JPH0610330A - Permeation type weir made of steel - Google Patents

Permeation type weir made of steel

Info

Publication number
JPH0610330A
JPH0610330A JP4167771A JP16777192A JPH0610330A JP H0610330 A JPH0610330 A JP H0610330A JP 4167771 A JP4167771 A JP 4167771A JP 16777192 A JP16777192 A JP 16777192A JP H0610330 A JPH0610330 A JP H0610330A
Authority
JP
Japan
Prior art keywords
columns
central part
dam
gravel
permeation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP4167771A
Other languages
Japanese (ja)
Other versions
JPH07119459B2 (en
Inventor
Shunichiro Kasai
俊一郎 葛西
Noboru Watanabe
昇 渡辺
Joji Shima
丈示 嶋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kobe Steel Ltd
Original Assignee
Kobe Steel Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kobe Steel Ltd filed Critical Kobe Steel Ltd
Priority to JP4167771A priority Critical patent/JPH07119459B2/en
Publication of JPH0610330A publication Critical patent/JPH0610330A/en
Publication of JPH07119459B2 publication Critical patent/JPH07119459B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Revetment (AREA)

Abstract

PURPOSE:To prevent movement of an aqueduct after an avalanche of sand and stone is captured by a method wherein the position of a beam between the columns of the central part of a permeation part of which a weir is composed is lowered to a level lower than that of a beam between other columns and by a distance shorter than a distance between the columns 1. CONSTITUTION:The position of a steel pipe beam 2 between steel pipe columns 1 at the central part of a permeation part of which a permeation type weir is composed is lowered to a level lower than that of a beam 2 between other columns 1. The position of the steel pipe beam 2 at a topmost stage between the steel pipes column 1 is gradually raised to a level higher than the position of the beam 2 between the columns 1 at the central part of the permeation part from the central part toward both sides. And the beam 2 is arranged by a distance shorter than a distance between the columns 1 below the beam 2 at a topmost stage between the columns 1. This constitution pushes out a larger quantity of stone gravels, accumulated at the beam 2 at the central part, of relatively smaller stone gravels subsequently accumulated on stone gravels having a maximum size captured by the weir, causes centralization of flowing water to a central part, and ensures an aqueduct.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明は、土石流規制用ダムに関
し、さらに詳しくは、土石流の捕捉後も水通し中央部に
水道がくる透過型鋼製堰堤に関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a debris flow control dam, and more particularly, to a transmission steel dam which allows water to pass through in the central portion of the water passage even after trapping debris flow.

【0002】[0002]

【従来の技術】土石流対策として、現在、透過型鋼製堰
堤が用いられている。この鋼製堰堤には、図3(a) に示
すように、鋼管柱1と鋼管梁2を立体格子状に組合せた
構造の格子形鋼製堰堤と図3(b) に示すように、鋼管柱
1と鋼管梁2を組合せた構造のB型スリットダムとがあ
る。これらの堰堤の特徴は、土石流が流下するとき、図
4に示すように、先端部に巨石が集中するという特徴を
利用して、土石流の全部あるいは一部を捕捉する機能を
有していることである。
2. Description of the Related Art Transmission steel dams are currently used as a measure against debris flow. In this steel dam, as shown in Fig. 3 (a), a grid-shaped steel dam having a structure in which steel pipe columns 1 and steel pipe beams 2 are combined in a three-dimensional lattice shape, and as shown in Fig. 3 (b), steel pipes are used. There is a B type slit dam having a structure in which a pillar 1 and a steel pipe beam 2 are combined. The feature of these dams is that they have the function of capturing all or part of the debris flow by utilizing the feature that megaliths concentrate at the tip when the debris flow flows down, as shown in FIG. Is.

【0003】土石流の捕捉効果は、土石流の先端部12を
構成するであろう石礫群に注目し、この石礫の最大径10
の 1.5倍以下の柱純間隔11であれば後続の土石流をも完
全に捕捉し、 2.0倍であれば先端部の石礫を捕捉するこ
とが知られている。また、柱、梁純間隔を 2.0倍にする
と柱純間隔の 1.5倍と同じ捕捉が得られる。この機能を
発揮させる要因は、ダム構造を構成している鋼管柱1の
内、上流側に位置する河川軸直角方向の柱純間隔11であ
る。そこで、現在この種の堰堤を構成する河川軸直角方
向の柱純間隔11は最大石礫径の 1.5〜2.0 倍の範囲を採
用している。
Regarding the debris flow capturing effect, attention is paid to the gravel gravel group that will constitute the tip portion 12 of the debris flow, and the maximum diameter of the gravel gravel is 10
It is known that if the net spacing of the pillars is less than 1.5 times, then the subsequent debris flow will be completely captured, and if it is 2.0 times, the gravel at the tip will be captured. Also, if the net spacing between columns and beams is increased by 2.0 times, the same capture as 1.5 times the net spacing between columns is obtained. The factor that exerts this function is the net spacing 11 between the steel pipe columns 1 forming the dam structure, which is located upstream and is perpendicular to the river axis. Therefore, at present, the net spacing 11 between the pillars in the direction perpendicular to the river axis, which constitutes this type of dam, is in the range of 1.5 to 2.0 times the maximum gravel diameter.

【0004】[0004]

【発明が解決しようとする課題】一般に、透過型鋼製堰
堤は透過部を鋼製とし、非透過部をコンクリート製とし
ている。透過部の中央部は河川軸の中央付近に設置され
る。しかし、土石流の流下特性によって、透過部の中央
部に石礫が堆積するため、堰堤が土石流を捕捉したあと
は、透過部の端に水道が移動することが調査によって確
かめられている。水道が透過部の端に移動すると、水道
のある側の山腹は浸食され、二次災害が発生する恐れが
生じる。
Generally, in a permeable steel dam, the permeable portion is made of steel and the non-permeable portion is made of concrete. The central part of the transparent part is installed near the center of the river axis. However, due to the flow characteristics of the debris flow, gravel is deposited in the central part of the permeation part, so it has been confirmed by research that the water supply moves to the end of the permeation part after the dam has captured the debris flow. When the water supply moves to the end of the permeable part, the hillside on the water supply side is eroded, which may cause a secondary disaster.

【0005】本発明は、上記の問題点を解決するために
なされたもので、鋼製堰堤を構成している柱間の梁の位
置を規制することによって、堰堤が土石流を捕捉したあ
とも水道が移動しない透過型鋼製堰堤を提供することを
目的とする。
The present invention has been made in order to solve the above problems, and regulates the position of the beam between the columns forming the steel dam, so that the waterworks can be performed even after the dam has captured the debris flow. It is an object of the present invention to provide a transmission steel dam that does not move.

【0006】[0006]

【課題を解決するための手段】透過型鋼製堰堤において
は、最上流の柱純間隔のみが土石流の捕捉効果をもって
いるが、本発明では構造部材として位置付けられている
梁を機能部材として積極的に利用するもので、第1発明
は、透過型鋼製堰堤において、堰堤を構成している透過
部の中央部の柱間の梁の位置を、他の柱間の梁の位置よ
りも、柱間隔よりも低くした透過型鋼製堰堤である。
In a transmission type steel dam, only the most upstream column net spacing has a debris trapping effect, but in the present invention, a beam positioned as a structural member is positively used as a functional member. According to the first aspect of the present invention, in a transmission type steel dam, the position of the beam between the pillars in the central part of the transparent portion forming the dam is set to be greater than the position of the beam between the other pillars. It is a permeation type steel dam that is lower than the gap.

【0007】第2発明は、透過型鋼製堰堤において、堰
堤を構成している透過部の柱間の最上段の梁の位置を、
透過部の中央部の柱間の梁の位置よりも、中央部から両
側にいくにしたがって、順次高くし、かつ前記柱間の最
上段の梁の下に柱間隔よりも短い間隔で梁を配置した透
過型鋼製堰堤である。
The second aspect of the present invention is that, in a transmission type steel dam, the position of the uppermost beam between the columns of the transmission part forming the dam is
The beam is positioned higher than the position of the beam between the pillars in the central part of the transparent part, going from the central part to both sides, and the beams are arranged below the uppermost beam between the pillars at intervals shorter than the column interval. It is a transmissive steel dam.

【0008】[0008]

【作用】土石流の先端部の石礫は柱純間隔により捕捉さ
れるが、後続流によって、捕捉された石礫が押し流され
る恐れがある。しかし、梁が存在する場合、梁より下の
部分で捕捉された石礫は、堰堤に捕捉されたままの状態
で留まることが調査によって確かめられている。
Operation: The gravel at the tip of the debris flow is captured by the column spacing, but the trapped gravel may be washed away by the subsequent flow. However, investigations have confirmed that when beams are present, the gravel trapped below the beams remains trapped in the dam.

【0009】この現象を利用して、堰堤を構成している
透過部の中央部の柱間の梁の位置を、他の柱間の梁の位
置よりも、柱間隔よりも低くすることによって、梁より
下の部分で捕捉された石礫は拘束され、梁より上の部分
を流れる比較的小さい石礫は越流する。したがって、梁
によって、拘束された石礫は中央部が最低となり、結果
的に、ここに水道が確保される。
By utilizing this phenomenon, the position of the beam between the pillars in the central part of the transmission part forming the dam is made lower than the position of the beam between the other pillars by a distance between the pillars. The gravel trapped below the beam is restrained, and the relatively small gravel flowing above the beam overflows. Therefore, the gravel bound by the beam has the lowest central portion, and as a result, the water supply is secured here.

【0010】柱間の梁の位置を、透過部の中央部の柱間
の梁の位置よりも、中央部から両側にいくにしたがって
順次高くすると、梁によって、拘束された石礫は両側に
いくにしたがって高くなり、石礫の堆積形状はV字形に
なる。したがって、流水を中央部に集めやすくなり、水
道が中央部から移動することはない。
If the positions of the beams between the columns are made higher than the positions of the beams between the columns in the central part of the transparent portion as they go from the central part to both sides, the stones and stones bound by the beams will go to both sides. The height of the gravel becomes V-shaped. Therefore, it becomes easy to collect the running water in the central part, and the water supply does not move from the central part.

【0011】ただし、柱間の梁の位置を、透過部の中央
部の柱間の梁の位置よりも、中央部から両側にいくにし
たがって順次高くするのみでは、中央部の柱間の梁の位
置が一番ひくくなり、ここが最も石礫を留めやすくな
る。すなわち、石礫が各柱間の梁まで堆積してV字形に
なるまでは、中央部に山なりに石礫を堆積することにな
り、流水を二つに分けることになる。このため、柱間の
最上段の梁の下に柱間隔よりも短い間隔で梁を配置する
ことによって、中央部に石礫が堆積するのをさける。
However, if the positions of the beams between the pillars are made higher than the positions of the beams between the pillars in the central portion of the transparent portion in order from the central portion to both sides, the beam between the pillars in the central portion will be increased. The position is the lowest, and it's the easiest place to hold gravel. That is, until the gravel is deposited up to the beam between the pillars and becomes V-shaped, the gravel is piled up in the central part, and the running water is divided into two. Therefore, by arranging the beams below the uppermost beam between the columns at an interval shorter than the column interval, it is possible to prevent gravel from accumulating in the central portion.

【0012】[0012]

【実施例】以下に、本発明の実施例を図に基づいて説明
する。図1(a) は本発明の透過部の中央部の柱間の梁の
位置を、他の柱間の梁の位置よりも低くし、かつ柱間隔
よりも低くした透過型鋼製堰堤の図で、図1(b) は柱間
の最上段の梁の位置を、透過部の中央部の柱間の梁の位
置よりも、中央部から両側にいくにしたがって、順次高
くし、かつ前記柱間の最上段の梁の下に柱間隔よりも短
い間隔で梁を配置した透過型鋼製堰堤の図である。図に
おいて、1は鋼管柱を、2は鋼管梁を、3は河川軸を、
4は梁純間隔をそれぞれ示す。なお、梁純間隔4は柱純
間隔よりも短い。
Embodiments of the present invention will be described below with reference to the drawings. FIG. 1 (a) is a diagram of a transmission type steel dam in which the position of the beam between the pillars in the central portion of the transparent portion of the present invention is lower than the position of the beam between other pillars and lower than the distance between the pillars. In Fig. 1 (b), the position of the uppermost beam between columns is higher than the position of the beam between columns in the central part of the transmissive part from the central part to both sides, and It is a figure of the permeation | transmission type steel dam which has arrange | positioned the beam with the space | interval shorter than the space | interval of a pillar under the beam of the highest step in between. In the figure, 1 is a steel pipe column, 2 is a steel pipe beam, 3 is a river axis,
4 shows the beam pure intervals, respectively. The beam net spacing 4 is shorter than the column net spacing.

【0013】図2は図1(a) に示す透過型鋼製堰堤に石
礫が堆積する過程を模式的に示したものである。以下図
2に基づいて実施例を説明していく。
FIG. 2 schematically shows a process in which gravel is deposited on the permeable steel dam shown in FIG. 1 (a). An embodiment will be described below with reference to FIG.

【0014】土石流を捕捉する機能自体は柱純間隔によ
り決定される。土石流の先端部が堰堤に到達すると、図
2(a) のように、最大石礫径を有する石礫5を柱部材が
捕捉する。このとき、捕捉状態の初期段階では堰堤の透
過部の中央部と端では、捕捉状態に差異は認められな
い。その後、後続流に含まれる中小砂礫が柱によって捕
捉された石礫5の隙間を埋めていく。
The function of capturing the debris flow itself is determined by the column net spacing. When the tip of the debris flow reaches the dam, the pillar member captures the gravel 5 having the maximum gravel diameter, as shown in Fig. 2 (a). At this time, in the initial stage of the trapped state, there is no difference in the trapped state between the central part and the end of the permeation part of the dam. After that, the small and medium gravel contained in the subsequent flow fills the gap of the gravel 5 captured by the pillar.

【0015】埋め尽くされると、後続の比較的小さい石
礫6は、この上を越流しようとし、図2(b) のように、
堆積高さを増す。すると、図2(C) のように、水面8が
堰き上げられて堆積した石礫の背面の水圧が大きくな
る。
When it is filled up, the subsequent relatively small gravel 6 tries to overflow over it, as shown in FIG. 2 (b).
Increase the pile height. Then, as shown in FIG. 2 (C), the water pressure on the back surface of the gravel accumulated by the water surface 8 being dammed up increases.

【0016】水圧に耐えきれなくなった石礫6は、図2
(d) のように、柱間から押し出される。このとき、梁よ
り下に堆積している石礫6は、梁部材によって拘束さ
れ、梁より上に堆積した石礫6のみ押し出される。ま
た、中央部の梁は低く配置しているため、押し出される
石礫6が多く、押し出されると、流水がここに集中する
ようになる。したがって、土石流通過後も堰堤透過部の
中央部に水道7が確保され、河川軸は移動しない。
The stone gravel 6 which cannot endure water pressure is shown in FIG.
As shown in (d), it is pushed out from the pillar. At this time, the gravel 6 deposited below the beam is restrained by the beam member, and only the gravel 6 deposited above the beam is pushed out. Further, since the beam in the central portion is arranged low, a large amount of gravel 6 is extruded, and when it is extruded, running water concentrates there. Therefore, even after passing the debris flow, the water supply 7 is secured in the central part of the dam penetration part, and the river axis does not move.

【0017】[0017]

【発明の効果】本発明は、透過型鋼製堰堤において、堰
堤を構成している透過部の中央部の柱間の梁の位置を、
他の柱間の梁の位置よりも低くし、かつ梁間の間隔(梁
純間隔)を柱間隔よりも短くし、柱間の最上段の梁の位
置を、透過部の中央部の柱間の梁の位置よりも、中央部
から両側にいくにしたがって、順次高くし、かつ前記柱
間の最上段の梁の下に柱間隔よりも短い間隔で梁を配置
した透過型鋼製堰堤であって、本透過型鋼製堰堤によれ
ば、透過部の中央部に堆積する石礫が少なく、土石流通
過後も堰堤透過部の中央部に水道が確保され、河川軸は
移動することはない。したがって、堰堤透過部の中央部
の水道が透過部の端に移動することもなく、水道が山腹
を浸食することもなく、二次災害の発生する恐れもなく
なる。
As described above, according to the present invention, in a transmission type steel dam, the position of the beam between the pillars in the central part of the transmission part forming the dam is
It is lower than the position of the beam between other columns, and the interval between beams (beam net interval) is shorter than the column interval, and the position of the uppermost beam between columns is set between the columns at the center of the transmission part. A transmission type steel dam, in which the beams are sequentially raised from the center to both sides from the position of the beams, and the beams are arranged below the uppermost beam between the columns at intervals shorter than the column intervals. According to this transmission type steel dam, the amount of stones and gravel accumulated in the central part of the permeation part is small, the water supply is secured in the central part of the permeation part of the dam after the debris flow and the river axis does not move. Therefore, the water supply in the central part of the dam permeation part does not move to the end of the permeation part, the water supply does not erode the hillside, and there is no risk of a secondary disaster.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明の透過型鋼製堰堤の説明図である。FIG. 1 is an explanatory view of a transmission type steel dam according to the present invention.

【図2】本発明の透過型鋼製堰堤に石礫が堆積する過程
を模式的に示す図である。
FIG. 2 is a view schematically showing a process in which stones and gravel are deposited on the transmission steel dam of the present invention.

【図3】従来の透過型鋼製堰堤の例を示す図である。FIG. 3 is a diagram showing an example of a conventional transmission steel dam.

【図4】透過型鋼製堰堤が土石流を捕捉する機能を説明
する図である。
FIG. 4 is a diagram illustrating a function of a transmission steel dam to capture a debris flow.

【符号の説明】[Explanation of symbols]

1…鋼管柱、2…鋼管梁、3…河川軸、4…梁純間隔、
5…石礫、6…石礫、7…水道、8…水面、10…石礫の
最大径、11…柱純間隔、12…土石流の先端部。
1 ... Steel tube column, 2 ... Steel tube beam, 3 ... River axis, 4 ... Net beam spacing,
5 ... Stone gravel, 6 ... Stone gravel, 7 ... Water supply, 8 ... Water surface, 10 ... Maximum diameter of stone gravel, 11 ... Net spacing of columns, 12 ... Tip of debris flow.

Claims (2)

【特許請求の範囲】[Claims] 【請求項1】 透過型鋼製堰堤において、堰堤を構成し
ている透過部の中央部の柱間の梁の位置を、他の柱間の
梁の位置よりも、柱間隔よりも低くしたことを特徴とす
る透過型鋼製堰堤。
1. In a transmissive steel dam, the position of the beam between the pillars in the central part of the transparent part constituting the dam is set lower than the position of the beam between other pillars. A permeation type steel dam.
【請求項2】 透過型鋼製堰堤において、堰堤を構成し
ている透過部の柱間の最上段の梁の位置を、透過部の中
央部の柱間の梁の位置よりも、中央部から両側にいくに
したがって、順次高くし、かつ前記柱間の最上段の梁の
下に柱間隔よりも短い間隔で梁を配置したことを特徴と
する透過型鋼製堰堤。
2. In the transmission type steel dam, the position of the uppermost beam between the columns of the transmission part forming the dam is set from the central portion rather than the position of the beam between the columns of the central portion of the transmission part. A permeation type steel dam, wherein the beams are gradually increased toward both sides, and the beams are arranged below the uppermost beam between the columns at intervals shorter than the column intervals.
JP4167771A 1992-06-25 1992-06-25 Transparent steel dam Expired - Fee Related JPH07119459B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP4167771A JPH07119459B2 (en) 1992-06-25 1992-06-25 Transparent steel dam

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP4167771A JPH07119459B2 (en) 1992-06-25 1992-06-25 Transparent steel dam

Publications (2)

Publication Number Publication Date
JPH0610330A true JPH0610330A (en) 1994-01-18
JPH07119459B2 JPH07119459B2 (en) 1995-12-20

Family

ID=15855801

Family Applications (1)

Application Number Title Priority Date Filing Date
JP4167771A Expired - Fee Related JPH07119459B2 (en) 1992-06-25 1992-06-25 Transparent steel dam

Country Status (1)

Country Link
JP (1) JPH07119459B2 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2017101502A (en) * 2015-12-04 2017-06-08 日鐵住金建材株式会社 Steel slit dam
JP2021120537A (en) * 2017-07-20 2021-08-19 Jfe建材株式会社 Method for identifying non-damaged portion, method for marking cutting position, tool for identifying non-damaged portion, and device for marking cutting position

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2017101502A (en) * 2015-12-04 2017-06-08 日鐵住金建材株式会社 Steel slit dam
JP2021120537A (en) * 2017-07-20 2021-08-19 Jfe建材株式会社 Method for identifying non-damaged portion, method for marking cutting position, tool for identifying non-damaged portion, and device for marking cutting position

Also Published As

Publication number Publication date
JPH07119459B2 (en) 1995-12-20

Similar Documents

Publication Publication Date Title
JP2016510095A (en) Fluid earth and sand damming device
Chanson Sabo check dams‐mountain protection systems in Japan
JPH0782725A (en) Permeable erosion control weir levee
JP3087260B2 (en) Debris stop work
JP2003129437A (en) Structure for catching flow-down matter and energy absorption in river and mountain stream
Chanson History of stepped channels and spillways: a rediscovery of the “wheel”
CN108755895A (en) A kind of counter-slope formula is shut off filtration system and its construction method
JPH0610330A (en) Permeation type weir made of steel
RU2321701C2 (en) Weir construction method
CN108204029A (en) A kind of municipal rainwater storage system
JP2005030070A (en) Flowing-down promoting dam structure and flowing-down promoting method of deposit sediment in dam water reservoir
Chanson Embankment overtopping protections system and earth dam spillways
RU2573328C2 (en) Reserve spillway of soil retaining structure (versions)
CN207032191U (en) River channel sewage intercepting and supporting construction
JP3000201B2 (en) Sabo dam and sabo method
CN104831689A (en) Siltation-preventing water intake facility achieving automatic flood prevention and pollution discharge
JP7212581B2 (en) Debris flow sedimentary work
JP5080620B2 (en) Intake mechanism of Sabo Dam
JP7022630B2 (en) Driftwood capture facility
RU2126868C1 (en) Dike
JP2003138545A (en) Permeable type check dam
KR101039619B1 (en) River with acceleration channel preventing sedimentation
JP3860029B2 (en) Transmission type sabo dam and manufacturing method thereof
JP7098039B2 (en) Driftwood capture facility
JP4118770B2 (en) Sabo dam storage and drainage structure

Legal Events

Date Code Title Description
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 19960618

LAPS Cancellation because of no payment of annual fees