JPH0674701U - Pillar embedding device - Google Patents

Pillar embedding device

Info

Publication number
JPH0674701U
JPH0674701U JP1581093U JP1581093U JPH0674701U JP H0674701 U JPH0674701 U JP H0674701U JP 1581093 U JP1581093 U JP 1581093U JP 1581093 U JP1581093 U JP 1581093U JP H0674701 U JPH0674701 U JP H0674701U
Authority
JP
Japan
Prior art keywords
column
column base
hole
steel
base
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP1581093U
Other languages
Japanese (ja)
Inventor
英隆 柴橋
俊明 田辺
健義 三木
則夫 椿
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Taisei Corp
Original Assignee
Taisei Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Taisei Corp filed Critical Taisei Corp
Priority to JP1581093U priority Critical patent/JPH0674701U/en
Publication of JPH0674701U publication Critical patent/JPH0674701U/en
Pending legal-status Critical Current

Links

Landscapes

  • Foundations (AREA)

Abstract

(57)【要約】 【目的】 鉄骨柱建方の施工性と施工精度を改善した柱
脚埋込装置を提供する。 【構成】 基礎1上面の地中梁2に予め形成した柱脚埋
込用孔3の底面に、レベル調整用のナット4,ボルト5
と誘導アンカー6とを設ける。鉄骨柱脚11のベースプ
レート12に誘導アンカー6を遊嵌させる穴部13を設
け、孔壁の開口端近傍と対向する側面には、各対角位置
に近傍して互いに直交するナット14,15を固着し、
該ナット14,15にそれぞれ建入れ調整用ボルト1
6,17を螺合する。柱脚11のベースプレート12の
穴部13に誘導アンカー6を挿通してボルト5上に着座
させると水平及び鉛直両方向の位置が決まる。柱脚11
のボルト16,17のうち1個の頭部を孔壁に押圧して
鉄骨柱10の向きを調整し、孔壁と対向する2個のボル
トの頭部を孔壁に押圧して鉄骨柱10の傾きを調整す
る。柱脚3と孔壁との空隙にはコンクリートを充填す
る。
(57) [Summary] [Purpose] To provide a column base embedding device with improved workability and construction accuracy of a steel frame column. [Structure] A level adjusting nut 4 and a bolt 5 are provided on a bottom surface of a column base embedding hole 3 formed in advance in the underground beam 2 on the upper surface of the foundation 1.
And a guide anchor 6. The base plate 12 of the steel column base 11 is provided with a hole portion 13 into which the guide anchor 6 is loosely fitted, and nuts 14 and 15 that are orthogonal to each other near each diagonal position are provided on the side surface facing the vicinity of the open end of the hole wall. Stuck,
The nuts 14 and 15 each have a construction adjustment bolt 1
Screw 6 and 17 together. When the guide anchor 6 is inserted into the hole 13 of the base plate 12 of the column base 11 and seated on the bolt 5, both horizontal and vertical positions are determined. Pedestal 11
The head of one of the bolts 16 and 17 is pressed against the hole wall to adjust the orientation of the steel column 10, and the heads of the two bolts facing the hole wall are pressed against the hole wall to contact the steel column 10. Adjust the tilt of. The space between the column base 3 and the hole wall is filled with concrete.

Description

【考案の詳細な説明】[Detailed description of the device]

【0001】[0001]

【産業上の利用分野】[Industrial applications]

この考案は、鉄骨柱の建方の施工性と施工精度を改善した柱脚埋込装置に関す る。 The present invention relates to a column base embedding device with improved workability and construction accuracy in constructing steel columns.

【0002】[0002]

【従来の技術】[Prior art]

柱脚固定で設計された鉄骨造において、基礎上面の地中梁躯体の完成後に鉄骨 柱の建方を行う工法として、地中梁に予めコア抜きして設けた孔に柱脚を挿入し てモルタル充填により固定する装置が近年開発されるに至り、たとえば実公平1 −15763号公報に記載された装置が提案されている。同公報の柱脚固定装置 は、側面にシヤーコネクターを取付けた柱脚を、予め基礎に形成した柱挿入孔に 挿通し、柱脚側面と基礎天端とを位置決め用金物により連結し、柱脚挿通孔との 間隙にモルタルを充填して柱脚を固定するというものである。 In the steel frame structure designed by fixing the column base, as a method of constructing the steel frame column after completion of the underground beam frame on the upper surface of the foundation, the column base is inserted into the hole made by removing the core in advance in the underground beam. A device for fixing by mortar filling has been developed in recent years, and for example, a device described in Japanese Utility Model Publication No. 1-15763 has been proposed. In the column base fixing device of the same publication, a column base with a shear connector attached to the side is inserted into a column insertion hole formed in the foundation in advance, and the side face of the column base and the top end of the foundation are connected by a metal fitting for positioning. The column base is fixed by filling the gap with the insertion hole with mortar.

【0003】[0003]

【考案が解決しようとする課題】[Problems to be solved by the device]

上記の柱脚固定装置を用いて鉄骨柱の建方を行うと、鉄骨フレームをある程度 形成してから柱脚を固定できるので、工期が短縮され、かつ柱挿通孔と側面にシ ヤーコネクターを取付けた柱脚との間隙にモルタルを充填してあるため、ベース プレートを取りつけるアンカーボルトが不要になる、という利点がある。 When the steel column is erected using the above-mentioned column base fixing device, the column base can be fixed after the steel frame has been formed to some extent, which shortens the construction period and also installs the shear connector on the column insertion hole and the side surface. Since the mortar is filled in the space between the base and the base, there is an advantage that the anchor bolts for mounting the base plate are not required.

【0004】 しかしながら、上記装置においては、柱脚の側面に取り付けてある位置決め用 金物と基礎天端に突設したアンカーボルトとのナット締着を、吊り下されたまま 動揺し易い柱脚に対して行う必要があるので、施工に際し困難を伴うという問題 があるだけでなく、鉄骨柱の建入れ調整に必要な機構が設けられていないから、 精密な施工精度を確保することも望み得ないという問題がある。However, in the above-mentioned device, the nut tightening between the positioning hardware attached to the side surface of the column base and the anchor bolt protruding from the top end of the foundation is applied to the column base that is easily shaken while being suspended. Not only is there a problem that it will be difficult to carry out the construction, it is also not possible to secure precise construction accuracy because there is no mechanism necessary for the adjustment of the steel frame column construction. There's a problem.

【0005】 この考案は、このような問題を解決して、施工性が良く、かつ高い施工精度を もつ柱脚埋込装置を提供することを目的とする。An object of the present invention is to solve such a problem and to provide a column base embedding device having good workability and high construction accuracy.

【0006】[0006]

【課題を解決するための手段】[Means for Solving the Problems]

この考案は上記目的を達成するため、基礎上面に構築された地中梁に予め形成 した柱脚埋込用孔の底面に、レベル調整材と誘導アンカーとを設け、鉄骨柱脚の ベースプレートに前記誘導アンカーが遊嵌される穴部を設けるとともに、柱脚埋 込用孔の開口端近傍の孔壁の各対角位置において互いに直交する方向に進退して 一端が孔壁に当接可能な建入れ調整用ボルトが螺合されたナットを、柱脚の対応 する側面に固着し、柱脚埋込用孔と柱脚との間の空隙に充填するコンクリートに より柱脚が固定される構成としてある。 In order to achieve the above-mentioned object, the present invention provides a level adjusting material and a guide anchor on the bottom of a column base embedding hole previously formed in an underground beam constructed on the upper surface of the foundation, and the base plate of the steel column base has the above-mentioned structure. A hole is provided in which the guide anchor is loosely fitted, and at a diagonal position of the hole wall near the opening end of the column base embedding hole, it is moved forward and backward in directions orthogonal to each other so that one end can abut the hole wall. The nut with the insertion adjustment bolt screwed is fixed to the corresponding side surface of the column base, and the column base is fixed by concrete filling the space between the column base embedding hole and the column base. is there.

【0007】[0007]

【作用】[Action]

この考案の柱脚埋込装置を用いて鉄骨柱の建方をするときは、地中梁に形成さ れている柱脚埋込用孔に鉄骨柱を吊り下して挿入し、柱脚のベースプレートの穴 部に孔底の誘導アンカーを挿通しながら、ベースプレートをレベル調整材上に着 座させる。これにより鉄骨柱の水平方向の芯位置と鉛直方向のレベルとが正確に 決められる。 When constructing a steel frame column using the column base embedding device of the present invention, the steel frame column is hung and inserted into the column base embedding hole formed in the underground beam, and the While inserting the guide anchor at the bottom of the hole into the hole of the base plate, seat the base plate on the level adjustment material. As a result, the horizontal core position and the vertical level of the steel column can be accurately determined.

【0008】 鉄骨柱の建入れの調整は、柱脚の各側面に取付けてある建入れ調整用ボルトを 使用して行う。 鉄骨柱の柱列方向の向きの調整は、たとえば、X方向の柱列と平行な柱脚の側 面の片方において孔壁と直交する何れか一方のボルトの一端(頭部)のみを、対 向する孔壁に当接させて軸回りに後退方向に回転させる。これにより鉄骨柱はベ ースプレートに挿通された誘導アンカーを支点としてボルトの後退方向と反対方 向に回転してX方向の柱列の向きがいずれか一方側に調整される。The adjustment of the steel frame column is carried out by using the building adjustment bolts attached to each side surface of the column base. To adjust the orientation of the steel column in the column row direction, for example, only one end (head) of one of the bolts orthogonal to the hole wall on one side of the column base parallel to the column row in the X direction should be paired. It is brought into contact with the facing hole wall and rotated in the backward direction around the axis. As a result, the steel column rotates in a direction opposite to the backward direction of the bolt with the guide anchor inserted in the base plate as a fulcrum, and the direction of the column row in the X direction is adjusted to one side.

【0009】 鉄骨柱の傾きの調整は、たとえばY方向と平行な柱脚の側面の片方において孔 壁と直交する双方のボルトの一端(頭部)を対向する孔壁に当接させて軸回りに 後退方向に回転させる。これにより鉄骨柱はベースプレートに挿通された誘導ア ンカーに支持されながら、ボルトの後退方向と反対方向のX方向に傾く。 建入れ調整が完了した後、建入れ調整用ボルトの全部の一端(頭部)が孔壁に 当接するように回転し、この状態で孔壁との間の空隙にコンクリートを充填する 。The tilt of the steel column is adjusted by, for example, bringing one end (head) of both bolts, which are orthogonal to the hole wall, on one side surface of the column base parallel to the Y direction into contact with the facing hole wall. Rotate in the backward direction. As a result, the steel column is tilted in the X direction, which is the opposite direction to the backward direction of the bolt, while being supported by the guide anchor inserted through the base plate. After the installation adjustment is completed, rotate all of the installation adjustment bolts so that one end (head) of the installation adjustment bolt comes into contact with the hole wall, and in this state, the space between the hole and the wall is filled with concrete.

【0010】[0010]

【実施例】【Example】

以下、この考案の実施例を図面に基づいて説明する。 図1に示すように、鉄骨柱10が建方される基礎1の上面には、建方前に地中梁 2の躯体工事が行なわれており、地中梁2のコンクリート打設時に予め、鉄骨柱 の柱脚11の固定位置に型枠をセットして、正方形断面の柱脚埋込用孔3が形成 されている。 An embodiment of the present invention will be described below with reference to the drawings. As shown in FIG. 1, on the upper surface of the foundation 1 on which the steel columns 10 are to be erected, the skeleton construction of the underground girder 2 is performed before the erection, and when the underground girder 2 is concrete-cast in advance, The formwork is set at a fixed position of the column base 11 of the steel frame column, and the column base embedding hole 3 having a square cross section is formed.

【0011】 地中梁2の柱脚埋込用孔3の底面には、図2に示すように正方形の対角点に相 当する4個所に植込まれたナット4にボルト5が螺着してある。このナット4及 びボルト5は、鉄骨柱10のレベル調整材としての機能を有している。また、孔 底には鉄骨柱10の柱列方向の芯位置(上記正方形の中心)に、先端が針状にな った誘導アンカー6を鉛直方向に突出させて植込んである。この誘導アンカー6 は鉄骨柱10の水平方向の位置決め部材と建入れ調整用の補助部材としての機能 を有している。On the bottom surface of the column base embedding hole 3 of the underground beam 2, bolts 5 are screwed to nuts 4 which are planted at four locations corresponding to diagonal points of a square, as shown in FIG. I am doing it. The nut 4 and the bolt 5 have a function as a level adjusting material for the steel frame column 10. Further, a guide anchor 6 having a needle-like tip is vertically projected and implanted at the core position of the steel column 10 in the column direction (center of the square) in the bottom of the hole. The guide anchor 6 has a function as a horizontal positioning member for the steel column 10 and an auxiliary member for adjusting the construction.

【0012】 図1に示す鉄骨柱10は四角形鋼からなるものであり、その柱脚11のベース プレート12には、前記柱脚埋込用孔3の誘導アンカー6が遊嵌される直径を持 つ穴部13が中心位置に設けてある。また、柱脚11の各側面には、柱脚埋込用 孔3の開口端近傍の孔壁に対応する部位の対角位置に接して、それぞれねじ穴の 中心を直交させたナット14,15を上下2段に溶接して固着し、これらのナッ ト14,15には、頭部を孔壁側に向けたボルト16,17を進退可能に螺合し てある。上記のボルト16,17はその軸回りに後退方向に回転させると、その 頭部が孔壁と当接する長さの軸部を有しており、これらのボルト16,17及び ナット14,15は鉄骨柱の建入れ調整部材としての機能を有している(図3, 図4参照)。The steel column 10 shown in FIG. 1 is made of square steel, and the base plate 12 of the column base 11 has a diameter such that the guide anchor 6 of the column base embedding hole 3 is loosely fitted. The hole 13 is provided at the center position. In addition, on each side surface of the column base 11, nuts 14 and 15 in which the centers of the screw holes are orthogonal to each other are in contact with the diagonal positions of the portion corresponding to the hole wall near the opening end of the column base embedding hole 3. Are welded and fixed in two upper and lower stages, and nuts 14 and 15 are screwed with bolts 16 and 17 whose head faces the hole wall side so as to be able to move forward and backward. When the bolts 16 and 17 are rotated in the backward direction about their axes, their heads have a shaft portion whose length contacts the hole wall. These bolts 16 and 17 and nuts 14 and 15 are It has a function as a building adjustment member for steel columns (see Figs. 3 and 4).

【0013】 さらに、柱脚11の各側面にはシヤーコネクター18が取り付けてある。この シヤーコネクター18は柱脚固定用のアンカーボルトとしての機能を有している 。 上記構成の柱脚11をもつ鉄骨柱10の建方を行う際の手順は次のとおりであ る。Further, a shear connector 18 is attached to each side surface of the column base 11. The shear connector 18 has a function as an anchor bolt for fixing a column base. The procedure for erection of the steel column 10 having the column base 11 having the above-described configuration is as follows.

【0014】 地中梁2に形成した柱脚埋込用孔3の底面のボルト5はナット4に対する螺合 長さを加減して、各ボルト5の頭部頂面を連ねるレベルが所定の高さ位置で水平 面を形成するように調整する。 地中梁2の上方に吊り上げた鉄骨柱10を下降させながら、柱脚11を柱脚埋 込用孔3に挿入し、孔底の誘導アンカー6に柱脚11のベースプレート12の穴 部13を挿通させ、この状態で柱脚11のベースプレート12を孔底のボルト5 の頭部上に着座させる。The bolt 5 on the bottom surface of the column base embedding hole 3 formed in the underground beam 2 has a screwing length adjusted with respect to the nut 4, so that the level at which the head top surfaces of the bolts 5 are connected to each other has a predetermined level. Adjust to form a horizontal plane in the vertical position. While lowering the steel column 10 suspended above the underground beam 2, the column base 11 is inserted into the column base embedding hole 3, and the hole 13 of the base plate 12 of the column base 11 is inserted into the guide anchor 6 at the bottom of the hole. The base plate 12 of the column base 11 is seated on the head of the bolt 5 at the bottom of the hole in this state.

【0015】 次いで、鉄骨柱10の柱列方向の向きと傾きとの建入れ調整を行う。 鉄骨柱10の柱列方向、たとえば図3のX方向の向きを調整するときは、柱脚 11の建入れ調整用ボルト16,17のうち、X方向と直交するY方向に対向し て取り付けてある何れか一方の側で図の左右何れか一方のボルト、たとえばボル ト17aをその軸回りに後退方向に回転させて、図4に示すように頭部をこれと 対向する孔壁に当接させる。このボルト17a以外の他のボルトの頭部はそれぞ れの対向する孔壁から離間させ、この状態でボルト17aをさらに後退方向に回 転させる。これにより鉄骨柱10にはベースプレート12に挿通されている誘導 アンカー6を支点としてその周りにボルト17aの孔壁に対する押圧力の反力が 偶力として作用するため、図3の矢印C方向に回転する。ボルト17aの代りに これと対角位置にあるボルト17cを用いて上記の操作を行ってもよい。鉄骨柱 10をC方向と反対方向に回転させるときは、ボルト17bとボルト17dとの 何れか一方を使用する。このようにして、鉄骨柱10の側面のX方向における平 行度が調整される。Next, the building adjustment of the direction and the inclination of the steel column 10 in the column row direction is performed. When adjusting the column direction of the steel column 10, for example, the direction of the X direction in FIG. 3, of the installation adjustment bolts 16 and 17 of the column base 11, mount them so that they face each other in the Y direction orthogonal to the X direction. Rotate either one of the left and right bolts in the figure, such as bolt 17a, in the backward direction around its axis on one side to bring the head into contact with the hole wall facing it, as shown in FIG. Let The heads of the bolts other than the bolt 17a are separated from the respective facing hole walls, and in this state, the bolt 17a is further rotated in the backward direction. As a result, a reaction force of the pressing force of the bolt 17a against the hole wall acts as a couple around the guide anchor 6 inserted in the base plate 12 as a fulcrum on the steel frame column 10, so that it rotates in the direction of arrow C in FIG. To do. Instead of the bolt 17a, a bolt 17c located diagonally thereto may be used to perform the above operation. When rotating the steel column 10 in the direction opposite to the C direction, one of the bolts 17b and 17d is used. In this way, the flatness of the side surface of the steel column 10 in the X direction is adjusted.

【0016】 鉄骨柱10のY方向の向きを調整するときは、ボルト16aと16cとの一方 、またはボルト16bとボルト16dとの一方を使用して、上記と同様の要領で 鉄骨柱10を誘導アンカー6の周りに回転させる。 鉄骨柱10の傾き、たとえば図3のX方向の傾きを調整するときは、柱脚11 の建入れ調整用ボルト16,17のうち、X方向に対向して取り付けてある何れ か一方の側における双方のボルト、たとえばボルト16a及びボルト16dをそ の軸回りに後退方向に回転させて、頭部をこれと対向する孔壁に当接させる。こ のボルト16a及びボルト16d以外の他のボルトの頭部はそれぞれの対向する 孔壁から離間させ、この状態でボルト16a及びボルト16dをさらに後退方向 に均等量回転させる。これにより、鉄骨柱10は、ベースプレート12に挿通さ せている誘導アンカー6に支持されて、ボルト16a及び16dの孔壁に対する 押圧力の水平反力により図3の矢印D方向に傾く。鉄骨柱10をD方向と反対方 向に傾けるときは、ボルト16b及びボルト16cを使用する。このようにして 、鉄骨柱10のX方向の傾きが調整される。When adjusting the direction of the steel frame column 10 in the Y direction, one of the bolts 16a and 16c or one of the bolts 16b and 16d is used to guide the steel frame column 10 in the same manner as described above. Rotate around anchor 6. When adjusting the inclination of the steel column 10, for example, the inclination in the X direction in FIG. 3, one of the installation adjustment bolts 16 and 17 of the column base 11 which is attached facing the X direction. Both bolts, such as the bolt 16a and the bolt 16d, are rotated about their axes in the backward direction to bring the head into contact with the hole wall facing the head. The heads of the bolts other than the bolts 16a and 16d are separated from the respective facing hole walls, and in this state, the bolts 16a and 16d are further rotated by an equal amount in the backward direction. As a result, the steel frame column 10 is supported by the guide anchor 6 inserted through the base plate 12, and tilts in the direction of arrow D in FIG. 3 due to the horizontal reaction force of the pressing force of the bolts 16a and 16d against the hole walls. When inclining the steel column 10 in the direction opposite to the D direction, the bolts 16b and 16c are used. In this way, the inclination of the steel column 10 in the X direction is adjusted.

【0017】 鉄骨柱10のY方向の傾きを調整するときは、ボルト17a及びボルト17b 、またはボルト17c及びボルト17dを使用して、上記と同様の操作を行う。 こうして建入れ調整が完了した鉄骨柱10は、建入れ調整用ボルト16,17 の全部の頭部を対向する孔壁に当接させて鉄骨柱10を仮固定し、この状態で柱 脚11と孔壁との間の空隙20にコンクリートを充填することにより、地中梁2 に対して柱脚11が本固定されることになる。When adjusting the inclination of the steel column 10 in the Y direction, the bolts 17a and 17b, or the bolts 17c and 17d are used to perform the same operation as described above. In the steel column 10 for which the installation adjustment has been completed in this manner, all the heads of the installation adjustment bolts 16 and 17 are brought into contact with the facing hole walls to temporarily fix the steel column 10, and in this state, By filling the space 20 between the hole wall and the concrete, the column base 11 is permanently fixed to the underground beam 2.

【0018】 図5は、H形鋼からなる鉄骨柱の柱脚11についての実施例を示し、対向する フランジ部19の各端面と各端縁とに、それぞれねじ穴の中心が直交するナット 14,15を上下2段に溶接により固着し、これらのナット14,15に建入れ 調整用のボルト16,17を螺合したものである。 上記実施例において、地中梁2の柱脚埋込用孔3の底面に植込まれた誘導アン カー6は、比較的長さの短小なものを図示してあるが、この誘導アンカー6の長 さは任意に設定すればよく、必要に応じ地中梁2の天端よりも上方に突出する長 さにすることもできる。FIG. 5 shows an embodiment of a column base 11 of a steel frame column made of H-shaped steel, in which nuts whose center of a screw hole is orthogonal to each end face and each edge of the opposing flange portion 19 are provided. , 15 are fixed to the upper and lower two stages by welding, and bolts 16 and 17 for installation adjustment are screwed into these nuts 14 and 15. In the above embodiment, the guide anchor 6 implanted in the bottom surface of the column base embedding hole 3 of the underground beam 2 is shown as having a relatively short length. The length may be set arbitrarily, and may be a length protruding above the top end of the underground beam 2 as necessary.

【0019】 また、柱脚埋込用孔3の孔底に設けたレベル調整材としてのボルト5,ナット 4は、適宜の厚さに盛り付けたセメントモルタルに代えてもよい。 また、鉄骨柱10の柱脚11の側面に取り付けてあるシヤーコネクタ18は必 要に応じて省略してもよい。Further, the bolts 5 and the nuts 4 as the level adjusting material provided on the hole bottoms of the column base embedding holes 3 may be replaced with cement mortar having an appropriate thickness. Further, the shear connector 18 attached to the side surface of the column base 11 of the steel frame column 10 may be omitted if necessary.

【0020】[0020]

【考案の効果】[Effect of device]

以上説明したように、この考案によれば、柱脚埋込用孔にレベル調整材と誘導 アンカーとを設け、柱脚のベースプレートに誘導アンカー遊嵌用穴部を設け、柱 脚埋込用孔の開口端近傍の孔壁と対向する柱脚の側面に固着したナットに建入れ 調整用ボルトを螺合してあるから、鉄骨柱の建方に際し、柱脚のベースプレート を柱脚埋込用孔の孔底に着座させると、これと同時に鉄骨柱の水平方向の芯位置 と鉛直方向のレベルとが正確に決められるだけでなく、柱列方向の向き及び傾き についても建入れ調整用ボルトによる簡単な操作で調整することができるので、 施工性が良好で、施工精度の高い鉄骨柱の建方が可能な柱脚埋込装置が得られる 。 As described above, according to the present invention, the level adjusting material and the guide anchor are provided in the column base embedding hole, and the guide anchor loose fitting hole is provided in the base plate of the column base. Since the installation adjustment bolts are screwed into the nuts fixed to the side of the column base facing the hole wall near the opening end of the column base, the base plate of the column base is installed in the column base embedding hole when building the steel column. When it is seated on the bottom of the hole, the horizontal center position and the vertical level of the steel frame columns are not only accurately determined at the same time, but also the direction and inclination in the column direction can be easily determined by the installation adjustment bolts. Since it can be adjusted by various operations, it is possible to obtain a column base embedding device that has good workability and is capable of erection of steel columns with high construction accuracy.

【図面の簡単な説明】[Brief description of drawings]

【図1】この考案の実施例を柱脚埋込前の状態において
示す縦断面図である。
FIG. 1 is a vertical sectional view showing an embodiment of the present invention in a state before being embedded in a column base.

【図2】図1の柱脚埋込用孔の孔底を示す平面図であ
る。
FIG. 2 is a plan view showing a hole bottom of a column base embedding hole in FIG.

【図3】図1のI−I線における拡大断面図である。FIG. 3 is an enlarged cross-sectional view taken along the line I-I of FIG.

【図4】建入れ調整用ボルトの使用状態を示す部分縦断
面図である。
FIG. 4 is a partial vertical cross-sectional view showing a usage state of a construction adjustment bolt.

【図5】この考案の柱脚の他の例を示す横断面図であ
る。
FIG. 5 is a cross-sectional view showing another example of the column base of the present invention.

【符号の説明】[Explanation of symbols]

1 基礎 2 地中梁 3 柱脚埋込用孔 4 ナット 5 レベル調整用ボルト 6 誘導アンカー 10 鉄骨柱 11 柱脚 12 ベースプレート 13 穴部 14,15 ナット 16,17 建入れ調整用ボルト 20 空隙 1 Foundation 2 Underground Beam 3 Hole for Embedding Column Base 4 Nut 5 Bolt for Level Adjustment 6 Induction Anchor 10 Steel Column 11 Column Base 12 Base Plate 13 Holes 14, 15 Nut 16, 17 Construction Adjustment Bolt 20 Void

───────────────────────────────────────────────────── フロントページの続き (72)考案者 椿 則夫 東京都新宿区西新宿一丁目25番1号 大成 建設株式会社内 ─────────────────────────────────────────────────── ─── Continuation of the front page (72) Inventor Norio Tsubaki 1-25-1 Nishi-Shinjuku, Shinjuku-ku, Tokyo Taisei Corporation

Claims (1)

【実用新案登録請求の範囲】[Scope of utility model registration request] 【請求項1】 基礎上面に構築された地中梁に予め形成
した柱脚埋込用孔の底面に、レベル調整材と誘導アンカ
ーとを設け、鉄骨柱脚のベースプレートに前記誘導アン
カーが遊嵌される穴部を設けるとともに、柱脚埋込用孔
の開口端近傍の孔壁と対応する柱脚の側面に、前記孔壁
の各対角位置において互いに直交する方向に進退して一
端が孔壁に当接可能な建入れ調整用ボルトが螺合された
ナットを固着し、柱脚埋込用孔と柱脚との間の空隙に充
填するコンクリートにより柱脚が固定される構成とした
ことを特徴とする柱脚埋込装置。
1. A level adjusting material and a guide anchor are provided on the bottom surface of a column base embedding hole previously formed in an underground beam constructed on the upper surface of the foundation, and the guide anchor is loosely fitted to the base plate of the steel column base. And a side wall of the column base corresponding to the hole wall in the vicinity of the opening end of the column base embedding hole, the one end of the hole wall is moved forward and backward in directions orthogonal to each other at each diagonal position. A nut that is screwed into a building adjustment bolt that can contact the wall is fixed, and the column base is fixed by concrete that fills the space between the column base embedding hole and the column base. Column base embedding device characterized by.
JP1581093U 1993-03-31 1993-03-31 Pillar embedding device Pending JPH0674701U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP1581093U JPH0674701U (en) 1993-03-31 1993-03-31 Pillar embedding device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP1581093U JPH0674701U (en) 1993-03-31 1993-03-31 Pillar embedding device

Publications (1)

Publication Number Publication Date
JPH0674701U true JPH0674701U (en) 1994-10-21

Family

ID=11899207

Family Applications (1)

Application Number Title Priority Date Filing Date
JP1581093U Pending JPH0674701U (en) 1993-03-31 1993-03-31 Pillar embedding device

Country Status (1)

Country Link
JP (1) JPH0674701U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007270431A (en) * 2006-03-30 2007-10-18 Toda Constr Co Ltd Cylindrical column erection method and erection jig

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007270431A (en) * 2006-03-30 2007-10-18 Toda Constr Co Ltd Cylindrical column erection method and erection jig

Similar Documents

Publication Publication Date Title
JPH0674701U (en) Pillar embedding device
JPH10204985A (en) Constructing method for column and plumbing jig
JP7018253B2 (en) Column base hardware and how to build a column base structure using it
JPH09189132A (en) Fixing method of column base for steel frame column
JP2001348952A (en) Position adjustment device for steel-frame column
JP3255253B2 (en) Construction method of pillar and its bottom support device
JPH09177366A (en) Structure and method for joining steel encased reinforced concrete support and seismic isolator
JP3084654B2 (en) Construction foundation, foundation structure using the same, and construction method thereof
JP2567631Y2 (en) Level adjuster for steel foundation beams
JP3236950B2 (en) Embedded column base and method of construction
JP3057481B2 (en) Steel frame member rebuilding device and nut used therefor
JP3499754B2 (en) Steel column rebuilding device
JP2000345719A (en) Reinforcing method of through opening in existing bearing wall
JP2004169546A (en) Supporting device for anchoring bolt
JPH06272219A (en) Support device of buffer stop support
JP2002349072A (en) Tool for erecting pillar and pillar erecting method using the same
JP3554393B2 (en) Method and apparatus for installing a pillar in a structure
JP3143624B2 (en) Panel mounting method
JPH04371635A (en) Connection of floorslab and post
JPH11293919A (en) Retaining structure of form and method thereof
JPH10299004A (en) Positioning method and equipment for steel pipe column in erecting insertion type steel pipe column
JPH0629233Y2 (en) Anchor bolt installation device
JP2831603B2 (en) Panel mounting method
JPS6046315B2 (en) How to install and fix the sole plate
JP2001081870A (en) Joint pin mounting device and prefabricated building installation method