JPH06266413A - Method and system for production management - Google Patents

Method and system for production management

Info

Publication number
JPH06266413A
JPH06266413A JP5171593A JP5171593A JPH06266413A JP H06266413 A JPH06266413 A JP H06266413A JP 5171593 A JP5171593 A JP 5171593A JP 5171593 A JP5171593 A JP 5171593A JP H06266413 A JPH06266413 A JP H06266413A
Authority
JP
Japan
Prior art keywords
lot
schedule
priority
lots
scheduler
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP5171593A
Other languages
Japanese (ja)
Other versions
JP3283951B2 (en
Inventor
Masahiro Yoshizawa
正浩 吉沢
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nippon Telegraph and Telephone Corp
Original Assignee
Nippon Telegraph and Telephone Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nippon Telegraph and Telephone Corp filed Critical Nippon Telegraph and Telephone Corp
Priority to JP5171593A priority Critical patent/JP3283951B2/en
Priority to US08/058,175 priority patent/US5442561A/en
Publication of JPH06266413A publication Critical patent/JPH06266413A/en
Application granted granted Critical
Publication of JP3283951B2 publication Critical patent/JP3283951B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/02Total factory control, e.g. smart factories, flexible manufacturing systems [FMS] or integrated manufacturing systems [IMS]
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/30Computing systems specially adapted for manufacturing

Landscapes

  • Control By Computers (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)
  • Multi-Process Working Machines And Systems (AREA)
  • General Factory Administration (AREA)

Abstract

PURPOSE:To shorten a processing time at the time of mapping out a processing plan of a manufacture line, in which lots whose priority or importance is different from each other are mixed, to reduce the number of use memories, and to execute advance control of the line, a completion date prediction of the low whose priority and importance are high, and advance control of the lost whose priority is low. CONSTITUTION:The system is constituted of an off-line scheduler 2 for mapping out a processing plan extending over a long period to the time of delivery with respect to a low whose priority or importance is high in the manufacturing lots by a scheduler, and an on-line scheduler 1 for mapping out a processing plan of a short period with respect to all the lots.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明は、LSI等の半導体部
品、衣料品、自動車等の各種工業製品の製造を管理する
システムに関するものである。ここでいう、製造の管理
は、複数の品種からなる製品の、それぞれの処理工程
や緊急度に応じて製造順序を決めるスケジューリング、
製造の進捗状況の監視、製造時の処理データの取
得、を含むものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a system for managing the production of semiconductor parts such as LSI, clothing, and various industrial products such as automobiles. Manufacturing management here means scheduling that determines the manufacturing order of products of multiple types according to their processing steps and urgency,
This includes monitoring the progress of manufacturing and acquiring process data during manufacturing.

【0002】[0002]

【従来の技術】LSIの製造工程を例にとって以下に従
来の生産管理システムを説明する。図9は、LSIの製
造手順の概略を説明した図である。単結晶ウェハの上
に、酸化膜/窒化膜等の絶縁膜の膜付け、熱処理による
拡散、フォトリソグラフィによるパタンの形成、蒸着や
スパッタによる膜付け、エッチング、イオン注入による
不純物の導入、スクライブ(分割)、マウント、ボンデ
ィング等の技術が、少なくとも1回、多いものは何十回
と用いられながら、半導体基板上に機能が作り込まれ、
LSIの製造が行われる。また、それぞれの技術は、さ
らにいくつかの処理に細分化される。例えば、フォトリ
ソグラフィ技術は、図9の左に示したように、(a)感
光剤であるレジストの塗布、(b)マスク合わせ/露
光、(c)現像によるパタン形成、(d)エッチングに
よる加工、等の処理から成り、このような処理単位を通
常『工程』と呼ぶ。これら工程を数百回繰り返し行うこ
とで、LSIは作られる。この製造工程の手順の一覧
が、図10に示すような『工程表』であり、処理順に、
少なくとも使用装置、処理条件(レシピ)を含む処理内
容が記述してある。
2. Description of the Related Art A conventional production management system will be described below by taking an LSI manufacturing process as an example. FIG. 9 is a diagram for explaining the outline of the manufacturing procedure of the LSI. Depositing an insulating film such as an oxide film / nitride film on a single crystal wafer, diffusion by heat treatment, pattern formation by photolithography, film deposition by vapor deposition or sputtering, etching, introduction of impurities by ion implantation, scribing (splitting) ), Mounting, bonding and other techniques are used at least once, and many are used dozens of times, while the function is built on the semiconductor substrate,
The LSI is manufactured. In addition, each technique is further subdivided into several processes. For example, in the photolithography technique, as shown in the left side of FIG. 9, (a) application of a resist as a photosensitizer, (b) mask alignment / exposure, (c) pattern formation by development, and (d) processing by etching. , Etc., and such a processing unit is usually called a “process”. An LSI is manufactured by repeating these steps several hundred times. A list of procedures of this manufacturing process is a “process chart” as shown in FIG.
The processing contents including at least the used device and the processing condition (recipe) are described.

【0003】この工程表は、ロット(処理単位:通常は
カセット単位、枚葉処理では1枚単位)ごとに指定し、
この工程表通りに順番に処理を行うことで、LSIの製
造が可能である。ここで特徴的なことは、この工程の中
で、同じ装置が、処理条件を変えて何回も用いられるこ
とである。また、異なる品種のものを製造する場合に
は、同じ工程でも異なる処理条件で製造が行われる。こ
こでいう処理条件(レシピ)は、熱処理を行う温度やガ
ス流量、露光時の使用マスク等の製造条件だけでなく、
寸法測定の位置等の検査条件をも含むものである。この
ように、多くの要素の順列組合せを制御対象とするた
め、複雑なラインとなっている。
This process chart is designated for each lot (processing unit: usually cassette unit, single-sheet processing unit),
The LSI can be manufactured by sequentially performing the processing according to the process chart. What is characteristic here is that the same apparatus is used many times under different process conditions in this step. When different types of products are manufactured, the same process is performed under different processing conditions. The processing conditions (recipe) here are not only the manufacturing conditions such as the temperature for heat treatment, the gas flow rate, and the mask used during exposure, but also
It also includes inspection conditions such as the position of dimension measurement. In this way, since a permutation combination of many elements is controlled, the line is complicated.

【0004】近年、LSIに限らず、製品の多様化、顧
客ニーズへの対応の即応化が要望されている。これに伴
い、LSI生産管理も、搬送の自動化による生産効率の
向上から、納期管理・TAT制御への需要が高まってい
る。製品の多様化に伴って、一つの製造ラインで、何品
種もの製品が生産されるようになった。また、これらの
製品は、その生産量が異なるだけでなく、品種ごとに重
要度、処理の優先度が異なる。ここで、重要度はマスク
等の設計コスト、特殊な工程を要する等の製造コスト等
の付加価値に依存し、通常ロットの投入時に決まる。一
方、優先度は、同じ製造装置で処理待ちとなった場合
に、どちらを先に処理させるかを示すもので、納期まで
の余裕できまる。このため、当初は納期まで十分な余裕
が見込まれたので優先度の低かったロットが、途中で予
定より遅れたので優先度を上げる必要が生じたり、逆
に、途中で余裕ができ優先度を下げる場合も生じる。
In recent years, not only LSIs but also diversification of products and immediate response to customer needs have been demanded. Along with this, in LSI production management as well, demand for delivery date management / TAT control is increasing due to improvement in production efficiency due to automation of transportation. With the diversification of products, many kinds of products have been produced on one production line. Further, these products are not only different in the amount of production, but also different in importance and processing priority for each kind. Here, the degree of importance depends on the added value such as the design cost of the mask or the like, the manufacturing cost of requiring a special process, etc., and is usually determined when the lot is put in. On the other hand, the priority indicates which is to be processed first when the same manufacturing apparatus waits for processing, and the delivery time can be afforded. For this reason, a lot with low priority was initially expected because there was a sufficient margin until the delivery date, so it was necessary to raise the priority because it was late on schedule in the middle, or conversely, there was room in the middle and priority was given. It may also be lowered.

【0005】また、処理実行データを取得し、モニタす
ることは、製品の不良を未然に防ぐだけでなく、故障時
の原因解析にも役立つ。従って、検査データを含めた処
理データを取得することが必須となる。ここで、この処
理データは、装置から自動収集されるのが望ましいが、
必ずしも自動である必要はない。この装置データ・検査
データの収集にあたっては、同一装置が工程内で何回も
使用されるので、そのデータが、どのロットのどの工程
(工程表の何番目の工程)のデータであるかを示すキー
(ワード)情報を付加してデータベースへ格納する。こ
のキー情報としては、スケジューリングにより作成した
処理予定を用いるのが簡便である。すなわち、ロット処
理時にバーコードリーダにより、そのロットを認識さ
せ、その処理予定をネットワーク通信により受信し、処
理データと合わせてデータベースへ格納する方法であ
る。または、磁気カード等をロットと一緒に搬送し、そ
のカードを読ませて、キー情報を読みだし、処理データ
と合わせてデータベースへ格納する方法がある。これら
は、いずれも、ロットの進捗管理を兼ねることができる
という特徴がある。このような、ライン管理の手順とし
ては、図11のようなものがある。スケジュール結果
を、予定表の形でライン内に配置した計算機に配り、作
業者はこの予定表による作業指示に基づいて処理を実行
する。その処理データ等の実行記録を、製造・検査装置
から直接送信するオンラインデータ収集、またはオペレ
ータが端末から行うオフラインの進行通知により、スケ
ジューラへフィードバックして進捗を管理するととも
に、次のスケジュール時にその進捗状況を反映させる。
Further, acquiring and monitoring the process execution data is useful not only for preventing product defects, but also for analyzing the cause at the time of failure. Therefore, it is essential to acquire the processing data including the inspection data. Here, it is desirable that this processed data be automatically collected from the device,
It does not necessarily have to be automatic. When collecting this equipment data / inspection data, the same equipment is used many times in the process, so the data indicates which process of which lot (the number of process in the process chart). Key (word) information is added and stored in the database. As this key information, it is convenient to use a processing schedule created by scheduling. That is, it is a method of recognizing the lot by a bar code reader at the time of lot processing, receiving the processing schedule through network communication, and storing it in a database together with the processing data. Alternatively, there is a method in which a magnetic card or the like is transported together with the lot, the card is read, the key information is read, and the processed data is stored in the database. All of these have the feature that they can also serve as lot progress management. Such a line management procedure is shown in FIG. The schedule result is distributed to the computers arranged in the line in the form of a schedule, and the worker executes the process based on the work instruction according to the schedule. Execution records such as processing data are sent directly from the manufacturing / inspection equipment to collect online data, or the operator notifies the progress of offline from the terminal to feed back to the scheduler to manage the progress, and to make progress at the next schedule. Reflect the situation.

【0006】同一品種のものが大量に生産される量産ラ
インでは、各装置に処理待ちで溜まっている滞留ロット
の中から、古いものを順番に処理していく(ファースト
イン・ファーストアウト)山積み方式や、到着ロットの
過不足を目にみえるように表示する看板方式等が生産方
法として使用されることが多い。順次、処理した結果
が、どのロットのどの工程のものかの情報を、その場
で、キー入力あるいはバーコードによる読み取り等で付
加して、データをデータベースに格納する。しかし、こ
の場合、個々のロットの各工程の処理予定は把握出来な
いので、納期管理、TAT(ロットが完成するまでにか
かる日数)を制御するのは困難である。
In a mass production line where a large number of products of the same type are produced, old ones are sequentially processed (first-in first-out) from the accumulated lots that are accumulated in each device waiting to be processed. In addition, a signboard method that visually displays the arrival lot excess or deficiency is often used as a production method. Sequentially, information on which process of which lot belongs to which lot is added on the spot by key input or reading with a barcode, and the data is stored in the database. However, in this case, since it is not possible to grasp the processing schedule of each process of each lot, it is difficult to control delivery date management and TAT (the number of days until the lot is completed).

【0007】一方、ASICLSIの生産ラインでは、
処理の優先度、重要度の異なる何品種ものロットが存在
する。ASICの中でも、フルカスタムやスタンダード
セルを用いたLSIは、基板工程から専用のマスクパタ
ンを用いる必要があるので、その重要度は高い。しか
し、ゲートアレイLSIでは、基板は共通なので、ゲー
トアレイの基板作成段階ではその重要度は低いが、専用
のマスクパタンを用いる配線工程に入ると、重要度があ
がる。一方、優先度は、同じ装置で処理待ちとなった場
合に、どちらを先に処理させるかを示すもので、納期ま
での余裕で決まる。このため、当初は納期まで十分な余
裕が見込まれたので優先度の低かったロットが、途中で
予定より遅れたので優先度を上げる必要が生じる。逆
に、途中で余裕ができ、優先度を下げる場合もある。こ
のように、優先度は、ロットの処理が進捗するにつれて
変わる。
On the other hand, in the ASIC LSI production line,
There are lots of varieties with different processing priorities and importance. Among ASICs, LSIs using full-custom or standard cells are highly important because they require a dedicated mask pattern from the substrate process. However, in the gate array LSI, since the substrate is common, the importance thereof is low at the stage of forming the gate array substrate, but becomes higher when the wiring process using the dedicated mask pattern is started. On the other hand, the priority indicates which is processed first when the same device waits for processing, and is determined by a margin until the delivery date. For this reason, it is necessary to raise the priority of a lot that was low in priority because it had a sufficient margin until the delivery date at the beginning and was delayed from the schedule in the middle. On the contrary, there is a case where there is a margin on the way and the priority is lowered. Thus, the priority changes as the lot processing progresses.

【0008】このような製品が投入から完成するまでの
時間(TAT)は、ライン内に投入されているロット数
によって変わる。また、優先度の異なる製品が混在する
と、優先度の低い製品は、優先度の高いもののために処
理が遅らされる。このため、従来行われているように、
個々のロットに対して、装置に仕掛けられているロット
数や処理時間から進捗を予測して納期に間に合うかとい
った判断だけからは、正確な完成日は予測できない。そ
こで、優先度や重要度の高いロット(以下では進捗制御
ロットと称する)の完成日を制御して納期に遅れないよ
うにするため、なおかつデータ取得のためのキー情報を
作成するためには、ロットの進捗を監視して、日に一度
程度の定期スケジューリングと装置のトラブルやロット
進捗遅れ等に伴う非定期のスケジューリングを実行して
処理予定を逐次更新していくことが必要である。即ち、
ロットの進行状況を監視し、その処理結果に基づいて、
どのロットを先に処理するかの優先度を変更し、既に処
理された以降のスケジューリングを、装置の稼働状況
(故障等の情報)、メンテナンス状況、あるいはオペレ
ータの稼働状況等を考慮して、実行しなくてはならな
い。このようなスケジューリングによる生産管理を行う
ためには、ライン内の全ロットについて、工程に分解
し、使用装置(場合によってはそのオペレータ)の稼働
の可否を判定し、個々のロットの優先度に応じた処理予
定を作成しなければならない。特にLSI製造では、前
の工程との連続性(ある一定時間以内に処理しなければ
いけない)が要求される工程も多く、納期を正確に予測
するためには、実際に稼働可能な時間帯をチェックしな
がら各ロットの各工程ごとの処理開始予定を詳細にスケ
ジュールする必要がある。
The time (TAT) from the loading of such a product to its completion depends on the number of lots loaded in the line. When products with different priorities are mixed, the products with low priorities are delayed in processing due to the products with high priorities. Therefore, as is done conventionally,
For each lot, the exact completion date cannot be predicted only by predicting the progress from the number of lots set in the device and the processing time and determining whether the delivery date can be met. Therefore, in order to control the completion date of a lot of priority or importance (hereinafter referred to as a progress control lot) so that the delivery date is not delayed, and to create the key information for data acquisition, It is necessary to monitor the progress of the lot and execute regular scheduling about once a day and aperiodic scheduling due to equipment troubles, lot progress delays, etc. to sequentially update the processing schedule. That is,
Monitor the progress of lots, and based on the processing results,
Change the priority of which lot to process first, and execute the scheduling after the processing has already been performed, considering the operating status (information such as failure) of the device, maintenance status, or operating status of the operator. I have to do it. In order to perform production management by such scheduling, all lots in the line are disassembled into processes, the availability of the equipment used (in some cases, the operator) is determined, and the priority of each lot is determined. You have to create a processing schedule. Especially in LSI manufacturing, many processes require continuity with the previous process (must be processed within a certain period of time), and in order to accurately predict the delivery date, the actual operating time While checking, it is necessary to schedule the process start schedule for each process of each lot in detail.

【0009】[0009]

【発明が解決しようとする課題】しかし、このような処
理予定を作成するにおいて、同種の装置が複数あるの
で、処理可能な装置やオペレータの組合せや次工程との
連続性を考慮した組合せは何通りもある。従って、装置
やオペレータの稼働状態(空き時間帯)をチェックしな
がら、全ロットの各工程を割り当ててスケジュールを作
成するために要するメモリ容量、計算時間は、ロット数
や装置台数(オペレータを考慮する場合は、更にオペレ
ータ数)の増加とともに増大し、特にロット数が多いと
多大なメモリ容量と計算時間を必要とする。
However, in preparing such a processing schedule, there are a plurality of apparatuses of the same kind, so what is the combination of apparatuses that can be processed, operators, and combinations considering the continuity with the next process? There is also a street. Therefore, the memory capacity and calculation time required to create a schedule by allocating each process of all lots while checking the operating status (vacant time zone) of the equipment and the operator, the number of lots and the number of equipment (consider the operator In this case, the number of operators increases as the number of operators increases, and especially when the number of lots is large, a large memory capacity and calculation time are required.

【0010】本発明の目的は、進捗を制御しなければい
けない優先度または重要度の高いロットが、優先度と重
要度ともに高くない量産品に混在しているようなライン
において、上記スケジューリング時の処理時間の短縮と
使用メモリの低減を図り、これによって、ラインの進捗
管理、優先度や重要度の高いロットの完成日予測を正確
に行うことができるようにすることにある。また、優先
度の低いロットについても、進捗を管理できるようにす
ることである。特に、ライン全体の製造ロット数、品種
数が多い製造ラインへの適応を可能とすることにある。
An object of the present invention is to provide a lot of lots of high priority or importance whose progress must be controlled in a mass-produced product in which neither priority nor importance is mixed. It is intended to shorten the processing time and the memory used, and thereby to manage the progress of the line and accurately predict the completion date of a lot having high priority or importance. It is also possible to manage the progress of low-priority lots. In particular, it is to be able to adapt to a manufacturing line in which the number of manufacturing lots and the number of types of the entire line are large.

【0011】[0011]

【課題を解決するための手段】第1の発明は、製造条
件、製造の順序等を示す工程表と、各製造装置の稼働予
定表から、製造ロットごとまたは前記製造装置ごとの処
理予定を、短期間の処理予定を作成する第1のステップ
と、長期間の処理予定を作成する第2のステップとによ
り作成し、前記処理予定に基づいて、処理の進行、デー
タ格納を行う生産管理方法であって、前記第1のステッ
プは、前記製造ロットの中から優先度または重要度の高
いロットのみを選択するステップと、前記選択されたロ
ットの工程表と、前記選択されたロットの納期と、前記
選択されたロットの現在の優先度とを前記第2のステッ
プへ渡すステップと、前記第2のステップで決定された
前記選択されたロットの優先度から、選択されなかった
ロットの優先度を決定するステップと、前記製造ロット
の短期間の処理予定を作成するステップとから構成さ
れ、前記第2のステップは、前記選択されたロットの処
理工程を装置に割り当てて完成日までの長期間の処理予
定を作成して完成日を予測するステップと、前記完成日
が納期よりも遅れるようであれば優先度をあげ、余裕の
あるロットの優先度を下げ、ロットの処理優先順位を決
定するステップと、決定した優先度を前記第1のステッ
プへ渡すステップとから構成されることを特徴とする。
According to a first aspect of the present invention, a process schedule showing manufacturing conditions, a manufacturing order, etc. and an operation schedule of each manufacturing apparatus are used to determine a processing schedule for each manufacturing lot or each manufacturing apparatus. A production management method in which a first step of creating a short-term processing schedule and a second step of creating a long-term processing schedule are created, and processing progresses and data is stored based on the processing schedule. Then, the first step includes a step of selecting only lots of high priority or importance from the production lots, a process chart of the selected lots, and a delivery date of the selected lots, From the step of passing the current priority of the selected lot to the second step, and the priority of the unselected lot from the priority of the selected lot determined in the second step. Decision And a step of creating a short-term processing schedule of the manufacturing lot, and the second step assigns the processing step of the selected lot to the device and performs a long-term processing until the completion date. Creating a schedule and predicting the completion date, and increasing the priority if the completion date is later than the delivery date, lowering the priority of the lot with a margin, and determining the processing priority of the lot. , Passing the determined priority to the first step.

【0012】第2の発明は上記第1の発明に加えて、前
記第2のステップは、前記重要度が低いロットの中か
ら、一定間隔で抽出したロットを、重要ロットとして処
理予定を作成し直すステップから構成されることを特徴
とする。第3の発明は生産管理システムであって、製造
条件、製造の順序等を示す工程表と、各製造装置の稼働
予定表から、製造ロットごとまたは前記製造装置ごと
に、処理する工程の処理予定時刻を算出するスケジュー
ラを持ち、スケジューラが作成した処理予定に基づい
て、処理の進行、データ格納を行う生産管理システムに
おいて、前記スケジューラは第1のスケジューラと第2
のスケジューラから構成され、前記第1のスケジューラ
は、少なくとも、前記第2のスケジューラとの通信を行
う通信制御部と、製造ロットの中から優先度または重要
度の高いロットのみを選択して、該当するロットの工程
表、納期、現在の優先度を前記通信制御部へ送信するた
めのロット選択部と、前記第2のスケジューラによる優
先度をもとにして全ロットの優先度を設定し、各ロット
のスケジュールを作成するスケジュール作成部とからな
り、前記第2のスケジューラは、前記第1のスケジュー
ラとの通信を行う通信制御部と、前記第1のスケジュー
ラからのデータによって処理予定を作成するスケジュー
ル作成部と、スケジュール作成部で作成した処理予定か
ら納期遅れをチェックして優先度を変更する優先度変更
部とから構成されることを特徴とする。
In addition to the first aspect of the invention, the second aspect of the invention is that, in the second step, lots extracted at regular intervals from among the lots of low importance are processed as important lots. It is characterized in that it is composed of a step of fixing. A third aspect of the present invention is a production management system, in which a process schedule of processes to be processed for each manufacturing lot or each of the manufacturing devices is shown based on a process chart showing manufacturing conditions, a manufacturing order, etc. In a production management system that has a scheduler that calculates time, and that progresses processing and stores data based on a processing schedule created by the scheduler, the scheduler includes a first scheduler and a second scheduler.
The first scheduler selects at least a communication control unit that communicates with the second scheduler, and selects only lots of high priority or importance from manufacturing lots, Set the priority of all lots based on the process schedule, the delivery date, the lot selection unit for transmitting the current priority to the communication control unit, and the priority of the second scheduler. A schedule creating unit that creates a lot schedule, the second scheduler is a communication control unit that communicates with the first scheduler, and a schedule that creates a processing schedule based on data from the first scheduler. It consists of a creation unit and a priority change unit that checks the delivery delay from the processing schedule created by the schedule creation unit and changes the priority. It is characterized in.

【0013】[0013]

【作用】本発明の生産管理システムおよび方法では、全
部のロットを、全工程スケジュールせずに、オフライン
スケジューラは、重要度の高いロットのみをスケジュー
ル対象としているので、スケジュール作成時の計算時間
短縮、使用メモリ削減が可能である。このため、納期ま
での長期間のスケジュールが可能となる。また、できあ
がった処理予定は、進捗を制御しなければならないロッ
トについては、長期の計画が反映されたものとなってい
る。一方、オンラインスケジューラでは、オフラインス
ケジューラでの優先度の変更結果を受けて、短期間の作
業予定を作成する。この場合に、期間が短いので、計算
時間短縮、使用メモリ削減が可能である。このため、オ
ペレータの稼働等を考慮した正確な処理予定が作成でき
る。
In the production management system and method of the present invention, the entire line schedule is not scheduled for all lots, and the offline scheduler only schedules lots of high importance. The memory used can be reduced. Therefore, it becomes possible to schedule for a long time until the delivery date. In addition, the finished processing schedule reflects the long-term plan for lots whose progress must be controlled. On the other hand, the online scheduler creates a short-term work schedule in response to the priority change result in the offline scheduler. In this case, since the period is short, it is possible to reduce the calculation time and the memory used. Therefore, an accurate processing schedule can be created in consideration of the operation of the operator.

【0014】[0014]

【実施例】以下、図面を参照して本発明の実施例を詳細
に説明する。まず、本発明の生産管理システム構成を図
1に示す。本システムでは、2台のスケジューラを使用
している。1台は製造ライン内の進捗管理/データ収集
システム3と直結したオンラインスケジューラ1であ
り、もう1台は完成日を予測する役目をもつオフライン
スケジューラ2である。
Embodiments of the present invention will now be described in detail with reference to the drawings. First, the production management system configuration of the present invention is shown in FIG. This system uses two schedulers. One is an online scheduler 1 that is directly connected to the progress management / data collection system 3 in the manufacturing line, and the other is an offline scheduler 2 that has a role of predicting the completion date.

【0015】オンラインスケジューラ1は、作業指示
(スケジュール情報の送信)と進捗の管理を行う他、オ
フラインスケジューラからの優先度の変更結果に基づい
て、製造ライン内の各端末への作業指示用に短期間の処
理予定を作成する。このようにオンラインスケジューラ
1では、データ格納時のキー情報として使用する処理予
定を作成するので、原則として全ロットがスケジュール
対象となる。ただし、データ格納不要な場合には、その
ロットをスケジュール対象外とする、あるいはその工程
をスケジュール対象外とした擬似工程表を用いることも
可能である。このオンラインスケジューラ1の処理予定
は、データ収集時のキー情報として、装置からの処理デ
ータ(人手投入も含む)と合わせてデータベース6へ格
納される。
The online scheduler 1 not only manages work instructions (sending schedule information) and progress, but also makes short-term work instructions to each terminal in the manufacturing line based on the priority change result from the offline scheduler. Create a processing schedule between. In this way, the online scheduler 1 creates a processing schedule to be used as key information at the time of data storage, so that in principle all lots are subject to scheduling. However, if it is not necessary to store data, it is also possible to use a pseudo process chart that excludes the lot from the schedule or excludes the process from the schedule. The processing schedule of the online scheduler 1 is stored in the database 6 as key information at the time of data collection together with processing data (including manual input) from the device.

【0016】オフラインスケジューラ2は、オンライン
スケジューラ1から登録情報と、進捗結果を受取り、以
降の長期間の処理予定を作成し、進捗制御ロット(優先
ロット・重要ロット)の完成日を予測する。その結果に
もとづいて、各ロットの優先度の変更を行いオンライン
スケジューラ1にわたす。なお、長期間の処理予定およ
びロットの処理結果は、ロット進捗チャート5 (ガント
チャート) 等の形で表示される。
The offline scheduler 2 receives the registration information and the progress result from the online scheduler 1, creates a long-term processing schedule thereafter, and predicts the completion date of the progress control lot (priority lot / important lot). Based on the result, the priority of each lot is changed and passed to the online scheduler 1. The long-term processing schedule and the lot processing result are displayed in the form of a lot progress chart 5 (Gantt chart) or the like.

【0017】図2は、オンラインスケジューラ1および
オフラインスケジューラ2の構成を示した図である。オ
ンラインスケジューラ1は、ライン内にある各ロットの
登録情報のデータベース10(ロット名、使用工程表、
納期、優先度の初期値または現在の優先度、装置の情報
等)と、各ロットの処理予定、処理結果のデータベース
11を持っている。このうち、処理予定の方は、適宜変
更されるものである。この他に、各ロットの登録情報か
ら優先度の高いロットや重要度の高いロットを選択する
ロット選択部12と、選択したロットの情報をオフライ
ンスケジューラへ転送する通信制御部14、スケジュー
ル作成部13からなる。通信制御部14は、オフライン
スケジューラ2から優先度や一部ロットの処理予定の受
信も行う。ここまでが本発明のオンラインスケジューラ
1の基本的な構成であるが、この他に、処理予定の作成
を短縮化するために、処理予定抽出部15を設けること
も可能である。一方、オフラインスケジューラ2は、通
信制御部17の他に、スケジュール作成部18と優先度
変更部19を持つ。
FIG. 2 is a diagram showing the configurations of the online scheduler 1 and the offline scheduler 2. The online scheduler 1 has a database 10 of registration information of each lot in the line (lot name, usage schedule,
It has a database 11 of delivery date, initial value of priority or current priority, device information, etc., processing schedule of each lot, and processing result. Of these, the one to be processed will be changed as appropriate. In addition to this, a lot selection unit 12 that selects a lot of priority or a lot of importance from the registration information of each lot, a communication control unit 14 that transfers information of the selected lot to an offline scheduler, and a schedule creation unit 13 Consists of. The communication control unit 14 also receives the priority and the processing schedule of some lots from the offline scheduler 2. The above is the basic configuration of the online scheduler 1 of the present invention, but in addition to this, it is also possible to provide the processing schedule extraction unit 15 in order to shorten the creation of the processing schedule. On the other hand, the offline scheduler 2 has a schedule creation unit 18 and a priority change unit 19 in addition to the communication control unit 17.

【0018】つぎに、本発明の生産管理方法における処
理予定の作成方法を図3に示す。ステップS1からS6
がオンラインスケジューラ1での処理、S7からS12
がオフラインスケジューラ2での処理である。まず、オ
ンラインスケジューラ1内のロット選択部12におい
て、登録情報を参照しながら、各ロットが優先ロットか
重要ロットにあたるかをチェックし、該当ロットの工程
表、現在の優先度(または初期値)、処理済の最終工程
を通信制御部14へ渡す(S1)。
Next, FIG. 3 shows a method of preparing a processing schedule in the production management method of the present invention. Steps S1 to S6
Is processing by the online scheduler 1, S7 to S12
Is the processing in the offline scheduler 2. First, the lot selection unit 12 in the online scheduler 1 refers to the registration information to check whether each lot is a priority lot or an important lot, and the process chart of the lot, the current priority (or initial value), The processed final step is passed to the communication control unit 14 (S1).

【0019】通信制御部14はロット選択部12からの
データをオフラインスケジューラ2の通信制御部17へ
転送する(S2)。ここで、選択するロットの中には、
現在ラインの中にあるロット以外に、これから投入する
予定のロットの中で優先度、重要度の高いロットも含ま
れる。これを受信したオフラインスケジューラ2の通信
制御部17では、このデータをスケジュール作成部18
に渡す(S7)。
The communication controller 14 transfers the data from the lot selector 12 to the communication controller 17 of the off-line scheduler 2 (S2). Here, among the lots to be selected,
In addition to the lots currently on the line, lots with high priority and importance among lots to be put in future are included. The communication control unit 17 of the offline scheduler 2 which has received this data stores this data in the schedule creation unit 18
(S7).

【0020】スケジュール作成部18では、選択された
これらのロットの処理予定の作成を行う(S8)。スケ
ジュール期間は、最低でも新規に投入されたロット(最
新の投入ロット)が完成するまでの期間を含むものであ
り、通常は数カ月の期間に及ぶものである。ここで計算
された各ロットの完成予定日と納期、優先度の情報は、
優先度変更部19へ送られる。
The schedule creating unit 18 creates a processing schedule for these selected lots (S8). The schedule period includes at least a period until a newly introduced lot (latest input lot) is completed, and usually extends over a period of several months. Information on the estimated completion date, delivery date, priority of each lot calculated here is
It is sent to the priority changing unit 19.

【0021】優先度変更部19では、各ロットが納期ま
でに完成するかをチェックし、遅れるロットがあれば、
優先度を変更し、再度スケジュールを実行して完成日を
チェックする(S9)。遅れるロットがなければ、その
時の各ロットの優先度(同じ装置に重なった場合に、ど
ちらの処理を優先させるかの優先順位)と、処理予定を
通信制御部17へ送る(S10)。
The priority changing unit 19 checks whether each lot is completed by the delivery date.
The priority is changed, the schedule is executed again, and the completion date is checked (S9). If there is no lot to be delayed, the priority of each lot at that time (priority of which process is prioritized when overlapping with the same device) and the process schedule are sent to the communication control unit 17 (S10).

【0022】一方、優先度の変更及び再スケジュールを
何回か行っても、納期遅れが防げない場合には、計算を
中止しアラームを発生する(S12)。通信制御部17
では、受け取ったデータをオンラインスケジューラ1の
通信制御部14へ転送する(S11)。ここで、優先度
のみを送り、改めてオンラインスケジューラ側で全ロッ
トをスケジュールすることも可能である。
On the other hand, if the delay in delivery cannot be prevented even if the priority is changed and the reschedule is performed several times, the calculation is stopped and an alarm is generated (S12). Communication control unit 17
Then, the received data is transferred to the communication control unit 14 of the online scheduler 1 (S11). Here, it is possible to send only the priority and schedule all lots again on the side of the online scheduler.

【0023】優先度の変更は、完成予想日と納期との差
(余裕)の大きいものを下げて、余裕の小さいものを上
げる。ここで、この完成予想日は、従来の方法のよう
に、各装置での処理時間を単純に合計して類推したり、
各装置での統計的な待ち時間の値を入れて算出したもの
でなく、各ロットの1工程ずつを、装置の空き時間をチ
ェックしながら割り当てているので、正確なものであ
る。このため、納期の正確な予測とその処理予定にもと
づく進捗管理が行える。なお、オフラインスケジューラ
2の処理予定作成では、ロットを選択して減らしている
ので、全ライン規模でスケジュールを作成すると、ロッ
ト数の割に装置が多いことになり、実際よりもロットが
速く進んでしまい、完成日が実際よりも速く計算されて
しまう。これを防ぐために、ライン内の装置が多重化さ
れている場合には、その装置台数をロットの選択比に比
例して減らして計算する。又、装置台数が減らせない場
合には、稼働可能時間に制約を設けて実行的に台数を減
らしている。なお、厳密には、優先度の高いロットの計
算時には、正規のライン構成で計算した後、優先度は低
いが重要なロット(後で述べるマーカロットなど)の計
算時にライン規模を縮小して計算するのが正しいが、優
先ロットの数が少なければ、初めから縮小した擬似ライ
ンでスケジュールを作成しても完成予測はそれほどずれ
ない。また、このラインの縮小は、ネックになりそうな
稼働率の高い数種類の装置についてのみ実行したのでも
よい。このオフラインのスケジュールは、オペレータへ
の作業指示などを行うオンラインスケジューラ1とは独
立しているので、再スケジュールなどを行っても、オペ
レータの実作業に支障はない。
To change the priority, the one with a large difference (margin) between the expected completion date and the delivery date is lowered and the one with a small margin is raised. Here, this expected completion date can be simply summed up the processing time in each device like the conventional method, or by analogy,
This is accurate because it is not calculated by including the statistical waiting time value in each device, but is assigned to each process of each lot while checking the idle time of the device. Therefore, it is possible to accurately predict the delivery date and manage the progress based on the processing schedule. In the process schedule creation of the offline scheduler 2, lots are selected and reduced. Therefore, if a schedule is created for the entire line scale, the number of devices will be large for the number of lots, and lots will advance faster than they actually are. The completion date will be calculated faster than it actually is. In order to prevent this, when the devices in the line are multiplexed, the number of devices is reduced in proportion to the lot selection ratio. Further, when the number of devices cannot be reduced, the available time is restricted to reduce the number of devices practically. Strictly speaking, when calculating lots with high priority, after calculating with a regular line configuration, when calculating lots with low priority but important (marker lots described later), the line scale is reduced. Although it is correct to do it, if the number of priority lots is small, the completion prediction does not deviate so much even if a schedule is created with a pseudo line reduced from the beginning. Further, the reduction of this line may be executed only for a few types of devices having a high operating rate that are likely to become a bottleneck. This off-line schedule is independent of the online scheduler 1 that issues work instructions to the operator, so that rescheduling does not hinder the actual work of the operator.

【0024】オフラインスケジューラ2による優先度の
設定が終わったならば、オンラインスケジューラ1の通
信制御部14はその結果を受取り、オンラインスケジュ
ーラ1のスケジュール作成部13に優先度のデータを渡
す(S3)。オンラインスケジューラ1のスケジュール
作成部13では、この優先度を参照し、全ロットの優先
度を付け直す(S4)。この付け直しは、優先度の高い
ロットについては、そのままである。オフラインスケジ
ュールの対象外のロットについては、同一品種のロット
でオフラインスケジューラ2によって付けられた優先度
を参照して優先度を割り当てる。(先行ロットが先に処
理されるように順番づけする。)この優先度にもとづい
て全ロットの作業指示用の短期間(通常は数日)の処理
予定を作成する(S6)。
When the priority setting by the offline scheduler 2 is completed, the communication control unit 14 of the online scheduler 1 receives the result, and passes the priority data to the schedule creating unit 13 of the online scheduler 1 (S3). The schedule creation unit 13 of the online scheduler 1 refers to this priority and resets the priority of all lots (S4). This reassignment is left unchanged for lots with high priority. Lots that are not covered by the off-line schedule are assigned priorities by referring to priorities assigned by the off-line scheduler 2 for lots of the same type. (The preceding lots are ordered so that they are processed first.) Based on this priority, a short-term (usually several days) processing schedule for work instructions for all lots is created (S6).

【0025】ステップS3,S4,S6で、あらためて
全ロットのスケジュールをやり直すことも可能である
が、優先度の高いロットの処理予定は殆ど変更ないの
で、優先度の高いものは、以下の方法を用いて処理予定
の作成時間を短縮することができる。即ち、オンライン
スケジューラに処理予定抽出部15を設けて、ここにオ
フラインスケジュールの結果(処理予定)を蓄えてお
く。この場合の処理予定の作成方法を図4に示す。図3
のS1,S2及びS7〜S12は省略してある。オンラ
インスケジューラ1においてスケジュール作成時には、
指定された期間の該当ロットの処理予定を抽出して処理
予定とする。他のロットは、この空き時間帯に処理予定
を埋めていく。
In steps S3, S4, and S6, it is possible to re-schedule all lots. However, since the processing schedules for lots with high priority are hardly changed, the following method is used for those with high priority. It is possible to shorten the time required to create a processing schedule by using this. That is, the online scheduler is provided with the processing schedule extraction unit 15, and the result (processing schedule) of the offline schedule is stored here. A method of creating a processing schedule in this case is shown in FIG. Figure 3
S1, S2, and S7 to S12 are omitted. When creating a schedule in the online scheduler 1,
The processing schedule of the relevant lot in the specified period is extracted and set as the processing schedule. For other lots, the processing schedule is filled in this free time zone.

【0026】なお、オンラインスケジュールとオフライ
ンスケジュールは、必ずしも両方同時に実行する必要は
ない。例えば、オフラインスケジューラ2で優先度の設
定を行ったものを記憶しておき、1週間以内程度であれ
ば、その値を使って、オンラインスケジューラ1でスケ
ジュールを作成し、オフラインスケジューラ2は、1週
間に1回程度起動させることも可能である。
The online schedule and the offline schedule do not necessarily have to be executed at the same time. For example, the offline scheduler 2 stores the priority setting, and if it is within a week, the online scheduler 1 creates a schedule using the value, and the offline scheduler 2 waits for 1 week. It is also possible to activate it once.

【0027】この方式では、オンラインスケジューラ側
では、期間が短いこと、また、オフラインスケジューラ
側では対象ロット数が少ないことから、一度に計算する
対象工程数が少なくなるので、計算時間・メモリの制約
を受けずに納期を考慮した生産計画を正確にたてること
ができる。従って、実効的に全体のロット数が多いライ
ンへ適用する事が可能となる。また、オフラインスケジ
ューラは、ロット投入計画をたてるためのシミュレーシ
ョンにも利用できる。
In this method, the online scheduler side has a short period, and the offline scheduler side has a small number of target lots. Therefore, the number of target processes to be calculated at one time is small. It is possible to accurately make a production plan that considers the delivery date without receiving it. Therefore, it can be effectively applied to a line having a large number of lots. The off-line scheduler can also be used for simulations for making lot lot planning.

【0028】図3の方法では、オフラインスケジュール
の対象が、優先ロットと重要ロットと記載している。こ
のような方法では、優先度・重要度ともに低い汎用品の
ロットでは、処理予定が立てられないので、生産計画や
ロットの進捗管理がやりにくい。これを防ぐ目的で、処
理予定を立て、かつ、そのスケジューリングに要する時
間やメモリを低減する方法として、マーカロットを用い
る方法がある。以下にその方法を述べる。
In the method of FIG. 3, the offline schedule targets are the priority lot and the important lot. In such a method, it is difficult to manage the production plan and the progress of the lot because a processing schedule cannot be set for a lot of general-purpose products having low priority and importance. In order to prevent this, there is a method of using a marker lot as a method of making a processing schedule and reducing the time and memory required for the scheduling. The method will be described below.

【0029】ライン上には、優先度の異なるロットが存
在する。このうち、優先度の高いロットは、納期を管理
するために、全工程スケジュールを実施し、完成日を予
測し、進捗を制御する。しかし、優先度の高いロットの
みをスケジュールするのでは、優先度の低いロットの進
捗は全く判らない。優先度の低いゲートアレイ基板等の
量産品(別マスクを用いていても、同一工程表を用いる
ものは、量産品とみなすことができる)は、量産品の中
から一定間隔で抽出したロット(マーカロット:例えば
10ロットおき等)を進捗管理(納期管理)を行うため
の指標として扱い、オフラインスケジューラで優先ロッ
トとともに全工程スケジューリングして進捗を予測し、
優先度の変更、次のロット投入等を行う。
There are lots of different priorities on the line. Among these, for the lots with high priority, the entire process schedule is executed, the completion date is predicted, and the progress is controlled in order to manage the delivery date. However, by scheduling only high priority lots, the progress of low priority lots is completely unknown. Mass-produced products such as low-priority gate array substrates (those that use the same process sheet even if different masks are used can be regarded as mass-produced products) are lots extracted at regular intervals from the mass-produced products ( Marker lot: Every 10 lots, for example, is used as an index for performing progress management (delivery date management), and the offline scheduler schedules all processes together with priority lots to predict progress,
Change the priority and add the next lot.

【0030】即ち、図5に示すように、量産品のロット
i,i+1,・・・, i+N,・・・がライン上に有る場合
に、Nロットごとに、マーカロットとし、このロットに
ついては、オフラインスケジューラで処理予定を作成す
る。この処理予定の作成においては、ロットの投入時
期、あるいは、当日の処理開始工程の指定を行うことに
より(ある時刻での終了工程を通知してもよい)、実際
のライン上の処理に則した処理予定を立てることがで
き、ライン上のロットの進捗状況を管理することができ
る。一方、他のロットの処理は、投入ロットの順に処理
するものとしておく。即ち、同一工程で複数のロットが
待ち状態に成った場合は、先に投入したロットを先に処
理すると決めておけば、前記2つのマーカロットの間に
ある他のロットについても、概略のロットの進行が管理
できる。また、データの収集については、通常のスケジ
ュールを実施したロットと同じように処理することがで
きる。
That is, as shown in FIG. 5, when lots C i, C i + 1, ... , C i + N, ... A lot is created and a processing schedule is created for this lot with the offline scheduler. This process schedule was created according to the actual process on the line by designating the lot start time or the process start process of the day (the end process may be notified at a certain time). It is possible to make a processing schedule and manage the progress of lots on the line. On the other hand, the other lots are processed in the order of the input lots. That is, when a plurality of lots are in a waiting state in the same process, if it is decided that the lot that has been put in first is processed first, the other lots between the two marker lots will also be rough lots. Can manage the progress of. In addition, data collection can be performed in the same manner as a lot that has been subjected to a normal schedule.

【0031】このマーカロットを用いた効果を図6に示
す。この図は、通常の全ロット、全工程をスケジュール
する方法で計算可能なロット数(納期をシミュレーショ
ンできるロット数)を1として規格化した、計算可能な
ロット数を、優先ロットの割合、マーカロットの割合を
パラメータに示した図である。例えば、優先ロットの割
合が0.01(1%)である場合は、マーカロットが5
%、即ち、20ロットに1ロットとして従来の15倍の
ロット数を計算できる。優先ロットがなければマーカロ
ットの比率に比例して計算量は減少する。日に100ロ
ットずつ投入する(年間30000ロット)量産ライン
を考えると、その日に投入する汎用ロット100のうち
の1ロットをマーカロットとすれば、1日以内のずれで
進捗が管理できる。この場合の計算量は、通常の場合に
比べて100分の1であり、300ロットが扱えるスケ
ジューラでよい。また、進捗管理の精度が2日程度でよ
ければ、更にその半分の150ロットが扱えるスケジュ
ーラでよい。このように、マーカロット法は、量産ライ
ンでは、極めて効率的な方法である。
The effect of using this marker lot is shown in FIG. This figure normalizes all lots and the number of lots that can be calculated by the method of scheduling all processes (the number of lots for which delivery can be simulated) is standardized as 1. It is the figure which showed the rate of as a parameter. For example, if the priority lot ratio is 0.01 (1%), the marker lot is 5
%, That is, 1 lot per 20 lots, the number of lots that is 15 times the conventional number can be calculated. If there is no priority lot, the calculation amount decreases in proportion to the ratio of the marker lot. Considering a mass production line in which 100 lots are put in each day (30,000 lots per year), if one lot of the general-purpose lots 100 put in that day is set as a marker lot, the progress can be managed within one day. The calculation amount in this case is 1/100 of that in the normal case, and a scheduler capable of handling 300 lots is sufficient. If the progress management accuracy is about 2 days, a scheduler that can handle 150 lots, which is half that amount, can be used. As described above, the marker lot method is an extremely efficient method in a mass production line.

【0032】さて、図1のオンラインスケジューラにお
いて、進捗制御ロット(マーカロットも含む)について
は、オフラインのスケジュールによる優先度が反映され
て全工程がスケジュールされている。このため、基本的
には両者は同じ処理予定となっている。これに対して、
進捗制御ロットでない(マーカロットでもない)汎用ロ
ットのスケジュールについては、期間が短いので、その
まま全工程をスケジュールすることも可能である。しか
し、マーカロット法を用いれば、進捗制御ロットでない
ロットは必ずしも全工程の処理予定を立てる必要はな
い。すなわち、処理予定の使用目的には、進捗予測・納
期管理の他に、データ格納時のキー情報への利用があ
り、後者の場合、スケジュール情報(工程表情報)がな
いと、データ格納ができない。このため、スケジュール
情報をデータ格納時に用いるシステムでは全ロットをス
ケジューリング対象とする必要があるが、このスケジュ
ーリングは、進捗予測のためでないので、時間的に正確
なスケジューリングである必要なない。処理された時刻
が正確に知りたい装置やデータを取得したい装置のみの
処理予定だけ作成すればよい。この場合には、擬似工程
表を用いて処理予定を立てればよい。以下に擬似工程表
について述べる。
In the online scheduler shown in FIG. 1, progress control lots (including marker lots) are scheduled for all processes by reflecting the priority of the offline schedule. For this reason, both are basically scheduled to be processed in the same way. On the contrary,
Since the schedule of a general-purpose lot that is not a progress control lot (also not a marker lot) has a short period, it is possible to schedule the entire process as it is. However, if the marker lot method is used, it is not always necessary to make a processing schedule for all lots that are not progress control lots. That is, in addition to progress prediction and delivery date management, the intended use of processing is to use key information when storing data. In the latter case, data cannot be stored without schedule information (process table information). . For this reason, in the system that uses the schedule information at the time of storing data, it is necessary to schedule all lots, but this scheduling is not for progress prediction, so it is not necessary to be accurate in terms of time. It suffices to create only the processing schedule of only the device whose processing time is to be known accurately and the device whose data is to be acquired. In this case, the process schedule may be set up using the pseudo process chart. The pseudo process chart will be described below.

【0033】擬似工程表は、データ収集を行う工程や進
捗管理に最低限必要な工程(ロット進捗チャートに表示
させる工程)だけをスケジュールの対象とした工程表の
ことであり、実際の処理は、標準工程表による作業指示
に基づいて行われる。図7は、擬似工程表の概念を説明
した図である。例えば、工程表の中には、必ずデータを
取得する検査等の工程(K2,K5)、ロット進捗チャ
ートに表示して進捗を監視する工程(K4)、その他の
工程が混在している。優先度の高いロット、マーカロッ
トからなる進捗制御ロットは、この全工程がスケジュー
ル対象となるので、もとの工程表をそのまま用いる。デ
ータ取得のみを行い、進捗管理は行わないロットは、デ
ータ取得工程のみからなるデータ収集用擬似工程表を用
いる。例えば、寸法測長、膜厚測定等だけの工程表であ
る。この擬似工程表を用いれば、スケジュール時のメモ
リ削減、時間短縮が可能である。また、オペレータから
みれば、正規の工程表による処理予定が有る場合と同じ
手順でデータ収集が可能となるので、オペレーションミ
スの危険も少なくなる。(各装置への指令の場合には、
マーカロットの間に、これらの擬似工程の処理予定をは
め込んで指令を出す。) なお、オンラインスケジュー
リング時には、短期間の標準スケジューリングと擬似ス
ケジューリングが同時に行われ、先ず、優先度の高いロ
ットの工程が予約され、その空き時間帯に擬似スケジュ
ーリングが行われる。このため、擬似スケジューリング
によって、標準スケジューリングの内容が変更されるこ
とはない。擬似スケジューリングの場合(非進捗制御ロ
ット)のウェハ処理は、標準工程表で別途作業指示が行
われ、進捗制御ロットの合間に、山済み方式、看板方式
等の生産管理手法で行う。
The pseudo process chart is a process chart in which only the minimum steps required for data collection and progress management (steps displayed on the lot progress chart) are the targets of the schedule, and the actual processing is It is performed based on the work instructions according to the standard process chart. FIG. 7 is a diagram illustrating the concept of the pseudo process chart. For example, in the process table, there are a mixture of processes such as inspections (K2 and K5) that always acquire data, processes that display on a lot progress chart to monitor the progress (K4), and other processes. For a progress control lot consisting of a lot with a high priority and a marker lot, all of these processes are subject to scheduling, so the original process chart is used as it is. For a lot that only acquires data but does not manage progress, use a pseudo data collection process chart that includes only data acquisition processes. For example, it is a process chart only for dimension measurement, film thickness measurement, and the like. By using this pseudo process chart, it is possible to reduce the memory and time at the time of scheduling. Further, from the operator's point of view, since data can be collected in the same procedure as when there is a processing schedule based on the regular process chart, the risk of operation mistakes is reduced. (In the case of a command to each device,
During the marker lot, the processing schedules of these pseudo processes are set and commands are issued. At the time of online scheduling, short-term standard scheduling and pseudo-scheduling are performed at the same time. First, a process of a lot with a high priority is reserved, and pseudo-scheduling is performed during the idle time. Therefore, the pseudo scheduling does not change the contents of the standard scheduling. In the case of the pseudo scheduling (non-progress control lot), the wafer processing is separately instructed in the standard process chart, and is performed by the production management method such as the piled-up method or the signboard method between the progress control lots.

【0034】図1のシステムにおいて、擬似工程表を取
り入れたスケジューリングの作成方法についてもう少し
詳しく説明する。TAT管理(完成日の予測等進捗管
理)を目的とした進捗制御ロットは長期間のスケジュー
リングが必要であるが、データ格納用の擬似スケジュー
リングは数日分の予定があればよい。従って、進捗制御
ロットのみの長期スケジューリングと、全ロット(擬似
工程表による非進捗制御ロットを含む)のデータ格納用
処理予定作成(短期間)は、一度にはスケジュールでき
ない。後者のスケジュールは、データ収集システムに直
結したオンラインスケジューラで実施する必要がある。
しかし、前者は本システムでは、オフラインスケジュー
ラで実施し、進捗制御ロットのスケジュールと、非進捗
制御ロットのスケジュールを2つのスケジューラに分離
してある。図8はその概念を示したものである。
In the system shown in FIG. 1, a method of creating a scheduling that incorporates a pseudo process chart will be described in more detail. Although a progress control lot for the purpose of TAT management (progress management such as prediction of completion date) requires long-term scheduling, pseudo scheduling for data storage may be scheduled for several days. Therefore, the long-term scheduling of only the progress control lot and the data storage process schedule creation (short period) of all lots (including the non-progress control lot based on the pseudo process chart) cannot be scheduled at once. The latter schedule should be implemented by an online scheduler directly connected to the data collection system.
However, in the former system, an offline scheduler is used in this system, and the schedule of the progress control lot and the schedule of the non-progress control lot are separated into two schedulers. FIG. 8 shows the concept.

【0035】図中、斜線部分が進捗制御ロットで、優先
度の高いロットとマーカロットを標準工程表により、オ
フラインスケジューラで長期のスケジューリングを行
う。この結果から、納期に遅れそうなロットの優先度を
上げ、納期まで余裕のあるロットの優先度を下げる。こ
の優先度変更を反映したオンラインスケジューラで、網
掛け部分の短期間の全ロットスケジューリングを行う。
この時、標準スケジューリングと非進捗制御ロットのデ
ータ格納用擬似スケジューリングが同時に行われるが、
優先度の高いロットの工程が予約され、その空き時間帯
に擬似スケジューリングが行われる。従って、優先ロッ
トのオンラインスケジューリング結果は、オフラインス
ケジューリングの内容と同じである。通常、このスケジ
ュール期間は、オフラインスケジューラでは、納期を計
算するので、2〜3カ月の期間にわたる。一方、オンラ
インスケジューラでは、数日間の処理予定を作成する。
また、これらのスケジュール結果は、進捗具合によって
適宜変更されるものである。その再スケジュールのタイ
ミングとしては、例えば、オンラインスケジューラは毎
日定時、オフラインスケジューラは週1回、のような定
期的なもののほかに、はじめの処理予定からロットの進
捗がある時間(例えば1日)遅れたら再スケジュールを
かけるものもある。
In the figure, the shaded area is the progress control lot, and the high-priority lot and the marker lot are subjected to long-term scheduling by the offline scheduler according to the standard process chart. From this result, the priority of the lot that is likely to be delayed is raised, and the priority of the lot that has time to delivery is lowered. An online scheduler that reflects this priority change performs short-term all-lot scheduling in the shaded area.
At this time, the standard scheduling and the pseudo-scheduling for storing the data of the non-progress control lot are simultaneously performed.
The process of the lot with a high priority is reserved, and the pseudo scheduling is performed during the idle time. Therefore, the result of the online scheduling of the priority lot is the same as the content of the offline scheduling. Normally, this schedule period extends over a period of 2-3 months because the offline scheduler calculates the delivery date. On the other hand, the online scheduler creates a processing schedule for several days.
Further, these schedule results are appropriately changed depending on the progress. The rescheduling timing is, for example, regular on a daily basis for the online scheduler, once a week for the offline scheduler, or delayed from the initial processing schedule by the time (eg, 1 day) in which the lot progresses. Some even re-schedule.

【0036】[0036]

【発明の効果】本発明の生産管理システムでは、全部の
ロットを、全工程スケジュールせずに、オンラインスケ
ジューラとオフラインスケジューラに分けている。オフ
ラインスケジューラでは、進捗管理ロット(優先度また
は重要度の高いロット)のみをスケジュール対象として
いるので、スケジュール作成時に大幅な使用メモリ削減
が可能である。
According to the production management system of the present invention, all lots are divided into an online scheduler and an offline scheduler without scheduling all processes. In the offline scheduler, only progress management lots (lots of high priority or importance) are targeted for scheduling, so it is possible to significantly reduce the memory used when creating a schedule.

【0037】また、オフラインスケジューラでできあが
った処理予定は、進捗を制御しなければならないロット
については、長期の計画が反映されたものとなってい
る。従って、この処理予定に基づいてライン全体の処理
予定を短期間ずつオンラインスケジューラで作成するの
で、この処理予定に従って処理を実行することにより、
正確な納期制御ができる。
The processing schedule created by the offline scheduler reflects the long-term plan for lots whose progress must be controlled. Therefore, based on this processing schedule, the processing schedule of the entire line is created by the online scheduler for each short period. By executing the processing according to this processing schedule,
Accurate delivery control is possible.

【0038】更に、進捗制御ロットでない量産ロット
も、マーカロットを用いることにより概略の進捗を管理
することができるので、実効的には、大量のロットが流
れるラインのスケジューリングによる納期予測を実施す
ることが可能となる。
Further, even in a mass production lot that is not a progress control lot, the approximate progress can be managed by using the marker lot. Therefore, it is effective to perform the delivery date prediction by scheduling the line in which a large number of lots flow. Is possible.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明の生産管理システムの構成を示した図で
ある。
FIG. 1 is a diagram showing a configuration of a production management system of the present invention.

【図2】本発明の生産管理システムのオンラインスケジ
ューラ及びオフラインスケジューラの構成を示した図で
ある。
FIG. 2 is a diagram showing configurations of an online scheduler and an offline scheduler of the production management system of the present invention.

【図3】オンラインスケジューラ及びオフラインスケジ
ューラにおける処理予定の作成方法を示した図である。
FIG. 3 is a diagram showing a method of creating a processing schedule in an online scheduler and an offline scheduler.

【図4】処理予定抽出部を付加した場合のオンラインス
ケジューラにおける処理予定の作成方法を示した図であ
る。
FIG. 4 is a diagram showing a method of creating a processing schedule in an online scheduler when a processing schedule extraction unit is added.

【図5】マーカロットによる進捗管理を行う場合の概念
を示した図である。
FIG. 5 is a diagram showing a concept in the case of performing progress management by a marker lot.

【図6】マーカロットを用いた場合に計算可能なロット
数が増加するようすを示した図である。
FIG. 6 is a diagram showing how the number of lots that can be calculated increases when a marker lot is used.

【図7】擬似工程表を作成する方法の一例を示した図で
ある。
FIG. 7 is a diagram showing an example of a method of creating a pseudo process chart.

【図8】本発明の生産システムにおける処理予定作成の
概念を示した図である。
FIG. 8 is a diagram showing a concept of processing schedule creation in the production system of the present invention.

【図9】LSIの製造手順の概略を説明した図である。FIG. 9 is a diagram illustrating an outline of a manufacturing procedure of an LSI.

【図10】工程表の例を示した図である。FIG. 10 is a diagram showing an example of a process table.

【図11】従来の生産管理方法を示した図である。FIG. 11 is a diagram showing a conventional production management method.

【符号の説明】[Explanation of symbols]

1・・・オンラインスケジューラ 2・・・オフラ
インスケジューラ 3・・・進捗管理/データ収集システム 4・・・
製造/検査装置 5・・・ロット進捗チャート 6・・・データベー
ス 10・・・登録情報データベース 11・・・処理
結果データベース 12・・・ロット選択部 13,18・・・スケジ
ュール作成部 14,17・・・通信制御部 15・・・処理予定
抽出部 16・・・処理予定(短期) 19・・・優先度変
更部
1 ... Online scheduler 2 ... Offline scheduler 3 ... Progress management / data collection system 4 ...
Manufacturing / inspection equipment 5 ... Lot progress chart 6 ... Database 10 ... Registration information database 11 ... Processing result database 12 ... Lot selection unit 13, 18 ... Schedule creation unit 14, 17 ... ..Communication control unit 15 ... Processing schedule extracting unit 16 ... Processing schedule (short-term) 19 ... Priority changing unit

Claims (3)

【特許請求の範囲】[Claims] 【請求項1】 製造条件、製造の順序等を示す工程表
と、各製造装置の稼働予定表から、製造ロットごとまた
は前記製造装置ごとの処理予定を、短期間の処理予定を
作成する第1のステップと、長期間の処理予定を作成す
る第2のステップとにより作成し、前記処理予定に基づ
いて、処理の進行、データ格納を行う生産管理方法であ
って、 前記第1のステップは、 前記製造ロットの中から優先度または重要度の高いロッ
トのみを選択するステップと、 前記選択されたロットの工程表と、前記選択されたロッ
トの納期と、前記選択されたロットの現在の優先度とを
前記第2のステップへ渡すステップと、 前記第2のステップで決定された前記選択されたロット
の優先度から、選択されなかったロットの優先度を決定
するステップと、 前記製造ロットの短期間の処理予定を作成するステップ
とから構成され前記第2のステップは、 前記選択されたロットの処理工程を装置に割り当てて完
成日までの長期間の処理予定を作成して完成日を予測す
るステップと、 前記完成日が納期よりも遅れるようであれば優先度をあ
げ、余裕のあるロットの優先度を下げ、ロットの処理優
先順位を決定するステップと、 決定した優先度を前記第1のステップへ渡すステップと
から構成されることを特徴とする生産管理方法。
1. A first process for preparing a processing schedule for each manufacturing lot or each of the manufacturing devices and a short-term processing plan from a process chart showing manufacturing conditions, manufacturing order, etc. and an operation schedule of each manufacturing apparatus. And a second step of creating a long-term processing schedule, and based on the processing schedule, the production management method of performing processing progress and storing data, wherein the first step comprises: Selecting only lots of high priority or importance from the production lots, the process chart of the selected lots, the delivery date of the selected lots, and the current priority of the selected lots To the second step, determining the priority of the unselected lot from the priority of the selected lot determined in the second step, and And a step of creating a short-term processing schedule of a lot, and the second step assigns the processing process of the selected lot to the device and creates a long-term processing schedule until the completion date. Predicting the date, increasing the priority if the completion date is later than the delivery date, lowering the priority of the lot with a margin, determining the processing priority of the lot, and determining the determined priority. A production control method comprising: a step of passing to the first step.
【請求項2】 前記第2のステップは、前記重要度が低
いロットの中から、一定間隔で抽出したロットを、重要
ロットとして処理予定を作成し直すステップから構成さ
れることを特徴とする請求項1に記載の生産管理方法
2. The second step comprises a step of re-creating a processing schedule as an important lot of lots extracted at regular intervals from the low-importance lots. Production management method according to item 1
【請求項3】 製造条件、製造の順序等を示す工程表
と、各製造装置の稼働予定表から、製造ロットごとまた
は前記製造装置ごとに、処理する工程の処理予定時刻を
算出するスケジューラを持ち、スケジューラが作成した
処理予定に基づいて、処理の進行、データ格納を行う生
産管理システムにおいて、 前記スケジューラは第1のスケジューラと第2のスケジ
ューラから構成され、 前記第1のスケジューラは、少なくとも、 前記第2のスケジューラとの通信を行う通信制御部と、 製造ロットの中から優先度または重要度の高いロットの
みを選択して、該当するロットの工程表、納期、現在の
優先度を前記通信制御部へ送信するためのロット選択部
と、 前記第2のスケジューラによる優先度をもとにして全ロ
ットの優先度を設定し、各ロットのスケジュールを作成
するスケジュール作成部とからなり、 前記第2のスケジューラは、 前記第1のスケジューラとの通信を行う通信制御部と、 前記第1のスケジューラからのデータによって処理予定
を作成するスケジュール作成部と、 スケジュール作成部で作成した処理予定から納期遅れを
チェックして優先度を変更する優先度変更部とから構成
されることを特徴とする生産管理システム。
3. A scheduler is provided, which calculates a scheduled processing time of a process to be processed for each manufacturing lot or for each manufacturing apparatus from a process table showing manufacturing conditions, manufacturing order, etc. and an operation schedule of each manufacturing apparatus. In a production management system that performs processing progress and data storage based on a processing schedule created by a scheduler, the scheduler includes a first scheduler and a second scheduler, and the first scheduler is at least the A communication control unit that communicates with the second scheduler, and selects only lots of high priority or importance from the production lots, and the communication control of the process table, delivery date, and current priority of the relevant lot is performed. A lot selection unit for transmitting to each department, and setting the priority of all lots based on the priority of the second scheduler, A schedule creation unit that creates a schedule, wherein the second scheduler is a communication control unit that communicates with the first scheduler, and a schedule creation unit that creates a processing schedule based on data from the first scheduler. And a priority change unit that checks the delivery delay from the processing schedule created by the schedule creation unit and changes the priority, and the production management system.
JP5171593A 1992-05-12 1993-03-12 Production management method and system Expired - Fee Related JP3283951B2 (en)

Priority Applications (2)

Application Number Priority Date Filing Date Title
JP5171593A JP3283951B2 (en) 1993-03-12 1993-03-12 Production management method and system
US08/058,175 US5442561A (en) 1992-05-12 1993-05-10 Production management system and its application method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP5171593A JP3283951B2 (en) 1993-03-12 1993-03-12 Production management method and system

Publications (2)

Publication Number Publication Date
JPH06266413A true JPH06266413A (en) 1994-09-22
JP3283951B2 JP3283951B2 (en) 2002-05-20

Family

ID=12894593

Family Applications (1)

Application Number Title Priority Date Filing Date
JP5171593A Expired - Fee Related JP3283951B2 (en) 1992-05-12 1993-03-12 Production management method and system

Country Status (1)

Country Link
JP (1) JP3283951B2 (en)

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0774068A (en) * 1993-09-02 1995-03-17 Matsushita Electric Ind Co Ltd Product treating device and method for determining product treatment
JP2002169996A (en) * 2000-09-22 2002-06-14 Sharp Corp Server device, scheduling control device, production/ physical distribution management system, terminal device, production/physical distribution management method, and computer-readable recording medium with production/physical distribution management program recorded thereon, program for making computer function as scheduling control device, and computer-readable recording medium with the same program recorded thereon
JP2003050612A (en) * 2001-08-07 2003-02-21 Kawasaki Microelectronics Kk Production management method and system
JP2004078917A (en) * 2002-07-23 2004-03-11 Dell Products Lp Process for optimization and synchronization for manufacture
JPWO2001075541A1 (en) * 2000-04-04 2004-04-30 富士通株式会社 Production management network system, production management method, and recording medium recording production management program
US6856848B2 (en) 2000-04-24 2005-02-15 Matsushita Electric Industrial Co., Ltd. Method and apparatus for controlling progress of product processing
JP2010165378A (en) * 2002-05-31 2010-07-29 Advanced Micro Devices Inc Calendaring system formed including computer
JP4701533B2 (en) * 2001-04-27 2011-06-15 トヨタ自動車株式会社 Product inspection equipment
JP2016151962A (en) * 2015-02-18 2016-08-22 澁谷工業株式会社 Schedule management system
CN112947340A (en) * 2021-02-22 2021-06-11 同济大学 Dynamic dispatching method for simulating pheromone mechanism

Cited By (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0774068A (en) * 1993-09-02 1995-03-17 Matsushita Electric Ind Co Ltd Product treating device and method for determining product treatment
JPWO2001075541A1 (en) * 2000-04-04 2004-04-30 富士通株式会社 Production management network system, production management method, and recording medium recording production management program
US6856848B2 (en) 2000-04-24 2005-02-15 Matsushita Electric Industrial Co., Ltd. Method and apparatus for controlling progress of product processing
JP2002169996A (en) * 2000-09-22 2002-06-14 Sharp Corp Server device, scheduling control device, production/ physical distribution management system, terminal device, production/physical distribution management method, and computer-readable recording medium with production/physical distribution management program recorded thereon, program for making computer function as scheduling control device, and computer-readable recording medium with the same program recorded thereon
JP4701533B2 (en) * 2001-04-27 2011-06-15 トヨタ自動車株式会社 Product inspection equipment
JP2003050612A (en) * 2001-08-07 2003-02-21 Kawasaki Microelectronics Kk Production management method and system
JP2010165378A (en) * 2002-05-31 2010-07-29 Advanced Micro Devices Inc Calendaring system formed including computer
JP2004078917A (en) * 2002-07-23 2004-03-11 Dell Products Lp Process for optimization and synchronization for manufacture
JP4559045B2 (en) * 2002-07-23 2010-10-06 デル・プロダクツ・エル・ピー Manufacturing optimization and synchronization process
JP2016151962A (en) * 2015-02-18 2016-08-22 澁谷工業株式会社 Schedule management system
WO2016132812A1 (en) * 2015-02-18 2016-08-25 澁谷工業株式会社 Schedule management system
US10783470B2 (en) 2015-02-18 2020-09-22 Shibuya Corporation Schedule management system
CN112947340A (en) * 2021-02-22 2021-06-11 同济大学 Dynamic dispatching method for simulating pheromone mechanism

Also Published As

Publication number Publication date
JP3283951B2 (en) 2002-05-20

Similar Documents

Publication Publication Date Title
US5442561A (en) Production management system and its application method
US6434440B1 (en) Production estimate management system
Johri Practical issues in scheduling and dispatching in semiconductor wafer fabrication
US20100268367A1 (en) Method for bin-based control
WO1996030767A1 (en) Automatic analysis system
Wang et al. Lean-pull strategy for order scheduling problem in a multi-site semiconductor crystal ingot-pulling manufacturing company
JP3283951B2 (en) Production management method and system
Crist et al. Prioritising production and engineering lots in wafer fabrication facilities: a simulation study
CN116757464B (en) Production plan management method, system, equipment and readable storage medium
JPH06203042A (en) Production line plan generating method
JPH06176032A (en) System and method for production control
JP2007213141A (en) Personnel distribution system, personnel distribution method, personnel distribution program, and recording medium with the program recorded thereon
JPH11345267A (en) Method and system for supporting inventory management job
US20040193291A1 (en) Production management method using delivery date prediction
JP2800795B2 (en) Production control method and production control device
JPH06176031A (en) System and method for production control
US7565218B2 (en) Method and system of prioritization for managing manufacturing processes
JP2973884B2 (en) Production control device
JPH0561507A (en) Job shop production control system
JPH06187356A (en) Production control system
US20020198617A1 (en) System and method for controlling priority of lots employed in MES
JP5359311B2 (en) Workpiece manufacturing time prediction method, manufacturing date prediction method, arrival time prediction method, arrival date prediction method, workpiece manufacturing time prediction device, and arrival time prediction device
US8666529B2 (en) Controlling non-process of record (POR) process limiting yield (PLY) inspection work
JP5359312B2 (en) Manufacturing line process management method and process management system
JP2005208891A (en) Control apparatus and processing system

Legal Events

Date Code Title Description
LAPS Cancellation because of no payment of annual fees