JPH06158712A - Construction method of beam - Google Patents
Construction method of beamInfo
- Publication number
- JPH06158712A JPH06158712A JP33380292A JP33380292A JPH06158712A JP H06158712 A JPH06158712 A JP H06158712A JP 33380292 A JP33380292 A JP 33380292A JP 33380292 A JP33380292 A JP 33380292A JP H06158712 A JPH06158712 A JP H06158712A
- Authority
- JP
- Japan
- Prior art keywords
- concrete
- beam member
- reinforcing bars
- outer beam
- spacer
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Abstract
Description
【0001】[0001]
【産業上の利用分野】本発明は、構造物の梁の構築方法
に関するものである。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method of constructing a beam for a structure.
【0002】[0002]
【従来の技術】従来、梁の構築方法として、特開昭62
−117938号公報により公表されているように、全
長にわたって上向き開口溝形になっているプレキャスト
コンクリート製外郭梁部材を、鉄筋コンクリート柱にわ
たって架設し、前記外郭梁部材内と柱鉄筋の周囲とにわ
たってコンクリートを打設する方法が知られている。2. Description of the Related Art Conventionally, as a method for constructing a beam, Japanese Patent Laid-Open No. Sho 62-62 is known.
As disclosed in Japanese Patent Laid-Open No. 117938, a precast concrete outer beam member having an upward opening groove shape over the entire length is erected over a reinforced concrete column, and concrete is laid in the outer beam member and around the column rebar. A method of setting is known.
【0003】[0003]
【発明が解決しようとする課題】前記従来の梁の構築方
法の場合は、高所へのコンクリートの打設量が多くなる
点で煩雑である。一方、梁の全面にわたって工場部材と
したものは、端部の鉄筋の継手に特別の方法を伴うこと
となり、この場合も煩雑である。However, the conventional method of constructing a beam is complicated in that the amount of concrete placed at a high place is large. On the other hand, in the case where the entire surface of the beam is used as a factory member, a special method is involved in the joint of the reinforcing bars at the ends, and in this case as well, it is complicated.
【0004】[0004]
【課題を解決するための手段】前述の問題を有利に解決
するために、本発明の梁の構築方法においては、端部が
上向き開口溝形断面になっているプレキャストコンクリ
ート製端部外郭梁部材1を、鉄筋コンクリート柱2にわ
たって架設し、前記端部外郭梁部材1における端部溝形
部分3内と、柱鉄筋4の付近とにわたって、コンクリー
ト5を打設する。In order to advantageously solve the above-mentioned problems, in the method of constructing a beam according to the present invention, a precast concrete end portion outer beam member whose end portion has an upward opening groove section. 1 is erected over a reinforced concrete column 2, and concrete 5 is placed over the inside of the end groove portion 3 of the end outer beam member 1 and in the vicinity of the column reinforcing bar 4.
【0005】[0005]
【実施例】図4ないし図8は本発明の実施例において用
いられるプレキャストコンクリート製端部外郭梁部材1
を示すものであって、中間部が中実で両端に上向き開口
溝形の端部溝形部分3を備えている端部外郭梁部材1に
おける前記端部溝形部分3の内周面に、多数の截頭円錐
形の凹部9が、一定間隔で千鳥状に、底面では直列に設
けられ、かつ前記端部外郭梁部材1の上部に、多数の枠
形のせん断補強鉄筋10が、端部外郭梁部材1の長手方
向に間隔をおいて埋込固定されている。DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS FIGS. 4 to 8 show a precast concrete end portion outer beam member 1 used in an embodiment of the present invention.
In the inner peripheral surface of the end grooved portion 3 of the end outer beam member 1 having a solid middle portion and provided with end grooved portions 3 having upward opening groove shapes at both ends, A large number of frustoconical recesses 9 are provided in a zigzag manner at regular intervals and in series on the bottom surface, and a large number of frame-shaped shear reinforcing bars 10 are provided at the upper end of the end outer beam member 1. The outer beam member 1 is embedded and fixed at intervals in the longitudinal direction.
【0006】図9および図10は本発明の実施例におい
て用いられる梁筋縦重ね用スペーサー8を示すものであ
って、丸鋼棒がコ字状に屈曲されてスペーサー本体11
が構成され、水平な帯状鋼板12の上面に、複数(図示
の場合は3箇)のスペーサー本体11が、帯状鋼板長手
方向に間隔をおいて溶接により固着されている。FIG. 9 and FIG. 10 show a beam bar vertical stacking spacer 8 used in an embodiment of the present invention, in which a round steel rod is bent in a U-shape to form a spacer body 11.
The plurality of spacer bodies 11 (three in the illustrated case) are fixed to the upper surface of the horizontal strip steel plate 12 by welding at intervals in the longitudinal direction of the strip steel plate.
【0007】次に前記プレキャストコンクリート製端部
外郭梁部材1および梁筋縦重ね用スペーサー8を使用し
て梁を構築する方法について説明する。まず図1および
図2に示すように、梁筋縦重ね用スペーサー8および継
手筋7を収容した端部外郭梁部材1を、クレーンにより
吊上げて、2本の鉄筋コンクリート柱2にわたって架設
する。次に図3に示すように、前記端部外郭梁部材1の
上部近傍に仮吊されていた複数本の継手筋7を、引き出
すと共に下して前記端部溝形部分3内の各下部梁主筋6
の上部に位置するように、梁筋縦重ね用スペーサー8に
より保持する。次に柱鉄筋4の周囲および端部溝形部分
3の内部にコンクリート5を打設すると共に、スラブコ
ンクリート13を打設する。なお図3において、14は
上部梁主筋、15はスラブコンクリートである。Next, a method of constructing a beam using the precast concrete end portion outer beam member 1 and the beam reinforcement vertical stacking spacer 8 will be described. First, as shown in FIG. 1 and FIG. 2, the end outer beam member 1 containing the beam reinforcement vertical stacking spacer 8 and the joint reinforcement 7 is hung by a crane and installed over two reinforced concrete columns 2. Next, as shown in FIG. 3, the plurality of joint bars 7 temporarily suspended near the upper portion of the end portion outer beam member 1 are pulled out and lowered to the lower beam members in the end groove portions 3. Main line 6
It is held by the spacer 8 for vertical stacking of beam reinforcement so that it is located on the upper part of. Next, the concrete 5 and the slab concrete 13 are cast around the column reinforcing bars 4 and inside the end groove portions 3. In FIG. 3, 14 is the upper beam main bar and 15 is slab concrete.
【0008】[0008]
【発明の効果】本発明によれば、端部が上向き開口溝形
断面になっているプレキャストコンクリート製端部外郭
梁部材1を、鉄筋コンクリート柱2にわたって架設し、
前記端部外郭梁部材1における端部溝形部分3内と、柱
鉄筋4の周囲とにわたって、コンクリート5を打設する
ので、高所へのコンクリート5の打設量を少なくして、
梁の施工を容易にかつ迅速に行なうことができ、梁の中
間部は中実で工場生産することができる。一方、端部鉄
筋の継手又は定着は、従来の慣用的な方法とすることが
できる。また下部梁主筋6は端部外郭梁部材1の端部か
ら突出していないので、その端部外郭梁部材1を吊上げ
運搬するとき、下部梁主筋6が他の部材に突き当たって
邪魔になったり、下部梁主筋6の端部が折れ曲がる恐れ
もなく、かつ柱側から端部溝形部分3内に延長している
継手筋7を、下部梁主筋6の上部に位置するように、梁
筋縦重ね用スペーサー8により保持することにより、継
手筋7を下部梁主筋6の上部に正しく配置して、鉄筋コ
ンクリート柱2に対する梁の連結強度を大きくすること
ができる。梁の中間部を中実とし、両端部を上向き開口
溝形断面とすることにより、梁重量を調整し当該現場の
揚重機能力に適合した重量とするこができるので、仮設
揚重機計画を容易なものにすることが可能となる。さら
に、この発明によれば、大梁に架渡す小梁の大梁中への
定着を容易に形成することがでるし、このような小梁は
大梁に比べて重量が近いものとなり揚重の無駄が省ける
利点がある。According to the present invention, a precast concrete end portion outer beam member 1 whose end portion has an upward opening groove-shaped cross section is erected over a reinforced concrete column 2,
Since the concrete 5 is cast in the end channel portion 3 of the end outer beam member 1 and around the column rebar 4, the amount of the concrete 5 to be cast in a high place can be reduced,
The construction of the beam can be carried out easily and quickly, and the middle part of the beam can be manufactured in a solid factory. On the other hand, the joining or anchoring of the end rebar can be done by conventional and conventional methods. Further, since the lower beam main reinforcement 6 does not project from the end portion of the end outer beam member 1, when the end outer beam member 1 is hoisted and transported, the lower beam main reinforcement 6 bumps against other members and becomes an obstacle, There is no fear that the end of the lower beam main bar 6 will bend, and the joint bar 7 extending from the column side into the end groove portion 3 is vertically stacked so that the joint bar 7 is located above the lower beam main bar 6. By holding it by the spacer 8 for use, the joint bar 7 can be correctly arranged on the upper part of the lower beam main bar 6, and the connection strength of the beam to the reinforced concrete column 2 can be increased. By making the middle part of the beam solid and making both ends upwardly grooved, it is possible to adjust the beam weight and make it suitable for the lifting function of the site. It becomes possible to make it. Further, according to the present invention, it is possible to easily form the fixing of the girder bridged over the girder in the girder, and such a girder has a weight closer to that of the girder, so that there is no waste of lifting. There is an advantage that it can be omitted.
【図1】端部外郭梁部材を鉄筋コンクリート柱に架設す
るときの状態を示す斜視図である。FIG. 1 is a perspective view showing a state in which an end outer beam member is installed on a reinforced concrete column.
【図2】端部外郭梁部材内に梁筋縦重ね用スペーサーを
用い継手筋を設置した状態を示す一部縦断正面図であ
る。FIG. 2 is a partially longitudinal front view showing a state in which a joint bar is installed in the end outer beam member by using a beam bar vertical stacking spacer.
【図3】完成した梁付近を示す縦断正面図である。FIG. 3 is a vertical sectional front view showing the vicinity of a completed beam.
【図4】一部露出したせん断補強鉄筋を有する端部外郭
梁部材を示す一部切欠斜視図である。FIG. 4 is a partially cutaway perspective view showing an end portion outer beam member having a partially exposed shear reinforcing bar.
【図5】一部露出したせん断補強鉄筋を有する端部外郭
梁部材を示す一部切欠側面図である。FIG. 5 is a partially cutaway side view showing an end outer beam member having a partially exposed shear reinforcing bar.
【図6】図5の一部を拡大して示す側面図である。FIG. 6 is a side view showing a part of FIG. 5 in an enlarged manner.
【図7】図6のA−A線断面図である。7 is a cross-sectional view taken along the line AA of FIG.
【図8】図6のBーB線断面図である。8 is a sectional view taken along line BB of FIG.
【図9】梁筋縦重ね用スペーサーの正面図である。FIG. 9 is a front view of a beam bar vertical stacking spacer.
【図10】梁筋縦重ね用スペーサーの平面図である。FIG. 10 is a plan view of a spacer for vertically overlapping beam reinforcement.
1 プレキャストコンクリート製端部外郭梁部材 2 鉄筋コンクリート柱 3 端部溝形部分 4 柱鉄筋 5 コンクリート 6 下部梁主筋 7 継手筋 8 梁筋縦重ね用スペーサー 9 凹部 10 せん断補強鉄筋 11 スペーサー本体 12 帯状鋼板 14 上部梁主筋 1 Precast Concrete End Exterior Beam Members 2 Reinforced Concrete Columns 3 End Channels 4 Column Reinforcement 5 Concrete 6 Lower Beam Main Bar 7 Joint Bar 8 Beam Bar Vertical Stacking Spacer 9 Recess 10 Shear Reinforcing Bar 11 Spacer Body 12 Strip Steel 14 Upper beam main bar
───────────────────────────────────────────────────── フロントページの続き (72)発明者 中野 克彦 東京都多摩市永山3−3−16−503 (72)発明者 村山 浩久 東京都杉並区久我山5−28−19 (72)発明者 魚谷 和亮 千葉県佐倉市稲荷台2−2−17−105 (72)発明者 堀 義孝 千葉県流山市富士見台2−8−1 ヴェル ドミール江戸川台304 (72)発明者 三原 幹雄 千葉県印旛郡白井町根66−4 大木社宅 202 (72)発明者 市村 信夫 千葉県船橋市柴山2丁目5街区7−505 (72)発明者 前田 和徳 千葉県市川市南行徳3丁目17−13−102 ─────────────────────────────────────────────────── --- Continuation of the front page (72) Inventor Katsuhiko Nakano 3-3-16-503 Nagayama, Tama-shi, Tokyo (72) Hirohisa Murayama 5-28-19 Kugayama, Suginami-ku, Tokyo (72) Inventor Kazu Uotani Ryo 2-2-17-105 Inaridai, Sakura City, Chiba Prefecture (72) Inventor Yoshitaka Hori 2-8-1, Fujimidai, Nagareyama City, Chiba Prefecture Verdomir Edogawadai 304 (72) Inventor Mikio Mihara Shirai Town, Inba District, Chiba Prefecture Root 66-4 Okisha Housing 202 (72) Inventor Nobuo Ichimura 2-5 Block Shibayama, Funabashi City Chiba 7-505 (72) Inventor Kazunori Maeda 3-17-13 Minamiyukinori Ichikawa City Chiba
Claims (2)
プレキャストコンクリート製端部外郭梁部材1を、鉄筋
コンクリート柱2にわたって架設し、前記端部外郭梁部
材1における端部溝形部分3内と、柱鉄筋4の付近とに
わたって、コンクリート5を打設する梁の構築方法。1. A precast concrete end portion outer beam member 1 having an upward opening groove-shaped cross-section at the end portion is erected over a reinforced concrete column 2, and inside the end groove portion 3 of the end outer beam member 1. And a method for constructing a beam in which concrete 5 is placed across the pillar reinforcement 4.
部材1の下部梁主筋6を、端部外郭梁部材1の端部から
突出しないように配置し、柱側から前記端部外郭梁部材
1の端部溝形部分3内に延長している継手筋7を、前記
下部梁主筋6の上部に位置するように、梁筋縦重ね用ス
ペーサー8を介して保持した請求項1の梁の構築方法。2. The lower beam main bar 6 of the precast concrete end portion outer beam member 1 is arranged so as not to project from the end portion of the end outer beam member 1, and the end of the end outer beam member 1 from the column side. The method for constructing a beam according to claim 1, wherein the joint bar 7 extending into the groove portion 3 is held via a beam bar vertical stacking spacer 8 so as to be located above the lower beam main bar 6.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP33380292A JPH06158712A (en) | 1992-11-20 | 1992-11-20 | Construction method of beam |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP33380292A JPH06158712A (en) | 1992-11-20 | 1992-11-20 | Construction method of beam |
Publications (1)
Publication Number | Publication Date |
---|---|
JPH06158712A true JPH06158712A (en) | 1994-06-07 |
Family
ID=18270121
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP33380292A Pending JPH06158712A (en) | 1992-11-20 | 1992-11-20 | Construction method of beam |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPH06158712A (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US4902176A (en) * | 1988-04-08 | 1990-02-20 | Sugino Machine Limited | Processing apparatus which may be selectively set in two positions in accordance with fluid pressure |
CN102936940A (en) * | 2012-11-12 | 2013-02-20 | 北京工业大学 | Enhanced ultra-high-performance concrete component made of mixed fiber reinforced plastic (FRP) bars |
GB2543513A (en) * | 2015-10-20 | 2017-04-26 | Bryden Wood Tech Ltd | Building system |
-
1992
- 1992-11-20 JP JP33380292A patent/JPH06158712A/en active Pending
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US4902176A (en) * | 1988-04-08 | 1990-02-20 | Sugino Machine Limited | Processing apparatus which may be selectively set in two positions in accordance with fluid pressure |
CN102936940A (en) * | 2012-11-12 | 2013-02-20 | 北京工业大学 | Enhanced ultra-high-performance concrete component made of mixed fiber reinforced plastic (FRP) bars |
GB2543513A (en) * | 2015-10-20 | 2017-04-26 | Bryden Wood Tech Ltd | Building system |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JPH06158712A (en) | Construction method of beam | |
JP4314712B2 (en) | Pier structure and its construction method | |
JP3234311B2 (en) | How to build a girder intersection | |
JPH0949331A (en) | Construction method of concrete building and construction member | |
JPH0953229A (en) | Concrete-filled steel pipe column-applied structure using steel framed reinforced concrete structure underground-wall as foundation and execution method thereof | |
JPH01137032A (en) | Method of lap joint construction of main reinforcement in post and beam joining section | |
JPS6022151B2 (en) | Precast reinforced concrete beam section split vertically | |
JP3008051B2 (en) | Reinforced preassembly with formwork and reinforced preassembly method with formwork | |
JPS63184609A (en) | Method for constructing underground continuous wall | |
JP2978011B2 (en) | U-shaped beam formwork and method of constructing beam and beam joint using the same | |
JPS61169559A (en) | Semi-existing concrete panel using assembled reinforcement | |
JPH04293824A (en) | Construction method for large span underground structure | |
JPH01214641A (en) | Construction of steel-pipe precast concrete pole | |
JPH0447737B2 (en) | ||
JPH0634498Y2 (en) | Prestressed and precast concrete beams | |
JP2514859B2 (en) | Precast Steel Reinforced Concrete Concrete Column | |
JPH0448136B2 (en) | ||
JPH0213692B2 (en) | ||
JPS6335773B2 (en) | ||
JP2548597B2 (en) | Joint structure of flat plate and true column | |
JPH02120446A (en) | Precast concrete panel | |
JPS6217233A (en) | Foundation base column | |
JPH0656209U (en) | Joint structure of columns and beams | |
JPS6236097B2 (en) | ||
JPH0460183B2 (en) |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A02 | Decision of refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A02 Effective date: 20010911 |