JPH07127080A - Beam and floor constructing method in inversely placing constructing method - Google Patents

Beam and floor constructing method in inversely placing constructing method

Info

Publication number
JPH07127080A
JPH07127080A JP5275830A JP27583093A JPH07127080A JP H07127080 A JPH07127080 A JP H07127080A JP 5275830 A JP5275830 A JP 5275830A JP 27583093 A JP27583093 A JP 27583093A JP H07127080 A JPH07127080 A JP H07127080A
Authority
JP
Japan
Prior art keywords
floor
concrete
ground
constructing
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP5275830A
Other languages
Japanese (ja)
Inventor
Tomoyuki Sagami
友行 相模
Tadao Murano
忠男 村野
Yoshitaka Tsunemi
良隆 恒見
Isao Yanagisawa
功 柳沢
Yasunori Hanada
安功 花田
Hashira Tamaki
柱 玉木
Toku Kishishita
徳 岸下
Shigefumi Hayashi
茂史 林
Ryuichi Kotake
龍一 小竹
Tetsuo Kimura
哲雄 木村
Yoshinori Kobiyama
善則 小桧山
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Takenaka Komuten Co Ltd
Original Assignee
Takenaka Komuten Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Takenaka Komuten Co Ltd filed Critical Takenaka Komuten Co Ltd
Priority to JP5275830A priority Critical patent/JPH07127080A/en
Publication of JPH07127080A publication Critical patent/JPH07127080A/en
Pending legal-status Critical Current

Links

Abstract

PURPOSE:To contribute to reduction in construction cost and shortening of a construction period by improving workability by reducing extremely ordinary form work or timbering installing work in a beam and floor constructing method performed when an underground structural building frame of a building is constructed by the so-called inversely placing construction method. CONSTITUTION:Excavation of the ground 3 is performed up to a level L slightly deeper than an under surface of a beam 1 to be constructed, and leveling concrete 4 is placed up to an under surface level of the beam 1 from an excavation surface L, and a form material 5 for the beam is located on a side surface of the beam, and a timbering 6 for a floor is installed on the leveling concrete 4 in an under surface part of the floor 2, and a form material 7 for the floor is supported, and concrete 8 is placed in a part of the beam 1 and a part of the floor 2, and after the concrete 8 reveals strength, the leveling concrete 4 is removed together with the excavation of the ground 3, and the timbering 6 for the floor is removed. Thereby, the form materials 5 and 7 are placed as they are, and can be used for a regular purpose, and the timbering 6 for the floor can be used according to its necessity.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】この発明は、建物の地下構造躯体
を所謂逆打ち工法により施工する際に実施される、梁及
び床の構築方法に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method of constructing a beam and a floor, which is carried out when a substructure of a building is constructed by a so-called reverse construction method.

【0002】[0002]

【従来の技術】逆打ち工法で地下構造の梁や床を構築す
る方法としては、従来下記の方法が公知である。一般的
には、まず梁下の1.0m〜1.5m位まで地盤の根切
りを深く行い、当該根切り表面を平滑にする鋤取り作業
をし、捨てコンクリートを打設した後、梁部分の底面と
側面及び床部分の底面に型枠を建込み、これらの型枠は
前記捨てコンクリートの上に立てた支保工で強固に支持
せしめた上で、型枠上にコンクリートを打設する。打設
コンクリートが硬化し強度を発現した後に、まず支保工
を撤去し、前記型枠の解体作業を行い、しかる後に地盤
の根切り作業と共に捨てコンクリートを除去して更に下
階の構築を進める方法が広く知られている(例えば特公
昭56ー6453号参照)。
2. Description of the Related Art The following methods are conventionally known as methods for constructing beams and floors having an underground structure by a reverse construction method. Generally, first, the ground is deeply cut to a depth of about 1.0 m to 1.5 m below the beam, the plow work is performed to smooth the root cutting surface, and after discarding concrete, the beam part is placed. Forming molds on the bottom and side surfaces of the base and the bottom of the floor, and these molds are firmly supported by supporting works standing on the aforesaid concrete, and then concrete is placed on the form. After placing concrete hardens and develops strength, first remove the support work, dismantle the formwork, and then remove the discarded concrete along with the root cutting work of the ground and proceed with the construction of the lower floor Is widely known (for example, see Japanese Patent Publication No. 56-6453).

【0003】また、特開平4ー281920号公報に
は、根切り底に梁構築用溝を部分的に深く掘削し、同掘
削溝の底部に底板を設置するか又は捨てコンクリートを
打設し、その上に梁側面の型枠を建込むと共に、当該型
枠の上端レベルの根切り底面上に床用型枠を設置し、前
記床用型枠及び梁用型枠内にコンクリートを打設して梁
及び床を構築する方法が記載されている。
Further, in Japanese Unexamined Patent Publication (Kokai) No. 4-281920, a beam construction groove is partially excavated deep in the root cutting bottom, and a bottom plate is installed at the bottom of the excavation groove, or waste concrete is placed, A formwork on the side of the beam is built on it, a floor formwork is installed on the bottom cut bottom surface at the upper end level of the formwork, and concrete is placed in the floor formwork and beam formwork. A method of constructing beams and floors is described.

【0004】更に、床版の構築方法に関して、特公平4
ー21767号公報には、根切り表面上に捨てコンクリ
ートを打設し、その上に分離層を施した後、当該分離層
上に床版用の配筋とコンクリートの打設を行い、前記コ
ンクリートの硬化後に、前記捨てコンクリートと分離層
を除去しながら床版コンクリートの下部を根切りする構
築方法が記載されている。
Further, regarding the construction method of the floor slab, Japanese Patent Publication No.
No. 21767 gazette, after discarding concrete is placed on the root cutting surface, a separating layer is applied thereon, and then reinforcement for floor slab and concrete is placed on the separating layer, After hardening, the construction method is described in which the lower part of the floor slab concrete is cut off while removing the waste concrete and the separation layer.

【0005】[0005]

【本発明が解決しようとする課題】従来の特公昭56ー
6453号公報に記載された梁及び床の構築方法は、梁
用及び床用の型枠を多くの支保工でしっかりと支持せし
める型枠工事や、その他の作業が必要であり、大変面倒
で煩わしく、それに起因して事故も起き易い。また、作
業工程が多いことにより工期も長くかかるという問題も
ある。
SUMMARY OF THE INVENTION A conventional method for constructing a beam and a floor disclosed in Japanese Patent Publication No. 56-6453 discloses a mold which allows a beam and a floor frame to be firmly supported by many supporting works. Frame work and other work are required, which is very troublesome and troublesome, and accidents are likely to occur due to it. There is also a problem that the construction period is long due to the large number of working steps.

【0006】この点、特開平4ー281920号公報に
記載された梁の構築方法は、支保工を殆んど不用ならし
めた利点を認められる。しかし、梁構築用溝を更に掘削
したり、梁底面の型枠として前記掘削溝の底部に底板を
設置したり、又は捨てコンクリートを打設しておく必要
があり、梁の型枠工事後の埋戻しをするなど構築作業が
未だ簡素化されているとは云い難い。
In this respect, the beam construction method described in Japanese Patent Application Laid-Open No. 4-281920 has the advantage that the supporting work is almost unnecessary. However, it is necessary to further excavate the groove for beam construction, install a bottom plate at the bottom of the excavation groove as a form of the beam bottom, or pour waste concrete. It is hard to say that construction work such as backfilling is still simplified.

【0007】更に、特公平4ー21767号に係るコン
クリート床版の構築方法は、床型枠及びその支保工が一
切省略されて簡素化されているが、床(コンクリート床
版)の構築にのみ関する工法であり、フラットスラブ
(無梁スラブ)への適用性はあるが、梁又は梁付スラブ
の構築方法は具体的に開示されていない。したがって、
本発明の目的は、逆打ち工法において梁及び床を構築す
る際の型枠の建込み工事や支保工の設置作業などの現場
作業を極力軽減して簡素化し、大幅な省人化による工費
の低減、工期の短縮、安全性の向上が図れる梁及び床の
構築方法を提供することにある。
Further, the method of constructing a concrete floor slab according to Japanese Examined Patent Publication No. 4-21767 is simplified by completely omitting the floor formwork and its supporting works, but only for constructing a floor (concrete floor slab). It is a related construction method and is applicable to a flat slab (beamless slab), but a method for constructing a beam or a slab with a beam is not specifically disclosed. Therefore,
The object of the present invention is to reduce and simplify the on-site work such as the construction work of the formwork and the installation work of the support work when constructing the beam and the floor in the reverse construction method as much as possible, and the labor cost is greatly reduced by manpower. It is to provide a method of constructing a beam and a floor that can reduce the number of works, shorten the construction period, and improve safety.

【0008】[0008]

【課題を解決するための手段】上記従来技術の課題を解
決するための手段として、この発明に係る逆打ち工法に
おける梁及び床の構築方法は、図1に示したとおり、梁
1及び床2等の本設躯体を構築しながら地下階に向かっ
て順次地盤3の根切りと躯体の構築を繰り返して建物の
地下構造を構築する逆打ち工法において、構築すべき梁
1の下面よりも若干深いレベルLまで地盤3の根切りを
行い、前記根切り表面Lから梁1の下面レベルまで捨て
コンクリート(レベリングコンクリート)4を打設する
こと、梁の側面に梁用の型枠材5を建込み、床2の下面
部分には捨てコンクリート4上に床用の支保工6を設置
して床用の型枠材7を支持せしめ、梁1の部分及び床2
の部分にコンクリート8を打設すること、前記コンクリ
ート8が強度を発現した後に、地盤3の根切りと共に捨
てコンクリート4を除去し、前記床用支保工6を撤去せ
しめること、をそれぞれ特徴とする。
As a means for solving the above-mentioned problems of the prior art, the method of constructing a beam and a floor in the upside-down construction method according to the present invention is as shown in FIG. In the upside-down construction method in which the root structure of the ground 3 and the construction of the skeleton are repeated in sequence toward the basement floor while constructing the main structure of the building, etc., it is slightly deeper than the lower surface of the beam 1 to be constructed. The root 3 of the ground is cut to the level L, and the discarded concrete (leveling concrete) 4 is placed from the root cutting surface L to the lower surface level of the beam 1, and the form material 5 for the beam is built on the side surface of the beam. In the lower surface of the floor 2, a support 6 for the floor is installed on the discarded concrete 4 to support the formwork material 7 for the floor, and the portion of the beam 1 and the floor 2 are supported.
The concrete 8 is cast in the portion of, and after the concrete 8 develops strength, the waste concrete 4 is removed together with the root cutting of the ground 3, and the floor support 6 is removed. .

【0009】なお、前記構築方法において、根切り表面
Lから梁1の下面レベルまで捨てコンクリート4を打設
した後、捨てコンクリート4のうち少なくとも梁1の下
面部分に絶縁材9を敷設し又は表面処理を施した上で梁
側面に梁用の型枠材5を建込むことや、床用の支保工6
を一切使用しないで施工することも行われる。また、第
2の発明の床の構築方法は、図2に示したとおり、構築
すべき床2の下面よりも少し深いレベルL′まで地盤3
の根切りをして地均しを行い、前記地均し面上に捨てコ
ンクリート4を敷設し、その上に直接床用のコンクリー
ト15を打設し、前記床コンクリート15が強度を発現
した後に、地盤3の根切りと共に捨てコンクリート4を
除去することを特徴とする。
In the construction method, after the waste concrete 4 is cast from the root cutting surface L to the lower surface level of the beam 1, the insulating material 9 is laid on at least the lower surface portion of the beam 1 of the discarded concrete 4 or the surface thereof. After processing, erection of beam form material 5 on the beam side, and floor support 6
It is also possible to construct without using. In addition, as shown in FIG. 2, the floor construction method of the second invention is such that the ground 3 reaches a level L ′ slightly deeper than the lower surface of the floor 2 to be constructed.
After cutting the roots of the soil and leveling the ground, laying the concrete 4 on the leveling surface, and placing the concrete 15 for the floor directly on it, after the floor concrete 15 develops strength It is characterized in that the waste concrete 4 is removed together with the root cutting of the ground 3.

【0010】[0010]

【作用】梁下面よりも少し深いレベル(図1中、符号L
で示したレベル位置)まで地盤3の根切りを行い、当該
根切り表面Lから梁1の下面レベルまで捨てコンクリー
ト4を打設し、この捨てコンクリート4が梁底面の型枠
として有効に働く。その上、梁側面の型枠材5は前記捨
てコンクリート4上に立設(支持)して建込むから、結
局、梁1の構築に関しては、一切支保工を使用しないで
迅速に安全に施工することができる。当該梁用型枠材5
を打込むことにより本設のまま梁1が簡便に施工され
る。なお、梁下面に絶縁材9を敷設し又は表面処理を施
すことにより、捨てコンクリート4との縁切りを確実に
行うことができる。
[Function] A level slightly deeper than the bottom surface of the beam (L in FIG.
Root cutting of the ground 3 is performed up to the level position shown by, and the discarded concrete 4 is placed from the root cutting surface L to the lower surface level of the beam 1, and the discarded concrete 4 effectively works as a formwork of the beam bottom. Moreover, since the formwork material 5 on the side surface of the beam is erected by standing (supporting) on the abandoned concrete 4, the construction of the beam 1 is completed quickly and safely without using any supporting work. be able to. Formwork material 5 for the beam
The beam 1 can be easily installed as it is by setting. By laying the insulating material 9 on the lower surface of the beam or performing a surface treatment, it is possible to surely cut the edge with the discarded concrete 4.

【0011】床部分には前記捨てコンクリート4上に必
要に応じて支保工6を設置し型枠材7を支持せしめるの
で、型枠材7が床2の型枠として働くと共に、当該型枠
材7をそのまま打込むことにより床2が簡便に施工され
る。梁のないフラットスラブの場合も、床下面よりも少
し深い位置(図2中、L′で示したレベル位置)まで地
盤3の根切りをして地均しを行い、当該地均し面上に捨
てコンクリート4を敷設するので、この捨てコンクリー
ト4が床底面の型枠として効果的に機能する上、至極簡
便に無梁スラブを施工することができる。
In the floor portion, supporting members 6 are installed on the waste concrete 4 as needed to support the formwork material 7, so that the formwork material 7 functions as the formwork of the floor 2 and the formwork material concerned. The floor 2 is easily constructed by driving 7 as it is. Even in the case of flat slabs without beams, the ground 3 is cut off to a position slightly deeper than the bottom surface of the floor (level position indicated by L'in Fig. 2), and the ground leveling is performed on the leveling surface. Since the discarded concrete 4 is laid on the floor, the discarded concrete 4 effectively functions as a formwork for the floor bottom, and the beamless slab can be constructed extremely simply.

【0012】[0012]

【実施例】次に、図面に示した本発明の実施例を説明す
る。図1は、梁1及び床2から成る本設躯体を構築しな
がら地下階に向かって順次地盤3の根切りと躯体の構築
を繰り返し、鉄筋コンクリート又は鉄骨鉄筋コンクリー
ト構造の地下躯体を構築する逆打ち工法の実施例を示し
ている。図中符号13は山留め用に構築したソイル柱列
壁である。
Embodiments of the present invention shown in the drawings will be described below. Figure 1 shows a reverse construction method for constructing a reinforced concrete or steel reinforced concrete structure underground structure by constructing a permanent structure consisting of a beam 1 and a floor 2 and repeating root cutting of the ground 3 and construction of the structure sequentially toward the basement. The example of is shown. In the figure, reference numeral 13 is a soil pillar row wall constructed for mountain retaining.

【0013】まず、構築すべき梁1の下面から50mm
ぐらい深い下方レベルLの位置まで地盤3の根切りを行
って十分に地均しをし、前記下方レベル(根切り表面)
Lから梁1の下面レベルまで平滑な水平面を形成する捨
てコンクリート(レベリングコンクリート)4を打設す
る。つまり、捨てコンクリート4の上面レベルが梁1の
下面レベルと同一レベルとされ、この捨てコンクリート
4が梁底の型枠の役割を果たすから、梁1の底面にわざ
わざ型枠を建込む必要がない。
First, 50 mm from the lower surface of the beam 1 to be constructed
Root cutting of the ground 3 is performed to the position of the lower level L, which is about as deep as possible, and the ground level is sufficiently leveled to the lower level (root cutting surface).
A waste concrete (leveling concrete) 4 that forms a smooth horizontal surface from L to the lower surface level of the beam 1 is placed. That is, the upper surface level of the discarded concrete 4 is set to the same level as the lower surface level of the beam 1, and the discarded concrete 4 serves as a formwork for the beam bottom. Therefore, it is not necessary to construct a formwork on the bottom surface of the beam 1. .

【0014】したがって、前記捨てコンクリート4の表
面のうち梁1の下面部分に必要に応じてフィルムシート
などの絶縁材9を敷設したり又は図示を省略した剥離材
などで表面処理を施した上で、構築すべき梁1の側面の
仮設用又は打込み用の型枠材5を建込む。当該梁側面の
型枠材5は、その高さが捨てコンクリート4の上面から
床2の下面までの高さと略同じ550mmとされ、捨て
コンクリート4上に立設して建込まれるから、結局、梁
1の構築に際しては支保工が一切不要である。しかも、
当該床用の型枠材5としてセメント系ボード等を使用
し、それを打込むことにより本設のまま梁1が容易に施
工される。梁1の部分には大梁鉄骨10を設置すると共
に梁鉄筋11を配筋する。なお、前記の絶縁材9は、通
常は捨てコンクリート4を最終的に除去する際に一緒に
取り除かれるが、支障ない限り残置してもよい。
Therefore, if necessary, an insulating material 9 such as a film sheet may be laid on the lower surface of the beam 1 on the surface of the waste concrete 4 or a surface treatment such as a peeling material (not shown) may be applied. Then, a form material 5 for temporary installation or driving of the side surface of the beam 1 to be constructed is built. Since the height of the formwork material 5 on the side surface of the beam is 550 mm, which is approximately the same as the height from the upper surface of the discarded concrete 4 to the lower surface of the floor 2, it is built upright on the discarded concrete 4, so that No support work is required to construct the beam 1. Moreover,
A cement board is used as the frame material 5 for the floor, and by driving it into the beam 1, the beam 1 can be easily constructed with the main installation. A large beam steel frame 10 is installed on the beam 1 and beam reinforcing bars 11 are arranged. The insulating material 9 is usually removed together when the discarded concrete 4 is finally removed, but may be left as long as it does not interfere.

【0015】つづいて、床の構築に際し、構築すべき床
2の直下の前記捨てコンクリート4上に支保工6(高さ
約550mm)を設置し、この支保工6によって床用の
型枠材7を支持せしめる。前記床用型枠材7としては、
例えば床2の下面を形成する本設のデッキプレート(鋼
製材)や、PCa版やセメント系ボード(コンクリート
材)等が実施される。また、前記本設の型枠材7の代わ
りに仮設の型枠材(ベニヤ板の木製材など)を使用する
ことも可能である。前記床用の支保工6としては絶縁材
9からデッキプレート7までの高さ寸法と略等しい厚さ
の木製材のほか、発砲スチロールフォームなどの発泡材
が好適に使用される。発泡材は軽量で取扱いが便利な
上、強度も十分大きいからである。また、留め具14に
よって当該支保工6をデッキプレート7へ仮留めしてお
くことにより、後述の捨てコンクリート4の除去及び根
切り作業の際にも支保工6がバラけて破損する虞れがな
く、再利用が可能となる。但し、梁間の間隔が短かい場
合や梁で直接支持できる等の場合は、前記の床用の支保
工6を使用せずして施工することが可能である。なお、
床2の部分には床鉄筋12を配筋し、同床鉄筋12の端
部は前記梁1の大梁鉄骨10に定着させておく。しかる
後に、梁1の部分と床2の部分にコンクリート8を打設
する。
Subsequently, when constructing the floor, a supporting work 6 (height of about 550 mm) is installed on the aforesaid concrete 4 just below the floor 2 to be constructed, and by this supporting work 6, the formwork material 7 for the floor is used. Support. As the floor form material 7,
For example, a permanent deck plate (steel material) that forms the lower surface of the floor 2, a PCa plate, a cement board (concrete material), or the like is used. It is also possible to use a temporary form material (such as a veneer wood material) instead of the main form material 7. As the supporting member 6 for the floor, a wooden material having a thickness substantially equal to the height from the insulating material 9 to the deck plate 7 and a foam material such as expanded polystyrene foam are preferably used. This is because the foam material is lightweight, convenient to handle, and sufficiently strong. Further, by temporarily fastening the supporting work 6 to the deck plate 7 with the fasteners 14, there is a possibility that the supporting work 6 may be broken and damaged during the removal of the waste concrete 4 and the root cutting work described later. Instead, it can be reused. However, when the distance between the beams is short, or when the beams can be directly supported, it is possible to carry out the construction without using the above-mentioned floor supporter 6. In addition,
Floor reinforcing bars 12 are arranged on the floor 2, and the ends of the floor reinforcing bars 12 are fixed to the girder steel frame 10 of the beam 1. After that, concrete 8 is placed on the beam 1 and the floor 2.

【0016】前記の打設コンクリート8が硬化して所定
強度を発現した後、地盤3の根切りを再開して捨てコン
クリート4を除去し、仮設用の梁用型枠材5の解体及び
床用支保工6の撤去をして梁1及び床2が完成される。
従来のように複雑、雑多な型枠工事や支保工の設置作業
がないので、捨てコンクリート4(地盤3)の除去作業
も容易に迅速に行うことができる。しかも、作業場所が
地盤3の近くであり高所位置での作業がなく安全に施工
できる。
After the pouring concrete 8 hardens and develops a predetermined strength, root cutting of the ground 3 is restarted to remove the discarded concrete 4, and the beam form material 5 for temporary construction is dismantled and for the floor. The beam 1 and the floor 2 are completed by removing the support work 6.
Since there is no complicated and miscellaneous formwork work and installation work for supporting work unlike the conventional art, the work of removing the discarded concrete 4 (ground 3) can be performed easily and quickly. Moreover, since the work place is near the ground 3, there is no work at a high place, and construction can be performed safely.

【0017】以下、上記と同様の手順で地下階構造の梁
及び床の構築作業を下向きに進め、逆打ち工法による地
下構造躯体が円滑に構築される。
In the following, the construction work of the beam and floor of the basement floor structure is carried out downward by the same procedure as described above, and the underground structure frame is constructed smoothly by the upside down construction method.

【0018】[0018]

【第2実施例】図2は、同じく逆打ち工法において、フ
ラットスラブ(無梁スラブ)を構築する方法の実施例を
示している。床2の下面から50mmぐらい深い位置
(図2中、符号L′で示したレベル位置)まで地盤3の
根切りをして地均しを行い、当該地均し面の上に捨てコ
ンクリート4を打設する。この捨てコンクリート4がそ
の上に打設される床コンクリート15と縁切り可能な程
度に強度を発現した後、捨てコンクリート4の上に床鉄
筋12を設置して直接床コンクリート15を打設する。
当該床コンクリート15が硬化した後に地盤3の根切り
と共に前記捨てコンクリート4を除去してフラットスラ
ブ2を完成する。
[Second Embodiment] FIG. 2 shows an embodiment of a method for constructing a flat slab (beamless slab) also in the reverse construction method. From the bottom surface of the floor 2 to a depth of about 50 mm (level position shown by L'in FIG. 2), the root of the ground 3 is cut off to level the ground, and the concrete 4 is discarded on the leveled surface. To set. After the discarded concrete 4 develops strength to the extent that it can cut edges with the floor concrete 15 to be placed thereon, the floor reinforcing bars 12 are installed on the discarded concrete 4 and the floor concrete 15 is directly placed.
After the floor concrete 15 is hardened, the waste concrete 4 is removed together with the root cutting of the ground 3 to complete the flat slab 2.

【0019】したがって、前記捨てコンクリート4が床
底面の型枠として有効に働き、支保工を一切使用しない
で至極簡便にフラットスラブが構築され、施工性の向
上、工費の低減が達成される。
Therefore, the abandoned concrete 4 works effectively as a formwork for the floor bottom, and a flat slab can be constructed extremely easily without using any supporting work, and the workability can be improved and the construction cost can be reduced.

【0020】[0020]

【本発明が奏する効果】本発明に係る逆打ち工法におけ
る梁及び床の構築方法によれば、梁用型枠材5や床用型
枠材7をそのまま打込んで本設用に使用でき、しかも床
用の支保工6は必要に応じて使用されるので、通常の型
枠工事や支保工の設置作業が極力軽減される上に施工性
が向上され、大幅な省力化による工費の低減及び工期の
短縮に寄与する。また、作業場所が地盤3に近く高所作
業がないので安全性の向上にも貢献する。
According to the method of constructing a beam and a floor in the upside-down construction method according to the present invention, the beam form material 5 and the floor form material 7 can be directly driven and used for main installation, Moreover, since the support 6 for the floor is used as necessary, normal formwork work and installation work of the support can be reduced as much as possible, the workability is improved, and the construction cost can be reduced by the significant labor saving. Contributes to shortening the construction period. Further, since the work place is close to the ground 3 and there is no work at a high place, it contributes to the improvement of safety.

【図面の簡単な説明】[Brief description of drawings]

【図1】枢要な工程を示した断面図である。FIG. 1 is a cross-sectional view showing important steps.

【図2】第2実施例の枢要な断面図である。FIG. 2 is a pivotal sectional view of a second embodiment.

【符号の説明】[Explanation of symbols]

1 梁 2 床 3 地盤 4 捨てコンクリート 5 梁用型枠材 6 支保工 7 床用型枠材 8 コンクリート 9 絶縁材 15 床コンクリート 1 Beam 2 Floor 3 Ground 4 Discarded concrete 5 Beam formwork 6 Supporting work 7 Floor formwork 8 Concrete 9 Insulation 15 Floor concrete

───────────────────────────────────────────────────── フロントページの続き (72)発明者 柳沢 功 東京都中央区銀座八丁目21番1号 株式会 社竹中工務店東京本店内 (72)発明者 花田 安功 東京都中央区銀座八丁目21番1号 株式会 社竹中工務店東京本店内 (72)発明者 玉木 柱 東京都中央区銀座八丁目21番1号 株式会 社竹中工務店東京本店内 (72)発明者 岸下 徳 東京都中央区銀座八丁目21番1号 株式会 社竹中工務店東京本店内 (72)発明者 林 茂史 東京都中央区銀座八丁目21番1号 株式会 社竹中工務店東京本店内 (72)発明者 小竹 龍一 東京都中央区銀座八丁目21番1号 株式会 社竹中工務店東京本店内 (72)発明者 木村 哲雄 東京都中央区銀座八丁目21番1号 株式会 社竹中工務店東京本店内 (72)発明者 小桧山 善則 東京都中央区銀座八丁目21番1号 株式会 社竹中工務店東京本店内 ─────────────────────────────────────────────────── ─── Continuation of front page (72) Inventor Isao Yanagisawa 8-21-1, Ginza, Chuo-ku, Tokyo Stock company Takenaka Corporation Tokyo head office (72) Inventor Anjo Hanada 8--21, Ginza, Chuo-ku, Tokyo No. 1 Takenaka Corporation Tokyo Main Store (72) Inventor Pillar Tamaki 21-21 Ginza, Chuo-ku, Tokyo Stockholder Takenaka Corporation Tokyo Main Store (72) Inventor Toshi Kishishita Central Tokyo 8-21-1, Ginza, Ginza, Tokyo Takenaka Corporation Tokyo Main Store (72) Inventor Shigefumi Hayashi 8-21-1, Ginza, Chuo-ku, Tokyo Takenaka Corporation Tokyo Head Office (72) Inventor Kotake Ryuichi Tokyo Ginza 8-21-1, Chuo-ku, Tokyo Stock company Takenaka Corporation Tokyo Main Store (72) Inventor Tetsuo Kimura Ginza 8-chome, Chuo-ku, Tokyo Takenaka Corporation Tokyo Main Store ( 72) Inventor Yoshinori Kobikiyama, 21-21 Ginza 8-chome, Chuo-ku, Tokyo Stock company Takenaka Corporation Tokyo head office

Claims (4)

【特許請求の範囲】[Claims] 【請求項1】梁及び床等の本設躯体を構築しながら地下
階に向かって順次地盤の根切りと躯体の構築を繰り返し
て建物の地下構造を構築する逆打ち工法において、 構築すべき梁の下面よりも若干深いレベルまで地盤の根
切りを行い、前記根切り表面から梁の下面レベルまで捨
てコンクリートを打設すること、 梁の側面に梁用の型枠材を建込み、床の下面部分には捨
てコンクリート上に床用の支保工を設置して型枠材を支
持せしめ、梁部分及び床部分にコンクリートを打設する
こと、 前記コンクリートが強度を発現した後に、地盤の根切り
と共に捨てコンクリートを除去し、前記床用支保工を撤
去すること、を特徴とする、逆打ち工法における梁及び
床の構築方法。
1. A beam to be constructed in a reverse construction method for constructing an underground structure of a building by repeating root cutting of the ground and construction of the structure sequentially toward the basement floor while constructing a main structure such as beams and floors. Root cutting of the ground to a level slightly deeper than the bottom surface of the ground, and pouring waste concrete from the root cutting surface to the bottom surface level of the beam. Place a supporting structure for the floor on the discarded concrete to support the formwork material, and place the concrete on the beam part and the floor part, after the concrete develops strength, along with root cutting of the ground A method for constructing a beam and a floor in a reverse construction method, characterized in that discarded concrete is removed and the floor support is removed.
【請求項2】根切り表面から梁の下面レベルまで捨てコ
ンクリートを打設した後、前記捨てコンクリートの表面
のうち少なくとも梁の下面部分に絶縁材を敷設し又は表
面処理を施した上で梁側面に梁用の型枠材を建込むこと
を特徴とする、請求項1に記載した逆打ち工法における
梁及び床の構築方法。
2. After the waste concrete is cast from the root cutting surface to the lower surface level of the beam, at least the lower surface portion of the beam of the surface of the discarded concrete is laid with an insulating material or subjected to a surface treatment and then the side surface of the beam. The method for constructing a beam and a floor in the upside-down construction method according to claim 1, wherein a form material for the beam is built in.
【請求項3】床用の支保工を一切使用しないで施工する
ことを特徴とする、請求項1又は2に記載した逆打ち工
法における梁及び床の構築方法。
3. The method for constructing a beam and a floor in the upside-down construction method according to claim 1 or 2, characterized in that the construction is carried out without using any supporting work for the floor.
【請求項4】床等の本設躯体を構築しながら地下階に向
かって順次地盤の根切りと躯体の構築を繰り返して建物
の地下構造を構築する逆打ち工法において、 構築すべき床の下面よりも少し深いレベルまで地盤の根
切りをして地均しを行い、前記地均し面上に捨てコンク
リートを敷設すること、 前記捨てコンクリートの上に直接床コンクリートを打設
し、当該床コンクリートが強度を発現した後に、地盤の
根切りと共に捨てコンクリートを除去すること、を特徴
とする、逆打ち工法における床の構築方法。
4. A bottom surface of a floor to be constructed in a reverse construction method for constructing an underground structure of a building by sequentially repeating root cutting of the ground and construction of the structure toward the basement floor while constructing a permanent structure such as a floor. Performing ground leveling by cutting the ground to a level slightly deeper than that, laying waste concrete on the leveling surface, placing floor concrete directly on the waste concrete, and applying the floor concrete. The method for constructing a floor in the upside-down construction method, characterized in that the concrete is removed and then the discarded concrete is removed together with the ground cutting.
JP5275830A 1993-11-04 1993-11-04 Beam and floor constructing method in inversely placing constructing method Pending JPH07127080A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP5275830A JPH07127080A (en) 1993-11-04 1993-11-04 Beam and floor constructing method in inversely placing constructing method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP5275830A JPH07127080A (en) 1993-11-04 1993-11-04 Beam and floor constructing method in inversely placing constructing method

Publications (1)

Publication Number Publication Date
JPH07127080A true JPH07127080A (en) 1995-05-16

Family

ID=17561027

Family Applications (1)

Application Number Title Priority Date Filing Date
JP5275830A Pending JPH07127080A (en) 1993-11-04 1993-11-04 Beam and floor constructing method in inversely placing constructing method

Country Status (1)

Country Link
JP (1) JPH07127080A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08158384A (en) * 1994-12-01 1996-06-18 Takenaka Komuten Co Ltd Timbering of floor form, etc.

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS62253821A (en) * 1986-04-23 1987-11-05 Shimizu Constr Co Ltd Construction of concrete floor slab
JPH04258439A (en) * 1991-02-13 1992-09-14 Kajima Corp Construction of concrete slab and half-precast concrete floor bed therefor
JPH0579049A (en) * 1991-09-20 1993-03-30 Fujita Corp Constructing method for beam and slab in underground body construction work

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS62253821A (en) * 1986-04-23 1987-11-05 Shimizu Constr Co Ltd Construction of concrete floor slab
JPH04258439A (en) * 1991-02-13 1992-09-14 Kajima Corp Construction of concrete slab and half-precast concrete floor bed therefor
JPH0579049A (en) * 1991-09-20 1993-03-30 Fujita Corp Constructing method for beam and slab in underground body construction work

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08158384A (en) * 1994-12-01 1996-06-18 Takenaka Komuten Co Ltd Timbering of floor form, etc.

Similar Documents

Publication Publication Date Title
WO1991019055A1 (en) A method of erecting a foundation structure for a building substructure
JPH0579049A (en) Constructing method for beam and slab in underground body construction work
JP3159141B2 (en) Construction method of building frame using existing outer wall
JP3053938B2 (en) Double striking method
JPH07127080A (en) Beam and floor constructing method in inversely placing constructing method
JPH11303386A (en) Construction method of building frame
JPH07127081A (en) Beam and floor constructing method in inversely placing constructing method
JPH07150579A (en) Floor construction method in inversely driving construction method
JPH07138972A (en) Construction method for underground skeleton
JPS62253821A (en) Construction of concrete floor slab
JP2555838B2 (en) Independent panel mountain retaining method
JPH07150578A (en) Floor construction method in inversely driving construction method
JP3108898B2 (en) Construction method of underground structure by reverse construction method
JPH07113220B2 (en) Beam construction method
AU703801B2 (en) Building construction method
JP3289163B2 (en) How to build underground structures
JPH0718675A (en) Sc pile and executing method thereof
JPH0681354A (en) Construction method for underground structural skeleton
CN116791885A (en) Daylighting well construction method
JPH02101223A (en) Construction method for ceiling slab for underground space
JP3062539B2 (en) Underground wall and its construction method
Bailey et al. Massive resistance
SU977644A1 (en) Method for erecting cast-in-place buildings
JPH07189396A (en) Floor slab construction method
JPH06146299A (en) Jointingly placing method for concrete foundation