JPH0625485B2 - Installation and replacement method of isolator for seismic isolation structure - Google Patents
Installation and replacement method of isolator for seismic isolation structureInfo
- Publication number
- JPH0625485B2 JPH0625485B2 JP26197885A JP26197885A JPH0625485B2 JP H0625485 B2 JPH0625485 B2 JP H0625485B2 JP 26197885 A JP26197885 A JP 26197885A JP 26197885 A JP26197885 A JP 26197885A JP H0625485 B2 JPH0625485 B2 JP H0625485B2
- Authority
- JP
- Japan
- Prior art keywords
- isolator
- new
- horizontal plate
- upper structure
- replacement
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Buildings Adapted To Withstand Abnormal External Influences (AREA)
- Working Measures On Existing Buildindgs (AREA)
Description
【発明の詳細な説明】 (産業上の利用分野) この発明は免震構造用アイソレータと上下の構造物に損
傷を与えることなくアイソレータの回収と設置を行う、
免震構造用アイソレタータの設置・取り替え工法に関す
るものである。DETAILED DESCRIPTION OF THE INVENTION (Industrial field of application) The present invention collects and installs an isolator for a seismic isolation structure without damaging the upper and lower structures.
The present invention relates to a method for installing and replacing isolators for seismic isolation structures.
(発明が解決しようとする問題点) 積層ゴムベアリングをアイソレータとして使用する免震
構造では、耐久性確認のための試験の他、老朽化したア
イソレータの点検を行う場合にアイソレータを回収する
必要が生ずるが、従来、試験や点検を見込んだ回収作業
は重視されていないためアイソレータの回収は上部構造
物全体をジャッキによって上昇させ、支持した状態で行
われることになり、大がかりな作業を強いられる。一部
のアイソレータのみを回収する場合にはその周辺にジャ
ッキを設置すれば足りるが、上下構造物間の距離が一定
であるためアイソレータと構造物の少なくともいずれか
を部分的に破壊する犠牲が払われることになる。(Problems to be solved by the invention) With a seismic isolation structure that uses laminated rubber bearings as an isolator, it is necessary to collect the isolator when performing inspections on the aged isolator in addition to the tests for confirming durability. However, conventionally, the recovery work that anticipates a test or inspection has not been emphasized, and therefore the recovery of the isolator is performed in a state where the entire upper structure is lifted by the jack and is supported, which requires a large-scale work. When only some of the isolators are to be collected, it is sufficient to install a jack around them, but since the distance between the upper and lower structures is constant, there is a sacrifice to partially destroy at least one of the isolators and structures. Will be seen.
また後者の方法では交換される新規アイソレータは無応
力状態で設置されるが、積層ゴムベアリングの鉛直剛性
の非線形特性によりアイソレータには上部構造物の支持
時に鉛直下方への沈み込みが発生するため、交換後に上
部構造物躯体の、各アイソレータ位置における鉛直荷重
による応力が変動し、構造物に応力の再分配が生じる結
果になる。Also, in the latter method, the new isolator to be replaced is installed in a stress-free state, but due to the non-linear characteristics of the vertical rigidity of the laminated rubber bearing, the isolator will have a vertical dip when supporting the upper structure. After replacement, the stress due to the vertical loading of the superstructure skeleton at each isolator position will fluctuate, resulting in stress redistribution in the structure.
この発明はアイソレータの回収に伴う諸問題に着目して
なされたもので、これらを解決する方法を提案しようと
するものである。The present invention has been made focusing on various problems associated with the collection of isolators, and is intended to propose a method for solving these problems.
(問題点を解決するための手段) 本発明ではアイソレータと上部構造物,または下部構造
物との間に取り替え用ジョイントを介在させておくこと
によりアイソレータと構造物のいずれにも損傷を与える
ことなくアイソレータの回収を行い、また交換される新
規アイソレータに旧アイソレータに作用していた圧力と
同等の圧力を加えた状態でこれを設置することにより上
部構造物への応力の再分配の発生を防止する。(Means for Solving Problems) In the present invention, a replacement joint is interposed between the isolator and the upper structure or the lower structure without damaging either the isolator or the structure. Prevents redistribution of stress to the upper structure by recovering the isolator and installing it under the same pressure as the pressure acting on the old isolator on the new isolator to be replaced. .
アイソレータの上端と下端には上部構造物と下部構造物
との接続用に水平プレートが接続され、そのいずれか一
方に、プレートを組み立てて構成された取り替え用ジョ
イントが接続される。アイソレータは下部構造物上に設
置され、このアイソレータ上に構築された上部構造物を
使用に供した状態でアイソレータの回収と新規アイソレ
ータの設置が行われる。Horizontal plates are connected to the upper and lower ends of the isolator for connecting the upper structure and the lower structure, and a replacement joint formed by assembling the plates is connected to either one of the horizontal plates. The isolator is installed on the lower structure, and the isolator is collected and a new isolator is installed while the upper structure constructed on the isolator is used.
既設の旧アイソレータは上部構造物をジャッキにより支
承し、上部構造物と下部構造物間の距離を保った状態
で、水平プレートを残して取り替え用ジョイントと共に
回収される。残された水平プレートには新規アイソレー
タが接続され、新規アイソレータの他方の水平プレート
に新規取り替え用ジョイントとが据え付けられる。新規
取り替え用ジョイントの新規アイソレータ側には新規ア
イソレータの他方の水平プレートに対向してこれを包囲
し、水平プレートが嵌合する樹脂注入用プレートが接続
されている。The existing old isolator supports the upper structure with a jack, and with the distance between the upper structure and the lower structure kept, it is recovered together with the replacement joint leaving the horizontal plate. A new isolator is connected to the remaining horizontal plate, and a new replacement joint is installed on the other horizontal plate of the new isolator. On the new isolator side of the new replacement joint, there is connected a resin injecting plate which faces the other horizontal plate of the new isolator so as to surround the other horizontal plate and which is fitted with the horizontal plate.
新規取り替え用ジョイントの樹脂注入用プレートと、こ
れに対向する新規アイソレータの水平プレート間には樹
脂が注入され、その注入圧力によって新規アイソレータ
に、旧アイソレータに作用していた圧力と同等の圧力が
鉛直方向に加えられる。Resin is injected between the resin injection plate of the new replacement joint and the horizontal plate of the new isolator facing it, and the injection pressure causes the new isolator to have a vertical pressure equivalent to the pressure acting on the old isolator. Added in direction.
アイソレータと上部構造物,または下部構造物との間に
取り替え用ジョイントが介在することにより取り替え用
ジョイントを切断するのみで上部構造物と下部構造物間
の距離を保ったままアイソレータの回収と新規アイソレ
ータの設置作業が行え、上部構造物全体をジャッキによ
って上昇させる必要がなくなり、またアイソレータと構
造物のいずれにも損傷は及ばない。The replacement joint is interposed between the isolator and the upper structure or the lower structure, so that the replacement joint is simply cut and the isolator is recovered and the new isolator is maintained while keeping the distance between the upper structure and the lower structure. The installation work can be performed, and it is not necessary to raise the entire upper structure by jacking, and neither the isolator nor the structure is damaged.
また新規アイソレータに旧アイソレータの圧力と同等の
圧力が導入されることにより、新規アイソレータが上部
構造物を支持することにより鉛直下方への沈み込みがな
くなり、沈み込みに伴う上部構造物躯体の応力の変動が
回避され、応力の再分配が防止される。In addition, by introducing a pressure equivalent to the pressure of the old isolator into the new isolator, the new isolator supports the upper structure, so that there is no vertical subsidence, and the stress of the upper structure skeleton due to the subsidence Variations are avoided and stress redistribution is prevented.
新規アイソレータへの加圧後、ジャッキを撤去してアイ
ソレータの取り替え作業が完了する。After pressurizing the new isolator, the jack is removed and the isolator replacement work is completed.
(実施例) 以下本発明を一実施例を示す図面に基づいて説明する。(Example) The present invention will be described below with reference to the drawings illustrating an example.
この発明は第1図に示すようにプレートを組み立てて構
成された取り替え用ジョイント2が接続されたアイソレ
ータ1を下部構造物7上に設置し、このアイソレータ1
上に構築された上部構造物Aを使用に供した状態でアイ
ソレータ1の回収と新規アイソレータ1′の設置を行う
方向である。実施例では取り替え用ジョイント2をアイ
ソレータ1と上部構造物Aとの間に配置しているが、下
部構造物7との間に配置する場合もある。The present invention installs an isolator 1 connected to a replacement joint 2 constructed by assembling plates as shown in FIG.
This is the direction in which the isolator 1 is recovered and the new isolator 1'is installed while the upper structure A constructed above is used. In the embodiment, the replacement joint 2 is arranged between the isolator 1 and the upper structure A, but it may be arranged between the isolator 1 and the lower structure 7.
アイソレータ1の上端と下端にはそれぞれ上部構造物A
と下部構造物7との接続のための上部水平プレート3と
下部水平プレート4が着脱自在に接続される。The upper structure A is provided at the upper and lower ends of the isolator 1, respectively.
The upper horizontal plate 3 and the lower horizontal plate 4 for connecting the lower structure 7 and the lower structure 7 are detachably connected.
取り替え用ジョイント2は第2図に示すようにプレート
2aを組み立てて構成され、上部構造物Aとの間に配置さ
れた実施例の場合は例えば第1図に示すように上部構造
物Aの柱5の基部に接合されたボトムプレート6にボル
ト等により接合される。The replacement joint 2 is a plate as shown in FIG.
In the case of an embodiment constructed by assembling 2a and arranged between the upper structure A and the upper structure A, for example, as shown in FIG. 1, a bolt or the like is attached to the bottom plate 6 joined to the base of the pillar 5 of the upper structure A. Are joined by.
アイソレータ1は上部水平プレート3,または下部水平
プレート4において取り替え用ジョイント2に接合さ
れ、他方側の水平プレート、実施例の場合は下部水平プ
レート4において下部構造物7の、例えばコンクリート
基礎にアンカーボルト8によって固定される。The isolator 1 is joined to the replacement joint 2 in the upper horizontal plate 3, or in the lower horizontal plate 4, and in the other horizontal plate, in the case of the lower horizontal plate 4 in the embodiment an anchor bolt to the lower structure 7, for example a concrete foundation. Fixed by 8.
取り替え用ジョイント2はアイソレータ1の回収時に中
間部で切断され、アイソレータ1の上部水平プレート3
と共に上部構造物Aから取り外され、アイソレータ1が
下部水平プレート4を残して回収される。The replacement joint 2 is cut at an intermediate portion when the isolator 1 is collected, and the upper horizontal plate 3 of the isolator 1 is cut.
At the same time, the isolator 1 is removed from the upper structure A, and the isolator 1 is recovered leaving the lower horizontal plate 4.
下部水平プレート4上には新規アイソレータ1′が新た
に設置され、新規アイソレータ1′と上部構造物Aとの
間に新規取り替え用ジョイント2′が据え付けられる。A new isolator 1'is newly installed on the lower horizontal plate 4, and a new replacement joint 2'is installed between the new isolator 1'and the upper structure A.
新規取り替え用ジョイント2′には第3図に示すように
アイソレータ1側、実施例の場合は下部に上部水平プレ
ート3に対向してこれを包囲し、上部水平プレート3が
嵌合する樹脂注入用プレート9が接続されており、新規
アイソレータ1′との接続後に樹脂注入用プレート9と
上部水平プレート3間に樹脂が注入され、新規アイソレ
ータ1′が鉛直方向に旧アイソレータ1に作用していた
圧力と同等になるまで加圧される。As shown in FIG. 3, a new replacement joint 2'is provided on the isolator 1 side, and in the case of the embodiment, the upper horizontal plate 3 is opposed to and surrounded by the lower horizontal plate 3 for resin injection into which the upper horizontal plate 3 is fitted. The plate 9 is connected, the resin is injected between the resin injecting plate 9 and the upper horizontal plate 3 after the connection with the new isolator 1 ′, and the new isolator 1 ′ acts on the old isolator 1 in the vertical direction. It is pressurized until it becomes equal to.
取り替え用ジョイント2の切断から新規アイソレータ1
の加圧までの作業は上部構造物Aをジャッキ10により支
承し、上部構造物Aと下部構造物7間の距離を保った状
態で行われる。From cutting the replacement joint 2 to the new isolator 1
The work up to the pressurization is carried out with the upper structure A supported by the jack 10 and the distance between the upper structure A and the lower structure 7 maintained.
ここでアイソレータ1の設置から回収と新規アイソレー
タ1′の設置までの施工手順を第4図により説明する。Here, the construction procedure from installation of the isolator 1 to collection and installation of the new isolator 1'will be described with reference to FIG.
まず下部構造物7に下部水平プレート4をアンカーボル
ト8により固定し(I)、下部水平プレート4上にアイ
ソレータ1を設置し(II)、続いてアイソレータ1上に
取り替え用ジョイント2を接続し(III)、上部構造物
Aを構築する(IV)。ここまでは回収を前提としたアイ
ソレータ1の設置の工程である。First, the lower horizontal plate 4 is fixed to the lower structure 7 by the anchor bolts 8 (I), the isolator 1 is installed on the lower horizontal plate 4 (II), and then the replacement joint 2 is connected on the isolator 1 ( III), construct superstructure A (IV). Up to this point, the process of installing the isolator 1 is premised on recovery.
アイソレータ1の回収に先立ち、アイソレータ1の周囲
の上部構造物Aと下部構造物7間にジャッキ10を設置し
(V)、ジャッキ10によって上部構造物Aの荷重をアイ
ソレータ1の取り替え作業中支持する。Prior to the recovery of the isolator 1, a jack 10 is installed between the upper structure A and the lower structure 7 around the isolator 1 (V), and the jack 10 supports the load of the upper structure A during the replacement work of the isolator 1. .
次に取り替え用ジョイント2を中間分で切断して上部構
造物A側とアイソレータ1側とに分割し(VI)、それぞ
れを上部水平プレート3と共に回収した後(VII)、ア
イソレータ1を下部水平プレート4から切り離して回収
する(VIII)。Next, the replacement joint 2 is cut at an intermediate portion to divide it into the upper structure A side and the isolator 1 side (VI), and after collecting each with the upper horizontal plate 3 (VII), the isolator 1 is moved to the lower horizontal plate. Separate from 4 and collect (VIII).
引き続き、新規アイソレータ1′を下部水平プレート4
に設置すると共に(IX)、その上に新規取り替え用ジョ
イント2′を接続し(X)、樹脂注入用プレート9と上
部水平プレート3間に樹脂を注入する(XI)。樹脂の
注入によって新規アイソレータ1′に旧アイソレータ1
に作用していた圧力と同等の圧力が加えられたところ
で、バルブをロックし(XII)、ジャッキ10をを撤去し
てアイソレータ1の取り替え作業が完了する。Then, install the new isolator 1'on the lower horizontal plate 4
(IX), a new replacement joint 2'is connected thereto (X), and resin is injected between the resin injection plate 9 and the upper horizontal plate 3 (XI). Old isolator 1 is added to new isolator 1'by injection of resin.
When a pressure equivalent to the pressure acting on the valve is applied, the valve is locked (XII), the jack 10 is removed, and the replacement work of the isolator 1 is completed.
ここでは取り替え用ジョイト2を上部構造物A側に設置
した場合の実施例によって説明したが、下部構造物7側
に設置した場合も同様の要領で施工される。Although the example in which the replacement joit 2 is installed on the side of the upper structure A has been described here, the same procedure can be applied to the case where it is installed on the side of the lower structure 7.
(発明の効果) この発明は以上の通りであり、上部構造物,または下部
構造物との間に取り替え用ジョイントを介在させてアイ
ソレータを設置しているため取り替え用ジョイントを切
断するのみで上部構造物と下部構造物間の距離を保ち、
上部構造物を使用状態においたままアイソレータの回収
と新規アイソレータの設置作業を行うことができ、上部
構造物全体をジャッキによって上昇させる必要がなく、
またアイソレータを構造物のいずれにも損傷を及ぼす事
態を回避することができる。(Effects of the Invention) The present invention is as described above. Since the isolator is installed with the replacement joint interposed between the upper structure and the lower structure, the upper structure can be simply cut. Keep the distance between the object and the substructure,
It is possible to recover the isolator and install a new isolator while keeping the upper structure in use, and there is no need to raise the entire upper structure with a jack.
Further, it is possible to avoid a situation where the isolator damages any structure.
また新規アイソレータは旧アイソレータの圧力と同等の
圧力が加えられた状態で設置されるため新規アイソレー
タが上部構造物を支持することによる鉛直下方への沈み
込みがなくなり、沈み込みに伴う上部構造物躯体の応力
の変動が回避され、応力の再分配とそれによる上部構造
物の不同沈下を防止することができる。In addition, the new isolator is installed under a pressure equivalent to that of the old isolator, so the new isolator does not sink vertically below because it supports the upper structure. It is possible to avoid the fluctuation of the stress of the above and prevent the redistribution of the stress and the uneven settlement of the upper structure due to the redistribution of the stress.
第1図は上下構造物間へのアイソレータの設置状態を示
した縦断面図、第2図は切り替え用ジョイントを示した
斜視図、第3図は新規アイソレータの設置後の加圧状態
を示した縦断面図、第4図−I〜XIIはアイソレータの
設置から新規アイソレータの設置までの手順を示した概
要図である。 A……上部構造物、1……アイソレータ、1′……新規
アイソレータ、2……取り替え用ジョイント、2′……
新規取り替え用ジョイント、3……上部水平プレート、
4……下部水平プレート、5……柱、6……ボトムプレ
ート、7……下部構造物、8……アンカーボルト、9…
…樹脂注入用プレート、10……ジャッキ。FIG. 1 is a vertical cross-sectional view showing an installation state of an isolator between upper and lower structures, FIG. 2 is a perspective view showing a switching joint, and FIG. 3 is a pressurization state after installation of a new isolator. A vertical cross-sectional view and FIGS. 4A to 4I are schematic diagrams showing a procedure from installation of an isolator to installation of a new isolator. A ... Upper structure, 1 ... Isolator, 1 '... New isolator, 2 ... Replacement joint, 2' ...
New replacement joint, 3 ... upper horizontal plate,
4 ... Lower horizontal plate, 5 ... Pillar, 6 ... Bottom plate, 7 ... Lower structure, 8 ... Anchor bolt, 9 ...
… Resin injection plate, 10… Jack.
フロントページの続き (72)発明者 池永 雅良 神奈川県藤沢市石川1632 オイレス工業株 式会社藤沢寮Front page continuation (72) Inventor Masayoshi Ikenaga 1632 Ishikawa, Fujisawa-shi, Kanagawa OILES Industrial Corporation Fujisawa Dormitory
Claims (1)
ートを組み立てて構成された取り替え用ジョイントが接
続されたアイソレータを下部構造物上に設置し、このア
イソレータ上に構築された上部構造物を使用に供した状
態で前記アイソレータの回収と新規アイソレータの設置
を行う工法であり、上部構造物をジャッキにより支承し
た状態で、水平プレートを残して取り替え用ジョイント
及びアイソレータを撤去し、次いで新規アイソレータを
残された水平プレートに接続すると共に、新規アイソレ
ータの他方の水平プレートに対向してこれを包囲し、水
平プレートが嵌合する樹脂注入用プレートが接続された
新規取り替え用ジョイントを新規アイソレータの他方の
水平プレートに据え付け、上記樹脂注入用プレートと新
規アイソレータの他方の水平プレート間に樹脂を注入
し、新規アイソレータを取り替え前のアイソレータに作
用していた圧力と同等になるまで加圧した後、ジャッキ
を撤去する、という工程からなる免震構造用アイソレー
タの設置・取り替え工法。1. An isolator in which a replacement joint constructed by assembling plates is connected to a horizontal plate at an upper end or a lower end is installed on a lower structure, and an upper structure constructed on this isolator is used. This is a construction method in which the above isolator is recovered and a new isolator is installed in the state of being used for the construction.With the upper structure supported by a jack, the replacement joint and the isolator are removed leaving the horizontal plate, and then the new isolator Connected to the other horizontal plate of the new isolator, facing the other horizontal plate of the new isolator and surrounding it, and connecting a new replacement joint with the resin injection plate to which the horizontal plate fits to the other horizontal plate of the new isolator. Installed on the plate, the resin injection plate and the new isolator Installation of an isolator for seismic isolation structure consisting of the steps of injecting resin between the two horizontal plates, pressurizing the new isolator to the same pressure as the isolator before replacement, and then removing the jack.・ Replacement method.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP26197885A JPH0625485B2 (en) | 1985-11-21 | 1985-11-21 | Installation and replacement method of isolator for seismic isolation structure |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP26197885A JPH0625485B2 (en) | 1985-11-21 | 1985-11-21 | Installation and replacement method of isolator for seismic isolation structure |
Publications (2)
Publication Number | Publication Date |
---|---|
JPS62121281A JPS62121281A (en) | 1987-06-02 |
JPH0625485B2 true JPH0625485B2 (en) | 1994-04-06 |
Family
ID=17369300
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP26197885A Expired - Fee Related JPH0625485B2 (en) | 1985-11-21 | 1985-11-21 | Installation and replacement method of isolator for seismic isolation structure |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPH0625485B2 (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH09100634A (en) * | 1995-10-06 | 1997-04-15 | Soken Sekkei:Kk | Method of repairing work of base isolation for existing building |
KR101449956B1 (en) * | 2013-03-05 | 2014-10-14 | 한국수력원자력 주식회사 | Isolating Device, Method of Changing Isolating Structure Part and Method of Controlling Load of Isolating Structure Part |
WO2016158382A1 (en) * | 2015-04-03 | 2016-10-06 | 三菱重工業株式会社 | Method for replacing base isolation device, and base isolation structure |
Families Citing this family (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH0376973A (en) * | 1989-08-18 | 1991-04-02 | Shimizu Corp | Replacement of vibration-proof laminated rubber |
JP6049526B2 (en) * | 2013-03-29 | 2016-12-21 | 中部電力株式会社 | How to handle seismic isolation devices and seismic isolation components |
-
1985
- 1985-11-21 JP JP26197885A patent/JPH0625485B2/en not_active Expired - Fee Related
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH09100634A (en) * | 1995-10-06 | 1997-04-15 | Soken Sekkei:Kk | Method of repairing work of base isolation for existing building |
KR101449956B1 (en) * | 2013-03-05 | 2014-10-14 | 한국수력원자력 주식회사 | Isolating Device, Method of Changing Isolating Structure Part and Method of Controlling Load of Isolating Structure Part |
WO2016158382A1 (en) * | 2015-04-03 | 2016-10-06 | 三菱重工業株式会社 | Method for replacing base isolation device, and base isolation structure |
JP2016196750A (en) * | 2015-04-03 | 2016-11-24 | 三菱重工業株式会社 | Method for replacing base isolation device and base isolation structure |
Also Published As
Publication number | Publication date |
---|---|
JPS62121281A (en) | 1987-06-02 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP2008163636A (en) | Base isolation device exchanging method | |
JP2014114581A (en) | Aseismic base isolation bearing mechanism and aseismic base isolation building | |
JP6022631B1 (en) | Seismic isolation device replacement method and seismic isolation structure | |
JPH0625485B2 (en) | Installation and replacement method of isolator for seismic isolation structure | |
JP2929923B2 (en) | Shear deformation correction structure of base-isolated bearing | |
KR102433336B1 (en) | Steel pipe girder with guide-plate and the construction method thereof | |
JP4187887B2 (en) | Seismic isolation method for existing buildings and the seismic isolation mechanism used therefor | |
JP2005220947A (en) | Structure of base isolation part using base isolation device in building and method for replacing base isolation device of base isolation part | |
KR101214531B1 (en) | A lifting apparatus of upper structure of bridge and lifting method of upper structure of bridge by using | |
CN210685474U (en) | Concrete underpins structure | |
JPH0323003Y2 (en) | ||
KR20150144155A (en) | Construction method of bridge bearing replacement and bridge bearing replacement thereof | |
JPS6337230B2 (en) | ||
JPS6022127B2 (en) | Main girder launching equipment for bridges, etc. | |
JP2842192B2 (en) | Shear deformation correction structure of base-isolated bearing | |
JP2766882B2 (en) | Detachment method of seismic isolation device and detachment device used for the method | |
JP3829458B2 (en) | Attaching the vibration control device to the building | |
JP4120515B2 (en) | Horizontal displacement restraint device for superstructure in seismic isolation structure | |
JP3079420B2 (en) | Precast concrete girder installation structure and method, and PC girder | |
JPH02104833A (en) | Changing method of earthquake-proofing isolator | |
JPH09177031A (en) | Provisionally receiving facility for jack in repair work of main girder constituting elevated bridge, etc. | |
JP3127360B2 (en) | Exchangeable elastic bearing device for bridge and its installation method | |
JP2000045542A (en) | Foundation base isolation method for existing structure | |
JPH1113306A (en) | Building supporting method at installation of vibration isolation device | |
JPH0317013B2 (en) |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
LAPS | Cancellation because of no payment of annual fees |