JPH06176026A - Work progress rate computing system - Google Patents

Work progress rate computing system

Info

Publication number
JPH06176026A
JPH06176026A JP32307092A JP32307092A JPH06176026A JP H06176026 A JPH06176026 A JP H06176026A JP 32307092 A JP32307092 A JP 32307092A JP 32307092 A JP32307092 A JP 32307092A JP H06176026 A JPH06176026 A JP H06176026A
Authority
JP
Japan
Prior art keywords
progress rate
man
work
hour
input means
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP32307092A
Other languages
Japanese (ja)
Inventor
Hiroshi Imamine
博司 今峯
Isao Osumi
功 大隅
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sekisui Chemical Co Ltd
Original Assignee
Sekisui Chemical Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sekisui Chemical Co Ltd filed Critical Sekisui Chemical Co Ltd
Priority to JP32307092A priority Critical patent/JPH06176026A/en
Publication of JPH06176026A publication Critical patent/JPH06176026A/en
Pending legal-status Critical Current

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/30Computing systems specially adapted for manufacturing

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

PURPOSE:To provide the work progress rate computing system which can calcu late a progress rate in consideration of the actual state according to the prog ress state and perform plan control of higher quality. CONSTITUTION:This computing system has an actual result man-hour input means 11 for inputting the actual result man-hours of respective work units, a progress rate input means 12 for inputting the progress rates of the respective work units, a plan man-hour input means 13 for inputting the plan man-hours of unstarted work units among the work units, and an arithmetic means 14 which calculates the progress rate to the whole work by processing the input values from the respective input means 11, 12, and 13. The computing means 14 processes the input values according to an expression to obtain the progress rate to the whole work.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】この発明は、研究開発,建設工事
等の業務のプロジェクト管理に用いられ、業務の進捗率
を演算するシステムに関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a system which is used for project management of work such as research and development and construction work and which calculates the progress rate of work.

【0002】[0002]

【従来の技術】この種の業務として、例えば図2に示す
ような図面を作成する場合の業務を例に取って、この場
合の進捗率の算出方法を説明する。
2. Description of the Related Art As a business of this type, a method of calculating a progress rate in this case will be described by taking a business in the case of creating a drawing as shown in FIG. 2, for example.

【0003】まず、1つの業務(図面作成業務)を複数
の単位業務、ここでは、納まり検討1,作図準備2,作
図3,検図4,リスト作成5及び出図6を単位業務から
構成し、各単位業務毎に工数の計画(例えば納まり検討
1では計画工数は5人日)を立てて作業を行う。
First, one work (drawing creation work) is composed of a plurality of unit works, in this case, the settlement examination 1, the drawing preparation 2, the drawing 3, the inspection 4, the list creation 5 and the drawing 6 are composed of the unit work. , The man-hour plan is set for each unit work (for example, the planned man-hour is 5 man-days in the settlement examination 1).

【0004】この作業途中で、進捗率を得るには以下の
ように行う。
During this work, the progress rate is obtained as follows.

【0005】すなわち、この作業途中において、納まり
検討1では、実績工数が10人日、実績進捗率が100
%、作図準備2では、実績工数が15人日、実績進捗率
が100%、作図3では、実績工数が10人日、実績進
捗率が50%、リスト作成5では、実績工数が5人日、
実績進捗率が60%とする。
That is, in the middle of this work, in the final examination 1, the actual man-hour is 10 man-days and the actual progress rate is 100.
%, In Plot Preparation 2, the actual man-hour is 15 man-days, and the actual progress rate is 100%. In Plot 3, the actual man-hour is 10 man-days, the actual progress rate is 50%, and in list creation 5, the actual man-hour is 5 man-days. ,
The actual progress rate is 60%.

【0006】この場合における工数進捗率を演算する
と、下記の数2のように、分母には、計画工数の総和
を、分子には、計画工数と単位業務進捗率との比の総和
をそれぞれ代入することにより、工数進捗率が算出され
る。
When the man-hour progress rate in this case is calculated, the sum of the planned man-hours is assigned to the denominator, and the sum of the ratios of the planned man-hour and the unit work progress rate is assigned to the numerator, as shown in the following Expression 2. By doing so, the man-hour progress rate is calculated.

【0007】[0007]

【数2】 また、工数消化率を演算すると、式(2)のように、分
母には、計画工数の総和を、分子には、実績工数の総和
をそれぞれ代入することにより、工数消化率が算出され
る(ここでは、工数消化率が111%)。
[Equation 2] Further, when the man-hour digestibility is calculated, the man-hour digestibility is calculated by substituting the total sum of the planned man-hours into the denominator and the total sum of the actual man-hours into the numerator, as shown in Expression (2) ( Here, the man-hour digestibility is 111%).

【0008】[0008]

【数3】 上記のような方法で進捗率を演算する場合、当初の計画
(工数読み、所要日数読み)の精度が高い場合、適正な
進捗率の把握が可能である。
[Equation 3] When the progress rate is calculated by the above method, if the accuracy of the initial plan (reading man-hours, reading required days) is high, it is possible to grasp the appropriate progress rate.

【0009】この種の工程管理方法としては、特開昭6
4ー29965号公報に記載されているようなものがあ
る。
As a process control method of this type, Japanese Patent Laid-Open No.
There is one as described in JP-A-4-29965.

【0010】[0010]

【発明が解決しようとする課題】しかしながら、研究開
発テーマ等で、十分な計画精度が得られない場合、実施
段階において、計画された日数や工数では進捗しない事
例が多発し、上述のように算出された進捗率は、実状を
反映しない場合が多い。
[Problems to be Solved by the Invention] However, when sufficient planning accuracy cannot be obtained due to research and development themes, etc., there are many cases where progress does not progress within the planned number of days and man-hours at the implementation stage, and calculation is performed as described above. The progress rate is often not reflected in the actual situation.

【0011】つまり、既に作業が終了し、又は、作業途
中の単位業務における計画工数を上記例のように演算式
に算入すると、この計画工数(例えば作図準備2では、
計画工数10人日)に対して、実績工数((例えば作図
準備2では、計画工数15人日)が異なる場合が多いた
め、現状に即した的確な進捗率を算出するのが難しい。
In other words, if the planned man-hours for the unit work that has already been completed or is in the middle of the work is included in the arithmetic expression as in the above example, the planned man-hours (for example, in the drawing preparation 2,
Since the actual man-hour (for example, the planned man-hour is 15 man-days in the drawing preparation 2) is often different from the planned man-hour 10 days, it is difficult to calculate an accurate progress rate according to the current situation.

【0012】そこで、この発明は、進捗状況に応じて、
実状を踏まえた進捗率が算出できて、より質の高い計画
管理を可能とする業務進捗率演算システムを提供するこ
とを課題としている。
Therefore, according to the present invention,
The challenge is to provide a business progress rate calculation system that can calculate the progress rate based on the actual situation and enables higher quality plan management.

【0013】[0013]

【課題を解決するための手段】この発明は、上記課題を
解決するため、複数の単位業務から一つの業務が構成さ
れ、該業務の進捗率を算出する業務進捗率演算システム
において、各単位業務の実績工数を入力する実績工数入
力手段と、各単位業務の進捗率を入力する進捗率入力手
段と、複数の単位業務の内の未着手の単位業務の計画工
数を入力する計画工数入力手段と、該各入力手段から入
力値を演算して業務全体に対する進捗率を算出する演算
手段とを有し、該演算手段では、前記入力値を以下の式
に基づいて演算することにより、
In order to solve the above problems, the present invention provides a task progress rate calculation system in which one task is composed of a plurality of unit tasks and the progress rate of the task is calculated. The actual man-hour input means for inputting the actual man-hours, the progress-rate input means for inputting the progress rate of each unit work, and the planned man-hour input means for inputting the planned man-hour of the unstarted unit work among the plurality of unit works. , And an operation means for calculating an input value from each of the input means to calculate a progress rate for the entire work, wherein the operation means calculates the input value based on the following equation:

【数4】 業務全体に対する進捗率を得る業務進捗率演算システム
としたことを特徴としている。
[Equation 4] It is characterized by a business progress rate calculation system that obtains the progress rate for the entire business.

【0014】[0014]

【作 用】かかる手段によれば、実績工数入力手段にて
各単位業務の実績工数を、進捗率入力手段にて各単位業
務の進捗率を、計画工数入力手段にて複数の単位業務の
内の未着手の単位業務の計画工数をそれぞれ演算手段に
入力する。
[Operation] According to such means, the actual man-hour input means indicates the actual man-hours of each unit work, the progress rate input means indicates the progress rate of each unit work, and the planned man-hour input means selects among a plurality of unit work. The planned man-hours of the unstarted unit work are input to the respective calculation means.

【0015】そして、演算手段では、上記数式に基づい
て演算することにより、業務全体に対する進捗率が得ら
れることとなる。
Then, the calculation means obtains the progress rate for the whole work by performing the calculation based on the above mathematical formula.

【0016】これによれば、従来と異なり、既に作業が
終了している単位業務の実績工数を算入することによ
り、より適正な進捗率が得られる。
According to this, unlike the conventional method, a more appropriate progress rate can be obtained by including the actual man-hours of the unit work already completed.

【0017】[0017]

【実施例】以下、この発明を実施例に基づいて説明す
る。
EXAMPLES The present invention will be described below based on examples.

【0018】図1はこの発明の一実施例を示すものであ
る。
FIG. 1 shows an embodiment of the present invention.

【0019】この発明は、図1に示すように、各単位業
務の実績工数を入力する実績工数入力手段11と、各単
位業務の進捗率を入力する進捗率入力手段12と、複数
の単位業務の内の未着手の単位業務の計画工数を入力す
る計画工数入力手段13と、該各入力手段から入力値を
演算して業務全体の進捗率を算出する演算手段14とを
有している。
The present invention, as shown in FIG. 1, includes actual man-hour input means 11 for inputting the actual man-hour of each unit work, progress rate input means 12 for inputting the progress rate of each unit work, and a plurality of unit work. It has a planned man-hour input means 13 for inputting a planned man-hour of a unit work which has not yet been started, and a calculation means 14 for calculating an input value from each of the input means and calculating a progress rate of the whole work.

【0020】この演算手段14では、前記入力値を以下
の式に基づいて演算することにより、
The calculation means 14 calculates the input value based on the following equation,

【数5】 業務全体に対する進捗率を得るようにしている。[Equation 5] I try to get the progress rate for the whole work.

【0021】以下に、図2に示す図面作成業務を例に取
って説明する。
The drawing making operation shown in FIG. 2 will be described below as an example.

【0022】すなわち、実績工数入力手段11から、各
単位業務において実際に掛かった実績工数、ここでは、
図2に示すように、納まり検討1では10人日、作図準
備2では15人日、作図3で10人日、リスト作成5で
は5人日を演算手段14に入力する。
That is, from the actual man-hour input means 11, the actual man-hour actually applied in each unit work, here,
As shown in FIG. 2, 10 man days are entered in the settlement examination 1, 15 man days are drawn in the drawing preparation 2, 10 man days are drawn in the drawing 3, and 5 man days are entered in the list creation 5 into the computing means 14.

【0023】また、進捗率入力手段12から、各単位業
務における実績進捗率、ここでは、納まり検討1では1
00%、作図準備2では100%、作図3で50%、リ
スト作成5では60%を演算手段14に入力する。
Further, from the progress rate input means 12, the actual progress rate in each unit work, here, 1 in the examination 1
00%, 100% in drawing preparation 2, 50% in drawing 3, and 60% in list creation 5 are input to the calculation means 14.

【0024】さらに、計画工数入力手段13から、未着
手の計画工数、ここでは、検図4では5人日、出図6で
は1人日を演算手段14に入力する。
Further, from the planned man-hour input means 13, the unmanned planned man-hour, here 5 man days in the inspection 4 and 1 man day in the FIG.

【0025】そして、演算手段14では、それら入力値
に基づいて、上記数5式に上記各入力値を代入すると、
以下の数6式のようになる。
Then, in the computing means 14, when the above input values are substituted into the above equation 5 based on the input values,
The following Expression 6 is obtained.

【0026】[0026]

【数6】 ここでは、分母に、各単位業務の実績工数及び単位業務
の進捗率の比(ここでは10/100%,15/100
%,10/50%,5/60)、未着手業務の計画工数
(ここでは5,1)の総和を取り、分子に、実績工数
(10,15,10,5)の総和を取り、それらを演算
することにより、業務全体に進捗率(67%)が得られ
る。
[Equation 6] Here, in the denominator, the ratio of the actual man-hours of each unit work and the progress rate of the unit work (here, 10/100%, 15/100
%, 10/50%, 5/60), the total of the planned man-hours (5, 1 here) of unstarted work, and the sum of the actual man-hours (10, 15, 10, 5) is taken as the numerator. By calculating, the progress rate (67%) can be obtained for the entire work.

【0027】これにより、適正な進捗率が算出されるこ
ととなる。つまり、既に作業が終了し、又は、作業途中
の単位業務においては、従来のように計画工数を使用す
ることなく、実績工数と実績進捗率との比を分母に取る
ことにより、より実施状況に応じた適正な進捗率が算出
されることとなる。
As a result, an appropriate progress rate can be calculated. In other words, in the unit work that has already been completed or is in the middle of work, the planned man-hours are not used as in the past, and the ratio of the actual man-hours to the actual progress rate is taken as the denominator. The appropriate progress rate will be calculated accordingly.

【0028】従って、事前に正確な工数読み等が行えな
い業務についても、従来より適正な進捗率を得ることが
できる。従って、算出した進捗率に基づいて、工数計画
を修正することにより、より適正な業務の推進を図るこ
とができる。
Therefore, it is possible to obtain a more appropriate progress rate than before even in the case of work in which accurate manhour reading cannot be performed in advance. Therefore, by correcting the man-hour plan based on the calculated progress rate, it is possible to promote more appropriate work.

【0029】なお、実績工数を必要期間に置き換えるこ
とで、日程的な面での進捗率を算出することも可能であ
る。
By replacing the actual man-hours with the required period, it is possible to calculate the progress rate in terms of schedule.

【0030】[0030]

【発明の効果】以上説明してきたように、この発明によ
れば、進捗状況に応じて、実状を踏まえた進捗率が算出
できて、より質の高い計画管理を可能とすることができ
る、という実用上有益な効果を発揮する。
As described above, according to the present invention, it is possible to calculate the progress rate based on the actual situation in accordance with the progress situation, and it is possible to perform higher quality plan management. It has a practically useful effect.

【図面の簡単な説明】[Brief description of drawings]

【図1】この発明の業務進捗率演算システムの一実施例
を示すブロック図である。
FIG. 1 is a block diagram showing an embodiment of a business progress rate calculation system of the present invention.

【図2】同実施例の図面作成業務を示すブロック図であ
る。
FIG. 2 is a block diagram showing a drawing creation task of the embodiment.

【符号の説明】[Explanation of symbols]

11 実績工数入力手段 12 進捗率入力手段 13 計画工数入力手段 14 演算手段 11 Actual man-hour input means 12 Progress rate input means 13 Planned man-hour input means 14 Calculation means

Claims (1)

【特許請求の範囲】[Claims] 【請求項1】 複数の単位業務から一つの業務が構成さ
れ、該業務の進捗率を算出する業務進捗率演算システム
において、 各単位業務の実績工数を入力する実績工数入力手段と、
各単位業務の進捗率を入力する進捗率入力手段と、複数
の単位業務の内の未着手の単位業務の計画工数を入力す
る計画工数入力手段と、該各入力手段から入力値を演算
して業務全体に対する進捗率を算出する演算手段とを有
し、 該演算手段では、前記入力値を以下の式に基づいて演算
することにより、 【数1】 業務全体に対する進捗率を得ることを特徴とする業務進
捗率演算システム。
1. A business progress rate calculation system for calculating a progress rate of a single business from a plurality of unit businesses, and an actual manhour input means for inputting the actual manhour of each unit business,
A progress rate input means for inputting a progress rate of each unit work, a planned man-hour input means for inputting a planned man-hour of a unit work that has not yet been started among a plurality of unit works, and an input value is calculated from each of the input means. And a calculation means for calculating the progress rate for the entire work, wherein the calculation means calculates the input value based on the following equation: A work progress rate calculation system characterized by obtaining a progress rate for the whole work.
JP32307092A 1992-12-02 1992-12-02 Work progress rate computing system Pending JPH06176026A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP32307092A JPH06176026A (en) 1992-12-02 1992-12-02 Work progress rate computing system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP32307092A JPH06176026A (en) 1992-12-02 1992-12-02 Work progress rate computing system

Publications (1)

Publication Number Publication Date
JPH06176026A true JPH06176026A (en) 1994-06-24

Family

ID=18150754

Family Applications (1)

Application Number Title Priority Date Filing Date
JP32307092A Pending JPH06176026A (en) 1992-12-02 1992-12-02 Work progress rate computing system

Country Status (1)

Country Link
JP (1) JPH06176026A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH11213069A (en) * 1998-01-27 1999-08-06 Sanyo Electric Co Ltd Computer for medical business and recording medium
CN113723763A (en) * 2021-08-06 2021-11-30 广东伟达智能装备股份有限公司 Order production efficiency management method and device, terminal equipment and storage medium

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH11213069A (en) * 1998-01-27 1999-08-06 Sanyo Electric Co Ltd Computer for medical business and recording medium
CN113723763A (en) * 2021-08-06 2021-11-30 广东伟达智能装备股份有限公司 Order production efficiency management method and device, terminal equipment and storage medium
CN113723763B (en) * 2021-08-06 2024-05-03 广东伟达智能装备股份有限公司 Order production efficiency management method, device, terminal equipment and storage medium

Similar Documents

Publication Publication Date Title
US7860595B2 (en) Production schedule creation device and method, production process control device and method, computer program, and computer-readable recording medium
CA2263386C (en) Scheduling system and scheduling method for reentrant line processes
Trybula Building simulation models without data
Doumeingts GRAI approach to designing and controlling advanced manufacturing system in CIM environment
CN111754200A (en) Service processing method and device
EP1672578A1 (en) Method and system for analyzing the risk of a project
JPH06176026A (en) Work progress rate computing system
JPS63150140A (en) Operation plan preparing device
JP2811827B2 (en) Production scheduling device
JPH07129677A (en) Production simulation device
Ershova et al. Organizational factors for manufacturing defects reduction in small batch production
JPH0728896A (en) System for generating and changing automatically lead time and standard time
JPH05225196A (en) Method and system for scheduling cooperated between sections and knowledge base debugging method
JP2008152350A (en) Working time estimation device, working time estimation method, program and machine-readable recording medium
JP2536066B2 (en) Fuzzy modeling control method
JPH0482661A (en) Changing method for production program
RU2261478C2 (en) Method for synchronizing blocks of data about events with their temporal values
JP2581428B2 (en) Production simulation equipment
JPH02196368A (en) Back-up system for development program
Atherton et al. Detailed simulation for semiconductor manufacturing
CN113450018A (en) Project progress processing method, device and equipment and storage medium
JP2004094827A (en) Software development progress management system
JPH07129668A (en) Work progress control method for job
JPH0441164A (en) Calculation device for work term