JPH073811A - Installation method of caisson - Google Patents

Installation method of caisson

Info

Publication number
JPH073811A
JPH073811A JP16861493A JP16861493A JPH073811A JP H073811 A JPH073811 A JP H073811A JP 16861493 A JP16861493 A JP 16861493A JP 16861493 A JP16861493 A JP 16861493A JP H073811 A JPH073811 A JP H073811A
Authority
JP
Japan
Prior art keywords
steel shell
caisson
shell caisson
mound
sand
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP16861493A
Other languages
Japanese (ja)
Inventor
Yasuhiro Kishi
恭博 喜志
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Taisei Corp
Original Assignee
Taisei Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Taisei Corp filed Critical Taisei Corp
Priority to JP16861493A priority Critical patent/JPH073811A/en
Publication of JPH073811A publication Critical patent/JPH073811A/en
Pending legal-status Critical Current

Links

Abstract

PURPOSE:To bear the whole bottom of a steel shell caisson with equal force, and increase the degree of accuracy of installation by applying substitutional sand to a planned sea-bottom of installation in advance, and constructing a bearing mound thereon. CONSTITUTION:Substitutional sand 1 is applied to a planned sea-bottom of installation of a steel shell caisson 3, and a bearing mound 2 having the same shape as that of a work room 34 of the steel shell caisson 3 is constructed thereon. After that, the steel shell caisson 3 is towed upward of the bearing mound 2, slab concrete is placed to a ceiling section 33 of the work room 34, and the steel shell caisson 3 is settled by concrete load. Then, a cutting edge section 32 is settled to the sea-bottom and is penetrated thereinto, a ceiling slab of the work roan 34 is settled to the upper surface of the bearing mound 2, and the steel shell caisson 3 is installed. At that time, the whole bottom of the steel shell caisson 3 can be borne on equal force by the substitutional sand 1 and bearing mound 2.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明は、鋼殻ケ−ソンの据付方
法に関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method of installing a steel shell casing.

【0002】[0002]

【従来の技術】鋼殻ケ−ソンを水深の浅い場所に据え付
ける場合、従来は図4に示すように、鋼殻ケ−ソンaを
据付予定場所まで曵航した後、刃口部bで包囲された底
部作業室cの天井部dにスラブコンクリ−トを打設し、
そのコンクリ−トの荷重により沈降させ、刃口部bを水
底地盤に着底、貫入させて据え付けを行っていた。
2. Description of the Related Art When a steel shell caisson is installed at a shallow water depth, conventionally, as shown in FIG. 4, the steel shell caisson a is towed to a planned installation location and then surrounded by a blade opening b. A slab concrete is placed on the ceiling portion d of the bottom working chamber c
It settled by the load of the concrete, and the blade opening part b was made to settle in the bottom of the water bottom ground, and was installed.

【0003】[0003]

【発明が解決しようとする課題】上記の従来技術には、
次のような問題点が存在する。 <イ>自然な状態の水底地盤は、ケ−ソンの支持力が均
等でないため、図4に示すように、ケ−ソン躯体が傾斜
しながら貫入することがあり、この場合、打設したスラ
ブコンクリ−トが傾斜の低い方に流動して、さらに大き
な傾斜を発生させることになる。そのため、後続のケ−
ソンの沈設方向が大きくずれてしまい、沈設方向の修正
作業に多大な工期と工費を費やすことになる。
DISCLOSURE OF THE INVENTION Problems to be Solved by the Invention
There are the following problems. <a> In the water-bed ground in a natural state, because the supporting capacity of the caisson is not uniform, as shown in FIG. 4, the caisson body may incline and intrude. The concrete flows toward the lower slope to generate a larger slope. Therefore, the subsequent case
The direction in which the song is sunk is greatly deviated, and a great deal of construction time and cost is required to correct the direction in which the song is sunk.

【0004】<ロ>また、図5に示すように、刃口部b
は水底地盤に支持されるが、天井部dは支持されていな
いため、スラブコンクリ−トを打設すると、その重みで
天井部dの中央に大きな曲げモ−メントが作用し、ケ−
ソン躯体に変形を及ぼすおそれがある。そのため、鋼殻
ケ−ソンの構造の剛性を高める必要があり、製作コスト
の増大の原因となる。
<B> Further, as shown in FIG.
Is supported on the water bottom ground, but the ceiling part d is not supported. Therefore, when the slab concrete is placed, a large bending moment acts on the center of the ceiling part d due to its weight, and the case
There is a risk of deformation of the body. Therefore, it is necessary to increase the rigidity of the structure of the steel shell caisson, which causes an increase in manufacturing cost.

【0005】[0005]

【本発明の目的】本発明は、上記のような問題点を解決
するためになされたもので、ケ−ソンの据付精度を高
め、さらにケ−ソンの構造を簡略化することができる鋼
殻ケ−ソンの据付方法を提供することを目的とする。
SUMMARY OF THE INVENTION The present invention has been made to solve the above-mentioned problems, and a steel shell capable of improving the installation accuracy of the caisson and simplifying the structure of the caisson. The purpose is to provide a method for installing a caisson.

【0006】[0006]

【課題を解決するための手段】即ち、本発明は、底部に
刃口部により包囲した作業室を有する鋼殻ケ−ソンを水
底地盤に据え付ける方法において、ケ−ソンの据付予定
地盤に事前に置換砂を施工し、その置換砂上に前記鋼殻
ケ−ソンの作業室とほぼ同じ形状の支持マウンドを築造
した後に、前記鋼殻ケ−ソンを支持マウンドの上方まで
曵航し、その作業室の天井部にスラブコンクリ−トを打
設してコンクリ−ト荷重により沈降させ、刃口部を水底
地盤に着底、貫入させると共に、作業室の天井スラブを
支持マウンド上面に着底させて据え付けることを特徴と
した、ケ−ソンの据付方法である。
That is, the present invention relates to a method of installing a steel shell caisson having a working chamber surrounded by a blade opening at the bottom on a submarine ground, in which the caisson is to be installed beforehand. After constructing a replacement sand and constructing a support mound having substantially the same shape as the working chamber of the steel shell caisson on the replacement sand, the steel shell caisson is towed above the support mound, and the working room The slab concrete is placed on the ceiling part of the above and settled by the concrete load, and the blade part is set to the bottom of the submerged ground and penetrates, and the ceiling slab of the working room is set on the upper surface of the support mound and installed. It is a method for installing a caisson, which is characterized by that.

【0007】[0007]

【実施例】以下、図面を参照しながら、本発明の一実施
例について説明する。 <イ>置換砂、支持マウンドの施工 図1に示すように、ケ−ソンの据付予定地盤に事前に置
換砂1を施工する。この置換砂1は、ケ−ソンの外形よ
りも広い範囲で施工する。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS An embodiment of the present invention will be described below with reference to the drawings. <a> Construction of replacement sand and support mound As shown in Fig. 1, replacement sand 1 is constructed in advance on the ground where the cason is to be installed. This replacement sand 1 is applied in a wider area than the outer shape of the caisson.

【0008】次に、置換砂1上に、後述の鋼殻ケ−ソン
3の作業室34とほぼ同じ形状(例えば台形状)の支持
マウンド2を築造する。支持マウンド2を構成する材料
は、据付地点の潮流あるいは波浪条件によって使い分け
を行うものとし、潮流あるいは波浪等の影響を受ける場
合は、砕石等の粒径の大きい材料を使用し、洗掘あるい
は流れ出し等に対抗する。
Next, a support mound 2 having a substantially same shape (for example, trapezoidal shape) as a working chamber 34 of a steel shell caisson 3 described later is built on the replacement sand 1. The materials that make up the support mound 2 should be selected according to the tidal current or wave conditions at the installation point. If the tidal current or wave conditions affect the material, use a material with a large particle size such as crushed stone, and then scour or drain. And so on.

【0009】また、支持マウンド2の法面保護として、
さらに粒径の大きい砕石あるいは袋詰めモルタル等を用
いる。静穏域で施工する場合は、荒目砂等をマウンド材
に用いる。
Also, as slope protection of the support mound 2,
Further, use crushed stone or bagged mortar with a larger particle size. When constructing in a quiet area, use coarse sand as the mound material.

【0010】また、支持マウンド2の築造高さは、ケ−
ソン内に打設されるコンクリ−ト荷重により水底面にそ
の刃口部33が貫入する量hを計算上から求め(図
3)、作業室34の高さHから差し引いた高さH−hと
する(図1)。
The building height of the support mound 2 is
The amount h of the blade opening 33 penetrating the bottom of the water due to the concrete load placed in the chamber is calculated (FIG. 3), and the height H−h is subtracted from the height H of the working chamber 34. (Fig. 1).

【0011】<ロ>ケ−ソンの曵航 鋼殻ケ−ソン3は鋼製の外殻を有し、図1に示すよう
に、円筒状あるいは角筒状等の側壁部31の底部に環状
の刃口部32を垂設し、この刃口部32と水平な天井部
33とにより包囲した作業室34を設けた構造である。
<B> Caisson towed steel shell caisson 3 has a steel outer shell, and as shown in FIG. 1, has an annular shape at the bottom of a side wall portion 31 having a cylindrical shape or a rectangular tube shape. In this structure, the blade opening portion 32 is vertically provided, and a working chamber 34 surrounded by the blade opening portion 32 and the horizontal ceiling portion 33 is provided.

【0012】このように構成した鋼殻ケ−ソン3を、図
1に示すように、支持マウンド2の上方まで曵航する。
The steel shell casing 3 thus constructed is towed to a position above the support mound 2 as shown in FIG.

【0013】<ハ>スラブコンクリ−トの打設、ケ−ソ
ンの据付 図2に示すように、鋼殻ケ−ソン3の曵航後、天井部3
3内にスラブコンクリ−ト4を打設し、コンクリ−ト荷
重により徐々に沈降させ、刃口部32を置換砂1上に着
底させる。
<C> Placing the slab concrete and installing the caisson As shown in FIG. 2, after the towing of the steel shell caisson 3, the ceiling 3
A slab concrete 4 is placed in 3 and is gradually settled by concrete load, and the blade opening 32 is bottomed on the replacement sand 1.

【0014】次に図3に示すように、コンクリ−ト荷重
をさらに増加させ、刃口部32を置換砂1に貫入させ
る。そして、貫入量がhに達すると、天井部33が支持
マウンド2の上面に着底し、鋼殻ケ−ソン3の据え付け
が完了する。
Next, as shown in FIG. 3, the concrete load is further increased so that the blade opening portion 32 penetrates into the replacement sand 1. Then, when the penetration amount reaches h, the ceiling portion 33 bottoms on the upper surface of the support mound 2, and the installation of the steel shell caisson 3 is completed.

【0015】置換砂1及び支持マウンド2は、自然な状
態の水底地盤と異なり、上部に据え付ける鋼殻ケ−ソン
3の底部全体を、均等な力で支持することができる。着
底後は、マテリアルロックを構築し、鋼殻ケ−ソン3を
沈下させるための圧気掘削が行われる。
The displacement sand 1 and the support mound 2 can support the entire bottom portion of the steel shell caisson 3 installed on the upper portion with an equal force, unlike the water bottom soil in a natural state. After bottoming, pressure rock excavation for constructing a material lock and sinking the steel shell caisson 3 is performed.

【0016】[0016]

【本発明の効果】本発明は以上説明したようになるた
め、次のような効果を得ることができる。 <イ>鋼殻ケ−ソンの底部は、置換砂と支持マウンドに
よる均等な支持力により支持されるため、ケ−ソンの着
底時の傾斜、偏位が防止できる。従って、従来のように
沈設方向の修正作業に多大な工期と工費を費やすことが
ない。
Since the present invention is as described above, the following effects can be obtained. <A> Since the bottom of the steel shell caisson is supported by an even supporting force of the displacement sand and the supporting mound, inclination and displacement of the caisson at the time of bottoming can be prevented. Therefore, unlike the conventional method, a great amount of work and cost are not required for the correction work in the sunk direction.

【0017】<ロ>鋼殻ケ−ソンの作業室の天井スラブ
は、支持マウンド上面の全面積により均等に支持される
ため、従来のように天井スラブの中央部に大きな曲げモ
−メントが作用し、ケ−ソン躯体に変形を及ぼすことが
ない。従って、鋼殻構造を簡略化でき、製作コストの低
減を図ることができる。
<B> Since the ceiling slab in the work chamber of the steel shell caisson is evenly supported by the entire area of the upper surface of the support mound, a large bending moment acts on the central portion of the ceiling slab as in the conventional case. However, it does not deform the casing body. Therefore, the steel shell structure can be simplified and the manufacturing cost can be reduced.

【0018】<ハ>周面摩擦力等が期待できない初期沈
設時に対し、ケ−ソン底部全体が置換砂及び支持マウン
ドに支持されているため、この支持面積を調整すること
により、安全な掘削及び沈設作業が可能となる。
<C> Since the entire bottom of the caisson is supported by the replacement sand and the support mound at the time of initial digging where the frictional force on the peripheral surface cannot be expected, safe excavation and excavation can be performed by adjusting the support area. It becomes possible to perform the laying work.

【図面の簡単な説明】[Brief description of drawings]

【図1】 鋼殻ケ−ソンの曵航工程の説明図FIG. 1 Explanatory drawing of tow process of steel shell caisson

【図2】 鋼殻ケ−ソンの沈降工程の説明図FIG. 2 is an explanatory view of a settling process of a steel shell caisson.

【図3】 鋼殻ケ−ソンの着底状態の説明図FIG. 3 is an explanatory view of a bottomed state of a steel shell caisson.

【図4】 従来技術の説明図FIG. 4 is an explanatory diagram of a conventional technique.

【図5】 従来技術の説明図FIG. 5 is an explanatory diagram of a conventional technique.

Claims (1)

【特許請求の範囲】[Claims] 【請求項1】 底部に刃口部により包囲した作業室を有
する鋼殻ケ−ソンを水底地盤に据え付ける方法におい
て、 ケ−ソンの据付予定地盤に事前に置換砂を施工し、 その置換砂上に前記鋼殻ケ−ソンの作業室とほぼ同じ形
状の支持マウンドを築造した後に、 前記鋼殻ケ−ソンを支持マウンドの上方まで曵航し、 その作業室の天井部にスラブコンクリ−トを打設してコ
ンクリ−ト荷重により沈降させ、 刃口部を水底地盤に着底、貫入させると共に、 作業室の天井スラブを支持マウンド上面に着底させて据
え付けることを特徴とした、 ケ−ソンの据付方法。
1. A method of installing a steel shell caisson having a working chamber surrounded by a blade opening at the bottom on a subseabed ground, in which replacement sand is applied in advance to the ground to be installed in the caisson, and the replacement sand is placed on the replacement sand. After constructing a support mound having almost the same shape as the working chamber of the steel shell caisson, the steel shell caisson is towed above the supporting mound, and a slab concrete is struck on the ceiling of the working chamber. The casson is characterized in that it is installed and settled by a concrete load, the blade opening is set on the bottom of the water bottom and penetrates, and the ceiling slab of the working chamber is set on the upper surface of the support mound. Installation method.
JP16861493A 1993-06-15 1993-06-15 Installation method of caisson Pending JPH073811A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP16861493A JPH073811A (en) 1993-06-15 1993-06-15 Installation method of caisson

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP16861493A JPH073811A (en) 1993-06-15 1993-06-15 Installation method of caisson

Publications (1)

Publication Number Publication Date
JPH073811A true JPH073811A (en) 1995-01-06

Family

ID=15871329

Family Applications (1)

Application Number Title Priority Date Filing Date
JP16861493A Pending JPH073811A (en) 1993-06-15 1993-06-15 Installation method of caisson

Country Status (1)

Country Link
JP (1) JPH073811A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100849673B1 (en) * 2008-01-29 2008-08-01 주식회사 진두아이에스 Caisson for double-current tidal stream device
CN104314092A (en) * 2014-10-30 2015-01-28 中交四航局第三工程有限公司 Open caisson construction method based on substitution method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100849673B1 (en) * 2008-01-29 2008-08-01 주식회사 진두아이에스 Caisson for double-current tidal stream device
CN104314092A (en) * 2014-10-30 2015-01-28 中交四航局第三工程有限公司 Open caisson construction method based on substitution method

Similar Documents

Publication Publication Date Title
Burland et al. Leaning Tower of Pisa: behaviour after stabilization operations
US3903662A (en) Method of securing structural support elements in soil
JP3534928B2 (en) Construction method of seismic isolation pit for existing building
JPH073811A (en) Installation method of caisson
JP2000008623A (en) Restoration method of structure
JPS62215727A (en) Foundation work for structure
JPH0559728A (en) Sheathing work above underground structure
JPS5843532B2 (en) Caisson sinking method
JP2007120240A (en) Foundation structure of building in weak ground
RU2056478C1 (en) Method for reinforcing bases and foundations on sagging ground in hindered conditions
JPH0536044Y2 (en)
JP3430376B2 (en) How to build an underground skeleton
JP4484100B2 (en) Installation method of steel pipe sheet pile assembly for well formation
JPH0438849B2 (en)
JPH10183660A (en) Foundation structure of building
JPH0237453B2 (en)
JPH0493430A (en) Floating prevention method for underground structure
JPH0612009B2 (en) Caisson sinking method
JPH028794A (en) Lowering of building
JPS6357566B2 (en)
JP3537641B2 (en) Basement submersion method and its equipment
JP2536108B2 (en) Foundation construction method for offshore structures
JP2630994B2 (en) Construction method of quay using caisson
JPH0353409B2 (en)
JP3234705B2 (en) Foundation for earth pressure reduction of underground structures