Lifting device for tower erection crane

Info

Publication number
JPH0728179Y2
JPH0728179Y2 JP1988031514U JP3151488U JPH0728179Y2 JP H0728179 Y2 JPH0728179 Y2 JP H0728179Y2 JP 1988031514 U JP1988031514 U JP 1988031514U JP 3151488 U JP3151488 U JP 3151488U JP H0728179 Y2 JPH0728179 Y2 JP H0728179Y2
Authority
JP
Japan
Prior art keywords
crane
tower
pair
guide rail
guide rails
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP1988031514U
Other languages
Japanese (ja)
Other versions
JPH01137311U (en
Inventor
勇 福井
悦郎 大西
国明 松本
好広 多久田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kawasaki Motors Ltd
Original Assignee
Kawasaki Jukogyo KK
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kawasaki Jukogyo KK filed Critical Kawasaki Jukogyo KK
Priority to JP1988031514U priority Critical patent/JPH0728179Y2/en
Publication of JPH01137311U publication Critical patent/JPH01137311U/ja
Application granted granted Critical
Publication of JPH0728179Y2 publication Critical patent/JPH0728179Y2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Description

【考案の詳細な説明】 〔産業上の利用分野〕 本考案は塔架設用クレーンのせり上げ装置に関するもの
である。
DETAILED DESCRIPTION OF THE INVENTION [Industrial field of application] The present invention relates to a lifting device for a tower erection crane.

〔従来技術〕[Prior art]

長大吊橋の主塔などの塔状構造物の分割ブロックをクレ
ーンで順々に積み上げて塔状構造物を架設していく場
合、塔体の架設工事が進むにつれてクレーンの作業域が
高くなるので、一般に塔状構造物の架設工事が進むにつ
れて、クレーンを塔体に沿ってせり上げる工法がとられ
ている。
When the divided blocks of tower-like structures such as the main tower of a long suspension bridge are piled up one after another with a crane and the tower-like structures are erected, the work area of the crane becomes higher as the tower erection work progresses. Generally, as the construction work of tower-like structures progresses, a method of raising a crane along the tower body is adopted.

この為クレーンせり上げ用の上下2組のガイドレールを
塔体に着脱可能に付設し、クレーン本体をこのガイドレ
ールに取付け、クレーン本体をガイドレールに沿ってせ
り上げる塔架設用クレーンのせり上げ装置が一般に用い
られている(特公昭56-27646号公報参照)。
Therefore, two sets of upper and lower guide rails for lifting the crane are detachably attached to the tower body, the crane main body is attached to this guide rail, and the crane main body is raised along the guide rail. Is generally used (see Japanese Patent Publication No. 56-27646).

従来のせり上げ装置によれば、所定範囲の架設作業の終
了後、まずクレーン本体下方にあるガイドレールを塔体
からとり外してクレーン本体の上方へ移設し、クレーン
本体が取付けられているガイドレールの上端に連なるよ
うにそのガイドレールを塔体に取付け、次に上段に移設
されたガイドレールの上部又は塔体の頂部に滑車ブロッ
クを有する天秤を取付け、上記滑車ブロックとクレーン
側の滑車及びウインチとにわたって掛装したワイヤでク
レーン本体の自重を支持した状態においてクレーン本体
をガイドレールから外してガイドレールに沿ってせり上
げ、所定位置でクレーン本体をガイドレールに再び固定
し、天秤を取外してから架設工事を再開する。
According to the conventional lifting device, after the installation work within a predetermined range is completed, first remove the guide rail below the crane body from the tower body and move it above the crane body, and the guide rail on which the crane body is attached. The guide rail is attached to the tower so as to be connected to the upper end of the tower, and then a balance having a pulley block is attached to the upper part of the guide rail transferred to the upper stage or the top of the tower, and the pulley block and the pulley and winch on the crane side are attached. Remove the crane body from the guide rail and lift it up along the guide rail while supporting the weight of the crane body with the wire hung over the rail, fix the crane body to the guide rail again at the specified position, and remove the balance. Resume construction work.

〔考案が解決しようとする課題〕[Problems to be solved by the device]

従来の塔架設用クレーンのせり上げ装置においては、ク
レーン本体をガイドレールを介して塔体に固定するよう
になっているので、クレーンに加わる吊荷の荷重とクレ
ーン本体の自重がすべてこのガイドレールに作用するた
め、ガイドレールを相当強固なものとする必要があり、
ガイドレール自身の重量も大きくなる。しかも、せり上
げの都度ガイドレールを順次上方へ移設する関係上ガイ
ドレールとしては上下2組必要となる。またガイドレー
ルとは別体の天秤を使用するためガイドレールの他に重
量の大きな天秤を移設しなければならず、高所でこれら
ガイドレールや天秤を移設するのは非常に危険で困難な
作業であり、そのためクレーン本体のせり上げ工程に架
設工程に匹敵する時間が必要で、クレーンの稼働率が著
しく低下し、塔体架設工事の期間が長期化するという問
題がある。
In the conventional lifting equipment for tower erection cranes, the crane body is fixed to the tower body via the guide rail, so the load of the suspended load on the crane and the weight of the crane body are all contained in this guide rail. Therefore, it is necessary to make the guide rail considerably strong,
The weight of the guide rail itself also increases. Moreover, since the guide rails are sequentially moved upward each time they are raised, two sets of guide rails are required. Also, since a balance separate from the guide rail is used, it is necessary to move a heavier balance in addition to the guide rail, and it is a very dangerous and difficult task to move these guide rails and the balance at a high place. Therefore, the raising process of the crane body requires a time comparable to that of the erection process, and there is a problem that the operating rate of the crane is significantly reduced and the period of tower erection work is prolonged.

本考案の目的は、このガイドレールを小型軽量化でき、
せり上げ用天秤を省略でき、クレーン本体のせり上げに
要する時間を大幅に短縮できるような塔架設用クレーン
のせり上げ装置を提供することである。
The purpose of the present invention is to reduce the size and weight of this guide rail,
An object of the present invention is to provide a hoisting device for a tower erection crane that can omit the hoisting balance and can significantly reduce the time required to hoist the crane body.

〔課題を解決するための手段〕[Means for Solving the Problems]

本考案に係る塔架設用クレーンのせり上げ装置は、塔架
設用クレーンをワイヤーロープを介してガイドレールに
沿ってせり上げ移設するせり上げ装置において、上記ガ
イドレールとして、塔体の側壁部の外面に水平方向に所
定間隔あけて1対の鉛直方向に延びるガイドレールを設
け、塔架設用クレーンのクレーン本体部に、1対のガイ
ドレールにより鉛直方向に摺動自在に案内される1対の
被案内部を設け、塔体の側壁部にクレーン本体を固定す
るための複数の取付ブラケットと、塔体の側壁部に1対
のガイドレールを固定するための複数の取付ブラケット
とを、夫々独立に設けて、クレーン本体とガイドレール
部材とを夫々独立に塔体の側壁部に直接固定出来る様に
構成し、1対のガイドレールの上端に滑車ブロックを一
体構造として夫々装備するとともに、これら1対の滑車
ブロックの下方に夫々対応するようにクレーン本体に1
対の滑車ブロックを装備し、ガイドレールの各滑車ブロ
ックと、それに対応するクレーン本体側の滑車ブロック
とにわたってワイヤーロープを複数巻きに掛け渡し、ク
レーン本体に装備された1対のウインチによって上記1
対のワイヤーロープを夫々巻取ることによりクレーン本
体をせり上げ可能に構成したものである。
The lifting device for a tower erection crane according to the present invention is a lifting device for lifting and relocating a tower erection crane along a guide rail via a wire rope, wherein the guide rail serves as the outer surface of the side wall of the tower body. Is provided with a pair of vertically extending guide rails in the horizontal direction, and a pair of guide rails is vertically slidably guided by the pair of guide rails to the crane main body of the tower erection crane. A plurality of mounting brackets for fixing the crane body to the side wall of the tower body and a plurality of mounting brackets for fixing the pair of guide rails to the side wall of the tower are provided independently. The crane main body and the guide rail member can be independently fixed directly to the side wall of the tower body, and the pulley blocks are integrally formed on the upper ends of the pair of guide rails. While Bei, the crane body so as respectively corresponding to the lower pulley block of one-to-one
Equipped with a pair of pulley blocks, a plurality of wire ropes are hung over each pulley block of the guide rail and the corresponding pulley block on the crane body side, and the above-mentioned 1
The crane body can be lifted by winding a pair of wire ropes.

〔作用〕[Action]

本考案に係る塔架設用クレーンのせり上げ装置において
は、塔架設の際にはクレーン本体は取付ブラケットを介
して塔体に直接固定され、1対のガイドレールは取付ブ
ラケットを介してクレーン本体とは独立に塔体に固定さ
れている。
In the hoisting device for a tower erection crane according to the present invention, the crane main body is directly fixed to the tower body through the mounting bracket when the tower is erected, and the pair of guide rails are connected to the crane main body through the mounting bracket. Are independently fixed to the tower.

クレーン本体をせり上げる場合には、先ず一方のガイド
レールの固定を解き、そのガイドレールに対応するウイ
ンチのワイヤーを繰出しつつクレーンの主巻フックや補
巻フックで上記ガイドレールを吊って所定距離上方へ移
設して塔体に固定する。次に、上記と同様にして、他方
のガイドレールを吊って所定距離上方へ移設して塔体に
固定する。
When raising the crane body, first unfix the guide rail on one side, and while paying out the winch wire corresponding to that guide rail, hang the guide rail with the main winding hook and auxiliary winding hook of the crane and move it up a predetermined distance. It is relocated to and fixed to the tower. Next, in the same manner as above, the other guide rail is suspended and moved upward by a predetermined distance to be fixed to the tower body.

次にクレーン本体の固定を解いて1対のウインチでワイ
ヤーを巻取っていくことにより1対のガイドレールに沿
ってクレーン本体を所定距離だけせり上げてから、クレ
ーン本体を取付ブラケットを介して塔体に固定する。
Next, the crane body is unfixed and the wire is wound up with a pair of winches to raise the crane body along the pair of guide rails by a predetermined distance, and then the crane body is attached to the tower via the mounting bracket. Fix it to the body.

この状態でクレーンによる塔架設作業を再開することが
出来る。
In this state, the tower erection work by the crane can be restarted.

〔考案の効果〕[Effect of device]

本考案に係る塔架設用クレーンのせり上げ装置によれ
ば、1対のガイドレールとクレーン本体が取付ブラケッ
トを介してそれぞれ独立に塔体側壁部に直接固定される
ので、クレーン本体に加わる吊荷の荷重とクレーン本体
の自重とがガイドレールに作用することなく、ガイドレ
ールはクレーン本体をせり上げるときのガイドとしての
強度のみあれば良いから軽量小型化することが出来る。
According to the lifting device for a tower erection crane according to the present invention, the pair of guide rails and the crane main body are directly fixed to the side wall of the tower independently through the mounting brackets. The load and the weight of the crane main body do not act on the guide rail, and the guide rail needs only to have strength as a guide when the crane main body is lifted up, so that the weight and size can be reduced.

また、1対のガイドレールがクレーン本体とは独立に塔
体側壁にとりつけられるので、クレーン本体とは独立に
ガイドレールのみの移動が可能であり、従来技術のよう
に上下に2分割されたガイドレールを用意する必要がな
く、ガイドレールを上方に移設する時にはクレーン本体
の被案内部に摺動自在に係合しているガイドレールを上
方に吊り上げれば良いから、上下方向に一体品の1対の
ガイドレールを設けるだけでよくその必要数が半減す
る。
In addition, since a pair of guide rails is attached to the side wall of the tower independently of the crane body, only the guide rails can be moved independently of the crane body, and the guides are divided into upper and lower parts as in the prior art. It is not necessary to prepare a rail, and when the guide rail is moved upward, the guide rail slidably engaged with the guided portion of the crane body can be lifted upward. Only by providing a pair of guide rails, the required number is reduced by half.

ガイドレールは従来技術のものに比べて軽量小型である
から、その取扱いは容易であり、且つクレーン本体が本
来の架設作業に従事しているときでも並行してガイドレ
ールの移設作業が出来るし、従来技術のように別体の天
秤を取付ける必要が無いので、クレーン本体のせり上げ
の為の労力と時間を大巾に減少させることができ、工期
の短縮とコストダウンを実現することができる。更に、
クレーン本体部に、1対のガイドレールにより鉛直方向
に摺動自在に案内される1対の被案内部を設けたので、
クレーン本体をせり上げる際の安定性を確保できるし、
また、各ガイドレールの上端の滑車ブロックと、これの
下方に対応するクレーン本体側の滑車ブロックとにわた
ってワイヤーロープを複数巻きに掛け渡してあるので、
このワイヤーロープを巻き取るウインチを著しく小型化
できる。
Since the guide rails are lighter and smaller than those of the prior art, it is easy to handle, and even when the crane body is engaged in the original erection work, the guide rails can be moved in parallel. Since it is not necessary to mount a separate balance as in the prior art, the labor and time for raising the crane body can be greatly reduced, and the construction period and cost can be reduced. Furthermore,
Since the crane body is provided with a pair of guided parts that are slidably guided in the vertical direction by a pair of guide rails,
You can secure stability when raising the crane body,
Also, since the wire block is laid over a plurality of windings over the pulley block on the upper end of each guide rail and the pulley block on the crane body side corresponding to the lower part of this block,
The winch for winding this wire rope can be significantly reduced in size.

〔実施例〕〔Example〕

以下、本考案の実施例を第1図〜第3図に基いて説明す
る。
An embodiment of the present invention will be described below with reference to FIGS.

本実施例は、長大吊橋の主塔(以下、塔体という)の架
設用クレーンを工事の進行に応じて順次せり上げていく
せり上げ装置に本考案を適用した場合のものである。
In this embodiment, the present invention is applied to a hoisting device for hoisting a main tower (hereinafter referred to as a tower body) of a long suspension bridge, which sequentially hoists according to the progress of construction.

クレーンCは、ブーム旋回式のジブクレーンであり、荷
役機構部1と支持機構部2とからなり、荷役機構部1は
台板3と、台板3に下端部で枢着され起倒自在のブーム
4と、滑車ブロック5と、滑車ブロック5を支持するフ
レーム6と、台板3上に設けた主巻ウインチ7及び補巻
きウインチ8などを備えており、支持機構部2はクレー
ンCを塔体10の側壁部に取付ブラケット11を介して着脱
自在に取付ける為の支持板12と、支持板12に連結部材13
により連結された立向きの筒部材14と、筒部材14内に配
設され台板3に連結された回動軸部材と、回動軸部材の
下端部に固着された大径回動部材15と、大径回動部材15
と台板3の外端部とを連結する1対の張力部材16とを備
えており、荷役機構部1は筒部材14及び張力部材16に支
持され筒部材14に対して所定角度範囲内で左右に水平旋
回自在で旋回装置(図示略)により旋回駆動されるよう
になっている。
The crane C is a boom-turning type jib crane, and includes a cargo handling mechanism unit 1 and a support mechanism unit 2. The cargo handling mechanism unit 1 is a base plate 3 and a boom which is pivotally attached to the base plate 3 at its lower end and can be tilted up and down. 4, a pulley block 5, a frame 6 supporting the pulley block 5, a main winding winch 7 and a supplementary winding winch 8 provided on the base plate 3, and the like. A support plate 12 for removably attaching to the side wall of 10 via a mounting bracket 11, and a connecting member 13 for the support plate 12.
The vertical cylinder member 14 connected by the above, the rotary shaft member disposed in the cylinder member 14 and connected to the base plate 3, and the large-diameter rotary member 15 fixed to the lower end of the rotary shaft member. And the large-diameter rotating member 15
And a pair of tension members 16 for connecting the outer end of the base plate 3 to each other. The cargo handling mechanism unit 1 is supported by the tubular member 14 and the tension member 16 within a predetermined angle range with respect to the tubular member 14. It can be horizontally swiveled to the left and right, and swiveled by a swivel device (not shown).

せり上げ装置Eは、塔体10の側壁部に取付ブラケット17
を介して着脱自在に取付けられる左右1対のガイドレー
ル18と、各ガイドレール18の上端部に一体的に設けられ
た滑車ブロック19と、支持板12の上端近傍部に各滑車ブ
ロック19に対応するように左右1対設けられた滑車ブロ
ック20と、各滑車ブロック20に対応しその直ぐ下方位置
で支持板12の外面に左右1対設けられたガイド滑車21
と、支持板12の中段部に各ガイド滑車21に対応するよう
に左右1対設けられたせり上げ用ウインチ22と、左右各
組の滑車ブロック19・20とガイド滑車21とせり上げ用ウ
インチ22とに亙って巻き掛けられたワイヤーロープ23と
からなる。尚、上記ガイドレール18は支持板12の約2倍
以上の長さに形成されている。
The lifting device E has a mounting bracket 17 attached to the side wall of the tower 10.
A pair of left and right guide rails 18 which are detachably attached via a pulley block 19, a pulley block 19 integrally provided at the upper end of each guide rail 18, and a pulley block 19 near the upper end of the support plate 12 1 pair of left and right pulley blocks 20 are provided, and a pair of left and right guide pulleys 21 are provided on the outer surface of the support plate 12 at a position immediately below and corresponding to each pulley block 20.
And a pair of left and right lifting winches 22 provided in the middle part of the support plate 12 so as to correspond to the respective guide pulleys 21, a pair of left and right pulley blocks 19, 20 and a guide pulley 21, and a lifting winch 22. It consists of a wire rope 23 wound around the ground. The guide rail 18 is formed to have a length which is about twice as long as the support plate 12 or more.

支持板12は塔体10の側壁部にほぼ垂直にとりつけられ、
その外側面に2台のせり上げ用ウインチ22が設けられて
いる。支持板12と塔体10の側壁部の間には2本のガイド
レール18が塔体10に添わせてほぼ垂直に挿入され、それ
らガイドレール18のそれぞれの上端に設けられたアーム
18aの上部に一体的に滑車ブロック19が設けられ、これ
と対応する様に支持板12の上部に2組の滑車ブロック20
が並設されている。各ガイドレール18に関して、ガイド
レール18上端の滑車ブロック19と支持板12に設けられた
滑車ブロック20との間に複数巻きにかけわたしたワイヤ
ーロープ23をガイド滑車21を介して支持板12の外側面に
設けられたせり上げ用ウインチ22で巻き取る様になって
いる。従って、ガイドレール18を取付ブラケット17を介
して塔体10の側壁部に固定しておき、支持板12を固定し
ている取付ブラケット11部を解放し、せり上げ用ウイン
チ22を巻き取れば支持板12はワイヤーロープ23によって
上方にせり上げられることになる。
The support plate 12 is attached almost vertically to the side wall of the tower body 10,
Two lifting winches 22 are provided on the outer surface thereof. Two guide rails 18 are inserted almost vertically between the support plate 12 and the side wall of the tower body 10 along the tower body 10, and the arms provided at the upper ends of the guide rails 18 respectively.
A pulley block 19 is integrally provided on the upper portion of 18a, and two sets of pulley blocks 20 are provided on the upper portion of the support plate 12 so as to correspond to this.
Are juxtaposed. With respect to each guide rail 18, a wire rope 23 wound around the pulley block 19 at the upper end of the guide rail 18 and a pulley block 20 provided on the support plate 12 is wound a plurality of times, and the outer surface of the support plate 12 is provided through the guide pulley 21. It is designed to be wound up by the lifting winch 22 provided at. Therefore, the guide rail 18 is fixed to the side wall portion of the tower body 10 via the mounting bracket 17, the mounting bracket 11 portion fixing the support plate 12 is released, and the lifting winch 22 is wound to support. The plate 12 will be lifted up by the wire rope 23.

支持板12の横断面は略E字形をなし、その2つの凹部に
はガイドレール18が摺動するガイドシューが適当数設け
られ、ガイドレール18を吊り上げるとき及びクレーンC
をせり上げるときのガイドとなり、せり上げ途中の姿勢
の安定と荷重の支持を行う。
The cross section of the support plate 12 is substantially E-shaped, and an appropriate number of guide shoes on which the guide rail 18 slides are provided in the two recesses, and when the guide rail 18 is lifted and the crane C is used.
It serves as a guide for raising the body and stabilizes the posture while supporting the load.

支持板12は、架設済みの塔体10の側壁部に設けた専用の
4組の取付ブラケット11を介して取付けられ、ガイドレ
ール18は同じく架設済みの塔体10の側壁部に別に設けら
れた専用の取付ブラケット17を介して取付けられる。従
って、支持板12とガイドレール18は別々に独立に取付け
取外しを行うことが出来る。
The support plate 12 is attached via four dedicated mounting brackets 11 provided on the side wall of the tower 10 already installed, and the guide rail 18 is separately provided on the side wall of the tower 10 already installed. It can be mounted via a dedicated mounting bracket 17. Therefore, the support plate 12 and the guide rail 18 can be separately attached and detached independently.

次に、上記せり上げ装置Eを用いてクレーンCをせり上
げるときの作用について説明すると、先ず塔体10の側壁
部の所定の位置にガイドレール用の取付ブラケット17と
支持板用取付ブラケット11とが溶接やボルトで予め取付
けられ、ガイドレール18は取付ブラケット17を介してま
たクレーンCは取付ブラケット11を介して塔体10に取付
けられているものとする。せり上げに際して、先ずクレ
ーンCの主巻フック若しくは補巻フックでガイドレール
18の上端を吊持した状態で、ガイドレール18を支持して
いる取付ブラケット17のピンを抜き取り、第2図に示す
ように、せり上げ用ウインチ22からワイヤーロープ23を
繰出しながら、ガイドレール18を所定の高さまで吊り上
げ、塔体10の側壁部に取付ブラケット17とピンを介して
取付ける。このときクレーンCを使用するのはガイドレ
ール18を吊り上げるときだけであるから、これらの作業
は塔体10の架設工事と略並行して行うことが出来、クレ
ーンのせり上げに要する時間を大巾に減少させる事が出
来る。
Next, the operation of hoisting the crane C using the hoisting device E will be described. First, the guide rail mounting bracket 17 and the support plate mounting bracket 11 are provided at predetermined positions on the side wall of the tower body 10. Are previously attached by welding or bolts, and the guide rail 18 is attached to the tower body 10 via the attachment bracket 17 and the crane C is attached to the tower body 10 via the attachment bracket 11. When raising the rail, first use the main or auxiliary winding hook of the crane C to guide rails.
While the upper end of 18 is suspended, the pin of the mounting bracket 17 supporting the guide rail 18 is pulled out, and as shown in FIG. 2, the wire rope 23 is extended from the lifting winch 22 while the guide rail 18 is being pulled out. Is lifted up to a predetermined height, and is attached to the side wall portion of the tower body 10 via a mounting bracket 17 and a pin. At this time, since the crane C is used only when the guide rail 18 is lifted, these operations can be performed substantially in parallel with the erection work of the tower body 10, and the time required for raising the crane can be greatly increased. Can be reduced to

次にクレーンCをせり上げるには、せり上げ用ウインチ
22でワイヤーロープ23を少量巻き取ってわずかにクレー
ンCをせり上げた状態でクレーンCを支持しているピン
を取付ブラケット11から抜き取り、第3図に示すよう
に、2台のせり上げ用ウインチ22でワイヤーロープ23を
巻き取れば、支持板12はガイドレール18に沿って徐々に
上昇して行き、所定の位置で取付ブラケット11とピンを
介して塔体10の側壁部に取付けられる。
Next, to lift crane C, lift the winch.
Take up a small amount of the wire rope 23 with 22 and lift the crane C slightly, and then pull out the pin supporting the crane C from the mounting bracket 11 and, as shown in FIG. When the wire rope 23 is wound up at 22, the support plate 12 gradually rises along the guide rail 18 and is attached to the side wall portion of the tower body 10 through the attachment bracket 11 and the pin at a predetermined position.

従来のせり上げ装置は、ガイドレールと別体の天秤を用
意する必要があり、この天秤もクレーンを吊り上げる大
型の部材であるため、この天秤の移設にも多くの労力と
工数を消費していた。
In the conventional lifting device, it is necessary to prepare a balance separate from the guide rail, and since this balance is also a large member for hoisting the crane, it requires a lot of labor and man-hours to move the balance. .

本考案のせり上げ装置では、この天秤に相当する部分が
ガイドレール18と一体となっているので天秤の移設工事
がなくなり、それだけクレーンのせり上げ時間が短縮さ
れる。更に従来は天秤のアームの下側に吊り上げ用滑車
ブロックを吊設していたので、この滑車ブロックが邪魔
になってクレーンのせり上げ範囲が制限されていたが、
本考案のせり上げ装置によればガイドレール18の滑車ブ
ロック19がアーム18aの上端に取付けられているので支
持板12を比較的高い位置迄せり上げることができる。し
かも、ガイドレール18としては、支持板12の長さの約2
倍程度の長さの左右1対のガイドレール18だけでよいの
で、その移設の回数が従来装置の約1/2となる。また、
荷役の際にはクレーンCは塔体10に直接取付けられてい
るので、ガイドレール18に吊荷の荷重は作用しなから、
ガイドレール18を小型軽量化することができる。従っ
て、せり上げの際の高所における重量物の取扱いが軽減
され、クレーンCのせり上げに要する労力と時間が著し
く低減し、クレーンCの稼働率が格段に向上し工期の大
幅な短縮が可能となる。その上、せり上げ装置の製作費
も安価となる。
In the lifting device of the present invention, since the portion corresponding to the balance is integrated with the guide rail 18, the balance relocation work is eliminated, and the crane lifting time is reduced accordingly. Furthermore, in the past, since the hoisting pulley block was hung under the arm of the balance, this hoisting block blocked the crane hoisting range,
According to the lifting device of the present invention, since the pulley block 19 of the guide rail 18 is attached to the upper end of the arm 18a, the support plate 12 can be lifted to a relatively high position. Moreover, as the guide rail 18, the length of the support plate 12 is about 2
Since only one pair of left and right guide rails 18 each having a length about twice as long as the guide rails 18 are required, the number of times of transfer is about half that of the conventional apparatus. Also,
Since the crane C is directly attached to the tower body 10 during cargo handling, the load of suspended load does not act on the guide rails 18.
The guide rail 18 can be made smaller and lighter. Therefore, the handling of heavy objects at a high place during lifting is significantly reduced, the labor and time required to lift the crane C are significantly reduced, the operating rate of the crane C is significantly improved, and the construction period can be greatly shortened. Becomes In addition, the cost of manufacturing the lifting device is low.

尚、上記ガイドレール18の外側面にラックを形成し、支
持板12のガイドシューに上記ラックに噛合し且つモータ
などの駆動装置で駆動されるピニオンを設け、ラック・
ピニオン機構によりガイドレール18を上方へ移設するよ
うにしてもよい。
A rack is formed on the outer surface of the guide rail 18, and a guide shoe of the support plate 12 is provided with a pinion that meshes with the rack and is driven by a driving device such as a motor.
The guide rail 18 may be moved upward by a pinion mechanism.

【図面の簡単な説明】[Brief description of drawings]

図面は本考案の実施例を示すもので、第1図は架設中の
塔体とクレーンとを示す側面図、第2図は塔体に取付け
られたクレーンの要部とせり上げ装置の斜視図、第3図
はせり上げ中の状況を示す要部斜視図である。 C……クレーン、E……せり上げ装置、10……塔体、11
……クレーン用取付ブラケット、12……支持板、17……
ガイドレール用取付ブラケット、18……ガイドレール、
19……滑車ブロック、20……滑車ブロック、21……ガイ
ド滑車、22……せり上げ用ウインチ、23……ワイヤーロ
ープ。
FIG. 1 shows an embodiment of the present invention. FIG. 1 is a side view showing a tower and a crane being installed, and FIG. 2 is a perspective view of a main part of the crane attached to the tower and a lifting device. FIG. 3 is a perspective view of an essential part showing a situation during raising. C: Crane, E: Lifting device, 10: Tower, 11
…… Crane mounting bracket, 12 …… Support plate, 17 ……
Mounting bracket for guide rail, 18 …… guide rail,
19 …… Pulley block, 20 …… Pulley block, 21 …… Guide pulley, 22 …… Raising winch, 23 …… Wire rope.

───────────────────────────────────────────────────── フロントページの続き (72)考案者 松本 国明 兵庫県加古郡播磨町新島8番地 川重工事 株式会社西部支社内 (72)考案者 多久田 好広 兵庫県加古郡播磨町新島8番地 川重工事 株式会社西部支社内 (56)参考文献 特開 昭59−158794(JP,A) ─────────────────────────────────────────────────── ─── Continuation of the front page (72) Inventor Kuniaki Matsumoto 8 Niijima, Harima-cho, Kako-gun, Hyogo Kawaju Construction Co., Ltd. West Branch Co., Ltd. (72) Yoshihiro Takuda 8th Niijima, Harima-cho, Kako-gun, Hyogo Kawaju Construction Seibu Branch Co., Ltd. (56) Reference JP-A-59-158794 (JP, A)

Claims (1)

【実用新案登録請求の範囲】[Scope of utility model registration request] 【請求項1】塔架設用クレーンをワイヤーロープを介し
てガイドレールに沿ってせり上げ移設するせり上げ装置
において、 上記ガイドレールとして、塔体の側壁部の外面に水平方
向に所定間隔あけて1対の鉛直方向に延びるガイドレー
ルを設け、 塔架設用クレーンのクレーン本体部に、1対のガイドレ
ールにより鉛直方向に摺動自在に案内される1対の被案
内部を設け、 塔体の側壁部にクレーン本体を固定するための複数の取
付ブラケットと、塔体の側壁部に1対のガイドレールを
固定するための複数の取付ブラケットとを、夫々独立に
設けて、クレーン本体とガイドレール部材とを夫々独立
に塔体の側壁部に直接固定出来る様に構成し、 1対のガイドレールの上端に滑車ブロックを一体構造と
して夫々装備するとともに、これら1対の滑車ブロック
の下方に夫々対応するようにクレーン本体に1対の滑車
ブロックを装備し、 ガイドレールの各滑車ブロックと、それに対応するクレ
ーン本体側の滑車ブロックとにわたってワイヤーロープ
を複数巻きに掛け渡し、 クレーン本体に装備された1対のウインチによって上記
1対のワイヤーロープを夫々巻取ることによりクレーン
本体をせり上げ可能に構成したことを特徴とする塔架設
用クレーンのせり上げ装置。
1. A hoisting device for hoisting and moving a tower erection crane along a guide rail via a wire rope, wherein the guide rails are provided at a predetermined horizontal interval on the outer surface of the side wall of the tower body. A pair of vertically extending guide rails is provided, and a pair of guided parts that are vertically slidably guided by a pair of guide rails are provided in the crane main body of the tower erection crane. A plurality of mounting brackets for fixing the crane body to the section and a plurality of mounting brackets for fixing the pair of guide rails to the side wall portion of the tower body are independently provided, and the crane body and the guide rail member are provided. And each of them can be independently fixed directly to the side wall of the tower, and the pulley blocks are equipped as an integral structure on the upper ends of the pair of guide rails. Equipped with a pair of pulley blocks on the crane body so as to correspond to the lower side of the car block, and hang a wire rope in multiple turns over each pulley block of the guide rail and the corresponding pulley block on the crane body side. A hoisting device for a tower erection crane, characterized in that the crane body can be hoisted by winding a pair of the wire ropes by a pair of winches mounted on the crane body.
JP1988031514U 1988-03-09 1988-03-09 Lifting device for tower erection crane Expired - Lifetime JPH0728179Y2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP1988031514U JPH0728179Y2 (en) 1988-03-09 1988-03-09 Lifting device for tower erection crane

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP1988031514U JPH0728179Y2 (en) 1988-03-09 1988-03-09 Lifting device for tower erection crane

Publications (2)

Publication Number Publication Date
JPH01137311U JPH01137311U (en) 1989-09-20
JPH0728179Y2 true JPH0728179Y2 (en) 1995-06-28

Family

ID=31257417

Family Applications (1)

Application Number Title Priority Date Filing Date
JP1988031514U Expired - Lifetime JPH0728179Y2 (en) 1988-03-09 1988-03-09 Lifting device for tower erection crane

Country Status (1)

Country Link
JP (1) JPH0728179Y2 (en)

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS59158794A (en) * 1983-02-25 1984-09-08 株式会社 巴組技研 Crane for assembling steel tower

Also Published As

Publication number Publication date
JPH01137311U (en) 1989-09-20

Similar Documents

Publication Publication Date Title
US4596336A (en) Mobile crane
JPH0728179Y2 (en) Lifting device for tower erection crane
JP2003054876A (en) Device and method for attaching and detaching side frame
JP3180203B2 (en) Material lifting assembly equipment used for construction of high-rise structures
JPH05147884A (en) Dismountable jib crane
JPH08218641A (en) Method of standing up pillar member in the air and device therefor
JPH0628548Y2 (en) Lifting device for self-propelled work platform
JPH04358698A (en) Carriage type crane
JP7230895B2 (en) crane hitch beam
JPH0328066Y2 (en)
JPH0111670Y2 (en)
JP2598741B2 (en) Lifting work beam device
JP2000118946A (en) Auxiliary hoising device
JP3595361B2 (en) crane
JP2833439B2 (en) Hoist type tower crane
JP2562475Y2 (en) Counterweight attachment / detachment device for construction machinery
JP3174454B2 (en) Method and device for installing and removing leader from pile driver
JP2003292263A (en) Elevator apparatus lifting device and method
JPH0448281Y2 (en)
JP2002037585A (en) Portal crane and bridge crane
JP2516881Y2 (en) Mobile crane
JPH0319518Y2 (en)
JP2533428Y2 (en) Crane equipment
JP3811419B2 (en) Building material lifting device and building material lifting method
JPH0881180A (en) Horizontally mobile crane