JPH06136881A - Split type previously assembled beam reinforcement and method of assembling construction of split type previously assembled beam reinforcement - Google Patents
Split type previously assembled beam reinforcement and method of assembling construction of split type previously assembled beam reinforcementInfo
- Publication number
- JPH06136881A JPH06136881A JP5033291A JP5033291A JPH06136881A JP H06136881 A JPH06136881 A JP H06136881A JP 5033291 A JP5033291 A JP 5033291A JP 5033291 A JP5033291 A JP 5033291A JP H06136881 A JPH06136881 A JP H06136881A
- Authority
- JP
- Japan
- Prior art keywords
- reinforcement
- beam reinforcement
- rebar
- stirrup
- assembled
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Landscapes
- Reinforcement Elements For Buildings (AREA)
Abstract
Description
【0001】[0001]
【産業上の利用分野】本発明は、狭い敷地内でも先組み
工法による交差梁の配筋が可能となる、分割形先組み梁
鉄筋および分割形先組み梁鉄筋組立て工法に関するもの
である。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a split type pre-assembled beam rebar and a split type pre-assembled beam rebar assembling method capable of arranging cross beams by the pre-assembled method even in a small site.
【0002】[0002]
【従来の技術】近年、建築の鉄筋工事において鉄筋工の
不足が著しく、これに対処して従来の場所組み鉄筋に代
り、労務の省力化、工期の短縮化が可能な先組み鉄筋工
法が多く採用されるようになってきた。しかしながら、
梁が交差する十字形梁、丁字形梁、L字形梁、あるいは
大梁、小梁の取合いの場合、現場の敷地が広ければこれ
らの梁鉄筋を一体に先組みすることができるが、敷地が
狭い場合には一方向の梁鉄筋は先組みできるが、これに
交差する他方向の梁鉄筋はどうしても能率の悪い場所組
みをせざるを得ないという問題があった。2. Description of the Related Art In recent years, there has been a marked shortage of reinforcing bar work in the construction of reinforcing bars. In response to this, there are many prefabricated reinforcing bar construction methods that can replace the conventional place-assembled rebar and save labor and shorten the construction period. It has been adopted. However,
In the case of cross beams, D-shaped beams, L-shaped beams, or large beams and small beams where the beams intersect, if the site of the site is wide, these beam reinforcements can be assembled in advance, but the site is small. In this case, the beam rebars in one direction can be assembled first, but the beam rebars in the other direction intersecting with the beam rebar must be assembled inefficiently.
【0003】[0003]
【本発明が解決しようとする課題】本発明は上記問題に
鑑み、これを解決することを課題としてなされたもので
あって、狭い敷地でも先組み鉄筋工法によって能率よく
交差梁の配筋が可能となる分割形先組み梁鉄筋および分
割形先組み梁鉄筋組立て工法を提供することを目的とし
ている。SUMMARY OF THE INVENTION In view of the above problems, the present invention has been made to solve the problems, and it is possible to efficiently arrange cross beams by the pre-assembled reinforcing bar construction method even in a small site. It is an object of the present invention to provide a split type pre-assembled beam reinforcing bar and a split type pre-assembled beam reinforcing bar assembling method.
【0004】[0004]
【課題を解決するための手段】上記目的を達成するため
本発明は、梁鉄筋を、梁上ば筋にスターラップを組付け
た上側梁鉄筋と、梁下ば筋にスターラップを組付けた下
側梁鉄筋とに分割して先組みした分割形先組み梁鉄筋、
および、梁鉄筋を、梁上ば筋にスターラップを組付けた
上側梁鉄筋、および梁下ば筋にスターラップを組付けた
下側梁鉄筋とに分割して先組みし、上記上側梁鉄筋と下
側梁鉄筋とを上下に組合せて一体の梁鉄筋を組立てる分
割形先組み梁鉄筋組立て工法を特徴としている。In order to achieve the above object, the present invention comprises a beam reinforcing bar, an upper beam reinforcing bar having a stirrup attached to a beam upper beam, and a stirrup attached to a beam lower beam. Split type pre-assembled beam rebar, which is divided into lower beam rebar and assembled first,
And, the beam rebar is divided into an upper beam rebar having a stirrup attached to the beam upper beam and a lower beam rebar having a stirrup attached to the beam lower beam to be pre-assembled. And a lower beam rebar are combined vertically to assemble an integrated beam rebar.
【0005】[0005]
【作用】従って本発明によれば、交差形梁の鉄筋を先組
みする場合、一体交差形に鉄筋を先組みせず、上側梁鉄
筋と下側梁鉄筋とに分割した一方向の鉄筋梁と、これに
交差する梁の完成形梁鉄筋とを別々に先組みし、これを
交差梁に組立てるため、狭い敷地でも交差梁の先組み鉄
筋工法が可能となる。Therefore, according to the present invention, when the reinforcing bars of the cross-shaped beam are assembled first, the reinforcing bars of one direction are divided into the upper beam reinforcing bars and the lower beam reinforcing bars without first assembling the reinforcing bars in the integral intersecting shape. , The prefabricated reinforcing bar method of the crossed beam is possible even in a small site because the completed beam of the crossed beam and the rebar of the beam are separately preassembled and assembled to the crossed beam.
【0006】[0006]
【実施例】以下本発明を図示の実施例に基いて詳細に説
明する。実施例は本発明を十字形梁に応用した例であっ
て、図1、図2、図3において、1は下階に構築された
鉄筋コンクリート柱、1aは上階に延長された柱1の継
手鉄筋、3は一方向の梁鉄筋2の上側梁鉄筋、4は同じ
く一方向の梁鉄筋2の下側梁鉄筋、5は上記一方向の梁
鉄筋2に交差する完成形梁鉄筋である。上記一方向の梁
鉄筋2の上側梁鉄筋3、同じく一方向の梁鉄筋2の下側
梁鉄筋4、および一方向の梁鉄筋2に交差する完成形梁
鉄筋5は敷地内または工場で先組みされるもので、上側
梁鉄筋3は、上ば筋3aにスターラップ3bを組付け、
スターラップ3bの中段を腹筋3cで連結すると共に、
該腹筋3cの両端部および中間部に2本ずつの補助筋3
dを柱1のパネルゾーンを除いて梁方向に入れて形成さ
れ、下側梁鉄筋4は、一段の下ば筋4aにスターラップ
4bを組付け、スターラップ4bの中段を腹筋4cで連
結すると共に、該腹筋4cの両端部および中間部に2本
ずつの補助筋4dを柱1のパネルゾーンを除いて梁方向
に入れて形成される。ここで上側下側両梁鉄筋3、4の
各せいhは上側下側両梁鉄筋3、4を上下に組合せた
時、所定の梁せいHになるように設定される。前記上側
下側両梁鉄筋3、4の腹筋3c、4cおよび補助筋3
d、4dは、分割形の両梁鉄筋3、4のゆがみを抑える
と共に、両梁鉄筋3、4を上下に重ね込んだ時の重なり
位置をの規定するために入れられるものである。上側下
側両梁鉄筋3、4の各スターラップ3b、4bは、図4
に示すように、上側のスターラップ3bの下部、下側の
スターラップ4bの上部に夫々間隙3e、4eを設け、
梁上ば筋3a、梁下ば筋4a、の各スターラップ3b、
4b内への落し込みを容易にしても良く、またいずれか
一方のスターラップ3b、4bの間隙3e、4eの鉄筋
端を曲げ返して図示のようなフック3fまたは4fを形
成してもよい。完成形梁鉄筋5は、上ば筋5a、下ば筋
5bにスターラップ5cを組付けて完成形に形成され
る。The present invention will be described below in detail with reference to the illustrated embodiments. The embodiment is an example in which the present invention is applied to a cross beam. In FIGS. 1, 2, and 3, 1 is a reinforced concrete column constructed on the lower floor, and 1a is a joint of the column 1 extended to the upper floor. Reinforcing bars 3, 3 are upper beam reinforcing bars of the unidirectional beam reinforcing bar 4, 4 are lower beam reinforcing bars of the unidirectional beam reinforcing bar 2 and 5 are completed beam reinforcing bars intersecting the unidirectional beam reinforcing bar 2. The upper beam rebars 3 of the unidirectional beam rebars 2, the lower beam rebars 4 of the unidirectional beam rebars 2, and the completed beam rebars 5 intersecting the unidirectional beam rebars 2 are preassembled on the premises or at the factory. The upper beam reinforcement 3 is assembled with the stirrup 3b on the upper rib 3a,
While connecting the middle part of the stirrup 3b with the abdominal muscle 3c,
Two auxiliary muscles 3 at both ends and an intermediate portion of the abdominal muscle 3c
d is formed in the direction of the beam except the panel zone of the pillar 1, and the lower beam rebar 4 is assembled with the stirrup 4b on the lower stirrup 4a of one step, and the middle stairs of the stirrup 4b is connected by the abdominal muscle 4c. At the same time, two auxiliary muscles 4d are formed at both ends and an intermediate portion of the abdominal muscle 4c in the beam direction except the panel zone of the column 1. Here, each hindrance of the upper and lower both beam rebars 3 and 4 is set so as to be a predetermined beam hut H when the upper and lower both beam rebars 3 and 4 are vertically combined. The abdominal muscles 3c, 4c and the auxiliary muscles 3 of the upper and lower beam rebars 3, 4
d and 4d are included to suppress the distortion of the split-type two-beam reinforcing bars 3 and 4 and to regulate the overlapping position when the two-beam reinforcing bars 3 and 4 are vertically stacked. Each of the stirrup 3b, 4b of the upper and lower both beam rebars 3, 4 is shown in FIG.
As shown in, gaps 3e and 4e are provided in the lower part of the upper stirrup 3b and the upper part of the lower stirrup 4b, respectively.
Each stirrup 3b of the upper beam 3a and the lower beam 4a of the beam,
4b may be easily dropped, and the reinforcing bar ends of the gaps 3e, 4e of either one of the stir wraps 3b, 4b may be bent back to form the hook 3f or 4f as shown. The completed beam reinforcement 5 is formed in a completed form by assembling the upper reinforcement 5a and the lower reinforcement 5b with the stirrup 5c.
【0007】次に上記十字形梁鉄筋の配筋工程を説明す
ると、まず上階の梁形枠6およびスラブ形枠(図示な
し)工事を行った後、先組みした下側梁鉄筋4を吊上
げ、柱1の柱頭部の継手鉄筋1aに組込む。この後、完
成形梁鉄筋5を吊上げ、組込んだ下側両梁鉄筋4に交差
させて柱頭部に組込む。下側梁鉄筋4には梁方向の上ば
筋がなく、かつスターラップ4b中段の梁方向の補助筋
4dは柱1のパネルゾーンで欠除されているため、この
組込みは可能である。次いで下側梁鉄筋4の上側から上
側梁鉄筋3を、そのスターラップ3bの下辺が下側梁鉄
筋4中段の補助筋4dに、上側梁鉄筋3中段の補助筋3
dが下側梁鉄筋4のスターラップ4bの上辺に当接する
位置まで重ね入れて一方向の梁鉄筋2を組立て、十字形
梁の配筋が完成する。分割形の上側、下側梁鉄筋3、
4、および完成形梁鉄筋5は、梁全長で先組みされる
が、スパンが長く、接続する場合は梁中央か1/4位置
で各上ば筋3a、下ば筋4aの端部を機械式継手、また
は溶接等で接続する。この後、梁、スラブコンクリート
を一体に打設して当階のコンクリート工事を完了する。
なおコンクリート工事は、柱、梁、スラブコンクリート
を同時に打設する工法によってもよい。Next, a description will be given of the step of arranging the above-mentioned cross beam rebar. First, the beam form 6 on the upper floor and the slab form (not shown) are constructed, and then the preassembled lower beam rebar 4 is lifted. Assemble into the joint rebar 1a of the pillar head of the pillar 1. After that, the completed shaped beam rebar 5 is lifted up, crossed over the assembled lower beam rebars 4 and assembled into the pillar head. This is possible because the lower beam reinforcing bar 4 does not have an upper bar in the beam direction and the auxiliary bar 4d in the beam direction in the middle stage of the stirrup 4b is omitted in the panel zone of the column 1. Next, from the upper side of the lower beam reinforcing bar 4, the upper beam reinforcing bar 3 is arranged.
The beam reinforcement 2 in one direction is assembled by stacking up to the position where d contacts the upper side of the stirrup 4b of the lower beam reinforcement 4, and the cross-shaped beam reinforcement is completed. Split type upper and lower beam rebar 3,
4 and the completed beam rebar 5 are preassembled by the entire length of the beam, but have a long span, and when connecting, the ends of each upper bar 3a and lower bar 4a are machined at the beam center or 1/4 position. Connect by type fitting or welding. After this, the beams and slab concrete will be cast together to complete the concrete work on this floor.
Note that the concrete construction may be performed by a method of placing columns, beams, and slab concrete at the same time.
【0008】図5は本発明をハーフプレキャストコンク
リート梁に応用した実施例を示すもので、梁をハーフプ
レキャストコンクリート化施工する場合、図に示すよう
に下側梁鉄筋4の腹筋4c以下をハーフプレキャストコ
ンクリート7に埋込み、上側梁鉄筋3をあとから下側梁
鉄筋4の腹筋4cから上部に組合せ可能にする。このよ
うに梁、スラブ等をハーフプレキャストコンクリート化
することによって、型枠工事が不要になって一層省力
化、工期の短縮が実現される。FIG. 5 shows an embodiment in which the present invention is applied to a half precast concrete beam. When the beam is subjected to half precast concrete construction, as shown in the figure, the abdominal muscles 4c and below of the lower beam reinforcing bar 4 are half precast. It is embedded in concrete 7 so that the upper beam reinforcing bar 3 can be later combined with the lower beam reinforcing bar 4 from the abdominal muscle 4c to the upper part. By making the beams, slabs, etc., into half-precast concrete in this way, formwork is not required, and labor is further saved and the construction period is shortened.
【0009】[0009]
【発明の効果】以上説明したように本発明は、梁鉄筋
を、梁上ば筋にスターラップを組付けた上側梁鉄筋と、
梁下ば筋にスターラップを組付けた下側梁鉄筋とに分割
して先組みし、上記上側梁鉄筋と下側梁鉄筋とを現場で
上下に組合せて一体の梁鉄筋を組立てるものであるか
ら、十字形梁、丁字形梁、L字形梁、あるいは大梁と小
梁の組立て鉄筋工事において、現場の狭い敷地でも、ま
た運搬が可能なため工場でも梁鉄筋の先組みができ、鉄
筋工不足の現時において梁鉄筋工事の省力化および工期
の短縮が実現されるという極めて有用な効果を奏するも
のである。As described above, according to the present invention, a beam rebar is an upper beam rebar in which a stirrup is attached to a beam upper bar,
This is to assemble the lower beam rebar with the stirrup attached to the lower beam rebar and assemble it first, and then assemble the upper beam rebar and the lower beam rebar above and below on site to assemble an integrated beam rebar. Therefore, in the cross-beam, D-shaped beam, L-shaped beam, or assembling rebar construction of large and small beams, beam rebars can be pre-assembled even in a small site on site or at a factory, so there is a shortage of rebar work. At the present time, the labor-saving work of the beam reinforcement and the shortening of the construction period are realized, which is a very useful effect.
【0010】[0010]
【図1】本発明工法によって配筋した十字形梁鉄筋の側
面図である。FIG. 1 is a side view of a cross beam rebar reinforced by the method of the present invention.
【図2】同上十字形梁鉄筋の平面図である。FIG. 2 is a plan view of the cross beam reinforcement of the same as above.
【図3】上側梁鉄筋を下側梁鉄筋に組合せて一方向の梁
鉄筋を組立てる工程を示す横断面図である。FIG. 3 is a cross-sectional view showing a step of assembling a beam reinforcement in one direction by combining an upper beam reinforcement with a lower beam reinforcement.
【図4】スターラツプの他の実施例を示す正面図であ
る。FIG. 4 is a front view showing another embodiment of the star lap.
【図5】本発明工法をハーフプレキャストコンクリート
梁に応用した実施例の横断面図である。FIG. 5 is a cross-sectional view of an example in which the method of the present invention is applied to a half precast concrete beam.
【0011】[0011]
2 一方向の梁鉄筋 3 上側梁鉄筋 3a 下ば筋 3b スターラップ 4 下側梁鉄筋 4a 上ば筋 4b スターラップ 5 一方向の梁鉄筋に交差する完成形梁鉄筋 5a 上ば筋 5b 下ば筋 5c スターラップ 2 Unidirectional beam rebar 3 Upper beam rebar 3a Lower rebar 3b Stirrup 4 Lower beam rebar 4a Upper bar 4b Stirrup 5 Completed beam rebar 5a Unidirectional beam rebar 5a Upper bar 5b Lower bar 5c stirrup
───────────────────────────────────────────────────── フロントページの続き (72)発明者 井上 晴久 東京都中央区京橋二丁目16番1号 清水建 設株式会社内 (72)発明者 斎藤 豊 東京都中央区京橋二丁目16番1号 清水建 設株式会社内 (72)発明者 山田 信一 東京都中央区京橋二丁目16番1号 清水建 設株式会社内 ─────────────────────────────────────────────────── ─── Continuation of the front page (72) Haruhisa Inoue, 2-16-1, Kyobashi, Chuo-ku, Tokyo Shimizu Construction Co., Ltd. (72) Yutaka Saito 2--16-1, Kyobashi, Chuo-ku, Tokyo Shimizu Construction company (72) Inventor Shinichi Yamada 2-16-1, Kyobashi, Chuo-ku, Tokyo Shimizu Construction company
Claims (2)
付けた上側梁鉄筋と、梁下ば筋にスターラップを組付け
た下側梁鉄筋とに分割して先組みしたことを特徴とする
分割形先組み梁鉄筋。1. A beam rebar is divided into an upper beam rebar having a stirrup attached to a beam upper beam and a lower beam rebar having a stirrup attached to a beam lower beam and preassembled. Characteristic split type pre-assembled beam rebar.
付けた上側梁鉄筋と、梁下ば筋にスターラップを組付け
た下側梁鉄筋とに分割して先組みし、上記上側梁鉄筋と
下側梁鉄筋とを上下に組合せて一体の梁鉄筋を組立てる
ことを特徴とする分割形先組み梁鉄筋組立て工法。2. The beam reinforcing bar is divided into an upper beam reinforcing bar having a stirrup attached to a beam upper beam and a lower beam reinforcing bar having a stirrup attached to a beam lower beam, which are preassembled, A split type pre-assembled beam rebar assembling method, characterized in that an upper beam rebar and a lower beam rebar are vertically combined to assemble an integrated beam rebar.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP3050332A JP3008305B2 (en) | 1991-02-22 | 1991-02-22 | Split pre-assembled beam rebar and split pre-assembled beam rebar assembling method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP3050332A JP3008305B2 (en) | 1991-02-22 | 1991-02-22 | Split pre-assembled beam rebar and split pre-assembled beam rebar assembling method |
Publications (2)
Publication Number | Publication Date |
---|---|
JPH06136881A true JPH06136881A (en) | 1994-05-17 |
JP3008305B2 JP3008305B2 (en) | 2000-02-14 |
Family
ID=12855963
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP3050332A Expired - Fee Related JP3008305B2 (en) | 1991-02-22 | 1991-02-22 | Split pre-assembled beam rebar and split pre-assembled beam rebar assembling method |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP3008305B2 (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20080302057A1 (en) * | 2005-07-28 | 2008-12-11 | Michael Muller | Method for Producing a Wall-Ceiling Reinforced Concrete Construction |
CN105297919A (en) * | 2015-10-30 | 2016-02-03 | 中国十七冶集团有限公司 | Seismic strengthening method for frame beam-column joint core area |
-
1991
- 1991-02-22 JP JP3050332A patent/JP3008305B2/en not_active Expired - Fee Related
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20080302057A1 (en) * | 2005-07-28 | 2008-12-11 | Michael Muller | Method for Producing a Wall-Ceiling Reinforced Concrete Construction |
US8484928B2 (en) * | 2005-07-28 | 2013-07-16 | Vst Verbundschalungstechnik Ag | Method for producing a wall-ceiling reinforced concrete construction |
CN105297919A (en) * | 2015-10-30 | 2016-02-03 | 中国十七冶集团有限公司 | Seismic strengthening method for frame beam-column joint core area |
Also Published As
Publication number | Publication date |
---|---|
JP3008305B2 (en) | 2000-02-14 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP3069753B2 (en) | Construction method of framed reinforced concrete structure | |
JPH069170Y2 (en) | Beam structure | |
JPH06136881A (en) | Split type previously assembled beam reinforcement and method of assembling construction of split type previously assembled beam reinforcement | |
JPH0728269Y2 (en) | Precast beams | |
JP3008051B2 (en) | Reinforced preassembly with formwork and reinforced preassembly method with formwork | |
JPH067125Y2 (en) | Structure of the stigma of the flat slab | |
JPH0118229B2 (en) | ||
JP2001020376A (en) | Sc beam construction method for building | |
JPH0197744A (en) | Shearing reinforcing structure of shear head section in flat plate building | |
JP3187618B2 (en) | How to assemble beam reinforcement | |
JPH0634498Y2 (en) | Prestressed and precast concrete beams | |
JPS61169559A (en) | Semi-existing concrete panel using assembled reinforcement | |
JPH05141025A (en) | Constructing method for reinforced concrete wall | |
JPH01214641A (en) | Construction of steel-pipe precast concrete pole | |
JPH07268883A (en) | Method of construction of footing section using precast footing beam | |
JP2978011B2 (en) | U-shaped beam formwork and method of constructing beam and beam joint using the same | |
JP2726606B2 (en) | How to assemble beam reinforcement | |
JP3108828B2 (en) | Beam-to-column reinforced body and method of arranging beam-to-column reinforcement | |
JPH056335Y2 (en) | ||
JP2732113B2 (en) | PC column / beam joining method | |
JPH1030273A (en) | Column/beam connecting structure and method | |
JP2651506B2 (en) | How to apply underground beams | |
JPH06108536A (en) | Framework by means of hollow precast concrete pole whose connecting part is formed into steel construction | |
JP2908088B2 (en) | Hollow composite slab method | |
JP2001073492A (en) | Reinforcing structure for flat plate joint part |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
LAPS | Cancellation because of no payment of annual fees |