JPH08144673A - Pre-boring method using auger - Google Patents

Pre-boring method using auger

Info

Publication number
JPH08144673A
JPH08144673A JP31555694A JP31555694A JPH08144673A JP H08144673 A JPH08144673 A JP H08144673A JP 31555694 A JP31555694 A JP 31555694A JP 31555694 A JP31555694 A JP 31555694A JP H08144673 A JPH08144673 A JP H08144673A
Authority
JP
Japan
Prior art keywords
guide
auger
spiral auger
excavation
pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP31555694A
Other languages
Japanese (ja)
Other versions
JP3563133B2 (en
Inventor
Kenzo Toyama
健三 遠山
Yutaka Nishimura
裕 西村
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Daido Concrete Kogyo KK
Daido Concrete Co Ltd
Original Assignee
Daido Concrete Kogyo KK
Daido Concrete Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Daido Concrete Kogyo KK, Daido Concrete Co Ltd filed Critical Daido Concrete Kogyo KK
Priority to JP31555694A priority Critical patent/JP3563133B2/en
Publication of JPH08144673A publication Critical patent/JPH08144673A/en
Application granted granted Critical
Publication of JP3563133B2 publication Critical patent/JP3563133B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Earth Drilling (AREA)

Abstract

PURPOSE: To easily excavate an embedding hole with high accuracy by performing a pre-boring. CONSTITUTION: An introducing pipe 10 for insertion of a spiral auger 5 is vertically movably provided in a scaffold 2 of a pile driving machine 1, on which the spiral auger 5 connected to a drive device 4 is mounted so as to be vertically movable. Before excavating an embedding hole for a pile or the like, the pipe 10 is lowered at a predetermined excavation site and the lower end thereof is forced into the ground to erect it and the spiral auger 5 is inserted into the pipe 10 so that an embedding hole is excavated using the pipe 10 as a guide.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明は、基礎杭等の施工にあた
り、オーガーによって埋設孔を掘削するプレボーリング
工法に関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a pre-boring method for excavating a buried hole with an auger when constructing a foundation pile or the like.

【0002】[0002]

【従来の技術】基礎杭等の施工では、オーガーによって
掘削孔を形成し、その孔の中に基礎杭等を埋設するプレ
ボーリング工法が多く採用されている。この工法は一般
に、図4に示すように、杭打機1のヤグラ2に設けられ
たガイドレール3に駆動装置4を昇降自在に設けるとと
もに、ヤグラ2の下部に振止め管6を設け、下部を振止
め管6に挿通したスパイラルオーガ5の上端を駆動装置
4に接続して、スパイラオーガ5を回転しながら地中に
押込んで掘削を行うものである。
2. Description of the Related Art In the construction of foundation piles and the like, a pre-boring method is often employed in which an excavation hole is formed by an auger and the foundation pile or the like is embedded in the hole. As shown in FIG. 4, this construction method generally includes a guide rail 3 provided on a yagler 2 of a pile driving machine 1 on which a drive device 4 can be raised and lowered, and a shake prevention tube 6 is provided on a lower portion of the yagler 2, The upper end of the spiral auger 5 which is inserted into the swing stop pipe 6 is connected to the drive device 4, and the spiral auger 5 is rotated and pushed into the ground for excavation.

【0003】この場合、掘削は杭を埋設する位置に正し
く削成する必要がある。そのため、従来は、図5に示す
ように、地上に埋設孔とほぼ同径の管状パネル7(鎖線
で示す)を載置し、その周囲に石灰等の粉末8を散布し
た後、管状パネル7を取除き、マーキングの粉末8によ
り囲まれた中を掘削地9として、その中心部にスパイラ
ルオーガ5の先端5aを合せるようにして掘削を開始す
るようにしている。
In this case, the excavation must be properly cut at the position where the pile is buried. Therefore, conventionally, as shown in FIG. 5, a tubular panel 7 (shown by a chain line) having substantially the same diameter as the buried hole is placed on the ground, and powder 8 such as lime is scattered around the tubular panel 7 and then the tubular panel 7 is placed. The excavation site 9 is surrounded by the marking powder 8, and the excavation is started by aligning the tip 5a of the spiral auger 5 with the center of the excavation site 9.

【0004】[0004]

【発明が解決しようとする課題】しかし、実際には、掘
削地9の中心部にスパイラルオーガ5の先端5aを正し
く合せることはなかなか困難なことで、芯ずれをおこす
ことが多い。また、たとえ芯合せが正しく行われた場合
でも、地盤の強度にバラツキがあったり石等があったり
すると、芯ずれが生じることが多く、そのため、埋設孔
を所定の位置に正しく掘削することが難しいという状況
である。
However, in practice, it is quite difficult to correctly align the tip 5a of the spiral auger 5 with the center of the excavation site 9, and misalignment often occurs. In addition, even if the centering is performed correctly, if the ground strength is uneven or there are stones, etc., misalignment often occurs, so that it is possible to correctly excavate the buried hole at a predetermined position. It is a difficult situation.

【0005】本発明は上記の問題を解決するためになさ
れたもので、相当長さの案内管を地面の所定位置に立設
し、その案内管にスパイラルオーガを挿通して掘削を行
うことにより、面倒な芯合せをすることなく埋設孔の掘
削が精度よく容易に行い得るようにしようとするもので
ある。
The present invention has been made to solve the above problems, and a guide pipe of a considerable length is erected at a predetermined position on the ground, and a spiral auger is inserted through the guide pipe to perform excavation. The purpose of the present invention is to make it possible to excavate a buried hole accurately and easily without complicated alignment.

【0006】[0006]

【課題を解決するための手段】上記の目的を達成するた
めの本発明の構成について、実施例に対応する図面を参
照して説明すると、本発明は、杭打機1のヤグラ2に、
駆動装置4に接続したスパイラルオーガ5及び該スパイ
ラルオーガ5を挿通する誘導管10を、それぞれ昇降自在
に設け、基礎杭等の埋設孔の掘削位置に合せて、地上に
上記誘導管10を降下させ、その下端を地盤に食い込ませ
て立設した後、スパイラルオーガ5を誘導管10に挿入
し、誘導管10をガイドとして掘削を行うことを特徴とす
るものである。
The structure of the present invention for achieving the above object will be described with reference to the drawings corresponding to the embodiments. The present invention relates to a yagura 2 of a pile driving machine 1,
A spiral auger 5 connected to the drive unit 4 and a guide pipe 10 through which the spiral auger 5 is inserted are provided so as to be vertically movable, and the guide pipe 10 is lowered to the ground in accordance with the excavation position of a buried hole such as a foundation pile. The bottom end of the spiral auger 5 is inserted into the guide pipe 10, and the guide pipe 10 is used as a guide for excavation.

【0007】[0007]

【作用】埋設孔の掘削に先立って、所定の掘削地9の周
囲にマーキングの粉末8を散布する。誘導管10は粉末8
に囲まれた掘削地9に合致できるように降下させれば、
誘導管10はその下端の刃形部12により地盤に食い込んで
立設される。ついで、スパイラルオーガ5を降下させて
行けば、その先端部は誘導管10に挿入され、誘導管10が
ガイドとなって埋設孔が掘削、形成されることになる。
Before the excavation of the buried hole, the marking powder 8 is sprinkled around the predetermined excavation site 9. Induction tube 10 is powder 8
If you descend so that it can match the excavated area 9 surrounded by
The guide pipe (10) is erected by cutting into the ground by a blade-shaped portion (12) at its lower end. Then, when the spiral auger 5 is lowered, the tip end thereof is inserted into the guide tube 10, and the guide tube 10 serves as a guide to excavate and form a buried hole.

【0008】[0008]

【実施例】以下、本発明の実施例について図面を参照し
て説明する。図1は本発明の一実施例による施工状態を
示す概略図、図2は同要部の拡大断面図、図3は本発明
において使用するスパイラルオーガの誘導管の斜視図で
ある。
Embodiments of the present invention will be described below with reference to the drawings. FIG. 1 is a schematic view showing a construction state according to an embodiment of the present invention, FIG. 2 is an enlarged sectional view of the same part, and FIG. 3 is a perspective view of a spiral auger guide tube used in the present invention.

【0009】図において、1は杭打機、2は杭打機1の
ヤグラ、3,3は2本一対のガイドレールである。ガイ
ドレール3,3は所要の間隔をおいて竪方向に並列さ
れ、互いに多数の連結材21,21により結合されており、
ヤグラ2の一側に、ヤグラ2と間隔をおいて多数の支持
部材22,22を介して取付けられている。
In the figure, 1 is a pile driver, 2 is a yagura of the pile driver 1, and 3 and 3 are a pair of guide rails. The guide rails 3, 3 are arranged in parallel in the vertical direction at a required interval and are connected to each other by a large number of connecting members 21, 21.
It is attached to one side of the yagura 2 via a large number of support members 22, 22 with a space from the yagura 2.

【0010】そして、ガイドレール3,3には駆動装置
4が昇降自在に設けられ、取付けられたワイヤロープ23
の引上げ、繰出しにより、ガイドレール3,3に沿って
昇降調節されるようになっており、駆動装置4には、駆
動装置4によって回転されるスパイラルオーガ5が吊設
される。また、ガイドレール3,3には、スパイラルオ
ーガ5を挿通する誘導管10が昇降自在に設けられてい
る。
A drive device 4 is provided on the guide rails 3 and 3 so as to be vertically movable, and is attached to the wire rope 23.
It is adapted to be vertically moved along the guide rails 3 and 3 by pulling up and feeding out, and a spiral auger 5 which is rotated by the drive device 4 is suspended from the drive device 4. Further, a guide tube 10 through which the spiral auger 5 is inserted is provided on the guide rails 3 and 3 so as to be vertically movable.

【0011】誘導管10は、鋼管等により上下に長く形成
されており、その上端部はスパイラルオーガ5の挿入を
容易にするためラッパ状11に拡げられ、下端は刃形部12
に形成されている。誘導管10の上部外側面には、誘導管
10をガイドレール3,3に昇降自在に取付けるための係
合部材13が突設されている。
The guide tube 10 is formed of a steel tube or the like so as to be vertically long, the upper end thereof is expanded into a trumpet shape 11 to facilitate the insertion of the spiral auger 5, and the lower end thereof is a blade portion 12.
Is formed. On the upper outer surface of the guide tube 10, the guide tube
Engaging members 13 for attaching the 10 to the guide rails 3 and 3 so as to be able to move up and down are projected.

【0012】係合部材13は、ガイドレール3に外接する
断面半円状の係合溝14を有する取付板の一対15,15と、
それらの間に介在された接続部材16と、取付板15,15と
接続部材16とを結合する締付けボルト17,17により形成
されている。そして、締付ボルト17,17の締付け度合に
よって、取付板15,15相互の間隔を若干変えることがで
き、それによってガイドレール3への接合圧力が調節で
きるようになっている。
The engaging member 13 is a pair of mounting plates 15 and 15 having an engaging groove 14 having a semicircular cross section, which circumscribes the guide rail 3.
It is formed by the connecting member 16 interposed between them, and the fastening bolts 17, 17 connecting the mounting plates 15, 15 and the connecting member 16. The distance between the mounting plates 15 and 15 can be slightly changed depending on the degree of tightening of the tightening bolts 17 and 17, whereby the joining pressure to the guide rail 3 can be adjusted.

【0013】また、誘導管10の上端には小さな環体18が
突設され、これに誘導管10を昇降させるワイヤロープ19
の端末が結合されている。ワイヤロープ19はヤグラ2の
上部に設けた滑車20を介して張設され、その引上げ、繰
出しにより、誘導管10がガイドレール3,3に沿って昇
降されるようになっている。
A small ring 18 is provided at the upper end of the guide tube 10, and a wire rope 19 for raising and lowering the guide tube 10 is provided on this.
Terminals are combined. The wire rope 19 is stretched via a pulley 20 provided on the upper portion of the yagura 2, and the guide tube 10 is moved up and down along the guide rails 3 and 3 by pulling up and feeding it out.

【0014】本発明の工法は、上記の杭打機1を使用し
て実施される。基礎杭等の埋設孔を掘削するにあたって
は、従来のように、掘削位置の地上に図5に示すよう
に、埋設孔とほぼ同径の管状パネル7を載置して、その
周囲に石灰等の粉末8を散布してマーキングを施した
後、管状パネル7を取除き、粉末8により囲まれた中を
掘削地9として定める。また、杭打機1の方は、スパイ
ラルオーガ5及び誘導管10を引上げた状態にして誘導管
10が掘削地9に合致する位置に移動する。
The construction method of the present invention is carried out by using the pile driving machine 1 described above. When excavating a buried hole such as a foundation pile, as in the conventional case, a tubular panel 7 having a diameter substantially the same as that of the buried hole is placed on the ground at the excavation position as shown in FIG. After the powder 8 is sprayed and marked, the tubular panel 7 is removed, and the area surrounded by the powder 8 is defined as the excavation site 9. For the pile driver 1, the spiral auger 5 and the guide pipe 10 are pulled up and the guide pipe is
10 moves to a position corresponding to the excavated site 9.

【0015】次に、誘導管10のワイヤロープ19を繰出し
て誘導管10を降下させ、誘導管10の下端を掘削地9に食
い込ませる。この場合、誘導管10の下端は刃形部12とな
っているとともに、誘導管10は相当の重量を有すること
から、その下端部は図示のように相当部分(5〜10cm)
地盤に食い込むことになって立設される。地盤が硬いよ
うな場合でも、誘導管10をある高さから急激に落下させ
るようにすれば確実に食い込ませることができる。
Next, the wire rope 19 of the guide tube 10 is paid out to lower the guide tube 10 and the lower end of the guide tube 10 is cut into the excavation site 9. In this case, the lower end of the guide tube 10 is a blade portion 12 and the guide tube 10 has a considerable weight, so that the lower end thereof is a corresponding portion (5 to 10 cm) as shown in the figure.
It is set up by cutting into the ground. Even when the ground is hard, it is possible to surely make the guide pipe 10 bite if it is made to fall suddenly from a certain height.

【0017】その後は、駆動装置4のワイヤロープ23を
繰出して降下させ、スパイラルオーガ5の先端部を誘導
管10に挿入してその先端5aを接地させる。その状態で
駆動装置4によりスパイラルオーガ5を回転させながら
降下させて行けば、誘導管10により囲まれた掘削地9よ
り掘削が進行し、掘削孔が形成されることになる。その
際、スクリューオーガ5は地盤に立設された誘導管10を
ガイドとして回転、掘削を行うので、従来のような面倒
な芯合せを行う必要がなく、所定の掘削地を確実に掘下
げて行くことができる。掘削孔の形成後は、スパイラル
オーガ5を引上げるとともに誘導管10を引上げ、杭打機
1を次の掘削位置に移動し、上記同様の作業が繰返し行
われる。
After that, the wire rope 23 of the drive unit 4 is paid out and lowered, the tip of the spiral auger 5 is inserted into the guide tube 10, and the tip 5a thereof is grounded. In that state, if the spiral auger 5 is lowered while being rotated by the drive device 4, the excavation will proceed from the excavation site 9 surrounded by the guide pipe 10, and the excavation hole will be formed. At that time, since the screw auger 5 rotates and excavates by using the guide pipe 10 erected on the ground as a guide, it is not necessary to perform the complicated centering as in the conventional case, and the predetermined excavation site is surely dug down. be able to. After the formation of the excavation hole, the spiral auger 5 is pulled up, the guide pipe 10 is pulled up, the pile driver 1 is moved to the next excavation position, and the same work as above is repeated.

【0018】[0018]

【発明の効果】以上説明したように、本発明によれば、
埋設孔の掘削にあたり、スクリューオーガの挿通できる
誘導管を、掘削位置の地盤にその下端を食い込ませて立
設し、その誘導管をスクリューオーガのガイドとして掘
削を行うようにしたので、従来のような、スクリューオ
ーガ先端の芯合せを行うという面倒な作業を行うことな
く、所定の位置への掘削孔の形成が容易、確実に行い得
られる。また、地盤強度のバラツキ等によるスクリュー
オーガの芯ずれも防止され、精度よく掘削ができる。
As described above, according to the present invention,
When excavating a buried hole, a guide pipe through which a screw auger can be inserted is erected upright at the bottom of the excavation position, and the guide pipe is used as a guide for the screw auger. In addition, it is possible to easily and surely form a drill hole at a predetermined position without performing the troublesome work of aligning the tip of the screw auger. Further, misalignment of the screw auger due to variations in ground strength, etc. is prevented, and excavation can be performed accurately.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明の一実施例による施工状態を示す該略図
である。
FIG. 1 is a schematic view showing a construction state according to an embodiment of the present invention.

【図2】同要部の拡大断面図である。FIG. 2 is an enlarged cross-sectional view of the same main part.

【図3】本発明で使用するスパイラルオーガの誘導管を
示す斜視図である。
FIG. 3 is a perspective view showing a guide tube of the spiral auger used in the present invention.

【図4】従来の施工術を示す概略図である。FIG. 4 is a schematic view showing a conventional construction technique.

【図5】同要部の拡大断面図である。FIG. 5 is an enlarged sectional view of the main part.

【符号の説明】[Explanation of symbols]

1 杭打機 2 ヤグラ 3 ガイドレール 4 駆動装置 5 スパイラルオーガ 6 振止め管 7 管状パネル 8 粉末 9 掘削地 10 誘導管 12 刃形部 13 係合部材 14 係合溝 15 取付板 16 接続部材 17 締付ボルト 18 環体 19,23 ワイヤロープ 1 Pile driver 2 Yagura 3 Guide rail 4 Drive device 5 Spiral auger 6 Swing pipe 7 Tubular panel 8 Powder 9 Excavation site 10 Guide tube 12 Edge portion 13 Engaging member 14 Engaging groove 15 Mounting plate 16 Connecting member 17 Tightening Attached bolt 18 Annular body 19,23 Wire rope

Claims (1)

【特許請求の範囲】[Claims] 杭打機のヤグラに、駆動装置に接続したスパイラルオー
ガ及び該スパイラルオーガを挿通する誘導管を、それぞ
れ昇降自在に設け、基礎杭等の埋設孔の掘削位置に合せ
て、地上に上記誘導管を降下させ、その下端を地盤に食
い込ませて立設した後、スパイラルオーガを誘導管に挿
入し、誘導管をガイドとして掘削を行うことを特徴とす
る、オーガーによるプレボーリング工法。
Spiral auger connected to the driving device and a guide pipe through which the spiral auger is inserted are provided in the yagura of the pile driver so that they can be moved up and down, respectively, in accordance with the excavation position of the buried hole of the foundation pile, etc. A pre-boring method using an auger, which comprises lowering the bottom end of the auger to stand upright by digging into the ground, inserting a spiral auger into the guide pipe, and excavating using the guide pipe as a guide.
JP31555694A 1994-11-25 1994-11-25 Pre-boring method by auger Expired - Fee Related JP3563133B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP31555694A JP3563133B2 (en) 1994-11-25 1994-11-25 Pre-boring method by auger

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP31555694A JP3563133B2 (en) 1994-11-25 1994-11-25 Pre-boring method by auger

Publications (2)

Publication Number Publication Date
JPH08144673A true JPH08144673A (en) 1996-06-04
JP3563133B2 JP3563133B2 (en) 2004-09-08

Family

ID=18066772

Family Applications (1)

Application Number Title Priority Date Filing Date
JP31555694A Expired - Fee Related JP3563133B2 (en) 1994-11-25 1994-11-25 Pre-boring method by auger

Country Status (1)

Country Link
JP (1) JP3563133B2 (en)

Also Published As

Publication number Publication date
JP3563133B2 (en) 2004-09-08

Similar Documents

Publication Publication Date Title
JPH08144673A (en) Pre-boring method using auger
CN110629765B (en) Safety protection device and protection method for H-shaped steel foundation pit
JP2779389B2 (en) Rotary press-in device for steel pipe piles for settlement settlement
JP2005220573A (en) Pile driving method
JP3169911B2 (en) Heavy weight type steel pipe digging and driving method using the same
JPH05287745A (en) Mounting method for wale in column aligning method
JP2003027469A (en) Steel pipe pile, foundation pile producing method using the same and device of the method
JP2002030658A (en) Support for hammer drill
JP3325550B2 (en) Pile construction equipment and pile construction method
JP2981164B2 (en) Drilling rig
JP2875338B2 (en) Excavation method by screw auger and its equipment
JP2589271B2 (en) Drilling rig
JP3265491B2 (en) Positioning method of vertical columns
JP2973186B2 (en) Pile driving method
JP3232196B2 (en) Drilling method and excavator for pile hole
JP2023077243A (en) Installation method for core material
JP2586459Y2 (en) Drilling equipment
JP4289617B2 (en) How to place ready-made piles
JPS6153915A (en) Method of driving down sheathing material
JP3622850B2 (en) Cutting method of shaft structure
JP2973187B2 (en) Screw wobbler for soil excavation
CN118065759A (en) Double-casing drilling construction process for rotary drilling of sand-rich stratum in riverside region
JP3203435B2 (en) Pile hole drilling method, guide plate for drilling head and drilling rod
JP2005226268A (en) Method for placing steel pipe sheet pile
JP2858050B2 (en) Shaft excavation method

Legal Events

Date Code Title Description
A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20040129

TRDD Decision of grant or rejection written
A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20040402

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20040518

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20040602

R150 Certificate of patent (=grant) or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

S111 Request for change of ownership or part of ownership

Free format text: JAPANESE INTERMEDIATE CODE: R313111

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20080611

Year of fee payment: 4

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090611

Year of fee payment: 5

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090611

Year of fee payment: 5

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100611

Year of fee payment: 6

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100611

Year of fee payment: 6

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110611

Year of fee payment: 7

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120611

Year of fee payment: 8

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120611

Year of fee payment: 8

S531 Written request for registration of change of domicile

Free format text: JAPANESE INTERMEDIATE CODE: R313531

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120611

Year of fee payment: 8

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120611

Year of fee payment: 8

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120611

Year of fee payment: 8

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130611

Year of fee payment: 9

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130611

Year of fee payment: 9

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

LAPS Cancellation because of no payment of annual fees