JPH0616553U - PC steel fixing body - Google Patents

PC steel fixing body

Info

Publication number
JPH0616553U
JPH0616553U JP5469592U JP5469592U JPH0616553U JP H0616553 U JPH0616553 U JP H0616553U JP 5469592 U JP5469592 U JP 5469592U JP 5469592 U JP5469592 U JP 5469592U JP H0616553 U JPH0616553 U JP H0616553U
Authority
JP
Japan
Prior art keywords
concrete
fixing
steel material
fixing plate
steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP5469592U
Other languages
Japanese (ja)
Inventor
昭男 遠藤
Original Assignee
株式会社ピー・エス
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 株式会社ピー・エス filed Critical 株式会社ピー・エス
Priority to JP5469592U priority Critical patent/JPH0616553U/en
Publication of JPH0616553U publication Critical patent/JPH0616553U/en
Pending legal-status Critical Current

Links

Landscapes

  • Reinforcement Elements For Buildings (AREA)

Abstract

(57)【要約】 【目的】PC鋼材の端部定着部が比較的薄いコンクリー
ト部に位置し、しかもコンクリート外に突出することが
好ましくない場合に定着体全体をコンクリート中に埋設
施工する。 【構成】雌コーン3と雄コーン4とからなるPC鋼材2
の定着体1において、雌コーン3の外径にフランジ31
を設け、このフランジ31によってPC鋼材の反力を定
着板5に支持させる。定着板5をコンクリート表面12
から浅い位置に設けることができる。
(57) [Abstract] [Purpose] When the end fixing part of PC steel is located in a relatively thin concrete part and it is not preferable to project outside the concrete, the whole fixing body is buried in the concrete. [Structure] PC steel material 2 consisting of female cone 3 and male cone 4
In the fixing body 1 of FIG.
The flange 31 is used to support the reaction force of the PC steel material on the fixing plate 5. Fixing plate 5 on concrete surface 12
Can be provided at a shallow position.

Description

【考案の詳細な説明】[Detailed description of the device]

【0001】[0001]

【産業上の利用分野】[Industrial applications]

本考案は雌コーンと雄コーンとからなるPC鋼材の定着体に関する。 The present invention relates to a PC steel fixing member composed of a female cone and a male cone.

【0002】[0002]

【従来の技術】[Prior art]

図5に示すように、プレストレスト構造物において、PC鋼材2の端部をコン クリート10に定着する雌コーン3と雄コーン4と定着板5とからなるPC鋼材 の定着体1が用いられる。この定着体1はコンクリート10の端面から突出して 設ける場合も、コンクリート内に埋め込んで定着する場合もある。 As shown in FIG. 5, in a prestressed structure, a PC steel material fixing body 1 including a female cone 3, a male cone 4, and a fixing plate 5 for fixing the end portion of the PC steel material 2 to the concrete 10 is used. The fixing body 1 may be provided so as to project from the end surface of the concrete 10 or may be embedded in the concrete to be fixed.

【0003】 ところで、この定着体1はPC構造物の構造によっては、例えば定着部のコン クリート躯体の厚さの関係からコンクリート中に定着体を埋め込むことができな い場合がある。また、突出を避ける理由でコンクリート内に埋め込む必要がある が、そのために必要不可決な部分のコンクリートに応力導入ができない場合など がある。By the way, depending on the structure of the PC structure, it may not be possible to embed the fixing body 1 in concrete depending on the thickness of the concrete frame of the fixing unit. In addition, it is necessary to embed it in the concrete for the purpose of avoiding protrusion, but there are cases where stress cannot be introduced into the concrete of the inevitable part.

【0004】 具体的な例を挙げると前者の例ではコンクリート橋桁の横桁の場合がある。こ れを図6に示した。多数の桁20を並列した橋桁では、桁20の長手方向両端部 、中央部等に桁20を横に結合する横桁21を現場打ちPCコンクリートで施工 する。このとき、横桁に応力を導入するPC鋼材23を図6に示すように挿通す る。このPC鋼材23の定着体1はウエブ22内に埋め込んで施工することが好 ましいが桁20のウエブ22は例えば幅240mmというような寸法なので、図 5に示すような定着体1を押込むことができる深さに限度があり、従来のPC鋼 材の定着体ではウエブ22の端面から突出させて施工せざるを得なかった。この ため、これを覆う化粧コンクリートを打設する。この化粧コンクリート24は桁 の横端面に施工するものであるために型枠取り付け、保持、コンクリート打設作 業等が容易でないという問題があった。To give a concrete example, in the former case, there may be a case of a horizontal girder of a concrete bridge girder. This is shown in FIG. For bridge girders in which a large number of girders 20 are arranged in parallel, transverse girders 21 that laterally connect the girders 20 to both ends in the longitudinal direction of the girder 20, the central part, etc. are constructed by cast-in-place PC concrete. At this time, the PC steel material 23 that introduces stress into the transverse beam is inserted as shown in FIG. It is preferable that the fixing body 1 of the PC steel material 23 is embedded in the web 22 for construction, but the web 22 of the girder 20 has a width of, for example, 240 mm, so the fixing body 1 as shown in FIG. There is a limit to the depth that can be formed, and in the conventional fixing member made of PC steel material, there was no choice but to project by projecting from the end face of the web 22. Therefore, decorative concrete is placed to cover it. Since this decorative concrete 24 is constructed on the lateral end surface of the girder, there has been a problem that it is not easy to attach the mold, hold it, and put concrete into it.

【0005】 また、後者の具体例としてはPCボックスカルバートの縦横締めPC鋼材の例 がある。この場合、定着体がボックスカルバートの外面より突出することは好ま しくないので、コンクリート内に埋め込まれる。そうすると、強度上非常に重要 な四隅のハンチ部に応力が導入されない部分が生ずるという問題がある。Further, as a concrete example of the latter, there is an example of a PC steel material of PC box culvert which is vertically and horizontally tightened. In this case, it is not preferable that the fixing body protrudes from the outer surface of the box culvert, so that the fixing body is embedded in the concrete. Then, there is a problem that stress is not introduced into the haunches at the four corners, which are very important for strength.

【0006】[0006]

【考案が解決しようとする課題】[Problems to be solved by the device]

本考案は上記の問題点を解決するために開発されたPC鋼材の定着体を提供す ることを目的とする。すなわち、定着体全体をコンクリート中に埋め込みとする が、定着板はなるべくコンクリート表面から浅い位置に設けることができ、厚さ の薄いコンクリートであっても十分な支圧力を有する位置に設けることができ、 また、できるだけ表面に近い部分のコンクリートにも応力導入できるような定着 体を提供するものである。 An object of the present invention is to provide a PC steel fixing member developed to solve the above problems. That is, although the entire fixing body is embedded in concrete, the fixing plate can be provided at a position as shallow as possible from the concrete surface, and even a thin concrete can be provided at a position having sufficient bearing pressure. It also provides a fixing body that can introduce stress into concrete as close to the surface as possible.

【0007】[0007]

【課題を解決するための手段】[Means for Solving the Problems]

本考案のPC鋼材の定着体は、雌コーンと雄コーンとからなるPC鋼材の定着 体において、雌コーンの外径に、定着板に係止するフランジを設け、このフラン ジが定着板にPC鋼材の反力を伝達するようにしたことを特徴とするPC鋼材の 定着体である。 The PC steel fixing member of the present invention is a PC steel fixing member composed of a female cone and a male cone, and a flange for engaging with the fixing plate is provided on the outer diameter of the female cone, and this flange is used as the PC plate. It is a fixed body of PC steel characterized by transmitting the reaction force of steel.

【0008】[0008]

【作用】[Action]

本考案では雌コーンの外径にフランジを設け、このフランジを定着板に係止さ せるようにしたので、フランジの位置を雌コーンの雄コーン定着位置よりもテー パ大径側上端に設けることが可能となった。したがって、定着板をコンクリート の表面から浅い位置に定着して反力を支持し、一方、雌コーンはフランジを定着 板に係止して本体をコンクリート内の深部に配設して定着体がコンクリートの表 面から外方に突出しないようにすることができる。 In the present invention, a flange is provided on the outer diameter of the female cone, and this flange is locked to the fixing plate.Therefore, the flange position should be provided on the upper end of the female cone on the larger diameter side than the male cone fixing position. Became possible. Therefore, the anchor plate is anchored at a position shallow from the surface of the concrete to support the reaction force, while the female cone locks the flange to the anchor plate to place the main body deep inside the concrete and the anchor body is It is possible to prevent it from protruding outward from the surface of the.

【0009】 上記フランジはもちろんPC鋼材の反力を支持し定着板に定着させるような設 計とする。The flange is of course designed to support the reaction force of the PC steel and fix it to the fixing plate.

【0010】[0010]

【実施例】【Example】

図1に本考案のPC鋼材の定着体の実施例を示した。本考案の定着体1は雌コ ーン3の外径にフランジ31を設け、このフランジ31が定着板5に係止するよ うにした。したがって、定着板5は雌コーン3が嵌入する孔を有しフランジ31 が定着板面に定着される。雌コーンは定着板よりもコンクリート10の内部に位 置する。このため、シース6は径違いのラッパシースを用いる。定着板5がコン クリート10の表面に近い浅い位置に設けられるので、例えばコンクリート10 の厚さが比較的厚くない場合でも定着可能である。定着板5は内ねじを施工した 型枠取付パイプ51を付属している。 FIG. 1 shows an embodiment of a PC steel fixing member of the present invention. The fixing member 1 of the present invention is provided with a flange 31 on the outer diameter of the female cone 3, and the flange 31 is engaged with the fixing plate 5. Therefore, the fixing plate 5 has a hole into which the female cone 3 is fitted, and the flange 31 is fixed on the fixing plate surface. The female cone is placed inside the concrete 10 rather than the fixing plate. Therefore, the sheath 6 uses a trumpet sheath having a different diameter. Since the fixing plate 5 is provided at a shallow position close to the surface of the concrete 10, the fixing can be performed even when the concrete 10 is not relatively thick, for example. The fixing plate 5 is attached with a formwork mounting pipe 51 having an inner thread.

【0011】 本考案の定着体1の施工方法を図2〜図4を参照して説明する。 図2は本考案の定着板5を型枠に取りつけてコンクリート10を打設する工程 を示している。ラッパシースを取りつけた定着板5の型枠取付パイプ51に治具 101を取り付ける。治具101は型枠取付パイプ51の内ねじに螺合する雄ね じを備えた円盤の背面にスタッドボルト102を取付けたものである。この治具 101のスタッドボルト102を型枠せき板100に挿通し、スタッドボルト1 02にナット104を螺合しワッシャ103を介して型枠せき板100に固定し 、コンクリート10を打設する。コンクリート10が硬化した後、型枠せき板1 00、治具101を取り外す。A method of applying the fixing member 1 of the present invention will be described with reference to FIGS. FIG. 2 shows a process of mounting the fixing plate 5 of the present invention on a mold and placing concrete 10. The jig 101 is attached to the frame attachment pipe 51 of the fixing plate 5 to which the trumpet sheath is attached. The jig 101 is one in which a stud bolt 102 is attached to the back surface of a disk provided with a male screw that is screwed into the inner screw of the formwork mounting pipe 51. The stud bolt 102 of the jig 101 is inserted into the form dam 100, the nut 104 is screwed into the stud bolt 102, the washer 103 is fixed to the form dam 100, and the concrete 10 is poured. After the concrete 10 hardens, the form dam 100 and the jig 101 are removed.

【0012】 図3は型枠取り外し後、PC鋼材2をシース内に装入し、定着端に雌コーン3 、雄コーン4を配設し、PC鋼材2に図示しないジャッキを用いて緊張し応力を 導入し、PC鋼材2を定着板5に定着させる工程を示している。応力導入後PC 鋼材2は定着体1の口元で切断される。次いでシース内にグラウトする。 図4は仕上モルタル11を施工して定着体をコンクリート10内に埋設して仕 上げ完了した状態を示している。このようにして、本考案の定着体は定着板5を コンクリート表面12から浅い位置に位置させてコンクリート内に施工すること ができる。In FIG. 3, after removing the formwork, the PC steel material 2 is loaded into the sheath, the female cone 3 and the male cone 4 are arranged at the fixing end, and the PC steel material 2 is tensioned and stressed using a jack (not shown). Is introduced to fix the PC steel material 2 to the fixing plate 5. After the stress is introduced, the PC steel material 2 is cut at the mouth of the fixing body 1. Then grout into the sheath. FIG. 4 shows a state in which the finishing mortar 11 has been applied, the fixing body has been embedded in the concrete 10, and the finishing has been completed. In this way, the fixing body of the present invention can be installed in the concrete by positioning the fixing plate 5 at a position shallow from the concrete surface 12.

【0013】[0013]

【考案の効果】[Effect of device]

本考案によれば、PC鋼材の定着体と定着板をコンクリート表面から浅い部分 に設置し、定着体全体はコンクリート中に埋設施工することができる。 したがって、例えばPC橋桁の横桁の定着体を従来は桁のウエブの側面に突出 して設け、これを被覆する化粧コンクリートを施工しなければならなかったのを ウエブ内に埋設して施工することが可能となったので、コンクリート表面には、 比較的小径の円形跡埋痕を残すのみとなり、橋桁の構造が突設施工部を必要とせ ず、信頼性の高い省力、短工期の施工ができる。 According to the present invention, the fixing member and fixing plate made of PC steel can be installed in a portion shallow from the concrete surface, and the entire fixing member can be embedded in concrete. Therefore, for example, a fixing member for a transverse girder of a PC bridge girder was conventionally provided so as to project on the side surface of the web of the girder, and it was necessary to construct a decorative concrete to cover this, but to embed it inside the web. As a result, only circular traces with a relatively small diameter are left on the concrete surface, the structure of the bridge girder does not require a projecting construction part, and highly reliable labor-saving and short-term construction is possible. .

【図面の簡単な説明】[Brief description of drawings]

【図1】本考案の実施例のPC鋼材の構造を示す縦断面
図である。
FIG. 1 is a vertical sectional view showing a structure of a PC steel material according to an embodiment of the present invention.

【図2】本考案の実施例のPC鋼材の型枠取り付け工程
を示す説明図である。
FIG. 2 is an explanatory view showing a process of mounting a PC steel material frame according to an embodiment of the present invention.

【図3】本考案の実施例のPC鋼材のPC鋼材定着工程
を示す説明図である。
FIG. 3 is an explanatory view showing a PC steel material fixing step of the PC steel material according to the embodiment of the present invention.

【図4】本考案の実施例のPC鋼材の仕上工程定着工程
を示す説明図である。
FIG. 4 is an explanatory view showing a finishing step fixing step of the PC steel material according to the embodiment of the present invention.

【図5】従来の定着体の縦断面図である。FIG. 5 is a vertical sectional view of a conventional fixing member.

【図6】橋桁の横桁の説明図である。FIG. 6 is an explanatory view of a cross girder of a bridge girder.

【符号の説明】[Explanation of symbols]

1 定着体 2 PC鋼材 3 雌コーン 4 雄コーン 5 定着板 6 シース 10 コンクリート 11 モルタル 12 コンクリート表面 20 桁 21 横桁 22 ウエブ 23 PC鋼材 24 化粧コンクリート 31 フランジ 51 型枠取付パイプ 100 型枠せき板 101 取付治具 102 スタッドボルト 103 ワッシャ 104 ナット 1 Fixing Body 2 PC Steel Material 3 Female Cone 4 Male Cone 5 Fixing Plate 6 Sheath 10 Concrete 11 Mortar 12 Concrete Surface 20 Girder 21 Transverse Girder 22 Web 23 PC Steel Material 24 Decorative Concrete 31 Flange 51 Formwork Pipe 100 Form Frame Board 101 Mounting jig 102 Stud bolt 103 Washer 104 Nut

Claims (1)

【実用新案登録請求の範囲】[Scope of utility model registration request] 【請求項1】 雌コーンと雄コーンとからなるPC鋼材
の定着体において、雌コーンの外径に定着板に係止する
フランジを設けたことを特徴とするPC鋼材の定着体。
1. A PC steel fixing member comprising a female cone and a male cone, wherein a flange for engaging a fixing plate is provided on the outer diameter of the female cone.
JP5469592U 1992-08-04 1992-08-04 PC steel fixing body Pending JPH0616553U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP5469592U JPH0616553U (en) 1992-08-04 1992-08-04 PC steel fixing body

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP5469592U JPH0616553U (en) 1992-08-04 1992-08-04 PC steel fixing body

Publications (1)

Publication Number Publication Date
JPH0616553U true JPH0616553U (en) 1994-03-04

Family

ID=12977941

Family Applications (1)

Application Number Title Priority Date Filing Date
JP5469592U Pending JPH0616553U (en) 1992-08-04 1992-08-04 PC steel fixing body

Country Status (1)

Country Link
JP (1) JPH0616553U (en)

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS60105634A (en) * 1983-11-12 1985-06-11 Wako Pure Chem Ind Ltd Production of primary amine
JPS60258370A (en) * 1984-06-06 1985-12-20 小林 一輔 Method and apparatus for tension anchoring of fiber reinforced plastc rod
JPS6214021B2 (en) * 1981-12-21 1987-03-31 Chuetsu Metal Works

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6214021B2 (en) * 1981-12-21 1987-03-31 Chuetsu Metal Works
JPS60105634A (en) * 1983-11-12 1985-06-11 Wako Pure Chem Ind Ltd Production of primary amine
JPS60258370A (en) * 1984-06-06 1985-12-20 小林 一輔 Method and apparatus for tension anchoring of fiber reinforced plastc rod

Similar Documents

Publication Publication Date Title
JPH0616553U (en) PC steel fixing body
JP2530485B2 (en) Flexible formwork method for gaps between structures
JP3255253B2 (en) Construction method of pillar and its bottom support device
JPS59192145A (en) Fixing of iron pillar
JP2607137B2 (en) How to bury the mounting bracket for mounting the support material
JP2000110175A (en) Individual footing for mat foundation
JP2005023769A (en) Fixing method for base plate having large bolt hole and anchor bolt
JP2002147027A (en) Fixing construction method for safety fence column
JP3078195U (en) Prestressed concrete structure
JPH0115761Y2 (en)
JPH0220778B2 (en)
JPH0222178B2 (en)
JP2730772B2 (en) Installation method of fender
JP2550354Y2 (en) Water stop plate fixing bracket
KR200329418Y1 (en) Structure for Reinforcing Structure Using Tendonr
JPS63289145A (en) Method for fixing anchor bolt
JPS5944464A (en) Anchoring of building to concrete foundation
JPH0711773A (en) Column erection method and column base supporting device
JPS5838093Y2 (en) Fixing body for PC steel materials
JP2584679Y2 (en) Embedded bolt formwork fitting
JPS5914595Y2 (en) Anchor installation tool
JPS62160339A (en) Method for arranging concrete embedded metal fittings
JPH0849306A (en) Anchorage device of anchor bolt
JP2922789B2 (en) Formwork, its manufacturing method and slope stabilization method
JPS5935693Y2 (en) Fixing body for PC steel materials

Legal Events

Date Code Title Description
A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02