JPH076345B2 - Enlarged tunnel lining method - Google Patents

Enlarged tunnel lining method

Info

Publication number
JPH076345B2
JPH076345B2 JP31914489A JP31914489A JPH076345B2 JP H076345 B2 JPH076345 B2 JP H076345B2 JP 31914489 A JP31914489 A JP 31914489A JP 31914489 A JP31914489 A JP 31914489A JP H076345 B2 JPH076345 B2 JP H076345B2
Authority
JP
Japan
Prior art keywords
lining
expansion
tunnel
expanded
base
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP31914489A
Other languages
Japanese (ja)
Other versions
JPH03180691A (en
Inventor
恒夫 脇田
芳昭 井戸田
利夫 伊沢
健一 松島
太郎 粕谷
茂 松岡
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tobishima Corp
Okumura Corp
Original Assignee
Tobishima Corp
Okumura Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tobishima Corp, Okumura Corp filed Critical Tobishima Corp
Priority to JP31914489A priority Critical patent/JPH076345B2/en
Publication of JPH03180691A publication Critical patent/JPH03180691A/en
Publication of JPH076345B2 publication Critical patent/JPH076345B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Description

【発明の詳細な説明】 〔産業上の利用分野〕 本発明はシールド工法によって築造したトンネルの所望
長さ部分に拡大トンネル部を構築する方法に関するもの
である。
The present invention relates to a method for constructing an enlarged tunnel portion in a desired length portion of a tunnel constructed by a shield construction method.

〔従来の技術〕[Conventional technology]

一般に、下水道や地下鉄或いは配線坑等のトンネルはシ
ールド工法によって掘削されているが、地下鉄における
退避場所や駅の構築、或いは排水、換気設備の設置場所
や配線の引き込み用空間部を必要とする場合には、該ト
ンネルの所定長さ部分に拡大トンネル部を設ける必要が
ある。
Generally, tunnels such as sewers, subways, and wiring pits are excavated by the shield construction method, but when constructing evacuation sites and stations in subways, or where drainage, ventilation equipment installation sites and wiring lead-in spaces are required. In this case, it is necessary to provide an enlarged tunnel portion in a predetermined length portion of the tunnel.

このような拡大トンネル部は、通常、シールド工法によ
ってトンネルを掘削した後、地上からトンネル拡大予定
位置に立坑を掘削し、この立坑を利用して所望のトンネ
ル拡大部を築造することが行われている。
Such an expanded tunnel section is usually constructed by excavating a tunnel by the shield method, then excavating a vertical shaft from the ground to a planned tunnel expansion position, and using this vertical shaft to construct a desired tunnel expansion section. There is.

しかしながら、市街地などにおいては道路事情の悪化や
環境保全等に鑑みて地上から立坑を掘削することができ
ない場合がある。
However, in urban areas and the like, it may not be possible to excavate a shaft from the ground due to deterioration of road conditions and environmental protection.

このため、例えば特公昭62−16309号公報に記載してい
るように、シールド工法によって施工した既設トンネル
における拡大予定区域において、その一端部のトンネル
覆工を切り広げて拡大掘削部を形成し、この拡大掘削部
に既設トンネルの外周部を掘削する拡大用シールド掘削
機を配設してその前方の既設トンネル覆工を順次取り外
しながら拡大用シールド掘削機を推進させて拡大計画予
定区域に拡大部を築造する方法が開発されている。
Therefore, for example, as described in Japanese Examined Patent Publication No. 62-16309, in the expansion planned area in the existing tunnel constructed by the shield construction method, the tunnel lining at one end is cut open to form an expanded excavation portion, An expansion shield excavator for excavating the outer circumference of the existing tunnel is installed in this expansion excavation part, and the expansion shield excavator is promoted while sequentially removing the existing tunnel lining in front of it, and the expansion part is expanded to the planned expansion area. A method of building a building has been developed.

〔発明が解決しようとする課題〕[Problems to be Solved by the Invention]

この工法によれば、立坑を掘削することなくトンネル拡
大部を築造できるが、拡大用シールド掘削機による拡大
部の掘削に先行して既設トンネル覆工を順次取り外して
いくものであるから、軟弱地盤や滯水地盤中に施工され
た既設トンネル覆工を取り外すと、地盤が崩壊したり地
下水がトンネル内に侵入して作業性を著しく低下させる
という問題点がある。
According to this method, the tunnel expansion part can be built without excavating the vertical shaft, but the existing tunnel lining is sequentially removed prior to the excavation of the expansion part by the shield excavator for expansion. If the existing tunnel lining constructed on the ground or the flooded ground is removed, there is a problem that the ground collapses or groundwater enters the tunnel to significantly reduce workability.

又、既設トンネル覆工の除去作業は、覆工セグメント解
体装置を前方側に順次移動しながらおこなわなければな
らず、拡大用シールド掘削機の前進に従って、該覆工セ
グメント解体装置のガイドレールの撤去等の作業が必要
となる。
In addition, the removal work of the existing tunnel lining must be performed while sequentially moving the lining segment dismantling device forward, and the guide rail of the lining segment dismantling device is removed as the expansion shield excavator advances. Work such as is required.

本発明はこのような問題点を解消することを目的とする
トンネルの拡大覆工方法を提供するものである。
The present invention provides a method for enlarging a lining of a tunnel, which aims to solve such problems.

〔課題を解決するための手段〕[Means for Solving the Problems]

上記目的を達成するために、本発明のトンネル拡大覆工
方法は、シールド工法によって築造した既設トンネル覆
工の拡大予定区域における両端覆工部を除去してその除
去跡の一方に拡大発進基地を、他方に拡大到達基地を掘
削形成したのち、拡大発進基地に築造すべき拡大覆工の
外周形状に略等しい掘削面板を配設して該掘削面板の前
面を拡大発進基地に露出した既設トンネル覆工の後端面
に当接させると共に外周部後面に一エレメントの拡大覆
工材を配し、しかるのち、該拡大覆工材の後面を推進装
置で押圧することにより拡大覆工材及び掘削面板を介し
て拡大予定区域における前記既設トンネル覆工を拡大到
達基地側に押し進めると共に該既設トンネル覆工の後端
から外方に突出した掘削面板の掘削部により前方の拡大
すべき地盤を掘削しながら発進基地内に取り込み、推進
により拡大到達基地に達した既設トンネル覆工部を該到
達基地内で撤去すると共に発進基地内において拡大覆工
材の後面に次の拡大覆工材を当接状態に配設して推進装
置により上記同様に押し進め、この作業を繰り返し行っ
て、拡大予定区域の全長に亘って拡大覆工材による拡大
部を築造することを特徴とするものである。
In order to achieve the above-mentioned object, the tunnel expansion lining method of the present invention is to remove both end lining parts in an expansion planned area of an existing tunnel lining constructed by the shield construction method and to set an expansion starting base on one of the removal marks. After excavating and forming the expansion reaching base on the other side, an excavation face plate that is approximately equal to the outer peripheral shape of the expansion lining to be built at the expansion starting base is provided, and the front face of the excavation face plate is covered with the existing tunnel covering exposed to the expansion starting base. The expanded lining material of one element is arranged on the rear surface of the outer peripheral portion while being brought into contact with the rear end surface of the work, and then the expanded lining material and the excavated face plate are pressed by pressing the rear surface of the expanded lining material with a propulsion device. The existing tunnel lining in the planned expansion area is pushed through to the expansion destination base side and the ground to be expanded in front is excavated by the excavation part of the excavation face plate protruding outward from the rear end of the existing tunnel lining. While taking it into the starting base, removing the existing tunnel lining part that reached the expansion base by promotion and removing the existing tunnel lining part in the base, while the next expansion lining is in contact with the rear surface of the expansion cover inside the base. It is characterized by constructing an enlarged portion by an enlarged lining material over the entire length of the area to be enlarged by repeating the above operation by pushing it in the same manner as above with a propulsion device.

〔作用〕[Action]

既設トンネル覆工の拡大予定区域における両端に拡大発
進基地と到達基地とを夫々掘削形成し、拡大発進基地に
築造すべき拡大覆工の外周形状に略等しい掘削面板を配
設して該掘削面板の前面を拡大発進基地に露出した既設
トンネル覆工の後端面に当接させると共に外周部後面に
一エレメントの拡大覆工材を配した状態にして、該拡大
覆工材の後面を推進装置で押圧するものであるから、拡
大予定区域の既設トンネル覆工部が地中に埋設された状
態で全体的に到達基地側に推進され、地下水等の浸水を
該既設トンネル覆工部で防止しながら掘削面板によって
拡大予定部の地盤を掘進していくことができる。
An expansion start base and an arrival base are excavated and formed at both ends of the expansion planned area of the existing tunnel lining, and an excavation face plate having substantially the same outer peripheral shape of the expansion lining to be built at the extension start base is provided. The front surface of the expanded lining material is brought into contact with the rear end surface of the existing tunnel lining exposed at the expansion starting base, and the expanded lining material of one element is arranged on the rear surface of the outer peripheral portion. Since it presses, the existing tunnel lining in the planned expansion area is generally pushed to the arrival base side while being buried in the ground, while preventing inundation of groundwater etc. with the existing tunnel lining. The excavated face plate allows the ground in the planned expansion area to be dug forward.

さらに、推進により拡大到達基地に達した既設トンネル
覆工部を該到達基地内で撤去するものであるから、トン
ネル覆工セグメント解体装置を移動させることなく、定
置させた状態で既設トンネルの覆工セグメントを順次解
体撤去できるものである。
Furthermore, since the existing tunnel lining that has reached the expanded arrival base due to propulsion is to be removed within the arrival base, the tunnel lining segment dismantling device is not moved, and the existing tunnel lining is kept in a stationary state. The segments can be dismantled and removed sequentially.

又、掘削面板の前進に後続して拡大覆工材を順次接続し
ながら押し進め、拡大予定区域の全長に亘って拡大覆工
材による拡大部を能率よく築造し得るものである。
In addition, following the forward movement of the excavation face plate, the expanded lining material is sequentially connected and pushed forward, and the expanded portion of the expanded lining material can be efficiently constructed over the entire length of the planned expansion area.

〔実施例〕〔Example〕

本発明の実施例を図面について説明すると、第1図にお
いて、(1)はシールド工法によって築造された既設の
トンネルであり、(2)は該既設のトンネル(1)の所
望個所に築造すべき拡大トンネル部である。
An embodiment of the present invention will be described with reference to the drawings. In FIG. 1, (1) is an existing tunnel constructed by a shield construction method, and (2) is an existing tunnel to be constructed at a desired portion of the existing tunnel (1). It is an enlarged tunnel section.

まず、この築造すべき拡大トンネル部(2)における既
設トンネル(1)の覆工部(3)の両端部、即ち、拡大
トンネル部(2)の形成始端部と終端部との覆工部
(3)のセグメント(3′)を適宜長さ部分だけ取り外
し、その取り外し部分から既設トンネル(1)の外径方
向に地盤を適宜な掘削手段により掘削して築造すべき拡
大トンネル部(2)の形成始端部に拡大発進基地(4)
を、終端部に拡大到達基地(5)を夫々形成する。
First, both ends of the lining portion (3) of the existing tunnel (1) in the enlarged tunnel portion (2) to be constructed, that is, the lining portion (formation end portion and end portion of the formation of the enlarged tunnel portion (2) ( The segment (3 ') of 3) is removed by an appropriate length, and the ground is excavated from the removed portion in the outer diameter direction of the existing tunnel (1) by an appropriate excavation means to construct an expanded tunnel section (2). Enlarged starting base at the start of formation (4)
And the extended arrival bases (5) are respectively formed at the end portions.

この際、セグメント(3′)を除去する前に、該セグメ
ント(3′)に穿設している孔から地盤中に公知の凍結
工法によって基地(4)(5)の形成部分を凍結地盤
(6)としたのち、これらの基地(4)(5)を掘削す
るものである。
At this time, before the segment (3 ') is removed, the portion where the bases (4) and (5) are formed is frozen through the hole formed in the segment (3') into the ground by a known freezing method. After 6), these bases (4) and (5) will be excavated.

又、トンネル(1)を築造する際に、拡大トンネル部
(2)の築造予定部分における上記トンネル覆工部
(3)を形成したセグメント中に、トンネル長さ方向に
適宜間隔毎に伸縮セグメント(3a)をリング状に組み込
んでおくと共に、トンネル覆工部(3)の外周面と地盤
間にセグメントの適所に穿設した注入孔(図示せず)か
ら滑剤(18)を注入しておく。
Further, when building the tunnel (1), in the segment in which the tunnel lining part (3) is formed in the planned construction part of the enlarged tunnel part (2), the expandable segment (3) is formed at appropriate intervals in the tunnel length direction. 3a) is assembled in a ring shape, and a lubricant (18) is injected from an injection hole (not shown) formed at an appropriate position in the segment between the outer peripheral surface of the tunnel lining portion (3) and the ground.

この伸縮セグメント(3a)は第6図に示すように、左右
一対のセグメント片(3a′)(3a′)を一方のセグメン
ト片(3a′)内に配設、固定した中押ジャッキ(7)
(7)によって左右方向(トンネルの長さ方向)に伸縮
自在に連結してなるものであり、このように構成した伸
縮セグメント(3a)をトンネル覆工部(3)の複数個所
に複数個、該セグメント穿設しているボルト連結孔
(8)を介してリング状に組立てることにより、覆工部
の一部を形成しておくものである。
As shown in FIG. 6, this telescopic segment (3a) has a pair of left and right segment pieces (3a ') (3a') arranged and fixed in one segment piece (3a '), and an intermediate push jack (7).
(7) is connected to the left and right directions (tunnel length direction) so as to be able to expand and contract, and a plurality of expanding and contracting segments (3a) configured in this way are provided at a plurality of positions of the tunnel lining part (3). A part of the lining portion is formed by assembling in a ring shape through the bolt connection hole (8) formed in the segment.

従って、上記基地(4)(5)を掘削形成する際に、該
部の伸縮セグメント(3a)を、その中押ジャッキ(7)
の収縮によりトンネル(1)の長さ方向に収縮させれ
ば、所望トンネル長さ部分のセグメントを容易に取り外
すことができる。
Therefore, when the bases (4) and (5) are excavated and formed, the telescopic segment (3a) of the base (4) (5) is pushed into the intermediate push jack (7).
By contracting in the lengthwise direction of the tunnel (1) by contracting, the segment of the desired tunnel length portion can be easily removed.

拡大発進基地(4)は後述する掘削面板(9)を囲繞す
るコンクリート製周壁部(4a)とこの周壁部(4a)の後
端に連設した反力壁部(4b)とを有し、周壁部(4a)の
前端部内周面には掘削面板(9)及び後述する拡大覆工
材(10)の外周面に摺接、密着するパッキン(11)を周
設してあり、拡大到達基地(5)はその周壁(5a)の前
端内周面を拡大予定区域外のトンネル覆工外周面に水密
的に固着していると共に後端内周面に拡大予定区域部に
おけるトンネル覆工部(3)の外周面に摺接、密着させ
たパッキン(12)を周設してある。
The expansion start base (4) has a concrete peripheral wall portion (4a) surrounding an excavation face plate (9) described later and a reaction force wall portion (4b) connected to the rear end of the peripheral wall portion (4a), On the inner peripheral surface of the front end of the peripheral wall portion (4a), there is provided a packing (11) which is in sliding contact with and adheres to the outer peripheral surface of the excavation face plate (9) and the expanded lining material (10) which will be described later. In (5), the inner peripheral surface of the front end of the peripheral wall (5a) is watertightly fixed to the outer peripheral surface of the tunnel lining outside the planned expansion area, and the inner peripheral surface of the rear end inner peripheral surface of the tunnel lining section in the planned expansion area ( A packing (12) is provided around the outer peripheral surface of (3) so as to be in sliding contact with and in close contact with the outer peripheral surface.

このように、発進基地(4)と到達基地(5)とを形成
したのち、発進基地(4)に築造すべき拡大覆工(13)
の外周形状に略等して形状に形成されている掘削面板
(9)を配設し、その前面を発進基地(4)の掘削面に
露出したトンネル覆工部(3)のセグメント(3′)の
後端面に当接させる。
In this way, after forming the starting base (4) and the reaching base (5), the expanded lining (13) to be built on the starting base (4)
The excavation face plate (9) formed in a shape substantially equal to the outer peripheral shape of the tunnel arranging part is provided, and the front surface of the excavation face plate (9) is exposed to the excavation surface of the starting base (4). ) Contact the rear end surface.

掘削面板(9)はトンネル覆工部(3)の内周径に略等
しい中央孔(14)を有し、その中央孔(14)の周囲の前
面を上述したようにセグメント(3′)の後端面に当接
させると共にその当接部から外方延長方向に突出した板
面部に周方向に適宜間隔毎に土砂取入口と掘削機(15)
(第3図参照)を設けてあり、さらに、外周縁には前方
に向かって刃口(16)を突設してある。
The excavation face plate (9) has a central hole (14) approximately equal to the inner diameter of the tunnel lining portion (3), and the front surface around the central hole (14) of the segment (3 ') is as described above. The earth and sand intakes and the excavator (15) are brought into contact with the rear end surface and at a suitable interval in the circumferential direction on the plate surface portion projecting in the outward extension direction from the contact portion.
(See FIG. 3) is provided, and a blade opening (16) is provided on the outer peripheral edge so as to project forward.

又、拡大覆工(13)を構成する覆工材(10)は一定寸法
のセグメントを周方向に連結してその外形が掘削面板
(9)の外周形状に略等しい大形のリング形状に形成さ
れてあり、この拡大覆工材(10)を掘削面板(9)の後
面外周部に当接させると共に該拡大覆工材(10)の後面
と発進基地(4)の反力壁部(4b)間の複数箇所に推進
ジャッキ(17)を介在させる。
In addition, the lining material (10) that constitutes the enlarged lining (13) is formed into a large ring shape by connecting segments of a certain size in the circumferential direction and the outer shape thereof is approximately equal to the outer peripheral shape of the excavation face plate (9). The enlarged lining material (10) is brought into contact with the outer peripheral portion of the rear surface of the excavation face plate (9), and the rear surface of the enlarged lining material (10) and the reaction force wall portion (4b) of the starting base (4). ) Intervening propulsion jacks (17).

しかるのち、掘削面板(9)に装着している掘削機(1
5)のカッタを回転させながら推進ジャッキ(17)を伸
長させると、掘削面板(9)は拡大覆工材(10)と共に
推進され、その前面で発進基地(4)と到達基地(5)
間のトンネル覆工部(3)を押し進める。
Then, the excavator attached to the excavation face plate (9) (1
When the propulsion jack (17) is extended while rotating the cutter of 5), the excavation face plate (9) is propelled together with the expanded lining material (10), and the starting base (4) and reaching base (5) are in front of it.
Push the tunnel lining section (3) in between.

この時、トンネル覆工部(3)と地盤間には滑剤(18)
が充填されているので、地盤との摺擦抵抗力を低減させ
てトンネル覆工部(3)の推進が行える。
At this time, a lubricant (18) was placed between the tunnel lining section (3) and the ground.
Since it is filled with, the tunnel lining part (3) can be propelled by reducing the frictional resistance against the ground.

さらに、トンネル覆工部(3)の複数箇所に配設してい
る伸縮セグメント(3a)を予め、或いは、トンネル覆工
部(3)の推進時に収縮させ、推進ジャッキ(17)によ
る押し進め後に該伸縮セグメント(3a)のセグメント片
(3a′)(3a′)間を中押ジャッキ(7)の伸長により
トンネル長さ方向に伸長させると、到達基地(5)側へ
のトンネル覆工部(3)の推進が円滑に行える。
Further, the expansion and contraction segments (3a) arranged at a plurality of locations of the tunnel lining portion (3) are contracted in advance, or when the tunnel lining portion (3) is propelled and then pushed forward by the propulsion jack (17). When the space between the segment pieces (3a ′) (3a ′) of the telescopic segment (3a) is extended in the tunnel length direction by the extension of the intermediate push jack (7), the tunnel lining portion (3) to the arrival base (5) side is formed. ) Can be promoted smoothly.

こうして、掘削面板(9)に装着した掘削機(15)と刃
口(16)によって前方の地盤を掘削すると共に掘削した
土砂をトンネル内に取り込みながら掘削面板(9)の推
進によって拡大トンネル部(2)を掘削形成していくと
共に該掘削面板(9)に後続する拡大覆工材(10)をそ
の外周面をパッキン(11)に摺接させながら掘進跡に圧
入して拡大覆工部を形成していく。
In this way, the excavator (15) and the cutting edge (16) mounted on the excavation face plate (9) excavate the ground in front of the excavation face plate (9), and the excavation face plate (9) is propelled while the excavated soil plate is taken into the tunnel. 2) is excavated and formed, and the enlarged lining material (10) following the excavated face plate (9) is pressed into the excavation track while sliding the outer peripheral surface of the enlarged lining material (10) to the packing (11) to form the enlarged lining portion. To form.

この際、1エレメント分の拡大覆工材(10)の推進が終
了すると、発進基地(4)内で次の拡大覆工材(10)を
セグメント組立装置(図示せず)により組み立てゝ推進
された拡大覆工材(10)の後面に重合状態に接合させ、
以下、同様にして順次拡大覆工部を接合、後続させる。
なお、推進させる拡大覆工材(10)の外周面と地盤間に
最前部の拡大覆工材(10)の適所に設けた注入孔(図示
せず)から滑材(19)を注入する。
At this time, when the promotion of the expanded lining material (10) for one element is completed, the next expanded lining material (10) is assembled and propelled by the segment assembly device (not shown) in the starting base (4). It is joined to the rear surface of the expanded lining material (10) in a polymerized state,
Hereinafter, similarly, the enlarged lining portions are sequentially joined and subsequently joined.
A lubricant (19) is injected from an injection hole (not shown) provided at an appropriate position in the foremost expanded lining material (10) between the outer peripheral surface of the expanded lining material (10) to be promoted and the ground.

一方、拡大覆工材(10)の推進に従って該拡大覆工材
(10)と置換されるようにしながら到達基地(5)側の
既設トンネル覆工部(3)のセグメント(3′)が到達
基地(5)内に押し出され、該到達基地(5)内に配設
したセグメント解体装置(図示せず)により解体し、ト
ンネル内を通じて撤去する。
On the other hand, the segment (3 ') of the existing tunnel lining part (3) on the arrival base (5) side arrives while being replaced with the expanded lining material (10) in accordance with the promotion of the expanded lining material (10). It is pushed into the base (5), disassembled by a segment dismantling device (not shown) arranged in the arrival base (5), and removed through the tunnel.

こうして、発進基地(4)側からの拡大覆工材(10)の
推進に従って到達基地(5)側に到達するトンネル覆工
部(3)のセグメント(3′)を順次、解体、撤去し、
掘削面板(9)が到達基地(5)に達すると、該掘削面
板(9)に一連に接合、後続している拡大覆工材(10)
(10)・・・(10)によって拡大トンネル部(2)の拡
大覆工(13)が発進基地(4)と到達基地(5)間に築
造されるものである(第5図)。
In this way, the segment (3 ') of the tunnel lining section (3) that reaches the arrival base (5) side in accordance with the promotion of the expanded lining material (10) from the start base (4) side is sequentially dismantled and removed,
When the excavation face plate (9) reaches the reaching base (5), the expanded lining material (10) joined in succession to the excavation face plate (9).
(10) ... (10) is used to build the enlarged lining (13) of the enlarged tunnel section (2) between the starting base (4) and the reaching base (5) (Fig. 5).

拡大覆工(13)の築造後、その外周面と地盤間に充填し
ている滑剤(19)を硬化性裏込剤(20)の注入によって
置換し、又、掘削面板(9)を解体、撤去すると共に推
進ジャッキ(17)等を撤去する。
After construction of the expanded lining (13), the lubricant (19) filled between the outer peripheral surface and the ground is replaced by injecting a curable backing agent (20), and the excavation face plate (9) is disassembled, At the same time as removing it, remove the propulsion jack (17).

しかるのち、発進基地(4)と到達基地(5)との周壁
内面にコンクリートを打設して拡大覆工(13)の内面に
連続した壁面(21)を形成する。
After that, concrete is placed on the inner surfaces of the peripheral walls of the starting base (4) and the reaching base (5) to form a continuous wall surface (21) on the inner surface of the expanded lining (13).

なお、以上の実施例においては、既設トンネル(1)に
対して一側方に偏心した円形状拡大覆工(13)の築造を
図示しているが、同心円の拡大覆工や形状の異なった拡
大覆工を上記工法によって築造できることは勿論であ
る。
In the above examples, the construction of the circular expanded lining (13) which is eccentric to one side with respect to the existing tunnel (1) is illustrated, but the expanded lining of concentric circles and the shape are different. Of course, the expanded lining can be constructed by the above method.

〔発明の効果〕〔The invention's effect〕

以上のように本発明のトンネル拡大覆工方法によれば、
既設トンネル覆工の拡大予定区域における両端に拡大発
進基地と到達基地とを夫々掘削形成し、拡大発進基地に
築造すべき拡大覆工の外周形状に略等しい掘削面板を配
設して該掘削面板の前面を拡大発進基地に露出した既設
トンネル覆工の後端部に当接させると共に外周部後面に
一エレメントの拡大覆工材を配した状態にして、該拡大
覆工材の後面を推進装置で押圧するものであるから、拡
大予定区域の既設トンネル覆工部を解体することなく地
中に埋設された状態で全体的に到達基地側に推進させる
ので、地下水等トンネル内に侵入するのを該既設トンネ
ル覆工部によって確実に防止しながら掘削面板の掘進に
よる拡大トンネル部の形成と拡大覆工材の推進による拡
大覆工を円滑且つ能率よく施すことができるものであ
る。
As described above, according to the tunnel expansion lining method of the present invention,
An expansion start base and an arrival base are excavated and formed at both ends of the expansion planned area of the existing tunnel lining, and an excavation face plate having substantially the same outer peripheral shape of the expansion lining to be built at the extension start base is provided. The front surface of the expanded lining material is brought into contact with the rear end portion of the existing tunnel lining exposed at the expansion starting base, and the expanded lining material of one element is arranged on the rear surface of the outer peripheral portion, and the rear surface of the expanded lining material is the propulsion device. Since it is pushed by, the existing tunnel lining part of the expansion planned area is totally buried in the ground without being dismantled and propelled to the arrival base side, so it is possible to intrude into the tunnel such as groundwater. It is possible to smoothly and efficiently perform the formation of the enlarged tunnel portion by the excavation of the excavation face plate and the enlarged lining by the promotion of the enlarged lining material while reliably preventing the existing tunnel lining portion.

さらに、推進により拡大到達基地に達した既設トンネル
覆工部を該到達基地内で撤去するものであるから、トン
ネル覆工セグメントの解体装置を移動させることなく、
定置させた状態で既設トンネルの覆工セグメントを順次
解体撤去できるものである。
Furthermore, since the existing tunnel lining section that has reached the expanded arrival base by promotion is to be removed within the arrival base, without moving the dismantling device of the tunnel lining segment,
The lining segment of the existing tunnel can be dismantled and removed in a fixed state.

【図面の簡単な説明】[Brief description of drawings]

図面は本発明の実施例を示すもので、第1図は拡大予定
区域部のトンネルの横断平面図、第2図は拡大トンネル
施工開始状態を示す縦断側面図、第3図は掘削面板部分
の簡略縦断正面図、第4図は施工中の拡大トンネル部の
縦断側面図、第5図は築造された拡大トンネル部の縦断
側面図、第6図は伸縮セグメントの斜視図である。 (1)……既設トンネル、(2)……拡大トンネル部、
(3)……トンネル覆工部、(3′)……セグメント、
(3a)……伸縮セグメント、(4)……拡大発進基地、
(5)……拡大到達基地、(9)……掘削面板、(10)
……拡大覆工材、(13)……拡大覆工、(17)……推進
ジャッキ。
The drawings show an embodiment of the present invention. Fig. 1 is a cross-sectional plan view of a tunnel in an enlarged planned area, Fig. 2 is a vertical sectional side view showing a state in which the enlarged tunnel is started to be constructed, and Fig. 3 is an excavated face plate portion. FIG. 4 is a simplified vertical sectional front view, FIG. 4 is a vertical sectional side view of an enlarged tunnel portion under construction, FIG. 5 is a longitudinal sectional side view of a built enlarged tunnel portion, and FIG. 6 is a perspective view of a telescopic segment. (1) …… Existing tunnel, (2) …… Enlarged tunnel section,
(3) …… Tunnel lining section, (3 ′) …… Segment,
(3a) …… Expansion / contraction segment, (4) …… Expansion start base,
(5) …… Expansion arrival base, (9) …… Excavation face plate, (10)
…… Expanded lining material, (13) …… Expanded lining, (17) …… Propulsion jack.

───────────────────────────────────────────────────── フロントページの続き (72)発明者 井戸田 芳昭 東京都港区元赤坂1―3―10 株式会社奥 村組東京支社内 (72)発明者 伊沢 利夫 東京都千代田区三番町2番地 飛島建設株 式会社内 (72)発明者 松島 健一 東京都千代田区三番町2番地 飛島建設株 式会社内 (72)発明者 粕谷 太郎 東京都千代田区三崎町2丁目5番3号 鉄 建建設株式会社内 (72)発明者 松岡 茂 東京都千代田区三崎町2丁目5番3号 鉄 建建設株式会社内 (56)参考文献 特開 昭59−102086(JP,A) 特開 昭62−133292(JP,A) 特開 昭61−242297(JP,A) ─────────────────────────────────────────────────── ─── Continuation of the front page (72) Inventor Yoshiaki Iwada 1-3-10 Moto-Akasaka, Minato-ku, Tokyo Okumuragumi Co., Ltd. Tokyo branch office (72) Toshio Izawa 2nd Sanbancho, Chiyoda-ku, Tokyo Tobishima Construction company (72) Inventor Kenichi Matsushima 2-3 Sanbancho, Chiyoda-ku, Tokyo Toshima Construction Co., Ltd. (72) Inventor Taro Kasuya 2-3-5 Misaki-cho, Chiyoda-ku, Tokyo Steel Construction Co., Ltd. In-company (72) Inventor Shigeru Matsuoka 2-5-3 Misaki-cho, Chiyoda-ku, Tokyo Inside Iron Construction Co., Ltd. (56) Reference JP 59-102086 (JP, A) JP 62-133292 ( JP, A) JP 61-242297 (JP, A)

Claims (2)

【特許請求の範囲】[Claims] 【請求項1】シールド工法によって築造した既設トンネ
ル覆工の拡大予定区域における両端覆工部を除去してそ
の除去跡の一方に拡大発進基地を、他方に拡大到達基地
を掘削形成したのち、拡大発進基地に築造すべき拡大覆
工の外周形状に略等しい掘削面板を配設して該掘削面板
の前面を拡大発進基地に露出した既設トンネル覆工の後
端面に当接させると共に外周部後面に一エレメントの拡
大覆工材を配し、しかるのち、該拡大覆工材の後面を推
進装置で押圧することにより拡大覆工材及び掘削面板を
介して拡大予定区域における前記既設トンネル覆工を拡
大到達基地側に押し進めると共に該既設トンネル覆工の
後端から外方に突出した掘削面板の掘削部により前方の
拡大すべき地盤を掘削しながら発進基地内に取り込み、
推進により拡大到達基地に達した既設トンネル覆工部を
該到達基地内で撤去すると共に発進基地内において拡大
覆工材の後面に次の拡大覆工材を当接状態に配設して推
進装置により上記同様に押し進め、この作業を繰り返し
行って、拡大予定区域の全長に亘って拡大覆工材による
拡大部を築造することを特徴とするトンネルの拡大覆工
方法。
1. An expansion starting base is excavated on one side of the removal mark and an expansion starting base is formed on one side of the removal mark by removing both end linings in an expansion planned area of an existing tunnel lining constructed by the shield construction method, and then expanded. An excavation face plate that is approximately equal to the outer peripheral shape of the expanded lining to be built at the starting base is provided, and the front surface of the excavation face plate is brought into contact with the rear end face of the existing tunnel lining exposed at the expansion starting base and at the rear face of the outer peripheral portion. One element of the expanded lining material is arranged, and then the rear surface of the expanded lining material is pressed by a propulsion device to expand the existing tunnel lining in the planned expansion area via the expanded lining material and excavation face plate. While pushing the ground to be expanded forward by the excavation part of the excavation face plate protruding outward from the rear end of the existing tunnel lining while pushing it toward the arrival base side, take it into the starting base.
The propulsion device is installed by removing the existing tunnel lining portion that has reached the expansion reaching base by propulsion in the arrival base and arranging the next expansion covering material in contact with the rear surface of the expansion covering material in the starting base. According to the method described above, an expanding lining method for a tunnel is characterized in that the expanding part is constructed with the expanding lining material over the entire length of the expansion planned area by repeating this work.
【請求項2】拡大予定区域における既設トンネル覆工
に、トンネル方向に伸縮するセグメントをトンネル長さ
方向に適宜間隔毎に配設していることを特徴とする請求
項記載のトンネルの拡大覆工方法。
2. The expanded lining of a tunnel according to claim 1, wherein segments which expand and contract in the tunnel direction are arranged at appropriate intervals in the tunnel length direction in the existing tunnel lining in the expansion planned area. Method.
JP31914489A 1989-12-09 1989-12-09 Enlarged tunnel lining method Expired - Lifetime JPH076345B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP31914489A JPH076345B2 (en) 1989-12-09 1989-12-09 Enlarged tunnel lining method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP31914489A JPH076345B2 (en) 1989-12-09 1989-12-09 Enlarged tunnel lining method

Publications (2)

Publication Number Publication Date
JPH03180691A JPH03180691A (en) 1991-08-06
JPH076345B2 true JPH076345B2 (en) 1995-01-30

Family

ID=18106935

Family Applications (1)

Application Number Title Priority Date Filing Date
JP31914489A Expired - Lifetime JPH076345B2 (en) 1989-12-09 1989-12-09 Enlarged tunnel lining method

Country Status (1)

Country Link
JP (1) JPH076345B2 (en)

Also Published As

Publication number Publication date
JPH03180691A (en) 1991-08-06

Similar Documents

Publication Publication Date Title
JPH076345B2 (en) Enlarged tunnel lining method
JP2001173368A (en) Box culvert for pipe jacking method in which outer edge of corner section is formed in arcuate shape and tunnel constructing method using box culvert
JPH0489992A (en) Existing pipe duct enlarging method and shield excavation device used with the method
JPH0868293A (en) Underground tunnel joint method and segment
JPH0516317Y2 (en)
JP3182099B2 (en) Removal method of shield excavator from arrival port
JPH0684711B2 (en) Construction method of tunnel widening section
JP2950166B2 (en) Starting method of shield machine from existing tunnel
JPS62148798A (en) Circumferential shielding segment
JPH0369438B2 (en)
JPS6216310B2 (en)
JPH05311995A (en) Construction method of tunnel structure using cornice steel plate
JP3713094B2 (en) Connection method of existing underground pipe and new pipe by shield method
JP4374517B2 (en) Tunnel construction method
KR101772276B1 (en) The front structure for non-open cut type tunnel pressing
JPH03281898A (en) Method for connecting shield tunnel to structure or shield tunnels each other, and device therefor
JPH025233B2 (en)
JPH0765456B2 (en) How to build an expanded tunnel section
JP3580624B2 (en) Tunnel lining method
JP2777540B2 (en) Tunnel connection method and tunnel connection segment
JPH08270391A (en) Hollow segment for forming underground wall body and connecting method thereof
JPS6362637B2 (en)
JPH033039B2 (en)
JPS59102090A (en) Circumference enlarging shield drilling method
JPH076346B2 (en) Underground docking method for shield tunnel

Legal Events

Date Code Title Description
R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20080130

Year of fee payment: 13

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090130

Year of fee payment: 14

FPAY Renewal fee payment (prs date is renewal date of database)

Year of fee payment: 15

Free format text: PAYMENT UNTIL: 20100130

EXPY Cancellation because of completion of term