JPH06298487A - Hoisting jig for precast concrete mold and method for hoisting precast concrete mold - Google Patents

Hoisting jig for precast concrete mold and method for hoisting precast concrete mold

Info

Publication number
JPH06298487A
JPH06298487A JP8893093A JP8893093A JPH06298487A JP H06298487 A JPH06298487 A JP H06298487A JP 8893093 A JP8893093 A JP 8893093A JP 8893093 A JP8893093 A JP 8893093A JP H06298487 A JPH06298487 A JP H06298487A
Authority
JP
Japan
Prior art keywords
precast concrete
concrete formwork
hoisting
precast
jig
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP8893093A
Other languages
Japanese (ja)
Inventor
Tomio Kondo
富美夫 近藤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shimizu Construction Co Ltd
Shimizu Corp
Original Assignee
Shimizu Construction Co Ltd
Shimizu Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shimizu Construction Co Ltd, Shimizu Corp filed Critical Shimizu Construction Co Ltd
Priority to JP8893093A priority Critical patent/JPH06298487A/en
Publication of JPH06298487A publication Critical patent/JPH06298487A/en
Pending legal-status Critical Current

Links

Landscapes

  • Load-Engaging Elements For Cranes (AREA)

Abstract

PURPOSE:To provide a hoisting jig by means of which a precast concrete mold temporarily laid on its side is safely hoisted so that an operation for plumbing the precast concrete mold can be performed with efficiency. CONSTITUTION:A hoisting jig includes a hanging beam 9, a plurality of anchored blocks 10... each secured to the hanging beam 9, a wire 11 wound to each of the anchored block 10..., and a plurality of running blocks 12... each suspended by means of the wire 11, and the wire 11 is wound to each of the anchored blocks 10... and to each of the running blocks 12... so that the running blocks 12... are allowed to freely go up and down relative to the anchored blocks 11..., and each of the running blocks 12... is provided with an engagement jig 12e to be engaged with a precast mold 2.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明は、プレキャストコンクリ
ート型枠を揚重機により吊り上げる際に使用されるプレ
キャストコンクリート型枠の吊治具およびこれを使用し
たプレキャスト型枠の吊り上げ方法に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a hoisting jig for precast concrete formwork used when hoisting a precast concrete formwork and a method for hoisting the precast formwork using the jig.

【0002】[0002]

【従来の技術】周知のように、建築構造物の柱の構築に
あっては、近年の作業者不足、せき板型枠の組立・解体
作業による作業の長期化、せき板の使用量の低減による
環境問題への対応等に鑑みて、その構築に際して、構築
する柱の側面を形成するように筒状に一体成形されたプ
レキャストコンクリート型枠(以下、単に「プレキャス
ト型枠」と略称する。)が使用されている。
2. Description of the Related Art As is well known, in the construction of columns for building structures, there is a shortage of workers in recent years, prolongation of work by assembling and disassembling dams for formwork, and reduction of the amount of dams used. In consideration of the environmental issues and the like, the precast concrete formwork (hereinafter simply referred to as "precast formwork") integrally formed in a tubular shape so as to form the side surface of the pillar to be constructed. Is used.

【0003】このプレキャスト型枠を使用した柱の構築
は、以下の主たる工程により行われる。 (1)当該プレキャスト型枠を揚重機により吊り上げる
とともに、作業床に予め建て込まれた柱鉄骨、柱主筋、
フープ筋等の補強材の上方から該補強材を内包するよう
に建て入れて立設する。 (2)その後のコンクリート打設時における当該プレキ
ャスト型枠の位置のずれを防ぐために、作業床に固定し
たパイプサポート、あるいは支持チェーン等の直立支持
部材を使用してその立設位置を調整して姿勢固定する。 (3)上記姿勢固定したプレキャスト型枠内にコンクリ
ートを打設し、該プレキャスト型枠と打設されたコンク
リートが一体となった柱を構築する。
The construction of columns using this precast formwork is performed by the following main steps. (1) The precast formwork is hoisted by a lifting machine, and a column steel frame, a column main bar, which is built in the work floor in advance,
The reinforcing material, such as a hoop streak, is built up from the upper side so as to enclose the reinforcing material and erected. (2) In order to prevent the displacement of the precast formwork during subsequent concrete pouring, adjust the standing position using a pipe support fixed to the work floor or an upright support member such as a support chain. Fix the posture. (3) Concrete is cast in the precast mold whose posture is fixed, and a column in which the precast mold and the cast concrete are integrated is constructed.

【0004】ところで、上記工程(1)のプレキャスト
型枠を揚重吊下し補強材の周りに建て入れるに際して
は、作業床上、あるいは作業現場内のストックヤードに
横倒しの状態で仮置されたプレキャスト型枠を引き起こ
す作業が必要となる。この引き起こし作業は、図6に示
すように、所定長さの山型鋼からなる吊金具1の板部1
aを、仮置されたプレキャスト型枠2の水平方向に対向
する側壁部2a、2aの端部にそれぞれ上下二箇所ずつ
当接させてボルト・ナットからなる締結具3により固定
し、各吊金具1の板部1bの上端部に設けた孔4にシャ
ックル5を取付けるとともに、各シャックル5に吊りワ
イヤー6の一端のフック7を引っ掛け、この吊りワイヤ
ー7の他端を所定の位置(図示せず)で収束させて揚重
機(図示せず)により吊り上げ、該プレキャスト型枠の
吊金具1を取付けない他の端部を支点として引き起こし
ていた。
By the way, when the precast formwork in the above step (1) is suspended by lifting and built around the reinforcing material, the precast is temporarily placed on the work floor or in a stockyard in the work site in a laid state. Work that causes the formwork is required. As shown in FIG. 6, this raising work is performed by the plate portion 1 of the hanging metal fitting 1 made of mountain steel having a predetermined length.
a is abutted at the upper and lower ends of side walls 2a, 2a of the temporarily placed precast formwork 2 which are opposed to each other in the horizontal direction, and fixed by fasteners 3 composed of bolts and nuts. The shackle 5 is attached to the hole 4 provided at the upper end of the plate portion 1b of No. 1, and the hook 7 at one end of the suspension wire 6 is hooked on each shackle 5, and the other end of the suspension wire 7 is placed at a predetermined position (not shown). ) And it was hoisted by a lifting machine (not shown), and the other end of the precast formwork where the hanging metal fitting 1 was not attached was used as a fulcrum.

【0005】[0005]

【発明が解決しようとする課題】しかしながら、上記従
来のプレキャスト型枠の引き起こし作業には次のような
問題が存在した。すなわち、プレキャスト型枠2に固定
した吊金具1に独立して吊りワイヤー6のフック5を引
っ掛けてプレキャスト型枠2を吊り上げているため、吊
り上げ初期から垂直に立設させるまでは下方に固定した
吊金具1に引っ掛けた吊りワイヤー6、6にのみ該プレ
キャスト型枠2の荷重が負荷される。つまり、図7に示
すように、上方の吊金具1、1に引っ掛けた吊りワイヤ
ー6、6が弛んでしまい、下方の吊金具1、1に引っ掛
けた吊りワイヤー6、6に荷重が集中してしまうので、
下方の吊金具1、1の固定された部位にプレキャスト型
枠2の荷重が集中してしまい、その破損の危険性があっ
た。
However, there are the following problems in the work of causing the above-mentioned conventional precast formwork. That is, since the precast formwork 2 is lifted by independently hooking the hook 5 of the hanging wire 6 to the hanging metal fitting 1 fixed to the precast formwork 2, from the initial stage of lifting up to the time of standing vertically, the suspension fixed to the lower side. The load of the precast mold 2 is applied only to the hanging wires 6 hooked on the metal fitting 1. That is, as shown in FIG. 7, the suspension wires 6, 6 hooked on the upper suspension fittings 1, 1 are loosened, and the load is concentrated on the suspension wires 6, 6 hooked on the lower suspension fittings 1, 1. Because it will
The load of the precast formwork 2 was concentrated on the fixed parts of the lower metal fittings 1 and 1, and there was a risk of damage.

【0006】特に、作業床上等に仮置されたプレキャス
ト型枠2は正確に水平状態が保たれていない場合があ
り、吊り上げ初期には吊金具1の取付けられた一箇所に
プレキャスト型枠2の全荷重が負荷されることになり、
破損が生じる危険性が非常に高かった。したがって、こ
の危険性を回避するためには、吊り上げ作業を慎重に行
わなければならず、プレキャスト型枠2の建て入れ作業
の効率が低くならざるを得なかった。
In particular, the precast formwork 2 temporarily placed on the work floor or the like may not be accurately kept in a horizontal state, and in the initial stage of lifting, the precast formwork 2 is attached to one place where the hanging metal fitting 1 is attached. The full load will be applied,
The risk of breakage was very high. Therefore, in order to avoid this danger, the lifting work must be performed carefully, and the efficiency of the work of installing the precast formwork 2 must be reduced.

【0007】また、上記の引き起こし作業において、そ
の吊り上げ速度が遅い場合には、前記支点となる他の端
部が作業床の床面から離れた際に、その重心の移動にと
もなってプレキャスト型枠2が振り子状に振れてしま
い、当該プレキャスト型枠2の支点とならない下端部が
作業床の床面と接触して破損が生じる場合があった。
Further, in the above-mentioned raising work, when the hoisting speed is slow, when the other end serving as the fulcrum is separated from the floor surface of the work floor, the precast formwork is moved due to the movement of the center of gravity thereof. 2 may swing like a pendulum, and the lower end of the precast mold 2 that does not serve as a fulcrum may come into contact with the floor surface of the work floor, resulting in damage.

【0008】本発明は、上記の課題に鑑みてなされたも
ので、横倒しの状態で仮置されたプレキャストコンクリ
ート型枠を破損を生じることなく安全に引き起こすこと
により、プレキャストコンクリート型枠の建て入れ作業
を効率よく行うことができる吊治具およびこれを用いた
プレキャストコンクリート型枠の吊り上げ方法を提供す
ることを目的としている。
The present invention has been made in view of the above-mentioned problems, and it is possible to safely raise a precast concrete formwork that is temporarily placed in a state of being laid down, without causing damage, so that the precast concrete formwork can be installed. It is an object of the present invention to provide a hoisting jig capable of efficiently performing the above and a hoisting method of a precast concrete formwork using the hoisting jig.

【0009】[0009]

【課題を解決するための手段】本発明の請求項1に係る
プレキャストコンクリート型枠の吊治具は、吊り梁と、
この吊り梁に定着される複数の定着滑車と、これら複数
の定着滑車に卷回されるワイヤーと、このワイヤーに卷
回吊下される複数の動滑車とを具備し、前記ワイヤー
は、前記複数の動滑車を卷回吊下した際に該ワイヤーが
緊張状態となるとともに、前記複数の動滑車が前記複数
の定着滑車に対して相対的に上下動自在となるように配
設され、前記動滑車の下方には前記プレキャストコンク
リート型枠に係合する係合治具が設けられていることを
特徴としている。
A hoisting jig for a precast concrete formwork according to claim 1 of the present invention is a hoisting beam,
A plurality of fixing pulleys fixed to the suspension beam, a wire wound around the plurality of fixing pulleys, and a plurality of moving pulleys suspended around the wire are provided, and the wire includes the plurality of fixing pulleys. The wire is placed in a tensioned state when the moving pulley is hung up and down, and the plurality of moving pulleys are arranged so as to be vertically movable relative to the plurality of fixing pulleys. An engaging jig that engages with the precast concrete formwork is provided below the pulley.

【0010】本発明の請求項2に係るプレキャストコン
クリート型枠の吊り上げ方法は、請求項1に記載のプレ
キャストコンクリート型枠の吊治具を使用し、仮置場に
横倒し状態に仮置された前記プレキャストコンクリート
型枠の一方の端部に前記動滑車に設けられた係合治具を
係合し、前記吊り梁を吊り上げて前記ワイヤーが緊張状
態となるように該プレキャストコンクリート型枠の荷重
を前記係合治具に等しく負荷し、その後該プレキャスト
コンクリート型枠の他方の端部を支点として上方に吊り
上げて起立させるとともに、前記仮置場の床面と該プレ
キャストコンクリート型枠の前記他方の端部の支点とな
らない部位との間に緩衝材を介在させることを特徴とし
ている。
A method of hoisting a precast concrete formwork according to a second aspect of the present invention uses the hoisting jig for the precast concrete formwork according to the first aspect, and the precast is temporarily placed in a laying state in a temporary storage place. The load of the precast concrete formwork is applied to the one end of the concrete formwork by engaging an engaging jig provided on the movable pulley to lift the suspension beam and tension the wire. The precast concrete formwork with the other end of the precast concrete formwork as a fulcrum to lift it upright, and the floor of the temporary storage space and the fulcrum of the other end of the precast concrete formwork. It is characterized in that a cushioning material is interposed between the non-retaining portion.

【0011】[0011]

【作用】前記請求項1の発明では、前記ワイヤーが、前
記複数の動滑車を卷回吊下した際に当該ワイヤーが緊張
状態となるとともに、前記複数の動滑車が前記複数の定
着滑車に対して相対的に上下動自在となるように配設さ
れており、前記複数の動滑車に設けられた係合治具のい
ずれかに荷重が負荷された場合に、前記定着滑車に対し
て当該いずれかの動滑車が下方に移動するとともに、い
ずれか他の動滑車の係合治具が上方に移動し、前記ワイ
ヤーが弛むことなく常に等しい張力が作用した緊張状態
となる。
In the invention of claim 1, when the wire is suspended from the plurality of moving sheaves, the wire is in a tensioned state, and the plurality of moving sheaves are different from the plurality of fixing sheaves. Are arranged so as to be vertically movable relative to each other, and when a load is applied to any one of the engaging jigs provided on the plurality of moving pulleys, the fixing pulley is either One of the movable pulleys moves downward, and the engaging jig of any other movable pulley moves upward, so that the wire is not loosened, and a constant tension is always applied.

【0012】前記請求項2の発明では、仮置場に横倒し
状態に仮置されたプレキャストコンクリート型枠の一方
の端部に前記動滑車に取付けられた係合治具が係合さ
れ、他方の端部を支点として当該プレキャストコンクリ
ート型枠が上方に吊り上げられて起立する。この際に、
前記定着滑車および動滑車に卷回されたワイヤーが弛ま
ずに常に緊張状態となるので、前記係合治具に等しい荷
重が負荷されることにより、当該吊り上げられるプレキ
ャストコンクリート型枠に偏荷重が負荷されることがな
い。
According to the second aspect of the present invention, the engaging jig attached to the movable pulley is engaged with one end of the precast concrete formwork which is temporarily placed in the temporary storage place in a state of being laid sideways, and the other end is engaged. The precast concrete formwork is lifted upward with the section as a fulcrum and stands up. At this time,
Since the wire wound around the fixing pulley and the moving pulley is always in a tension state without slackening, an equal load is applied to the engaging jig, so that an unbalanced load is applied to the hoisted precast concrete formwork. Never be done.

【0013】また、前記仮置場の床面と当該プレキャス
トコンクリート型枠の前記他方の端部の支点とならない
部位との間に緩衝材が介在されており、吊り上げる際
に、プレキャストコンクリートがその重心の移動にとも
なって振り子運動をした場合にも床面と当該プレキャス
トコンクリート型枠との接触を回避することができる。
Further, a cushioning material is interposed between the floor surface of the temporary storage space and a portion which does not serve as a fulcrum of the other end of the precast concrete formwork, and when the precast concrete is lifted up, It is possible to avoid contact between the floor surface and the precast concrete formwork even when a pendulum motion is performed along with the movement.

【0014】[0014]

【実施例】以下、本発明の実施例を添付図面を参照して
詳細に説明する。図1は、本発明のプレキャストコンク
リート型枠の吊治具の第1実施例を示したものである。
なお、図6および図7に示した従来例と共通する部分に
ついては同一符号を付し、その説明を省略する。
Embodiments of the present invention will now be described in detail with reference to the accompanying drawings. FIG. 1 shows a first embodiment of a suspension jig for precast concrete formwork of the present invention.
The same parts as those of the conventional example shown in FIGS. 6 and 7 are designated by the same reference numerals, and the description thereof will be omitted.

【0015】図1に示すように、プレキャストコンクリ
ート型枠の吊治具8は、平面視して略十字型の吊り梁9
と、この吊り梁9の下端部に固定される定滑車10…
(定着滑車)と、定滑車10に卷回される無端状ワイヤ
ー11と、この無端状ワイヤー11に卷回吊下される動
滑車12…とを主体として構成されている。
As shown in FIG. 1, a suspension jig 8 for a precast concrete formwork has a substantially cross-shaped suspension beam 9 in plan view.
And a fixed pulley 10 fixed to the lower end of the suspension beam 9 ...
(Fixing pulley), an endless wire 11 wound around the fixed pulley 10, and a moving pulley 12 suspended around the endless wire 11 are mainly configured.

【0016】前記吊り梁9の各突出端部9a…の上端面
9bには吊り孔13aを有する板材13が溶接固定さ
れ、また、下端面9cには複数の孔14a…が水平方向
に連接して形成された板材14が溶接固定されている。
前記上端面9aに固定された板材13の吊り孔13aに
は、図中二点鎖線で示すように、揚重ワイヤー15…の
一端が連結されている。この揚重ワイヤー15…の他端
は、揚重機のフック(図示せず)に連結できるように吊
り梁9の上方において集結されている。
A plate member 13 having a hanging hole 13a is welded and fixed to an upper end surface 9b of each projecting end portion 9a of the hanging beam 9, and a plurality of holes 14a are horizontally connected to the lower end surface 9c. The plate material 14 thus formed is welded and fixed.
One end of a lifting wire 15 ... Is connected to the hanging hole 13a of the plate member 13 fixed to the upper end surface 9a, as shown by a two-dot chain line in the figure. The other ends of the lifting wires 15 ... Are gathered above the suspension beam 9 so that they can be connected to a hook (not shown) of the lifting machine.

【0017】前記定滑車10は、下方に開口する側面略
コ字状の支持体10aの内部において前記プーリー10
bを回転自在に支持する支持軸10c(水平軸)が架設
されるとともに、支持体10aの天板部10dの上面に
係合フック10eが設けられた構成とされている。一
方、動滑車12は、定滑車10とほぼ同様の支持体12
a、プーリー12b、支持軸12c(水平軸)、および
係合フック12e(係合治具)を具備した構成とされて
いる。
The fixed pulley 10 has the pulley 10 inside a support 10a having a substantially U-shaped side surface that opens downward.
A support shaft 10c (horizontal shaft) that rotatably supports b is installed, and an engaging hook 10e is provided on the upper surface of the top plate portion 10d of the support body 10a. On the other hand, the movable pulley 12 is a support 12 similar to the fixed pulley 10.
a, a pulley 12b, a support shaft 12c (horizontal shaft), and an engaging hook 12e (engaging jig).

【0018】前記無端状ワイヤー11は、後述する動滑
車12のプーリー12aの下弦部を卷回するとともに、
該動滑車12を吊下可能となるように下方に垂れ下がる
長さに設定され、前記定滑車10…のうち隣接する定滑
車10の各プーリー10aの上弦部に卷回されている。
The endless wire 11 winds around a lower chord portion of a pulley 12a of a moving pulley 12 which will be described later, and
The length of the movable pulley 12 is set so that the movable pulley 12 can be suspended downward, and the movable pulley 12 is wound around the upper chord portion of each pulley 10a of the adjacent constant pulley 10 among the constant pulleys 10 ...

【0019】前記定滑車10…は、前記吊り梁9の各板
材14の孔14a…の一つに取付けられたシャックル1
6に前記係合フック10eを引掛けることにより吊り梁
9に連結されている。そして、このシャックル16を孔
14a…に取付ける位置を変えることにより、吊り上げ
るプレキャスト型枠の幅に合わせて定滑車10の位置を
適宜変更できるようになっている。
The fixed pulleys 10 ... Are attached to one of the holes 14a of each plate member 14 of the suspension beam 9 and are attached to the shackle 1.
It is connected to the suspension beam 9 by hooking the engaging hook 10e on the shaft 6. The position of the fixed pulley 10 can be appropriately changed according to the width of the precast frame to be lifted by changing the position where the shackle 16 is attached to the holes 14a.

【0020】前記無端状ワイヤー11は、上記のように
固定された定滑車10…のうち、隣接する定滑車10の
各プーリー10aの上弦部に卷回されるとともに、この
隣接する定滑車間の中間部において前記動滑車12のプ
ーリー12aの下弦部に卷回されており、この状態で動
滑車12は、その係合フック12eを下方向けて無端状
ワイヤー11に吊下げられている。
The endless wire 11 is wound around the upper chords of the pulleys 10a of the adjacent fixed pulleys 10 among the fixed pulleys 10 fixed as described above, and between the adjacent fixed pulleys. In the intermediate portion, the pulley 12a of the moving pulley 12 is wound around the lower chord portion, and in this state, the moving pulley 12 is suspended from the endless wire 11 with its engaging hook 12e facing downward.

【0021】そして、当該無端状ワイヤー11に吊下さ
れた動滑車12…の各係合フック12eのいずれかに荷
重が負荷された場合に、前記定滑車10…に対して係合
フックに荷重の負荷された動滑車が下方に移動するとと
もに、係合フックに荷重の負荷されない他の動滑車が上
方に移動し、無端状ワイヤー11が弛むことなく常に等
しい張力が作用した緊張状態となるように卷回されてい
る。
When a load is applied to any of the engaging hooks 12e of the movable pulleys 12 ... Suspended on the endless wire 11, the engaging hooks are loaded against the constant pulley 10. The moving pulley under load moves downward, and the other moving pulley whose load is not loaded on the engaging hook moves upward, so that the endless wire 11 does not loosen and is in a tension state in which equal tension is always applied. Has been wound around.

【0022】次に、上記構成のプレキャストコンクリー
ト型枠の吊治具8による略正方形断面を有するプレキャ
スト型枠の引き起こし作業について説明する。まず、作
業床F(仮置場)に横倒し状態に仮置されたプレキャス
ト型枠2(図2参照)の水平方向に対向する側壁部2a
の一端部にそれぞれ上下に二箇所ずつ所定の吊金具17
を固定し、各吊金具の上端部に取付けた丸環17aにシ
ャックル18を取付ける。
Next, the work of raising the precast formwork having a substantially square cross section by the hanging jig 8 of the precast concrete formwork having the above-mentioned structure will be described. First, a side wall portion 2a of the precast formwork 2 (see FIG. 2) that is temporarily placed on the work floor F (temporary storage place) in a horizontal state and that faces the horizontal direction.
Predetermined suspending metal fittings 17 are provided at one end of the
Is fixed, and the shackle 18 is attached to the circular ring 17a attached to the upper end of each suspension fitting.

【0023】次に、予め揚重機により吊治具8を吊り上
げ、前記シャックル18に吊治具8の各動滑車12に設
けた係合フック12eを引っ掛ける。そして、さらに吊
治具8を吊り上げて無端状ワイヤー11が緊張状態とな
るように当該プレキャスト型枠2の荷重を係合フック1
2eに等しく負荷し、その後、図2に示すように、当該
プレキャスト型枠2を吊金具17を取付けない端部(図
示せず)を支点として吊り上げる。この際に、図3に示
すように、作業床Fと当プレキャスト型枠2の支点とな
らない端部との間にゴム製の緩衝材19を配置し、当該
プレキャスト型枠2を直立状態に起立させた後に(図4
参照)、さらに上方に吊り上げ、所定の立設位置に搬入
する。
Next, the hoisting jig 8 is previously hoisted by a lifting machine, and the shackle 18 is hooked with an engaging hook 12e provided on each moving pulley 12 of the hoisting jig 8. Then, the hanging jig 8 is further lifted, and the load of the precast mold 2 is applied so that the endless wire 11 is in a tension state.
2e is applied equally, and thereafter, as shown in FIG. 2, the precast mold 2 is hoisted with an end portion (not shown) to which the hanging metal fitting 17 is not attached as a fulcrum. At this time, as shown in FIG. 3, a rubber cushioning material 19 is arranged between the work floor F and the end of the precast mold 2 which does not serve as a fulcrum, and the precast mold 2 is erected in an upright state. After making (Fig. 4
(See), and hoist it further upward, and carry it to a predetermined standing position.

【0024】上記構成のプレキャストコンクリートの吊
治具8では、揚重機(図示せず)でプレキャスト型枠2
を引き起こす際に、前記動滑車12の前記係合フック1
2eの係合位置によらず、前記定滑車10…および動滑
車12…に卷回された無端状ワイヤー11が弛まずに常
に緊張状態となり、常に各係合フック12eにプレキャ
スト型枠2の荷重が等しく負荷されることにより、当該
吊り上げられるプレキャスト型枠2に偏荷重を負荷せず
に引き起こし作業がなされる。
In the hoisting jig 8 of precast concrete having the above-mentioned structure, the precast formwork 2 is lifted by a lifting machine (not shown).
The engaging hook 1 of the movable pulley 12 when
Regardless of the engagement position of 2e, the endless wire 11 wound around the fixed pulleys 10 ... And the moving pulleys 12 ... does not slacken and is always in a tensioned state, and the load of the precast mold 2 is always applied to each engagement hook 12e. Are equally loaded, an unbalanced load is applied to the precast formwork 2 to be lifted and the work is performed.

【0025】また、作業床の床面Fとプレキャスト型枠
2の支点とならない下端部との間に緩衝材19が配設さ
れているので、プレキャスト型枠を吊り上げるにつれて
前記支点となる端部が作業床Fと離れた際に、当該プレ
キャスト型枠2が振り子運動をした場合にも、当該プレ
キャスト型枠2の支点とならない下端部と該作業床Fと
の接触が回避される。
Further, since the cushioning material 19 is disposed between the floor surface F of the work floor and the lower end of the precast formwork 2 which does not serve as a fulcrum, as the precast formwork is lifted, the end serving as the fulcrum is formed. Even when the precast mold 2 makes a pendulum motion when it is separated from the work floor F, contact between the work floor F and the lower end which is not the fulcrum of the precast mold 2 is avoided.

【0026】このように、上記実施例のプレキャストコ
ンクリート型枠の吊治具8によれば、横倒し状態に仮置
されたプレキャスト型枠2の一方の端部に前記各動滑車
12に設けられた係合フック12eを係合し、該プレキ
ャスト型枠2の他方の端部を支点として上方に吊り上げ
ることによって、当該吊り上げられるプレキャスト型枠
2に偏荷重を負荷せずに起立させることができる。した
がって、仮置場に横倒し状態で仮置されたプレキャスト
型枠2を損傷を生じることなく安全に引き起こすことが
でき、その後の建て入れ作業を効率よく行うことができ
る。
As described above, according to the hanging jig 8 of the precast concrete formwork of the above-mentioned embodiment, the movable pulley 12 is provided at one end of the precast formwork 2 which is temporarily placed in the state of being laid down. By engaging the engaging hook 12e and hoisting upward with the other end of the precast mold 2 as a fulcrum, the precast mold 2 to be hoisted can be erected without applying an unbalanced load. Therefore, the precast formwork 2 temporarily placed in the temporary storage place in a state of being laid down can be safely raised without damage, and the subsequent erection work can be efficiently performed.

【0027】また、プレキャスト型枠2の前記支点とな
らない下端部と作業床Fとの間に緩衝材19を配設させ
るようにしたので、プレキャスト型枠2を吊治具8によ
って起立せしめる際に、当該プレキャスト型枠2がその
重心の移動にともなう振り子運動をした場合にも、その
下端と前記作業床Fとの接触を回避してその損傷を防ぐ
ことができる。
Further, since the cushioning material 19 is arranged between the lower end of the precast mold 2 which does not serve as the fulcrum and the working floor F, when the precast mold 2 is erected by the hanging jig 8. Even when the precast mold 2 makes a pendulum motion due to the movement of its center of gravity, it is possible to avoid contact between the lower end of the precast mold 2 and the work floor F and prevent damage.

【0028】なお、上記の実施例においては、断面形状
が矩形のプレキャストコンクリート型枠2を対象として
定滑車10、動滑車12の数をそれぞれ4基ずつ使用す
るとともに、平面視略十字型の吊り梁9を使用した構成
としたが、吊り上げるプレキャストコンクリート型枠の
形状によって、これら定滑車10、動滑車12の数、お
よび吊り梁9の形状等を適宜変更できることは言うまで
もない。
In the above embodiment, the precast concrete formwork 2 having a rectangular cross section is used with four fixed pulleys 10 and four movable pulleys 12, and a substantially cross-shaped suspension in plan view is used. Although the beam 9 is used, it goes without saying that the number of the fixed pulleys 10, the moving pulleys 12, the shape of the hanging beam 9 and the like can be appropriately changed depending on the shape of the precast concrete formwork to be lifted.

【0029】図5は、本発明のプレキャストコンクリー
ト型枠の吊治具の第2実施例を示したものである。図に
おいて、上記第1実施例と共通する部分については同一
符号を付し、その説明を省略する。この第2実施例で
は、図5に示すように、上記第1実施例における無端状
ワイヤー11に変えて、その両端部20aが円弧状に仕
上げられたワイヤー20が使用されており、この両端部
20aが直接吊り梁9の下端面9cに固定された一つの
板材14’にシャックル16を介して連結され、残り三
つの板材14のそれぞれに定滑車10…がシャックル1
6を介して連結された構成とされている。
FIG. 5 shows a second embodiment of a hoisting jig for a precast concrete formwork according to the present invention. In the figure, the same parts as those of the first embodiment are designated by the same reference numerals, and the description thereof will be omitted. In the second embodiment, as shown in FIG. 5, instead of the endless wire 11 in the first embodiment, a wire 20 whose both ends 20a are finished in an arc shape is used. 20 a is directly connected to one plate member 14 ′ fixed to the lower end surface 9 c of the hanging beam 9 via a shackle 16, and a fixed pulley 10 is connected to each of the remaining three plate members 14 by a shackle 1.
It is configured to be connected via 6.

【0030】そして、この構成のもと、上記第1実施例
と同様に、横倒し状態に仮置されたプレキャスト型枠2
の一方の端部に前記各動滑車12に設けられた係合フッ
ク12eを係合し、該プレキャスト型枠2の他方の端部
を支点として上方に吊り上げることによって、当該吊り
上げられるプレキャスト型枠2に偏荷重を負荷せずに起
立させることができる。したがって、仮置場に横倒し状
態で仮置されたプレキャスト型枠2を損傷を生じること
なく安全に引き起こすことができ、その後の建て入れ作
業を効率よく行うことができる。
Under this structure, as in the first embodiment, the precast mold 2 temporarily placed in the sideways state.
By engaging the engaging hooks 12e provided on each of the movable pulleys 12 with one end of the precast mold 2 and hoisting the precast mold 2 upward with the other end of the precast mold 2 as a fulcrum, the precast mold 2 is lifted. It is possible to stand without imposing an unbalanced load on. Therefore, the precast formwork 2 temporarily placed in the temporary storage place in a state of being laid down can be safely raised without damage, and the subsequent erection work can be efficiently performed.

【0031】[0031]

【発明の効果】本発明に係るプレキャストコンクリート
型枠の吊治具およびプレキャストコンクリート型枠の吊
り上げ方法によれば、以下の効果を奏することができ
る。請求項1に記載のプレキャストコンクリート型枠の
吊治具によれば、前記複数の動滑車の係合治具のいずれ
かに荷重が負荷された場合に、前記定着滑車に対して当
該いずれかの動滑車が下方に移動するとともに、いずれ
か他の動滑車が上方に移動し、前記ワイヤーが弛むこと
なく常に等しい張力が作用した緊張状態となるので、係
合治具に負荷される荷重が該係合治具の係合位置にかか
わらず等荷重となる。したがって、プレキャストコンク
リート型枠を吊り上げて起立させる際に、当該プレキャ
ストコンクリート型枠に偏荷重を負荷せずに引き起こす
ことができる。
According to the hoisting jig for precast concrete formwork and the method for hoisting precast concrete formwork according to the present invention, the following effects can be obtained. According to the precast concrete formwork suspension jig of claim 1, when a load is applied to any of the engaging jigs of the plurality of moving pulleys, the suspension jig of any one of the fixing pulleys is used. As the moving pulley moves downward, any other moving pulley moves upward, and the wire is in a tension state in which the same tension is always applied without slackening, so that the load applied to the engaging jig is The load is equal regardless of the engaging position of the engaging jig. Therefore, when the precast concrete formwork is lifted to stand up, the precast concrete formwork can be caused without applying an unbalanced load.

【0032】請求項2に記載のプレキャストコンクリー
ト型枠の吊り上げ方法によれば、横倒し状態に仮置され
たプレキャストコンクリート型枠の一方の端部に前記動
滑車に取付けられた係合治具を係合し、他方の端部を支
点として上方に吊り上げることにより、プレキャストコ
ンクリート型枠に偏荷重を負荷せずに該プレキャストコ
ンクリート引き起こすことができる。したがって、横倒
しの状態で仮置されたプレキャストコンクリート型枠を
損傷を生ずることなく安全に引き起こし、プレキャスト
コンクリート型枠の建て入れ作業を効率よく行うことが
できる。
According to the method of hoisting the precast concrete formwork of claim 2, the engaging jig attached to the movable pulley is engaged with one end of the precast concrete formwork temporarily placed in a lying state. In this case, the precast concrete form can be raised without applying an unbalanced load to the precast concrete form by lifting the other end with the other end as a fulcrum. Therefore, the precast concrete formwork temporarily placed in the state of being laid down can be safely brought up without damage, and the precast concrete formwork can be efficiently installed.

【0033】また、プレキャストコンクリート型枠の前
記支点とならない下端部と仮置場との間に緩衝材を介在
させるようにしたので、当該プレキャストコンクリート
型枠を吊り上げる場合に、該プレキャストコンクリート
型枠がその重心の移動に伴う振り子運動をした場合に
も、その下端部と前記仮置場の床面との接触を回避する
ことができ、プレキャストコンクリートの損傷を防ぐこ
とができる。
Further, since the cushioning material is interposed between the lower end portion of the precast concrete formwork which is not the fulcrum and the temporary storage space, when the precast concrete formwork is lifted, the precast concrete formwork Even when a pendulum movement is performed due to the movement of the center of gravity, it is possible to avoid contact between the lower end of the pendulum and the floor surface of the temporary storage space, and prevent damage to the precast concrete.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明のプレキャストコンクリート型枠の吊治
具の第1実施例を示した要部側面図である。
FIG. 1 is a side view of essential parts showing a first embodiment of a hoisting jig for a precast concrete formwork of the present invention.

【図2】同実施例のプレキャストコンクリート型枠の吊
治具を使用してプレキャストコンクリート型枠の吊り上
げを行っている状況を示す斜視図である。
FIG. 2 is a perspective view showing a situation in which the precast concrete formwork is hoisted using the hanging jig for the precast concrete formwork of the same embodiment.

【図3】同実施例のプレキャストコンクリート型枠の吊
治具を使用したプレキャストコンクリート型枠の吊り上
げを行っている状況を示す側面図である。
FIG. 3 is a side view showing a situation where the precast concrete formwork is being hoisted using the precast concrete formwork suspension jig of the embodiment.

【図4】同実施例のプレキャストコンクリート型枠の吊
治具を使用したプレキャストコンクリート型枠の吊り上
げを行っている状況を示す斜視図である。
FIG. 4 is a perspective view showing a situation in which a precast concrete formwork is hoisted using the precast concrete formwork suspension jig of the embodiment.

【図5】本発明のプレキャストコンクリート型枠の吊治
具の第2実施例を示した要部側面図である。
FIG. 5 is a side view of essential parts showing a second embodiment of the hanging jig for precast concrete formwork of the present invention.

【図6】従来のプレキャストコンクリート型枠の吊治具
を示した要部斜視図である。
FIG. 6 is a perspective view of an essential part showing a conventional hanging jig for a precast concrete formwork.

【図7】同従来の吊治具を使用してプレキャストコンク
リート型枠の吊り上げを行っている状況を示した要部斜
視図である。
FIG. 7 is a perspective view of a main part showing a situation in which a precast concrete formwork is hoisted using the conventional hoisting jig.

【符号の説明】[Explanation of symbols]

2 プレキャストコンクリート型枠 8 プレキャストコンクリート型枠の吊金具 9 吊り梁 10 定着滑車 11 ワイヤー 12 動滑車 12e 係合治具 19 緩衝材 F 仮置場 2 Precast concrete formwork 8 Precast concrete formwork suspension metal fittings 9 Suspended beam 10 Fixing pulley 11 Wire 12 Moving pulley 12e Engaging jig 19 Buffer material F Temporary storage

Claims (2)

【特許請求の範囲】[Claims] 【請求項1】 プレキャストコンクリート型枠を揚重吊
下する際に使用するプレキャストコンクリート型枠の吊
治具であって、吊り梁と、この吊り梁に定着される複数
の定着滑車と、これら複数の定着滑車に卷回されるワイ
ヤーと、このワイヤーに卷回吊下される複数の動滑車と
を具備し、前記ワイヤーは、前記複数の動滑車を卷回吊
下した際に当該ワイヤーが緊張状態となるとともに、前
記複数の動滑車が前記複数の定着滑車に対して相対的に
上下動自在となるように配設され、前記動滑車の下方に
は前記プレキャストコンクリート型枠に係合する係合治
具が設けられていることを特徴とするプレキャストコン
クリート型枠の吊治具。
1. A hoisting jig for a precast concrete formwork used when hoisting a precast concrete formwork, the hoisting beam, a plurality of fixing pulleys fixed to the hoisting beam, and a plurality of these pulleys. A wire wound around the fixing pulley and a plurality of moving pulleys suspended around the wire, and the wire is tensioned when the plurality of moving pulleys are suspended around the wire. The plurality of moving pulleys are arranged so as to be vertically movable relative to the plurality of fixing pulleys, and are engaged with the precast concrete formwork below the moving pulleys. A hoisting jig for precast concrete formwork, which is provided with a fitting jig.
【請求項2】 請求項1に記載のプレキャストコンクリ
ート型枠の吊治具を使用したプレキャストコンクリート
型枠の吊り上げ方法であって、仮置場に横倒し状態に仮
置された前記プレキャストコンクリート型枠の一方の端
部に前記動滑車に設けられた係合治具を係合し、前記吊
り梁を吊り上げて前記ワイヤーが緊張状態となるように
該プレキャストコンクリート型枠の荷重を前記係合治具
に等しく負荷し、その後該プレキャストコンクリート型
枠の他方の端部を支点として上方に吊り上げて起立させ
るとともに、前記仮置場の床面と該プレキャストコンク
リート型枠の前記他方の端部の支点とならない部位との
間に緩衝材を介在させることを特徴とするプレキャスト
コンクリート型枠の吊り上げ方法。
2. A method of hoisting a precast concrete formwork using the hoisting jig for a precast concrete formwork according to claim 1, wherein one of the precast concrete formwork is temporarily laid down in a temporary yard. The engaging jig provided on the movable pulley is engaged with the end portion of the precast concrete formwork so that the wire is tensioned by lifting the suspension beam so that the load is equal to the engaging jig. With loading, and then lifted up with the other end of the precast concrete formwork as a fulcrum to stand up, and between the floor surface of the temporary storage and the part that does not serve as a fulcrum of the other end of the precast concrete formwork. A method of hoisting a precast concrete formwork, characterized in that a cushioning material is interposed therebetween.
JP8893093A 1993-04-15 1993-04-15 Hoisting jig for precast concrete mold and method for hoisting precast concrete mold Pending JPH06298487A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP8893093A JPH06298487A (en) 1993-04-15 1993-04-15 Hoisting jig for precast concrete mold and method for hoisting precast concrete mold

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP8893093A JPH06298487A (en) 1993-04-15 1993-04-15 Hoisting jig for precast concrete mold and method for hoisting precast concrete mold

Publications (1)

Publication Number Publication Date
JPH06298487A true JPH06298487A (en) 1994-10-25

Family

ID=13956625

Family Applications (1)

Application Number Title Priority Date Filing Date
JP8893093A Pending JPH06298487A (en) 1993-04-15 1993-04-15 Hoisting jig for precast concrete mold and method for hoisting precast concrete mold

Country Status (1)

Country Link
JP (1) JPH06298487A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2012180195A (en) * 2011-03-02 2012-09-20 Sumitomo Heavy Industries Engineering-Service Co Ltd Hoisting accessory for crane
JP2017077961A (en) * 2015-10-22 2017-04-27 住友重機械搬送システム株式会社 Bridge type crane
JP2019167762A (en) * 2018-03-26 2019-10-03 前田建設工業株式会社 Column reinforcement hanging jig
JP2021519249A (en) * 2020-04-16 2021-08-10 漢丁 林 Monitoring / detection device and crane that display the swing angle of the hook in real time

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2012180195A (en) * 2011-03-02 2012-09-20 Sumitomo Heavy Industries Engineering-Service Co Ltd Hoisting accessory for crane
JP2017077961A (en) * 2015-10-22 2017-04-27 住友重機械搬送システム株式会社 Bridge type crane
JP2019167762A (en) * 2018-03-26 2019-10-03 前田建設工業株式会社 Column reinforcement hanging jig
JP2021519249A (en) * 2020-04-16 2021-08-10 漢丁 林 Monitoring / detection device and crane that display the swing angle of the hook in real time

Similar Documents

Publication Publication Date Title
JP3440422B2 (en) Bridge construction method and bridge construction device
JPH11181725A (en) Method for constructing horizontal beam of main tower made of concrete
US5241797A (en) Elevated water tank floor and construction thereof
JPH06298487A (en) Hoisting jig for precast concrete mold and method for hoisting precast concrete mold
JPH09302919A (en) Transfer platform for columnar body
JPH06167089A (en) Facing of lower surface of aerial framing body
JP2002302382A (en) Vertically suspending method of long size material
AU2004209463A1 (en) Hoist for construction material
JPH06144774A (en) Hoisting device for pc board
JPH1181246A (en) Tension jack moving device for precast concrete block construction method
JPH11147690A (en) Low head space reinforcing bar building-in device
JP3532161B2 (en) Tower construction machine and tower construction method
KR200159796Y1 (en) Elevating device of form for underground building construction work in the underground
JPH0683684U (en) Hanging jig for precast concrete formwork
CN114263115B (en) Bridge deck construction device and method
CN217997841U (en) Cantilever casting continuous beam hanging basket dismantling construction device
CN117513764B (en) Sliding method with installation position lower than sliding rail
JPH1088786A (en) Scaffold for columnar structure
JPH062437A (en) Device for building steel structure cage
JP2023058859A (en) slide form
JP2001302171A (en) Hoisting jig
JP2722264B2 (en) Construction method and construction device for trussed pillar
JPH11323838A (en) Construction method of bridge
JP3224152B2 (en) Construction method of cross beam in concrete building
JPH10140839A (en) Device for vertically hoisting form material and pipe support

Legal Events

Date Code Title Description
A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 20011120