JPH08144295A - Execution method of precast reinforced concrete foundation and ruler for execution of work - Google Patents

Execution method of precast reinforced concrete foundation and ruler for execution of work

Info

Publication number
JPH08144295A
JPH08144295A JP28830594A JP28830594A JPH08144295A JP H08144295 A JPH08144295 A JP H08144295A JP 28830594 A JP28830594 A JP 28830594A JP 28830594 A JP28830594 A JP 28830594A JP H08144295 A JPH08144295 A JP H08144295A
Authority
JP
Japan
Prior art keywords
reinforced concrete
precast reinforced
foundations
precast
ruler
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP28830594A
Other languages
Japanese (ja)
Other versions
JP3432310B2 (en
Inventor
Hiroshi Shimoyama
洋 下山
Toshiki Nogami
利樹 野上
Kunio Ando
邦雄 安藤
Norikatsu Shiyou
典克 正
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
NAGOYA SEKISUI HAIMU KENSETSU
NAGOYA SEKISUI HAIMU KENSETSU KK
Sekisui Chemical Co Ltd
Original Assignee
NAGOYA SEKISUI HAIMU KENSETSU
NAGOYA SEKISUI HAIMU KENSETSU KK
Sekisui Chemical Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by NAGOYA SEKISUI HAIMU KENSETSU, NAGOYA SEKISUI HAIMU KENSETSU KK, Sekisui Chemical Co Ltd filed Critical NAGOYA SEKISUI HAIMU KENSETSU
Priority to JP28830594A priority Critical patent/JP3432310B2/en
Publication of JPH08144295A publication Critical patent/JPH08144295A/en
Application granted granted Critical
Publication of JP3432310B2 publication Critical patent/JP3432310B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Foundations (AREA)

Abstract

PURPOSE: To position a foundation accurately by inserting the bolt inserting sections of a ruler for the execution of works to each anchor bolt of adjacent precast reinforced concrete foundations and positioning the relative places of the foundations. CONSTITUTION: A plurality of precast reinforced concrete foundations 10 are hung up and juxtaposed. The bolt inserting sections 111, 112 of a ruler 110 for the execution of works are inserted to each anchor bolt 101 of the adjacent foundations 10, and the relative places of the foundations 10 are positioned. Main reinforcements 11A, 11B projected from the cast-in-place concrete sections 12 of the foundations 10 are connected mutually on the rear sides of precast sections 11 while stirrups 19 are arranged, and web reinforcements 20 are disposed and bound at places crossed at right angles with the stirrups 19. Forms are installed around the base concrete placing sections 13 and cast-in-place concrete sections 12 of the foundations 10 while base reinforcements are bound with the main reinforcements 11B of the foundations 10. Concrete is placed to the concrete placing sections 13, 12.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明は、プレキャスト鉄筋コン
クリート基礎の施工方法と施工用定規に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a construction method for a precast reinforced concrete foundation and a construction ruler.

【0002】[0002]

【従来の技術】従来、建物の基礎構築に係る工期を、現
場打ち鉄筋コンクリート基礎に比して短縮するため、特
開平2-38626 号公報に記載の如くのプレキャスト鉄筋コ
ンクリート基礎が提案されている。この従来のプレキャ
スト鉄筋コンクリート基礎は、下記(1) 〜(3) の如くに
施工される。
2. Description of the Related Art Conventionally, a precast reinforced concrete foundation as disclosed in Japanese Patent Laid-Open No. 2-38626 has been proposed in order to shorten the construction period for building foundation as compared with a cast-in-place reinforced concrete foundation. This conventional precast reinforced concrete foundation is constructed as described in (1) to (3) below.

【0003】(1) 複数の工場生産したプレキャスト鉄筋
コンクリート基礎を現場にて並べる。
(1) A plurality of factory-produced precast reinforced concrete foundations are lined up on site.

【0004】(2) 相隣るプレキャスト鉄筋コンクリート
基礎の現場コンクリート打設部に突き出ている鉄筋同士
を互いに接続して連結する。
(2) Reinforcing bars that project from the adjacent precast reinforced concrete foundations on the site where concrete is cast are connected to each other.

【0005】(3) プレキャスト鉄筋コンクリート基礎の
現場コンクリート打設部回りに型枠を施し、この現場コ
ンクリート打設部及びベースコンクリート打設部にコン
クリートを打設することにより、相隣るプレキャスト鉄
筋コンクリート基礎を接合して一体の基礎とする。
(3) Forming a frame around the on-site concrete placing portion of the precast reinforced concrete foundation, and by placing concrete on the on-site concrete placing portion and the base concrete placing portion, the adjacent precast reinforced concrete foundation is placed. Join to form the basis of one.

【0006】尚、基礎にあっては、基礎上に載置される
鉄骨構造建物ユニットの床大梁、もしくは木質建物の土
台に設けてあるアンカーボルト孔を、基礎の天端に突設
してあるアンカーボルトに挿通することにて、それらの
床大梁、もしくは土台を基礎上にて締結するものとな
る。そこで、従来技術では、上記(1) において、相隣る
プレキャスト鉄筋コンクリート基礎の据付時に、一方の
プレキャスト鉄筋コンクリート基礎を先に設置した後に
他方のプレキャスト鉄筋コンクリート基礎をクレーン等
で吊り込み、両プレキャスト鉄筋コンクリート基礎のプ
レキャスト部の天端に設けてあるアンカーボルト間距離
を鋼製スケール等で測定し、測定したアンカーボルト間
距離が所定値になるように上記他方のプレキャスト鉄筋
コンクリート基礎の据付位置を修正してそれらの相対位
置を位置決めすることとしている。
In the foundation, an anchor bolt hole provided on the floor girder of a steel structure building unit placed on the foundation or on the base of a wooden building is provided at the top end of the foundation. By inserting the anchor bolts, those floor girders or foundations are fastened on the foundation. Therefore, in the prior art, in the above (1), when installing the precast reinforced concrete foundations next to each other, first install one precast reinforced concrete foundation and then hang the other precast reinforced concrete foundation with a crane, etc. Measure the distance between the anchor bolts provided at the top of the precast part with a steel scale, etc., and correct the installation position of the other precast reinforced concrete foundation so that the measured distance between the anchor bolts will be a predetermined value. The relative position is set.

【0007】[0007]

【発明が解決しようとする課題】然しながら、従来技術
では、相隣るプレキャスト鉄筋コンクリート基礎のアン
カーボルト間距離が所定値に合致するまで、プレキャス
ト鉄筋コンクリート基礎の据付位置の修正とアンカーボ
ルト間距離の再測定とを何回も繰り返す必要がある。こ
のため、施工工数が多大となり、据付位置精度の向上に
も困難がある。
However, in the prior art, until the distance between the anchor bolts of the adjacent precast reinforced concrete foundations matches the predetermined value, the installation position of the precast reinforced concrete foundation is corrected and the distance between the anchor bolts is measured again. It is necessary to repeat and many times. For this reason, the number of construction steps becomes large, and it is difficult to improve the accuracy of the installation position.

【0008】本発明は、相隣るプレキャスト鉄筋コンク
リート基礎の相対位置を迅速かつ正確に位置決めするこ
とを目的とする。
It is an object of the present invention to quickly and accurately position the relative positions of adjacent precast reinforced concrete foundations.

【0009】[0009]

【課題を解決するための手段】請求項1に記載の本発明
は、プレキャスト部の天端にアンカーボルトを突設して
なるとともに、プレキャスト部の端部に鉄筋が突き出た
現場コンクリート打設部を備えてなるプレキャスト鉄筋
コンクリート基礎の施工方法において、相隣るプレキャ
スト鉄筋コンクリート基礎の所定のアンカーボルト間距
離をなす2つの位置にボルト嵌入部を備えてなる施工用
定規を予め用意し、複数のプレキャスト鉄筋コンクリー
ト基礎を現場にて並べ、相隣るプレキャスト鉄筋コンク
リート基礎それぞれのアンカーボルトに上記施工用定規
のボルト嵌入部を嵌入して、相隣るプレキャスト鉄筋コ
ンクリート基礎の相対位置を位置決めし、相隣るプレキ
ャスト鉄筋コンクリート基礎の現場コンクリート打設部
に突き出ている鉄筋同士を互いに接続し、それらプレキ
ャスト鉄筋コンクリート基礎の現場コンクリート打設部
にコンクリートを打設して一体の基礎とするようにした
ものである。
According to a first aspect of the present invention, an anchor bolt is projectingly provided at a top end of a precast portion, and a reinforcing bar is projected at an end portion of the precast portion. In a method of constructing a precast reinforced concrete foundation comprising a plurality of precast reinforced concrete bases, a construction ruler having bolt insertion portions at two positions forming a predetermined anchor bolt distance between adjacent precast reinforced concrete foundations is prepared in advance. The foundations are lined up at the site, and the anchor fittings of the adjacent precast reinforced concrete foundations are fitted with the bolt insertion parts of the above-mentioned ruler to position the relative positions of the adjacent precast reinforced concrete foundations, and the adjacent precast reinforced concrete foundations. Iron sticking out on the site concrete placing part of Connect to each other to each other, in which as the basis of the integral by Da設 concrete on site concrete portion thereof precast reinforced concrete foundation.

【0010】請求項2に記載の本発明は、請求項1に記
載の施工用定規であって、少なくとも一方のボルト嵌入
部が該定規の側部に開口するU字溝状をなし、アンカー
ボルトに水平方向から係脱できるように構成されてなる
ものである。
The present invention as set forth in claim 2 is the construction ruler as set forth in claim 1, wherein at least one bolt fitting portion has a U-shaped groove opening to a side portion of the ruler, and the anchor bolt. It is configured so that it can be engaged and disengaged from the horizontal direction.

【0011】[0011]

【作用】請求項1に記載の本発明によれば下記の作用
がある。 相隣るプレキャスト鉄筋コンクリート基礎それぞれの
アンカーボルトに施工用定規のボルト嵌入部を嵌入し
て、相隣るプレキャスト鉄筋コンクリート基礎の相対位
置を位置決めするものであるから、相隣るプレキャスト
鉄筋コンクリート基礎の相対位置を迅速かつ正確に位置
決めできる。
According to the present invention as set forth in claim 1, the following effects are obtained. The relative position of the adjacent precast reinforced concrete foundations is determined by inserting the bolt insertion part of the construction ruler into each anchor bolt of the adjacent precast reinforced concrete foundations and positioning the relative position of the adjacent precast reinforced concrete foundations. Can be positioned quickly and accurately.

【0012】請求項2に記載の本発明によれば下記の
作用がある。 施工用定規の少なくとも一方のボルト嵌入部が定規の
側部に開口するU字溝状をなす。従って、先行設置した
プレキャスト鉄筋コンクリート基礎のアンカーボルトに
施工用定規のボルト嵌入部を嵌入した状態で、施工用定
規のU字溝状ボルト嵌入部が後続設置のプレキャスト鉄
筋コンクリート基礎のアンカーボルトに水平方向から係
入できる位置まで、後続のプレキャスト鉄筋コンクリー
ト基礎を先行のプレキャスト鉄筋コンクリート基礎に対
して接近/離隔する一方向にのみ誘導すれば、施工用定
規のU字溝状ボルト嵌入部は水平方向から移動されて極
めて容易にアンカーボルトに嵌入でき、施工作業性を向
上できる。
The present invention according to claim 2 has the following effects. At least one bolt fitting portion of the construction ruler has a U-shaped groove opening to a side portion of the ruler. Therefore, the U-shaped grooved bolt insertion part of the construction ruler is inserted into the anchor bolt of the pre-cast reinforced concrete foundation that is installed in advance, and the U-shaped grooved bolt insertion part of the construction ruler is installed from the horizontal direction to the anchor bolt of the pre-cast reinforced concrete foundation that is installed subsequently. By guiding the subsequent precast reinforced concrete foundation in only one direction to approach / separate from the preceding precast reinforced concrete foundation to the position where it can be engaged, the U-shaped grooved bolt fitting part of the construction ruler is moved from the horizontal direction. It can be inserted into the anchor bolt very easily, and the workability of construction can be improved.

【0013】[0013]

【実施例】図1はプレキャスト鉄筋コンクリート基礎を
示す模式図、図2はプレキャスト鉄筋コンクリート基礎
の鉄筋接続構造を示す模式図、図3はプレキャスト鉄筋
コンクリート基礎の施工手順を示す模式図、図4は施工
用定規を示す模式図である。
EXAMPLE FIG. 1 is a schematic diagram showing a precast reinforced concrete foundation, FIG. 2 is a schematic diagram showing a reinforcing rod connection structure of the precast reinforced concrete foundation, FIG. 3 is a schematic diagram showing a construction procedure of the precast reinforced concrete foundation, and FIG. 4 is a construction ruler. It is a schematic diagram which shows.

【0014】プレキャスト鉄筋コンクリート基礎10
は、図1〜図3に示す如く、予め工場生産されたもので
ある。
Precast reinforced concrete foundation 10
Is manufactured in advance in a factory as shown in FIGS.

【0015】プレキャスト鉄筋コンクリート基礎10
は、プレキャスト部11の端部に上下の主鉄筋11A、
11Bを突出した現場コンクリート打設部12を備え
る。尚、プレキャスト鉄筋コンクリート基礎10は、図
2(B)に示す如く、プレキャスト部11における現場
コンクリート打設部12に臨む端面に埋め込んであるね
じ込み式金具12Aに上記主鉄筋11Aをねじ込み接続
し、この主鉄筋11Aをプレキャスト部11の端部に突
き出すものであっても良い。
Precast reinforced concrete foundation 10
Is the upper and lower main reinforcing bars 11A at the end of the precast portion 11,
The on-site concrete placing part 12 protruding 11B is provided. In addition, as shown in FIG. 2 (B), the precast reinforced concrete foundation 10 is obtained by screwing and connecting the main rebar 11A to the screw-type metal fitting 12A embedded in the end face of the precast part 11 facing the on-site concrete placing part 12. The reinforcing bar 11A may be projected to the end of the precast portion 11.

【0016】また、プレキャスト鉄筋コンクリート基礎
10は、プレキャスト部11の下部に下主鉄筋11Bを
延在させ、且つ多数の鉄筋11Cを突き出したベースコ
ンクリート打設部13を備える。
Further, the precast reinforced concrete foundation 10 is provided with a base concrete placing section 13 in which a lower main reinforcing bar 11B is extended below the precast section 11 and a large number of reinforcing bars 11C are projected.

【0017】このとき、プレキャスト鉄筋コンクリート
基礎10は、図1、図2に示す如く、プレキャスト部1
1の端部において、現場コンクリート打設部12をプレ
キャスト部11の裏面側に設けることとしている。
At this time, the precast reinforced concrete foundation 10 has the precast part 1 as shown in FIGS.
At the end of No. 1, the on-site concrete placing section 12 is provided on the back surface side of the precast section 11.

【0018】また、プレキャスト鉄筋コンクリート基礎
10は、図1、図3に示す如く、プレキャスト部11の
下部において、鉄筋11Cの突出部の側傍で該鉄筋11
Cの突出量より下方に大きく突き出るとともに、下主鉄
筋11Bの中間部の一部を包む台座14を備えている。
Further, as shown in FIGS. 1 and 3, the precast reinforced concrete foundation 10 has a lower portion of the precast portion 11 at the side of the projecting portion of the reinforcing rod 11C.
It is provided with a pedestal 14 that protrudes downward more than the protruding amount of C and encloses a part of the intermediate portion of the lower main reinforcing bar 11B.

【0019】また、プレキャスト鉄筋コンクリート基礎
10は、図1に示す如く、プレキャスト部11の表面に
化粧模様15を備えている。化粧模様15は、縦横に伸
びるタイル目地状模様である。
Further, the precast reinforced concrete foundation 10 is provided with a decorative pattern 15 on the surface of the precast portion 11 as shown in FIG. The decorative pattern 15 is a tile joint pattern that extends vertically and horizontally.

【0020】また、プレキャスト鉄筋コンクリート基礎
10は、図1〜図3に示す如く、プレキャスト部11の
天端にアンカーボルト101を突設している。このアン
カーボルト101は、プレキャスト鉄筋コンクリート基
礎10を用いて施工された基礎上に載置される鉄骨構造
建物ユニットの床大梁、もしくは木質建物の土台に設け
られるアンカーボルト孔が挿通され、それらの床大梁も
しくは土台を基礎上にて締結するものである。このた
め、基礎の構築に際しては、相隣るプレキャスト鉄筋コ
ンクリート基礎10のアンカーボルト101、101の
距離が所定値Lをなすようにそれらのプレキャスト鉄筋
コンクリート基礎10を設置しなければならない。
The precast reinforced concrete foundation 10 has an anchor bolt 101 protruding from the top end of the precast portion 11 as shown in FIGS. The anchor bolt 101 has a floor girder of a steel structure building unit placed on a foundation constructed by using a precast reinforced concrete foundation 10 or an anchor bolt hole provided in a base of a wooden building is inserted through the floor girder. Alternatively, the foundation is fastened on the foundation. Therefore, when constructing the foundations, the precast reinforced concrete foundations 10 must be installed so that the distance between the anchor bolts 101, 101 of the adjacent precast reinforced concrete foundations 10 is a predetermined value L.

【0021】そこで、本実施例では、プレキャスト鉄筋
コンクリート基礎10の据付けに際しては、図4に示す
如くの施工用定規110を用いることとした。施工用定
規110は、コンクリートの線膨張係数とあまり大きく
異ならない、例えば鋼製の角管等にて製作され、その上
端のそれぞれにアンカーボルト嵌入部111、112が
設けられる。両ボルト嵌入部111、112は、相隣る
プレキャスト鉄筋コンクリート基礎10の所定のアンカ
ーボルト間距離Lをなす2つの位置のそれぞれに設けら
れる。そして、一方のボルト嵌入部111は丸孔状をな
し、他方のボルト嵌入部112は該定規110の側部に
開口するU字溝状をなし、結果としてボルト嵌入部11
1を先行設置のプレキャスト鉄筋コンクリート基礎10
のアンカーボルト101に嵌入した状態で、定規110
をそのアンカーボルト101まわりで回動し、ボルト嵌
入部112を後続設置のプレキャスト鉄筋コンクリート
基礎10のアンカーボルト101に水平方向から容易に
係脱できるようにしている。
Therefore, in this embodiment, when installing the precast reinforced concrete foundation 10, a construction ruler 110 as shown in FIG. 4 is used. The construction ruler 110 is made of, for example, a square tube made of steel or the like that does not significantly differ from the linear expansion coefficient of concrete, and anchor bolt fitting portions 111 and 112 are provided at the upper ends thereof, respectively. Both bolt fitting portions 111 and 112 are provided at two positions forming a predetermined inter-anchor bolt distance L of the adjacent precast reinforced concrete foundations 10. One of the bolt fitting portions 111 has a round hole shape, and the other bolt fitting portion 112 has a U-shaped groove shape that opens to a side portion of the ruler 110. As a result, the bolt fitting portion 11 is formed.
1 pre-installed precast reinforced concrete foundation 10
With the anchor bolt 101 fitted in, the ruler 110
Is rotated about the anchor bolt 101 so that the bolt fitting portion 112 can be easily engaged and disengaged from the anchor bolt 101 of the precast reinforced concrete foundation 10 to be installed later in the horizontal direction.

【0022】以下、施工用定規110を用いたプレキャ
スト鉄筋コンクリート基礎10の施工手順について説明
する。 (1) 工場生産したプレキャスト鉄筋コンクリート基礎1
0を集積、保管場から現場に運搬する。このとき、プレ
キャスト鉄筋コンクリート基礎10は台座14を着座面
とする立てた状態で取扱われる。
The procedure for constructing the precast reinforced concrete foundation 10 using the construction ruler 110 will be described below. (1) Factory produced precast reinforced concrete foundation 1
0 is collected and transported from the storage to the site. At this time, the precast reinforced concrete foundation 10 is handled in an upright state with the pedestal 14 as a seating surface.

【0023】(2) 現場では、プレキャスト鉄筋コンクリ
ート基礎10の設置基板が整えられ、敷板16、ベース
筋17が配置される(図3(A))。
(2) At the site, the installation substrate of the precast reinforced concrete foundation 10 is prepared, and the floor board 16 and the base reinforcement 17 are arranged (FIG. 3 (A)).

【0024】(3) プレキャスト鉄筋コンクリート基礎1
0をクレーン等で吊り込み設置する。このとき、敷板1
6上にはジャッキプレート18が配置されており、プレ
キャスト鉄筋コンクリート基礎10の台座14がジャッ
キプレート18上に降ろされ据付けられる。ジャッキプ
レート18の位置調整により、プレキャスト鉄筋コンク
リート基礎10の通りと天端高さが揃えられる(図3
(B))。このとき、プレキャスト鉄筋コンクリート基
礎10のプレキャスト部11に付されている化粧模様1
5の横目地15Aが基礎ベース部に対するレベル出し、
相隣る基礎10同士のレベル合わせの目安として用いら
れる。
(3) Precast reinforced concrete foundation 1
0 is installed by hanging it with a crane. At this time, floor plate 1
A jack plate 18 is arranged on the jack 6, and the pedestal 14 of the precast reinforced concrete foundation 10 is lowered onto the jack plate 18 and installed. By adjusting the position of the jack plate 18, the top height is aligned with that of the precast reinforced concrete foundation 10 (Fig. 3).
(B)). At this time, the decorative pattern 1 attached to the precast portion 11 of the precast reinforced concrete foundation 10
The horizontal joint 15A of 5 gives a level to the basic base portion,
It is used as a standard for level adjustment between adjacent foundations 10.

【0025】また、相隣るプレキャスト鉄筋コンクリー
ト基礎10それぞれのアンカーボルト101に施工用定
規110のボルト嵌入部111、112を嵌入して相隣
るプレキャスト鉄筋コンクリート基礎10の相対位置を
位置決めする。このとき、施工用定規110は、丸孔状
ボルト嵌入部111を先行設置のプレキャスト鉄筋コン
クリート基礎10のアンカーボルト101に嵌入した状
態で、後続設置のプレキャスト鉄筋コンクリート基礎1
0を先行設置のプレキャスト鉄筋コンクリート基礎10
に対して接近/離隔する一方向においてのみ移動し、U
字溝状ボルト嵌入部112を後続設置のプレキャスト鉄
筋コンクリート基礎10のアンカーボルト101に前述
したように水平方向から嵌入する。
Further, the bolt insertion portions 111 and 112 of the construction ruler 110 are inserted into the anchor bolts 101 of the adjacent precast reinforced concrete foundations 10 to position the relative positions of the adjacent precast reinforced concrete foundations 10. At this time, the construction ruler 110 is a state in which the round hole-shaped bolt fitting portion 111 is fitted into the anchor bolt 101 of the pre-installed precast reinforced concrete foundation 10 and then the precast reinforced concrete foundation 1 is installed subsequently.
0 pre-installed precast reinforced concrete foundation 10
Move only in one direction to approach / separate from
The grooved bolt fitting portion 112 is fitted from the horizontal direction into the anchor bolt 101 of the precast reinforced concrete foundation 10 to be installed subsequently, as described above.

【0026】(4) 相隣るプレキャスト鉄筋コンクリート
基礎10の現場コンクリート打設部12に突き出ている
主鉄筋11A、11B同士をそれらのプレキャスト部1
1の裏側で結束もしくは接続具を用いて互いに接続す
る。スターラップ19を所定のピッチで配置する。腹筋
20を上下の主鉄筋11A、11Bの間でスターラップ
19に直交する位置に配置し、鉄線で結束する(図3
(B))。
(4) The main rebars 11A and 11B protruding from the on-site concrete placing part 12 of the adjacent precast reinforced concrete foundations 10 are connected to each other by the precast part 1
They are connected to each other on the back side of 1 using ties or connectors. The stirrup 19 is arranged at a predetermined pitch. The abdominal muscles 20 are arranged between the upper and lower main reinforcing bars 11A and 11B at a position orthogonal to the stirrup 19, and are bound by iron wires (FIG.
(B)).

【0027】(5) プレキャスト鉄筋コンクリート基礎1
0のベースコンクリート打設部13、現場コンクリート
打設部12回りに型枠21を施す(図3(C))。尚、
プレキャスト鉄筋コンクリート基礎10の下主鉄筋11
Bにベース筋17を結束する。
(5) Precast reinforced concrete foundation 1
A form 21 is provided around the base concrete placing section 13 of 0 and the on-site concrete placing section 12 (FIG. 3 (C)). still,
Precast reinforced concrete foundation 10 Lower main reinforcement 11
The base muscle 17 is tied to B.

【0028】(6) プレキャスト鉄筋コンクリート基礎1
0のベースコンクリート打設部13にコンクリートを打
設し、続いて現場コンクリート打設部12にコンクリー
トを打設することにより、相隣るプレキャスト鉄筋コン
クリート基礎10を接合して一体の基礎とする。図1に
おいて、23は基礎ベースコンクリート、22は現場打
設コンクリートである。
(6) Precast reinforced concrete foundation 1
0 is cast into the base concrete placing portion 13 and then into the site concrete placing portion 12 to join the adjacent precast reinforced concrete foundations 10 to form an integral foundation. In FIG. 1, 23 is a foundation base concrete and 22 is a cast-in-place concrete.

【0029】以下、本実施例の作用について説明する。 相隣るプレキャスト鉄筋コンクリート基礎10それぞ
れのアンカーボルト101に施工用定規110のボルト
嵌入部111、112を嵌入して、相隣るプレキャスト
鉄筋コンクリート基礎10の相対位置を位置決めするも
のであるから、相隣るプレキャスト鉄筋コンクリート基
礎10の相対位置を迅速かつ正確に位置決めできる。
The operation of this embodiment will be described below. Since the bolt fitting portions 111 and 112 of the construction ruler 110 are fitted into the anchor bolts 101 of the adjacent precast reinforced concrete foundations 10 to position the relative positions of the adjacent precast reinforced concrete foundations 10, The relative position of the precast reinforced concrete foundation 10 can be positioned quickly and accurately.

【0030】施工用定規110の一方のボルト嵌入部
112が定規110の側部に開口するU字溝状をなす。
従って、先行設置したプレキャスト鉄筋コンクリート基
礎10のアンカーボルト101に施工用定規110のボ
ルト嵌入部111を嵌入した状態で、施工用定規110
のU字溝状ボルト嵌入部112が後続設置のプレキャス
ト鉄筋コンクリート基礎10のアンカーボルト101に
水平方向から係入できる位置まで、後続のプレキャスト
鉄筋コンクリート基礎10を先行のプレキャスト鉄筋コ
ンクリート基礎10に対して接近/離隔する一方向にの
み誘導すれば、施工用定規110のU字溝状ボルト嵌入
部112は水平方向から移動されて極めて容易にアンカ
ーボルト101に嵌入でき、施工作業性を向上できる。
One of the bolt fitting portions 112 of the construction ruler 110 has a U-shaped groove shape that opens to the side of the ruler 110.
Therefore, with the bolt fitting portion 111 of the construction ruler 110 fitted in the anchor bolt 101 of the precast reinforced concrete foundation 10 installed in advance, the construction ruler 110
The subsequent precast reinforced concrete foundation 10 approaches / separates from the preceding precast reinforced concrete foundation 10 until a position where the U-shaped grooved bolt fitting portion 112 of FIG. 11 can be engaged with the anchor bolt 101 of the subsequently installed precast reinforced concrete foundation 10 from the horizontal direction. If it is guided only in one direction, the U-shaped grooved bolt fitting portion 112 of the construction ruler 110 can be moved from the horizontal direction and can be extremely easily fitted into the anchor bolt 101, and construction workability can be improved.

【0031】以上、本発明の実施例を図面により詳述し
たが、本発明の具体的な構成はこの実施例に限られるも
のではなく、本発明の要旨を逸脱しない範囲の設計の変
更等があっても本発明に含まれる。例えば、施工用定規
は、基礎のアンカーボルト間ピッチに合致する所定ピッ
チをなす3個以上のボルト嵌入部を備えるものであって
も良い。また、施工用定規は、両ボルト嵌入部とも丸孔
状、もしくは両ボルト嵌入部ともU字溝状をなすもので
あっても良い。
The embodiment of the present invention has been described in detail above with reference to the drawings. However, the specific configuration of the present invention is not limited to this embodiment, and changes in design within the scope not departing from the gist of the present invention can be made. Even if it exists, it is included in the present invention. For example, the construction ruler may include three or more bolt fitting portions having a predetermined pitch that matches the pitch between the anchor bolts of the foundation. Further, the construction ruler may have a round hole shape for both bolt fitting portions or a U-shaped groove shape for both bolt fitting portions.

【0032】また、施工用定規は、相隣るプレキャスト
鉄筋コンクリート基礎の通りを揃えるための機能、或い
はプレキャスト鉄筋コンクリート基礎の水平を出すため
の水平器の機能を備えるものであっても良い。
The construction ruler may have a function of aligning the streets of the adjacent precast reinforced concrete foundations or a function of a leveler for leveling the precast reinforced concrete foundations.

【0033】[0033]

【発明の効果】以上のように本発明によれば、相隣るプ
レキャスト鉄筋コンクリート基礎の相対位置を迅速かつ
正確に位置決めすることができる。
As described above, according to the present invention, the relative positions of adjacent precast reinforced concrete foundations can be positioned quickly and accurately.

【図面の簡単な説明】[Brief description of drawings]

【図1】図1はプレキャスト鉄筋コンクリート基礎を示
す模式図である。
FIG. 1 is a schematic diagram showing a precast reinforced concrete foundation.

【図2】図2はプレキャスト鉄筋コンクリート基礎の鉄
筋接続構造を示す模式図である。
FIG. 2 is a schematic view showing a reinforcing bar connection structure of a precast reinforced concrete foundation.

【図3】図3はプレキャスト鉄筋コンクリート基礎の施
工手順を示す模式図である。
FIG. 3 is a schematic diagram showing a procedure for constructing a precast reinforced concrete foundation.

【図4】図4は施工用定規を示す模式図である。FIG. 4 is a schematic view showing a construction ruler.

【符号の説明】[Explanation of symbols]

10 プレキャスト鉄筋コンクリート基礎 11 プレキャスト部 101 アンカーボルト 110 施工用定規 111、112 ボルト嵌入部 10 Precast Reinforced Concrete Foundation 11 Precast Section 101 Anchor Bolt 110 Construction Ruler 111, 112 Bolt Insertion Section

───────────────────────────────────────────────────── フロントページの続き (72)発明者 野上 利樹 茨城県つくば市和台32 積水化学工業株式 会社内 (72)発明者 安藤 邦雄 愛知県名古屋市中村区名駅4−7−35 名 古屋セキスイハイム建設株式会社内 (72)発明者 正 典克 愛知県名古屋市中村区名駅4−7−35 名 古屋セキスイハイム建設株式会社内 ─────────────────────────────────────────────────── ─── Continuation of front page (72) Inventor Toshiki Nogami 32 Wadai, Tsukuba City, Ibaraki Prefecture Sekisui Chemical Co., Ltd. (72) Inventor Kunio Ando 4-7-35 Mei Station, Nakamura-ku, Aichi Prefecture Heim Construction Co., Ltd. (72) Masanori Masakatsu 4-7-35 Mei Station, Nakamura-ku, Nagoya, Aichi Prefecture Sekisui Heim Construction Co., Ltd.

Claims (2)

【特許請求の範囲】[Claims] 【請求項1】 プレキャスト部の天端にアンカーボルト
を突設してなるとともに、プレキャスト部の端部に鉄筋
が突き出た現場コンクリート打設部を備えてなるプレキ
ャスト鉄筋コンクリート基礎の施工方法において、 相隣るプレキャスト鉄筋コンクリート基礎の所定のアン
カーボルト間距離をなす2つの位置にボルト嵌入部を備
えてなる施工用定規を予め用意し、 複数のプレキャスト鉄筋コンクリート基礎を現場にて並
べ、相隣るプレキャスト鉄筋コンクリート基礎それぞれ
のアンカーボルトに上記施工用定規のボルト嵌入部を嵌
入して、相隣るプレキャスト鉄筋コンクリート基礎の相
対位置を位置決めし、 相隣るプレキャスト鉄筋コンクリート基礎の現場コンク
リート打設部に突き出ている鉄筋同士を互いに接続し、 それらプレキャスト鉄筋コンクリート基礎の現場コンク
リート打設部にコンクリートを打設して一体の基礎とす
るプレキャスト鉄筋コンクリート基礎の施工方法。
1. A method for constructing a precast reinforced concrete foundation, comprising an anchor bolt projecting from the top end of the precast part, and a site concrete placing part in which a reinforcing bar projects from the end of the precast part. Pre-cast reinforced concrete foundations Prepare a construction ruler that has bolt insertion parts at two positions that make a predetermined distance between anchor bolts, arrange multiple pre-cast reinforced concrete foundations on-site, and each adjacent pre-cast reinforced concrete foundation Insert the bolt fitting part of the above-mentioned construction ruler into the anchor bolt of the above to position the relative position of the adjacent precast reinforced concrete foundations, and reinforce the reinforcing bars protruding into the site concrete placing part of the adjacent precast reinforced concrete foundations to each other. Connect and precast them Construction method of precast reinforced concrete foundation to be the basis for the integrated and Da設 the concrete on-site concrete portion of the reinforced concrete foundation.
【請求項2】 請求項1に記載の施工用定規であって、
少なくとも一方のボルト嵌入部が該定規の側部に開口す
るU字溝状をなし、アンカーボルトに水平方向から係脱
できるように構成されてなる施工用定規。
2. The construction ruler according to claim 1, wherein:
A ruler for construction, wherein at least one bolt fitting portion has a U-shaped groove shape that opens to a side portion of the ruler and is configured to be engageable with and disengageable from an anchor bolt in a horizontal direction.
JP28830594A 1994-11-22 1994-11-22 Precast reinforced concrete foundation construction method and construction ruler. Expired - Fee Related JP3432310B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP28830594A JP3432310B2 (en) 1994-11-22 1994-11-22 Precast reinforced concrete foundation construction method and construction ruler.

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP28830594A JP3432310B2 (en) 1994-11-22 1994-11-22 Precast reinforced concrete foundation construction method and construction ruler.

Publications (2)

Publication Number Publication Date
JPH08144295A true JPH08144295A (en) 1996-06-04
JP3432310B2 JP3432310B2 (en) 2003-08-04

Family

ID=17728456

Family Applications (1)

Application Number Title Priority Date Filing Date
JP28830594A Expired - Fee Related JP3432310B2 (en) 1994-11-22 1994-11-22 Precast reinforced concrete foundation construction method and construction ruler.

Country Status (1)

Country Link
JP (1) JP3432310B2 (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108222292A (en) * 2018-03-17 2018-06-29 福州大学 Detachable connection structure and its installation method between prefabricated board
CN111255060A (en) * 2020-03-18 2020-06-09 常州工程职业技术学院 Detachable reinforced concrete strip foundation combination system and assembling method
CN114809074A (en) * 2022-04-20 2022-07-29 浙江交工金筑交通建设有限公司 Construction method for horizontal prefabricated assembly type box-shaped channel of cast-in-place bottom plate

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108222292A (en) * 2018-03-17 2018-06-29 福州大学 Detachable connection structure and its installation method between prefabricated board
CN108222292B (en) * 2018-03-17 2024-03-22 福州大学 Detachable connecting structure between prefabricated plates and installation method thereof
CN111255060A (en) * 2020-03-18 2020-06-09 常州工程职业技术学院 Detachable reinforced concrete strip foundation combination system and assembling method
CN114809074A (en) * 2022-04-20 2022-07-29 浙江交工金筑交通建设有限公司 Construction method for horizontal prefabricated assembly type box-shaped channel of cast-in-place bottom plate

Also Published As

Publication number Publication date
JP3432310B2 (en) 2003-08-04

Similar Documents

Publication Publication Date Title
EP2250323B1 (en) Masonry with vertical reinforced concrete strengthening
US6637167B2 (en) Modular wall construction
EP2313575B1 (en) Masonry bracket, system and construction method
CA1179519A (en) Precast building element and method
KR20110128396A (en) Pre-embedded anchor frame equipped with coupler and anchoring method of steel column thereof
JPH08269911A (en) Structure of attaching part of concrete wall transom
US20090165408A1 (en) Construction elements and methods of construction
JP3432310B2 (en) Precast reinforced concrete foundation construction method and construction ruler.
JP2926149B2 (en) Column and beam joining method and its structure
AU2009297184B2 (en) Hanger system for cementitious building units
US5150552A (en) Building system for extension of progressive housing
JP3662207B2 (en) Construction block for concrete foundation for construction and construction method for concrete foundation for construction
JP3108112B2 (en) Foundation structure
JPH0988348A (en) Method for constructing foundation beam
JP3232487B2 (en) Construction method of column base and column base structure
KR200233319Y1 (en) A Sectional L Type Retaining Wall
KR20240086283A (en) Seismic retrofit wall with U-tie
JPH0881960A (en) Precast reinforced concrete foundation and execution method thereof
KR200242422Y1 (en) A Sectional T Type Retaining Wall
KR20200025292A (en) A method of construction for bridge abutment using concrete retaining wall
JPH0881961A (en) Precast reinforced concrete foundation
GB2201700A (en) Wall ties for concrete block constructions
JPH02285110A (en) Construction method of form for placing concrete foundation
JPH0813512A (en) Foundation constructing method
JPH08144296A (en) Execution method of precast reinforced concrete foundation and form fixture

Legal Events

Date Code Title Description
LAPS Cancellation because of no payment of annual fees