JPH06167114A - Prefabricated beam-column structure of reinforcements and application by use thereof - Google Patents
Prefabricated beam-column structure of reinforcements and application by use thereofInfo
- Publication number
- JPH06167114A JPH06167114A JP34557992A JP34557992A JPH06167114A JP H06167114 A JPH06167114 A JP H06167114A JP 34557992 A JP34557992 A JP 34557992A JP 34557992 A JP34557992 A JP 34557992A JP H06167114 A JPH06167114 A JP H06167114A
- Authority
- JP
- Japan
- Prior art keywords
- column
- main bar
- reinforcements
- main
- main reinforcements
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Landscapes
- Reinforcement Elements For Buildings (AREA)
Abstract
Description
【0001】[0001]
【産業上の利用分野】この発明は、柱梁先組み鉄筋体と
それを用いた先組み鉄筋工法に関するものである。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a column-beam pre-assembled rebar body and a pre-assembled rebar construction method using the same.
【0002】[0002]
【従来の技術】建物構築位置の近くに設けられた鉄筋組
立作業エリヤにおいて、二つの柱主筋群間に、柱主筋群
を横断する状態に配置した梁主筋群を架設してなる柱梁
先組み鉄筋体を組み立て、これを揚重機で建物構築位置
に吊り込むようにした先組み鉄筋工法は、既に知られて
いる。2. Description of the Related Art In a reinforcing bar assembly work area provided near a building construction position, a beam-column front assembly is constructed by erection of a beam main bar group arranged in a state of traversing the column main bar group between two column main bar groups. A prefabricated reinforcing bar construction method in which a reinforcing bar body is assembled and is suspended at a building construction position by a lifting machine is already known.
【0003】しかしながら、上記の従来例では、鉄筋組
立作業エリヤで柱梁先組み鉄筋体を組み立てる場合、柱
主筋群を垂直に立てた状態で組立て作業を行うと、梁主
筋群の組立てが高い位置で行われることになり、大規模
な足場が必要になる他、作業能率が悪いばかりでなく、
高所での作業量が多いため、安全上、問題があった。ま
た、高所作業による危険を回避するために、柱主筋群を
横倒しした状態で、柱梁先組み鉄筋体の組立て作業を行
うことも考えられるが、この場合には、組立て作業に必
要な面積が大きくなり、複数の柱梁先組み鉄筋体を並行
して組み立てるにあたっては、広大な鉄筋組立作業エリ
ヤが必要となる。However, in the above-mentioned conventional example, when assembling the post-beam pre-assembled rebar body by the reinforcing bar assembling work area, if the assembling work is performed with the column main bar group standing vertically, the assembly of the beam main bar group is at a high position. In addition to the need for large-scale scaffolding and not only poor work efficiency,
There was a safety problem due to the large amount of work in high places. In addition, in order to avoid the danger of working at heights, it is possible to assemble the column-beam-end-reinforcement bars with the column main reinforcement group lying down.In this case, the area required for the assembly work is However, when assembling a plurality of column-beam-end assembled reinforcing bars in parallel, an enormous reinforcing bar assembly work area is required.
【0004】[0004]
【発明が解決しようとする課題】本発明は、上記の点に
留意してなされたものであって、その目的とするところ
は、柱梁先組み鉄筋体の組立て作業を、狭い面積で能率
良く安全に行えるようにした柱梁先組み鉄筋体とそれを
用いた先組み鉄筋工法を提供することにある。SUMMARY OF THE INVENTION The present invention has been made with the above points in mind, and an object of the present invention is to efficiently perform the work of assembling the column-beam-end assembled rebar body in a small area. An object of the present invention is to provide a column-beam pre-assembled rebar body that can be safely performed and a pre-assembled rebar construction method using the same.
【0005】[0005]
【課題を解決するための手段】上記の目的を達成するた
めに本発明が講じた技術的手段は次のとおりである。即
ち、第1発明による柱梁先組み鉄筋体は、所定の配筋状
態に位置決めして垂直に自立させた柱主筋群と、梁筋所
定位置よりも低位置で且つ柱主筋群を横断する状態に配
置した梁主筋群と、柱主筋群の上端近傍部に固定された
抜止め具とからなり、梁主筋群が抜止め具を上限として
上下方向スライド自在に構成したものである。The technical means taken by the present invention to achieve the above object are as follows. That is, the post-beam pre-assembled rebar body according to the first aspect of the present invention is a column main bar group positioned vertically in a predetermined bar arrangement state and a state in which the bar bar crosses the bar main bar group at a position lower than the beam bar predetermined position. And a retaining member fixed near the upper end of the column principal reinforcement group, and the beam principal reinforcement group is configured to be vertically slidable with the retaining device as an upper limit.
【0006】第2発明による先組み鉄筋工法は、建物構
築位置以外の場所で、所定の配筋状態に位置決めして垂
直に自立させた柱主筋群と、梁筋所定位置よりも低位置
で且つ柱主筋群を横断する状態に配置した梁主筋群と、
柱主筋群の上端近傍部に固定された抜止め具とからな
り、梁主筋群が抜止め具を上限として上下方向スライド
自在に構成されている柱梁先組み鉄筋体を組み立て、こ
の柱梁先組み鉄筋体を建物構築位置に吊り込むことを特
徴としている。In the prefabricated reinforcing bar construction method according to the second aspect of the present invention, a column main bar group that is positioned in a predetermined bar arrangement state and is made to stand vertically at a position other than the building construction position and a position lower than the beam bar predetermined position. Beam main bar group arranged to cross the column main bar group,
Assemble a column-beam-end assembled rebar body that is composed of a retaining tool fixed near the upper end of the column main reinforcement group, and the beam main reinforcement group is configured to be slidable in the vertical direction with the retaining tool as the upper limit. The feature is that the braided bar is suspended at the building construction position.
【0007】[0007]
【作用】上記の構成によれば、柱主筋群を垂直に立てた
状態で、柱梁先組み鉄筋体を組み立てるため、組立て作
業に必要な面積が小さくて済み、例えば、複数の柱梁先
組み体を並行して組み立てるような場合でも、広大な鉄
筋組立作業エリヤが不要であり、それでいて、梁主筋群
の組立て作業は、低位置で行われるので能率良く安全に
作業できる。柱梁先組み鉄筋体を揚重機で建物構築位置
に吊り込む際には、梁主筋群を吊り上げることにより、
梁主筋群が抜止め具に当たる位置まで柱主筋群に対して
上方へスライドし、柱主筋群も一体的に吊り上げられる
ことになる。また、梁主筋群が柱主筋群に対して上下方
向スライド自在であるため、柱梁先組み鉄筋体を建物構
築位置に吊り込んで、柱主筋群の下端部の固定や梁主筋
群の固定を行う際、梁主筋群のレベル調整や柱主筋下端
部の接合作業を容易に行えることになる。According to the above construction, since the column beam front assembly rebar body is assembled in a state where the column main reinforcing bar group is erected vertically, the area required for the assembly work can be small. Even when the bodies are assembled in parallel, the vast area for assembling the reinforcing bars is unnecessary, and yet the assembly work of the beam main bar group can be performed efficiently and safely because it is performed at a low position. When suspending the pillar-beam tip rebar body with a lifting machine at the building construction position, by lifting the beam main reinforcement group,
The beam main bar group slides upward with respect to the column main bar group to a position where the beam main bar group hits the retainer, and the column main bar group is also integrally lifted. In addition, since the beam main bar group is vertically slidable with respect to the column main bar group, the column-beam front braided rebar body is hung at the building construction position to fix the bottom end of the column main bar group and the beam main bar group. At the time of performing, it is possible to easily adjust the level of the beam main bars and join the lower end of the column main bars.
【0008】[0008]
【実施例】以下、本発明の実施例を図面に基づいて説明
する。図1は、本発明に係る柱梁先組み鉄筋体とそれを
用いた先組み鉄筋工法に使用される柱主筋位置決め装置
Aの一例を示す。この柱主筋位置決め装置Aは、柱主筋
群の下端側を所定の配筋状態に位置決めする下部治具1
と、柱主筋群の上端側を所定の配筋状態に位置決めする
上部治具2と、上部治具2を下部治具1に一定姿勢に且
つ着脱自在に支持させるための角パイプ3とから構成さ
れている。Embodiments of the present invention will be described below with reference to the drawings. FIG. 1 shows an example of a post-beam pre-assembled rebar body according to the present invention and a column main bar positioning device A used in a pre-assembled rebar construction method using the same. This column main bar positioning device A is a lower jig 1 for positioning the lower end side of the column main bar group in a predetermined bar arrangement state.
And an upper jig 2 for positioning the upper end side of the column main bar group in a predetermined bar arrangement state, and a square pipe 3 for supporting the upper jig 2 on the lower jig 1 in a fixed posture and detachably. Has been done.
【0009】前記下部治具1は、アングル材等によって
構成された矩形状の枠体1a及びその長辺の中央部間に
架設された連結枠1bと、前記枠体1aの四隅の上面及
び四辺の上面に配置され、溶接等の手段により固定され
た柱主筋の本数と等しい数(この実施例では12個)の
上下方向の筒体1cと、前記連結枠1bの中央部上面に
立設した角パイプ製の鞘管1dとから構成されており、
図3に示すように、前記筒体1cに各々柱主筋4の下端
部を差し込むことにより、柱主筋群の下端側を位置決め
するようになっている。また、鞘管1dには、前記角パ
イプ3の下端側を挿抜自在に嵌入させるようになってい
る。The lower jig 1 includes a rectangular frame 1a made of an angle member and a connecting frame 1b laid between the central portions of its long sides, and the upper and four sides of the four corners of the frame 1a. The vertical cylinders 1c, which are arranged on the upper surface of the column and are fixed by means such as welding, in the same number as the number of column main bars (12 in this embodiment) and the upper surface of the central portion of the connecting frame 1b. It is composed of a square pipe 1d and
As shown in FIG. 3, by inserting the lower ends of the column main reinforcements 4 into the cylindrical body 1c, the lower end side of the column main reinforcements is positioned. Further, the lower end side of the square pipe 3 is inserted into the sheath pipe 1d so as to be freely inserted and removed.
【0010】前記上部治具2は、矩形状周辺枠とそれに
直角な複数本の直線状枠とから構成された格子状部材2
aと、その中央部に固定されたアングル材等よりなる水
平杆2bと、水平杆2bの中央部下面に垂設された角パ
イプ製の鞘管2cとから構成され、鞘管2cに前記角パ
イプ3の上端側を嵌入した状態において、前記格子状部
材2aにおける矩形状周辺枠の四隅と、当該矩形状周辺
枠と前記直線状部材とのなす角部が前記各筒体1cの真
上に位置するようになっている。そして、図3、図4に
示すように、柱主筋4の上端側を前記格子状部材2aの
所定位置に挿通して結束線(図示せず)で仮固定するこ
とにより、柱主筋群の上端側を位置決めするようになっ
ている。The upper jig 2 is a grid-shaped member 2 composed of a rectangular peripheral frame and a plurality of linear frames perpendicular to the rectangular peripheral frame.
a, a horizontal rod 2b made of an angle member or the like fixed to the central portion thereof, and a sheath pipe 2c made of a square pipe suspended from the lower surface of the central portion of the horizontal rod 2b. In the state where the upper end side of the pipe 3 is fitted, the four corners of the rectangular peripheral frame of the grid-shaped member 2a and the corners formed by the rectangular peripheral frame and the linear member are directly above each of the tubular bodies 1c. It is supposed to be located. Then, as shown in FIGS. 3 and 4, the upper end of the column main bar 4 is inserted by inserting the upper end side of the column main bar 4 into a predetermined position of the lattice member 2a and temporarily fixed with a binding line (not shown). The side is positioned.
【0011】尚、上部治具2は、構築される梁の上端レ
ベルよりも高い位置において、柱主筋4に仮固定するこ
とが望ましい。このようにすれば、後述するとおり、上
部治具2を梁や柱のコンクリート打設後、回収すること
ができる。また、当該上部治具2をコンクリート打設時
における柱主筋群の上端側の位置ずれ防止にも利用でき
る。It is desirable that the upper jig 2 be temporarily fixed to the column main bar 4 at a position higher than the upper end level of the beam to be constructed. In this way, as will be described later, the upper jig 2 can be recovered after the concrete of the beam or the pillar has been cast. In addition, the upper jig 2 can be used to prevent displacement of the upper end side of the column main bar group during concrete pouring.
【0012】図2は、梁主筋群の組立て作業に使用され
る架台Bを示す。この架台Bは、梁幅方向に間隔を開け
て一対ずつ複数組み設置され、架台Bの上端部間に架設
したカンザシ筋5で梁の上端主筋6aを支持するように
なっている。各架台Bは、アングル材等で作製されたも
ので、上縁にカンザシ筋5を安定良く載置するための凹
部7が形成された支柱部8と、その下端に連設された安
定良く設置するための十字状接地部9とから構成されて
いる。尚、カンザシ筋5は単管パイプを使用してもよ
い。FIG. 2 shows a pedestal B used in the work of assembling the beam main bar group. A plurality of pairs of the gantry B are installed at intervals in the beam width direction, and the upper and lower main reinforcements 6a of the beam are supported by the knotted reinforcements 5 laid between the upper ends of the pedestal B. Each pedestal B is made of an angle material or the like, and has a column portion 8 formed with a concave portion 7 for stably mounting the kanzashi muscle 5 on its upper edge and a stable installation continuously provided at its lower end. And a cross-shaped grounding portion 9 for Incidentally, the kanzashi muscle 5 may use a single pipe.
【0013】次に、柱梁先組み鉄筋体とそれを用いた先
組み鉄筋工法について説明する。先ず、建物構築位置の
近くに設けられた鉄筋組立作業エリヤの所定位置に、上
述した柱主筋位置決め装置Aや架台Bを必要個数設置し
ておく。そして、図3や図7に示すように、下部治具1
に柱主筋4の下端側を差し込み、上端側を上部治具2の
所定位置に結束線で仮固定して、柱2本分の柱主筋群4
…を垂直に自立させ、各々の柱主筋群の上端近傍部(具
体的には、梁を構築した状態における梁の上端主筋6a
よりも若干高い位置)に、異形鉄筋よりなる仮フープ筋
を巻き付け固定する等して梁主筋群の抜止め具10を構成
する。Next, a column-beam pre-assembled rebar body and a pre-assembled rebar construction method using the same will be described. First, a required number of the above-described pillar main bar positioning device A and gantry B are installed at a predetermined position of the reinforcing bar assembling work area provided near the building construction position. Then, as shown in FIGS. 3 and 7, the lower jig 1
The lower end side of the column main reinforcement 4 is inserted into the column, and the upper end side is temporarily fixed to a predetermined position of the upper jig 2 with a binding wire.
... is made to stand vertically, and the vicinity of the upper end of each column main bar group (specifically, the upper main bar 6a of the beam in the state where the beam is constructed)
At a position slightly higher than that), a temporary hoop bar made of deformed reinforcing bar is wound and fixed to form a retaining device (10) for the main beam bar group.
【0014】尚、柱主筋群の下端側には、予め、必要個
数のフープ筋11を密集させた状態に結束線で固定してお
く。柱主筋4に対する抜止め具10の固定には、溶接や結
束線を用いてもよいが、この実施例では、図5、図6に
示すような圧着式の鉄筋固定用金物Cを使用している。
この金物Cは、柱主筋4と抜止め具10の交差部に嵌着し
た状態で、外周を工具で締め付けて塑性変形させること
により、金物Cの一部が柱主筋4や抜止め具10として使
用されている異形鉄筋のリブにかみ込んで、柱主筋4、
抜止め具10、金物Cの三者が一体化するように構成した
ものである。図5に示す金物Cは、抜止め具10の直線部
と柱主筋4との交差部に使用される。図6に示す金物C
は、抜止め具10のコーナー部と柱主筋4との交差部に使
用されるものであり、抜止め具10に圧着する部分が平面
視において直角に折れ曲がっている点だけが、図5の金
物Cと相違している。It is to be noted that the necessary number of hoop muscles 11 are fixed in advance to the lower end side of the column main bar group with a binding wire in a dense state. Although the welding and binding wires may be used to fix the retainer 10 to the column main bar 4, in this embodiment, a crimp-type rebar-fixing hardware C as shown in FIGS. 5 and 6 is used. There is.
The metal C is fitted to the intersection of the column main bar 4 and the retainer 10, and the outer periphery is tightened with a tool to plastically deform, whereby a part of the metal C is used as the column main bar 4 and the retainer 10. Engage in the ribs of the deformed bar used,
The stopper 10 and the metal C are configured so as to be integrated. The hardware C shown in FIG. 5 is used at the intersection of the straight line portion of the retainer 10 and the column main bar 4. Hardware C shown in FIG.
Are used at the intersections of the corners of the retainer 10 and the column main bars 4, and only the point where the portion to be crimped to the retainer 10 is bent at a right angle in plan view is It differs from C.
【0015】そして、図3、図4に示すように、抜止め
具10よりも低位置で且つ柱主筋群を横断する状態に配置
した梁の上端主筋6a及び下端主筋6bとそれらに巻き
付け固定したスターラップ12とにより構成された上下方
向スライド自在な梁主筋群13とからなる柱梁先組み鉄筋
体14を組み立てる。Then, as shown in FIGS. 3 and 4, the upper end main bar 6a and the lower end main bar 6b of the beam arranged at a position lower than the stopper 10 and in a state of traversing the column main bar group and fixed around them. A pillar-beam tip assembled rebar body (14) including a beam main bar group (13) composed of a stirrup (12) and vertically slidable is assembled.
【0016】より具体的に説明すると、図7に示すよう
に、架台Bに前記カンザシ筋5を介して架設した梁の上
端主筋6aにスターラップ12を支持させ、スターラップ
12には梁の下端主筋6bを挿通して支持させる。図中の
Dはスターラップ12を支持するコンクリートブロックで
ある。More specifically, as shown in FIG. 7, the stirrup 12 is supported by the upper main stirrup 6a of the beam erected on the pedestal B through the knotted streak 5, and the stirrup 12 is supported.
The lower end main bar 6b of the beam is inserted into 12 and supported. D in the figure is a concrete block that supports the stirrup 12.
【0017】この状態で、図8に示すように、スターラ
ップ12を所定ピッチに拡げて、上端主筋6a及び下端主
筋6bに結束線等で固定し、梁主筋群13を組み立てるこ
とになる。この組立て作業は、低位置であるため、仮設
足場等を使用せずに、行われる。スターラップ12を所定
ピッチに拡げるのは、下端主筋6bの挿入前であっても
よい。その場合の具体的な手順は次の通りである。ス
ターラップ12をコンクリートブロックDに載置する。
上端主筋6aを挿入し、架台Bで支持する。スターラ
ップ12を所定位置に配置する。下端主筋6bを挿入し
て固定する。In this state, as shown in FIG. 8, the stirrup 12 is expanded to a predetermined pitch and fixed to the upper end main bar 6a and the lower end main bar 6b with binding wires or the like to assemble the beam main bar group 13. Since this assembly work is in a low position, it is performed without using a temporary scaffold or the like. The stirrup 12 may be expanded to a predetermined pitch before the lower end main bar 6b is inserted. The specific procedure in that case is as follows. Place the stirrup 12 on the concrete block D.
The upper main bar 6a is inserted and supported by the gantry B. Place the stirrup 12 in place. The lower end main bar 6b is inserted and fixed.
【0018】しかる後、図9、図10に示すように、ク
レーン等の揚重機で前記柱梁先組み鉄筋体14を建物構築
位置に吊り込むのである。この場合、柱梁先組み鉄筋体
14は、梁主筋群13が柱主筋群に対して上下方向スライド
自在に構成され、且つ、柱主筋群の上端近傍部には、抜
止め具10が固定されているので、梁主筋群13を吊り上げ
ることにより、図3に仮想線で示すように、梁の上端主
筋6aが仮フープ筋10に当たる位置まで梁主筋群13が柱
主筋群に対して上方へスライドし、図9に示すように、
柱主筋群も一体的に吊り上げられることになる。After that, as shown in FIGS. 9 and 10, the column-beam-end assembled rebar body 14 is suspended at a building construction position by a lifting machine such as a crane. In this case, the pillar-beam pre-assembled rebar body
14, the beam main bar group 13 is configured to be slidable in the vertical direction with respect to the column main bar group, and the retainer 10 is fixed near the upper end of the column main bar group. By lifting, as shown in phantom lines in FIG. 3, the beam main bar group 13 slides upward with respect to the column main bar group until the upper end main bar 6a of the beam hits the temporary hoop bar 10, and as shown in FIG.
The main pillar groups will also be lifted together.
【0019】尚、柱梁先組み鉄筋体14の吊り上げによ
り、下部治具1や角パイプ3は鉄筋組立作業エリヤに残
され、次の組立て作業に転用される。上部治具2は柱主
筋群に付いたまま、建物構築位置へと運ばれ、コンクリ
ート打設後、回収して、別の組立て作業に転用されるこ
とになる。The lower jig 1 and the square pipe 3 are left in the reinforcing bar assembling work area by lifting the post-beam pre-assembled reinforcing bar body 14 and are diverted to the next assembling work. The upper jig 2 is carried to the building construction position while being attached to the main pillar group, and after the concrete is placed, it is collected and diverted to another assembling work.
【0020】そして、建物構築位置に吊り込まれた柱梁
先組み鉄筋体14は、梁上端主筋を支持するカンザシ筋
(単管パイプ)をねじ式ジャッキ機構を備えた多数のポ
スト(図示せず)で支え、ジャッキ機構により梁主筋群
13のレベル調整を行った後、図11に示すように、柱主
筋群の下端部を先行して施工された柱主筋群の上端部
に、機械継手等によりて接合して、フープ筋11を所定ピ
ッチに拡げて結束線等で固定する一方、梁主筋群13を柱
主筋4に結束線等で固定するか、先行して構築された梁
主筋群と接合する等して、所定レベルに固定する。前記
ポストは、梁型枠を構築し、支保工により支持した後に
撤去するのである。The column-beam front-end rebar body 14 hung at the building construction position is provided with a large number of posts (not shown) provided with screw-type jack mechanisms for a single-bar pipe that supports the beam upper end bar. ), And the beam mechanism by the jack mechanism
After performing the level adjustment of 13, as shown in FIG. 11, the lower end of the column main bar group is joined to the upper end of the column main bar group that was constructed in advance by a mechanical joint, etc. The beam main reinforcement group 13 is fixed to the column main reinforcement 4 by a binding line or the like while being expanded to a predetermined pitch and fixed with a binding line or the like, or is fixed to a predetermined level by joining the beam main reinforcement group constructed in advance. To do. The post is to be removed after constructing a beam formwork, supporting it by supporting work.
【0021】以上の実施例では、スターラップ12の全て
を梁の上端主筋6a及び下端主筋6bに固定して所定の
配筋が完了した梁主筋群13を構成したが、梁主筋群13と
しては、スターラップ12の一部を固定しておき、残りの
スターラップ12を適当な時点(例えば、柱梁先組み鉄筋
体14を建物構築位置に吊り込んだ後)で、固定するよう
にししてもよい。In the above embodiment, all the stirrup 12 is fixed to the upper end main bar 6a and the lower end main bar 6b of the beam to constitute the beam main bar group 13 in which predetermined bar arrangement is completed. , A part of the stirrup 12 is fixed, and the rest of the stirrup 12 is fixed at an appropriate time (for example, after suspending the column beam tip assembled rebar body 14 at the building construction position). Good.
【0022】[0022]
【発明の効果】以上のように、本発明によれば、柱主筋
群を垂直に立てた状態で、柱梁先組み鉄筋体を組み立て
るため、組立て作業に必要な面積が小さくて済み、複数
の柱梁先組み鉄筋体を並行して組み立てるように場合で
も、広大な鉄筋組立作業エリヤが不要であり、それでい
て、梁主筋群の組立て作業は、低位置で行われるので能
率良く安全に作業できる。また、梁主筋群が柱主筋群に
対して抜止め具を上限として上下方向スライド自在であ
るため、柱梁先組み鉄筋体を建物構築位置に吊り込ん
で、柱主筋群の下端部の固定や梁主筋群の固定を行う
際、梁主筋群のレベル調整や柱主筋下端部の接合作業を
容易に行える利点がある。As described above, according to the present invention, since the column beam-end pre-assembled rebar body is assembled in a state where the column main bar group is erected vertically, the area required for the assembly work can be small, and Even when assembling the column-beam-end assembled rebar bodies in parallel, a vast rebar assembly work area is not necessary, yet the work of assembling the beam main rebar group is performed at a low position, so that the work can be performed efficiently and safely. In addition, since the beam main bar group is vertically slidable with respect to the column main bar group with the retaining device as the upper limit, the column beam front assembled rebar body is hung at the building construction position and the lower end of the column main bar group is fixed or When fixing the beam main bar group, there is an advantage that the level adjustment of the beam main bar group and the joining work of the lower end of the column main bar can be easily performed.
【図1】本発明に係る柱梁先組み鉄筋体とそれを用いた
先組み鉄筋工法に使用される柱主筋位置決め装置の斜視
図である。FIG. 1 is a perspective view of a column beam pre-assembled rebar body according to the present invention and a column main bar positioning device used in a pre-assembled rebar construction method using the same.
【図2】梁主筋群の組立て作業に使用される架台の斜視
図である。FIG. 2 is a perspective view of a gantry used for an assembly operation of a beam main bar group.
【図3】柱梁先組み鉄筋体の側面図である。FIG. 3 is a side view of a post-beam pre-assembled rebar body.
【図4】柱梁先組み鉄筋体の平面図である。FIG. 4 is a plan view of a post-beam pre-assembled rebar body.
【図5】フープ筋固定用金物の斜視図である。FIG. 5 is a perspective view of a hoop muscle fixing hardware.
【図6】フープ筋固定用金物の斜視図である。FIG. 6 is a perspective view of a hoop muscle fixing hardware.
【図7】本発明に係る柱梁先組み鉄筋体とそれを用いた
先組み鉄筋工法を説明するための概略側面図である。FIG. 7 is a schematic side view for explaining a post-beam pre-assembled rebar body according to the present invention and a pre-assembled rebar construction method using the same.
【図8】図7に続く工程を説明するための概略側面図で
ある。FIG. 8 is a schematic side view for explaining a process following the process in FIG.
【図9】図8に続く工程を説明するための概略側面図で
ある。FIG. 9 is a schematic side view for explaining a process following the process in FIG.
【図10】図9に続く工程を説明するための概略側面図
である。FIG. 10 is a schematic side view for explaining a process following the process in FIG.
【図11】図10に続く工程を説明するための概略側面
図である。FIG. 11 is a schematic side view for explaining a step following FIG.
4…柱主筋、6a…梁の上端主筋、6b…梁の下端主
筋、10…抜止め具、12…スターラップ、13…梁主筋群、
14…柱梁先組み鉄筋体。4 ... Column main bar, 6a ... Beam upper end bar, 6b ... Beam lower end bar, 10 ... Stopper, 12 ... Stirrup, 13 ... Beam main bar group,
14… Post-beam pre-assembled rebar body.
Claims (2)
立させた柱主筋群と、梁筋所定位置よりも低位置で且つ
柱主筋群を横断する状態に配置した梁主筋群と、柱主筋
群の上端近傍部に固定された抜止め具とからなり、梁主
筋群が抜止め具を上限として上下方向スライド自在に構
成されていることを特徴とする柱梁先組み鉄筋体。1. A column main bar group positioned in a predetermined bar arrangement state and made to stand vertically, a beam main bar group arranged at a position lower than a predetermined position of the beam bar and traversing the column main bar group, and a column A column-beam pre-assembled rebar body, comprising a retaining member fixed to a portion near an upper end of a main bar group, and the beam main bar group is configured to be vertically slidable with the retaining member as an upper limit.
状態に位置決めして垂直に自立させた柱主筋群と、梁筋
所定位置よりも低位置で且つ柱主筋群を横断する状態に
配置した梁主筋群と、柱主筋群の上端近傍部に固定され
た抜止め具とからなり、梁主筋群が抜止め具を上限とし
て上下方向スライド自在に構成されている柱梁先組み鉄
筋体を組み立て、この柱梁先組み鉄筋体を建物構築位置
に吊り込むことを特徴とする先組み鉄筋工法。2. A column main bar group positioned in a predetermined bar arrangement state and made to stand vertically in a place other than the building construction position, and a state in which the beam bar crosses the column main bar group at a position lower than the beam bar predetermined position. A column-beam-pre-assembled rebar body composed of arranged beam main reinforcements and retaining members fixed near the upper end of the column main reinforcements, and the beam main reinforcements are configured to be vertically slidable with the retaining members as the upper limit. The pre-assembled rebar construction method characterized by assembling the above and suspending this column-beam pre-assembled rebar body at the building construction position.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP34557992A JP3324807B2 (en) | 1992-11-30 | 1992-11-30 | Column-beam pre-assembled reinforced body and pre-assembled reinforced construction method using it |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP34557992A JP3324807B2 (en) | 1992-11-30 | 1992-11-30 | Column-beam pre-assembled reinforced body and pre-assembled reinforced construction method using it |
Publications (2)
Publication Number | Publication Date |
---|---|
JPH06167114A true JPH06167114A (en) | 1994-06-14 |
JP3324807B2 JP3324807B2 (en) | 2002-09-17 |
Family
ID=18377554
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP34557992A Expired - Fee Related JP3324807B2 (en) | 1992-11-30 | 1992-11-30 | Column-beam pre-assembled reinforced body and pre-assembled reinforced construction method using it |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP3324807B2 (en) |
-
1992
- 1992-11-30 JP JP34557992A patent/JP3324807B2/en not_active Expired - Fee Related
Also Published As
Publication number | Publication date |
---|---|
JP3324807B2 (en) | 2002-09-17 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JPS6348753Y2 (en) | ||
CN216194062U (en) | Temporary support structure | |
JPH06167114A (en) | Prefabricated beam-column structure of reinforcements and application by use thereof | |
CN109736451B (en) | Stirrup framework and construction method thereof applied to beam column joint encryption process | |
JPH0536042Y2 (en) | ||
JP3187618B2 (en) | How to assemble beam reinforcement | |
CN114165057B (en) | Construction site steel bar binding construction method | |
JP2004270377A (en) | Column-beam preassembled reinforcement body, and preassembled reinforcement method using the same | |
JPH0270861A (en) | Mounting and overhaulting method of work scaffold in step-up technique | |
JPH0459978B2 (en) | ||
JP2009097247A (en) | Column steel frame erection method, steel frame reinforcement unit for column, and steel framed reinforced concrete column | |
JPH0649748Y2 (en) | Scaffolding for rebar assembly | |
JP2023172647A (en) | Reinforcement bar mount and construction method of wall | |
JPH0115800Y2 (en) | ||
JPH07217074A (en) | Assembly auxiliary device of reinforcing steel cage and assembling method | |
JP2997449B1 (en) | Rebar assembling work scaffold and construction method of rebar structure using this work scaffold | |
JP2024020043A (en) | Reinforcement frame and bar arrangement method using reinforcement frame | |
JP2634271B2 (en) | Jack-up method and device | |
JP2000054619A (en) | Suspended scaffold and its erection method | |
JPH0327166Y2 (en) | ||
JPH0528248Y2 (en) | ||
JP2546355B2 (en) | Boiler assembly method | |
JP2575800Y2 (en) | Hoop muscle hanging jig | |
JPH06336841A (en) | Support member for prior assembling of beam reinforcements used on constructing standardized apartment house | |
JPH1113141A (en) | Constructing method of composite structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
LAPS | Cancellation because of no payment of annual fees |