JPH0663237B2 - Construction method of basement - Google Patents

Construction method of basement

Info

Publication number
JPH0663237B2
JPH0663237B2 JP9854689A JP9854689A JPH0663237B2 JP H0663237 B2 JPH0663237 B2 JP H0663237B2 JP 9854689 A JP9854689 A JP 9854689A JP 9854689 A JP9854689 A JP 9854689A JP H0663237 B2 JPH0663237 B2 JP H0663237B2
Authority
JP
Japan
Prior art keywords
floor
basement
concrete
pillar
construction method
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP9854689A
Other languages
Japanese (ja)
Other versions
JPH02274917A (en
Inventor
行信 黒瀬
豊 斉藤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shimizu Corp
Original Assignee
Shimizu Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shimizu Corp filed Critical Shimizu Corp
Priority to JP9854689A priority Critical patent/JPH0663237B2/en
Publication of JPH02274917A publication Critical patent/JPH02274917A/en
Publication of JPH0663237B2 publication Critical patent/JPH0663237B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Residential Or Office Buildings (AREA)

Description

【発明の詳細な説明】 [産業上の利用分野] 本発明は、鉄筋コンクリート造等の建築物の地下階の構
築工法に係り、とくに、地表面近くに切梁を構築し、そ
の支承のもとで地下階部を掘削するようにした地下階の
構築工法に関するものである。
TECHNICAL FIELD The present invention relates to a method for constructing a basement floor of a building such as a reinforced concrete structure, and in particular, constructing a crossbeam near the ground surface and supporting it. It relates to the construction method of the basement floor where the basement floor is excavated.

[従来の技術] 建築物が鉄筋コンクリート造で形成され、地下階の施工
を先行させるときには、一般に、掘削工事のために四周
に土留の腹起しを廻らせ、これを切梁で支承する必要が
ある。このとき、杭、または地下階柱の地上からの施工
を先行させ、1階の床の位置に切梁を架設し、その支承
のもとで根切り掘削をし、外壁コンクリートを逆打ちし
ながら下向きに掘削を進める工法、掘削の完了後に底盤
から上向きに外壁を構築する工法などの地下階の構築工
法が知られている。
[Prior Art] When a building is made of reinforced concrete and construction of the basement is preceded, it is generally necessary to rotate the earth retaining rod up to four laps for excavation work and to support it with a girder. is there. At this time, the construction of piles or basement pillars from the ground is preceded, a girder is erected at the floor position on the first floor, root excavation is performed under the bearing, and the outer wall concrete is hammered back. There are known construction methods for the basement floor, such as a construction method that promotes excavation downwards and a construction method that constructs an outer wall upwards from the bottom after completion of excavation.

また、切梁として、鋼製の仮設材を使用し、または、コ
ンクリート造の本設床梁の施工を先行させることもよく
行われている。
Further, it is often performed that a temporary steel material is used as the cutting beam or a concrete floor beam made of concrete is first constructed.

[発明が解決しようとする課題] しかしながら、地上からの杭、または地下階柱の施工で
は、精度に限界があるばかりでなく、杭、または地下階
柱とコンクリート造床梁との接合部では、各工種の作業
が集中し、多数の個所に労力を必要として、施工性が低
下することが免れられず、このような欠点が認識されな
いままに経過しているのが現状である。
[Problems to be Solved by the Invention] However, in the construction of piles or basement columns from the ground, there is a limit to the accuracy, and at the joints between the piles or basement columns and concrete floor beams, The current situation is that the work of each type of work is concentrated, labor is required in a large number of places, workability is unavoidable, and such drawbacks are not recognized.

[課題を解決するための手段] 本発明は、上記のような欠点を一掃し、これを課題とし
て、先行する杭または地下階柱と、床梁との接合部の構
造を改善し、ひいては、地下階全体の構築工法を提供す
ることを目的とするものであり、杭、または地下階柱の
地上からの施工を先行させ、その頂部に1階の本設床梁
を架設して切梁とし、その支承のもとで根切り掘削を行
うようにした地下階の構築工法において、とくに、杭の
頂部に鋼製の柱を接続して地中に先行打設する工程、柱
の頂部に、中央部に貫通孔を有するプレキャストコンク
リート製の接合体を遊嵌、挿通して柱に係着させる工
程、接合体にプレキャストコンクリート造のはりを接続
する工程、鋼製柱にコンクリートを後打ちする工程を包
含することを特徴とするものである。これによって、地
下階柱の頂部におけるコンクリート造の本設梁との接合
部における施工方法を改善する目的を達成することに成
功したものである。
[Means for Solving the Problems] The present invention eliminates the above-mentioned drawbacks, and as a problem, improves the structure of a joint between a preceding pile or an underground floor column and a floor beam, and The purpose is to provide a construction method for the entire basement floor. Prior to the construction of piles or basement pillars from the ground, the main floor floor beam of the first floor is erected on top of it to form a cut beam. , In the construction method of the underground floor where root excavation was carried out under the support, especially the process of connecting the steel column to the top of the pile and placing it in the ground in advance, at the top of the column, A process of loosely fitting a precast concrete joint with a through hole in the center and inserting it into the pillar to attach it, a step of connecting a precast concrete beam to the joint, and a step of post-casting concrete to the steel pillar. It is characterized by including. This has succeeded in achieving the purpose of improving the construction method at the joint with the concrete main beam at the top of the basement.

[実施例] 本発明の地下階の構築工法を、好適な実施例を示す図面
に基づいて詳細に説明する。第1図は、本発明を採用す
る鉄筋コンクリート造建築物の地下階部分の断面図であ
り、第2図は柱と梁の接合部の平面図である。図におい
て、1は鉄筋コンクリート造の建築物であり、2は地
盤、3は建築物1の地下室部分の外壁、4は杭、5は地
下室の底盤、6は地下室部分の柱、7は地上階の床梁、
8はその床スラブである。
[Example] The construction method of the basement floor of the present invention will be described in detail with reference to the drawings showing a preferred example. FIG. 1 is a sectional view of a basement floor portion of a reinforced concrete building to which the present invention is applied, and FIG. 2 is a plan view of a joint portion between a column and a beam. In the figure, 1 is a reinforced concrete building, 2 is the ground, 3 is the outer wall of the basement of the building 1, 4 is a pile, 5 is the base of the basement, 6 is the pillar of the basement, and 7 is the ground floor. Floor beams,
8 is the floor slab.

杭4はコンクリート造の場所打ち杭として、底盤5を支
持する地盤2中の所定の深さに打設され、その頂部21
に、柱6の鋼性の芯柱61の下端部62を埋設して接続
してある。この芯柱61の頂部63には、本発明の特徴
となる柱6と梁7との接合体10を載置するブラケット
64が固着してある。
The pile 4 is cast as a concrete cast-in-place pile to a predetermined depth in the ground 2 that supports the bottom 5, and its top portion 21
The lower end portion 62 of the steel core pillar 61 of the pillar 6 is embedded and connected thereto. A bracket 64 for mounting the joined body 10 of the pillar 6 and the beam 7, which is a feature of the present invention, is fixed to the top portion 63 of the core pillar 61.

接合体10は、第2図に示すように、中央の本体部11
と、梁7に対応して突出する複数のアーム部12とから
なるプレキャスト・コンクリート(以下PCという)造
の成形体であり、その本体部11の中心部には、芯柱6
1を遊嵌、挿通する貫通孔13を形成すると共に、一部
に示すアーム部12の先端には、梁7との接合手段72
を設けてある。貫通孔13の周囲には、上下の柱6の接
合のための多数の鉄筋挿通用のスリーブ14を埋設して
あり、貫通孔13の周囲で前記のブラケット64によっ
て支持されている。
As shown in FIG. 2, the joined body 10 includes a main body 11 at the center.
And a plurality of arm portions 12 projecting corresponding to the beam 7, which is a molded body made of precast concrete (hereinafter referred to as “PC”).
A through hole 13 for loosely fitting and inserting 1 is formed, and a joining means 72 for joining to the beam 7 is provided at a tip of an arm portion 12 shown in a part
Is provided. A plurality of sleeves 14 for inserting reinforcing bars for joining the upper and lower columns 6 are embedded around the through hole 13, and are supported by the bracket 64 around the through hole 13.

梁7は、中間部分71がPC梁として形成され、その柱
6側の端部には、鋼製の接続部材72の基端部を埋設し
て突出させてあり、アーム部12に設けた同様の接続部
材72に接続されている。その外壁3側の外方の端部7
3にも、同様の接続部材72が突設されており、外壁3
の頂部31に設けたブラケット32に支持される外周の
梁7Aの鉄骨74に接続されて、梁7Aは梁7を切梁と
する外壁3の腹起しになっている。図中の75はコンク
リート小梁である。
In the beam 7, the intermediate portion 71 is formed as a PC beam, and the base end portion of the connecting member 72 made of steel is embedded and protruded at the end portion on the side of the column 6 so as to be provided in the arm portion 12. Is connected to the connecting member 72. The outer end 7 on the outer wall 3 side
A similar connecting member 72 is also provided on the outer wall 3 of the outer wall 3 as well.
The beam 7A is connected to the steel frame 74 of the beam 7A on the outer periphery supported by the bracket 32 provided on the top 31 of the beam 7A, and the beam 7A is a bulge of the outer wall 3 with the beam 7 as a cut beam. 75 in the figure is a concrete beam.

PC梁71と接合部10とは、スラブ8の厚さだけ床面
より低く形成され、PC梁71と接合部10のアーム部
12とは、小梁75とスラブ8のコンクリートと一体に
打設されたコンクリートによって接続される。
The PC beam 71 and the joint 10 are formed lower than the floor surface by the thickness of the slab 8, and the PC beam 71 and the arm 12 of the joint 10 are cast integrally with the beam 75 and the concrete of the slab 8. Connected by crushed concrete.

このようにして、本設の床梁7が形成され、腹起しに対
する切梁としての機能を有するようになってのち、芯柱
61を中心にして、コンクリート65を打設して、柱6
が完成する。このとき、柱6の鉄筋66の上部は、前記
のスリーブ14を介して、上階の柱6の鉄筋に接続され
る。
In this way, the floor beam 7 that is permanently installed is formed, and after it has a function as a girder for uprising, concrete 65 is placed around the core column 61 to form the column 6
Is completed. At this time, the upper portion of the reinforcing bar 66 of the pillar 6 is connected to the reinforcing bar of the pillar 6 on the upper floor through the sleeve 14.

貫通孔13に挿通された鋼製の芯柱61の頂部63は、
貫通孔13内に遊嵌されているので、接合体10に対し
て十分に精度よく設置され、柱6のコンクリート65と
スラブ8のコンクリートとによって、一体に接続されて
いる。
The top portion 63 of the steel core post 61 inserted into the through hole 13 is
Since it is loosely fitted in the through hole 13, it is installed with sufficient accuracy in the joined body 10 and is integrally connected by the concrete 65 of the pillar 6 and the concrete of the slab 8.

本発明の構成は、上記の実施例に限定されないことはも
ちろんであり、例えば、杭4は、その頂部41に芯柱6
1の下端部61を接続して先行して埋設されるものであ
れば、鋼製杭、PC杭等と代替することができ、また、
接合体10とPC梁71との接合手段も鋼板部材72に
限定されない。
Needless to say, the configuration of the present invention is not limited to the above-described embodiment. For example, the pile 4 has the core column 6 at the top 41 thereof.
1 can be replaced with a steel pile, a PC pile or the like as long as it is connected by connecting the lower end portion 61 of the No. 1 and buried in advance.
The means for joining the joined body 10 and the PC beam 71 is not limited to the steel plate member 72.

[作用] 本発明の地下階の構築工法は、上記のような構成の地下
室を形成するものであるから、その施工は、通常の施工
方法に本発明の接合体10を適用するだけで容易に実施
することができる。このように構成される本発明の作用
を、第1図に基づいて説明する。図において、まず、地
上から場所打ちのコンクリート杭4が所定の深さに打設
され、その硬化が十分進行しないうちに、その頂部41
に鋼製の芯柱61の下端部62を挿入して接続させる。
[Operation] Since the basement floor construction method of the present invention forms the basement having the above-described configuration, its construction can be easily performed by applying the joined body 10 of the present invention to a normal construction method. It can be carried out. The operation of the present invention thus configured will be described with reference to FIG. In the figure, first, a cast-in-place concrete pile 4 is cast from the ground to a predetermined depth, and while its hardening does not proceed sufficiently, its top part 41
The lower end portion 62 of the steel core column 61 is inserted into and connected to.

ついで、別途にプレハブによって成形した接合体10
を、芯柱61の頂部63から嵌挿すれば、接合体10は
ブラケット64上に安定して支持され、その下方におけ
る柱6のコンクリート65の工事が可能である。
Then, a joined body 10 separately molded by a prefab
When the joint body 10 is fitted and inserted from the top portion 63 of the core column 61, the joined body 10 is stably supported on the bracket 64, and the concrete 65 of the column 6 under the bracket 64 can be constructed.

一方、外壁3の内側の位置に梁7Aを構築し、接合体1
0のアーム部12と梁7Aとの間に、PC梁71を配置
し、それらの端部を接合部材72によって接続し、床梁
7を完成させれば、次工程の掘削工事が可能になる。
On the other hand, a beam 7A is constructed at a position inside the outer wall 3,
If the PC beam 71 is arranged between the zero arm part 12 and the beam 7A and their ends are connected by the joining member 72 and the floor beam 7 is completed, the excavation work in the next step becomes possible. .

掘削に伴う外壁3の構築工法は任意であり、通常、本設
床梁7の支承のもとで、逆打ち工法が採用される。
The construction method of the outer wall 3 associated with the excavation is arbitrary, and normally, the reverse construction method is adopted under the support of the permanent floor beam 7.

ここで、本発明においては、接合体10が上記のような
構成になるものであるから、芯柱61の頂部への装着が
極めて容易であり、しかも、貫通孔13によって、柱6
と梁7との接合精度を確保したうえで固定することがで
きるから、切梁の軸力は安全に伝達され、ガセット等の
詳細鋼製は不要である。
Here, in the present invention, since the bonded body 10 is configured as described above, it is extremely easy to mount the core pillar 61 on the top portion, and the through hole 13 allows the pillar 6 to be mounted.
Since it can be fixed after securing the joining accuracy between the beam and the beam 7, the axial force of the cutting beam is safely transmitted, and it is not necessary to use a detailed steel product such as a gusset.

[発明の効果] 本発明の地下階の構築工法は、杭、または地下階柱の地
上からの施工を先行させ、その頂部に1階の本設床梁を
架設して切梁とし、その支承のもとで根切り掘削を行う
ようにした地下階の構築工法において、杭の頂部に鋼製
の柱を接続して地中に先行打設する工程、柱の頂部に、
中央部に貫通孔を有するプレキャストコンクリート製の
接合体を遊嵌、挿通して柱に係着させる工程、接合体に
プレキャストコンクリート造の梁を接続する工程、鋼製
柱にコンクリートを後打ちする工程を包含するものであ
るから、杭または柱と、本設の床梁を使用した切梁との
接合部を、あらかじめ形成した接合体を配置することに
よって、複雑な構成の工事を簡便にしかも精度よく形成
することができる。従って、本発明は、地下室の構築に
欠くことができない根切り掘削に先行して、本設の床梁
を切梁とするものでありながら、杭、柱と切梁との合理
化した接合が確保され、とくに、PC部材の採用によっ
て、労務費と工期の削減に大いに貢献し、従って、地下
階の構築工法に適用して課題を解決することができる。
[Effects of the Invention] In the construction method of the basement floor of the present invention, the construction of the pile or the basement column from the ground is preceded, and the main floor floor beam of the first floor is erected at the top of the pile to form a girder, and its support. In the construction method of the basement floor where the root excavation was performed under the condition, the step of connecting the steel column to the top of the pile and placing it in the ground in advance, at the top of the column,
A process of loosely fitting a precast concrete joint with a through hole in the center and inserting it into a pillar to attach it, a step of connecting a precast concrete beam to the joint, and a step of post-casting concrete to a steel pillar Therefore, by arranging a joint body in which the joints of piles or columns and beam beams using the floor beam of the permanent construction are formed in advance, it is possible to easily and accurately carry out the construction of complicated structures. Can be well formed. Therefore, in the present invention, prior to excavation excavation that is indispensable for the construction of the basement, while the floor beam of the main construction is used as the cutting beam, the rational connection between the pile, the pillar and the cutting beam is secured. In particular, the adoption of the PC member greatly contributes to the reduction of labor cost and construction period, and therefore can be applied to the construction method of the underground floor to solve the problem.

【図面の簡単な説明】[Brief description of drawings]

図面は本発明の地下階の構築工法を実施例に基づいて説
明するものであり、第1図は本発明を採用した鉄筋コン
クリート造建築物の地下階部分の断面図であり、第2図
は柱と梁の接合部の平面図である。 1…建築物、2…地盤、3…外壁、4…杭、5…底盤、
6…柱、7…床梁、8…床スラブ、10…接合体、11
…本体部、12…アーム部、13…貫通孔、14…スリ
ーブ、61…芯柱、62…下端部、63…頂部、64…
ブラケット、65…コンクリート、71…PC梁、72
…接合部材。
The drawings are for explaining the construction method of the basement floor of the present invention based on examples, FIG. 1 is a sectional view of the basement floor portion of a reinforced concrete building adopting the present invention, and FIG. 2 is a pillar It is a top view of the junction part of a beam and a beam. 1 ... Building, 2 ... Ground, 3 ... Exterior wall, 4 ... Pile, 5 ... Bottom board,
6 ... Pillar, 7 ... Floor beam, 8 ... Floor slab, 10 ... Joined body, 11
... body part, 12 ... arm part, 13 ... through hole, 14 ... sleeve, 61 ... core post, 62 ... lower end part, 63 ... top part, 64 ...
Bracket, 65 ... Concrete, 71 ... PC beam, 72
... Joining member.

Claims (1)

【特許請求の範囲】[Claims] 【請求項1】杭、または地下階柱の地上からの施工を先
行させ、その頂部に1階の本設床梁を架設して切梁と
し、その支承のもとで根切り掘削を行うようにした地下
階の構築工法において、杭の頂部に鋼製の柱を接続して
地中に先行打設する工程、柱の頂部に、中央部に貫通孔
を有するプレキャストコンクリート製の接合体を遊嵌、
挿通して柱に係着させる工程、接合体にプレキャストコ
ンクリート造の梁を接続する工程、鋼製柱にコンクリー
トを後打ちする工程を包含することを特徴とする地下階
の構築工法。
[Claim 1] Construction of piles or basement pillars from the ground is preceded, and a permanent floor beam on the first floor is erected on the top of the pile to form a cut beam, and root excavation is performed under the bearing. In the construction method of the basement, the step of connecting a steel column to the top of the pile and placing it in the ground in advance, at the top of the column, play a precast concrete joint with a through hole in the center. Fit,
A method for constructing a basement floor, which includes a step of inserting and fastening to a pillar, a step of connecting a beam of precast concrete to a joint, and a step of post-casting concrete to a steel pillar.
JP9854689A 1989-04-18 1989-04-18 Construction method of basement Expired - Lifetime JPH0663237B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP9854689A JPH0663237B2 (en) 1989-04-18 1989-04-18 Construction method of basement

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP9854689A JPH0663237B2 (en) 1989-04-18 1989-04-18 Construction method of basement

Publications (2)

Publication Number Publication Date
JPH02274917A JPH02274917A (en) 1990-11-09
JPH0663237B2 true JPH0663237B2 (en) 1994-08-22

Family

ID=14222689

Family Applications (1)

Application Number Title Priority Date Filing Date
JP9854689A Expired - Lifetime JPH0663237B2 (en) 1989-04-18 1989-04-18 Construction method of basement

Country Status (1)

Country Link
JP (1) JPH0663237B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105040706A (en) * 2015-05-19 2015-11-11 昆明理工大学 Double-row pile support structure capable of fully utilizing basement space and construction method of double-row pile support structure

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105040706A (en) * 2015-05-19 2015-11-11 昆明理工大学 Double-row pile support structure capable of fully utilizing basement space and construction method of double-row pile support structure

Also Published As

Publication number Publication date
JPH02274917A (en) 1990-11-09

Similar Documents

Publication Publication Date Title
JP3671344B2 (en) Joint structure between foundation pile and column base and its construction method
JP4625692B2 (en) Building construction method of base-isolated structure with laminated rubber bearing
JP2531038B2 (en) Pillar PC structure
JPH0663237B2 (en) Construction method of basement
JP3062909B2 (en) Construction method of composite underground wall using soil cement column wall
JP2001132275A (en) Sign pole foundation and method for constructing the same
JPH07109098B2 (en) Construction method of basement floor and beam-column joint used for the construction method
JP2002194748A (en) Foundation constructing method and building foundation structure
JPH0721196B2 (en) Reverse construction method of underground structure
JP3700119B2 (en) Pillar construction method
JP2504578B2 (en) Steel frame construction method
JPH1113067A (en) Burying construction method for supplementary stud in reverse concreting construction method
JP2763488B2 (en) Prefabricated pillar and inverted ramen prefabricated construction method
JPH03132521A (en) Strut construction method of basement floor excavation work
JPH11181807A (en) Construction method for underground story
JP3567387B2 (en) How to build an underground skeleton
JP4589506B2 (en) Pre-installation method of large steel columns for constructing buildings with superstructure structure by the reverse driving method
JP2913509B2 (en) How to build PC members
JP2000291146A (en) Joint structure of pile head and column, and construction method therefor
JPH09256383A (en) Erection method of steel framed column
JP2001262592A (en) Foundation of structure and execution work method therefor
JPH05140953A (en) Building with steel skeleton
JPH0726574A (en) Reverse driving method with prior excavation for column
JP3027498B2 (en) Precast concrete foundation and its construction method
JPH05112947A (en) Execution method of foundation