JPH07296060A - Work instruction book issuing device - Google Patents
Work instruction book issuing deviceInfo
- Publication number
- JPH07296060A JPH07296060A JP9262594A JP9262594A JPH07296060A JP H07296060 A JPH07296060 A JP H07296060A JP 9262594 A JP9262594 A JP 9262594A JP 9262594 A JP9262594 A JP 9262594A JP H07296060 A JPH07296060 A JP H07296060A
- Authority
- JP
- Japan
- Prior art keywords
- time
- work
- production
- product
- data
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000004519 manufacturing process Methods 0.000 claims abstract description 108
- 238000003860 storage Methods 0.000 claims description 10
- 238000002360 preparation method Methods 0.000 description 12
- 238000010586 diagram Methods 0.000 description 8
- 238000000034 method Methods 0.000 description 8
- 230000005540 biological transmission Effects 0.000 description 4
- 230000015654 memory Effects 0.000 description 3
- 238000004891 communication Methods 0.000 description 2
Classifications
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02P—CLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
- Y02P90/00—Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
- Y02P90/30—Computing systems specially adapted for manufacturing
Landscapes
- General Factory Administration (AREA)
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Abstract
Description
【0001】[0001]
【産業上の利用分野】この発明は、生産計画情報に基づ
いて、生産日時に対応して、生産する各製品毎に生産数
量等の作業指示の情報を印字した作業指示書を発行する
作業指示書発行装置に関する。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention is based on production plan information, and issues work instructions for printing work instruction information such as production quantity for each product to be produced, corresponding to the production date and time. Regarding the book issuing device.
【0002】[0002]
【従来の技術】従来の作業指示書発行装置は、生産日、
製品名、生産台数を印字した作業指示書を発行してい
た。2. Description of the Related Art A conventional work order issuing device is
It issued a work order that printed the product name and the number of units produced.
【0003】例えば、生産日の前日に作業指示書は発行
され、その作業指示書には、生産日と、その生産日( 1
日 )で生産する全ての製品について各製品毎にその製品
名とその生産台数とを印字していた。For example, a work order is issued the day before the production date, and the work order includes the production date and the production date (1
For all products manufactured in Japan, the product name and the number of units produced were printed for each product.
【0004】生産管理者は、この作業指示書にしたがっ
て生産ラインでの製品の生産を管理していた。The production manager manages the production of products on the production line according to this work instruction.
【0005】[0005]
【発明が解決しようとする課題】上述したように、従来
の作業指示書発行装置は、作業指示書に、その生産日に
生産する全ての製品について各製品毎にその製品名とそ
の生産台数しか印字されないため、生産管理者は、その
作業指示書を見ても、各製品の作業( 生産 )進捗状況に
ついて判断できないという問題があった。As described above, in the conventional work instruction sheet issuing apparatus, the work instruction sheet includes only the product name and the number of units produced for each product produced on the production date. Since it is not printed, the production manager cannot judge the work (production) progress of each product even by looking at the work instruction sheet.
【0006】すなわち、生産日一日のうちに複数の製品
を生産する場合に、作業指示書を見て、各製品毎に作業
開始予定時刻又は作業終了予定時刻を知ることができれ
ば、各製品の作業進捗状況を簡単に判断することができ
る。That is, when a plurality of products are produced within one day on the production day, if the work start scheduled time or the work finished scheduled time can be known for each product by looking at the work instruction sheet, The work progress status can be easily determined.
【0007】そこでこの発明は、生産日一日のうちの生
産する各製品毎に、作業開始予定時刻又は作業終了予定
時刻の少なくとも一方が印字された作業指示書を発行す
ることができる作業指示書発行装置を提供することを目
的とする。Therefore, the present invention is capable of issuing a work instruction sheet in which at least one of the scheduled work start time and the scheduled work end time is printed for each product to be produced within one day of the production day. It is intended to provide an issuing device.
【0008】[0008]
【課題を解決するための手段】この発明は、各製品毎に
その製品を単位数量生産するのに要する基準生産時間を
記憶した基準生産時間記憶手段と、この基準生産時間記
憶手段に記憶された基準生産時間に基づいて、製品毎に
その生産数量を設定した生産計画情報の各製品につい
て、この生産計画情報でそれぞれ設定された生産数量分
生産するのに必要な生産時間を算出し、各製品の生産の
作業開始予定時刻又は作業終了予定時刻の少なくとも一
方を求め、各製品毎に、その生産数量及びその生産の作
業開始予定時刻又は作業終了予定時刻の少なくとも一方
を印字した作業指示書を発行する指示書発行手段とを設
けたものである。According to the present invention, a standard production time storage means for storing a standard production time required to produce a unit quantity of each product for each product, and the standard production time storage means are stored. Based on the standard production time, for each product in the production plan information that sets the production quantity for each product, calculate the production time required to produce the production quantity set in this production plan information, and calculate each product At least one of the scheduled work start time or the scheduled work end time of the production is obtained, and a work instruction sheet is printed for each product, and the production quantity and at least one of the scheduled work start time or the scheduled work end time of the production are printed. And a means for issuing an instruction sheet.
【0009】[0009]
【作用】このような構成の本発明において、基準生産時
間記憶手段には、各製品毎にその製品を単位数量分生産
するのに要する基準生産時間が記憶されている。In the present invention having such a structure, the standard production time storage means stores, for each product, the standard production time required to produce a unit quantity of the product.
【0010】指示書発行手段は、基準生産時間記憶手段
に記憶された基準生産時間に基づいて、生産計画情報の
各製品を生産計画情報で定められた生産数量分生産する
のに必要な生産時間を算出し、この各製品の生産時間に
基づいて各製品の生産の作業開始予定時刻又は作業終了
予定時刻の少なくとも一方を求め、各製品毎に、生産数
量及び作業開始予定時刻又は作業終了予定時刻の少なく
とも一方を印字した作業指示書を発行する。The instruction book issuing means produces the production time required for producing each product of the production plan information by the production quantity determined by the production plan information based on the reference production time stored in the reference production time storage means. Is calculated, and at least one of the scheduled work start time and the scheduled work end time of the production of each product is calculated based on the production time of each product, and the production quantity and the scheduled work start time or the scheduled work end time are calculated for each product. Issue a work instruction sheet that prints at least one of the above.
【0011】[0011]
【実施例】以下、この発明の一実施例を図面を参照して
説明する。DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS An embodiment of the present invention will be described below with reference to the drawings.
【0012】図1は、この発明を適用した作業指示書発
行装置の要部回路構成を示すブロック図である。FIG. 1 is a block diagram showing a circuit configuration of a main part of a work instruction sheet issuing device to which the present invention is applied.
【0013】1は、制御部本体を構成するCPU(centr
al processing unit) である。このCPU1が行う処理
のプログラムデータが記憶されたROM(read only mem
ory)2、前記CPU1が処理を行うときに使用する各種
メモリのエリアが形成されたRAM(random access mem
ory)3、基準生産時間記憶手段としての製品マスタ4や
生産計画ファイル( 図1では図示せず )等の各種データ
ファイルが記憶されたフロッピーディスク5とのデータ
の伝送制御を行うフロッピーディスクインターフェイス
6、ホストコンピュータと回線を介してデータの伝送制
御を行う通信インターフェイス7は、それぞれシステム
バス8を介して前記CPU1と接続されている。Reference numeral 1 is a CPU (centr
al processing unit). A ROM (read only mem) in which program data for processing performed by the CPU 1 is stored
ory) 2, RAM (random access mem) in which areas of various memories used when the CPU 1 performs processing are formed.
ory) 3, a product master 4 as a standard production time storage means, and a floppy disk interface 6 for controlling data transmission with a floppy disk 5 in which various data files such as a production plan file (not shown in FIG. 1) are stored. A communication interface 7 for controlling data transmission via a host computer and a line is connected to the CPU 1 via a system bus 8, respectively.
【0014】さらに、前記CPU1は前記システムバス
8を介して、キーボード9とのデータの伝送制御を行う
キーボードインターフェイス10、CRT( cathode ra
ytube )ディスプレイ11を制御するCRTコントロー
ラ12、作業指示書を印字するプリンタ13とのデータ
の伝送制御を行うプリンタインターフェイス14とも接
続されている。Further, the CPU 1 has a keyboard interface 10 for controlling data transmission with a keyboard 9 via the system bus 8 and a CRT (cathode ra).
ytube) A CRT controller 12 for controlling the display 11 and a printer interface 14 for controlling data transmission with a printer 13 for printing work instructions are also connected.
【0015】図2は、前記製品マスタ4の要部のメモリ
構成を示す図である。FIG. 2 is a diagram showing a memory configuration of a main part of the product master 4.
【0016】この製品マスタ4には、1日の作業開始時
刻、休憩開始時刻、休憩終了時刻等の時刻データが記憶
されていると共に、各製品名毎に、該当する製品1台を
生産するのに必要な作業時間としての基準生産時間デー
タ及び作業を開始するための準備に必要な作業時間とし
ての準備時間データが記憶されている。The product master 4 stores time data such as work start time, break start time, break end time, etc. for one day, and produces one corresponding product for each product name. The standard production time data as the work time necessary for and the preparation time data as the work time required for preparation for starting the work are stored.
【0017】図3は、前記フロッピーディスク5に記憶
された生産計画ファイルの構成を示す図である。FIG. 3 is a diagram showing the structure of the production planning file stored in the floppy disk 5.
【0018】この生産計画ファイルは、各作業日の各製
品名毎に、該当する製品の生産台数が設定され、例えば
ホストコンピュータから回線を介して前記通信インター
フェイス7で受信されるか又は、前記キーボード9によ
り直接入力される。In this production plan file, the production quantity of the corresponding product is set for each product name on each work day, and is received by the communication interface 7 from a host computer via a line, for example, or by the keyboard. Directly input by 9.
【0019】なお、この生産計画ファイルを記憶する記
憶媒体としては、フロッピーディスク5に限定されるも
のではなく、例えばRAM3やハードディスク装置( 図
示せず )でも良いものである。The storage medium for storing the production plan file is not limited to the floppy disk 5, but may be, for example, the RAM 3 or a hard disk device (not shown).
【0020】図4は、前記CPU1が行う作業指示書発
行処理の流れを示す図である。FIG. 4 is a diagram showing the flow of the work instruction document issuing process performed by the CPU 1.
【0021】まず、RAM3に形成された格納エリア
「ワーク時刻」( 図示せず )に、製品マスタ4に記憶さ
れた1日の作業開始時刻データを設定する。First, the work start time data for one day stored in the product master 4 is set in a storage area "work time" (not shown) formed in the RAM 3.
【0022】次に、キーボード9による作業日の入力が
行われるまでの待機状態となり、作業日の入力が行われ
ると、ステップ1( ST1 )の処理として、フロッピー
ディスク5に記憶された生産計画ファイルから、キーボ
ード9により入力された作業日の対象となる生産計画デ
ータ( 生産計画情報 )の全ての読取りが終了したか否か
を判断する。Next, a standby state is entered until the work day is input using the keyboard 9, and when the work day is input, the production plan file stored in the floppy disk 5 is processed as step 1 (ST1). From this, it is determined whether or not all reading of the production plan data (production plan information) which is the target of the work day and which is input by the keyboard 9 is completed.
【0023】ここで、対象となる生産計画データの全て
の読取りが終了したと判断されれば、この時設定されて
いる製品名、生産台数、作業開始時刻( 作業開始予定時
刻 )、作業終了時刻( 作業終了予定時刻 )に基づいて、
プリンタ13により作業指示書を印字して発行する。If it is determined that all the target production planning data has been read, the product name, the number of units produced, the work start time (scheduled work start time), and the work end time set at this time are determined. Based on (scheduled work end time)
The printer 13 prints and issues a work instruction sheet.
【0024】また、対象となる生産計画データの全ての
読取りが終了していないと判断されれば、生産計画ファ
イルから残っている生産計画データのうち1つの製品に
ついてのデータを読取り、この読取ったデータとして設
定されている製品名及び生産台数のデータをRAM3に
形成されたプリントバッファ( 図示せず )に設定する。If it is determined that all of the target production planning data has not been read, the data of one product among the remaining production planning data is read from the production planning file and read. The data of the product name and the number of products produced, which are set as data, are set in a print buffer (not shown) formed in the RAM 3.
【0025】次に、この読取ったデータの製品名に該当
する基準生産時間及び準備時間を製品マスタ4から読取
る。Next, the standard production time and the preparation time corresponding to the product name of the read data are read from the product master 4.
【0026】次に、ワーク時刻に設定されている時刻デ
ータをプリントバッファに作業開始時刻として設定す
る。Next, the time data set as the work time is set as the work start time in the print buffer.
【0027】次に、製品マスタ4から読取った基準生産
時間及び準備時間に基づいて、作業終了時刻を算出し、
この算出した作業終了時刻をプリントバッファに設定す
る。なお、作業終了時刻の算出は、ワーク時刻に設定さ
れている時刻データ( 作業開始時刻 )に基準生産時間に
生産台数を乗算した結果を加算し、さらに、この加算結
果に準備時間を加算して得る。すなわち、作業終了時刻
=作業開始時刻+( 基準生産時間×生産台数 )+準備時
間という式により算出する。Next, the work end time is calculated based on the standard production time and the preparation time read from the product master 4,
The calculated work end time is set in the print buffer. To calculate the work end time, add the result of multiplying the standard production time by the number of production units to the time data set for the work time (work start time), and then add the preparation time to this addition result. obtain. That is, the work end time = work start time + (standard production time × production quantity) + preparation time.
【0028】次に、作業開始時刻( ワーク時刻に設定さ
れた時刻データ )が製品マスタ4に記憶されている休憩
開始時刻より小さい、すなわち作業開始時刻が休憩開始
時刻より早いか否かを判断し、ここで作業開始時刻が休
憩開始時刻以上、すなわち作業開始時刻が休憩開始時刻
より遅い( 基本的に等しいことはない )と判断されれ
ば、後述するステップ2( ST2 )の処理に移行するよ
うになっている。Next, it is judged whether or not the work start time (time data set to the work time) is smaller than the break start time stored in the product master 4, that is, the work start time is earlier than the break start time. If the work start time is equal to or longer than the break start time, that is, if the work start time is later than the break start time (basically not equal to each other), the process proceeds to step 2 (ST2) described later. It has become.
【0029】また、作業開始時刻が休憩開始時刻より小
さいと判断されれば、上述したように算出・設定された
作業終了時刻が製品マスタ4に記憶されている休憩開始
時刻より大きい、すなわち作業終了時刻が休憩開始時刻
より遅いか否か判断する。ここで、作業終了時刻が休憩
開始時刻以下、すなわち作業終了時刻が休憩開始時刻よ
り早いと判断されれば、ステップ2の処理に移行するよ
うになっている。If it is determined that the work start time is smaller than the break start time, the work end time calculated and set as described above is larger than the break start time stored in the product master 4, that is, the work end time. It is determined whether the time is later than the break start time. Here, if it is determined that the work end time is less than or equal to the break start time, that is, the work end time is earlier than the break start time, the process proceeds to step 2.
【0030】また、作業終了時刻が休憩開始時刻より大
きいと判断されれば、作業終了時刻に休憩時間( 休憩終
了時刻−休憩開始時刻 )を加算し、この加算した新しい
作業終了時刻でプリントバッファに設定された作業終了
時刻を設定変更して、ステップ2の処理に移行するよう
になっている。If it is determined that the work end time is greater than the break start time, the break time (break end time-break start time) is added to the work end time, and the new work end time added to the print buffer is added. The set work end time is changed, and the process proceeds to step 2.
【0031】ステップ2( ST2 )の処理は、ワーク時
刻にプリントバッファに設定されている最新の作業終了
時刻を設定する。In the process of step 2 (ST2), the latest work end time set in the print buffer is set as the work time.
【0032】次に、ワーク時刻に設定された時刻データ
が休憩開始時刻と等しいか否かを判断する。ここでワー
ク時刻に設定された時刻データが休憩開始時刻と等しく
ないと判断されれば、再び前述のステップ1の処理に戻
るようになっており、ワーク時刻に設定された時刻デー
タが休憩開始時刻と等しいと判断されれば、ワーク時刻
に休憩終了時刻を設定して、再び前述のステップ1の処
理に戻るようになっている。Next, it is determined whether or not the time data set as the work time is equal to the break start time. If it is determined that the time data set as the work time is not equal to the break start time, the process returns to step 1 described above, and the time data set as the work time is set as the break start time. If it is determined that the work end time is equal to the work end time, the break end time is set, and the process returns to step 1 described above.
【0033】なお、この作業指示書発行処理により前記
CPU1、前記ROM2、前記RAM3、前記プリンタ
インターフェイス14及び前記プリンタ13は、指示書
発行手段を構成している。The CPU 1, the ROM 2, the RAM 3, the printer interface 14 and the printer 13 constitute an instruction issuing means by this work instruction issuing processing.
【0034】このような構成の本実施例において、まず
初期設定として、RAM3に形成された格納エリア「ワ
ーク時刻」に、製品マスタ4に記憶された1日の作業開
始時刻8:00が設定される。In this embodiment having such a configuration, first, as an initial setting, the work start time 8:00 of the day stored in the product master 4 is set in the storage area "work time" formed in the RAM 3. It
【0035】次に、作業日としてキーボード9から××
年3月4日を示す××0304と入力すると、図3に示
す生産計画ファイルから作業日××0304の対象とな
る生産データが、各製品毎に順次読取られる。Next, from the keyboard 9 as a working day, xx
When XX0304 indicating March 4th of the year is input, the production data which is the target of the work day XX0304 is sequentially read from the production plan file shown in FIG. 3 for each product.
【0036】すなわち、第1番目の生産データとして、
製品計画ファイルから先頭の製品名A、生産台数40が
読取られる。従って、製品名としてA、生産台数として
40がRAM3に形成されたプリントバッファに設定さ
れる。That is, as the first production data,
The first product name A and the production number 40 are read from the product plan file. Therefore, the product name A and the production number 40 are set in the print buffer formed in the RAM 3.
【0037】次に、製品Aについて製品マスタ4から基
準生産時間5、準備時間10が読取られる。Next, for the product A, the standard production time 5 and the preparation time 10 are read from the product master 4.
【0038】ここで、ワーク時刻の時刻データ8:00
が製品Aについての作業開始時刻(作業開始予定時刻 )
としてプリントバッファに設定される。Here, the time data of the work time is 8:00.
Is the work start time for product A (scheduled work start time)
Is set in the print buffer as.
【0039】さらに、作業終了時刻が、 作業開始時刻8:00+( 基準生産時間5×生産台数4
0 )+準備時間10=11:30 として算出され、この作業終了時刻11:30が、作業
終了時刻( 作業終了予定時刻 )としてプリントバッファ
に設定される。Further, the work end time is the work start time 8: 00+ (standard production time 5 × production number 4
0) + preparation time 10 = 11: 00, and this work end time 11:30 is set in the print buffer as the work end time (work end scheduled time).
【0040】この時、この作業終了時刻11:30は、
製品マスタ4に記憶された休憩開始時刻12:00より
も早い時刻なので、この作業終了時刻11:30で決定
となる。At this time, the work end time 11:30 is
Since the time is earlier than the break start time 12:00 stored in the product master 4, the work end time is 11:30.
【0041】そこで、ワーク時刻に、この作業終了時刻
11:30が設定される。Therefore, the work end time 11:30 is set as the work time.
【0042】次に、第2番目の生産データとして、製品
計画ファイルから次の製品B、生産台数25が読取られ
る。従って、製品名としてB、生産台数として25がプ
リントバッファに設定される。Next, as the second production data, the next product B and the production number 25 are read from the product planning file. Therefore, B is set in the print buffer as the product name and 25 as the production number.
【0043】次に、製品Bについて製品マスタ4から基
準生産時間3、準備時間10が読取られる。Next, for the product B, the standard production time 3 and the preparation time 10 are read from the product master 4.
【0044】ここで、ワーク時刻の時刻データ11:3
0が製品Bについての作業開し時刻としてプリントバッ
ファに設定される。Here, the time data of the work time is 11: 3.
0 is set in the print buffer as the work opening time for product B.
【0045】さらに、作業終了時刻が、 作業開始時刻11:30+( 基準生産時間3×生産台数
25 )+準備時間10=12:55 として算出され、プリントバッファに作業終了時刻とし
て設定される。しかし、作業開始時刻11:30が、休
憩開始時刻12:00より早い時刻であり、しかも作業
終了時刻12:55は、休憩開始時刻12:00より遅
い時刻であるので、作業終了時刻12:55は、 作業終了時刻12:55+( 休憩終了時刻13:00−
12:00 )=13:55 として算出され、プリントバッファに設定された旧作業
終了時刻12:55に代わって、この新しい作業終了時
刻13:55が設定される。Further, the work end time is calculated as work start time 11: 30+ (standard production time 3 × production number 25) + preparation time 10 = 12: 55, and is set in the print buffer as the work end time. However, since the work start time 11:30 is earlier than the break start time 12:00 and the work end time 12:55 is later than the break start time 12:00, the work end time 12:55. Is the work end time 12: 55+ (break end time 13: 00-
This new work end time 13:55 is set in place of the old work end time 12:55 calculated in the print buffer as 12:00) = 13: 55.
【0046】そこで、ワーク時刻に、この作業終了時刻
13:55が設定される。Therefore, the work end time 13:55 is set as the work time.
【0047】以降、第3番目及び第4番目の生産データ
として、製品計画ファイルから、製品C、生産台数10
と製品D、生産台数20が読取られ、上述したのと同様
に処理され、製品Cについては、作業開始時刻13:5
5、作業終了時刻15:50がプリントバッファに設定
され、製品Dについては、作業開始時刻15:50、作
業終了時刻17:20がプリントバッファに設定され
る。Thereafter, as the third and fourth production data, from the product plan file, the product C and the production number 10
And the product D and the production number 20 are read and processed in the same manner as described above. For the product C, the work start time is 13: 5.
5, work end time 15:50 is set in the print buffer, and for product D, work start time 15:50 and work end time 17:20 are set in the print buffer.
【0048】なお、作業終了時刻が12:00になった
ときには、ワーク時刻には、13:00が設定される。When the work end time is 12:00, the work time is set to 13:00.
【0049】そこで、生産計画ファイルから作業日××
0304の対象となる生産計画データの全ての読取りが
終了したので、RAM3に形成されたプリントバッファ
から印字データがプリンタ13に転送されて、プリンタ
13により図5に示す作業指示書が印字発行される。な
おこの作業指示書の書面上では、作業開始時刻は「開始
時刻」、作業終了時刻は「終了時刻」として印字されて
いる。Therefore, from the production plan file, work days XX
Since the reading of all the production planning data targeted by 0304 has been completed, the print data is transferred from the print buffer formed in the RAM 3 to the printer 13, and the printer 13 prints out the work instruction sheet shown in FIG. . In the document of this work instruction, the work start time is printed as “start time” and the work end time is printed as “end time”.
【0050】このように本実施例によれば、各製品毎に
製品1台を生産するのに必要な基準生産時間データ及び
準備時間データが記憶された製品マスタ4を設け、生産
計画ファイルから呼出された各製品毎に、生産計画デー
タの生産台数、基準生産時間データ及び準備時間データ
により作業終了時刻を算出し、各製品毎に製品名、生産
台数、作業開始時刻及び作業終了時刻をプリンタ13に
より作業指示書に印字発行することにより、作業日( 生
産日 )一のうちの生産する各製品毎に、作業開始時刻(
開始時刻 )及び作業終了時刻( 終了時刻 )を印字した作
業指示書を発行することができる。As described above, according to the present embodiment, the product master 4 in which the standard production time data and the preparation time data necessary for producing one product for each product are stored is provided and called from the production plan file. The work end time is calculated for each product based on the production quantity of the production plan data, the standard production time data and the preparation time data, and the product name, the production quantity, the work start time and the work end time of each product are calculated by the printer 13. By printing and issuing on the work instruction sheet, the work start time (for each product to be produced within the work day (production date))
It is possible to issue a work instruction sheet in which the start time) and the work end time (end time) are printed.
【0051】従って、生産管理者は、この作業指示書を
みれば、1日の作業時間割りが分かり、作業の進捗状況
を随時確認することができる。Therefore, the production manager can see the work time schedule for one day by looking at the work instruction sheet, and can check the progress status of the work at any time.
【0052】なお、この実施例では生産計画データを生
産計画ファイルとして持っているが、この発明はこれに
限定されるものではなく、例えばキーボードにより直接
入力されるものでも良いし、また回線を介してホストコ
ンピュータ等から送信されるものでも良い。Although the production plan data is stored as a production plan file in this embodiment, the present invention is not limited to this. For example, it may be directly input by a keyboard, or via a line. It may be transmitted from a host computer or the like.
【0053】[0053]
【発明の効果】以上詳述したようにこの発明によれば、
生産日一日のうちの生産する各製品毎に、作業開始予定
時刻又は作業終了予定時刻の少なくとも一方が印字され
た作業指示書を発行することができる作業指示書発行装
置を提供できる。As described above in detail, according to the present invention,
It is possible to provide a work instruction sheet issuing device that can issue a work instruction sheet on which at least one of the scheduled work start time and the scheduled work end time is printed for each product to be produced in one production day.
【図1】この発明の一実施例の作業指示書発行装置の要
部回路構成を示すブロック図。FIG. 1 is a block diagram showing a circuit configuration of a main part of a work instruction document issuing device according to an embodiment of the present invention.
【図2】同実施例の作業指示書発行装置の製品マスタの
要部のメモリ構成の一例を示す図。FIG. 2 is a diagram showing an example of a memory configuration of a main part of a product master of the work instruction sheet issuing apparatus according to the embodiment.
【図3】同実施例の作業指示書発行装置の生産計画ファ
イルの構成の一例を示す図。FIG. 3 is a diagram showing an example of a configuration of a production plan file of the work instruction sheet issuing apparatus according to the embodiment.
【図4】同実施例の作業指示書発行装置で行われる作業
指示書発行処理の流れを示す図。FIG. 4 is a diagram showing a flow of a work instruction document issuing process performed by the work instruction document issuing device according to the embodiment.
【図5】同実施例の作業指示書発行装置で印字発行され
る作業指示書の一例を示す図。FIG. 5 is a view showing an example of a work instruction document printed and issued by the work instruction document issuing device according to the embodiment.
1…CPU、 2…ROM、 3…RAM、 4…製品マスタ、 9…キーボード、 13…プリンタ。 1 ... CPU, 2 ... ROM, 3 ... RAM, 4 ... Product master, 9 ... Keyboard, 13 ... Printer.
Claims (1)
のに要する基準生産時間を記憶した基準生産時間記憶手
段と、この基準生産時間記憶手段に記憶された基準生産
時間に基づいて、製品毎にその生産数量を設定した生産
計画情報の各製品について、この生産計画情報でそれぞ
れ設定された生産数量分生産するのに必要な生産時間を
算出し、前記各製品の生産の作業開始予定時刻又は作業
終了予定時刻の少なくとも一方を求め、前記各製品毎
に、その生産数量及びその生産の前記作業開始予定時刻
又は前記作業終了予定時刻の少なくとも一方を印字した
作業指示書を発行する指示書発行手段とを設けたことを
特徴とする作業指示書発行装置。1. A product based on a standard production time storage means for storing a standard production time required to produce a unit quantity of each product and a standard production time stored in the reference production time storage means. For each product in the production plan information for which the production quantity is set for each, the production time required to produce the production quantity set in the production plan information is calculated, and the scheduled work start time for the production of each product Or, issue at least one of the scheduled work end times, and issue a work instruction for each product, which prints at least one of the production quantity and the scheduled work start time or the scheduled work end time of the production. A work order issuing device, which is provided with means.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP9262594A JPH07296060A (en) | 1994-04-28 | 1994-04-28 | Work instruction book issuing device |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP9262594A JPH07296060A (en) | 1994-04-28 | 1994-04-28 | Work instruction book issuing device |
Publications (1)
Publication Number | Publication Date |
---|---|
JPH07296060A true JPH07296060A (en) | 1995-11-10 |
Family
ID=14059632
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP9262594A Pending JPH07296060A (en) | 1994-04-28 | 1994-04-28 | Work instruction book issuing device |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPH07296060A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2021054028A (en) * | 2019-10-02 | 2021-04-08 | 株式会社Isowa | Target preparation time notification device for cardboard sheet carton former |
-
1994
- 1994-04-28 JP JP9262594A patent/JPH07296060A/en active Pending
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2021054028A (en) * | 2019-10-02 | 2021-04-08 | 株式会社Isowa | Target preparation time notification device for cardboard sheet carton former |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US5243691A (en) | System for printing documents | |
US7869072B2 (en) | Printer device | |
JPH11296335A (en) | Preview method for print data and device therefor and recording medium | |
JP3054230B2 (en) | Printing apparatus and print control method | |
JPH07296060A (en) | Work instruction book issuing device | |
JPS6214689A (en) | Character output controller | |
JPH10329369A (en) | Printer | |
JPH0522933B2 (en) | ||
JPH07101431A (en) | Label issuer | |
JP2516898B2 (en) | Illustration embedding processing method | |
JPH0659829A (en) | Print controller | |
JPH01208141A (en) | Printing control apparatus | |
JP2903516B2 (en) | Document processing device | |
JPH07253860A (en) | Printer load distribution system | |
JPH11105370A (en) | Print controller, print control method and memory medium | |
JPS58112132A (en) | Slip output processing system | |
JP2602976Y2 (en) | Handy terminal | |
JP2846211B2 (en) | Information processing device | |
JP2562481B2 (en) | Setting method of unique data for terminals | |
JPH08279010A (en) | Model wage output method | |
JPH113380A (en) | Document print-out device | |
JPH07149025A (en) | Label publishing apparatus | |
JPH0113128B2 (en) | ||
JPH07148992A (en) | Printing device | |
JPH0689019A (en) | Slip plotting system and proofreading paper |