JPH07302285A - Device and method for preparing transport plan - Google Patents

Device and method for preparing transport plan

Info

Publication number
JPH07302285A
JPH07302285A JP9506794A JP9506794A JPH07302285A JP H07302285 A JPH07302285 A JP H07302285A JP 9506794 A JP9506794 A JP 9506794A JP 9506794 A JP9506794 A JP 9506794A JP H07302285 A JPH07302285 A JP H07302285A
Authority
JP
Japan
Prior art keywords
loading
plan
landing
lot
shipping
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
JP9506794A
Other languages
Japanese (ja)
Inventor
友吾 ▲高▼
Yuugo Kou
Kazuo Suzuki
和夫 鈴木
Sunao Hiyama
直 桧山
Yukio Yasuhara
征紀夫 安原
Ryota Takenaka
良太 武中
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
JFE Steel Corp
JFE Logistics Corp
JFE Systems Inc
Original Assignee
Kawasaki Steel Systems R&D Corp
Kawasaki Steel Corp
Kawatetsu Logistics Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kawasaki Steel Systems R&D Corp, Kawasaki Steel Corp, Kawatetsu Logistics Corp filed Critical Kawasaki Steel Systems R&D Corp
Priority to JP9506794A priority Critical patent/JPH07302285A/en
Publication of JPH07302285A publication Critical patent/JPH07302285A/en
Withdrawn legal-status Critical Current

Links

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

PURPOSE:To prepare a suitable entire transport plan concerning ships. CONSTITUTION:The transport plan from a forwarding site to a landing site is divided into plural small plans, a transport plan preparing part 9 possesses the combination of ships and on-ship lots satisfying planning conditions on the respective small plans, and a landing site waiting evaluating function 97 and an inference engine 98 decide any optimum combination from that possessed combination based on a total evaluation reference.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明は、コンピュータを用いて
輸送計画を作成する輸送計画作成装置に関し、特に船舶
による貨物の輸送に当たり、船舶の運航計画および岸壁
における積揚荷役計画(以下、バースプランと称する)
を一貫して作成する場合に好適な輸送計画作成装置およ
び方法に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a transportation plan creating apparatus for creating a transportation plan by using a computer, and particularly when transporting a cargo by a ship, an operation plan of the ship and a loading / unloading plan (hereinafter referred to as a berth plan) of the ship. Called)
The present invention relates to a transportation plan creating apparatus and method suitable for consistently creating a transportation plan.

【0002】[0002]

【従来の技術】船舶による輸送計画を作成する場合の立
案事項には、貨物を一船分の重量にグルーピングする船
積ロット編成、船積ロットと船舶を紐付けする積載船舶
決定、積地において積荷役を行う岸壁(クレーン)と作
業時間帯を決定する積バースプラン作成等がある。
2. Description of the Related Art Items to be planned when preparing a transportation plan by ship include the formation of a shipping lot for grouping cargo into the weight of one ship, the determination of a loading ship for linking the shipping lot and the ship, and the loading and unloading at the loading site. There are berths (cranes) for carrying out work and product berth plans for determining working hours.

【0003】輸送の効率を高くし輸送にかかる費用を少
なくするためには船舶の積載率が高く、船舶の積地や揚
地における待ち時間が少ない計画を作成する必要があ
る。このような目的のために特開平3−189702号
では1つの港について待ち時間の少ない最適なバースプ
ランを作成するバース管理エキスパートシステムが提案
されている。
In order to increase the efficiency of transportation and reduce the cost of transportation, it is necessary to prepare a plan in which the loading rate of vessels is high and the waiting time at the loading and unloading points of vessels is low. For this purpose, JP-A-3-189702 proposes a berth management expert system for creating an optimum berth plan with a short waiting time for one port.

【0004】また、輸送効率の高い運航計画を作成する
装置としては特開平5−12308号に船の運航計画自
動作成システムが開示されている。
As an apparatus for creating an operation plan with high transportation efficiency, Japanese Patent Application Laid-Open No. 5-12308 discloses an automatic operation plan creation system for ships.

【0005】[0005]

【発明が解決しようとする課題】全体の輸送計画を立案
する際に一部分の輸送計画を上記輸送計画装置を組み合
わせ用いてもその一部分、たとえば、バースプランのみ
および運航計画のみでは好適な輸送計画であっても全体
の船舶の運航から見ると効率の良い計画になるとは限ら
ない。
Even when a part of the transportation plan is used in combination with the above-mentioned transportation planning device when the entire transportation plan is drafted, a part of the transportation plan, for example, only the berth plan and the operation plan are suitable transportation plans. Even if there is one, it is not always an efficient plan from the viewpoint of the operation of the entire ship.

【0006】例えば、1つの港における効率的なバース
プランを作成する装置ではどの船がどの荷物を積んでい
つ対象の港に入港するかを予め別の手段で決めておく必
要があり、そちらの方が全体の輸送効率への影響が大き
い。また、1つの港で効率的であっても、それが船の次
の港では悪影響を及ぼす場合もあり得る。
[0006] For example, in an apparatus for creating an efficient berth plan at one port, it is necessary to determine in advance which means should be loaded by which ship and when to enter the target port by another means. Has a greater impact on the overall transportation efficiency. Also, being efficient at one port can have a negative effect at the port next to the ship.

【0007】さらに、1つの船について揚荷役を含めた
効率の良い運航計画を作成する装置では、複数の船で輸
送する場合にどの荷物をどの船に積むかや、船同士の岸
壁での競合といった要素を考慮することはできない。
Further, in a device for creating an efficient operation plan including unloading for one ship, which cargo is loaded on which ship when transporting by a plurality of ships, and competition between the ships on the quay. Such factors cannot be taken into consideration.

【0008】このような全体的な観点から全体の輸送効
率の最適性を追求することは経験ある人間に頼ってい
る。しかしながら、輸送量が大きい場合や船の隻数が多
い場合には人間の処理能力を超えることが多く、輸送計
画の立案のための情報収集、および担当者間の調整に多
大な負荷がかかるという問題がある。
[0008] Pursuing the optimality of the overall transportation efficiency from such an overall viewpoint relies on an experienced person. However, when the amount of transportation is large or the number of ships is large, it often exceeds the human processing capacity, and it takes a great load to collect information for making a transportation plan and to coordinate between personnel. There is.

【0009】そこで、本発明の目的は、個別輸送計画の
寄せ集めではなく、船舶の全体的な輸送計画を立案し、
さらに、船舶の積載率が高く、待ち時間が少なくなるよ
うな効率のよい輸送計画作成装置および方法を提供する
ことにある。
Therefore, the object of the present invention is not to collect individual transportation plans but to formulate an overall transportation plan of a ship,
Another object of the present invention is to provide an efficient transportation planning apparatus and method that allows the loading rate of ships to be high and the waiting time to be reduced.

【0010】[0010]

【課題を解決するための手段】このような目的を達成す
るために、請求項1の発明は、出荷可能品を積合せ可能
な条件を考慮して一船分の重量にまとめた船積ロットを
複数編成する船積ロット編成手段と、当該編成した各船
積ロットに対し、揚地において想定される待ち時間と、
該揚地から逆算した積地の最適出港時刻とを求める揚地
待ち判定手段と、前記編成した船積ロットを出荷必要性
と前記揚地における待ち時間の少なさによる優先順に1
つずつ選択するバースプラン作成船積ロット選択手段
と、当該選択した船積ロットをできるだけ積地の最適出
港時刻に合わせた時間帯で荷役する積荷役計画を作成す
る積バースプラン作成手段と、前記船積ロットに対し、
それを輸送可能で、入港が積開始に間に合う船舶を割り
付ける積載船舶決定手段と、前記船積ロットと船舶に対
し、航海時間を計算し、揚地における揚荷役計画を作成
する揚バースプラン作成手段と、該バースプラン作成手
段の作成結果における揚地待ち時間を評価し、想定より
も待ちが大きい場合にバースプランを解消し、船積ロッ
トの選択をやり直す揚地待ち評価手段と、を有すること
を特徴とする。
In order to achieve such an object, the invention of claim 1 considers a condition in which shipmentable products can be stacked, and sets a shipping lot into a weight for one ship. A shipping lot forming means for forming a plurality of pieces, and a waiting time expected at the landing site for each of the formed forming lots,
A landing waiting determination means for obtaining the optimum departure time of the loading land which is calculated back from the landing land, and a priority order depending on the necessity of shipping the shipping lot and the short waiting time at the landing place 1
A berth plan creation loading lot selection means for selecting each one, a loading berth plan creation means for creating a loading and unloading plan that loads the selected shipping lots in a time zone that matches the optimal departure time of the loading place as much as possible, and the loading lot As opposed to
A loading vessel determining means for allocating a vessel capable of transporting the vessel and arriving at the port in time to start loading, and a unloading berth plan creating means for calculating a voyage time for the loading lot and the vessel and creating an unloading plan at the landing site. And evaluating the landing waiting time in the creation result of the berth plan creating means, canceling the berth plan when the waiting is longer than expected, and re-selecting the shipping lot, and landing waiting evaluation means. And

【0011】請求項2の発明は、積地から揚地まで船舶
により出荷可能品を輸送する輸送計画をコンピュータに
より作成する輸送計画作成方法において、前記輸送計画
を船積ロット編成計画、積バースプラン、船舶の運航計
画、揚バースプランからなる複数の小計画で構成し、前
記複数の小計画のそれぞれについて、立案条件を予め定
めておき、前記コンピュータは当該立案条件を全て満足
する船舶および船積ロットの組み合わせを取得し、当該
組み合わせの中から、予め定めた総合評価基準に最も合
致する船舶および船積ロットの組合わせを輸送計画の立
案要素と決定することを特徴とする。
According to a second aspect of the present invention, there is provided a transportation plan creating method for creating a transportation plan for transporting shippable items from a loading place to a landing place by a computer by a computer, wherein the transportation plan is a shipping lot formation plan, a loading berth plan, It is composed of a plurality of small plans consisting of a ship operation plan and a lifting berth plan, and a planning condition is set in advance for each of the plurality of small plans, and the computer determines the ships and shipping lots that satisfy all the planning conditions. A feature is that a combination is acquired, and a combination of a ship and a shipping lot that best matches a predetermined comprehensive evaluation standard is determined as a planning element of a transportation plan from the combination.

【0012】[0012]

【作用】請求項1の発明では、船積ロット編成手段によ
り積載率が一定値以上に達する船積ロットを多数編成
し、揚地待ち判定手段により各船積ロットの揚地におけ
る待ち時間を判定する。そして、バースプラン作成船積
ロット選択手段により、揚地における待ち時間の少ない
順に船積ロットを選択し、選択された船積ロットに対
し、積バースプラン作成手段、積載船舶決定手段、揚バ
ースプラン作成手段により、積揚荷役計画、船舶運航計
画を作成する。揚バースプラン作成手段では、揚地待ち
判定手段により求めた積地最適出港時刻にできるだけ合
わせた積荷役計画を作成する。揚地待ち評価手段は、選
択された船積ロットの積揚荷役計画、船舶運航計画に対
して、揚地待ち時間の評価を行う。揚地における待ち時
間が、揚地待ち判定手段で想定したものより長い場合に
は、積揚荷役計画、船舶運航計画を解消し、バースプラ
ンを作成する船積ロットを選択し直す。これにより、一
定以上の積載率があり、揚地における待ち時間の少ない
船積ロットが優先的に計画されるので、全体として効率
のよい船舶による輸送計画が作成される。
According to the first aspect of the present invention, a large number of shipping lots whose loading rate reaches a certain value or more are organized by the shipping lot organization means, and the waiting time at each landing land of each shipping lot is determined by the landing waiting determination means. Then, the berth plan creation shipping lot selection means selects the shipping lots in ascending order of waiting time at the landing site, and the loading berth plan creation means, the loading vessel determination means, and the unloading berth plan creation means select the selected shipping lots. Create a loading / unloading plan and ship operation plan. The unloading berth plan creating means creates a loading and unloading plan as close as possible to the optimum loading port departure time obtained by the landing waiting determination means. The landing waiting evaluation means evaluates the landing waiting time for the loading / unloading plan and the ship operation plan of the selected loading lot. When the waiting time at the landing place is longer than that assumed by the landing place waiting determination means, the loading / unloading plan and the ship operation plan are canceled, and the loading lot for which the berth plan is prepared is reselected. As a result, shipping lots with a loading rate above a certain level and with a short waiting time at the landing are preferentially planned, so that an efficient transportation plan by ship is created as a whole.

【0013】請求項2の発明では、全体輸送計画を分割
した小計画の中で立案条件を満足する船舶および船積ロ
ットの組合せを立案要素の候補として選択し、これらの
組合せの中から好適な組合せを総合評価基準により選択
する。
According to the second aspect of the present invention, a combination of a ship and a loading lot that satisfies the planning conditions is selected as a planning element candidate in a small plan obtained by dividing the entire transportation plan, and a suitable combination is selected from these combinations. Is selected according to the comprehensive evaluation criteria.

【0014】[0014]

【実施例】以下、図面を使用して、本発明の実施例を詳
細に説明する。
Embodiments of the present invention will be described in detail below with reference to the drawings.

【0015】本発明を適用する輸送計画装置には周知の
パーソナルコンピュータやワークステーションを用いる
ことができる。このような情報処理装置は、ソフトウェ
アを記憶するためのハードディスクなどの記憶手段、ユ
ーザが情報を入力するためのキーボードなどの入力手
段、演算情報を格納するRAMなどの記憶手段、上記ソ
フトウェアを実行するCPUなどの演算処理手段を用い
ているものであればよい。輸送計画はキーボードから入
力され、ハードディスクに知識ベースとして格納された
ルール(決定条件)を判別処理に用いて立案される。こ
のために、ハードディスク上に予め用意されたソフトウ
ェアをCPUが実行することにより上記輸送関連情報か
ら上記決定条件に従って本発明に関わる全体輸送計画を
作成する。このため、本実施例では、上記ソフトウェア
の構成要素をその処理内容を示す機能と表現することに
する。
A well-known personal computer or workstation can be used for the transportation planning apparatus to which the present invention is applied. Such an information processing apparatus executes storage means such as a hard disk for storing software, input means such as a keyboard for a user to input information, storage means such as a RAM for storing calculation information, and the above software. It may be any one that uses arithmetic processing means such as a CPU. The transportation plan is input from the keyboard, and the rule (decision condition) stored as a knowledge base on the hard disk is used for the discrimination process. For this purpose, the CPU executes software prepared in advance on the hard disk to create an entire transportation plan according to the present invention from the transportation-related information according to the determination conditions. Therefore, in the present embodiment, the constituent elements of the software will be expressed as a function indicating the processing content thereof.

【0016】このようなハード構成で作成される輸送計
画の機能ブロック図を図1に示す。
FIG. 1 shows a functional block diagram of a transportation plan created with such a hardware configuration.

【0017】図1において、9は情報処理装置上に構築
される輸送計画作成機能を担う輸送計画作成部である。
輸送計画作成部9には計画対象日情報記憶部1、出荷可
能品情報記憶部2、積揚地情報記憶部3、船舶情報記憶
部4、計画基準情報記憶部5、船積ロット情報記憶部
6、積揚荷役情報記憶部7、船舶航海情報記憶部8が接
続している。
In FIG. 1, reference numeral 9 denotes a transportation plan preparation section having a transportation plan preparation function constructed on the information processing apparatus.
The transportation plan creation unit 9 includes a planned target date information storage unit 1, a shippable product information storage unit 2, a landing site information storage unit 3, a ship information storage unit 4, a planning standard information storage unit 5, and a shipping lot information storage unit 6. The loading / unloading information storage unit 7 and the ship navigation information storage unit 8 are connected.

【0018】計画対象日情報記憶部1には計画の対象と
する日付が予め記憶されている。本実施例においては積
地で1日間に出荷する分の船積ロット、積揚荷役計画、
船舶運航計画を作成の対象とする。
The date to be planned is stored in the plan target date information storage unit 1 in advance. In this embodiment, a shipping lot, a loading / unloading plan, which is shipped in one day at the loading place,
Target the creation of ship operation plans.

【0019】出荷可能品情報記憶部2には貨物関連情
報、すなわち、出荷可能品の積地、揚地(向先)、品
種、顧客、重量、指定出荷日(猶予期間を含み、指定が
ある場合にのみ記憶)、優先度を示す特性等を予め記憶
する。
The freight-related information is stored in the feasible-goods information storage unit 2, that is, the freight origin, the landing place (destination), the product type, the customer, the weight, the designated shipping date (including the grace period, and designated). (Stored only in the case), the characteristics indicating the priority, etc. are stored in advance.

【0020】積揚地情報記憶部3には積揚地の情報、す
なわち、積揚地の所在地、稼働日、標準稼働開始時刻、
標準稼働終了時刻、標準稼働時間、使用可能クレーン、
クレーン稼働基数、倉庫の庫腹に関する情報等を予め記
憶する。
The landing site information storage unit 3 stores information on the landing site, that is, the location of the landing site, the working day, the standard operation start time,
Standard operation end time, standard operation time, usable crane,
Information such as the number of operating cranes and the hunger of the warehouse is stored in advance.

【0021】船舶情報記憶部4には、船舶情報、例え
ば、船舶の船型、積載可能重量、積載可能品種、航海可
能地区等を予め記憶する。
The ship information storage unit 4 stores in advance ship information, for example, ship type, loadable weight, loadable product type, sailable area, etc.

【0022】計画基準情報記憶部5には次のような各種
の計画作成における標準情報が予め記憶される。
The plan reference information storage unit 5 stores in advance the following standard information for creating various plans.

【0023】1)出荷可能品をグルーピングする単位を
定めるための出荷可能品グルーピング基準 2)積地・揚地・品種別に出荷量や距離などからもっと
も輸送効率が高い船型を定めた輸送最適船型基準(船型
は、Deadweight tonにより複数段階に分
けたクラスを示す。) 3)積地・揚地・品種別に輸送可能な船型を定めた輸送
可能船型基準 4)船積ロットを編成する量を定めた船積ロット編成量
基準 5)船積ロットとして許容する最低の積載率を定めた最
低積載率基準 6)積合せ可能な異なる品種同士の組み合わせを定めた
品種積合わせ可能基準 7)積合わせ可能な異なる揚地同士の組み合わせて定め
た多港揚可能基準 8)積揚地・品種毎の荷役可能クレーンと優先順を定め
た荷役可能クレーン基準 9)積揚地・クレーン・品種毎の荷役能率を定めた荷役
能率基準 10)積バースプラン作成における積地最適出港時刻か
らの荷役終了時刻の前倒し時間の許容値を定めた積荷役
前倒し許容時間基準 船積ロット情報記憶部6には既に計画されている船積ロ
ットの積地、揚地、品種、重量、計画積日、積載船舶な
どの情報が予め記憶されており新たに計画した船積ロッ
トの情報もここに格納する。
1) Standards for grouping shipmentable products for determining units for grouping shipmentable products 2) Optimal transportation ship type standards that determine the ship type with the highest transportation efficiency from the shipping amount and distance etc. according to loading place, landing place and product type (The ship type indicates the class divided into multiple stages by Deadweight ton.) 3) Transportable ship type standard that determines the ship type that can be transported by loading place, landing place, and type 4) Shipping that determines the amount of forming a shipping lot Lot formation amount standard 5) Minimum loading ratio standard that defines the minimum loading ratio allowed as a loading lot 6) Product mixability standard that defines combinations of different products that can be stacked 7) Different landing sites that can be stacked Criteria for multi-port unloading defined by combining each other 8) Cranes capable of loading and unloading according to loading land / product type and criteria for loading unloadable cranes defining priority 9) Loading and unloading clay・ Cargo handling efficiency standard that defines the cargo handling efficiency for each product type 10) Cargo handling advance allowance time standard that defines the allowable value of the cargo handling end time ahead of the loading port optimum departure time in the loading berth plan creation Shipping lot information storage unit 6 The information of the loading lot, the landing place, the product type, the weight, the planned loading date, the loading vessel, etc. of the planned shipping lot is stored in advance, and the information of the newly planned shipping lot is also stored here.

【0024】積揚荷役情報記憶部7にはすでに計画され
ている各積揚荷役の積揚地、使用クレーン、荷役開始時
刻、荷役終了時刻、荷役する船積ロット、積載船舶等の
情報が予め記憶されており、新たに計画した積揚荷役の
情報もここに格納する。
The loading / unloading information storage unit 7 stores in advance information such as the landing site of each loading / unloading plan, the crane to be used, the loading / unloading start time, the loading / unloading end time, the loading lot to be loaded / unloaded, and the loading vessel. The information on the newly planned loading and unloading operations is also stored here.

【0025】船舶航海情報記憶部8にはすでに計画され
ている出港地、出港予定、実績時刻、入港地、入港予
定、実績時刻、積載船積ロットなどの情報が予め記憶さ
れており、新たに計画した船舶の航海情報もここに格納
する。
The ship voyage information storage unit 8 stores in advance information such as planned port of departure, scheduled port of departure, actual time, port of entry, planned arrival of port, actual time of day, loaded shipping lot, etc. The voyage information of the ships that have made a flight is also stored here.

【0026】このように構成された船舶による輸送計画
作成装置の動作について説明する。図2は輸送計画作成
部9の処理手順を示す。
The operation of the transportation planning device using the ship thus configured will be described. FIG. 2 shows a processing procedure of the transportation plan creation unit 9.

【0027】まず、出荷可能品情報記憶部2に記憶され
ている出荷可能品を、揚地・品種が同じで、顧客その他
の属性により積み合わせの制約がないもの同士でグルー
ピングする。より具体的には推論エンジン98により、
まず出荷可能品に対し付随する揚地・品種その他の情報
を出荷可能品グループ基準(計画基準情報記憶部5に記
憶)と照合し、グループコードを付加する。次に、同じ
グループコードを持つものを抽出し集計することにより
グルーピングが実現される(ステップS1)。
First, the shippable products stored in the shippable product information storage unit 2 are grouped by those having the same landing place and product type and having no restrictions on stacking due to customer or other attributes. More specifically, the inference engine 98
First, the information such as the landing site, product type, etc. attached to the shippable product is collated with the shippable product group standard (stored in the planning standard information storage unit 5), and the group code is added. Next, grouping is realized by extracting and totaling those having the same group code (step S1).

【0028】次に、後述のループ処理の船積ロット編成
の終了判定を行う(ステップS2)。
Next, it is judged whether or not the shipping lot formation in the loop processing described later is completed (step S2).

【0029】終了の条件は、編成した船積ロットの量が
船積ロット編成基準量(評価基準情報記憶部5に記憶)
に達するか、すべての可能な船積ロットを編成すること
である。船積ロット編成基準量は、1日分の出荷量より
も多く設定し、できるだけ多くの船積ロットを編成し、
よいものが選択されるようにする。
The termination condition is that the quantity of the formed shipping lots is the standard quantity of shipping lots (stored in the evaluation standard information storage unit 5).
To reach or organize all possible shipping lots. The shipping lot organization standard amount is set to be larger than the shipping amount for one day, and as many shipping lots are organized as possible.
Make sure the good ones are selected.

【0030】次に、ステップS1でグループ分けされた
出荷可能品グループをS2〜S4のループ処理により一
船分の重量にまとめた船積ロットを編成する(ステップ
S3)。
Next, the shipping lots are grouped into the weight of one ship by the loopable processing of S2 to S4, and the shipping lot group grouped in step S1 is organized (step S3).

【0031】ここでは、一船分の重量の目安として船型
ごとの標準積載可能重量情報(船舶情報記憶部4に記
憶)を使用する。
Here, the standard loadable weight information (stored in the ship information storage unit 4) for each ship type is used as a guide for the weight of one ship.

【0032】まず、出荷可能品グループを次に示す優先
順に1つ選択する。
First, one shipmentable product group is selected in the following priority order.

【0033】(1)出荷日の範囲が指定されており、計
画対象日がその最終日であるもの。
(1) A shipping date range is specified, and the planning target date is the final date.

【0034】(1a)出荷可能品の特性の優先順。(1a) Priority order of characteristics of products that can be shipped.

【0035】(2)(1)以外のもの。(2) Other than (1)

【0036】(2a)出荷可能品の重量が該当する積地
・揚地・品種の輸送最適船型分の重量以上あるもの。
(2a) A product that can be shipped has a weight equal to or greater than the weight of the optimum ship shape for transportation of the relevant loading place, landing place, and type.

【0037】(2b)(2a)以外のもの。(2b) Other than (2a)

【0038】次に、選択した出荷可能品グループが計画
対象日に輸送最適船型分の重量に達している場合、その
出荷可能品グループ単独で輸送最適船型の船積ロットを
1つ編成する。一方、そうでない場合は、小さい船型の
船積ロットや、他の出荷可能品グループとの積合せによ
る船積ロットを複数編成する。ただし、輸送最適船型の
船積ロットが後述の「揚地待ち判定」により、1日以上
の揚地待ちがあると判定された場合には、小さい船型の
船積ロットや、他の出荷可能品グループとの積合せの船
積ロットの編成を行う。
Next, if the selected group of deliverable products has reached the weight of the optimal shipping form for the planned date, one shipping lot of the optimal shipping form is organized by the group of deliverable products. On the other hand, if this is not the case, a plurality of small-sized shipping lots or shipping lots that are combined with other shippable product groups are organized. However, if the optimum shipping type shipping lot is judged to have a waiting time of landing for more than one day by the “waiting landing judgment” to be described later, it will be Organize shipping lots for the above.

【0039】これらは、1品種1港揚の輸送最適船型の
船積ロットが編成できる場合は、できるだけそれをねら
い、ただし、揚地での待ちが想定される場合には、より
揚地待ちの少ない船積ロットの組み方を探るためであ
る。
These are aimed at as much as possible when a shipping lot of the optimum ship type for transportation of one product and one port can be organized. However, when waiting at the landing is assumed, waiting for landing is less. This is to find out how to assemble the shipping lot.

【0040】船積ロットの編成においては、次の条件を
チェックする。
The following conditions are checked in the formation of the shipping lot.

【0041】船積ロットの重量が、上記船型の標準積
載可能重量に対する最低積載率(計画基準情報記憶部5
に記憶)の基準を満たす。
The weight of the shipping lot is the minimum loading ratio (plan reference information storage unit 5) with respect to the standard loadable weight of the above ship type.
Memorize) to meet the criteria.

【0042】船積ロットの船型が、積地・揚地・品種
の輸送可能船型を満たす。
The ship type of the shipping lot satisfies the transportable ship types of the loading place, the landing place, and the type.

【0043】異なる品種の出荷可能品を積合せる場
合、品種積合せ可能基準を満たす。
In the case of stacking products of different types that can be shipped, the product type stackability criterion is satisfied.

【0044】異なる揚地の出願可能品を積合せる場
合、多港揚可能基準を満たす。
In the case of stacking feasible products from different landings, the multi-port landing standard is satisfied.

【0045】このような条件を全て満足するように、船
積ロットの船型やそれを構成する出荷可能品グループを
試行錯誤的な手法を用いて決定する。このような処理を
船積ロット編成機能91および推論エンジン98により
実行する。
In order to satisfy all of the above conditions, the shipping lot hull form and the shippable goods groups constituting the hull lot are determined by a trial and error method. Such processing is executed by the shipping lot organization function 91 and the inference engine 98.

【0046】次に、編成した各船積ロットに対し、揚地
待ち日数および積地最適出港時刻の算出して揚地待ち判
定を揚地待ち判定機能92および推論エンジン98によ
り行う(ステップS4)。
Next, with respect to each of the formed shipping lots, the number of waiting days for landing and the optimum departure time of the landing place are calculated, and the landing waiting judgment is made by the landing waiting judgment function 92 and the inference engine 98 (step S4).

【0047】図3はステップS4「揚地待ち判定」処理
の詳細な手順を示す処理フロー図である。
FIG. 3 is a processing flow chart showing the detailed procedure of the step S4 "discharging landing judgment" processing.

【0048】まず、揚地待ち判定を行う船積ロットを1
つ選択する(ステップS401)。
First, the loading lot for which landing waiting is determined is 1
Two are selected (step S401).

【0049】次に、積地の出港時刻を仮に設定し、揚地
までの航海時間を積揚地情報記憶部3と船舶情報記憶部
4の記憶情報に基き計算し、揚地への仮の入港時刻を求
める(ステップS402〜S404)。
Next, the departure time of the loading port is provisionally set, the voyage time to the landing is calculated based on the stored information in the loading land information storage unit 3 and the ship information storage unit 4, and the temporary departure time to the landing place is set. The arrival time is calculated (steps S402 to S404).

【0050】次に、荷役可能クレーン基準により、揚荷
役可能で優先順が1位のクレーンを選択する(ステップ
S405)。
Next, the crane capable of unloading and having the first priority is selected based on the loadable crane standard (step S405).

【0051】次に、船積ロットを構成している出荷可能
品の重量を荷役能率(計画基準情報記憶部5に記憶)で
割って足し合わせ、揚荷役時間を求める(ステップS4
06)。
Next, the weight of the deliverable composing the shipping lot is divided by the cargo handling efficiency (stored in the planning reference information storage unit 5) and added to obtain the cargo handling time (step S4).
06).

【0052】次に、揚荷役時間を揚地の標準稼働時間
(積揚地情報記憶部3に記憶)で割り、標準揚荷役日数
を求める(ステップS407)。
Next, the unloading time is divided by the standard operating time of the landing (stored in the loading land information storage unit 3) to obtain the standard unloading days (step S407).

【0053】次に、揚地の仮入港時刻より揚荷役を行っ
たときの揚荷役想定開始時刻および揚荷役想定終了時刻
を設定する(ステップS408)。
Next, the unloading estimated start time and the unloading estimated end time when the unloading operation is performed are set from the temporary arrival time of the landing place (step S408).

【0054】次に、開始−終了に設定した時間帯で、次
に示す各種の制約のチェックを積揚地情報記憶部3の格
納情報を用いて行う(ステップS409)。
Next, in the time zone set to start-end, various constraints described below are checked using the storage information of the loading land information storage unit 3 (step S409).

【0055】揚地の稼働日である。This is the working day of the landing site.

【0056】揚地の稼働時間帯である。This is the operating time zone of the landing site.

【0057】同じクレーンで他の荷役や修理が行われ
ていない。
No other cargo handling or repairs have been performed on the same crane.

【0058】同時に稼働できるクレーンの基数を満た
している。
The number of cranes that can be operated simultaneously is satisfied.

【0059】揚地倉庫が受入可能である。A landing warehouse is acceptable.

【0060】制約を満たさない場合、揚荷役想定開始時
刻および揚荷役想定終了時刻を後ろにずらし、再度チェ
ックを行う(ステップS411)。
If the constraint is not satisfied, the unloading estimated start time and the unloading estimated end time are shifted backward and checked again (step S411).

【0061】揚地の仮入港時刻から揚荷役想定終了時刻
までの所要日数を求め、想定揚荷役日数とする(ステッ
プS412)。
The number of days required from the temporary arrival time of the landing place to the estimated end time of the unloading operation is calculated and used as the estimated unloading day number (step S412).

【0062】想定揚荷役日数と標準揚荷役日数との差を
揚地待ち日数とする(ステップS413)。
The difference between the estimated unloading days and the standard unloading days is set as the landing waiting days (step S413).

【0063】揚地待ち日数が1日以上あり、未選択の揚
荷役可能クレーンが他にあれば、次に優先順が高いもの
を選択し(ステップS416)、同様の処理を行う。
If the number of days waiting for landing is one day or more and there are other unselected cranes capable of unloading, the crane having the next highest priority is selected (step S416), and the same processing is performed.

【0064】複数の荷役可能クレーンに対し、揚地待ち
日数の算出を行った場合、その最小値を揚地待ち日数と
して採用する(ステップS418)。
When the landing waiting days have been calculated for a plurality of loadable cranes, the minimum value is adopted as the landing waiting days (step S418).

【0065】次に、1港目の揚地の揚荷役想定開始時刻
から航海時間を引いて逆算した時刻を積地最適出港時刻
とする(ステップS420)。
Next, a time calculated by subtracting the voyage time from the estimated loading start time of the unloading land of the first port and calculating back is set as the optimum loading port departure time (step S420).

【0066】多港揚の船積ロットの場合は、2港目以降
の揚地についても同様の判定を行う。
In the case of a multi-port loading lot, the same determination is made for the landing after the second port.

【0067】全揚地についての判定終了後、各揚地の揚
地待ち日数を加え、トータルの揚地待ち日数を求める
(ステップS424)。
After the determination of all landings is completed, the number of days waiting for landing of each landing is added to obtain the total number of days waiting for landing (step S424).

【0068】未選択の船積ロットがある間、上記の処理
を繰り返す(図3のステップS401〜S425のルー
プ処理)。
The above processing is repeated while there is an unselected shipping lot (loop processing of steps S401 to S425 in FIG. 3).

【0069】編成した全船積ロットについて終了した場
合、船積ロット編成の終了判定に戻る(図2のステップ
S4→S2)。
When all the formed shipping lots have been finished, the process returns to the judgment of the end of the shipping lot formation (steps S4 → S2 in FIG. 2).

【0070】ここまでで、船積ロット編成基準量に達す
るか、可能なすべての船積ロットが編成される。
Up to this point, the shipping lot organization reference amount is reached or all possible shipping lots are organized.

【0071】編成した船積ロットの中で未選択のものが
ある間、バースプラン作成,船積ロット選択機能93お
よび推論エンジン98によりバースプラン作成を行う船
積ロットを次の優先順に1つ選択する(ステップS
6)。
While some of the organized shipping lots are unselected, one shipping lot for which a berth plan is to be created is selected by the berth plan creation / shipping lot selection function 93 and the inference engine 98 (step 1). S
6).

【0072】(1)出荷日の範囲が指定されており、計
画対象日がその最終日であるもの。
(1) A shipping date range is specified, and the planning target date is the final date.

【0073】(1a)出荷可能品の特性の優先順。(1a) Priority order of shippable product characteristics.

【0074】(2)(1)以外のもの。(2) Other than (1).

【0075】(2a)揚地待ち日数が少ないもの。(2a) The number of days waiting for landing is small.

【0076】(2aイ)1品種1港揚の輸送最適船型の
積載ロット。
(2a b) Transportation of one product, one port, optimal shipping type loading lot.

【0077】(2aロ)(2aイ)以外のもの。Other than (2a-b) and (2a-a).

【0078】これにより、出荷日の指定があるものはそ
れを守った上で、揚地待ちがなるべく少ない船積ロット
について後述のバースプランが作成される。また、揚地
待ちが同程度ならば、輸送最適船型が優先される。
As a result, after the shipment date is designated, the berth plan described later is prepared for the shipping lots with as few waiting lines as possible while keeping them. In addition, if waiting for landing is about the same, priority will be given to the optimal transport type.

【0079】次に、選択した船積ロットについて、積バ
ースプラン作成機能94および推論エンジン98により
積バースプランを作成する(ステップS7)。
Next, for the selected shipping lot, a product berth plan is created by the product berth plan creation function 94 and the inference engine 98 (step S7).

【0080】まず、計画基準情報記憶部5の荷役可能ク
レーン基準により、積荷役可能で優先順が最も高いクレ
ーンを1つ選択する。
First, one crane that can be loaded and has the highest priority is selected based on the loadable crane standard in the plan standard information storage unit 5.

【0081】次に、船積ロットを構成している出荷可能
品の重量を荷役能率で割って足し合わせ、積荷役時間を
求める。
Next, the weight of the deliverable composing the shipping lot is divided by the cargo handling efficiency and added to obtain the cargo handling time.

【0082】次に、積地最適出港時刻を積荷役終了時刻
とし、これから積荷役時間を引いた時刻を積荷役開始時
刻とする。
Next, the loading port optimal departure time is set as the loading end time, and the time obtained by subtracting the loading time from this is set as the loading start time.

【0083】次に、開始−終了に設定した時間帯で、次
に示す各種の制約のチェックを行う。
Next, in the time zone set to start-end, the following various constraints are checked.

【0084】同じクレーンで他の荷役や修理が行われ
ていない。
No other cargo handling or repairs have been performed on the same crane.

【0085】同時に稼働できるクレーンの基数を満た
している。
The number of cranes that can be operated simultaneously is satisfied.

【0086】制約を満たさない場合、積荷役開始時刻お
よび積荷役終了時刻を前にずらし、再度チェックを行
う。
When the constraint is not satisfied, the cargo handling start time and the cargo handling end time are shifted forward and the check is performed again.

【0087】繰り返しても、制約を満たせない場合、未
選択の積荷役可能クレーンが他にあれば、次に優先順が
高いものを選択し、同様の処理を行う。
When the constraint cannot be satisfied even after repeating, if there are other unselected loadable cranes, the one with the next highest priority is selected and the same processing is performed.

【0088】すべての積荷役可能クレーンで制約を満た
せない場合、選択した船積ロットを積バースプラン作成
失敗とする。
When the constraints cannot be satisfied with all the loadable cranes, the selected loading lot is regarded as a loading berth plan creation failure.

【0089】また、前にずらした時間が積荷役前倒し許
容基準時間を超えた場合も、他に積荷役可能クレーンが
あれば、そのクレーンで積バースプラン作成を試みる。
Also, when the forward shifted time exceeds the cargo handling advancing permissible reference time, if there is another loadable crane, that crane is used to try to create a load berth plan.

【0090】複数のクレーンで積バースプラン作成を行
った場合、前にずらした時間が最小のクレーンの結果を
積バースプランとして採用する。
When the product berth plan is created by using a plurality of cranes, the result of the crane having the minimum time shifted before is adopted as the product berth plan.

【0091】積バースプラン作成に失敗した場合、船積
ロットの選択に戻る(ステップS8)。
If the loading berth plan creation fails, the process returns to the selection of the shipping lot (step S8).

【0092】次に、積バースプラン作成した船積ロット
に対し、それを積載する船舶を積載船舶決定機能95お
よび推論エンジン98により割り当てる(ステップS
9)。
Next, to the shipping lot for which the loading berth plan has been created, the loading vessel is assigned by the loading vessel determination function 95 and the inference engine 98 (step S).
9).

【0093】まず、船舶情報記憶部4および船舶航海情
報記憶部8に記憶されている船舶の情報をもとに、次の
条件を満たす船を候補船として抽出する。
First, a ship satisfying the following conditions is extracted as a candidate ship based on the ship information stored in the ship information storage unit 4 and the ship navigation information storage unit 8.

【0094】積地への入港予定時刻が積荷役開始時刻
より早い。
The scheduled arrival time at the loading point is earlier than the loading start time.

【0095】船積ロットと同じ船型である。It has the same ship shape as the shipping lot.

【0096】船積ロットの品種が積載可能品種であ
る。
The types of shipping lots are the types that can be loaded.

【0097】積載ロットの揚地が航行可能地区にあ
る。
The landing site for the loading lot is in a navigable area.

【0098】次に、抽出した候補船の中で、まだ他の船
積ロットに割り付いていないものを選択し、上記の船積
ロットに割り付ける。
Next, of the extracted candidate vessels, those which have not yet been assigned to other loading lots are selected and assigned to the above loading lots.

【0099】全候補船が他に割付済の場合は、他の船積
ロットに割り付けた船を別の船に入れ換えて、船を割り
付けられないか試みる。入れ換えができない、または、
候補船が1隻もない場合は、積載船舶決定失敗とする。
積載船舶決定に失敗した場合、作成した積バースプラン
を解消し、船積ロット選択に戻る(ステップS10)。
If all the candidate vessels have already been assigned, the vessel assigned to another shipping lot is replaced with another vessel and an attempt is made to assign the vessel. Cannot be replaced, or
If there is no candidate vessel, the decision on loading vessel is unsuccessful.
When the decision of the loading vessel fails, the created loading berth plan is canceled and the process returns to the loading lot selection (step S10).

【0100】次に、上記の船積ロットについて、揚バー
スプラン作成機能96および推論エンジン98により揚
バースプランを作成する(ステップS11)。
Next, for the above-mentioned shipping lot, a lifting berth plan is created by the lifting berth plan creating function 96 and the inference engine 98 (step S11).

【0101】まず、積荷役終了時刻に積揚地間の航海時
間を加え、揚地入港時刻を求める。
First, the voyage time between loading ports is added to the loading end time to obtain the loading port entry time.

【0102】以下、「揚地待ち判定」とほぼ同様の処理
を行い、揚荷役を行うクレーン、揚荷役開始時刻、揚荷
役終了時刻を決定する。揚バースプランの作成結果にも
とづき、揚地待ち日数を求め直す。
Hereinafter, almost the same processing as the "waiting landing determination" is performed to determine the crane to perform unloading, the unloading start time, and the unloading end time. Recalculate the number of days to wait for landing based on the results of the landing berth plan.

【0103】次に、上記の結果揚地待ち日数の評価を揚
地待ち評価機能97および推論エンジン98により行う
(ステップS12)。
Next, the above-mentioned number of days for waiting landing as a result is evaluated by the landing waiting evaluation function 97 and the inference engine 98 (step S12).

【0104】図2のステップS4の「揚地待ち判定」処
理で求めた揚地待ち日数は、計画作成前の状況のもとで
求めたものであり、実際にバースプランを作成しようと
すると、積地や揚地での船積ロットの競合により、判定
どおりに作成できるとは限らない。そこで、揚地待ち日
数を揚バースプラン作成結果のものと比較し、揚地待ち
日数が増加している場合、積揚バースプランと割り付け
た船舶を解消し、船舶ロット選択に戻る(ステップS1
3)。
The number of days to wait for landing obtained in the "landing wait determination" process of step S4 in FIG. 2 is obtained under the conditions before the plan is made, and when actually making a berth plan, Due to competition of shipping lots at loading and unloading sites, it may not always be possible to create according to the judgment. Therefore, the number of days waiting for landing is compared with the number of days waiting for landing, and if the number of days waiting for landing is increasing, the loading berth plan and the allocated ship are canceled, and the process returns to ship lot selection (step S1).
3).

【0105】このとき、当該船積ロットは、現地待ち日
数を揚バースプラン作成結果のものに更新し、バースプ
ラン作成船積ロット選択で再度対象となるようにする。
At this time, the shipping lot is updated with the number of days waiting on site to be the result of the preparation of the lifting berth plan so that the shipping lot can be targeted again when the shipping lot is selected.

【0106】これにより、他に揚地待ちの少ない船積ロ
ットがあれば、そちらが優先的に計画作成される。
As a result, if there are other loading lots with less waiting for landing, those lots are preferentially planned.

【0107】一方、揚地待ち日数が増加していなけれ
ば、当該船積ロットの計画は成立とし、バースプラン作
成船積ロット選択に戻り、次の船積ロットの計画作成を
行う。
On the other hand, if the number of days waiting for landing has not increased, the plan for the relevant loading lot is established, the process returns to the berth plan creation loading lot selection, and the planning for the next loading lot is performed.

【0108】ここまでで、ひととおり船積ロット、積揚
荷役、船舶の計画が作成される。
Up to this point, plans for loading lots, loading and unloading, and ships are created.

【0109】次に、作成した船積ロット、船舶、バース
プランの調整を行う(ステップS14)。
Next, the prepared shipping lot, ship and berth plan are adjusted (step S14).

【0110】まず、よりより船積ロットと船舶の組合せ
があれば、そうなるように船積ロットに割り付けた船舶
の入れ換えを行い、船積ロットと船舶の割り付けを確定
する。
First, if there are more combinations of shipping lots and ships, the ships assigned to the shipping lots are replaced so as to do so, and the allocation of the shipping lots and ships is confirmed.

【0111】次に、各船舶固有の積載可能重量に合わせ
船積ロットの積荷の調整を行い、船積ロットを確定す
る。
Next, the loading of the shipping lot is adjusted according to the loadable weight peculiar to each ship, and the shipping lot is determined.

【0112】最後に、荷役時間帯の前にクレーンの空き
があれば、前に詰め、バースプランを確定する。
Finally, if there is a vacant crane before the cargo handling time zone, the crane is packed before the berth plan is confirmed.

【0113】最後に、作成した船積ロット、積揚荷役、
船舶運航の計画結果を、船積ロット情報記憶部、積揚荷
役情報記憶部、船舶航海情報記憶部に格納する。
Finally, the created shipping lot, loading / unloading operation,
The plan result of the ship operation is stored in the shipping lot information storage unit, the loading / unloading information storage unit, and the ship navigation information storage unit.

【0114】これにより、船積ロット、船舶運航計画、
積揚荷役計画を一貫した計画の作成が完了する。
As a result, the shipping lot, the ship operation plan,
Completion of a consistent plan for the loading and unloading plan.

【0115】以上、説明したように本実施例では船積ロ
ット、積載船舶、積揚バースプランで構成される全体輸
送計画の作成において、予め定めた条件を満足する船積
ロットを多数編成し、これらの中から選択することによ
り揚地待ち回数が最小となる計画立案要素が決定され
る。の組み合わせや積載船舶等の計画立案要素と選択し
た後、これら選択したものの中から揚地待ち日数が最少
となる計画立案要素が決定される。
As described above, in the present embodiment, in the creation of the entire transportation plan including the shipping lot, the loading ship, and the loading berth plan, a large number of shipping lots satisfying the predetermined conditions are organized and these By selecting from among them, the planning element that minimizes the number of landing waits is determined. After selecting a planning element such as a combination of ships and loading vessels, a planning element that minimizes the number of days to wait for landing is determined from these selected elements.

【0116】なお、参考のために特許請求の範囲の記載
と実施例の記述との対応関係を簡単説明しておく。請求
項1の構成要件は、図1の各機能91〜97および推論
エンジン98の組み合せにそれぞれ対応する。
For reference, the correspondence between the claims and the examples will be briefly described. The constituent features of claim 1 correspond to combinations of the respective functions 91 to 97 and the inference engine 98 of FIG.

【0117】また請求項2の総合評価基準が揚地待ち日
数に対応する。
Further, the comprehensive evaluation criterion of claim 2 corresponds to the number of days waiting for landing.

【0118】[0118]

【発明の効果】以上説明したように、請求項1の発明に
よれば、一定以上の積載率をもつ船積ロットを多数編成
し、それぞれについて揚地における待ち時間を判定し、
待ちの少ないものから優先的に、積揚荷役計画、船舶運
航計画を作成するので、全体的に積載率が高く、揚地に
おける待ち時間の少ない、効率的な輸送計画が作成でき
る。これにより、従来、各積地・揚地で担当者が多大な
負荷をかけて個別に行っていた計画の作成が、積地にお
ける1日分を20分程度で行うことが可能になった。
As described above, according to the invention of claim 1, a large number of loading lots having a loading rate above a certain level are organized, and the waiting time at the landing is determined for each.
Since the loading and unloading plan and the ship operation plan are created with priority from the one with the least waiting time, it is possible to create an efficient transportation plan with a high overall loading rate and a short waiting time at the landing site. As a result, it is now possible to create a plan that a person in charge of each loading and unloading place had to do with a large load individually in the past in about 20 minutes for one day at the loading land.

【0119】さらに請求項2の発明では各小計画の中で
は最適ではないにしても最適に近い船舶と船積ロットの
組み合わせが得られると共に、その組み合わせが総合的
に最適となるため、実際の輸送に際し無理なく円滑に輸
送を実施できる。
Further, according to the invention of claim 2, a combination of the ship and the loading lot which is close to the optimum but not optimum in each sub-plan can be obtained, and the combination is comprehensively optimized, so that the actual transportation is performed. In this case, the transportation can be smoothly carried out without difficulty.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明の一実施例である船舶による輸送計画作
成装置の機能ブロック図である。
FIG. 1 is a functional block diagram of an apparatus for creating a transportation plan by a ship, which is an embodiment of the present invention.

【図2】図1に示す輸送計画作成装置の動作の概要を示
すフローチャートである。
FIG. 2 is a flowchart showing an outline of an operation of the transportation plan creation device shown in FIG.

【図3】図2に示す「揚地待ち判定」の詳細な内容を示
すフローチャートである。
FIG. 3 is a flowchart showing detailed contents of “awaiting landing determination” shown in FIG.

【符号の説明】[Explanation of symbols]

1 計画対象日情報記憶部 2 出荷可能品情報記憶部 3 積揚地情報記憶部 4 船舶情報記憶部 5 計画基準情報記憶部 6 船積ロット情報記憶部 7 積揚荷役情報記憶部 8 船舶航海情報記憶部 9 輸送計画(作成)部 91 船積ロット編成機能 92 揚地待ち判定機能 93 バースプラン作成船積ロット選択機能 94 積バースプラン作成機能 95 積載船舶決定機能 96 揚バースプラン作成機能 97 揚地待ち評価機能 1 Plan target date information storage unit 2 Shipable item information storage unit 3 Landing site information storage unit 4 Ship information storage unit 5 Planning standard information storage unit 6 Shipping lot information storage unit 7 Loading / unloading information storage unit 8 Ship navigation information storage Part 9 Transport Plan (Preparation) Part 91 Shipping Lot Organizing Function 92 Landing Wait Judgment Function 93 Berth Plan Creation Shipping Lot Selection Function 94 Loading Berth Plan Creation Function 95 Loading Ship Decision Function 96 Lifting Berth Plan Creation Function 97 Landing Wait Evaluation Function

───────────────────────────────────────────────────── フロントページの続き (72)発明者 ▲高▼ 友吾 東京都千代田区内幸町2丁目2番3号 川 崎製鉄株式会社内 (72)発明者 鈴木 和夫 東京都千代田区内幸町2丁目2番3号 川 崎製鉄株式会社内 (72)発明者 桧山 直 東京都江東区豊洲三丁目3番3号 川鉄シ ステム開発株式会社内 (72)発明者 安原 征紀夫 兵庫県神戸市中央区北本町通1丁目1番23 号 川鉄運輸株式会社内 (72)発明者 武中 良太 兵庫県神戸市中央区北本町通1丁目1番23 号 川鉄運輸株式会社内 ─────────────────────────────────────────────────── ─── Continuation of the front page (72) Inventor ▲ High ▼ Yugo 2-3 2-3 Uchisaiwaicho, Chiyoda-ku, Tokyo Within Kawasaki Steel Works (72) Inventor Kazuo Suzuki 2-2, Uchisaiwaicho, Chiyoda-ku, Tokyo No. 3 in Kawasaki Steel Co., Ltd. (72) Inventor Nao Hiyama No. 3-3 Toyosu, Koto-ku, Tokyo No. 3 in Kawatetsu System Development Co., Ltd. (72) Inventor Seikio Yasuhara Dori Kitahonmachi, Chuo-ku, Kobe-shi, Hyogo 1-21-2 Kawatetsu Transport Co., Ltd. (72) Inventor, Ryota Takenaka 1-2-23 Kitahonmachi-dori, Chuo-ku, Kobe-shi, Hyogo Prefecture Kawatetsu Transport Co., Ltd.

Claims (2)

【特許請求の範囲】[Claims] 【請求項1】 出荷可能品を積合せ可能な条件を考慮し
て一船分の重量にまとめた船積ロットを複数編成する船
積ロット編成手段と、 当該編成した各船積ロットに対し、揚地において想定さ
れる待ち時間と、該揚地から逆算した積地の最適出港時
刻とを求める揚地待ち判定手段と、 前記編成した船積ロットを出荷必要性と前記揚地におけ
る待ち時間の少なさによる優先順に1つずつ選択するバ
ースプラン作成船積ロット選択手段と、 当該選択した船積ロットをできるだけ積地の最適出港時
刻に合わせた時間帯で荷役する積荷役計画を作成する積
バースプラン作成手段と、 前記船積ロットに対し、それを輸送可能で、入港が積開
始に間に合う船舶を割り付ける積載船舶決定手段と、 前記船積ロットと船舶に対し、航海時間を計算し、揚地
における揚荷役計画を作成する揚バースプラン作成手段
と、 該バースプラン作成手段の作成結果における揚地待ち時
間を評価し、想定よりも待ちが大きい場合にバースプラ
ンを解消し、船積ロットの選択をやり直す揚地待ち評価
手段と、を有することを特徴とする輸送計画作成装置。
1. A loading lot organization means for organizing a plurality of loading lots into a weight for one vessel in consideration of a condition in which deliverable products can be loaded, and each loading lot that has been organized at the landing site. A landing waiting determination means for obtaining an estimated waiting time and an optimum departure time of the loading land calculated back from the landing, and priority due to the necessity of shipping the formed shipping lot and the short waiting time at the landing A berth plan creation loading lot selection means for selecting one by one in order, and a loading berth plan creation means for creating a loading and unloading plan for loading the selected shipping lots in a time zone that matches the optimum departure time of the loading place as much as possible, Loading vessel determination means for allocating a vessel capable of transporting it to a loading lot and arriving at the port in time to start loading, and calculating a voyage time for the loading lot and the vessel to arrive at the landing site. The unloading berth plan creating means for creating an unloading plan and the waiting time for landing in the creation result of the berth plan creating means are evaluated. If the waiting time is longer than expected, the berth plan is canceled and the shipping lot is selected. A transportation plan creation device comprising: a landing waiting evaluation means for redoing.
【請求項2】 積地から揚地まで船舶により出荷可能品
を輸送する輸送計画をコンピュータにより作成する輸送
計画作成方法において、 前記輸送計画を船積ロット編成計画、積バースプラン、
船舶の運航計画、揚バースプランからなる複数の小計画
で構成し、 前記複数の小計画のそれぞれについて、立案条件を予め
定めておき、 前記コンピュータは当該立案条件を全て満足する船舶お
よび船積ロットの組み合わせを取得し、 当該組み合わせの中から、予め定めた総合評価基準に最
も合致する船舶および船積ロットの組合わせを輸送計画
の立案要素と決定することを特徴とする輸送計画作成方
法。
2. A transportation plan creation method for creating a transportation plan for transporting shippable goods by a ship from a loading place to a landing place by a computer, wherein the transportation plan is a shipping lot formation plan, a loading berth plan,
It consists of a plurality of small plans consisting of a ship operation plan and a lifting berth plan. For each of the plurality of small plans, a planning condition is set in advance, and the computer determines the ships and shipping lots that satisfy all the planning conditions. A method for preparing a transportation plan, which comprises acquiring a combination and determining, from the combination, a combination of a ship and a loading lot that most closely matches a predetermined comprehensive evaluation criterion as a planning element of the transportation plan.
JP9506794A 1994-05-09 1994-05-09 Device and method for preparing transport plan Withdrawn JPH07302285A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP9506794A JPH07302285A (en) 1994-05-09 1994-05-09 Device and method for preparing transport plan

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP9506794A JPH07302285A (en) 1994-05-09 1994-05-09 Device and method for preparing transport plan

Publications (1)

Publication Number Publication Date
JPH07302285A true JPH07302285A (en) 1995-11-14

Family

ID=14127665

Family Applications (1)

Application Number Title Priority Date Filing Date
JP9506794A Withdrawn JPH07302285A (en) 1994-05-09 1994-05-09 Device and method for preparing transport plan

Country Status (1)

Country Link
JP (1) JPH07302285A (en)

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2001075709A1 (en) * 2000-03-31 2001-10-11 Marinenet Co., Ltd. Tramper matching method
WO2002016236A1 (en) * 2000-08-25 2002-02-28 Mitsui & Co., Ltd. Ship assigning business managing system
KR100474134B1 (en) * 2002-02-20 2005-03-08 (주)토탈소프트뱅크 Scheduling method for loading and unloading containers at the terminal and programming of the same recorded on a computer accessible recording medium
WO2006003708A1 (en) * 2004-07-02 2006-01-12 Yasunobu Abe System for assisting ship cargo handling practice
JP2006111387A (en) * 2004-10-14 2006-04-27 Kobe Steel Ltd Raw material ship sailing plan device, raw material ship sailing plan method, and program
JP2009227354A (en) * 2008-03-19 2009-10-08 Jfe Steel Corp Method and device for making shipping lot
JP2011201657A (en) * 2010-03-25 2011-10-13 Jfe Steel Corp Method, system and program for preparing shipping plan
JP2012020839A (en) * 2010-07-15 2012-02-02 Jfe Steel Corp Method and system of creating transportation plan for steel product by ship
JP2012086948A (en) * 2010-10-20 2012-05-10 Jfe Steel Corp Transportation plan preparation method and transportation plan preparation device
JP2014119356A (en) * 2012-12-17 2014-06-30 Taisei Corp Marine navigation simulation device
KR101417518B1 (en) * 2012-12-27 2014-07-08 주식회사 포스코 System and method for modifying supply and demand plan of steel raw material and fuel
WO2015045236A1 (en) * 2013-09-30 2015-04-02 出光興産株式会社 Ship-allocation-plan generation device and ship-allocation-plan generation method

Cited By (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2001075709A1 (en) * 2000-03-31 2001-10-11 Marinenet Co., Ltd. Tramper matching method
WO2002016236A1 (en) * 2000-08-25 2002-02-28 Mitsui & Co., Ltd. Ship assigning business managing system
KR100474134B1 (en) * 2002-02-20 2005-03-08 (주)토탈소프트뱅크 Scheduling method for loading and unloading containers at the terminal and programming of the same recorded on a computer accessible recording medium
WO2006003708A1 (en) * 2004-07-02 2006-01-12 Yasunobu Abe System for assisting ship cargo handling practice
JP4498878B2 (en) * 2004-10-14 2010-07-07 株式会社神戸製鋼所 Raw material ship allocation planning apparatus, raw material ship allocation planning method, and program
JP2006111387A (en) * 2004-10-14 2006-04-27 Kobe Steel Ltd Raw material ship sailing plan device, raw material ship sailing plan method, and program
JP2009227354A (en) * 2008-03-19 2009-10-08 Jfe Steel Corp Method and device for making shipping lot
JP2011201657A (en) * 2010-03-25 2011-10-13 Jfe Steel Corp Method, system and program for preparing shipping plan
JP2012020839A (en) * 2010-07-15 2012-02-02 Jfe Steel Corp Method and system of creating transportation plan for steel product by ship
JP2012086948A (en) * 2010-10-20 2012-05-10 Jfe Steel Corp Transportation plan preparation method and transportation plan preparation device
JP2014119356A (en) * 2012-12-17 2014-06-30 Taisei Corp Marine navigation simulation device
KR101417518B1 (en) * 2012-12-27 2014-07-08 주식회사 포스코 System and method for modifying supply and demand plan of steel raw material and fuel
WO2015045236A1 (en) * 2013-09-30 2015-04-02 出光興産株式会社 Ship-allocation-plan generation device and ship-allocation-plan generation method
JP2015067427A (en) * 2013-09-30 2015-04-13 出光興産株式会社 Shipping plan creation device and shipping plan creation method

Similar Documents

Publication Publication Date Title
US8626540B2 (en) Method and apparatus for transportation planning based on mission-specific vehicle capacity constraints
JP3161529B2 (en) Vehicle dispatching equipment
Güven et al. Trip allocation and stacking policies at a container terminal
EP1909221A1 (en) Container vessel stowage planning
JPH07302285A (en) Device and method for preparing transport plan
CN111144806B (en) Automatic loading method for dangerous goods container
KR102604656B1 (en) System for repositioning optimization of empty container in ship network based artificial intelligence planning technology and method therefor
JP5728881B2 (en) Transportation plan creation method and transportation plan creation device
JP5272534B2 (en) Ship operation plan creation method and apparatus
JP6065866B2 (en) Transportation loading plan creation method and transportation loading plan creation device
JP6468235B2 (en) Ship allocation plan creation method, steelworks operation method, and ship allocation plan creation device
KR100389076B1 (en) Method for dispatching a transporter of a port container terminal
JP5532542B2 (en) Shipping lot creation method and apparatus
WO2022013966A1 (en) Container storage planning device, container storage planning system, and container storage planning method
CN115258482A (en) Warehouse-out control method, electronic device, readable storage medium and warehouse-out system
CN113780938A (en) Greedy algorithm-based overseas warehouse vehicle and goods matching strategy and system
JPH09267918A (en) Method and device for preparing ship cargo handling in plan container terminal
Sahun Perspective directions of artificial intelligence systems in aircraft load optimization process
JP4940602B2 (en) Transportation lot creation apparatus and method
JP5659590B2 (en) Transportation planning method and system for steel products by ship
TW201528202A (en) Ship-allocation-plan generation device and ship-allocation-plan generation method
Hamedi Containership load planning with crane operations
JP5703577B2 (en) Ship assignment plan creation method, ship assignment plan creation system, and ship assignment plan creation program
Wang et al. A Decision-support Framework for Port Container Stowage Plan
JP2012148896A (en) System and program for preparaing delivery plan

Legal Events

Date Code Title Description
A300 Application deemed to be withdrawn because no request for examination was validly filed

Free format text: JAPANESE INTERMEDIATE CODE: A300

Effective date: 20010731