JPH0699940B2 - Method of constructing underground skeleton and formwork for underground skeleton construction - Google Patents

Method of constructing underground skeleton and formwork for underground skeleton construction

Info

Publication number
JPH0699940B2
JPH0699940B2 JP1336575A JP33657589A JPH0699940B2 JP H0699940 B2 JPH0699940 B2 JP H0699940B2 JP 1336575 A JP1336575 A JP 1336575A JP 33657589 A JP33657589 A JP 33657589A JP H0699940 B2 JPH0699940 B2 JP H0699940B2
Authority
JP
Japan
Prior art keywords
formwork
constructing
water
skeleton
mold
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP1336575A
Other languages
Japanese (ja)
Other versions
JPH03199531A (en
Inventor
昭 内田
Original Assignee
株式会社間組
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 株式会社間組 filed Critical 株式会社間組
Priority to JP1336575A priority Critical patent/JPH0699940B2/en
Publication of JPH03199531A publication Critical patent/JPH03199531A/en
Publication of JPH0699940B2 publication Critical patent/JPH0699940B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Description

【発明の詳細な説明】 〈産業上の利用分野〉 本発明は地盤中に構築構造物の躯体を構築する地下躯体
の構築方法及び地下躯体構築用型枠に関する。
TECHNICAL FIELD The present invention relates to a method of constructing an underground skeleton for constructing a skeleton of a construction structure in the ground and a formwork for constructing an underground skeleton.

〈従来の技術〉 従来、地盤中にビル等の建築構造物の躯体を構築する場
合には、一般に根切り工が行なわれる。この根切り工を
行うには、まず根切り周囲の地盤から作用する土圧及び
水圧を支持するための山留め壁を築造し、該山留め壁で
囲まれた内側に、順次支保工を行いながら、必要な深さ
まで地盤の掘削を行うものである。上記のように掘削し
た掘削坑内の床付面や壁面で型枠を支持し、コンクリー
トを打設し地下躯体を構築していた。
<Prior Art> Conventionally, when constructing a skeleton of a building structure such as a building in the ground, root cutting work is generally performed. To perform this root cutting work, first build a mountain retaining wall to support the earth pressure and water pressure acting from the ground around the root cutting, and while performing the support work sequentially inside the mountain retaining wall, The ground is excavated to the required depth. The formwork was supported by the floor surface and wall surface in the excavation mine excavated as described above, and concrete was placed to construct the underground structure.

〈発明が解決しようとする課題〉 従来の地下躯体の構築方法では、床付け面まで根切り工
を行う場合には、山留め壁の構築→掘削→支保工→従来
掘削→支保工・・・を繰り返して行なわなければなら
ず、全体として地下躯体の構築に係る工期が長期化する
傾向にあり、したがって施工費も増大するという問題点
があった。
<Problems to be solved by the invention> In the conventional method of constructing an underground skeleton, when root cutting work is performed up to the flooring surface, construction of mountain retaining wall → excavation → support work → conventional excavation → support work ... Since it has to be repeated, the construction period for the construction of the underground structure tends to be long as a whole, and thus the construction cost is increased.

また、地盤の掘削を行う際には、地盤中に地下水が含ま
れている場合が多く、掘削を行う前に、デープウエル工
法、ウエルポイント工法などの地下水低下工法により、
地下水位を掘削面まで低下させることが行われている
が、地下水位が低下すると周辺地盤の沈下を生じ、環境
問題等を引き起こす場合もあった。
In addition, when excavating the ground, groundwater is often contained in the ground, and before excavation, by the groundwater reduction method such as the Dapwell method and the Wellpoint method,
Although the groundwater level is being lowered to the excavated surface, when the groundwater level is lowered, subsidence of the surrounding ground may occur, which may cause environmental problems.

本発明は上記欠点を解決すべくなされたものであり、そ
の目的は、根切り工から地下躯体構築までの工期を短縮
すると共に、施工費を軽減することができ、しかも地盤
沈下等の周辺地盤に悪影響を及ぼすことのない地下躯体
の構築方法及び地下躯体構築用型枠を提供することにあ
る。
The present invention has been made to solve the above-mentioned drawbacks, and its purpose is to shorten the construction period from root cutting to construction of an underground skeleton, reduce the construction cost, and further reduce the surrounding ground such as ground subsidence. It is intended to provide a method for constructing an underground skeleton and a formwork for constructing an underground skeleton that do not adversely affect the above.

〈課題を解決するための手段〉 本発明は上記目的に鑑みてなされたものであり、その要
旨は地盤中に建築構造物の躯体を構築する方法であっ
て、泥水圧により溝壁の側圧を支持しながら、地盤を所
定の形状に掘削する第1の工程と、該第1の工程で掘削
した掘削坑内に、躯体を構築するための通水性を有する
型枠を吊り込む第2の工程と、該第2の工程により泥水
中に設置した型枠内にコンクリートを打設することによ
って、該型枠内に浸入した泥水を型枠の通水性により型
枠の外部へ排水させる第3の工程と、該第3の工程で打
設したコンクリートの硬化後、前記掘削坑内に満たされ
た泥水を排出する第4の工程とからなる地下躯体の構築
方法にある。
<Means for Solving the Problems> The present invention has been made in view of the above objects, and the gist thereof is a method of constructing a skeleton of a building structure in the ground. A first step of excavating the ground into a predetermined shape while supporting, and a second step of suspending a water-permeable formwork for constructing a skeleton in the excavation mine excavated in the first step. A third step of pouring concrete into the formwork installed in the muddy water by the second process, thereby draining the muddy water entering the formwork to the outside of the formwork by the water permeability of the formwork And a fourth step of discharging the muddy water filled in the excavation mine after the concrete poured in the third step is hardened.

また本発明の他の要旨は、地下躯体を構築するため泥水
中に設置する型枠であって、該型枠が、所望形状に組ま
れた鉄筋かごと、該鉄筋かごの外周部の型枠のうち、少
なくとも構築すべき躯体の内側表面に設けた型枠板とか
らなり、しかもこの型枠板が型枠内の泥水を外部へ排出
するために通水性を有するものである地下躯体構築用型
枠にある。
Another aspect of the present invention is a formwork installed in muddy water for constructing an underground structure, wherein the formwork is a rebar cage assembled in a desired shape, and a formwork of the outer peripheral portion of the rebar cage. Among them, for the construction of the underground skeleton, which consists of at least a form plate provided on the inner surface of the structure to be constructed, and which has water permeability for discharging the muddy water in the form to the outside. On the formwork.

なお、上記通水性を有する型枠板の材質としては、エキ
スパンドメタル、ラスメタルなどが好ましく、該型枠板
には泥水を排水させるための通水性を多数設けるか、ま
たは、型枠板自体をメッシュ構造とするなど、コンクリ
ート打設時に型枠内部の泥水を排出できる通水性を有す
るものが好ましい。
The material of the mold plate having water permeability is preferably expanded metal, lath metal or the like, and the mold plate is provided with a large number of water permeates for draining muddy water, or the mold plate itself is meshed. It is preferable that the structure has water permeability such that muddy water inside the mold can be discharged at the time of placing concrete.

〈実施例〉 本発明に係る地下躯体の構築方法及び地下躯体構築用型
枠を添付図面に基づいて説明する。
<Examples> A method for constructing an underground skeleton and a formwork for constructing an underground skeleton according to the present invention will be described with reference to the accompanying drawings.

第1a図、第1b図に示すように、コンクリート型枠10は、
上下方向に延びる柱筋11、横方向に延びる梁筋12及びフ
ープ筋13を溶接及び針金結束等により、所望の地下躯体
形状に製作した鉄筋かご14(第3図参照)を有し、鉄筋
かご14の坑壁側を除く、地下躯体の内側表面に設けた型
枠板15とで構成する。なお、型枠板15はスペーサー17を
介して鉄筋かごに取付けている。前記型枠板15には型枠
板15内の泥水を外部へ排水するための多数の通水孔16を
設けており、後述するように、泥水中に設置した型枠10
内にコンクリートを打設する際、該型枠10内での泥水と
コンクリートの置換が容易に行なわれるものである。特
に従来の非通水性の型枠を使用した場合には、隅角部な
どで打設したコンクリートによって泥水が閉じ込めら
れ、型枠内全体にコンクリートが回り込まないことがあ
ったが、通水孔を設けることにより、このような欠点が
解消できる。
As shown in FIGS. 1a and 1b, the concrete formwork 10 is
It has a reinforcing bar cage 14 (see FIG. 3) in which a column reinforcing bar 11 extending in the vertical direction, a beam reinforcing bar 12 extending in the horizontal direction, and a hoop reinforcing bar 13 are manufactured into a desired underground structure by welding and wire binding, etc. It is composed of a form plate 15 provided on the inner surface of the underground skeleton except for the mine wall side of 14. The form plate 15 is attached to the rebar cage via a spacer 17. The mold plate 15 is provided with a large number of water passage holes 16 for draining muddy water in the mold plate 15 to the outside, and as will be described later, the mold 10 installed in muddy water is used.
When pouring concrete into the mold, the mud water and concrete in the form 10 can be easily replaced. In particular, when using a conventional non-water-permeable form, muddy water was trapped by the concrete placed in the corners, etc. By providing it, such a defect can be eliminated.

次に、前記コンクリート型枠10を使用した地下躯体の構
築方法を工程順に説明する。
Next, a method of constructing an underground skeleton using the concrete formwork 10 will be described in the order of steps.

まず、地下躯体を構築するための根切り工を行う(第2
図)。この根切り工には、リバースサーキュレーション
式掘削機18等を使用し、掘削坑19内に例えば地下水位0.
2kg/cm2の泥水圧を加えて、溝壁の側圧を支持しながら
掘削を行う。所望の形状に掘削した後、型枠10をクレー
ン等を利用して、前記掘削坑19の泥水中に吊り込む(第
3図)。このとき、掘削坑内に設置した型枠10内には型
枠板15の通水孔16を通して泥水が入り込む。次に、泥水
中に設置した型枠10内の下部付近までトレミー管20を挿
入し、コンクリートの打設を行う(第4図)。泥水中で
のコンクリートの打設に際しては、トレミー管20の下端
部が常にコンクリート中に埋設する状態を保ちながら、
徐々に引き抜く必要がある。このように順次、型枠10内
にコンクリートを打設することにより、型枠10内の泥水
は、型枠板15の通水孔16を通して型枠10外に排水され、
型枠10内でのコンクリートと泥水との置換が良好に行な
われる。なお、型枠10の坑壁21側側面には、型枠板15を
設けておらず、坑壁21に直接コンクリートを打設してい
る。さらに、打設したコンクリートが硬化した後、型枠
板15を取り外し、掘削坑19内の泥水を全て排出して、地
下躯体22の構築工程は完了する。
First, root cutting work is performed to build the underground structure (second
Figure). For this rooting work, a reverse circulation type excavator 18 or the like is used, and the groundwater level 0.
Excavation is carried out by applying a mud pressure of 2 kg / cm 2 and supporting the lateral pressure of the trench wall. After excavating into a desired shape, the formwork 10 is suspended in the muddy water of the excavation pit 19 using a crane or the like (FIG. 3). At this time, muddy water enters the formwork 10 installed in the excavation pit through the water passage holes 16 of the formwork plate 15. Next, the tremie pipe 20 is inserted into the vicinity of the lower part of the mold 10 installed in the muddy water, and concrete is poured (FIG. 4). When pouring concrete in muddy water, keeping the lower end of the tremie pipe 20 always buried in concrete,
It is necessary to pull out gradually. In this way, by sequentially placing concrete in the mold 10, muddy water in the mold 10 is drained to the outside of the mold 10 through the water holes 16 of the mold plate 15,
The replacement of concrete with muddy water in the mold 10 is favorably performed. The form plate 15 is not provided on the side surface of the formwork 10 on the mine wall 21 side, and concrete is directly placed on the mine wall 21. Further, after the cast concrete is hardened, the formwork plate 15 is removed, all the muddy water in the excavation pit 19 is discharged, and the construction process of the underground skeleton 22 is completed.

〈効果〉 本発明によれば、泥水圧により溝壁の側圧を支持しなが
ら掘削を行った後、泥水中に通水性の型枠を吊り込み、
該型枠中にコンクリートを打設し、地下躯体を構築する
方法を採用するので、山留め、支保工の必要がないた
め、根切りから地下躯体構築までの工期を短縮すること
ができると共に、施工費を軽減することができる。
<Effect> According to the present invention, after excavating while supporting the lateral pressure of the groove wall by the mud pressure, the water-permeable mold is suspended in the mud,
Since the method of placing concrete in the formwork and constructing the underground skeleton is adopted, there is no need for mountain fastening and support work, so the construction period from root cutting to underground skeleton construction can be shortened, and construction The cost can be reduced.

また、通水性の型枠を使用することにより、コンクリー
ト打設時に、泥水と伴にスライムが型枠外へ排出される
ため、打設コンクリート中へのスライムの混入を防ぎ、
不純物混入によるコンクリート強度の低下を防止するこ
とができる。
In addition, by using a water-permeable form, slime is discharged out of the form along with muddy water when pouring concrete, preventing the inclusion of slime in the pouring concrete,
It is possible to prevent a decrease in concrete strength due to inclusion of impurities.

さらに、従来の非通水性の型枠では泥水が閉じ込められ
てコンクリートが回り込みにくい隅角部でも、通水性の
型枠を通して排水が行なわれるため、型枠内の隅々まで
コンクリートを打設できる等の優れた効果を奏する。
Furthermore, even in the corners where concrete is difficult to turn around in a conventional non-water-permeable formwork, concrete can be placed in every corner of the formwork because drainage is performed through the water-permeable formwork. Exerts the excellent effect of.

【図面の簡単な説明】[Brief description of drawings]

第1a図は型枠10の平面図、第1b図は第1a図における破線
Ib内の拡大図、第2図乃至第5図は地下躯体の構築工程
を示す概略断面図である。 10……型枠、14……鉄筋かご、15……型枠板、16……通
水孔、21……坑壁、22……躯体。
FIG. 1a is a plan view of the mold 10, and FIG. 1b is a broken line in FIG. 1a.
The enlarged views in Ib, FIGS. 2 to 5 are schematic cross-sectional views showing the process of constructing an underground skeleton. 10 …… Formwork, 14 …… Reinforcing cage, 15 …… Formwork plate, 16 …… Water passage hole, 21 …… Mine wall, 22 …… Skeletal structure.

Claims (2)

【特許請求の範囲】[Claims] 【請求項1】地盤中に建築構造物の躯体を構築する方法
であって、 泥水圧により溝壁の側圧を支持しながら、地盤を所定の
形状に掘削する第1の工程と、 該第1の工程で掘削した掘削坑内に、躯体を構築するた
めの通水性を有する型枠を吊り込む第2の工程と、 該第2の工程により泥水中に設置した型枠内にコンクリ
ートを打設することによって、該型枠内に浸入した泥水
を型枠の通水性により型枠の外部へ排水させる第3の工
程と、 該第3の工程で打設したコンクリートの硬化後、前記掘
削坑内に満たされた泥水を排出する第4の工程とからな
ることを特徴とする地下躯体の構築方法。
1. A method of constructing a skeleton of a building structure in the ground, comprising a first step of excavating the ground into a predetermined shape while supporting a lateral pressure of a groove wall by mud pressure, and the first step. The second step of suspending the water-permeable formwork for constructing the skeleton in the excavation mine that was excavated in the step of (3), and the concrete is placed in the formwork installed in the muddy water by the second step. By this, the third step of draining the muddy water that has entered the mold to the outside of the mold by the water permeability of the mold, and the hardening of the concrete poured in the third step, and then filling the excavation mine The method for constructing an underground skeleton, which comprises a fourth step of discharging the collected muddy water.
【請求項2】地下躯体を構築するため泥水中に設置する
型枠であって、 該型枠が、所望形状に組まれた鉄筋かごと、該鉄筋かご
の外周部の型枠のうち、少なくとも構築すべき躯体の内
側表面に設けた型枠板とからなり、しかもこの型枠板が
型枠内の泥水を外部へ排出するために通水性を有するも
のであることを特徴とする地下躯体構築用型枠。
2. A formwork to be installed in mud water for constructing an underground structure, wherein the formwork is at least a rebar cage assembled in a desired shape and a formwork on the outer peripheral portion of the rebar cage. An underground skeleton construction characterized in that it consists of a form plate provided on the inner surface of the structure to be constructed, and that this form plate has water permeability for discharging muddy water in the form to the outside. Formwork.
JP1336575A 1989-12-27 1989-12-27 Method of constructing underground skeleton and formwork for underground skeleton construction Expired - Fee Related JPH0699940B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP1336575A JPH0699940B2 (en) 1989-12-27 1989-12-27 Method of constructing underground skeleton and formwork for underground skeleton construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP1336575A JPH0699940B2 (en) 1989-12-27 1989-12-27 Method of constructing underground skeleton and formwork for underground skeleton construction

Publications (2)

Publication Number Publication Date
JPH03199531A JPH03199531A (en) 1991-08-30
JPH0699940B2 true JPH0699940B2 (en) 1994-12-12

Family

ID=18300564

Family Applications (1)

Application Number Title Priority Date Filing Date
JP1336575A Expired - Fee Related JPH0699940B2 (en) 1989-12-27 1989-12-27 Method of constructing underground skeleton and formwork for underground skeleton construction

Country Status (1)

Country Link
JP (1) JPH0699940B2 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102888847B (en) * 2012-10-19 2014-12-24 中国二十二冶集团有限公司 Construction method free from lowering water level for local deep foundation pit of elevator shaft

Also Published As

Publication number Publication date
JPH03199531A (en) 1991-08-30

Similar Documents

Publication Publication Date Title
JP2837128B2 (en) Construction method of cast-in-place concrete pile
CN216108526U (en) Underground continuous wall structure for foundation pit support
CN113957887B (en) Pile-wall integrated construction method of core barrel
AU2020100004B4 (en) A Method Of Constructing A Column, A Subterranean Structure, And A Structure Made From The Method
JP2604210B2 (en) Construction method of underground large-scale spatial structure
JPH0699940B2 (en) Method of constructing underground skeleton and formwork for underground skeleton construction
KR101077242B1 (en) Construction method of basement structure using retaining wall and steel column
JP2588075B2 (en) Underground building construction method
JPS5936058B2 (en) How to construct a structure using underground continuous walls
JP3614587B2 (en) How to install a shaft in the groundwater under pressure
CN113106979B (en) Excavation method of upper cover foundation pit and construction method for upper cover storey addition
JP2693028B2 (en) Construction method of human hole in middle of pipeline
JPH073781A (en) Method for constructing foundation footing on cast-in-place concrete pile head
JP6851180B2 (en) How to rebuild the building
JPH08105072A (en) Erection method of column in inverted construction method
CN113832983A (en) Construction method for supporting foundation pit by adopting variable-cross-section underground continuous wall
JP3794097B2 (en) Construction method for underground structures
JPH06194485A (en) Construction of nuclear power plant building
JPH10140557A (en) Construction method of cast-in-place diaphragm wall with hollow
JPH0317314A (en) Execution of underground continuous wall
JPH0657958B2 (en) Reverse floor construction method
JPS59177422A (en) Construction work of underground continuous wall using disposable formwork
JPH0748848A (en) Construction method for underground skeleton by inverted construction method
JP2933546B2 (en) Basement construction method and lower frame material used in the construction method
RU2123558C1 (en) Method for erection of wall in ground

Legal Events

Date Code Title Description
LAPS Cancellation because of no payment of annual fees