedule planning information.

【図8】コスト情報の一例の説明図。FIG. 8 is an explanatory diagram of an example of cost information.

【図9】図1のステップ105の対話処理を支援する表
示画面例の説明図。
9 is an explanatory diagram of an example of a display screen that supports the interactive process of step 105 of FIG.

【図10】本発明の他の実施例の処理フローチャート。FIG. 10 is a processing flowchart of another embodiment of the present invention.

【図11】本発明の他の実施例の処理結果の例の説明
図。
FIG. 11 is an explanatory diagram of an example of a processing result of another embodiment of the present invention.

【符号の説明】[Explanation of symbols]

210…データ保持部、 211…受注情報保持部、 212…作業内容情報保持部、 213…作業能力情報保持部、 214…コスト情報保持部、 215…日程計画情報保持部、 216…制約情報保持部、 220…演算処理装置、 221…作業選択手段、 222…割当て手段、 223…日程計画立案手段、 224…費用算出手段、 225…日程選択手段、 230…入出力装置。 210 ... Data holding unit, 211 ... Order information holding unit, 212 ... Work content information holding unit, 213 ... Work ability information holding unit, 214 ... Cost information holding unit, 215 ... Schedule planning information holding unit, 216 ... Constraint information holding unit Reference numeral 220 ... Arithmetic processing device, 221 ... Work selection means, 222 ... Assignment means, 223 ... Schedule planning means, 224 ... Cost calculation means, 225 ... Schedule selection means, 230 ... Input / output device.

───────────────────────────────────────────────────── フロントページの続き (72)発明者 佐藤 匡弘 神奈川県横浜市戸塚区吉田町292番地株式 会社日立製作所生産技術研究所内 ─────────────────────────────────────────────────── ─── Continuation of the front page (72) Inventor Masahiro Sato 292 Yoshida-cho, Totsuka-ku, Yokohama-shi, Kanagawa Stock Company Hitachi, Ltd.

Claims (6)

【特許請求の範囲】[Claims] 【請求項1】顧客の受注に応じて製造・物流・サービス
の日程計画を行う統括日程計画方法において、顧客の受
注を実現するために必要となる一つまたは複数の作業を
抽出する処理と、前記作業を実行可能な作業部門に割当
てる処理と、各作業部門における各作業の日程を選択す
る処理と、各作業部門毎に発生する費用を算出する処理
と、一つまたは複数の日程計画案の中から、発生費用に
基づき日程計画を選択する処理とを行うことを特徴とす
る統括日程計画方法。
Claim: What is claimed is: 1. In a general schedule planning method for scheduling a schedule for manufacturing, logistics, and services according to an order received from a customer, a process of extracting one or a plurality of works required to realize an order from the customer, The process of assigning the work to an executable work department, the process of selecting the schedule of each work in each work department, the process of calculating the cost incurred for each work department, and the schedule plan of one or more An integrated schedule planning method, characterized by performing a process of selecting a schedule based on the cost incurred.
【請求項2】顧客の受注に応じて製造・物流・サービス
の日程計画を行う統括日程計画装置において、製品仕様
・顧客情報等の受注情報を保持する受注情報保持部、受
注情報と作業内容の対応を示す作業内容情報を保持する
作業内容情報保持部、各作業部門の作業能力情報を保持
する作業能力情報保持部、作業内容・作業時刻等に応じ
た費用算出方法を示すコスト情報を保持するコスト情報
保持部、既存の日程計画を示す日程計画情報を保持する
日程計画情報保持部を有し、受注情報と作業内容情報か
ら、一つまたは複数の必要となる作業を選択する作業選
択手段と、前記作業を実行可能な作業部門に割当てる割
当て手段と、作業内容と各作業部門の作業能力情報及び
日程計画情報から、各作業部門における各作業の日程を
選択する日程選択手段と、日程計画情報と前記の選択し
た日程及びコスト情報から、発生する費用を算出する費
用算出手段と、一つまたは複数の日程計画案の中から、
発生費用に基づき日程計画を選択する日程計画案選択手
段を備えたことを特徴とする統括日程計画装置。
[Claim 2] In an integrated schedule planning device for scheduling a schedule for manufacturing, distribution, and service according to an order received from a customer, an order information holding unit for holding order information such as product specifications and customer information, an order information and work contents A work content information holding unit that holds work content information indicating correspondence, a work ability information holding unit that holds work ability information of each work department, and cost information indicating a cost calculation method according to work contents, work time, etc. A cost information storage unit, a schedule plan information storage unit that stores schedule plan information indicating an existing schedule plan, and work selection means for selecting one or more required works from order information and work content information. , Selecting a schedule for selecting each work schedule in each work department from the assignment means for allocating the work to an executable work department and the work content, work capability information of each work department, and schedule planning information And stage, from the selected schedule and cost information of the scheduling information, and cost calculation means for calculating the costs incurred from among the one or more schedule plan,
An integrated schedule planning device comprising a schedule plan selecting means for selecting a schedule plan based on incurred costs.
【請求項3】請求項1において、複数の作業部門にわた
り作業を行う際に、作業部門の間の日程に関する制約条
件を満足させる作業の日程を選択する処理と、一つまた
は複数の日程計画案の中から、全作業部門で発生する費
用に基づき日程計画を選択する処理を行うことを特徴と
する統括日程計画方法。
3. A process according to claim 1, wherein when performing work across a plurality of work departments, a process of selecting a work schedule that satisfies a constraint condition regarding a schedule between work departments, and one or more schedule plans. The schedule scheduling method is characterized by performing a process of selecting a schedule based on the costs incurred by all work departments.
【請求項4】請求項2において、作業部門の間の日程に
関する制約条件である制約情報を保持する制約情報保持
部を有し、作業内容と各作業部門の作業能力情報、日程
計画情報及び制約情報から、各作業部門における各作業
の日程を選択する日程選択手段と、日程計画情報と前記
の選択した日程及びコスト情報から、発生する費用を算
出する費用算出手段と、一つまたは複数の日程計画案の
中から、全作業部門で発生する費用に基づき日程計画を
選択する日程計画案選択手段を備えたことを特徴とする
統括日程計画装置。
4. The work information processing system according to claim 2, further comprising a constraint information holding unit for holding constraint information which is a constraint condition regarding a schedule between the work departments, the work content, work capability information of each work department, schedule planning information and constraints. Schedule selection means to select the schedule of each work in each work department from the information, cost calculation means to calculate the cost incurred from the schedule plan information and the selected schedule and cost information, and one or more schedules An integrated schedule planning device comprising: a schedule plan selecting means for selecting a schedule based on costs incurred by all work departments from a plan.
【請求項5】請求項1において、既存の日程計画に含ま
れている作業と新規に計画が必要な作業をあわせて、一
括して日程計画立案する統括日程計画方法。
5. The integrated schedule planning method according to claim 1, wherein a work schedule included in the existing schedule plan and a work requiring a new schedule are collectively planned.
【請求項6】請求項1または2において、前記統括日程
計画により選択された日程に基づき、顧客への納期、あ
るいは引渡し日を設定する処理を有する統括日程計画方
法。
6. The integrated schedule planning method according to claim 1, further comprising the step of setting a delivery date or a delivery date to the customer based on the schedule selected by the integrated schedule plan.
JP28166994A 1994-11-16 1994-11-16 Method and device for general schedule Pending JPH08147354A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP28166994A JPH08147354A (en) 1994-11-16 1994-11-16 Method and device for general schedule

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP28166994A JPH08147354A (en) 1994-11-16 1994-11-16 Method and device for general schedule

Publications (1)

Publication Number Publication Date
JPH08147354A true JPH08147354A (en) 1996-06-07

Family

ID=17642332

Family Applications (1)

Application Number Title Priority Date Filing Date
JP28166994A Pending JPH08147354A (en) 1994-11-16 1994-11-16 Method and device for general schedule

Country Status (1)

Country Link
JP (1) JPH08147354A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109636196A (en) * 2018-12-14 2019-04-16 天津字节跳动科技有限公司 Task arrangement method, device, electronic equipment and storage medium

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109636196A (en) * 2018-12-14 2019-04-16 天津字节跳动科技有限公司 Task arrangement method, device, electronic equipment and storage medium
CN109636196B (en) * 2018-12-14 2021-12-28 北京字节跳动网络技术有限公司 Task scheduling method and device, electronic equipment and storage medium

Similar Documents

Publication Publication Date Title
US8571912B2 (en) Method and system for allocating specific appointment time windows in a service industry
US8417368B2 (en) Method and apparatus for scheduling work orders in a manufacturing process
US5787000A (en) Method and apparatus for scheduling work orders in a manufacturing process
US7860737B2 (en) Constraint-based production planning and scheduling
US5923552A (en) Systems and methods for facilitating the exchange of information between separate business entities
US6119102A (en) MRP system with viewable master production schedule
US6947905B1 (en) System and method for displaying planning information associated with a supply chain
EP0797164A1 (en) Appointment booking and scheduling system
JP2003228410A (en) Work commencement management system
US20030171970A1 (en) Project scheduler interface
EP2610696A1 (en) Process design/production planning device
JPH10254962A (en) Group-based work capability correction device and work allocation system
WO1994016397A2 (en) Method of enterprise-wide to do list scheduling
JPH08147354A (en) Method and device for general schedule
JPH1087036A (en) Stock allocating method, and deciding method of distribution mode and stocking position, in physical distribution system
EP1114374A2 (en) System and method for displaying planning information associated with a supply chain
JPH06149848A (en) Automatic reserving method for stock of product
JPH1086044A (en) Worker's discretion utilization schedule planning method and device therefor
JP2006244470A (en) Delivery date reply system, delivery date reply method, and delivery date reply program
JPH07271864A (en) Production control method
JP3741076B2 (en) Delivery date answering system, delivery date answering method, order / delivery date answering device and program
JP2003237946A (en) Inventory allocation method
JPH10166247A (en) Production plan planning/operating supporting device
JP3853649B2 (en) Production management support system, method, apparatus, and program
JP2004145591A (en) System and method for distributing production capacity