JPH0726439B2 - Construction method of steel-framed reinforced concrete structure using precast members - Google Patents

Construction method of steel-framed reinforced concrete structure using precast members

Info

Publication number
JPH0726439B2
JPH0726439B2 JP1090598A JP9059889A JPH0726439B2 JP H0726439 B2 JPH0726439 B2 JP H0726439B2 JP 1090598 A JP1090598 A JP 1090598A JP 9059889 A JP9059889 A JP 9059889A JP H0726439 B2 JPH0726439 B2 JP H0726439B2
Authority
JP
Japan
Prior art keywords
column
steel
main bar
floor
pillar
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP1090598A
Other languages
Japanese (ja)
Other versions
JPH02272124A (en
Inventor
仁 佐々木
昭彦 三瓶
次彦 吉野
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fujita Corp
Original Assignee
Fujita Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Fujita Corp filed Critical Fujita Corp
Priority to JP1090598A priority Critical patent/JPH0726439B2/en
Publication of JPH02272124A publication Critical patent/JPH02272124A/en
Publication of JPH0726439B2 publication Critical patent/JPH0726439B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Description

【発明の詳細な説明】 (産業上の利用分野) 本発明は鉄骨鉄筋コンクリート建築構造物を、柱,梁,
床の構造部材をプレキヤスト化して構築するプレキヤス
ト部材による鉄骨鉄筋コンクリート構造物の構築方法に
係るものである。
DETAILED DESCRIPTION OF THE INVENTION (Industrial field of application) The present invention relates to a steel-framed reinforced concrete building structure, including columns, beams,
The present invention relates to a method of constructing a steel-framed reinforced concrete structure using a precast member, which is constructed by precasting floor structural members.

(従来の技術) 従来、鉄骨鉄筋コンクリート構造物の構築方法において
は、所要の鉄骨部材を予め工場で加工し、現場に搬入し
て組立て、下層階より柱,梁,床と順次鉄筋を組立てて
コンクリートを打設し、各階を順次構築していく方法
や、一部の部材をプレキヤスト化して残る部材の殆んど
を現場で施工する方法が採用されている。
(Prior Art) Conventionally, in the method of constructing a steel-framed reinforced concrete structure, the required steel-framed members are processed in advance in a factory, carried into the site, and assembled, and then columns, beams, and floors are assembled from the lower floor in order to assemble concrete. Is used to build each floor one by one, or some of the members are precast and most of the remaining members are installed on site.

(発明が解決しようとする課題) しかしながら前記従来の方法では、現場施工に頼る部分
が多く、同部分の施工には鉄骨工,型枠工,鉄筋工等の
専門技能員が必要であるが、近年慢性的な建築技能者の
不足によって要員の確保が困難になっている。このため
工程の遅延や品質性能の確保等が問題になっている。
(Problems to be Solved by the Invention) However, in the above-mentioned conventional method, many parts rely on on-site construction, and the construction of the parts requires specialized engineers such as steelwork, formwork, and rebar construction. In recent years, it has become difficult to secure personnel due to the chronic shortage of construction engineers. For this reason, there are problems such as process delays and quality assurance.

本発明は前記従来技術の有する問題点に鑑みて提案され
たもので、その目的とする処は、鉄骨鉄筋コンクリート
造構造物において、構造部材をプレキヤスト化し、現場
施工の省力化と工期の短縮が図られ、更に品質性能が確
保されるプレキヤスト部材による鉄骨鉄筋コンクリート
造構造物の構築方法を提供する点にある。
The present invention has been proposed in view of the problems of the prior art, the purpose of the purpose is to precast the structural members in a steel-framed reinforced concrete structure to save labor in the field construction and shorten the construction period. In addition, the present invention provides a method for constructing a steel-framed reinforced concrete structure using a precast member that ensures quality performance.

(課題を解決するための手段) 前記の目的を達成するため、本発明に係るプレキヤスト
部材による鉄骨鉄筋コンクリート造構造物の構築方法に
よれば、下端部にスプライススリーブが定着された柱主
筋の上端部が柱頭部より突設され、上下端部外側にブラ
ケツト及び梁主筋が突設された鉄骨鉄筋PC柱を所定位置
に建込み、 次いで柱主筋位置にスリーブが埋設され、且つ鉄骨柱部
片が内蔵された柱部片の外周より鉄骨梁部片が岐出され
た柱梁接合PC部材を、前記PC柱上に同PC柱の柱主筋突出
部が前記スリーブを貫通するように設置するとともに、
同スリーブにグラウト材を注入し、 次いで相隣る前記PC柱間に、梁鉄骨及び梁下端主筋を端
部が両端面より突出するように内蔵してなる鉄骨鉄筋PC
梁を建込み、同PC梁の鉄骨梁突出端部及び前記柱梁接合
PC部材における鉄骨梁部片の各ウエブを添板及び高力ボ
ルトで接合するとともに、各フランジを溶接し、且つ前
記PC梁の梁下端主筋及び前記PC柱の梁主筋の各突出端部
を溶接し、 次いで上階の鉄骨鉄筋PC柱を前記下階のPC柱柱頭の柱梁
接合PC部材上に、同部材より突出する下階柱の柱主筋が
前記上階柱のスプライススリーブに嵌入するように建込
み、同上階柱の下部ブラケツトと前記柱梁接合PC部材の
鉄骨梁部片と下階柱の上部ブラケツトとをボルト接合す
るとともに、前記スリーブにグラウト材を注入し、 次いで前記上階のPC柱下端より突設された梁主筋と前記
鉄骨鉄筋PC梁上部に配設された梁上端筋とを溶接し、 次いで上記PC梁間に半PC床板を架設するとともに、同床
板及び前記柱梁接合PC部材並に前記PC梁の接合部並に前
記床板上にコンクリートを打設するものである。
(Means for Solving the Problem) In order to achieve the above object, according to the method for constructing a steel-framed reinforced concrete structure using the precast member according to the present invention, the upper end portion of the column main bar with the splice sleeve fixed to the lower end portion is used. Is installed from the top of the pillar, and the bracket and beam main bar are projected outside the upper and lower ends, and the steel rebar PC column is installed in the specified position, then the sleeve is embedded in the main bar position and the steel column part is built in. A column-beam joining PC member in which the steel beam part is diverted from the outer periphery of the pillar part that has been installed, while the pillar main bar protrusion of the PC pillar is installed on the PC pillar so as to penetrate the sleeve,
A grout material is injected into the same sleeve, and then a steel beam rebar and a beam lower end main bar are embedded between the adjacent PC columns so that the ends project from both end faces.
A beam is built, and the steel beam protruding end of the PC beam and the beam-column connection
Weld each web of the steel beam part of the PC member with an attachment plate and high-strength bolts, weld each flange, and weld each projecting end of the beam bottom main bar of the PC beam and the beam main bar of the PC column. Then, the steel reinforced PC columns of the upper floor are then connected to the beam-joined PC member of the PC column stigma of the lower floor, and the column main bars of the lower floor columns protruding from the member are fitted into the splice sleeves of the upper floor columns. Built in the same, while bolting the lower bracket of the upper floor pillar and the steel beam part of the column beam joint PC member and the upper bracket of the lower floor pillar, injecting grout material into the sleeve, and then the upper floor Weld the beam main bar projecting from the lower end of the PC column and the beam upper bar placed on the steel frame rebar PC beam upper part, and then erection a half-PC floor plate between the PC beams, and join the same floor plate and the column-beam joint Concrete on the floor board as well as the PC member as well as the joint of the PC beam. The door is intended to pouring.

(作用) 本発明によれば前記したように、所定位置に建込まれた
鉄骨鉄筋PC柱上に、鉄骨柱片が内蔵された柱部片の外周
より鉄骨梁部片が岐出された柱梁接合PC部材を設置する
とともに、同部材における前記柱部片に埋設されたスリ
ーブに、前記PC柱の柱頭部より突設された柱主筋を貫通
し、前記スリーブにグラウト材を注入することによっ
て、前記PC柱の柱頭に前記柱梁接合PC部材を一体に固着
するものである。
(Operation) According to the present invention, as described above, on the steel-framed rebar PC column built in a predetermined position, a column where the steel beam part is diverged from the outer periphery of the column part containing the steel frame part. By installing a beam-joined PC member, the sleeve embedded in the pillar portion piece in the same member, through the pillar main bar protruding from the pillar head of the PC pillar, by injecting grout material into the sleeve The column-beam bonded PC member is integrally fixed to the stigma of the PC column.

次いでこのように柱頭に柱梁接合PC部材が一体に設置さ
れた前記PC柱間に、鉄骨鉄筋PC梁を建込み、同PC梁にお
ける梁鉄骨の突出端部、及び、前記柱梁接合PC部材にお
ける柱部片より岐出された鉄骨梁部片の各ウエブを添板
及び高力ボルトで接合するとともに、各フランジを溶接
し、且つ前記鉄骨鉄筋PC梁の梁下端主筋の突出端部と前
記PC柱の上端部における梁筋突出端部を溶接することに
よって、前記鉄骨鉄筋PC梁を相隣る前記鉄骨鉄筋PC柱間
に一体に接合するものである。
Then, between the PC columns in which the column-beam joining PC members are integrally installed on the sill like this, a steel-frame-reinforced PC beam is built, the projecting end of the beam steel frame in the PC beam, and the column-beam joining PC member While joining each web of the steel beam part piece diverged from the pillar part piece with the addition plate and the high-strength bolt, welding each flange, and the projecting end part of the beam lower end main bar of the steel frame rebar PC beam and the above By welding the projecting end portion of the beam reinforcement at the upper end portion of the PC column, the steel frame reinforcement PC beams are integrally joined between the adjacent steel frame reinforcement PC columns.

次いで上階の鉄骨鉄筋PC柱を下階の鉄骨鉄筋PC柱上に建
込み、同PC柱のスプライススリーブに同下階のPC柱上に
接合された柱梁接合PC部材より上方に突出する柱主筋を
嵌入せしめ、上下階のPC柱の各ブラケットと前記柱梁接
合PC部材の鉄骨梁部片とをボルト接合するとともに、前
記スリーブにグラウト材を注入することによって、上下
の鉄骨鉄筋PC柱を一体に接合する。
Next, the steel reinforced PC columns on the upper floor are built on the steel reinforced PC columns on the lower floor, and the splice sleeves of the PC columns are joined to the PC columns on the lower floor. Insert the main bar, while bolting each bracket of the upper and lower PC columns and the steel beam beam piece of the beam-column joining PC member, and by injecting grout material into the sleeve, the upper and lower steel rebar PC columns Join together.

次いで前記PC梁間に半PC床板を架設し、同床板上、及び
同床板と前記PC梁柱梁接合PC部材の接合部にコンクリー
トを打設し、以下前記同様の工程を反覆して、プレキヤ
スト化された柱,梁,床部材によって鉄骨鉄筋コンクリ
ート構造物を構築するものである。
Next, a half-PC floorboard is installed between the PC beams, concrete is placed on the floorboard, and at the joint between the floorboard and the PC beam column-beam joint PC member, and the same steps as above are repeated, and precast. A steel-framed reinforced concrete structure is constructed from the columns, beams, and floor members that have been constructed.

(実施例) 以下本発明を図示の実施例について説明する。(Examples) The present invention will be described below with reference to illustrated examples.

(A)は鉄骨鉄筋PC柱で、階床面から梁下までの高さを
有し、柱主筋(1)の下端部にはスプライススリーブ
(2)が定着され、上端部は柱頭部より梁成に鉄筋継手
長さを加算した長さ分、突出されている。
(A) is a steel reinforced PC column, having a height from the floor to the bottom of the beam, a splice sleeve (2) is fixed to the lower end of the column main bar (1), and the upper end is a beam from the column head It is projected by the length of the reinforcing bar joint length added.

(3)は帯筋を示す。更に前記PC柱(A)の上下端部に
は同柱に内蔵された柱鉄骨(4)に接合されたブラケッ
ト(5)(5′)が水平に突設されるとともに、柱を貫
通する梁下端主筋(6)及び梁上端主筋(6′)が突設
されている。
(3) shows the stirrups. Further, brackets (5) and (5 ') joined to a pillar steel frame (4) built in the PC pillar (A) are horizontally projected at the upper and lower ends of the PC pillar (A), and a beam penetrating the pillar. A lower end main bar (6) and a beam upper end main bar (6 ') are projected.

(B)は柱梁接合PC部材で、前記PC柱(A)の柱鉄骨
(4)と同一断面の柱鉄骨(7)が内蔵され、柱主筋位
置に柱主筋貫通スリーブ(8)が埋設された柱部片
(9)の外周に、前記柱鉄骨(7)に接合されたH型鋼
製鉄骨梁部片(10)が岐出され、同鉄骨梁部片(10)の
上下フランジとウエブとの間に亘って函型スチフナー
(11)が一体に接合されている。
(B) is a beam-column jointed PC member, and a column steel frame (7) having the same cross section as the column steel frame (4) of the PC column (A) is built in, and a column main bar penetrating sleeve (8) is embedded in the column main bar position. The H-shaped steel beam member (10) joined to the pillar steel frame (7) is extended to the outer periphery of the pillar member (9), and the upper and lower flanges and the web of the steel beam member (10) are joined. A box-shaped stiffener (11) is integrally joined to and.

(C)は鉄骨鉄筋PC梁で、同梁に内蔵された梁鉄骨(1
2)及び梁下端主筋(13)の端部が梁端面より突出して
いる。
(C) is a steel rebar reinforced PC beam, and the beam steel frame (1
2) and the ends of the beam bottom main bars (13) project from the beam end face.

図中(14)は肋筋である。(14) in the figure is the ribs.

而して前記鉄骨鉄筋PC柱(A)を所定位置に垂直に建込
み床面より突出する下階柱の柱主筋、または柱据付用鉄
筋を前記柱(A)の柱主筋(1)下端に定着されたスプ
ライススリーブ(2)に嵌入するとともに、斜めサポー
ト(15)で固定し、前記スリーブ(2)に無収縮モルタ
ルを注入する。(第1図参照) なお第1図は最下階のPC柱(A)を示している。
Then, the steel rebar PC column (A) is vertically installed at a predetermined position and the column main bar of the lower floor column projecting from the floor surface or the column installation rebar is attached to the lower end of the column main bar (1) of the column (A). It is fitted into the fixed splice sleeve (2) and fixed with an oblique support (15), and non-shrink mortar is poured into the sleeve (2). (See Fig. 1) Fig. 1 shows the PC pillar (A) on the bottom floor.

次いで柱梁接合PC部材(B)を前記PC柱(A)の柱頭に
落し込み、(第2図参照)鉄骨梁部片(10)をPC柱
(A)上部のブラケット(5)に着座せしめるととも
に、柱主筋貫通スリーブ(8)に柱主筋(1)の突出端
部を貫通し、同スリーブ(8)にグラウト材を注入して
前記柱梁PC部材(B)をPC柱(A)の柱頭に固定する。
Then, the column-beam joining PC member (B) is dropped onto the stigma of the PC column (A), and the steel beam part (10) is seated on the bracket (5) above the PC column (A). At the same time, the projecting end portion of the column main bar (1) is pierced through the column main bar penetrating sleeve (8), and grout material is injected into the sleeve (8) to replace the column beam PC member (B) with the PC column (A). Fix to the stigma.

次いでX,Y両方向に相隣る前記PC部材(B)が接合され
たPC柱(A)間に前記鉄骨鉄筋PC梁(C)を架設し、
(第3図参照)前記柱梁接合PC部材(B)の鉄骨梁部片
(10)と前記PC梁(C)の梁鉄骨(12)のウエブとに跨
って添板(16)を添接し、高力ボルト(17)で接合する
とともに、フランジ間を溶接し、前記PC梁(C)の梁下
端主筋(13)と前記柱梁接合PC部材(B)の梁鉄筋
(6)とをエンクローズ溶接によって添接する。
Next, the steel rebar PC beam (C) is installed between the PC columns (A) to which the PC members (B) adjacent to each other in both X and Y directions are joined,
(See FIG. 3) An attachment plate (16) is affixed across the steel beam portion (10) of the column-beam joint PC member (B) and the web of the beam steel frame (12) of the PC beam (C). , The high-strength bolts (17) are joined, and the flanges are welded to each other, and the beam bottom main bar (13) of the PC beam (C) and the beam rebar (6) of the column-beam bonded PC member (B) are connected. It is attached by close welding.

次いで上階の鉄骨鉄筋PC柱(A′)を、下階の柱梁接合
PC部材(B)における柱主筋貫通スリーブ(8)を貫通
して突出する下階のPC柱(A)の柱主筋(1)の突出部
に挿入して、同柱主筋(1)を前記上階PC柱(A′)の
スリーブに嵌入せしめるとともに、上階のPC柱(A)の
下端ブラケット(5′)を前記柱梁接合PC部材(B)の
鉄骨梁部片(10)上に着座せしめ、前記ブラケット
(5′)及び下階柱(A)のブラケット(5)並に鉄骨
梁部片(10)を、同梁部片(10)のウエブ補強用スチフ
ナー(11)及び上下フランジを貫通する長尺の高力ボル
ト(18)で締付け固定し、前記PC柱(A)の垂直を確認
したのち、斜めサポート(19)で固定し、同柱(A)の
スプライススリーブ(2)に無収縮モルタルをグラウト
する。(第4図参照) 次いで前記柱梁接合PC部材(B)上における上階PC柱
(A′)の梁鉄筋(6′)と梁上端主筋(20)とを溶着
し、前記PC梁(C)及びPC柱(A)(A′)の各梁主筋
接合部分に肋筋(21)を配筋し、型枠組立て後、相隣る
前記PC梁(C)間に、トラス鉄筋の一部が板面に突出し
た公知の半PC床板(D)を架設し、同床板(D)上及び
前記柱梁接合PC部材(B)、PC梁(C)及び床板(D)
の接合部にコンクリート(E)を打設してこれらの部材
を一体化し、(第5図参照)以下前記の工程を反覆して
プレキヤスト部材による鉄骨鉄筋コンクリート造構築物
の構築するものである。
Next, connect the steel-framed steel reinforced PC column (A ') on the upper floor to the beam-column connection on the lower floor.
The column main bar (1) of the PC member (B) is inserted into the projecting portion of the column main bar (1) of the PC column (A) on the lower floor, which protrudes through the column main bar penetrating sleeve (8), and the column main bar (1) is inserted above. It is fitted into the sleeve of the PC pillar (A ') on the floor, and the lower end bracket (5') of the PC pillar (A) on the upper floor is seated on the steel beam part (10) of the pillar-beam-joined PC member (B). The bracket (5 '), the bracket (5) of the lower floor pillar (A), the steel beam part (10), the web reinforcing stiffener (11) and the upper and lower flanges of the beam part (10). Tighten and fix it with a long high-strength bolt (18) that passes through, check the verticality of the PC pillar (A), and then fix it with the diagonal support (19), and attach it to the splice sleeve (2) of the pillar (A). Grout non-shrink mortar. (See FIG. 4) Next, the beam reinforcements (6 ') of the upper floor PC columns (A') and the beam upper end reinforcements (20) on the column-beam jointed PC member (B) are welded together, and the PC beams (C ) And PC columns (A) and (A ') with ribs (21) at the main beam joints of each beam, and after assembling the formwork, a part of the truss rebar between the adjacent PC beams (C). A publicly known semi-PC floor board (D) protruding from the board surface is installed, and the above-mentioned floor board (D) and the above-mentioned beam-column-joined PC member (B), PC beam (C) and floor board (D)
Concrete (E) is poured into the joint of (1) to integrate these members (see FIG. 5), and the above steps are repeated to construct a steel-framed reinforced concrete structure using precast members.

(発明の効果) 本発明によれば前記したように、従来現場施工していた
鉄骨鉄筋コンクリート柱及び柱梁接合部、鉄骨鉄筋コン
クリート梁,床板を工場生産化したプレキヤスト化構造
部材より構成し、これらの部材を現場で組立せて鉄骨鉄
筋コンクリート構造物を構築するようにし、躯体工事の
内、殆んどの構造部材を工場生産することによって、現
場での専門技能員を大幅に削減し、現場施工の省力化を
図り、工期を短縮し、品質性能を向上しうるものであ
る。
(Effects of the Invention) According to the present invention, as described above, the steel-framed reinforced concrete columns and beam-column joints, which were conventionally constructed on-site, the steel-framed reinforced concrete beams, the floorboards are made of precast cast structural members, and these By assembling members on-site to construct a steel-framed reinforced concrete structure, and by producing most of the structural members at the factory in the frame work, the number of specialists on site is greatly reduced, and labor saving on-site is reduced. It is possible to improve the quality and performance by shortening the construction period.

請求項2の発明は、前記柱梁接合PC部材における鉄骨梁
部片のウエブ部に函型スチフナーを配設して、同鉄骨梁
部片を補剛するとともに、上下階各鉄骨鉄筋PC柱のブラ
ケツトとをボルト接合することによって、同PC柱を前記
柱梁接合PC部材を介して一体的に接合しうるものであ
る。
According to a second aspect of the present invention, a box stiffener is provided in the web portion of the steel beam beam piece in the beam-column-bonded PC member to stiffen the steel beam beam piece, and at the same time, the upper and lower steel frame rebar PC columns By bolting the bracket and the bracket, the PC column can be integrally joined via the column-beam joining PC member.

請求項3の発明は、前記鉄骨鉄筋PC柱を階床面から梁下
までの高さとし、柱主筋と梁鉄骨とを内蔵し、同柱主筋
の上端は柱頭より突出せしめ、下端には下階柱の柱主筋
接合用スプライススリーブを定着して、上下の柱主筋を
一体に接合しうるようにし、また柱の上下端にはブラケ
ツトを突設したことと相俟って、上下柱を一体的に接合
しうるようにするとともに、PC柱端部より梁主筋を突設
して、PC柱間に架設される鉄骨鉄筋PC梁の下端主筋及び
上端主筋と確実に接合されるようにしたものである。
In the invention of claim 3, the steel rebar PC column has a height from the floor to the bottom of the beam, the column main bar and the beam steel are built in, the upper end of the main bar of the column is projected from the stigma, and the lower end is at the lower floor. By fixing the splice sleeve for connecting the pillar main bars of the pillars so that the upper and lower pillar main bars can be integrally bonded, and in addition to the fact that brackets are projected on the upper and lower ends of the pillars, the upper and lower pillars are integrated. In addition to making it possible to connect to the PC column, the main beam of the beam is projected from the end of the PC column so that it can be securely connected to the lower and upper main bars of the steel frame rebar PC beam installed between the PC columns. is there.

請求項4の発明は、前記PC柱の柱鉄骨と同一断面の柱鉄
骨及び柱主筋貫通スリーブを内蔵した柱部片の外周よ
り、前記柱鉄骨に接続された鉄骨梁部片を岐出したこと
によって、前記PC柱の柱頭にこれと一体的に取付けられ
るようにするとともに、鉄骨鉄筋PC梁を簡単確実に接合
しうるようにしたものである。
According to a fourth aspect of the present invention, the steel beam portion connected to the column steel frame is diverged from the outer periphery of the column portion including the column steel frame having the same cross-section as the column steel frame of the PC column and the column main bar penetrating sleeve. Thus, the PC pillar can be integrally attached to the stigma of the PC pillar, and the steel frame rebar PC beam can be simply and surely joined.

【図面の簡単な説明】[Brief description of drawings]

第1図乃至第5図は本発明に係るプレキヤスト部材によ
る鉄骨鉄筋コンクリート造構造物の構築方法の一実施例
の工程を示す正面図、第6図は柱梁接合部を示す正面
図、第7図は柱頭部を示す平面図、第8図及び第9図は
夫々鉄骨鉄筋PC柱の正面図並に斜視図、第10図は柱梁接
合PC部材の斜視図、第11図は前記PC柱の柱頭に柱梁接合
PC柱部材を設置した状態を示す斜視図、第12図は鉄骨鉄
筋PC梁の正面図である。 (A)……鉄骨鉄筋PC柱、(B)……柱梁接合PC部材、
(C)……鉄骨鉄筋PC梁、(D)……半PC床板、(E)
……コンクリート、(1)……柱主筋、(2)……スプ
ライススリーブ、(4)……柱鉄骨、(5)(5′)…
…ブラケツト、(6)(6′)……梁鉄筋、(8)……
柱主筋貫通スリーブ、(9)……柱部片、(10)……鉄
骨梁部片、(11)……スチフナー、(12)……梁鉄骨、
(13)……梁下端主筋、(16)……添板、(17)(18)
……高力ボルト、(20)……梁上端筋。
1 to 5 are front views showing steps of an embodiment of a method for constructing a steel-framed reinforced concrete structure using a precast member according to the present invention, FIG. 6 is a front view showing a beam-column joint, and FIG. Is a plan view showing a stigma, FIG. 8 and FIG. 9 are perspective views along with a front view of a steel-framed rebar PC column, FIG. 10 is a perspective view of a column-beam joining PC member, and FIG. Beam-to-column connection to stigma
FIG. 12 is a perspective view showing a state in which a PC column member is installed, and FIG. 12 is a front view of a steel frame rebar PC beam. (A) …… Steel frame rebar PC column, (B) …… Column beam joint PC member,
(C) …… Steel frame reinforced PC beam, (D) …… Semi-PC floor board, (E)
…… Concrete, (1) …… Column main bar, (2) …… Splice sleeve, (4) …… Column steel frame, (5) (5 ′)…
… Bracket, (6) (6 ′) …… Beam rebar, (8) ……
Column main bar through sleeve, (9) …… Column piece, (10) …… Steel beam piece, (11) …… Stiffener, (12) …… Beam steel frame,
(13) …… Main beam bottom beam, (16) …… Additional plate, (17) (18)
…… High-strength bolt, (20) …… Beam top beam.

Claims (4)

【特許請求の範囲】[Claims] 【請求項1】下端部にスプライススリーブが定着された
柱主筋の上端部が柱頭部より突設され、上下端部外側に
ブラケツト及び梁主筋が突設された鉄骨鉄筋PC柱を所定
位置に建込み、 次いで柱主筋位置にスリーブが埋設され、且つ鉄筋柱部
片が内蔵された柱部片の外周より鉄骨梁部片が岐出され
た柱梁接合PC部材を、前記PC柱上に同PC柱の柱主筋突出
部が前記スリーブを貫通するように設置するとともに、
同スリーブにグラウト材を注入し、 次いで相隣る前記PC柱間に、梁鉄骨及び梁下端主筋を端
部が両端面より突出するように内蔵してなる鉄骨鉄筋PC
梁を建込み、同PC梁の鉄骨梁突出端部及び前記柱梁接合
PC部材における鉄骨梁部片の各ウエブを添板及び高力ボ
ルトで接合するとともに、各フランジを溶接し、且つ前
記PC梁の梁下端主筋及び前記PC柱の梁主筋の各突出端部
を溶接し、 次いで上階の鉄骨鉄筋PC柱を前記下階のPC柱柱頭の柱梁
接合PC部材上に、同部材より突出する下階柱の柱主筋が
前記上階柱のスプライススリーブに嵌入するように建込
み、同上階柱の下部ブラケツトと前記柱梁接合PC部材の
鉄骨梁部片と下階柱の上部ブラケツトとをボルト接合す
るとともに、前記スリーブにグラウト材を注入し、 次いで前記上階のPC柱下端より突設された梁主筋と前記
鉄骨鉄筋PC梁上部に配設された梁上端筋とを溶接し、 次いで前記PC梁間に半PC床板を架設するとともに、同床
板及び前記柱梁接合PC部材並に前記PC梁の接合部並に前
記床板上にコンクリートを打設することを特徴とするプ
レキヤスト部材による鉄骨鉄筋コンクリート造構造物の
構築方法。
1. A steel-framed PC column with a splice sleeve fixed to the lower end, the upper end of the column main bar protruding from the column head, and the bracket and the beam main bar projecting outside the upper and lower ends at a predetermined position. Next, the column-beam joining PC member in which the sleeve is embedded in the main column position of the column and the steel beam part is diverged from the outer periphery of the column part with the built-in rebar column part Installed so that the pillar main bar protrusion of the pillar penetrates the sleeve,
A grout material is injected into the same sleeve, and then a steel beam rebar and a beam lower end main bar are embedded between the adjacent PC columns so that the ends project from both end faces.
A beam is built, and the steel beam protruding end of the PC beam and the beam-column connection
Weld each web of the steel beam part of the PC member with an attachment plate and high-strength bolts, weld each flange, and weld each projecting end of the beam bottom main bar of the PC beam and the beam main bar of the PC column. Then, the steel reinforced PC columns of the upper floor are then connected to the beam-joined PC member of the PC column stigma of the lower floor, and the column main bars of the lower floor columns protruding from the member are fitted into the splice sleeves of the upper floor columns. Built in the same, while bolting the lower bracket of the upper floor pillar and the steel beam part of the column beam joint PC member and the upper bracket of the lower floor pillar, injecting grout material into the sleeve, and then the upper floor Weld the beam main bar projecting from the lower end of the PC column and the beam upper bar arranged on the steel beam rebar PC beam upper part, and then erection a half-PC floor plate between the PC beams and joining the same floor plate and the column-beam joint. Concrete on the floor board as well as the PC member as well as the joint of the PC beam. Method for constructing a steel reinforced concrete structure according Purekiyasuto member, characterized by pouring the door.
【請求項2】前記柱梁接合PC部材における鉄骨梁部片の
ウエブ部に函型のスチフナーが配設され、同スチフナー
と上下階各PC柱のブラケツトとをボルト接合する請求項
1記載のプレキヤスト部材による鉄骨鉄筋コンクリート
造構造物の構築方法。
2. The precast according to claim 1, wherein a box-shaped stiffener is disposed on the web portion of the steel beam portion of the column-beam joining PC member, and the stiffener is bolted to the brackets of the PC columns on the upper and lower floors. Construction method of steel-framed reinforced concrete structure by members.
【請求項3】前記鉄骨鉄筋PC柱は、階床面より梁下まで
の高さを有し、鉄骨柱と柱主筋とを内蔵し、同柱主筋は
下端部にスプライススリーブが定着され、上端部は柱頭
より突設され、柱の上下両端部外周にブラケツト及び梁
主筋が突設された請求項1記載のプレキヤスト部材によ
る鉄骨鉄筋コンクリート造構造物の構築方法。
3. The steel-reinforced steel-reinforced concrete column has a height from the floor surface to a lower part of the beam and has a built-in steel-framed column and a column main bar, and the column main bar has a splice sleeve fixed to the lower end and an upper end. 2. The method for constructing a steel-framed reinforced concrete structure using a precast member according to claim 1, wherein the portion is projected from the stigma, and the bracket and the beam main bar are projected on the outer circumferences of the upper and lower ends of the pillar.
【請求項4】前記柱梁接合PC部材を、前記PC柱の柱鉄骨
と同一断面の柱鉄骨、及び柱主筋貫通スリーブが内蔵さ
れた柱部片の外周より、前記柱鉄骨に接続された鉄骨梁
部片が岐出された請求項1記載のプレキヤスト部材によ
る鉄骨鉄筋コンクリート造構造物の構築方法。
4. A steel frame in which the column-beam joining PC member is connected to the column steel frame from an outer periphery of a column steel frame having the same cross section as the column steel frame of the PC column and a column main bar penetrating sleeve embedded therein. The method for constructing a steel-framed reinforced concrete structure using the precast member according to claim 1, wherein the beam pieces are diverged.
JP1090598A 1989-04-12 1989-04-12 Construction method of steel-framed reinforced concrete structure using precast members Expired - Lifetime JPH0726439B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP1090598A JPH0726439B2 (en) 1989-04-12 1989-04-12 Construction method of steel-framed reinforced concrete structure using precast members

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP1090598A JPH0726439B2 (en) 1989-04-12 1989-04-12 Construction method of steel-framed reinforced concrete structure using precast members

Publications (2)

Publication Number Publication Date
JPH02272124A JPH02272124A (en) 1990-11-06
JPH0726439B2 true JPH0726439B2 (en) 1995-03-22

Family

ID=14002908

Family Applications (1)

Application Number Title Priority Date Filing Date
JP1090598A Expired - Lifetime JPH0726439B2 (en) 1989-04-12 1989-04-12 Construction method of steel-framed reinforced concrete structure using precast members

Country Status (1)

Country Link
JP (1) JPH0726439B2 (en)

Also Published As

Publication number Publication date
JPH02272124A (en) 1990-11-06

Similar Documents

Publication Publication Date Title
JPH03250130A (en) Constructing method using reinforced steel framed reinforced half-precast concrete beam without main reinforcing steel
JPH02136444A (en) Construction of composite structure consisting of precast reinforced concrete column and steel structural beam
JPH0726440B2 (en) Method of joining steel-reinforced bar precast concrete columns and steel beams
JPH06212691A (en) Construction of building
JP3766940B2 (en) Seismic reinforcement method for existing buildings
JPH0726439B2 (en) Construction method of steel-framed reinforced concrete structure using precast members
JPH08284311A (en) Precast concrete column member in composite structure, and construction of building using it
JPH11166294A (en) Steel frame-contained concrete beam and floor construction method using the concrete beam
JP2516808B2 (en) Construction method of ramen type precast concrete structure
JPH03132532A (en) Construction method of precast reinforced concrete column and beam
JP2758208B2 (en) Joint method between column and steel reinforced concrete beam
JPH0380946B2 (en)
JPH0781307B2 (en) How to build a skyscraper
JPH0732706Y2 (en) Reinforcement structure of precast reinforced concrete columns and crossed steel frames for joining steel beams
JP2516820B2 (en) Frame of SRC structure
JPH0366878A (en) Construction method for precast column and beam and precast anti-seismic wall
JPH0833021B2 (en) How to build a skyscraper
JPH07103620B2 (en) Construction method for steel structure
JP2656175B2 (en) Column-beam joint structure
JPS6195136A (en) Construction of multistoried building skeletal by precast reinforced concrete unit
JP3125165B2 (en) Warehouse frame
JPH10131353A (en) Precast reinforced concrete made continuous layer earthquake resisting wall
JPH0762740A (en) Joint method for precast steel framed reinforced concrete construction pillar and beam
JPH09177239A (en) Precast reinforced concrete beam and its framing method
JPH02167939A (en) Construction work of precast steel framed, reinforced concrete structure

Legal Events

Date Code Title Description
A711 Notification of change in applicant

Effective date: 20040521

Free format text: JAPANESE INTERMEDIATE CODE: A711

A711 Notification of change in applicant

Effective date: 20040521

Free format text: JAPANESE INTERMEDIATE CODE: A712

A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20050114

RD02 Notification of acceptance of power of attorney

Effective date: 20050114

Free format text: JAPANESE INTERMEDIATE CODE: A7422

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20050119

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20071026

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20071113

A02 Decision of refusal

Effective date: 20080306

Free format text: JAPANESE INTERMEDIATE CODE: A02