JPH08100530A - Confirmation method for injection or discharge of grout for post-tension prestressed concrete and device therefor - Google Patents

Confirmation method for injection or discharge of grout for post-tension prestressed concrete and device therefor

Info

Publication number
JPH08100530A
JPH08100530A JP25972594A JP25972594A JPH08100530A JP H08100530 A JPH08100530 A JP H08100530A JP 25972594 A JP25972594 A JP 25972594A JP 25972594 A JP25972594 A JP 25972594A JP H08100530 A JPH08100530 A JP H08100530A
Authority
JP
Japan
Prior art keywords
grout
injection
confirmation device
discharge
hose
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP25972594A
Other languages
Japanese (ja)
Inventor
Kenichi Tokura
賢一 徳良
Seiroku Miyama
清六 深山
Akira Takebe
陽 武部
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
P C KYORYO KK
Original Assignee
P C KYORYO KK
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by P C KYORYO KK filed Critical P C KYORYO KK
Priority to JP25972594A priority Critical patent/JPH08100530A/en
Publication of JPH08100530A publication Critical patent/JPH08100530A/en
Pending legal-status Critical Current

Links

Landscapes

  • Reinforcement Elements For Buildings (AREA)

Abstract

PURPOSE: To easily confirm visually non-charge or shortage of charge due to human errors, by providing a transparent or translucent spherical or square preliminary pool in the middle of a grouting hose. CONSTITUTION: A spherical or square confirmation device 6 of grout injection or discharge, made of a transparent or translucent high strength material, by which non-charge or shortage of charge can be visually confirmed, is inserted in a grout hose 4 erected in a sheath 3 of a precast concrete structure 1. And the upper and lower ends are fixed by stop rings 7. The confirmation device 6 of grout injection or discharge is fitted at 400mm or higher level than the top end 1a of the precast concrete structure and the capacity must be twice of the case of only grout hose 4 or larger than that. The outer periphery of the confirmation device 6 of grout injection and discharge is reinforced by a high strength mesh body. And it is preferable to set a check valve 8 at the upper end of grout hose 4 lest dusts and foreign materials should are mixed before grouting.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明は、ポストテンション方式
プレストレストコンクリート構造物の施工に関し、特
に、その定着体及びシース内へのグラウト注入に際し、
シースの壁面に穿設された小孔や定着体前面に取り付け
たグラウトホースにグラウト注入及び排出状態を目視確
認し、かつグラウトの予備溜めを可能とした、グラウト
注入及び排出確認器具を取着してなるポストテンション
方式プレストレストコンクリートグラウト注入及び排出
確認方法及び注入及び排出確認装置に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to the construction of a post-tension type prestressed concrete structure, and in particular, when injecting grout into the fixing body and the sheath,
A grout injection and discharge confirmation device was installed to visually check the grout injection and discharge conditions on a small hole drilled on the wall surface of the sheath and a grout hose attached to the front of the fixing body, and to enable preliminary storage of grout. Post tension type prestressed concrete grout injection and discharge confirmation method and injection and discharge confirmation device.

【0002】[0002]

【従来の技術】ポストテンション方式によるプレストレ
ストコンクリート構造物の製造方法においては、PC鋼
材とそれを覆うシース及び補強鉄筋を型枠内に配置した
後、該型枠内へのコンクリートを打設し、コンクリート
が所定の強度に達したのち、PC鋼材を左右両端あるい
はどちらか一方から緊張し、このPC鋼材の端部を定着
具により定着することによって、コンクリートにプレス
トレスを導入している。図3は従来のポストテンション
方式プレストレストコンクリート構造物の緊張端部施工
方法の概要説明図であって、図中、1はポストテンショ
ン方式プレストレストコンクリート構造物、2は定着
体、3はシース、4は該シースの上面に垂直に配設した
グラウトホースであって、グラウトの注入やシース3内
に注入されるグラウト(以下に説明する)によって、シ
ース内に存在する水や空気等を排出するためのものであ
る。また、グラウトホース4の上端は逆U字に折り曲げ
られ、ワイヤー5を介し、三脚支保具(図示せず)に結
束されて、垂直に吊り上げられている。
2. Description of the Related Art In a method of manufacturing a prestressed concrete structure by a post-tension method, a PC steel material, a sheath for covering it and reinforcing reinforcing bars are placed in a mold, and then concrete is poured into the mold. After the concrete reaches a predetermined strength, the PC steel material is tensioned from the left and right ends or one of the both ends, and the end portion of the PC steel material is fixed by a fixing tool to introduce prestress to the concrete. FIG. 3 is a schematic explanatory view of a tension end construction method for a conventional post-tensioning prestressed concrete structure, in which 1 is a post-tensioning prestressed concrete structure, 2 is a fixing member, 3 is a sheath, and 4 is A grout hose arranged vertically on the upper surface of the sheath, for discharging water, air, etc. existing in the sheath by injecting grout or grout (described below) injected into the sheath 3 It is a thing. Further, the upper end of the grout hose 4 is bent in an inverted U shape, is bound to a tripod support tool (not shown) via a wire 5, and is vertically lifted.

【0003】また、このポストテンション方式に用いら
れる従来の一般的な定着体2の詳細構成を図4に示す。
図中、10は単又は複数本のPC鋼材であって、その端
部はメスコーン11に挿通され、各オスコーン12が嵌
挿されて、シース3に包まれ、プレストレスを導入され
たPC鋼材10を固定している。また、緊張したPC鋼
材10の腐食を防止し、かつPC鋼材10をシース3内
に緊張した状態で固定するため、また定着体21の内外
付近部を固定化するため、外部より定着体21付近及び
シース3内へグラウトを注入充填することが行われる。
その際において、グラウトの注入充填は高圧で実施され
るので、グラウトキャン28を定着体21に固定して定
着体21全体を密封状態で覆うか、定着体21の前面に
後打ちコンクリート又はモルタルを打設して密封し、グ
ラウトキャン28のグラウト充填孔29又は定着体背面
のグラウト充填孔30からグラウトを高圧(注入圧2〜
3kg/cm,最終注入圧3〜6kg/cm)で注
入し、その後硬化させてPC鋼材10を固定する。
FIG. 4 shows a detailed structure of a conventional general fixing member 2 used in this post tension system.
In the figure, 10 is a single or a plurality of PC steel materials, the end portion of which is inserted into a female cone 11, each male cone 12 is fitted and inserted into the sheath 3, and PC steel material 10 into which prestress is introduced. Is fixed. Further, in order to prevent the strained PC steel material 10 from corroding and fix the PC steel material 10 in the sheath 3 in a tensioned state, and to fix the inner and outer portions of the fixing body 21, the vicinity of the fixing body 21 from the outside. Injecting and filling the grout into the sheath 3 is performed.
At this time, since the grout is injected and filled at a high pressure, the grout can 28 is fixed to the fixing body 21 to cover the entire fixing body 21 in a sealed state, or the front surface of the fixing body 21 is covered with post-cast concrete or mortar. The grout is filled with high pressure (injection pressure 2 to 5) from the grout filling hole 29 of the grout can 28 or the grout filling hole 30 on the rear surface of the fixing member.
3 kg / cm 2, was injected with a final injection pressure 3~6kg / cm 2), by then cured to secure the PC steel 10.

【0004】[0004]

【発明が解決しようとする課題】従来は前記のごとく、
グラウトの注入においては、注入排気排水用のグラウト
ホース4をコンクリート構造物1の打ち上がり天端1a
より1m以上の高さに立設し、注入側グラウトと排出側
グラウトが均質となった時点で排出側グラウトホースを
封止し、注入側圧力を所要の圧力に保持したのち、注入
側グラウトホースを封止する。その後、注入及び排出さ
れたグラウトが該ホース4の高さまで達したことでシー
ス3内の充填を確認していた。また同時にブリージング
水の注出をも確認していた。また該ホース4の1mの高
さ内に備蓄されるグラウトの量は、ホース内径を12m
mとすると約113ccになり、これがグラウト注入不
足あるいは膨張不足時の予備量として作用していた。し
かしながら、グラウトホース4にはメッシュで補強され
た比較的透明性のよい材料を使用してはいるが、プレス
トレストコンクリートの緊張端部に配置するグラウトホ
ース4の本数が多い場合などはグラウト注入時に注入忘
れのグラウトホースが発生する場合がある。また、注入
するグラウト量が多い場合などにおいて、当初のグラウ
ト注入時には十分と見受けられても、その後シース内で
の未充填の空隙部への充填進行に応じて、グラウト注入
に不足が生じる場合も発生する。
Conventionally, as described above,
When injecting grout, the grout hose 4 for injecting, exhausting, and draining is launched into the concrete structure 1 and the top 1a
Standing at a height of 1 m or more, when the injection-side grout and the discharge-side grout are homogeneous, the discharge-side grout hose is sealed, and the injection-side pressure is maintained at the required pressure, then the injection-side grout hose Is sealed. After that, when the injected and discharged grout reached the height of the hose 4, the filling of the sheath 3 was confirmed. At the same time, he also confirmed the pouring of breathing water. In addition, the amount of grout stored within the height of 1 m of the hose 4 is 12 m when the inner diameter of the hose is 12 m.
When m was set to about 113 cc, this acted as a reserve amount when the grout injection was insufficient or the expansion was insufficient. However, although a relatively transparent material reinforced with a mesh is used for the grout hose 4, when the number of the grout hoses 4 arranged at the tensioned end of the prestressed concrete is large, the grout hose 4 is injected at the time of pouring the grout. A forgotten grout hose may occur. In addition, when the amount of grout to be injected is large, even if it seems to be sufficient at the time of initial grout injection, there may be a shortage of grout injection as the filling progresses into the unfilled voids in the sheath. appear.

【0005】[0005]

【課題を解決するための手段及び作用】本発明は上記課
題を解決するもので、従来のグラウト注入及び排出で発
生しがちなヒューマンエラーによるシース内へのグラウ
トの十分充填・不足充填を平易に目視確認可能とし、か
つ不足分を自動的に補給するすることを可能とするプレ
ストレストコンクリート用グラウト注入及び排出確認方
法並びに注入及び排出確認装置を提供するものである。
すなわち本発明は、(1)プレストレストコンクリート
用シースの壁面に穿設した小孔や定着体前面に取付けら
れ、立設されたグラウトホースに、容器状の透明材料製
又は半透明材料製のグラウト注入及び排出確認器具を取
着し、該器具により、注入グラウトの目視確認をし、か
つグラウトの予備溜めを行うことを特徴とするポストテ
ンション方式プレストレストコンクリート用グラウト注
入及び排出確認方法、及び(2)プレストレストコンク
リート用シースの壁面に穿設された小孔や定着体前面に
取付けられ、立設されたグラウトホースに、容器状の透
明材料製又は半透明材料製のグラウト確認器具を取着し
てなることを特徴とするポストテンション方式プレスト
レストコンクリート用グラウト注入及び排出確認装置で
ある。上記本発明においては、容器状の透明材料製又は
半透明材料製のグラウト注入及び排出確認器具は立設さ
れたグラウトホースの中途部に取着することが好ましい
が、グラウトホースの上端部に取着してもよい。容器状
の透明材料製又は半透明材料製のグラウト注入及び排出
確認器具は、断面積がグラウトホースより大きく内容積
が大きいものであり、形状は球形、楕円球形あるいは各
種方形等種々形状のものであってよい。上記グラウト注
入及び排出確認器具は、例えばその中央部分が球状又は
方形状に膨張し、その両端部分が前記グラウトホースに
嵌挿可能に円筒状に収縮して形成されてなるものであっ
てよい。グラウト注入及び排出確認器具は透明又は半透
明であるため、注入グラウトの目視確認が容易にでき、
かつグラウトの予備溜めの作用を達成する。グラウト確
認器具を構成する透明材料又は半透明材料としては、ポ
リエステル樹脂系、シリコン樹脂系、ポリエチレン樹脂
系、ナイロン樹脂系、アクリル樹脂系、ビニル樹脂系、
透明ゴム系等の各種プラスチックが使用できる。また、
透明又は半透明ガラス、透明又は半透明セラミックス等
も使用できる。
Means and Actions for Solving the Problems The present invention is to solve the above problems, and it is easy to sufficiently and insufficiently fill the grout into the sheath due to a human error that tends to occur in the conventional grout injection and discharge. (EN) Provided are a grout pouring and discharging confirmation method for prestressed concrete and a pouring and discharging confirmation device which can be visually confirmed and can automatically replenish a shortage.
That is, the present invention is: (1) Injecting grout made of a container-like transparent material or a translucent material into a grouting hose that is attached to a small hole formed in the wall surface of a prestressed concrete sheath or a front surface of a fixing body and is erected. And a method for confirming injection and discharge of post-tension type grout for prestressed concrete, characterized in that a discharge confirmation device is attached, the injection grout is visually confirmed by the device, and preliminary storage of the grout is performed. Attached to a small hole drilled on the wall surface of the prestressed concrete sheath or the front of the fixing body, and a container-shaped grout confirmation device made of transparent material or translucent material is attached to the erected grout hose. This is a post-tension type grout injection and discharge confirmation device for prestressed concrete. In the above-mentioned present invention, the container-shaped transparent material or translucent material grout injection and discharge confirmation device is preferably attached to the middle portion of the erected grout hose, but is attached to the upper end of the grout hose. You may wear it. Container-shaped transparent or translucent material grout injection and discharge confirmation devices have a cross-sectional area larger than that of the grout hose and a large internal volume, and are of various shapes such as spherical, elliptical spherical, and various rectangular shapes. You can The grout injection and discharge confirmation device may be formed, for example, such that a central portion thereof expands into a spherical shape or a rectangular shape, and both end portions thereof are contracted into a cylindrical shape so as to be fitted into the grout hose. Since the grout injection and discharge confirmation device is transparent or translucent, it is easy to visually confirm the injection grout,
It also achieves the effect of a preliminary storage of grout. The transparent material or the translucent material that constitutes the grout confirmation device includes polyester resin type, silicon resin type, polyethylene resin type, nylon resin type, acrylic resin type, vinyl resin type,
Various plastics such as transparent rubber can be used. Also,
Transparent or translucent glass, transparent or translucent ceramics, etc. can also be used.

【0006】[0006]

【実施例】本発明の実施例を、以下に図面に基づき説明
する。図1は本発明に係る注入及び排出確認器具を介挿
したグラウトホースの構成図であり、図2は注入及び排
出確認器具の断面図である。図中、1はコンクリート構
造体、1aはその天端、4a,4bはグラウトホース4
の下の部分と上の部分、6はグラウト注入及び排出確認
器具、8は逆止弁である。本発明実施例に係るグラウト
注入及び排出確認器具6は、その中央部分6aが球状に
膨張し、その両端部分6a、6bがグラウトホース4に
嵌挿可能な適径の円筒状に収縮して形成されている。材
質は、透明又は半透明のプラスチック材料(ポリエチレ
ン樹脂)が使用され、ブロー成形又はインジュクション
成形で製造される。 なお、グラウト注入及び排出確認
器具6の中央部分6aは図示しない方形状に形成されて
もよい。また該器具6は、強度上では外周を高強度メッ
シュ体で囲まれて補強されていることが望ましいが、必
ずしもその必要はない。
Embodiments of the present invention will be described below with reference to the drawings. FIG. 1 is a configuration diagram of a grout hose in which the injection and discharge confirmation device according to the present invention is inserted, and FIG. 2 is a sectional view of the injection and discharge confirmation device. In the figure, 1 is a concrete structure, 1a is its top end, 4a and 4b are grout hoses 4.
Lower part and upper part, 6 is a grout injection and discharge confirmation device, and 8 is a check valve. The grout injection and discharge confirmation instrument 6 according to the embodiment of the present invention is formed by expanding the central portion 6a into a spherical shape and contracting both end portions 6a and 6b into a cylindrical shape having an appropriate diameter that can be inserted into the grout hose 4. Has been done. A transparent or translucent plastic material (polyethylene resin) is used as the material, and is manufactured by blow molding or injection molding. The central portion 6a of the grout injection / discharge confirmation device 6 may be formed in a rectangular shape (not shown). Further, in terms of strength, it is preferable that the outer periphery of the device 6 is surrounded by a high-strength mesh body and reinforced, but this is not always necessary.

【0007】7はグラウト確認器具6の両端部分6b,
6bを嵌挿したグラウトホース4a,4bを周囲から締
付けて、密着させるための止め輪である。また、グラウ
トホース4の上の部分4bの上端は、従来例(図3)の
ごとく逆U字に折曲げてもよいが、折曲げないときはグ
ラウトが逆流してグラウトホース4外へ流出しないよう
にするため、あるいはグラウト注入前にホース4内に粉
塵や異物が入り込まないようにするため、逆止弁8を装
着することが望ましい。また、確認器具6の内容量は2
00〜500cc程度が好適で、取付高さは天端1aか
ら400mm以上あればよく、従来のグラウトホース4
だけの場合の予備量約113ccに比べると2倍以上の
予備量が備蓄でき、誤ってブリージングの大きいグラウ
トを注入した場合であっても十分に対応処置可能なもの
となる。ところで、従来はグラウトホース4に透明度の
高い材料を使用してグラウト注入及び排出確認をしてい
たが、本発明によれば透明又は半透明のグラウト確認器
具6でグラウト注入状態を目視確認できるので、その上
下のホース4a.4bは必ずしも透明性のものでなくて
差し支えなく、よって高強度な材料を自由に採用でき
る。
Reference numeral 7 denotes both end portions 6b of the grout confirming device 6,
It is a retaining ring for tightening and closely adhering the grout hoses 4a and 4b into which the 6b is fitted. Further, the upper end of the upper portion 4b of the grout hose 4 may be bent in an inverted U shape as in the conventional example (FIG. 3), but when not bent, the grout flows backward and does not flow out of the grout hose 4. In order to do so, or to prevent dust or foreign matter from entering the hose 4 before pouring grout, it is desirable to install the check valve 8. Also, the content of the confirmation device 6 is 2
About 100 to 500 cc is suitable, and the mounting height may be 400 mm or more from the top end 1a.
Compared with the reserve amount of about 113 cc in this case, a reserve amount more than twice as much can be stored, and even if accidentally injecting grout with large breathing, it is possible to sufficiently deal with it. By the way, conventionally, a material with high transparency was used for the grout hose 4 to check the grout injection and discharge. However, according to the present invention, the state of the grout injection can be visually checked with the transparent or translucent grout checking device 6. , The upper and lower hoses 4a. 4b is not necessarily transparent, so that a high-strength material can be freely adopted.

【0008】[0008]

【発明の効果】本発明のグラウト注入及び排出確認方法
並びに注入及び排出確認装置は、以上の構成並びに機能
を有するので、従来技術で発生しがちなヒューマンエラ
ーによるグラウトの未充填・不足充填等を平易に目視で
確認することができる。また、プレストレストコンクリ
ートの緊張端部に配置するグラウトホースの本数が多い
場合であっても、本確認器具によればグラウト注入時に
注入忘れを発生する恐れがない。そして、本発明に係る
グラウト注入及び排出確認器具には、従来のグラウトホ
ースの2倍以上のグラウト予備量が備蓄できるので、誤
ってブリージングの大きい又は膨張のすくないグラウト
を注入した場合でも十分に対処可能となる。また、注入
するグラウト量が多い場合などにおいて、当初のグラウ
ト注入時には十分と見受けられても、その後シース内で
の未充填の空隙部への充填進行に応じて、グラウト注入
に不足が生じた場合でも、自動的に補給できる。したが
って、本発明によればポストテンション方式プレストレ
ストコンクリート構造物の構造強度を長期にわたって安
全確実に保持することが可能となる。
EFFECTS OF THE INVENTION The grout injection and discharge confirmation method and the injection and discharge confirmation device of the present invention have the above-mentioned configurations and functions. It can be easily visually confirmed. Further, even if the number of grout hoses arranged at the tensioned end of the prestressed concrete is large, according to the present confirmation tool, there is no risk of forgetting to inject during grout injection. Further, since the grout injection and discharge confirmation device according to the present invention can store a grout reserve amount which is more than twice as large as that of the conventional grout hose, even if accidentally injecting grout with large breathing or less expansion, it is sufficiently dealt with. It will be possible. In addition, when the amount of grout to be injected is large, even if it seems to be sufficient at the time of initial grout injection, but after that, the grout injection becomes insufficient as the filling progresses into the unfilled void in the sheath. But it can be replenished automatically. Therefore, according to the present invention, the structural strength of the post-tensioning prestressed concrete structure can be maintained safely and reliably for a long period of time.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明実施例の注入及び排出確認器具を介挿し
た構成図である。
FIG. 1 is a configuration diagram in which an injection and discharge confirmation device of an embodiment of the present invention is inserted.

【図2】実施例に係るグラウト注入及び排出確認器具の
断面図である。
FIG. 2 is a cross-sectional view of a grout injection and discharge confirmation device according to an embodiment.

【図3】従来方法の概要説明図である。FIG. 3 is a schematic explanatory diagram of a conventional method.

【図4】従来のポストテンション方式プレストレストコ
ンクリート定着体の詳細構成図である。
FIG. 4 is a detailed configuration diagram of a conventional post tension type prestressed concrete fixing body.

【符号の説明】[Explanation of symbols]

1 プレストレストコンクリート構造物 1a 天端 2 定着体 3 シー
ス 4 グラウトホース 4a 下の
部分 4b 上の部分 5 ワイ
ヤー 6 注入及び排出確認器具 6a 中央
部分 6b 両端部分 7 止め
輪 8 逆止弁 10 PC
鋼材 11 メスコーン 12 オス
コーン 21 定着体 28 グラ
ウトキャン 29,30 グラウト充填孔
1 Prestressed concrete structure 1a Top end 2 Anchoring body 3 Sheath 4 Grout hose 4a Lower part 4b Upper part 5 Wire 6 Injection and discharge confirmation device 6a Central part 6b Both end parts 7 Stop ring 8 Check valve 10 PC
Steel material 11 Female cone 12 Male cone 21 Fixing body 28 Grout can 29, 30 Grout filling hole

Claims (6)

【特許請求の範囲】[Claims] 【請求項1】 プレストレストコンクリート用シースの
壁面等に穿設した小孔や定着体前面に取付けられ、立設
されたグラウトホースに、容器状の透明材料製又は半透
明材料製のグラウト注入及び排出確認器具を取着し、該
器具により、注入グラウトの目視確認をし、かつグラウ
トの予備溜めを行うことを特徴とするポストテンション
方式プレストレストコンクリート用グラウト注入及び排
出確認方法。
1. A grout hose, which is attached to a small hole formed in a wall surface of a prestressed concrete sheath or a front surface of a fixing member and is erected upright, injects and discharges a container-shaped transparent or translucent material grout. A method for confirming pouring and discharging grout for pre-tensioned pre-stressed concrete, which comprises attaching a confirmation tool, visually confirming the pouring grout with the tool, and preliminarily storing the grout.
【請求項2】 容器状の透明材料製又は半透明材料製の
グラウト注入及び排出確認器具を立設されたグラウトホ
ースの中途部に取着することを特徴とする請求項1記載
のポストテンション方式プレストレストコンクリート用
グラウト注入及び排出確認方法。
2. The post-tensioning method according to claim 1, wherein a container-shaped transparent or translucent material grout injection and discharge confirmation device is attached to an intermediate part of the vertically-mounted grout hose. Checking method for grout injection and discharge for prestressed concrete.
【請求項3】 容器状の透明材料製又は半透明材料製の
グラウト注入及び排出確認器具が、楕円球状のものであ
ることを特徴とする請求項1又は2に記載のポストテン
ション方式プレストレストコンクリート用グラウト注入
及び排出確認方法。
3. The post-tension prestressed concrete according to claim 1, wherein the container-shaped grout injection and discharge confirmation device made of a transparent material or a semi-transparent material has an oval spherical shape. How to check grout injection and discharge.
【請求項4】 プレストレストコンクリート用シースの
壁面に穿設された小孔や定着体前面に取付けられ、立設
されたグラウトホースに、容器状の透明材料製又は半透
明材料製のグラウト注入及び排出確認器具を取着してな
ることを特徴とするポストテンション方式プレストレス
トコンクリート用グラウト注入及び排出確認装置。
4. A container-shaped grout hose made of a transparent material or a translucent material is inserted into and discharged from a grout hose which is attached to a small hole formed in the wall surface of a sheath for prestressed concrete or a front surface of a fixing body and which is provided upright. A post-tensioning grout injection and discharge confirmation device for prestressed concrete, characterized by being equipped with a confirmation device.
【請求項5】 容器状の透明材料製又は半透明材料製の
グラウト注入及び排出確認器具が、立設されたグラウト
ホースの中途部に取着されてなることを特徴とする請求
項4記載のポストテンション方式プレストレストコンク
リート用グラウト注入及び排出確認装置。
5. The container-shaped grout injection and discharge confirmation device made of a transparent material or a translucent material is attached to an intermediate part of the grouting hose which is provided upright. Post-tension type grout injection and discharge confirmation device for prestressed concrete.
【請求項6】 容器状の透明材料製又は半透明材料製の
グラウト注入及び排出確認器具が、楕円球状のものであ
ることを特徴とする請求項4又は5に記載のポストテン
ション方式プレストレストコンクリート用グラウト注入
及び排出確認装置。
6. The post-tension type prestressed concrete according to claim 4 or 5, wherein the container-like transparent or translucent material grout injection and discharge confirmation device has an oval spherical shape. Grout injection and discharge confirmation device.
JP25972594A 1994-09-30 1994-09-30 Confirmation method for injection or discharge of grout for post-tension prestressed concrete and device therefor Pending JPH08100530A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP25972594A JPH08100530A (en) 1994-09-30 1994-09-30 Confirmation method for injection or discharge of grout for post-tension prestressed concrete and device therefor

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP25972594A JPH08100530A (en) 1994-09-30 1994-09-30 Confirmation method for injection or discharge of grout for post-tension prestressed concrete and device therefor

Publications (1)

Publication Number Publication Date
JPH08100530A true JPH08100530A (en) 1996-04-16

Family

ID=17338087

Family Applications (1)

Application Number Title Priority Date Filing Date
JP25972594A Pending JPH08100530A (en) 1994-09-30 1994-09-30 Confirmation method for injection or discharge of grout for post-tension prestressed concrete and device therefor

Country Status (1)

Country Link
JP (1) JPH08100530A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP1054106A3 (en) * 1999-05-17 2002-07-03 Anderson Technology Corporation Box girder structure for bridge provided with outer cable and method of building the box girder
JP2007247267A (en) * 2006-03-16 2007-09-27 Shoki:Kk Cable protection sheath member to be embedded in bridge road and cable protection sheath to be embedded in bridge road
JP2011021463A (en) * 2009-06-19 2011-02-03 Kyoritsu Enji Kk Injection method for pc grout
CN104196244A (en) * 2014-09-09 2014-12-10 上海建工七建集团有限公司 Serial-connection circulating pressure grouting device and pressure grouting method

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP1054106A3 (en) * 1999-05-17 2002-07-03 Anderson Technology Corporation Box girder structure for bridge provided with outer cable and method of building the box girder
JP2007247267A (en) * 2006-03-16 2007-09-27 Shoki:Kk Cable protection sheath member to be embedded in bridge road and cable protection sheath to be embedded in bridge road
JP2011021463A (en) * 2009-06-19 2011-02-03 Kyoritsu Enji Kk Injection method for pc grout
CN104196244A (en) * 2014-09-09 2014-12-10 上海建工七建集团有限公司 Serial-connection circulating pressure grouting device and pressure grouting method
CN104196244B (en) * 2014-09-09 2016-08-24 上海建工七建集团有限公司 Tandem circulation squeezing unit and mud jacking method

Similar Documents

Publication Publication Date Title
KR100684149B1 (en) The constructure method, manufacture method and a precast reinforced concrete column of building
US5437430A (en) Method for preparing or repairing a machine foundation
JP4512899B2 (en) Construction method of large cylindrical concrete structures for LNG storage tanks.
KR101966015B1 (en) One-piece septic tank with excellent workability and durability
US6854934B2 (en) Structure of pile head joint portion and pile head fitting tubular body
JPH08100530A (en) Confirmation method for injection or discharge of grout for post-tension prestressed concrete and device therefor
JP2009114815A (en) Reinforcing structure of hollow concrete structure, and reinforcing method of hollow concrete structure
JPH0411080Y2 (en)
KR102079574B1 (en) Composite multi-cap for finishing fixtures and method for constructing prestressed concrete structures using the same
JPH0656011B2 (en) Waste-enclosed buried block and waste disposal method
JPH0387420A (en) Erection configuration for columnar body for building
CN214614049U (en) Prestressed anchor cable structure
GB2092215A (en) Method of constructing tanks
JPS5850238A (en) Construction member for pillar and beam
CN111622429A (en) Method for improving connection safety of grouting sleeve and grouting sleeve
KR19990041358U (en) Fence holding formwork
JPH0790855A (en) Slant face covering member and installing method for bag body and slant face covering member
KR102528588B1 (en) Open type water tank for quick construction
KR102556250B1 (en) Vertical anchor, vertical anchor assembly and post-tension method using it
CN214941079U (en) Sleeve inverted-inserting type connecting structure of prefabricated column and cast-in-place concrete structure
JP2971038B2 (en) Climbing wall and climbing wall hold mounting cup
ES1058317U (en) Kit for the manufacture of balusters
WO1991009249A1 (en) Foundation and method preparing or reparing same
JP3207792U (en) Seismic expansion pillar frame
KR100200030B1 (en) Socle for a fence and method of laying fence using socle