JPH0723486Y2 - Hanging jig for building material unit - Google Patents

Hanging jig for building material unit

Info

Publication number
JPH0723486Y2
JPH0723486Y2 JP1989013527U JP1352789U JPH0723486Y2 JP H0723486 Y2 JPH0723486 Y2 JP H0723486Y2 JP 1989013527 U JP1989013527 U JP 1989013527U JP 1352789 U JP1352789 U JP 1352789U JP H0723486 Y2 JPH0723486 Y2 JP H0723486Y2
Authority
JP
Japan
Prior art keywords
building material
material unit
hanging
beam member
suspended
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP1989013527U
Other languages
Japanese (ja)
Other versions
JPH02105446U (en
Inventor
辰巳 金原
高広 山田
信親 栗原
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sekisui Chemical Co Ltd
Kito Corp
Original Assignee
Sekisui Chemical Co Ltd
Kito Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sekisui Chemical Co Ltd, Kito Corp filed Critical Sekisui Chemical Co Ltd
Priority to JP1989013527U priority Critical patent/JPH0723486Y2/en
Publication of JPH02105446U publication Critical patent/JPH02105446U/ja
Application granted granted Critical
Publication of JPH0723486Y2 publication Critical patent/JPH0723486Y2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)
  • Load-Engaging Elements For Cranes (AREA)

Description

【考案の詳細な説明】 [産業上の利用分野] 本考案は、プレハブ式の家屋等を組立・建設する際に建
材ユニットを組立現場へ搬入するために用いられる建材
ユニット用吊り治具に関する。
[Detailed Description of the Invention] [Industrial field of application] The present invention relates to a hanging jig for a building material unit which is used to carry a building material unit to an assembly site when assembling and constructing a prefabricated house or the like.

[従来の技術] 一般に、プレハブ式の家屋等を、建設する際には、第7
図に示すように、その組立現場21の三方もしくは四方に
足場22を組んだ後、建材ユニット23を、第8図に示すよ
うな吊り治具24を介してクレーン(図示せず)により吊
り上げ、組立現場21へ搬入している。
[Prior Art] Generally, when constructing a prefabricated house, etc.,
As shown in the figure, after assembling the scaffolds 22 on three sides or four sides of the assembly site 21, the building material unit 23 is lifted by a crane (not shown) via a hanging jig 24 as shown in FIG. Carried to assembly site 21.

このとき用いられる従来の吊り治具24は、第8図に示す
ように、Iビーム(梁部材)24aの上下面に、クレーン
懸吊用アイプレート24bおよび建材ユニット吊下用アイ
プレート24cをそれぞれ取り付けられて構成されてい
る。クレーン懸吊用アイプレート24b,24bは、Iビーム2
4aの上面において、Iビーム24aの長さ方向中心Cにつ
いて対称に配置される。一方、建材ユニット吊下用アイ
プレート24cは、Iビーム24aの下面において、搬入すべ
き建材ユニット23の大きさに対応すべく、長さ方向中心
Cについて対称に複数組(ここでは3組)配置されてい
る。
As shown in FIG. 8, the conventional hanging jig 24 used at this time has a crane suspension eye plate 24b and a building material unit hanging eye plate 24c on the upper and lower surfaces of an I-beam (beam member) 24a, respectively. It is installed and configured. Crane suspension eye plates 24b and 24b are I-beam 2
On the upper surface of 4a, they are arranged symmetrically with respect to the center C in the longitudinal direction of the I beam 24a. On the other hand, a plurality of building material unit hanging eye plates 24c are arranged symmetrically with respect to the center C in the length direction (here, three sets) on the lower surface of the I-beam 24a so as to correspond to the size of the building material unit 23 to be carried in. Has been done.

このような吊り治具24により建材ユニット23を吊下する
際には、アイプレート24b,24bにワイヤロープ(上部吊
り索)25の両端部をそれぞれ係止するとともに、このワ
イヤロープ25にクレーン(図示せず)先端のフック26を
係止することにより、吊り治具24を懸吊する。また、搬
入すべき建材ユニット23を、その大きさに応じて適当な
位置のアイプレート24c,24cにワイヤロープ(下部吊り
索)27を介して吊下する。このとき、建材ユニット23
は、Iビーム24aの長さ方向中心Cについて対称になる
ように吊下される。
When the building material unit 23 is suspended by such a suspension jig 24, both ends of the wire rope (upper suspension line) 25 are respectively locked to the eye plates 24b, 24b, and the crane ( By suspending the hook 26 at the tip (not shown), the hanging jig 24 is suspended. Further, the building material unit 23 to be carried in is hung on the eye plates 24c, 24c at appropriate positions according to the size thereof via the wire rope (lower hanging rope) 27. At this time, the building material unit 23
Are suspended so as to be symmetrical with respect to the center C in the longitudinal direction of the I beam 24a.

このようにして、吊り治具24に吊下された建材ユニット
23を、ワイヤロープ25および吊り治具24を介してクレー
ンにより吊り上げ、第7図に示す所定の組立現場21内へ
搬入する。
In this way, the building material unit suspended by the suspension jig 24
23 is hoisted by a crane via a wire rope 25 and a hoisting jig 24, and is carried into a predetermined assembly site 21 shown in FIG.

[考案が解決しようとする課題] しかしながら、上述の従来の建材ユニット用吊り治具で
は、第8図に示すように、吊り治具24のIビーム24aよ
りも短い建材ユニット23を吊下・搬入する際には、左右
のバランスをとるべく建材ユニット23がIビーム24aの
長さ方向中心Cについて対称になるように吊下されるた
めに、Iビーム24aの両端が建材ユニット23よりも外方
へ突出してしまう。従って、建材ユニット23を組立現場
21の所定位置(特に足場22の近傍位置)に搬入する際
に、先行して組まれた足場22にIビーム24aの突出部が
当って干渉し合い、搬入作業性の低下を招くことにな
る。
[Problems to be Solved by the Invention] However, in the above-mentioned conventional hanging jig for building material units, as shown in FIG. 8, the building material unit 23 shorter than the I beam 24a of the hanging jig 24 is hung and carried in. In doing so, since the building material unit 23 is suspended symmetrically with respect to the longitudinal center C of the I beam 24a in order to balance the left and right, both ends of the I beam 24a are located outside the building material unit 23. Will stick out. Therefore, the building material unit 23 is
When carrying in to the predetermined position of 21 (especially the position near the scaffold 22), the protruding parts of the I-beam 24a hit the scaffolding 22 assembled in advance and interfere with each other, resulting in a decrease in carrying-in workability. .

本考案は、このような課題を解決しようとするもので、
建材ユニットと先行足場等の障害物とが干渉し合うこと
なく搬入できるようにして、搬入作業性の向上をはかっ
た建材ユニット用吊り治具を提供することを目的とす
る。
The present invention is intended to solve such a problem,
An object of the present invention is to provide a hanging jig for a building material unit in which the building material unit and an obstacle such as a preceding scaffold can be carried in without interfering with each other, thereby improving the workability of carrying in.

[課題を解決するための手段] 上記目的を達成するために、本考案の建材ユニット用吊
り治具は、複数の建材ユニット吊下用掛け止め金具を、
梁部材の一端部に設けられ建材ユニットの一端部を下部
吊り索により支持する端部掛け止め金具と、前記複数種
の建材ユニットの長さに応じ前記端部掛け止め金具との
間に適当な間隔をあけて前記梁部材の他端側に設けられ
前記建材ユニットの他端部を下部吊り索により支持する
複数の他端側掛け止め金具とにより構成するとともに、
複数のクレーン懸吊用掛け止め金具を、前記複数の建材
ユニット吊下用掛け止め金具の各位置に対応して設けた
ことを特徴としている。
[Means for Solving the Problem] In order to achieve the above object, the building material unit hanging jig of the present invention comprises a plurality of building material unit hanging latches,
A suitable end fitting metal fitting is provided at one end of the beam member to support one end of the building material unit by a lower suspension line, and an appropriate end fitting metal fitting according to the length of the plurality of types of building material units. With a plurality of other end side retaining metal fittings that are provided on the other end side of the beam member at intervals and that support the other end portion of the building material unit by a lower suspension rope,
It is characterized in that a plurality of hanging metal fittings for suspending a crane are provided corresponding to respective positions of the plurality of hanging metal fittings for hanging a building material unit.

[作用] 上述した本考案の建材ユニット用吊り治具では、建材ユ
ニットを吊下する際に、その両端部が、それぞれ、端部
掛け止め金具と、この端部掛け止め金具から建材ユニッ
トの長さに応じた間隔の他端側掛け止め金具とに下部吊
り索を介して支持され、建材ユニットが梁部材の下方に
吊下される。このとき、建材ユニットは、その一端部が
梁部材の一端部の位置に合わせて吊下されることになる
ので、梁部材の一端部側ではこの梁部材が建材ユニット
よりも突出することはない。
[Operation] In the above-described building material unit hanging jig of the present invention, when the building material unit is hung, both ends of the building material unit are the end hooks and the length of the building material unit from the end hooks, respectively. The building material unit is hung below the beam member by being supported by the other end side hooking metal fittings at intervals according to the height through the lower hanging rope. At this time, since the one end of the building material unit is suspended according to the position of the one end of the beam member, the beam member does not protrude beyond the building material unit on the one end side of the beam member. .

また、このように梁部材の下方に建材ユニットを吊下し
た場合、建材ユニットを支持する建材ユニット吊下用掛
け止め金具の位置に対応したクレーン懸吊用掛け止め金
具に、上部吊り索を係止し、この上部吊り索を介してク
レーンにより梁部材を懸吊する。これによって、建材ユ
ニットが、梁部材の下方において一端側へ片寄って吊下
されても、バランスを損なうことなく懸吊される。
Also, when the building material unit is hung below the beam member in this way, the upper suspension rope is attached to the crane suspension hanging metal fitting that corresponds to the position of the building material unit hanging metal fitting that supports the building material unit. Then, the beam member is suspended by a crane through the upper suspension rope. As a result, even if the building material unit is suspended to one end side below the beam member, the building material unit is suspended without impairing the balance.

[考案の実施例] 以下、図面により本考案の一実施例としての建材ユニッ
ト用吊り治具について説明すると、第1図はその梁部材
および上部吊り索(アッパースリング)を示す正面図、
第2図はその下部吊り索(ロアスリング)の例を示す正
面図、第3図は上記下部吊り索の側面図、第4図はその
延長チェーンを示す正面図である。
[Embodiment of the Invention] A hanging jig for a building material unit as one embodiment of the present invention will be described below with reference to the drawings. FIG. 1 is a front view showing a beam member and an upper sling (upper sling),
FIG. 2 is a front view showing an example of the lower suspension rope (lower ring), FIG. 3 is a side view of the lower suspension rope, and FIG. 4 is a front view showing an extension chain thereof.

第1図において、1は梁部材(ディスタンスバー)で、
この梁部材1は、上方からアッパースリング(上部吊り
索)2A,2Bおよびマスターリング3を介してクレーン
(図示せず)により懸吊されるとともに、下方にロアス
リング(下部吊り索;第2図の符号6参照)を介して建
材ユニット〔第5図(a)〜(f)および第6図の符号
8a〜8f参照〕を吊下するものである。
In FIG. 1, 1 is a beam member (distance bar),
This beam member 1 is suspended from above by a crane (not shown) via upper slings (upper suspension lines) 2A and 2B and a master ring 3, while lower beams are suspended downward (lower suspension lines; FIG. 2). (See reference numeral 6) of the building material unit [reference numerals in FIG. 5 (a) to (f) and FIG. 6]
8a to 8f].

そして、この梁部材1の下面側には、ロアスリングの上
端側フック(第2図の符号6a参照)を係止される複数
(本実施例では5個)の建材ユニット吊下用アイプレー
ト(掛け止め金具)4a〜4eが設けられている。
On the lower surface side of the beam member 1, a plurality of (five in this embodiment) building material unit hanging eye plates (upper side hooks (see reference numeral 6a in FIG. 2) of the lower ring are locked. Locking metal fittings) 4a to 4e are provided.

これらのアイプレートのうち、アイプレート4aは、梁部
材1の一端部(第1図の左端部)に設けられ建材ユニッ
トの一端部をロアスリングにより支持する端部アイプレ
ートとして機能するものであり、アイプレート4b〜4e
は、建材ユニットの長さに応じ端部アイプレート4aとの
間に適当な間隔をあけて梁部材1の他端側に設けられた
もので、建材ユニットの他端部をロアスリングにより支
持する他端側アイプレートとして機能するものである。
本実施例では、アイプレート4aと各アイプレート4b〜4e
との間隔は、第5図(a)〜(f)にて後述する建材ユ
ニット8a〜8eの長さに応じて設定されている。
Of these eye plates, the eye plate 4a is provided at one end (the left end in FIG. 1) of the beam member 1 and functions as an end eye plate that supports one end of the building material unit by the lower ring. , Eye plates 4b-4e
Is provided on the other end side of the beam member 1 at an appropriate interval from the end eye plate 4a according to the length of the building material unit, and supports the other end of the building material unit by a lower ring. It functions as an eye plate on the other end.
In this embodiment, the eye plate 4a and each eye plate 4b-4e
The intervals between and are set according to the lengths of building material units 8a to 8e described later with reference to FIGS.

また、梁部材1の上面側には、アッパースリング2A,2B
のフック2c,2f,2gを係止される複数(本実施例では5
個)のクレーン懸吊用アイプレート(掛け止め用金具)
5a〜5eが設けられている。そして、これらのアイプレー
ト5a〜5eは、前述した建材ユニット吊下用アイプレート
4a〜4eの位置に対応して配置されている。
Also, on the upper surface side of the beam member 1, upper slings 2A, 2B
A plurality of hooks 2c, 2f, 2g (5 in this embodiment)
) Eye plates for hanging the crane (brackets for hanging)
5a-5e are provided. These eye plates 5a to 5e are the eye plates for hanging the building material unit described above.
It is arranged corresponding to the positions of 4a to 4e.

さらに、アッパースリング2A,2Aは、常時使用されるも
ので、鎖部2aに大径リング2bを介装されるとともに、上
端部をマスターリング3に取り付けられ、下端部にアイ
プレート5a〜5eに係止されるフック2cを取り付けられて
構成されている。また、アッパースリング2Bは、梁部材
1を3点支持する際(つまり建材ユニットをロアスリン
グにより6点支持する際)に使用されるもので、上端部
をマスターリング3に取り付けられた鎖部2aと、この鎖
部2a下端部に大径リング2bを介して接続された2本の鎖
部2d,2eと、各鎖部2d,2eの下端にそれぞれ取り付けられ
たフック2f,2gとから構成されている。ここで、鎖部2d,
フック2fは、アッパースリング2Bをアイプレート5bに係
止するのに適した長さに設定される一方、鎖部2e,フッ
ク2gは、アッパースリング2Bをアイプレート5cに係止す
るに適した長さに設定されている。
Further, the upper slings 2A, 2A are always used, the large diameter ring 2b is interposed in the chain portion 2a, the upper end is attached to the master ring 3, and the eye plates 5a to 5e are attached to the lower end. A hook 2c to be locked is attached and configured. The upper sling 2B is used when supporting the beam member 1 at three points (that is, when the building material unit is supported by the lower ring at six points), and the upper end of the chain part 2a is attached to the master ring 3. And two chain portions 2d and 2e connected to the lower end portion of the chain portion 2a through a large-diameter ring 2b, and hooks 2f and 2g attached to the lower ends of the respective chain portions 2d and 2e. ing. Where the chain 2d,
The hook 2f is set to a length suitable for locking the upper sling 2B to the eye plate 5b, while the chain portion 2e and the hook 2g have a length suitable for locking the upper sling 2B to the eye plate 5c. Is set to

ところで、アイプレート4a〜4eに係止されるロアスリン
グ6は、第2,3図に示すように構成されている。即ち、
ロアスリング6は、アイプレート4a〜4eに係止されるフ
ック6aと、このフック6aに鎖部6bおよび大径リング6cを
介して接続された2本の鎖部6d,6dと、各鎖部6d,6dの下
端部に取り付けられた建材ユニットに係止されるフック
6h,6hとを有している。そして、各鎖部6dには、4個の
大径のバランス(水平)調整用リング6eが介装されると
ともに、これらのリング6eよりも上方の鎖部6dからは、
リング6eに係止されうるバランス調整用フック6gが鎖部
6fを介し分岐して設けられている。
By the way, the lower ring 6 locked to the eye plates 4a to 4e is constructed as shown in FIGS. That is,
The lower ring 6 includes a hook 6a locked to the eye plates 4a to 4e, two chain portions 6d and 6d connected to the hook 6a via a chain portion 6b and a large diameter ring 6c, and each chain portion. Hook that is locked to the building material unit attached to the lower end of 6d, 6d
It has 6h and 6h. Then, four large-diameter balance (horizontal) adjusting rings 6e are interposed in each chain portion 6d, and from the chain portion 6d above these rings 6e,
The balance adjustment hook 6g that can be locked to the ring 6e is the chain
It is provided by branching through 6f.

さらに、第4図により、必要に応じて用いられる延長チ
ェーン7について説明する。この延長チェーン7は、特
にロアスリング6をさらに延長する必要がある場合(例
えば第6図により後述するような場合)について、ロア
スリング6のフック6hに係止されるもので、フック6hに
係止されうる連続する4個の大径リング7aと、最下端の
大径リング7aに取り付けられ建材ユニットに係止される
フック7bとから構成されている。
Further, referring to FIG. 4, the extension chain 7 used as necessary will be described. This extension chain 7 is engaged with the hook 6h of the lower ring 6 especially when the lower ring 6 needs to be further extended (for example, as will be described later with reference to FIG. 6). It is composed of four continuous large-diameter rings 7a that can be stopped, and hooks 7b that are attached to the large-diameter ring 7a at the lowermost end and are locked to the building material unit.

本考案の一実施例としての建材ユニット用吊り治具は上
述のごとく構成されているので、第5,6図に示すように
して各種の建材ユニット8a〜8fが吊り上げられ組立現場
(第7図の符号21参照)へ搬入される。
Since the building material unit hanging jig as one embodiment of the present invention is configured as described above, various building material units 8a to 8f are lifted up as shown in FIGS. (Refer to the reference number 21).

なお、本実施例では、建材ユニット8a〜8cは、それぞれ
長さが異なり4点支持によって吊下されるもの(それぞ
れ27ユニット,36ユニット,45ユニットと呼ばれるもの)
である。また、建材ユニット8d,8eは、いずれも同じ長
さで6点支持によって吊下されるものであるが、建材ユ
ニット8dは、中央位置に仕切部8gをもつもの〔54ユニッ
ト(27/27)〕であり、建材ユニット8eは、第5図
(f)に示すように2:1の位置に仕切部8hをもつもの〔5
4ユニット(36/18)〕である。さらに、建材ユニット8f
は、断面L字形の例えば屋上バルコニ等のユニットであ
る。
In the present embodiment, the building material units 8a to 8c have different lengths and are suspended by four-point support (each of which is called 27 units, 36 units, 45 units).
Is. Also, the building material units 8d and 8e are both of the same length and are hung by six-point support, but the building material unit 8d has a partition 8g at the central position [54 units (27/27) ], The building material unit 8e has a partition 8h at a 2: 1 position as shown in FIG. 5 (f) [5
4 units (36/18)]. Furthermore, building material unit 8f
Is a unit such as a rooftop balcony having an L-shaped cross section.

さて、4点支持を行なう建材ユニット8a〜8cについて
は、それぞれ第5図(a)〜(c)に示すように、各建
材ユニット8a〜8cの両端部が、それぞれ、端部アイプレ
ート4aと、この端部アイプレート4aから適当な間隔をあ
けた他端側アイプレート4b〜4dとに2組のロアスリング
6,6を介して支持され、各建材ユニット8a〜8cが梁部材
1の下方に吊下される。
Now, regarding the building material units 8a to 8c that perform four-point support, as shown in FIGS. 5A to 5C, both ends of the building material units 8a to 8c are respectively connected to the end eye plates 4a. , 2 sets of lower rings on the other end side eye plates 4b to 4d which are appropriately spaced from this end eye plate 4a
The building material units 8a to 8c are supported via 6 and 6 and are hung below the beam member 1.

このとき、建材ユニット8a〜8cは、その左端部が端部ア
イプレート4aのある梁部材1の左端部の位置に合わせて
吊下されることになるので、梁部材1の左端部側では、
この梁部材1が、従来のように建材ユニット8a〜8cより
も突出することはない。
At this time, since the left ends of the building material units 8a to 8c are suspended according to the position of the left end of the beam member 1 having the end eye plate 4a, on the left end side of the beam member 1,
The beam member 1 does not project more than the building material units 8a to 8c as in the conventional case.

また、第5図(a)〜(c)に示すごとく梁部材1の下
方に各建材ユニット8a〜8cを吊下した場合、各建材ユニ
ット8a〜8cを支持するアイプレート4a〜4dの位置に対応
したクレーン懸吊用アイプレート5a〜5dに、アッパース
リング2A,2Aをそれぞれ係止し、このアッパースリング2
A,2Aおよびマスターリング3を介してクレーンにより梁
部材1および各建材ユニット8a〜8cを懸吊する。つま
り、第5図(a)に示す建材ユニット8aについてはアイ
プレート5a,5bに、第5図(b)に示す建材ユニット8b
についてはアイプレート5a,5cに、さらに第5図(c)
に示す建材ユニット8cについてはアイプレート5a,5d
に、それぞれアッパースリング2A,2A下端のフック2c,2c
が係止される。
Further, as shown in FIGS. 5 (a) to (c), when the building material units 8a to 8c are hung below the beam member 1, at the positions of the eye plates 4a to 4d supporting the building material units 8a to 8c. The upper slings 2A, 2A are locked to the corresponding eye plates 5a to 5d for suspending cranes, and the upper slings 2
The beam member 1 and the building material units 8a to 8c are suspended by a crane via A, 2A and the master ring 3. That is, the building material unit 8a shown in FIG. 5 (a) is attached to the eye plates 5a, 5b, and the building material unit 8b shown in FIG. 5 (b).
For eye plates 5a and 5c, see Fig. 5 (c)
For building material unit 8c shown in, eye plates 5a, 5d
Upper hooks 2c, 2A bottom hooks 2c, 2c, respectively
Is locked.

このようにアッパースリング2A,2Aを係止することによ
り、建材ユニット8a〜8cが、第5図(a)〜(c)に示
すように、梁部材1の下方において左端側へ片寄って吊
下されても、バランスを損なうことなく懸吊される。
By locking the upper slings 2A, 2A in this way, the building material units 8a to 8c are hung toward the left end side below the beam member 1 as shown in FIGS. 5 (a) to (c). Even if it is done, it is suspended without losing the balance.

なお、第5図(a)〜(c)に示す例では4点支持であ
るので、アッパースリング2Bは不要であり、その不要時
には、アッパースリング2B先端のフック2f,2gをアッパ
ースリング2Aの大径リング2bに係止させておき、アッパ
ースリング2Bが操作の邪魔になるのを防止している。
In addition, in the example shown in FIGS. 5 (a) to (c), since the four points are supported, the upper sling 2B is unnecessary, and when it is not necessary, the hooks 2f, 2g at the tip of the upper sling 2B are attached to the upper sling 2A. It is locked to the diameter ring 2b to prevent the upper sling 2B from interfering with the operation.

また、第5図(a)に示す建材ユニット8aについては、
その長さが梁部材1の長さの半分であるので、第5図
(a)に実線で示す位置もしくは鎖線で示す位置のいず
れでも、建材ユニット8aを吊り上げることができる。つ
まり、鎖線で示す位置では、建材ユニット8aをアイプレ
ート4b,4eにより支持するとともに、アッパースリング2
A,2Aをアイプレート5b,5eに係止する。
Further, regarding the building material unit 8a shown in FIG. 5 (a),
Since the length is half the length of the beam member 1, the building material unit 8a can be lifted at either the position shown by the solid line or the position shown by the chain line in FIG. 5 (a). That is, at the position shown by the chain line, the building material unit 8a is supported by the eye plates 4b and 4e, and the upper sling 2
Lock A and 2A on the eye plates 5b and 5e.

一方、6点支持を行なう建材ユニット8d,8eについて
は、それぞれ第5図(d)または(e),(f)に示す
ように吊り上げられる。即ち、各建材ユニット8d,8eの
両端部が、それぞれ、端部アイプレート4aと、梁部材1
の右端部に配置される他端側アイプレート4eとにロアス
リング6,6を介して支持されるとともに、仕切部8g,8h位
置が、他端側アイプレート4bまたは4cにロアスリング6
を介して支持される。これにより、各建材ユニット8d,8
eが梁部材1の下方に吊下される。このとき、建材ユニ
ット8d,8eは梁部材1の長さとほぼ等しい長さをもつた
め、これらの建材ユニット8d,8eについては、その両端
部が梁部材1の両端部の位置に合わせて吊下されること
になり、梁部材1が、従来のように建材ユニット8d,8e
よりも突出することはない。
On the other hand, the building material units 8d and 8e that support six points are lifted as shown in FIG. 5 (d) or (e), (f), respectively. That is, both ends of each building material unit 8d, 8e are respectively the end eye plate 4a and the beam member 1
It is supported by the other end side eye plate 4e arranged at the right end of the through lower rings 6 and 6, and the partition portions 8g and 8h are located on the other end side eye plate 4b or 4c.
Supported through. As a result, each building material unit 8d, 8
e is suspended below the beam member 1. At this time, since the building material units 8d and 8e have a length substantially equal to the length of the beam member 1, both ends of these building material units 8d and 8e are hung according to the positions of both ends of the beam member 1. As a result, the beam member 1 is constructed as in the conventional construction material units 8d, 8e.
No more prominent.

また、第5図(d)〜(f)に示すごとく梁部材1の下
方に各建材ユニット8d,8eを吊下した場合、各建材ユニ
ット8d,8eを支持する3個のアイプレート4a,4b,4eまた
は4a,4c,4eの位置に対応したクレーン懸吊用アイプレー
ト5a,5b,5eまたは5a,5c,5eに、アッパースリング2A,2B,
2Aをそれぞれ係止し、このアッパースリング2A,2B,2Aお
よびマスターリング3を介してクレーンにより梁部材1
および各建材ユニット8d,8eを懸吊する。このように3
本のアッパースリング2A,2B,2Aを係止することにより、
6点支持される建材ユニット8d,8eが、バランスを損な
うことなく且つ梁部材1の変形を招くことなく懸吊され
る。
Moreover, when each building material unit 8d, 8e is hung below the beam member 1 as shown in FIGS. 5 (d) to (f), three eye plates 4a, 4b supporting each building material unit 8d, 8e. , 4e or 4a, 4c, 4e corresponding to the crane suspension eye plates 5a, 5b, 5e or 5a, 5c, 5e, upper sling 2A, 2B,
2A are respectively locked, and a beam member 1 is made by a crane through the upper slings 2A, 2B, 2A and the master ring 3.
And each building material unit 8d, 8e is suspended. Like this 3
By locking the book upper sling 2A, 2B, 2A,
The building material units 8d and 8e supported at six points are suspended without impairing the balance and without causing deformation of the beam member 1.

このように、本実施例の吊り治具によれば、各建材ユニ
ット8a〜8eは、バランスを損なうことなく、少なくとも
左端部を梁部材1の左端部の位置に合わせて吊下される
ことになるので、梁部材1の左端部側ではこの梁部材1
が各建材ユニット8a〜8eよりも突出することはない。従
って、第5図(a)に示すように、建材ユニット8a(8b
〜8eについても同様)と足場22等の障害物とが干渉し合
うのを確実に防止できて、足場22近傍位置であっても建
材ユニット8a〜8eを搬入でき、搬入作業性が大幅に向上
する。
As described above, according to the hanging jig of the present embodiment, each building material unit 8a to 8e is hung so that at least the left end is aligned with the position of the left end of the beam member 1 without impairing the balance. Therefore, on the left end side of the beam member 1, the beam member 1
Does not protrude beyond the building material units 8a to 8e. Therefore, as shown in FIG. 5 (a), the building material unit 8a (8b
~ 8e) and obstacles such as scaffolding 22 can be surely prevented from interfering with each other, and building material units 8a to 8e can be carried in even at a position near scaffolding 22, greatly improving the workability of carrying in. To do.

また、本実施例では、第5図(d)〜(f)に示すよう
に、建材ユニット8d,8eを6点支持する際には、その支
持位置に合わせて3本のアッパースリング2A,2Bが用い
られるので、梁部材1の変形を防止できるという利点も
ある。
Further, in this embodiment, as shown in FIGS. 5 (d) to (f), when the building material units 8d, 8e are supported at six points, three upper slings 2A, 2B are aligned with their supporting positions. Is used, there is also an advantage that the deformation of the beam member 1 can be prevented.

ところで、次に、ロアスリング6におけるバランス調整
用のリング6eおよびフック6gと、第4図に示した延長チ
ェーン7との使用例について第6図により説明する。第
6図に示すように、例えば、建材ユニットとして断面L
字形の例えば屋上バルコニ等のユニット8fを吊り上げる
場合、このような建材ユニット8fを水平に吊下するため
には、ロアスリング6において左右の長さを変える必要
がある。
Now, an example of use of the ring 6e and the hook 6g for balance adjustment in the lower ring 6 and the extension chain 7 shown in FIG. 4 will be described with reference to FIG. As shown in FIG. 6, for example, a section L as a building material unit
When a unit 8f such as a rooftop balcony is lifted, it is necessary to change the left and right lengths of the lower ring 6 in order to suspend such a building material unit 8f horizontally.

そこで、本実施例では、ロアスリング6の右側について
は、フック6gを最下部のリング6eに係止し3個のリング
6eを弛ませることにより長さを短縮する一方、ロアスリ
ング6の左側については、フック6gを係止させずに、下
端のフック6hに延長チェーン7を係止させる。そして、
フック6hと、延長チェーン7下端のフック7bとをそれぞ
れ建材ユニット8fに係止させることにより、建材ユニッ
ト8fが水平に保たれながら懸吊されることになる。
Therefore, in the present embodiment, on the right side of the lower ring 6, the hook 6g is locked to the lowermost ring 6e and three rings are attached.
While the length is shortened by loosening 6e, the extension chain 7 is locked to the lower end hook 6h without locking the hook 6g on the left side of the lower ring 6. And
By locking the hook 6h and the hook 7b at the lower end of the extension chain 7 to the building material unit 8f, the building material unit 8f is suspended while being kept horizontal.

このように、バランス調整用のリング6e,フック6gや延
長チェーン7を用いることで、懸吊すべき建材ユニット
の重量のバランス調整が容易にできるほか、断面L字形
の屋上バルコニ等のユニット8fがロアスリング6の吊り
角度αを適正角度に確保しながら懸吊されるので、大き
な吊り角度αによる建材ユニット8fにおけるアイボルト
部(図示せず)の破損が防止される。
In this way, by using the balance adjusting ring 6e, the hook 6g, and the extension chain 7, the balance of the weight of the building material unit to be suspended can be easily adjusted, and the unit 8f such as a rooftop balcony having an L-shaped cross section can be lowered. Since the ring 6 is suspended while ensuring a proper suspension angle α, the eyebolt portion (not shown) in the building material unit 8f due to the large suspension angle α is prevented from being damaged.

なお、上記実施例において、フック2f,2g,建材ユニット
吊下用アイプレート4a〜4e,クレーン懸吊用アイプレー
ト5a〜5e,バランス調整用リング6e等に適当な色を塗装
することにより、吊り治具の操作性を高めることができ
るほか、バランス調整に際して作業ミスが発生するのを
防止できる。例えば、フック2fとアイプレート5bとを黄
色塗装し、フック2gとアイプレート5cとを赤色塗装する
ことにより、フック2f,2gをそれぞれ間違ったアイプレ
ート5c,5bへ係止するような作業ミスが発生するのを防
止できる。
In the above example, the hooks 2f and 2g, the building material unit hanging eye plates 4a to 4e, the crane hanging eye plates 5a to 5e, the balance adjustment ring 6e, etc. are painted by applying an appropriate color, thereby hanging. In addition to improving the operability of the jig, it is possible to prevent work errors during balance adjustment. For example, by painting the hook 2f and the eye plate 5b in yellow and painting the hook 2g and the eye plate 5c in red, there is a mistake in working such as locking the hooks 2f and 2g to the wrong eye plates 5c and 5b. It can be prevented from occurring.

また、上記実施例では、掛け止め金具として、アイプレ
ートを用いた場合について説明したが、本考案は、これ
に限定されるものではなく、アイボルト,掛け止めリン
グ,フック等を用いてもよい。
Further, in the above-described embodiment, the case where the eye plate is used as the hook metal is described, but the present invention is not limited to this, and an eye bolt, a hook ring, a hook, or the like may be used.

[考案の効果] 以上詳述したように、本考案の建材ユニット用吊り治具
によれば、複数種の長さの建材ユニットを、バランスを
損なうことなく吊下でき、しかも建材ユニットの一端部
を梁部材の一端部の位置に合わせて吊下できるで、梁部
材の一端部側でこの梁部材が吊下された建材ユニットよ
りも突出することはなくなり、建材ユニットと先行足場
等の障害物とが干渉し合うのを確実に防止しながら建材
ユニットを搬入でき、搬入作業性が大幅に向上するとい
う効果が得られる。
[Effects of the Invention] As described in detail above, according to the hanging jig for a building material unit of the present invention, it is possible to hang building material units of a plurality of lengths without impairing the balance, and at the same time, one end of the building material unit. Can be suspended according to the position of one end of the beam member, so that the beam member does not project beyond the suspended building material unit on the one end side of the beam member, and the building material unit and obstacles such as preceding scaffolding It is possible to bring in the building material unit while surely preventing the interference with each other, and it is possible to obtain an effect that the carrying-in workability is significantly improved.

【図面の簡単な説明】[Brief description of drawings]

第1〜6図は本考案の一実施例としての建材ユニット用
吊り治具を示すもので、第1図はその梁部材および上部
吊り索を示す正面図、第2図はその下部吊り索の例を示
す正面図、第3図は上記下部吊り索の側面図、第4図は
その延長チェーンを示す正面図、第5図(a)〜(f)
および第6図はいずれも本実施例での吊り治具の動作を
説明するための図であり、第7図は一般的な建材ユニッ
トの組立現場を説明するための平面図、第8図は従来の
建材ユニット用吊り治具を示す正面図である。 図において、1…梁部材、2A,2B…アッパースリング
(上部吊り索)、2a…鎖部、2b…大径リング、2c…フッ
ク、2d,2e…鎖部、2f,2g…フック、3…マスターリン
グ、4a…端部アイプレート(建材ユニット吊下用掛け止
め金具)、4b〜4e…他端側アイプレート(建材ユニット
吊下用掛け止め金具)、5a〜5e…クレーン懸吊用アイプ
レート(クレーン懸吊用掛け止め金具)、6…ロアスリ
ング(下部吊り索)、6a…フック、6b…鎖部、6c…大径
リング、6d…鎖部、6e…バランス調整用リング、6f…鎖
部、6g…バランス調整用フック、6h…フック、7…延長
チェーン、7a…大径リング、7b…フック、8a〜8f…建材
ユニット、8g〜8h…仕切部。
1 to 6 show a hanging jig for a building material unit as one embodiment of the present invention. FIG. 1 is a front view showing the beam member and an upper hanging rope, and FIG. 2 is a lower hanging rope. A front view showing an example, FIG. 3 is a side view of the lower suspension rope, FIG. 4 is a front view showing an extension chain thereof, and FIGS. 5 (a) to 5 (f).
6 and FIG. 6 are diagrams for explaining the operation of the hanging jig in this embodiment, FIG. 7 is a plan view for explaining an assembly site of a general building material unit, and FIG. It is a front view which shows the conventional hanging jig for building materials units. In the figure, 1 ... Beam member, 2A, 2B ... Upper sling (upper suspension line), 2a ... Chain part, 2b ... Large diameter ring, 2c ... Hook, 2d, 2e ... Chain part, 2f, 2g ... Hook, 3 ... Master ring, 4a ... End eye plate (building material unit hanging latch), 4b-4e ... Other end eye plate (building unit hanging latch), 5a-5e ... Crane hanging eye plate (Hanging metal for hanging the crane), 6 ... Lower ring (lower suspension line), 6a ... Hook, 6b ... Chain part, 6c ... Large diameter ring, 6d ... Chain part, 6e ... Balance adjusting ring, 6f ... Chain Part, 6g ... Balance adjusting hook, 6h ... Hook, 7 ... Extension chain, 7a ... Large diameter ring, 7b ... Hook, 8a-8f ... Building material unit, 8g-8h ... Partition section.

───────────────────────────────────────────────────── フロントページの続き (56)参考文献 実願昭和54−115646号(実開昭56− 32764号)の願書に添付した明細書及び図 面の内容を撮影したマイクロフィルム(J P,U) ─────────────────────────────────────────────────── ───Continued from the front page (56) References Microfilm (JP, U), which is a photograph of the details and drawings attached to the application for Japanese Patent Application No. Showa 54-115646 (No. Sho 56-32764). )

Claims (1)

【実用新案登録請求の範囲】[Scope of utility model registration request] 【請求項1】複数種の長さの建材ユニットを吊下すべ
く、上方から上部吊り索を介してクレーンにより懸吊さ
れるとともに下方に複数の下部吊り索を介して前記建材
ユニットを吊下する梁部材を有し、前記梁部材の上面側
に設けられ前記上部吊り索の下端を係止される複数のク
レーン懸吊用掛け止め金具と、前記梁部材の下面側に設
けられ前記下部吊り索の上端を係止される複数の建材ユ
ニット吊下用掛け止め金具とをそなえてなる建材ユニッ
ト用吊り治具において、前記複数の建材ユニット吊下用
掛け止め金具が、前記梁部材の一端部に設けられ前記建
材ユニットの一端部を前記下部吊り索により支持する端
部掛け止め金具と、前記複数種の建材ユニットの長さに
応じ前記端部掛け止め金具との間に適当な間隔をあけて
前記梁部材の他端側に設けられ前記建材ユニットの他端
部を前記下部吊り索により支持する複数の他端側掛け止
め金具とからなるとともに、前記複数のクレーン懸吊用
掛け止め金具が、前記複数の建材ユニット吊下用掛け止
め金具の各位置に対応して設けられていることを特徴と
する建材ユニット用吊り治具。
1. A construction material unit having a plurality of lengths is suspended from above by a crane via an upper suspension rope, and the construction material unit is suspended downward from a plurality of lower suspension ropes. A plurality of hanging metal fittings for suspending a crane, which has a beam member, is provided on an upper surface side of the beam member and locks a lower end of the upper hanging rope, and the lower hanging rope provided on a lower surface side of the beam member. In a building material unit hanging jig, which comprises a plurality of building material unit hanging latches that are locked at the upper ends of the above, the plurality of building material unit hanging latches are provided at one end of the beam member. An appropriate interval is provided between the end hooks provided to support one end of the building material unit by the lower suspension rope and the end hooks according to the length of the plurality of types of building material units. The other end side of the beam member A plurality of other end side retaining metal fittings provided to support the other end of the building material unit by the lower suspension rope, and the plurality of crane suspension retaining metal fittings are for suspending the plurality of building material units. A hanging jig for a building material unit, characterized in that it is provided corresponding to each position of the hanging metal fitting.
JP1989013527U 1989-02-09 1989-02-09 Hanging jig for building material unit Expired - Lifetime JPH0723486Y2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP1989013527U JPH0723486Y2 (en) 1989-02-09 1989-02-09 Hanging jig for building material unit

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP1989013527U JPH0723486Y2 (en) 1989-02-09 1989-02-09 Hanging jig for building material unit

Publications (2)

Publication Number Publication Date
JPH02105446U JPH02105446U (en) 1990-08-22
JPH0723486Y2 true JPH0723486Y2 (en) 1995-05-31

Family

ID=31223907

Family Applications (1)

Application Number Title Priority Date Filing Date
JP1989013527U Expired - Lifetime JPH0723486Y2 (en) 1989-02-09 1989-02-09 Hanging jig for building material unit

Country Status (1)

Country Link
JP (1) JPH0723486Y2 (en)

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5632764U (en) * 1979-08-22 1981-03-31

Also Published As

Publication number Publication date
JPH02105446U (en) 1990-08-22

Similar Documents

Publication Publication Date Title
CN100549348C (en) Construction method for hanging wide span arcuated open-web beam
CN112609953A (en) A operation platform for managing truss
JPH0723486Y2 (en) Hanging jig for building material unit
JP6661142B1 (en) Hanging scaffold
CN211257761U (en) Lifting type elevator shaft operating platform
CN113445723A (en) Construction platform for mounting overhanging structure curtain wall and mounting method
JP2022076945A (en) Suspended scaffold
JPH0317350A (en) Scaffold for building structure
JP3457168B2 (en) Construction method of long structure and lifting beam used in this method
JP3567425B2 (en) Horizontal stay for tower crane
JPH0711181B2 (en) Portable walkway for construction
CN220926005U (en) Girder steel hoist device of no bracket node
JPH061581Y2 (en) Crane lifting equipment
CN109368475A (en) The application method of super large abnormity furred ceiling shipped and lifting integrated auxiliary device
JP2003314054A (en) Temporary scaffold for steel work
CN217972216U (en) Reinforced concrete pipeline hoisting device and pipeline hoisting system
JPH0736001Y2 (en) Detachable lifting device
JPH072549Y2 (en) Crane lifting equipment
JP3004731U (en) Multi-point hanging jig
JPH0740668U (en) Suspension equipment for mountain retaining materials
CN115897986A (en) Installation method of simple operation platform for installation of bracket-free steel beam
JPH04153460A (en) Constructing method for building, and its equipment
JPH0978840A (en) Hanging metal tool for building
JPS6235802Y2 (en)
JPH0674642B2 (en) Jig for suspending wall materials and its usage

Legal Events

Date Code Title Description
EXPY Cancellation because of completion of term