JPH06301684A - Schedule calculating method for process network - Google Patents
Schedule calculating method for process networkInfo
- Publication number
- JPH06301684A JPH06301684A JP10738993A JP10738993A JPH06301684A JP H06301684 A JPH06301684 A JP H06301684A JP 10738993 A JP10738993 A JP 10738993A JP 10738993 A JP10738993 A JP 10738993A JP H06301684 A JPH06301684 A JP H06301684A
- Authority
- JP
- Japan
- Prior art keywords
- work
- holiday
- days
- date
- schedule
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02P—CLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
- Y02P90/00—Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
- Y02P90/30—Computing systems specially adapted for manufacturing
Abstract
Description
【0001】[0001]
【産業上の利用分野】本発明は、建設工事の工程計画に
用いられる工程ネットワークの日程計算方法に関し、特
に、工程ネットワークにおける日程を、休日か作業日か
を評価しながら計算することができる工程ネットワーク
の日程計算方法に関する。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method of calculating a schedule of a process network used for a process plan of a construction work, and more particularly, a process of calculating a schedule in a process network while evaluating whether it is a holiday or a work day. It is related to a network schedule calculation method.
【0002】[0002]
【従来の技術】建設工事における工程計画は、建築物を
指定工期内に精度の高い品質の施工を工事予算に合わせ
て実施し、竣工させることを目的として行うものであっ
て、その工程計画の作成にはネットワーク技法が使用さ
れる。従来、このような工程ネットワークにおいて、例
えば、構造物の鉄筋コンクリート工事の日程計算を行う
場合は、図5に示すように、鉄筋組、型枠組、コンクリ
ート打設、コンクリート養生、型枠払いからなる工程ネ
ットワークの作業開始時刻をゼロとして、各作業の所要
日数を逐次加算しながら、作業終了点への到達時刻を求
め、これから鉄筋コンクリート工事ネットワークの工期
を求めるようにしていた。この場合、図5から明らかな
ように、5日目が作業開始日であり、16日目が作業終
了日となり、12日目が休日となる。また、休日や稼働
率をカレンダ処理により作業休止日という方法で指定
し、明確に区別することなしに設定する。さらに、休日
を伴う場合の日程割付方法では、まず、休日を除いた日
程に関して工程ネットワーク計算を行い、その後、休日
を割り付ける方法を採っていた。2. Description of the Related Art A construction process plan is for the purpose of executing a construction with high precision and quality within a designated construction period according to a construction budget and completing the construction. Network techniques are used for the creation. Conventionally, in such a process network, for example, when calculating a schedule for reinforced concrete construction of a structure, as shown in FIG. 5, a process consisting of a reinforcing bar assembly, a formwork, concrete placing, concrete curing, and formwork removal. With the work start time of the network set to zero, the time required to reach the work end point was calculated by successively adding the required days for each work, and the construction period of the reinforced concrete construction network was calculated from this. In this case, as is clear from FIG. 5, the fifth day is the work start date, the sixteenth day is the work end date, and the twelfth day is a holiday. In addition, holidays and operating rates are specified by calendar processing by the method of work suspension days, and are set without distinction. Further, in the schedule allocation method involving a holiday, first, a process network calculation is performed for the schedule excluding the holiday, and then the holiday is allocated.
【0003】[0003]
【発明が解決しようとする課題】しかしながら、上記従
来の工程ネットワークの日程計算方法では、休日と稼働
率をカレンダにより明確に区別せずに設定しているた
め、工程計画上においても、その違いを明確に表すこと
ができない。即ち、建設工事の工程ネットワークには、
建設工事に特有のコンクリート打設に伴う養生期間な
ど、作業間にタイムラグを伴った順序関係が多く現れる
が、ある作業が、どのような期間(例えば、作業間の休
日を挟んでいるかどうか)に行うのか何ら考慮していな
いため、上述したコンクリート養生期間などの養生期間
が休日に重なった場合には、休日を養生期間と考えず、
休日と養生期間を別々に加算する日程計算が行われてい
た。このため、工程計画と現実の工事との間に大きな差
が生じ、正確な日程計算ができないという問題があっ
た。However, in the above-mentioned conventional schedule calculation method for the process network, the holiday and the operation rate are set without being clearly distinguished by the calendar, so that the difference in the process plan is also caused. It cannot be expressed clearly. That is, in the construction process network,
There are many sequence relationships with a time lag between works, such as the curing period associated with concrete pouring, which is peculiar to construction work, but during what work (for example, whether or not there are holidays between work) Since no consideration is given to what to do, if the curing period such as the concrete curing period mentioned above overlaps with the holiday, do not consider the holiday as the curing period,
The schedule was calculated to add holidays and curing periods separately. For this reason, there is a large difference between the process plan and the actual construction, and there is a problem that an accurate schedule cannot be calculated.
【0004】本発明は、上述のような従来の問題を解決
するものであり、その目的とするところは、より現実の
工事に近い実質に合った日程計算を行うことができる工
程ネットワークの日程計算方法を提供することにある。The present invention solves the above-mentioned conventional problems, and an object of the present invention is to calculate a schedule of a process network capable of performing a schedule calculation that is more closely matched to actual construction and is substantially suitable for actual construction. To provide a method.
【0005】[0005]
【課題を解決するための手段】上記目的を達成するため
に、本発明は、構造物を建造するのに必要な複数の作業
の順序関係を表わす工程ネットワークの作業開始から終
了までの日程を求める工程ネットワークの日程計算方法
であって、暦日上から前記工程ネットワークの作業開始
日もしくは作業終了日が休日かを判定する工程と、前記
各作業で使用する工事資源、及び前記構造物を建造する
時期に応じて設定された実働日数と稼働率に基づいて前
記各作業を遂行するのに必要な所要日数を算出する工程
と、前記休日でないと判定された作業開始日もしくは作
業終了日から暦日を参照しながら1日毎に前記所要日数
の作業割り付け日が休日かを判定し、休日でないと判定
される毎に作業日数をカウントアップするとともに、そ
の作業日数が前記算出された所要日数に達するまで作業
日を暦日上に順番に割り付ける工程とを備えてなるもの
である。また、本発明は、コンクリート養生期間等の作
業間に生じるタイムラグを休日として割り付けるように
したことを特徴とする。In order to achieve the above object, the present invention obtains a schedule from the start to the end of work of a process network which represents the order relation of a plurality of works required for constructing a structure. A method of calculating a schedule of a process network, comprising a step of determining whether a work start date or a work end date of the process network is a holiday from a calendar day, a construction resource used in each work, and the structure. A step of calculating the required number of days required to perform each work based on the actual work days and the operating rate set according to the time, and a calendar day from the work start date or work end date determined not to be the holiday It is determined for each day whether the work allocation date of the required number of days is a holiday, and the number of work days is incremented each time it is determined not to be a holiday. The work day until reaching the number of days required issued is made and a step of assigning sequentially on calendar days. Further, the present invention is characterized in that a time lag generated during work such as a concrete curing period is allocated as a holiday.
【0006】[0006]
【実施例】以下、本発明方法の一実施例を図に基づいて
説明する。図1は、本発明による工程ネットワーク日程
計算方法のシステム構成図である。図1において、10
はシステム全体を管理し制御する中央処理装置(以下、
CPUと略称する)であり、このCPU10には、日程
演算プログラム等を格納する記憶装置11、年間の七
曜、祭日を記憶するカレンダ装置12及び各種のインタ
フェース13、14、15がそれぞれ接続されている。An embodiment of the method of the present invention will be described below with reference to the drawings. FIG. 1 is a system configuration diagram of a process network schedule calculation method according to the present invention. In FIG. 1, 10
Is a central processing unit that manages and controls the entire system (hereinafter,
The CPU 10 is connected to a storage device 11 for storing a schedule calculation program and the like, a calendar device 12 for storing seven days of the year and holidays, and various interfaces 13, 14, 15 respectively. .
【0007】入力用のインタフェース13にはキーボー
ド等からなる入力装置16が接続され、表示用のインタ
フェース14には、表示制御回路17を介してCRTか
らなる表示装置18が接続され、また、出力用のインタ
フェース15には、プリンタ制御回路19を介してプリ
ンタ20が接続されている。さらに、CPU10には、
出力用のインタフェース21が接続され、このインタフ
ェース21にはプロッタ制御回路22を介してXYプロ
ッタ23が接続されている。An input device 16 such as a keyboard is connected to the input interface 13, a display device 18 formed of a CRT is connected to the display interface 14 via a display control circuit 17, and an output device is also provided. A printer 20 is connected to the interface 15 of FIG. Further, the CPU 10 has
An output interface 21 is connected, and an XY plotter 23 is connected to the interface 21 via a plotter control circuit 22.
【0008】次に、本実施例による工程ネットワークの
日程計算を図2に示すフローチャートを参照して説明す
る。工程ネットワークの作成に際しては、工事の設計
図、施工場所の立地条件、施工計画、各作業の作業量、
各職労務者並びに工事機械の作業能率、資材、労務調達
に関する準備データを用意し、これらの準備データを入
力装置16から入力した後、構造物を建造するのに必要
な複数の作業とその順序関係を表すネットワークデータ
と、これらの工事資源データに応じて設定された作業に
要する実働日数及び月単位や週単位で期間毎に設定され
る稼働率を入力装置16から入力し、ネットワーク作成
の見積りを行う。その後、本実施例の日程計算が実行さ
れる。Next, the schedule calculation of the process network according to this embodiment will be described with reference to the flowchart shown in FIG. When creating the process network, the blueprint of the construction, the site conditions of the construction site, the construction plan, the work volume of each work,
After preparing preparation data concerning work efficiency of each worker and construction machine, materials, and labor procurement and inputting these preparation data from the input device 16, a plurality of works necessary for constructing a structure and the order thereof. Estimate the creation of the network by inputting from the input device 16 the network data representing the relationship and the actual work days required for the work set according to these construction resource data and the operating rate set for each period in monthly or weekly units. I do. After that, the schedule calculation of this embodiment is executed.
【0009】日程演算プログラムがスタートすると、C
PU10はステップS1において、カレンダ装置12の
暦日を参照しながら工程ネットワークの作業開始日が休
日かを判定する。ここで、休日であると判定された場合
はステップS2に進み、作業開始日(ES)=ES+1
の処理を行ってステップS3に戻り、休日かの判定を再
度実行する。また、作業開始日が休日でないと判定され
たときはステップS3に進む。ステップS3では、作業
開始日(ES)を暦日上の日付(D)に代入し、CPU
内蔵の作業日数計数用カウンタの計数値(N)を0にリ
セットする。本実施例では、図3に示すように、暦日上
の5日が休日であるので、次の6日を参照する。この場
合、6日が平日であるので、作業開始日には6日が割り
当てられる。When the schedule calculation program starts, C
In step S1, the PU 10 determines whether the work start date of the process network is a holiday with reference to the calendar date of the calendar device 12. If it is determined that it is a holiday, the process proceeds to step S2, and the work start date (ES) = ES + 1
Processing is performed and the process returns to step S3 to determine again whether it is a holiday. When it is determined that the work start date is not a holiday, the process proceeds to step S3. In step S3, the work start date (ES) is substituted for the calendar date (D), and the CPU
The count value (N) of the built-in work day counting counter is reset to 0. In this embodiment, as shown in FIG. 3, 5 days on a calendar day is a holiday, so the next 6 days are referred to. In this case, since 6 days are weekdays, 6 days are assigned to the work start date.
【0010】次のステップS4では、作業に要する実働
日数と稼働率に基づいて全作業工程に要する所要日数
(DUL)を算出する。このときの稼働率は、割り付け
られた最早開始日(作業を始め得る最も早い日)もしく
は最遅開始日(作業を最も遅く開始してもよい日)から
の所要日数を求める場合に考慮される必要がある。本実
施例における実働日数は6日間で、稼働率は75%であ
るから、図3に示すように、全作業工程に要する所要日
数は8日間となる。In the next step S4, the required number of days (DUL) required for all work processes is calculated based on the actual number of work days required for the work and the operating rate. The operating rate at this time is taken into consideration when calculating the required number of days from the earliest start date (the earliest day when work can be started) or the latest start date (day when work may be started latest) There is a need. Since the actual working days in this embodiment are 6 days and the operating rate is 75%, the number of days required for all working steps is 8 days as shown in FIG.
【0011】次のステップS5では、暦日上の日付
(D)を作業開始日からインクリメントし、インクリメ
ント毎にD+1の日付が休日かを判定する。ここで、休
日であると判定されたときはステップS5の処理を繰り
返し実行する。また、休日でないと判定されたときはス
テップS6に進み、日付(D)が休日でないと判定され
る毎に作業日数(N)をカウントアップし、その作業日
数(N)が算出した所要日数(DUL)に達したかを判
定する。作業日数(N)が所要日数(DUL)に達して
いないときはステップS5に戻り、作業日数(N)が所
要日数(DUL)に達するまでステップS5及びステッ
プS6の処理を繰り返し実行する。そして、作業日数
(N)が所要日数(DUL)に達したことが判定された
場合はステップS7に進み、その日付(D)を作業終了
日として割り付け、記憶装置11に記録する。本実施例
では、図3に示すように、暦日上の16日が作業終了日
となる。In the next step S5, the calendar date (D) is incremented from the work start date, and it is determined for each increment whether the date D + 1 is a holiday. If it is determined that it is a holiday, the process of step S5 is repeatedly executed. When it is determined that it is not a holiday, the process proceeds to step S6, and the number of working days (N) is counted up every time it is determined that the date (D) is not a holiday, and the number of working days (N) calculated is the required number of days ( DUL) is reached. When the number of working days (N) has not reached the required number of days (DUL), the process returns to step S5, and the processes of steps S5 and S6 are repeatedly executed until the number of working days (N) reaches the required number of days (DUL). When it is determined that the number of work days (N) has reached the required number of days (DUL), the process proceeds to step S7, and the date (D) is assigned as the work end date and recorded in the storage device 11. In this embodiment, as shown in FIG. 3, the 16th calendar day is the work end date.
【0012】このようにして計算された日程データは、
CPU10からプレシーデンス形式の工程ネットワーク
表データとともに表示制御回路17を通して表示装置1
8に出力され、表示される。また、必要に応じて日程デ
ータをプリンタ20によりプリントアウトすることがで
きる。さらに、工程ネットワークデータをプロッタ制御
回路22を通してXYプロッタ23に出力することによ
り、ネットワーク工程図を描画することができる。The schedule data calculated in this way is
The display device 1 from the CPU 10 through the display control circuit 17 together with the precedence network process network table data.
8 is output and displayed. Further, the schedule data can be printed out by the printer 20 as needed. Further, by outputting the process network data to the XY plotter 23 through the plotter control circuit 22, a network process diagram can be drawn.
【0013】上記のような本実施例においては、上記図
2のフローチャートから明らかなように、指定した工程
ネットワークの作業開始日が暦日上の休日でないと判定
されたときは、その日を作業開始日として割り付け、そ
して、工事資源および時期に応じて設定した実働日数と
稼働率に基づいて所要日数を算出し、この所要日数を基
に日程割り付けを行うときに、1日毎に休日か作業日か
を判定しながら作業日数のみをカウントし、その作業日
数が所要日数になった日付(D)を作業終了日として割
り付けるようにしたので、現実の工事に近い日程計算が
可能になるとともに、稼働率と休日を明確に区別するこ
とにより、工程計画時に稼働率を変動させた日程シミュ
レーションが可能になる。また、建設工事に特有のコン
クリート養生期間などのタイムラグを用いて表現した場
合、休日にタイムラグを割り付けることが可能になり、
より現実の工事に近い実質的な工程ネットワークを作成
することができる。In this embodiment as described above, as is apparent from the flow chart of FIG. 2, when it is determined that the work start date of the designated process network is not a holiday on a calendar day, the work is started on that day. Allocate as days, and calculate the required number of days based on the actual number of working days and the operating rate set according to the construction resource and time, and when allocating the schedule based on this number of days Only the number of work days is counted while determining the number of days, and the date (D) when the number of work days becomes the required number is assigned as the work end date. Therefore, it becomes possible to calculate a schedule close to the actual construction and the operating rate. By clearly distinguishing between holidays and holidays, it becomes possible to perform schedule simulations with varying operating rates during process planning. Also, when expressed using a time lag such as the concrete curing period that is unique to construction work, it becomes possible to allocate a time lag to holidays,
It is possible to create a substantial process network that is closer to actual construction.
【0014】なお、上記実施例では、日程計算を前進計
算により求めた場合について述べたが、本発明はこれに
限定されず、これと反対に作業終了日から開始日に向か
って逆に計算する後進計算で日程割り付けにも適用され
る。この場合の日程割り付けの状態を図4に示す。In the above embodiment, the case where the schedule calculation is obtained by the forward calculation has been described, but the present invention is not limited to this, and conversely, the calculation is performed backward from the work end date to the start date. It is also applied to schedule allocation in backward calculation. The schedule allocation state in this case is shown in FIG.
【0015】[0015]
【発明の効果】以上述べたように本発明によれば、構造
物を建造するのに必要な複数の作業の順序関係を表わす
工程ネットワークの作業開始から終了までの日程を求め
る工程ネットワークの日程計算方法であって、暦日上か
ら前記工程ネットワークの作業開始日もしくは作業終了
日が休日かを判定する工程と、前記各作業で使用する工
事資源、及び前記構造物を建造する時期に応じて設定さ
れた実働日数と稼働率に基づいて前記各作業を遂行する
のに必要な所要日数を算出する工程と、前記休日でない
と判定された作業開始日もしくは作業終了日から暦日を
参照しながら1日毎に前記所要日数の作業割り付け日が
休日かを判定し、休日でないと判定される毎に作業日数
をカウントアップするとともに、その作業日数が前記算
出された所要日数に達するまで作業日を暦日上に順番に
割り付ける工程とを備える構成にしたので、現実の工事
に近い日程計算が可能になるとともに、稼働率と休日を
明確に区別することにより、工程計画時に稼働率を変動
させた日程シミュレーションが可能になる。また、本発
明においては、コンクリート養生期間などの作業間に生
じるタイムラグを休日に割り付けることが可能になり、
より現実の工事に近い実質的な工程ネットワークを作成
することができる。As described above, according to the present invention, the schedule calculation of the process network for obtaining the schedule from the start to the end of the work of the process network that represents the order relation of a plurality of works necessary for constructing the structure A method for determining whether a work start date or a work end date of the process network is a holiday from a calendar day, a construction resource used in each work, and a time to construct the structure Referring to a calendar day from a work start date or a work end date determined not to be the above-mentioned holiday, based on the calculated number of actual work days and the operating rate For each day, it is determined whether the work allocation date of the required number of days is a holiday, and the number of working days is incremented each time it is determined that it is not a holiday, and the number of working days is the calculated required number of days. Since it has a process that allocates work days in order on the calendar day until it reaches, it is possible to calculate the schedule close to the actual construction, and by clearly distinguishing the operating rate and holidays, it is possible to operate at the time of process planning. It becomes possible to perform a schedule simulation with varying rates. Further, in the present invention, it becomes possible to allocate a time lag that occurs during work such as a concrete curing period to a holiday,
It is possible to create a substantial process network that is closer to actual construction.
【図1】本発明による工程ネットワーク日程計算方法の
システム構成図である。FIG. 1 is a system configuration diagram of a process network schedule calculation method according to the present invention.
【図2】本実施例における日程計算の処理手順を示すフ
ローチャートである。FIG. 2 is a flowchart showing a processing procedure of a schedule calculation in the present embodiment.
【図3】本実施例における日程計算を前進計算で求めた
場合の説明図である。FIG. 3 is an explanatory diagram of a case where a schedule calculation in the present embodiment is obtained by forward calculation.
【図4】本実施例における日程計算を後進計算で求めた
場合の説明図である。FIG. 4 is an explanatory diagram of a case where a schedule calculation is obtained by a backward calculation in the present embodiment.
【図5】従来の日程計算を前進計算で求めた場合の説明
図である。FIG. 5 is an explanatory diagram when a conventional schedule calculation is obtained by forward calculation.
10 CPU 11 記憶装置 12 カレンダ装置 16 入力装置 18 表示装置 20 プリンタ 10 CPU 11 Storage Device 12 Calendar Device 16 Input Device 18 Display Device 20 Printer
Claims (2)
の順序関係を表わす工程ネットワークの、作業開始から
終了までの日程を求める工程ネットワークの日程計算方
法であって、 暦日上から前記工程ネットワークの作業開始日もしくは
作業終了日が休日かを判定する工程と、 前記各作業で使用する工事資源、及び前記構造物を建造
する時期に応じて設定された実働日数と稼働率に基づい
て前記各作業を遂行するのに必要な所要日数を算出する
工程と、 前記休日でないと判定された作業開始日もしくは作業終
了日から暦日を参照しながら1日毎に前記所要日数の作
業割り付け日が休日かを判定し、休日でないと判定され
る毎に作業日数をカウントアップするとともに、その作
業日数が前記算出された所要日数に達するまで作業日を
暦日上に順番に割り付ける工程と、 を備えてなる工程ネットワークの日程計算方法。1. A process network schedule calculation method for obtaining a schedule from a work start to a finish of a process network that represents a sequence relationship of a plurality of works required for constructing a structure, the calendar method comprising: Based on the process of determining whether the work start date or the work end date of the process network is a holiday, the work resources used in each work, and the actual work days and the operating rate set according to the time of constructing the structure A step of calculating the required number of days required to perform each of the work, and a work allocation date of the required number of days every day while referring to a calendar day from the work start date or work end date determined not to be the holiday It is determined whether it is a holiday, and the number of working days is incremented each time it is determined that it is not a holiday, and the working days are ordered in calendar days until the number of working days reaches the calculated required number of days. A process network schedule calculation method that comprises processes to be assigned to the numbers.
るタイムラグを休日として割り付けるようにしたことを
特徴とする請求項1記載の工程ネットワークの日程計算
方法。2. The process network schedule calculation method according to claim 1, wherein a time lag that occurs between works such as a concrete curing period is allocated as a holiday.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP10738993A JPH06301684A (en) | 1993-04-09 | 1993-04-09 | Schedule calculating method for process network |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP10738993A JPH06301684A (en) | 1993-04-09 | 1993-04-09 | Schedule calculating method for process network |
Publications (1)
Publication Number | Publication Date |
---|---|
JPH06301684A true JPH06301684A (en) | 1994-10-28 |
Family
ID=14457897
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP10738993A Pending JPH06301684A (en) | 1993-04-09 | 1993-04-09 | Schedule calculating method for process network |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPH06301684A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2014080768A (en) * | 2012-10-16 | 2014-05-08 | Takenaka Komuten Co Ltd | Vertical loading testing method of existing pile, and construction method of concrete reaction body |
-
1993
- 1993-04-09 JP JP10738993A patent/JPH06301684A/en active Pending
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2014080768A (en) * | 2012-10-16 | 2014-05-08 | Takenaka Komuten Co Ltd | Vertical loading testing method of existing pile, and construction method of concrete reaction body |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN110503325B (en) | Construction progress resource automatic optimization method based on building information model | |
US7752020B2 (en) | System and method for modeling construction risk using location-based construction planning models | |
Padilla et al. | Resource strategies for dynamic project management | |
EP1640834B1 (en) | Dynamic-state waiting time analysis method for complex discrete manufacturing | |
US20040098291A1 (en) | Apparatus and method for visualizing resource consumption | |
US8244569B2 (en) | Non-destructive element splitting using location-based construction planning models | |
JPH05225205A (en) | Sequential defined production planning system | |
WO2011058606A1 (en) | Construction process creation system and construction process creation method | |
Arditi et al. | Scheduling system for repetitive unit construction using line‐of‐balance technology | |
US5506783A (en) | Method and apparatusa for determining supply sequence of products ot be processed to production line | |
US20070239410A1 (en) | Location-based construction planning and scheduling system | |
JPH06301684A (en) | Schedule calculating method for process network | |
WO1994016397A2 (en) | Method of enterprise-wide to do list scheduling | |
CN114503140A (en) | Production simulation device | |
JP3010269B2 (en) | Work schedule creation device | |
JPH1086044A (en) | Worker's discretion utilization schedule planning method and device therefor | |
Baxendale | Construction resource models by Monte Carlo simulation | |
JP3045075B2 (en) | Production scheduling method | |
JPH10244442A (en) | Large-scale production planning method | |
JP2615575B2 (en) | Production management method and production management device | |
JPH06332909A (en) | Plan managing system | |
JPH09231420A (en) | Method for preparing process network | |
JP2004038405A (en) | Apparatus for creating production schedule | |
JP2000011039A (en) | Device for calculating cost index | |
JPH09198441A (en) | Estimation device and estimation method |