JPH072521U - Base for temporary protective fence - Google Patents
Base for temporary protective fenceInfo
- Publication number
- JPH072521U JPH072521U JP030890U JP3089093U JPH072521U JP H072521 U JPH072521 U JP H072521U JP 030890 U JP030890 U JP 030890U JP 3089093 U JP3089093 U JP 3089093U JP H072521 U JPH072521 U JP H072521U
- Authority
- JP
- Japan
- Prior art keywords
- base
- pillar
- forming body
- support
- hole forming
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Landscapes
- Refuge Islands, Traffic Blockers, Or Guard Fence (AREA)
- Fencing (AREA)
Abstract
(57)【要約】
【目的】本考案は、仮設防護柵を分解可能な構造にする
とともに、防護柵の基台の体積を抑えてコンパクトな構
造とし、仮設防護柵の設置スペースを小さくし、かつ、
積み重ね可能にして保管や運搬を容易とし、さらに何回
でも繰り返して仮設できることを目的とする。
【構成】本考案の仮設防護柵用基台は、金属製中空基台
2の内に支柱穴形成体3を立設し、中空基台2の中空部
16に金属片15を充填し、支柱穴形成体3に支柱4を
縦方向に挿脱自在とし、支柱4を支柱穴形成体3に取付
け部材11,12,13等で着脱自在としてなることを
特徴とするものである。
(57) [Summary] [Purpose] The present invention has a structure in which the temporary protective fence can be disassembled, and the volume of the base of the protective fence is suppressed to a compact structure to reduce the installation space of the temporary protective fence. And,
The purpose is to make them stackable for easy storage and transportation, and to be able to be temporarily installed any number of times. [Structure] In the temporary protection fence base of the present invention, a pillar hole forming body 3 is erected in a metal hollow base 2, and a hollow portion 16 of the hollow base 2 is filled with metal pieces 15 to form a pillar. It is characterized in that the support column 4 can be inserted into and removed from the hole forming body 3 in the vertical direction, and the support column 4 can be attached to and detached from the support hole forming body 3 by attaching members 11, 12, 13 and the like.
Description
【0001】[0001]
本考案は、道路等に仮設される仮設防護柵用基台に関するものである。 The present invention relates to a temporary protection fence base temporarily installed on a road or the like.
【0002】[0002]
従来の仮設防護柵は、コンクリート基台の縦穴に支柱を差し込んでモルタルを 流し込んで固定し、前記コンクリート基台を道路に所定間隔で配置し、前記支柱 でガードレールを連結し支持してなるものであった。 A conventional temporary protection fence is one in which a pillar is inserted into a vertical hole of a concrete base and mortar is poured and fixed, the concrete base is arranged at a predetermined interval on the road, and a guard rail is connected and supported by the pillar. there were.
【0003】[0003]
しかしながら、従来のコンクリート製仮設防護柵では、コンクリートの比重が 約2kgf/lであり、安全性確保のため一定重量以上を確保するためにはコン クリート基台の体積を大きくしなければならず、仮設防護柵の設置スペースが増 大してしまうといった欠点があった。また、コンクリート製仮設防護柵を道路か ら撤去した後には、廃棄の問題が生ずるし、また保管して再度利用するにしても 、解体できない構造であるので保管や運搬等の際に積み重ねることができず、余 分なスペースを取り非常に不便であった。 However, in the conventional concrete temporary protection fence, the specific gravity of concrete is about 2 kgf / l, and in order to secure a certain weight or more to ensure safety, the volume of the concrete base must be increased. There was a drawback that the installation space for temporary protective fences increased. Also, after removing the concrete temporary protection fence from the road, there is a problem of disposal, and even if it is stored and reused, it is a structure that cannot be dismantled, so it may be stacked during storage or transportation. I couldn't do that, and it took up extra space and was very inconvenient.
【0004】 そこで、本考案は、仮設防護柵を分解可能な構造にするとともに、防護柵の基 台の体積を抑えてコンパクトな構造として仮設防護柵の設置スペースを小さくし 、かつ、積み重ね可能にして保管や運搬等を容易とし、さらに何回でも繰り返し て仮設できることによって資源の有効活用を図ることを目的とする。In view of this, the present invention has a structure in which the temporary protective fence can be disassembled, and the volume of the base of the protective fence is suppressed to make the installation space of the temporary protective fence small and stackable as a compact structure. The aim is to make effective use of resources by facilitating storage and transportation, etc., and by allowing temporary construction repeatedly.
【0005】[0005]
かかる目的を達成するため、本考案は、支柱が上下方向に挿脱自在な支柱穴形 成体を金属製の中空基台に立設し、該中空基台の中空部に金属片を充填し、前記 支柱を支柱穴形成体に取付け部材で着脱自在にしてなることを特徴とする仮設防 護柵用基台を要旨とするものである。また、本考案は、支柱が上下方向に挿脱自 在な支柱穴を金属製の基台に立設し、前記支柱を支柱穴に取付け部材で着脱自在 としてなることを特徴とする仮設防護柵用基台を要旨とするものである。 In order to achieve such an object, the present invention provides a pillar hole forming body in which a pillar is vertically insertable and detachable, standing on a metal hollow base, and filling the hollow portion of the hollow base with a metal piece. The gist of the present invention is a temporary protection fence base, characterized in that the pillar is detachably attached to the pillar hole forming member with a mounting member. Further, the present invention is a temporary protection fence characterized in that a pillar hole is vertically inserted and removed, and a pillar hole is erected on a metal base, and the pillar is attachable to and detachable from the pillar hole by a mounting member. It is based on the use base.
【0006】[0006]
本考案は、仮設防護柵を基台と支柱とに分解可能な構造としたので、基台を積 み重ねることができ場所をとらないことから保管や運搬等が極めて容易であり、 かつ、何回でも繰り返して仮設できるのである。また本考案の金属製中空基台に 金属片が充填されているので、基台の比重を増加させることによって仮設防護柵 の基台の体積を抑えて小型の構造とすることができ、設置スペースを小さくする ことができるし、さらに金属片が加工屑であれば資源の有効利用となるのである 。また、中空部を設けない仮設防護柵用基台では、鋳型により一体成形する等に より製造工程が効率化されるとともに、設置作業が簡素化され、また、比重が増 大することにより基台の体積を更に小さくできるのである。 Since the present invention has a structure in which the temporary protective fence can be disassembled into a base and columns, the bases can be stacked and occupy no space, so storage and transportation are extremely easy, and It can be temporarily and repeatedly installed. Moreover, since the metal hollow base of the present invention is filled with metal pieces, the volume of the base of the temporary protection fence can be suppressed by increasing the specific gravity of the base, and a small structure can be achieved. Can be reduced, and if the metal pieces are processing scraps, the resources can be effectively used. In addition, with a temporary protective fence base without a hollow part, the manufacturing process is streamlined by integrally molding with a mold, the installation work is simplified, and the specific gravity is increased to increase the base. The volume of can be further reduced.
【0007】[0007]
以下、本考案の第一実施例を図面に基づいて説明する。図1に示すように、仮 設防護柵1は、鋼製で中空直方体形状に形成された基台2と、基台2の内部に設 けられた支柱穴形成体3と、ボルトやナット等の取り付け部材により支柱穴形成 体3に着脱自在な支柱4と、この支柱4に着脱自在なガードレール5とからなっ ており、基台2が道路に適宜の間隔をもって複数設置されているものである。 Hereinafter, a first embodiment of the present invention will be described with reference to the drawings. As shown in FIG. 1, the temporary protective fence 1 includes a base 2 made of steel in the shape of a hollow rectangular parallelepiped, a support hole forming body 3 provided inside the base 2, bolts, nuts, etc. It is composed of a pillar 4 which can be freely attached to and detached from the pillar hole forming member 3 by a mounting member and a guardrail 5 which can be freely attached to and detached from the pillar 4, and a plurality of bases 2 are installed on the road at appropriate intervals. .
【0008】 次に図2,図3に基づいて、基台2の内部構造を説明する。基台2の内部には 、支柱4を縦方向に挿脱自在な鋼製パイプからなる支柱穴形成体3が立設されて いる。すなわち、この支柱穴形成体3の下端部が基台2の底板2aに溶接により 固着されているのである。また基台2の側板2bに丸孔6が、支柱穴形成体3に 丸孔7と丸穴8が、支柱4の側壁に縦長孔9,10(図5)が、直径方向に一直 線上に整列して穿設されている。また鋼製の案内管11が側板2bと支柱穴形成 体3とに溶接されて、基台2の内部において、丸孔6と丸孔7とを水平に連通し ている。案内管11は、ボルト12を横方向から挿入するだけで支柱4と支柱穴 形成体3とを容易に直径方向に貫通することができるようにして、煩雑な位置合 わせを不要とするため設けられたものである。そして、ナット13が支柱穴形成 体3に固着され、丸穴8がナット13の穴として形成され、支柱穴形成体3の内 部の空隙部と丸穴8とが連通しているので、ボルト12の先端部が丸穴8にねじ こまれるようになっている。このようにして、ボルト12を挿通するための通路 が水平方向に一直線状に形成されているので、ボルト12を図で右方向から水平 に基台2に挿入すると、丸孔6、案内管11、丸孔7、及び縦長孔9,10を貫 通できることとなる。そして、ボルト12を締めることにより、ボルト12と、 ナット13とが螺合して、支柱4が支柱穴形成体3に取り付けられ、支柱4が基 台2から抜けないようになるのである。また、側板2bには、凹部14が設けら れており、ボルト12が基台2の外表面から突出しないようにしている。また、 鋼片15が基台2の中空部16にまんべんなく充填されており、基台2の比重を 増加させている。したがって、基台2の全体重量を一定以上にして安全性を確保 するとともに、基台2を小型にするという要求を満足させているのである。鋼片 15は、鉄鋼板を打ち抜いて製造されているが、加工屑を利用することにすれば 、資源を有効活用できることとなる。さらに、支柱穴形成体3の底部には、スト ッパ板17が水平に設けられ、支柱4を最低位置において支持するようになって いるとともに、支柱穴形成体3が貫通孔ではなく、下端部が閉じられた穴状に形 成されている。また、ストッパ板17には丸孔18が、基台2の底板2aには丸 孔19が、それぞれ設けられており、雨水が溜まらないようにしている。Next, the internal structure of the base 2 will be described with reference to FIGS. 2 and 3. Inside the base 2, a support hole forming body 3 made of a steel pipe in which the support pillar 4 can be inserted and removed in the vertical direction is erected. That is, the lower end of the support hole forming body 3 is fixed to the bottom plate 2a of the base 2 by welding. Further, round holes 6 are formed in the side plate 2b of the base 2, round holes 7 and 8 are formed in the support hole forming body 3, and vertically elongated holes 9 and 10 (FIG. 5) are formed in the side wall of the support 4, in a straight line in the diameter direction. They are aligned and drilled. Further, a steel guide tube 11 is welded to the side plate 2b and the support hole forming body 3 to horizontally connect the round hole 6 and the round hole 7 inside the base 2. The guide tube 11 is provided so that the support 4 and the support hole forming body 3 can be easily penetrated in the diametrical direction only by inserting the bolt 12 from the lateral direction, and complicated positioning is unnecessary. It has been done. Then, the nut 13 is fixed to the strut hole forming body 3, the round hole 8 is formed as a hole of the nut 13, and the void portion inside the strut hole forming body 3 and the round hole 8 communicate with each other. The tip portion of 12 is screwed into the round hole 8. In this way, since the passage for inserting the bolt 12 is formed in a straight line in the horizontal direction, when the bolt 12 is horizontally inserted from the right side in the drawing into the base 2, the round hole 6 and the guide tube 11 are formed. The circular hole 7 and the vertically elongated holes 9 and 10 can be penetrated. Then, by tightening the bolt 12, the bolt 12 and the nut 13 are screwed together, the support 4 is attached to the support hole forming body 3, and the support 4 does not come off from the base 2. Further, the side plate 2b is provided with a recess 14 so that the bolt 12 does not protrude from the outer surface of the base 2. Further, the steel piece 15 is evenly filled in the hollow portion 16 of the base 2 to increase the specific gravity of the base 2. Therefore, the requirement that the entire weight of the base 2 is not less than a certain level to ensure safety and the size of the base 2 is small is satisfied. The steel slab 15 is manufactured by punching out a steel plate, but if processing waste is used, resources can be effectively used. Further, a stopper plate 17 is horizontally provided at the bottom of the support hole forming body 3 to support the support pillar 4 at the lowest position, and the support hole forming body 3 is not a through hole but a lower end. The part is shaped like a closed hole. Further, a round hole 18 is provided in the stopper plate 17 and a round hole 19 is provided in the bottom plate 2a of the base 2 to prevent rainwater from collecting.
【0009】 次に、図3に示すように、基台2の各側板の下端部には切欠20,21が一対 づつ設けられており、工具を差し込んで基台2を持ち上げ、位置調整等ができる ようになっている。基台2の側板2cの中央部には、掛止穴23a,23bが設 けられ、それらに吊下金具を掛止して、クレーン等で基台2をつり上げ、設置や 撤去等ができるようになっている。また、基台2の内壁部2dには鋼製の蓋体2 2を支持するため一部が切り欠かれた縦割パイプ24a,24b,24c,24 dが固着されている。図示するように、蓋体22が矢印方向に取り付け、あるい は、取り外し可能となっているのは、鋼片15を中空部16に充填するためであ る。また、蓋体22には、支柱4を貫通させるための丸孔27と、強度向上のた めの溝体28や目隠し等を設置するための小孔29,30,31,32が設けら れている。丸孔27の直径と、支柱穴形成体3の直径とは、同じ大きさにされて いる。Next, as shown in FIG. 3, a pair of notches 20 and 21 are provided at the lower end of each side plate of the base 2, and a tool is inserted to lift the base 2 to adjust the position. You can do it. Hook holes 23a and 23b are provided at the center of the side plate 2c of the base 2, and hanging metal fittings can be hooked on these so that the base 2 can be lifted by a crane or the like for installation and removal. It has become. Further, vertical split pipes 24a, 24b, 24c, 24d, which are partially cut out, are fixed to the inner wall portion 2d of the base 2 to support the lid 22 made of steel. As shown in the figure, the reason why the lid 22 is attached in the direction of the arrow or is removable is that the steel piece 15 is filled in the hollow portion 16. Further, the lid body 22 is provided with a round hole 27 for penetrating the support column 4 and small holes 29, 30, 31, 32 for installing a groove body 28 for improving strength and a blind. ing. The diameter of the round hole 27 and the diameter of the support hole forming body 3 are the same.
【0010】 次に図4に基づいて支柱4を説明する。支柱4は円管状で頂部が塞がれており 、支柱4には、前述したように、ボルト12を挿通できる縦楕円状の縦長孔9, 10が直径方向に対向するように設けられている。縦長孔10は波状に切り欠か れており、支柱穴形成体5への支柱4の取付位置の高さが調整できるようになっ ている。縦長孔9,10の上には、ガードレール5を取り付けるための取付孔3 3,34が設けられている。これら取付孔にボルト35を挿通し、ナット36に て締めつけてガードレール5を連結して固定するようになっている。Next, the support column 4 will be described with reference to FIG. The column 4 has a circular tubular shape and is closed at the top. As described above, the column 4 is provided with vertically elongated elliptical holes 9 and 10 through which the bolts 12 can be inserted so as to face each other in the diametrical direction. . The vertically elongated hole 10 is notched in a wavy shape so that the height of the mounting position of the pillar 4 on the pillar hole forming body 5 can be adjusted. Mounting holes 33 and 34 for mounting the guardrail 5 are provided on the vertically long holes 9 and 10. Bolts 35 are inserted into these mounting holes and tightened with nuts 36 to connect and fix the guardrails 5.
【0011】 次に、仮設防護柵1の設置について説明する。図2に示すように支柱穴形成体 5が固着された基台2に鋼片15を充填して全体の比重を増大させ、図3に示す ように蓋体22を被せる。次に、図2に示すように、支柱穴形成体3に支柱4を 差し込み、支柱4の高さを調整したあと、ボルト12を基台2の凹部14から横 方向から挿入すると、ボルト12の先端がナット13に到達する。次に、ボルト 12を工具で締めつけて、ボルト12とナット13とを螺合させる。そして、図 1に示すように、道路に所定間隔に基台2を設置し、そして、ボルト35とナッ ト36でガードレール5を支柱4に連結し固定するのである。なお、必要に応じ て、溝体28を連結することができる。Next, the installation of the temporary protective fence 1 will be described. As shown in FIG. 2, the base 2 to which the support hole forming body 5 is fixed is filled with the steel piece 15 to increase the specific gravity of the whole, and the lid body 22 is covered as shown in FIG. Next, as shown in FIG. 2, after inserting the column 4 into the column hole forming body 3 and adjusting the height of the column 4, the bolt 12 is inserted from the recess 14 of the base 2 in the lateral direction. The tip reaches the nut 13. Next, the bolt 12 is tightened with a tool so that the bolt 12 and the nut 13 are screwed together. Then, as shown in FIG. 1, the bases 2 are installed at predetermined intervals on the road, and the guard rails 5 are connected and fixed to the support columns 4 by the bolts 35 and nuts 36. In addition, the groove bodies 28 can be connected as needed.
【0012】 次に、仮設防護柵1の撤去や保管について説明する。まず、ボルト35とナッ ト36の螺合を解除して、ガードレール5を支柱4から外し、次に、ボルト12 とナット13の螺合を解除し、ボルト12を基台2から引き抜き、支柱形成体3 から支柱4を抜く。そうして、基台2と支柱4とガードレール5等をトラックに 積んで倉庫等まで運搬し保管する。基台2は、直方体形状であるので、積み重ね ることができ、場所を取らないため、運搬や保管等が極めて容易である。そして 、次に仮設するときは、これらを仮設場所まで運搬して、組み立てればよいので ある。このようにして、仮設防護柵1は、何回でも繰り返して利用することがで きるのである。Next, the removal and storage of the temporary protective fence 1 will be described. First, the bolt 35 and the nut 36 are unscrewed to remove the guardrail 5 from the column 4, then the bolt 12 and the nut 13 are unscrewed, and the bolt 12 is pulled out from the base 2 to form the column. Pull out the column 4 from the body 3. Then, the base 2, the columns 4, the guardrails 5 and the like are loaded on a truck and transported to a warehouse and stored. Since the base 2 has a rectangular parallelepiped shape, it can be stacked and does not occupy a lot of space, so that it can be transported and stored very easily. Then, at the next temporary installation, these should be transported to the temporary installation site and assembled. In this way, the temporary protective fence 1 can be used repeatedly as many times as desired.
【0013】 次に第一実施例の変形例であるところの第二実施例について説明すると、それ は、基台2に中空部16を設けずに鋳型で一体成形して全体を簡略に構成したも のである。詳しくは、支柱穴形成体3の代わりに、鉄製基台に支柱を受け入れる ための支柱穴が設けられ、ボルト12より長いボルトを受け入れるためのボルト 孔が支柱穴と直交するように、かつ、基台の中央部を貫通するように設けられ、 凹部14と同様の形状の凹部が基台の表面に支柱穴直径方向に対称的に1対設け られ、丸孔18,19の代わりに雨水を排出するため支柱穴から垂直に穿孔され た縦孔が設けられたものである。仮設防護柵を設置するには、支柱穴に支柱を差 し込み、支柱の高さを調整したあと、ボルトを基台の表面にある凹部から横方向 に挿入し、ボルトの先端が基台の反対表面に出るまで、つまり、他の凹部に到達 するまで差し込み、ボルト又はナットを工具で締めつけて、ボルトとナットとを 螺合させ、道路に所定間隔に基台を設置し、そして、ボルトとナットでガードレ ールを支柱に連結し固定するのである。仮設防護柵の解体について説明すると、 まず、ボルトとナットの螺合を解除して、ガードレールを支柱から外し、次に、 ボルトとナットの螺合を解除してボルトを基台から引き抜き、支柱穴から支柱を 抜くのである。第二実施例の効果は、第一実施例の効果とほぼ同様であるが、鋳 型により一体成形する等により製造工程が効率化されるとともに、また、金属片 を中空部に充填する作業や蓋をする作業がなく、基台の比重をより大きくして基 台の体積を更に小さくできるという利点がある。Next, a second embodiment, which is a modification of the first embodiment, will be described. It is formed integrally by a mold without providing the hollow portion 16 in the base 2 and is simply configured as a whole. It is a thing. Specifically, instead of the support hole forming body 3, a support hole for receiving a support is provided in the iron base, and the bolt hole for receiving a bolt longer than the bolt 12 is orthogonal to the support hole, and A pair of recesses that are formed so as to penetrate through the center of the base and have the same shape as the recesses 14 are provided symmetrically in the diameter direction of the support hole on the surface of the base, and rainwater is discharged instead of the round holes 18 and 19. In order to do this, a vertical hole was drilled vertically from the support hole. To install a temporary protective fence, insert the support into the support hole, adjust the height of the support, and then insert the bolts laterally through the recesses on the surface of the base so that the tips of the bolts are on the base. Insert it until it comes out on the opposite surface, that is, until it reaches the other recess, tighten the bolt or nut with a tool, screw the bolt and nut together, install the base at a prescribed interval on the road, and then The nut is used to connect and secure the guard rail to the column. Explaining the dismantling of the temporary protection fence, first, unscrew the bolts and nuts to remove the guardrail from the post, then unscrew the bolts and nuts to pull the bolts out of the base, Remove the pillar from the. The effects of the second embodiment are almost the same as the effects of the first embodiment, but the manufacturing process is streamlined by integrally molding with a casting mold, and the work of filling the hollow portion with metal pieces and There is an advantage that the volume of the base can be further reduced by increasing the specific gravity of the base without the work of covering.
【0014】 なお、本考案の要旨を逸脱しない範囲で本考案の構成を適宜変更しうることは 勿論であり、これらの変更も技術的思想を同一にする限り、本考案に包含される べきものである。例示すれば、基台2、支柱穴形成体3、鋼片15は、実施例で は鉄鋼製であるが、それに限定されず、仮設防護柵として使用できる金属であれ ば良いのである。また、ボルト12とナット13等で、支柱4を支柱穴形成体3 に取り付けているが、例えば、嵌め込みや係合等の他の機械的構造でも良いこと は当然である。It is needless to say that the configuration of the present invention can be appropriately changed without departing from the gist of the present invention, and these changes are also included in the present invention as long as the technical idea is the same. Is. For example, the base 2, the support hole forming body 3, and the steel piece 15 are made of steel in the embodiment, but are not limited thereto, and any metal that can be used as a temporary protective fence may be used. Further, although the support column 4 is attached to the support column hole forming body 3 with the bolts 12 and the nuts 13 and the like, it goes without saying that other mechanical structures such as fitting and engagement may be used.
【0015】[0015]
本考案は、仮設防護柵を、基台と支柱等に分解可能な構造であるので、基台を 積み重ねることができて場所をとらないことから、保管や運搬等が容易となり、 また、金属製であるので、何回でも繰り返して仮設できる利点がある。また本考 案の金属製の基台には金属片が充填されているので、基台の比重が二倍以上に増 大して基台が小型の構造となることができ、基台の設置スペースを半分以下にで き、また、加工屑金属片を用いれば、資源の有効利用となる利点がある。 Since the present invention has a structure in which the temporary protection fence can be disassembled into a base and columns, etc., the bases can be stacked and occupy no space, so storage and transportation are easy, and metal bases are also available. Therefore, there is an advantage that the temporary installation can be repeated any number of times. In addition, since the metal base of the present proposal is filled with metal pieces, the specific gravity of the base can be doubled or more, and the base can have a compact structure, which reduces the installation space of the base. If it is less than half, and if scrap metal pieces are used, there is an advantage that resources are effectively used.
【0016】 また、中空部を設けない仮設防護柵用基台によれば、鋳型により一体成形する 等により製造が効率化され、支柱の取り付け作業が簡略化され、比重をより大き くして基台の体積を更に小さくできるのである。[0016] Furthermore, according to the temporary protection fence base without the hollow portion, the manufacturing is streamlined by integrally molding with a mold, the mounting work of the support is simplified, the specific gravity is increased, and the base is increased. The volume of can be further reduced.
【図1】 本実施例の全体構造図である。FIG. 1 is an overall structural diagram of this embodiment.
【図2】 本実施例の一部断面とした側面図である。FIG. 2 is a side view showing a partial cross section of the present embodiment.
【図3】 本実施例の基台2の内部構造を示す斜視図で
あるFIG. 3 is a perspective view showing an internal structure of a base 2 of this embodiment.
【図4】 図4(a)は、本実施例の支柱の斜視図であ
り、図4(b)は、(a)の反対側から見た斜視図であ
るFIG. 4 (a) is a perspective view of a column of the present embodiment, and FIG. 4 (b) is a perspective view seen from the opposite side of (a).
1 仮設防護柵 2 基台 3 支柱穴形成体 4 支柱 5 ガードレール 6,7 丸孔 8 丸穴 9,10 縦長孔 12 ボルト 13 ナット 15 鋼片 16 中空部 22 蓋体 1 Temporary Guard Fence 2 Base 3 Support Hole Former 4 Support 5 Guardrail 6,7 Round Hole 8 Round Hole 9,10 Vertically Long Hole 12 Bolt 13 Nut 15 Steel Piece 16 Hollow Part 22 Lid
───────────────────────────────────────────────────── フロントページの続き (51)Int.Cl.6 識別記号 庁内整理番号 FI 技術表示箇所 E04H 17/14 102 Z ─────────────────────────────────────────────────── ─── Continuation of the front page (51) Int.Cl. 6 Identification code Internal reference number FI technical display location E04H 17/14 102 Z
Claims (2)
を金属製の中空基台に立設し、該中空基台の中空部に金
属片を充填し、前記支柱を支柱穴形成体に取付け部材で
着脱自在にしてなることを特徴とする仮設防護柵用基
台。1. A pillar hole forming body in which a pillar can be inserted and removed vertically is erected on a metal hollow base, and a metal piece is filled in the hollow portion of the hollow base to form the pillar hole in the pillar. A temporary protection fence base characterized by being removable from the body with a mounting member.
製の基台に立設し、前記支柱を支柱穴に取付け部材で着
脱自在としてなることを特徴とする仮設防護柵用基台。2. A temporary protective fence base for a temporary protection fence, characterized in that a pillar hole is vertically installed so that the pillar hole can be inserted and removed vertically on a metal base, and the pillar is detachably attached to the pillar hole by a mounting member. Stand.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP1993030890U JP2515477Y2 (en) | 1993-06-10 | 1993-06-10 | Support for temporary protective fence |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP1993030890U JP2515477Y2 (en) | 1993-06-10 | 1993-06-10 | Support for temporary protective fence |
Publications (2)
Publication Number | Publication Date |
---|---|
JPH072521U true JPH072521U (en) | 1995-01-13 |
JP2515477Y2 JP2515477Y2 (en) | 1996-10-30 |
Family
ID=12316327
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP1993030890U Expired - Lifetime JP2515477Y2 (en) | 1993-06-10 | 1993-06-10 | Support for temporary protective fence |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP2515477Y2 (en) |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2008231756A (en) * | 2007-03-20 | 2008-10-02 | ▲蔦▼井株式会社 | Subsidence prevention device for strut for supporting guard rail and method of constructing the strut |
CN103061291A (en) * | 2011-10-20 | 2013-04-24 | 孙希贤 | Movable green barrier support |
KR101314909B1 (en) * | 2012-12-10 | 2013-10-04 | 박재선 | Fence for transport rail of coal storage yard |
KR101636216B1 (en) * | 2015-08-06 | 2016-07-04 | 주식회사 웰콘 | Foundation structure for pillar |
JP2016211354A (en) * | 2015-04-30 | 2016-12-15 | 株式会社サンリツ | Flotation prevention device and flotation prevention method of manhole |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2002058618A (en) * | 2000-08-21 | 2002-02-26 | Aron Kasei Co Ltd | Portable stool |
Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH01137318U (en) * | 1988-03-11 | 1989-09-20 | ||
JPH0452256U (en) * | 1990-09-04 | 1992-05-01 |
-
1993
- 1993-06-10 JP JP1993030890U patent/JP2515477Y2/en not_active Expired - Lifetime
Patent Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH01137318U (en) * | 1988-03-11 | 1989-09-20 | ||
JPH0452256U (en) * | 1990-09-04 | 1992-05-01 |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2008231756A (en) * | 2007-03-20 | 2008-10-02 | ▲蔦▼井株式会社 | Subsidence prevention device for strut for supporting guard rail and method of constructing the strut |
CN103061291A (en) * | 2011-10-20 | 2013-04-24 | 孙希贤 | Movable green barrier support |
CN103061291B (en) * | 2011-10-20 | 2016-08-03 | 孙希贤 | Movable green barrier support |
KR101314909B1 (en) * | 2012-12-10 | 2013-10-04 | 박재선 | Fence for transport rail of coal storage yard |
JP2016211354A (en) * | 2015-04-30 | 2016-12-15 | 株式会社サンリツ | Flotation prevention device and flotation prevention method of manhole |
KR101636216B1 (en) * | 2015-08-06 | 2016-07-04 | 주식회사 웰콘 | Foundation structure for pillar |
Also Published As
Publication number | Publication date |
---|---|
JP2515477Y2 (en) | 1996-10-30 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US5746036A (en) | Railroad crossing signal foundation and spider and method of producing the same | |
US5388663A (en) | Portable walkway systems | |
JPH072521U (en) | Base for temporary protective fence | |
JP3115824U (en) | Concrete foundation structure for standing upright | |
CN111577001A (en) | Temporary enclosure fixing piece for non-hardened area and construction method thereof | |
CN212743611U (en) | Temporary enclosure fixing piece for hardening-free area | |
JP3008876U (en) | Temporary protective fence | |
CN113338537A (en) | Construction method of ultrahigh large-section concrete frame column | |
CN216142043U (en) | Foundation pit support system | |
JP2649205B2 (en) | Anchor bolt burying method | |
JP3072102U (en) | Reinforcing bar jig for pier construction | |
KR100684390B1 (en) | Anchor bolt assembly | |
KR200307607Y1 (en) | Temporang construction sfuctare for culvating slad | |
CA2109501C (en) | Portable walkway systems | |
CN217840991U (en) | A can have enough to meet need formula and enclose fender device for protection of floor adjacent side | |
JP2555216Y2 (en) | Retaining wall with protective fence | |
CN216920057U (en) | Assembled pier stud reinforcing bar construction platform | |
CN210003017U (en) | But adopt prefabricated construction of concrete prefabricated section to enclose fender | |
JP3142180B2 (en) | Concrete construction method | |
JP2953499B2 (en) | Pipe support fixture and method for hollow slab construction | |
JP3073303U (en) | Temporary guardrail | |
JP3703740B2 (en) | Fixing method of steel pillar | |
JPS6322192Y2 (en) | ||
JPH0438030Y2 (en) | ||
JP2003213704A (en) | Structure of soil retaining wall block |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
EXPY | Cancellation because of completion of term |