JPH07247515A - Overhanging structure - Google Patents

Overhanging structure

Info

Publication number
JPH07247515A
JPH07247515A JP6067621A JP6762194A JPH07247515A JP H07247515 A JPH07247515 A JP H07247515A JP 6067621 A JP6067621 A JP 6067621A JP 6762194 A JP6762194 A JP 6762194A JP H07247515 A JPH07247515 A JP H07247515A
Authority
JP
Japan
Prior art keywords
overhanging
precast
slope
overhang
anchor
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP6067621A
Other languages
Japanese (ja)
Other versions
JP2592438B2 (en
Inventor
Yasuhiro Yamada
泰弘 山田
Kunimitsu Yamada
邦光 山田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kensetsu Kiso Engineering Co Ltd
Original Assignee
Kensetsu Kiso Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kensetsu Kiso Engineering Co Ltd filed Critical Kensetsu Kiso Engineering Co Ltd
Priority to JP6067621A priority Critical patent/JP2592438B2/en
Publication of JPH07247515A publication Critical patent/JPH07247515A/en
Application granted granted Critical
Publication of JP2592438B2 publication Critical patent/JP2592438B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A30/00Adapting or protecting infrastructure or their operation
    • Y02A30/60Planning or developing urban green infrastructure

Landscapes

  • Devices Affording Protection Of Roads Or Walls For Sound Insulation (AREA)
  • Road Paving Structures (AREA)

Abstract

PURPOSE:To provide an overhang structure which is constituted to effectively transmit a load to the slope side and have an excellent scene and facilitate the construction. CONSTITUTION:L-shaped overhang materials 6 each comprising a support part 7 erected on a foundation on the slope side and an overhanging part 8 are arranged on the soil side. A support member 9 is located between the overhanging part 8 and a slope 3 of each precast overhang 6. An anchor 5 driven on a natural ground on the soil side is anchored to the tip of a roof part 8. The overhanging material 6 is pulled toward the soil side by a prestress force. A tendor 10 extending through the overhang material 6 is also extended through the overhanging material 6 not anchored by an anchor 5 for integral formation. There are neither support column nor wall on the downward slope side, a scene is improved, and a dangerous work on a slope and large scale construction are reduced. The bending bearing of the overhanging material 8 is improved by a prestress force. The prestress force is transmitted to the slope 3 through the overhang part 8 and the support member 9, incurring of a tensile force loss is prevented, and long term stability is improved.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】この発明は山岳地や海岸縁などの
傾斜地での落石から道路敷地や建物敷地を防護したり、
或いは張出し道路などの敷地としても使用可能な張出し
構造物に関するものである。
[Industrial application] This invention protects road sites and building sites from falling rocks on slopes such as mountainous areas and coastal edges,
Alternatively, it relates to an overhanging structure that can be used as a site such as an overhanging road.

【0002】[0002]

【従来の技術】山岳地や海岸縁などの傾斜地における道
路や建物は、斜面からの落石の危険に晒されている。こ
の落石からの防護のために、洞門やスノーシェッドと称
する落石防護のための構造物が採用されている。これら
従来の構造物は、道路敷地や建物敷地の上り傾斜側と下
り傾斜側の双方に支柱を立て、この柱の上に屋根部分を
構築して敷地を覆うようにしていた。つまりこれら構造
物は敷地をトンネルのように覆って土砂・岩石が敷地の
上に落下するのを防ぐものであった。
2. Description of the Related Art Roads and buildings on slopes such as mountainous areas and coastal edges are exposed to the risk of falling rocks from the slopes. In order to protect against this rockfall, structures such as a cave and a snowshed are used for rockfall protection. In these conventional structures, pillars are erected on both the upslope side and the downslope side of a road site or a building site, and a roof portion is constructed on the pillars to cover the site. In other words, these structures covered the site like a tunnel to prevent earth and sand and rocks from falling onto the site.

【0003】また同じく山岳地や海岸縁などで道路や建
物のための敷地を確保するのは極めて困難である。この
ために山を切り崩したり、海に支柱を立ててこの上に床
部分を構築して敷地にするなどの施工を行なっていた。
Similarly, it is extremely difficult to secure a site for roads and buildings in mountainous areas and coastal margins. For this reason, constructions such as cutting mountains and building columns on the sea to build a floor on the site were made.

【0004】[0004]

【この発明が解決しようとする課題】前記した従来の落
石から防護するための構造物であると、敷地を囲うよう
に覆ってしまうため、景観が良くない。つまり外側から
見た場合にも周囲の景観との調和が良好でないととも
に、敷地側から外を見る場合にも折角の景色を遮ってし
まうことになる。またスノーシェッドのような構造であ
ると、敷地の下り斜面側にも柱を立てるのであるが、下
り斜面側の地盤は崩れ易く不安定であり、この上に柱を
立てる作業は極めて難しい。したがって下り斜面側の地
盤を補強してこの上に柱を立てる必要があるため、その
作業は極めて大がかりなものとなり、また斜面での作業
には多くの労力と危険を伴うことになる。
However, the conventional structure for protecting against falling rocks described above does not provide a good view because the structure covers the site. In other words, even when viewed from the outside, the harmony with the surrounding landscape is not good, and when viewing the outside from the site side, it obstructs the view. Also, with a structure like a snow shed, pillars are erected on the down slope side of the site, but the ground on the down slope side is easily collapsed and unstable, and it is extremely difficult to erect pillars on it. Therefore, since it is necessary to reinforce the ground on the down slope side and to set up a pillar on this, the work becomes extremely large-scale work, and the work on the slope involves a lot of labor and danger.

【0005】これは前記した敷地を確保するための施工
でも同じであって、山を切り崩す作業は極めて大がかり
であり、また海や斜面に支柱を立てる施工は作業者に大
きな危険を課するものである。
This is the same as the construction for securing the above-mentioned site, the work of cutting down the mountain is extremely large-scale work, and the construction of erecting the pillar on the sea or slope imposes a great risk to the worker. is there.

【0006】この発明は以上のような課題を解決するた
めになされたもので、周囲の景観との調和も良好である
とともに、外側の景色を遮ることがなく、また施工が容
易に行なえる張出し構造物を提供することを目的とす
る。
The present invention has been made in order to solve the above problems, and it is well harmonious with the surrounding scenery, and does not block the outside scenery, and can be easily constructed. The purpose is to provide a structure.

【0007】[0007]

【課題を解決するための手段】この発明にかかる張出し
構造物は、荷重や自重を斜面側でのみ支えるようにする
ものである。この発明ではプレキャストコンクリート製
の張出し材を使用するもので、プレキャスト張出し材は
斜面側の基礎の上に起立する支持部と、道路敷地や建物
敷地を覆う張出し部とからL形となっている。斜面に構
築した基礎の上にプレキャスト張出しを置き、複数個を
連続して並べる。各プレキャスト張出し材の張出し部と
斜面との間に支持部材を介在させる。支持部材はプレキ
ャスト防護体が山側へ倒れるのを防ぐためのもので、プ
レキャストのコンクリート製でも鋼製の部材でもよく、
様々な形状・材質のものが採用できる。斜面には予めア
ンカーを打設しておき、これにプレストレス力を与えて
プレキャスト張出しの先端に定着して山側へ引き寄せ
る。このアンカーをプレキャスト張出し材の張出し部内
に配するために、張出し部は断面コ字状の溝形に形成し
ておくことが好適である。
The overhanging structure according to the present invention is designed to support the load and its own weight only on the slope side. In the present invention, an overhanging material made of precast concrete is used, and the precast overhanging material is L-shaped from a support portion standing up on a foundation on the slope side and an overhanging portion covering a road site or a building site. A precast overhang is placed on the foundation constructed on the slope, and multiple pieces are lined up continuously. A support member is interposed between the overhang portion and the slope of each precast overhang member. The support member is for preventing the precast protective body from falling to the mountain side, and may be a precast concrete member or a steel member,
Various shapes and materials can be adopted. Anchor is placed in advance on the slope, and prestressing force is applied to this to fix it at the tip of the precast overhang and pull it toward the mountain side. In order to arrange this anchor in the overhanging portion of the precast overhanging material, it is preferable that the overhanging portion is formed in a groove shape having a U-shaped cross section.

【0008】プレキャスト張出し材は全てをアンカーに
よって定着するのではなく、所望のいくつかを選択して
アンカーにて定着する。例えば並んだ複数個のプレキャ
スト張出し材のうちアンカーにて定着するのは、ふたつ
置きのプレキャスト張出し材として、飛ばしたプレキャ
スト張出し材にはアンカーにて定着したプレキャスト張
出し材を貫通した緊張材を貫通して定着し、プレキャス
ト張出し材を一体化させる。プレキャスト張出し材の溝
形の内側には、モルタルやコンクリートなどのセメント
系硬化材を詰める。
The precast overhanging material is not entirely fixed by the anchor, but some desired ones are selected and fixed by the anchor. For example, among the multiple precast overhanging materials arranged side by side, anchors fix the two precast overhanging materials, and the skipped precast overhanging material penetrates the tension material that penetrates the precast overhanging material fixed by the anchors. And fix it, and integrate the precast overhanging material. A cement-based hardening material such as mortar or concrete is filled inside the groove of the precast overhanging material.

【0009】以上のように構成した構造物を落石防護体
として、或いは張り出し敷地として使用する。落石防護
体とする場合は、道路敷地や建物敷地の上に張り出すよ
うに構築し、支持部と斜面との間及び張出し部の上に緩
衝のための土砂を盛る。張出し構造物が敷地を覆い、落
石から防護する。張出し敷地として使用する場合は、斜
面の途中に基礎を構築し、この上にプレキャスト張出し
材を立てて構造物を構成する。このプレキャスト張出し
材の支持部と斜面との間に土砂を詰め、張出し部上を道
路敷地や建物敷地として使用する。
The structure constructed as described above is used as a rockfall protective body or as an overhanging site. When it is used as a rockfall protection body, it is constructed so as to extend over the road site or building site, and earth and sand for buffering is placed between the support part and the slope and on the overhang part. A projecting structure covers the site and protects against falling rocks. When it is used as an overhang site, a foundation is constructed in the middle of the slope and a precast overhang material is erected on this to construct the structure. Sediment is filled between the support and slope of this precast overhanging material, and the overhanging area is used as a road site or building site.

【0010】[0010]

【作用】構造物全体を山側でのみ支えるため、不安定な
下り斜面側での基礎工などが一切不要である。アンカー
を防護体の先端で定着するため、アンカーはプレキャス
ト防護体の屋根部にプレストレスの圧縮力を与え、曲げ
耐力の向上を図ることができる。アンカーの緊張力がプ
レキャスト張出し材から支持部材を介して山側に伝わ
る。これによって緊張力の長期的な維持が可能となる。
張出し材の張出し部を溝形に形成することにより、アン
カーを屋根部内に配設して、また型枠としてセメント系
硬化材を埋めることが可能となる。
[Operation] Since the entire structure is supported only on the mountain side, no foundation work is required on the unstable down slope side. Since the anchor is anchored at the tip of the protective body, the anchor can exert a prestressing compressive force on the roof portion of the precast protective body to improve bending strength. The tension of the anchor is transmitted from the precast overhanging material to the mountain side through the support member. This makes it possible to maintain tension over the long term.
By forming the overhanging portion of the overhanging material in a groove shape, it becomes possible to dispose the anchor in the roof portion and to fill the cement-based hardening material as a formwork.

【0011】[0011]

【実施例】以下、図に示す一実施例に基づきこの発明を
詳細に説明する。図1に示す実施例は道路1の落石から
の防護体としてを施工した場合である。道路1の山側の
斜面下に、道路1に沿ってコンクリートの基礎2を構築
する。また斜面3には、やはり道路1に沿ってコンクリ
ートの基礎4構築する。この基礎4を貫通してグラウン
ドアンカー5を地山に打設する。グラウンドアンカー5
は、シースの中に複数本の引張材を配して削孔内に挿入
し、グラウトを注入して定着したものである。またグラ
ウンドアンカー5を先に打設して、その後基礎4を構築
することも可能である。
DESCRIPTION OF THE PREFERRED EMBODIMENTS The present invention will be described in detail below based on an embodiment shown in the drawings. The embodiment shown in FIG. 1 is a case in which the road 1 is constructed as a protective body against rockfall. Under the slope on the mountain side of the road 1, a concrete foundation 2 is constructed along the road 1. On the slope 3, a concrete foundation 4 is constructed along the road 1. A ground anchor 5 is placed in the ground through the foundation 4. Ground anchor 5
Is a device in which a plurality of tension members are arranged in a sheath, inserted into a drilled hole, and grout is injected and fixed. It is also possible to first place the ground anchor 5 and then construct the foundation 4.

【0012】基礎2の上にはプレキャスト張出し材6を
置く。プレキャスト張出し材6は支持部7と張出し部8
からL形に形成されており、支持部7を基礎2の上に起
立させ、張出し部8は敷地側へ張り出させる。プレキャ
スト張出し材6は、張出し部8から支持部7に掛けて断
面コ字状の溝形に形成されている。このプレキャスト張
出し材6の張出し部8と斜面3の基礎4との間に支持部
材9を介在させる。支持部材9はプレキャストコンクリ
ート製であり、実施例では円筒形である。この支持部材
9内と張出し部8内にはグラウンドアンカー5を通し、
プレストレス力を与えて張出し部8の先端にて定着す
る。このプレストレス力によってプレキャスト張出し材
6を山側へ引き寄せる。プレストレス力は防護体6の屋
根部8、支持部材9を介して斜面の基礎4に伝わる。
A precast overhanging material 6 is placed on the foundation 2. The precast overhanging material 6 includes a supporting portion 7 and an overhanging portion 8.
To L-shape, the supporting portion 7 is erected on the foundation 2, and the projecting portion 8 is projecting to the site side. The precast overhanging member 6 is formed in a groove shape with a U-shaped cross section, which extends from the overhanging portion 8 to the supporting portion 7. A supporting member 9 is interposed between the overhanging portion 8 of the precast overhanging member 6 and the foundation 4 of the slope 3. The support member 9 is made of precast concrete, and has a cylindrical shape in the embodiment. The ground anchor 5 is passed through the support member 9 and the overhanging portion 8,
A prestressing force is applied to fix the tip of the overhanging portion 8. This prestressing force pulls the precast overhanging material 6 to the mountain side. The prestressing force is transmitted to the sloped foundation 4 through the roof portion 8 and the support member 9 of the protective body 6.

【0013】アンカー5を定着するのは、並んだプレキ
ャスト張出し材6のうち所望のプレキャスト張出し材6
であり、実施例ではひとつ置きのプレキャスト張出し材
をアンカー5で固定し、これを貫通させた緊張材10で
あるアンボンドのPCストランドをアンカー5によって
定着していないプレキャスト張出し材6にも貫通させて
プレストレスを与えて端部を張出し材6の側面に定着
し、全プレキャスト張出し材6を一体化させる。場合に
よっては、緊張材10は全張出し材6のうち幾本かづつ
を一体化して定着し、順次緊張材10をオーバーラップ
させて連結するように一体化してもよい。
The anchor 5 is fixed by the desired precast overhanging member 6 among the precast overhanging members 6 arranged side by side.
In the embodiment, every other precast overhanging material is fixed by the anchor 5, and the unbonded PC strand, which is the tension material 10 penetrating this, is also passed through the precast overhanging material 6 not fixed by the anchor 5. Prestressing is applied to fix the ends to the side surfaces of the overhanging material 6, and all the precast overhanging materials 6 are integrated. In some cases, the tension members 10 may be integrated by fixing some of the entire overhang members 6 and then, the tension members 10 may be integrated so that they are sequentially overlapped and connected.

【0014】張出し部8と支持部7の溝内にはモルタル
やコンクリートを打設する。必要に応じて溝内には鉄筋
を配筋しておく。このようなプレキャスト張出し材6を
道路1に沿って連続して並べる。プレキャスト張出し材
6の支持部7と斜面3との間に土砂11を詰め、張出し
部8の上にも落石の衝撃の緩衝のための土砂11を敷
く。
Mortar and concrete are placed in the grooves of the overhanging portion 8 and the supporting portion 7. Reinforcing bars are arranged in the groove if necessary. Such precast overhanging members 6 are continuously arranged along the road 1. Sediment 11 is packed between the support portion 7 and the slope 3 of the precast overhanging material 6, and the overhanging portion 8 is also overlaid with earth / sand 11 for buffering the impact of falling rocks.

【0015】図4に示すのは張出し構造物を道路敷地と
して使用した場合である。基礎2は斜面3の途中に構築
し、前記したようにプレキャスト張出し材6を並べて一
体化する。支持部7と斜面との間に土砂11を詰め、こ
の上と張出し部8の上を舗装して道路とする。
FIG. 4 shows the case where the projecting structure is used as a road site. The foundation 2 is constructed in the middle of the slope 3, and the precast overhanging members 6 are arranged and integrated as described above. Sediment 11 is packed between the support portion 7 and the slope, and the road and the overhanging portion 8 are paved to form a road.

【0016】[0016]

【発明の効果】この発明は以上のような構成を有し、以
下のような効果を得ることができる アンカーのプレストレス力は張出し材の支持部材を通
じて斜面の岩盤に伝達され、アンカーの引張力の維持が
期待でき、長期的にロスなく保持され、構造物の安定性
が保証される。 アンカーを防護体の張出し部先端に定着するため、張
出し部の曲げ耐力をプレストレス力によって向上させる
ことができると同時に、地山側からの水平荷重をアンカ
ーで分担することができる。 張出し材の張出し部を溝形に形成することにより、ア
ンカーを埋設してこの力を的確に張出し材が受けること
ができる。 プレキャスト製の張出し材を使用するため現場での作
業が軽減され、施工期間を短くすることができる。 張出し材は敷地の斜面側のみで支えるため、斜面側で
の作業や大がかりな仮設が減少し、施工が容易になると
ともに危険性が減少する。 落石防護体として使用した場合、下り斜面側には柱や
壁が無くなり、外側から見る景観も良好となるととも
に、道路などからも景色が遮られず良好な視界をうるこ
とができる。 張出し材を断面コ字状の溝形としたため、部材の軽量
化を図ることができ、搬入作業が容易になるとともに、
この溝を型枠としても使用できるので、型枠組みが省力
化され、経済的で工期の短縮が図れる。
EFFECTS OF THE INVENTION The present invention has the above-mentioned constitution and can obtain the following effects. The prestressing force of the anchor is transmitted to the rock mass on the slope through the supporting member of the overhanging member, and the tensile force of the anchor is obtained. Can be expected to be maintained, it will be retained for a long time without loss, and the stability of the structure is guaranteed. Since the anchor is fixed to the tip of the overhanging portion of the protective body, the bending resistance of the overhanging portion can be improved by the prestressing force, and at the same time, the horizontal load from the ground side can be shared by the anchor. By forming the overhanging portion of the overhanging member in a groove shape, the anchor can be embedded and the overhanging member can accurately receive this force. The use of precast overhanging materials reduces on-site work and shortens the construction period. Since the overhanging material is supported only on the slope side of the site, work on the slope side and large-scale temporary construction are reduced, which facilitates construction and reduces the risk. When used as a rockfall protector, there are no pillars or walls on the down slope side, and the view seen from the outside is good, and the view is not obstructed by roads, etc., and good visibility can be obtained. Since the overhanging material has a groove shape with a U-shaped cross section, the weight of the member can be reduced, and the carrying-in work is facilitated.
Since this groove can also be used as a formwork, the formwork is labor-saving, economical and the construction period can be shortened.

【図面の簡単な説明】[Brief description of drawings]

【図1】落石防護のための張出し構造物の斜視図であ
る。
FIG. 1 is a perspective view of an overhanging structure for rockfall protection.

【図2】落石防護のための張出し構造物の断面図であ
る。
FIG. 2 is a cross-sectional view of an overhanging structure for rockfall protection.

【図3】プレキャスト張出し材の張出し部の断面図であ
る。
FIG. 3 is a cross-sectional view of an overhang portion of a precast overhang member.

【図4】張出し道路敷地のための張出し構造物の断面図
である。
FIG. 4 is a cross-sectional view of an overhang structure for an overhang road site.

【符号の説明】[Explanation of symbols]

1 道路 2 基礎 3 斜面 4 基礎 5 グラウンドアンカー 6 プレキャスト張出し材 7 支持部 8 張出し部 9 支持部材 10 緊張材 11 土砂 1 Road 2 Foundation 3 Slope 4 Foundation 5 Ground anchor 6 Precast overhanging material 7 Supporting portion 8 Overhanging portion 9 Supporting member 10 Tensile material 11 Sand

Claims (3)

【特許請求の範囲】[Claims] 【請求項1】 上り斜面側の基礎の上に起立する支持部
と、敷地の上を覆う張出し部からなる複数個のL形のプ
レキャスト張出し材を上り斜面側に並べ、プレキャスト
張出し材の張出し部と上り斜面との間に支持部材を介在
させ、上り斜面側地山に打設したアンカーを張出し部の
先端に定着してプレストレス力によって所望のプレキャ
スト張出し材を上り斜面側に引き寄せ、このアンカーを
定着したプレキャスト張出し材を貫通させた緊張材をア
ンカーを定着していないプレキャスト張出し材にも貫通
させて定着してプレキャスト張出し材を一体化し、敷地
を覆う落石防護体としてなる張出し構造物。
1. A plurality of L-shaped precast overhanging members, each of which is composed of a support portion standing on a foundation on the upslope side and an overhanging portion covering the site, are arranged on the upslope side to form an overhanging portion of the precast overhanging material. An anchor placed on the ground on the upslope side is fixed to the tip of the overhanging part with a support member interposed between the upslope and the upslope, and the desired precast overhanging material is pulled toward the upslope side by prestressing force. An overhang structure that acts as a rockfall protective body that covers the site by allowing the tension material that penetrates the fixed precast overhanging material to penetrate through the precast overhanging material that does not have the anchor and fix it to integrate the precast overhanging material.
【請求項2】 斜面側の基礎の上に起立する支持部と、
斜面から張出す張出し部からなる複数個のL形にプレキ
ャスト張出し材を斜面側に並べ、プレキャスト張出し材
の張出し部と斜面との間に支持部材を介在させ、斜面側
地山に打設したアンカーを張出し部を張出し部先端に定
着してプレストレス力によって所望のプレキャスト張出
し材を斜面側に引き寄せ、このアンカーを定着したプレ
キャスト張出し材を貫通させた緊張材をアンカーを定着
していないプレキャスト張出し材にも貫通させて定着し
てプレキャスト張出し材を一体化し、張り出し部上を敷
地としてなる張出し構造物。
2. A support portion standing upright on a slope-side foundation,
Anchor placed in the ground on the slope side, with precast overhanging materials arranged in a plurality of L-shapes with overhanging parts extending from the slope, arranging the precast overhanging materials on the slope side, interposing a supporting member between the overhanging part and the slope The precast overhanging material is fixed to the tip of the overhanging portion, and the desired precast overhanging material is pulled to the slope side by the prestressing force. An overhang structure where the precast overhanging material is integrated by penetrating it and fixing it, and the overhanging part is the site.
【請求項3】 プレキャスト張出し材の張り出し部は断
面コ字状の溝形に形成し、このプレキャスト張出し材に
セメント系硬化材を充填してあることを特徴とする請求
項1又は2記載の張出し構造物。
3. The overhang according to claim 1, wherein the overhang portion of the precast overhang material is formed in a groove shape having a U-shaped cross section, and the precast overhang material is filled with a cement-based hardening material. Structure.
JP6067621A 1994-03-11 1994-03-11 Overhang structure Expired - Fee Related JP2592438B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP6067621A JP2592438B2 (en) 1994-03-11 1994-03-11 Overhang structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP6067621A JP2592438B2 (en) 1994-03-11 1994-03-11 Overhang structure

Publications (2)

Publication Number Publication Date
JPH07247515A true JPH07247515A (en) 1995-09-26
JP2592438B2 JP2592438B2 (en) 1997-03-19

Family

ID=13350239

Family Applications (1)

Application Number Title Priority Date Filing Date
JP6067621A Expired - Fee Related JP2592438B2 (en) 1994-03-11 1994-03-11 Overhang structure

Country Status (1)

Country Link
JP (1) JP2592438B2 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007291756A (en) * 2006-04-26 2007-11-08 Nishi Nippon Spc Kk Rock-fall protection structure
CN109403180A (en) * 2018-10-29 2019-03-01 中铁四院集团西南勘察设计有限公司 A kind of steep slope region underloading road structure and construction method

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0562161A (en) * 1991-09-05 1993-03-12 Matsushita Electric Ind Co Ltd Magnetic recording medium and its manufacture

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0562161A (en) * 1991-09-05 1993-03-12 Matsushita Electric Ind Co Ltd Magnetic recording medium and its manufacture

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007291756A (en) * 2006-04-26 2007-11-08 Nishi Nippon Spc Kk Rock-fall protection structure
CN109403180A (en) * 2018-10-29 2019-03-01 中铁四院集团西南勘察设计有限公司 A kind of steep slope region underloading road structure and construction method

Also Published As

Publication number Publication date
JP2592438B2 (en) 1997-03-19

Similar Documents

Publication Publication Date Title
US5551810A (en) Retaining wall with an outer face and method of forming the same
KR20100138122A (en) Base of arch rigid frame structure including composite covering arch structure and constructing method thereof
JP2000513773A (en) Underground structure for constructing tunnel, underground passage, underground parking lot, etc., method of constructing the same, and prefabricated member for the structure
US5794921A (en) Masonry fence system
KR100726984B1 (en) Temporary system for land-side protection wall
KR100532248B1 (en) A arch-shaped composite structure with psc pannel and the steel girder using the open trench tunnel method, and method for manufacturing it
JPH0960498A (en) Structure and execution method for timbering wall
JP2004100157A (en) Retaining wall structure and its construction method
KR100510092B1 (en) A one-piece type arch-shaped structure with the precast concrete pannel and the steel frame under the earth, and method for manufacturing it
KR102111153B1 (en) Retaining Wall Panel Structure using PC Strand
JP2592438B2 (en) Overhang structure
JP2787806B2 (en) Earth retaining wall
JPH0996197A (en) Structure of support wall and construction method therefor
JP3244324B2 (en) Mountain retaining method
JPS63156120A (en) Construction for cast-in-place form of slope
KR101809554B1 (en) Structure using key-block and sheetfile
JPH1150407A (en) Road and construction method thereof
JPH01244003A (en) Lock-shade and construction thereof
JP2000314143A (en) Retaining wall execution method and retaining wall device
JP2843532B2 (en) Reticulated formwork with finishing plate
JPH0447021A (en) Construction method for sheathing guide pile
JP2532445Y2 (en) Road protection shed
JPH0538094Y2 (en)
IL169878A (en) Method for tunnel construction
JP4560843B2 (en) Construction method of protective structure

Legal Events

Date Code Title Description
R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20081219

Year of fee payment: 12

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20111219

Year of fee payment: 15

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20111219

Year of fee payment: 15

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20111219

Year of fee payment: 15

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20121219

Year of fee payment: 16

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20121219

Year of fee payment: 16

LAPS Cancellation because of no payment of annual fees