JPH059931A - Joining method for underground continuous wall - Google Patents
Joining method for underground continuous wallInfo
- Publication number
- JPH059931A JPH059931A JP3189399A JP18939991A JPH059931A JP H059931 A JPH059931 A JP H059931A JP 3189399 A JP3189399 A JP 3189399A JP 18939991 A JP18939991 A JP 18939991A JP H059931 A JPH059931 A JP H059931A
- Authority
- JP
- Japan
- Prior art keywords
- joint
- horizontal
- reinforcing bar
- reinforcement
- bar
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Landscapes
- Bulkheads Adapted To Foundation Construction (AREA)
Abstract
Description
【0001】[0001]
【産業上の利用分野】本発明は、地下連続壁の水平鉄筋
継手による接合方法に関するものである。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for joining underground continuous walls with horizontal reinforcing bar joints.
【0002】[0002]
【従来の技術】地下連続壁は周知のごとく、横長の掘削
孔を地盤に形成してこの掘削孔内に鉄筋カゴを挿入し、
次いで、コンクリートを掘削孔内に打設して鉄筋コンク
リート製のパネルを地中に作製し、このコンクリート製
のパネルを単位エレメントとしてこれを順次接続してい
くものである。そして、従来、地下連続壁を地下階の耐
震壁として利用する場合には、面内力を伝達するための
クロスバー継手工法などにより各パネル間を連結するこ
とになる。As is well known for underground continuous walls, a horizontally long drill hole is formed in the ground, and a reinforcing bar basket is inserted into the drill hole.
Next, concrete is poured into the excavation hole to fabricate a reinforced concrete panel in the ground, and the concrete panel is used as a unit element and sequentially connected. Then, conventionally, when the continuous underground wall is used as an earthquake-resistant wall of a basement floor, each panel is connected by a crossbar joint construction method or the like for transmitting in-plane force.
【0003】さらに継手工法としては面内および面外力
を伝達できる壁間継手工法として、水平筋重ね継手工法
が採用されることがある。この工法を図5、図6に示す
と、先行エレメント1は後端部に鉄板型枠としての仕切
板3を組み込んだ鉄筋カゴ4の該仕切板3から先に鉄筋
継手5を突出させている。この鉄筋継手5も鉄筋カゴ4
と同様に水平筋5aと縦筋5bの組合わせで構成する。
先行エレメント1側で打設するコンクリートはこの仕切
板3で止められる。後行エレメント2は先端部に鉄筋継
手8を設けた鉄筋カゴ9を配設する。この鉄筋継手8は
前記鉄筋継手5内に入り込むような巾狭のもので、鉄筋
継手5と同じく水平筋8aと縦筋8bの組合わせで構成
するが、水平筋8aを曲成してその相互間隔を狭めるよ
うに構成している。Further, as a joint construction method, a horizontal streak lap joint construction method may be adopted as an inter-wall joint construction method capable of transmitting in-plane and out-of-plane forces. This construction method is shown in FIGS. 5 and 6. In the preceding element 1, the reinforcing bar joint 5 is projected from the partition plate 3 of the reinforcing bar basket 4 in which the partition plate 3 as the iron plate form is incorporated at the rear end. . This rebar joint 5 is also a rebar basket 4
Similarly, the horizontal streaks 5a and the vertical streaks 5b are combined.
The concrete placed on the side of the preceding element 1 is stopped by this partition plate 3. The trailing element 2 is provided with a reinforcing bar basket 9 having a reinforcing bar joint 8 at its tip. The rebar joint 8 is narrow so that it can be inserted into the rebar joint 5, and is composed of a combination of the horizontal bar 8a and the vertical bar 8b as in the rebar joint 5, but the horizontal bar 8a is bent and the mutual It is configured to narrow the gap.
【0004】先行エレメント1のコンクリート6を打設
した後で、後行エレメント2の鉄筋カゴ4を掘削孔10内
に配設し、図示は省略するが後行エレメント2のコンク
リートを打設すれば、ラップする鉄筋継手5と鉄筋継手
8で接合がなされる。After the concrete 6 of the preceding element 1 is poured, the reinforcing bar basket 4 of the trailing element 2 is placed in the excavation hole 10 and, although not shown, the concrete of the trailing element 2 is poured. The reinforced rebar joint 5 and the rebar joint 8 are wrapped to make a joint.
【0005】[0005]
【発明が解決しようとする課題】前記図5、図6に示す
従来の継手接合構造は、鉄筋継手相互の接合としては接
合鉄筋である水平筋5a,8aを間隔を存してラップさ
せているだけなので、面外の曲げ応力βを受けると引っ
張り側のこれらの水平筋が外側に弾け、図5のαに示す
ように後行エレメント2側のコンクリートにひび割れが
発生して耐力が低下してしまうおそれがある。In the conventional joint joint structure shown in FIGS. 5 and 6, the horizontal bars 5a and 8a, which are joint bars, are lapped at intervals with respect to each other for joining the reinforcing bar joints. Therefore, when an out-of-plane bending stress β is applied, these horizontal streaks on the pulling side bounce outward, and as shown by α in Fig. 5, cracks occur in the concrete on the trailing element 2 side and the yield strength decreases. There is a risk that
【0006】このような水平筋5a,8aによる割裂破
壊は極めて脆弱的であり、水平筋量を増やしても割裂破
壊を防げない。また、割裂破壊耐力は水平筋の重ね長さ
と正の相関関係にあり、かつ先行パネル側水平筋と後行
パネル側水平筋が鉛直方向に離れている場合でも、割裂
破壊耐力が多少高くなる程度で割裂破壊は生じる。The splitting fracture by the horizontal streaks 5a and 8a is extremely fragile, and the splitting fracture cannot be prevented even if the amount of the horizontal streaks is increased. In addition, the splitting fracture resistance is positively correlated with the overlapping length of the horizontal streak, and even if the leading panel side horizontal strip and the trailing panel side horizontal strip are separated vertically Split fracture occurs at.
【0007】本発明の目的は前記従来例の不都合を解消
し、重ね継手をする場合の鉄筋継手相互の水平筋の水平
方向の隙間を予め無くしておくことにより水平筋相互が
離れて外側に弾けることを防止でき、接合部の耐力を向
上させることができる地下連続壁の接合方法を提供する
ことにある。The object of the present invention is to eliminate the disadvantages of the prior art and eliminate the horizontal gap between the horizontal bars of the reinforcing bar joints in the lap joint in advance so that the horizontal bars can be separated from each other and flipped outward. It is to provide a method for joining underground continuous walls, which can prevent such a situation and improve the yield strength of the joint.
【0008】[0008]
【課題を解決するための手段】本発明は前記目的を達成
するため、先行エレメントの鉄筋カゴ端の鉄筋継手の水
平筋間に後行エレメントの鉄筋カゴ端の鉄筋継手の水平
筋を差し入れ、重ね継手で接合する地下連続壁の接合方
法において、後行エレメント側の鉄筋カゴの鉄筋継手の
左右の水平筋は先端部またはその近傍を線状部材で緊張
して該水平筋の弾性に抗して先端が相互に近接するよう
に撓ませ、このように幅狭とした後行エレメント側の鉄
筋継手を先行エレメント側の鉄筋継手の水平筋間に差し
入れた後、前記線状部材を切断して後行エレメント側の
鉄筋継手の左右の水平筋を弾性により直状として先行エ
レメント側の鉄筋継手の水平筋に近接させること、およ
び線状部材は一端を水平筋に結着した番線の他端に環体
を設け、この環体を重合させて棒材で縦方向に貫き、該
棒材を上方向に引き抜くことで環体相互を分離して切断
状態とすることを要旨とするものである。In order to achieve the above object, the present invention inserts a horizontal bar of a reinforcing bar joint of a trailing element of a reinforcing element of a trailing element between horizontal bars of a reinforcing bar joint of a leading element of a preceding element and stacks them. In the method of joining underground continuous walls to be joined with joints, the horizontal bars on the left and right of the reinforcing bar joint of the reinforcing element cage on the trailing element side are tensioned with a linear member at the tip or in the vicinity thereof to resist the elasticity of the horizontal bars. After bending the tips so that they are close to each other, and inserting the narrow reinforcing bar joints on the trailing element side between the horizontal bars of the reinforcing bar joints on the preceding element side, cutting the linear member Align the left and right horizontal bars of the reinforcing bar joint on the row element side by elasticity so that they are close to the horizontal bars of the reinforcing bar joint on the preceding element side, and the linear member has one end connected to the other end of the number line connected to the horizontal bar. The body is set and this ring is Polymerization was pierced longitudinally by the bar, it is an Abstract that separates the ring member mutually disconnected by pulling out the rod member upward.
【0009】[0009]
【作用】請求項1記載の本発明によれば、水平重ね継手
部が面外力を受ける場合、先行エレメントの鉄筋継手の
水平筋と後行エレメントの鉄筋継手の水平筋とが水平方
向で離れようとする動きをする。本発明によれば、後行
エレメント側の鉄筋継手を先行エレメント側の鉄筋継手
の水平筋間に差し入れた後、前記線状部材を切断して後
行エレメント側の鉄筋継手の左右の水平筋を弾性により
直状として先行エレメント側の鉄筋継手の水平筋に近接
させるので、鉄筋継手相互の水平筋の水平方向の隙間を
予め無くし1本の棒状に近い重ね継手とすることができ
る。その結果、割裂破壊耐力の増大が期待でき、継手部
に面外の曲げ応力を受けても急激なひび割れの進展を防
ぐことができる。According to the present invention as set forth in claim 1, when the horizontal lap joint portion receives an out-of-plane force, the horizontal bar of the reinforcing bar joint of the preceding element and the horizontal bar of the reinforcing bar joint of the following element will be separated in the horizontal direction. And make a move. According to the present invention, after inserting the reinforcing bar joint of the trailing element side between the horizontal bars of the reinforcing bar joint of the preceding element side, the linear member is cut to form the left and right horizontal bars of the reinforcing bar joint of the trailing element side. Since it is made straight by elasticity and is brought close to the horizontal bar of the reinforcing bar joint on the side of the preceding element, it is possible to eliminate a gap between the horizontal bars of the reinforcing bar joints in the horizontal direction in advance to form a single bar-shaped lap joint. As a result, an increase in split fracture resistance can be expected, and abrupt crack development can be prevented even when the joint portion receives out-of-plane bending stress.
【0010】請求項2記載の本発明によれば、前記作用
に加えて、線状部材の切断の容易性を考慮したものであ
り、線状部材が水平筋の段数だけ上下に間隔を存して並
んでいても棒材を上方向に引き抜くことでこれら複数の
線状部材を一挙に切断状態とすることができる。According to the second aspect of the present invention, in addition to the above action, the easiness of cutting the linear member is taken into consideration, and the linear members are vertically spaced by the number of steps of the horizontal streaks. Even if they are arranged side by side, the plurality of linear members can be cut at once by pulling out the rods in the upward direction.
【0011】[0011]
【実施例】以下、図面について本発明の実施例を詳細に
説明する。図1は本発明の地下連続壁の接合工法の1実
施例を示す横断平面図で、前記従来例を示す図4、図5
と同一構成要素には同一参照符号を付したものである。Embodiments of the present invention will now be described in detail with reference to the drawings. FIG. 1 is a cross-sectional plan view showing one embodiment of a method for joining underground continuous walls of the present invention, and FIGS.
The same components as those of the above are designated by the same reference numerals.
【0012】先行エレメント1側のものとしては、型枠
としての仕切板3を組み込んだ鉄筋カゴ4の該仕切板3
から先に水平筋5aと縦筋5bの組合わせで構成した鉄
筋継手5を突出させる。この水平筋5aは鉄筋カゴ4の
水平筋の延長部となるもので左右の水平筋5aの間隔は
鉄筋カゴ4の水平筋と同じ幅を保つ直状のものである。On the side of the preceding element 1, the partition plate 3 of the reinforcing bar basket 4 incorporating the partition plate 3 as a formwork.
First, the reinforcing bar joint 5 configured by the combination of the horizontal bar 5a and the vertical bar 5b is projected. The horizontal bar 5a is an extension of the horizontal bar of the reinforcing bar basket 4, and the interval between the left and right horizontal bars 5a is a straight line that maintains the same width as the horizontal bar of the reinforcing bar basket 4.
【0013】仕切板3は両端にこれと直交する向きのフ
ランジ板3aを所要幅で設け、仕切板3の全体形状がH
形をなすようにする。仕切板3は掘削孔の幅に等しいも
のであるから、該フランジ板3aは掘削孔壁に当接し、
掘削孔壁と平行する位置に存する。また、フランジ板3
aから仕切板3を貫通する向きで剪断補強筋22を設ける
ようにしてもよい。The partition plate 3 is provided at both ends with flange plates 3a in a direction orthogonal to the partition plate 3 with a required width.
Try to make a shape. Since the partition plate 3 is equal to the width of the drill hole, the flange plate 3a is in contact with the wall of the drill hole,
It is located parallel to the borehole wall. Also, the flange plate 3
The shear reinforcing bar 22 may be provided so as to pass through the partition plate 3 from a.
【0014】一方、後行エレメント2側のものとして
は、先端部に水平筋8aと縦筋8bの組合わせで構成し
た鉄筋継手8を設けた鉄筋カゴ9を配設するが、この鉄
筋継手8の左右の水平筋8aは何も拘束しない状態では
鉄筋カゴ9の水平筋の延長部として直状を保つものであ
る。さらに、左右の水平筋8aの間隔は左右の水平筋5
aの間隔とほぼ同じとする。On the other hand, on the trailing element 2 side, a reinforcing bar basket 9 having a reinforcing bar joint 8 composed of a combination of horizontal bars 8a and vertical bars 8b at its tip is provided. The left and right horizontal streaks 8a maintain a straight shape as an extension of the horizontal streaks of the reinforcing bar basket 9 when nothing is restrained. Further, the interval between the left and right horizontal streaks 8a is
It is almost the same as the interval of a.
【0015】本発明は、このような後行エレメント2側
の鉄筋カゴ9の鉄筋継手8は、左右の水平筋8aは先端
部またはその近傍を線状部材15で緊張して該水平筋8a
の弾性に抗して先端が相互に近接するように撓ませる。
なお、鉄筋カゴ9側または鉄筋継手8の根本部では左右
の水平筋間に割裂防止筋16を掛け渡して溶接などで固定
して連結し、水平筋8aを撓ませた場合でも一定の間隔
を保持できるようにしておく。According to the present invention, in the reinforcing bar joint 8 of the reinforcing bar basket 9 on the trailing element 2 side, the horizontal bars 8a on the left and right are tensioned by the linear member 15 at or near the tips of the horizontal bars 8a.
The tips are bent so as to approach each other against the elasticity of.
It should be noted that at the reinforcing bar basket 9 side or at the root of the reinforcing bar joint 8, the split preventing bar 16 is hung between the left and right horizontal bars and fixedly connected by welding or the like, and even if the horizontal bar 8a is bent, a certain interval is maintained. Be able to hold.
【0016】さらに、鉄筋継手8の中で割裂防止筋17を
設けることもできるが、この場合は該割裂防止筋17は水
平筋8aに固定せずにスライド可能なようにチャンネル
状のガイド18を介して載置するだけのものとする。Further, a split preventing bar 17 can be provided in the reinforcing bar joint 8. In this case, the split preventing bar 17 is provided with a channel-shaped guide 18 so as to be slidable without being fixed to the horizontal bar 8a. It should only be placed through.
【0017】線状部材15は紐もしくはワイヤー等で、こ
れを後で刃物等で切断するようにしてもよいが、本実施
例では一端を水平筋8aに結着した番線19の他端に環体
20を設けたものの組合せとした。この環体20を重合させ
る位置まで水平筋8aを撓ませて相互に引き付け、重な
る環体20内を丸鋼等の棒材21で縦方向に貫く。このよう
にすれば、水平筋8aの上下方向にある多段の線状部材
15の全てを一本の棒材21で中央部で係止することができ
る。The linear member 15 may be a cord or a wire, which may be cut later with a knife or the like. In this embodiment, one end of the wire 19 is attached to the horizontal line 8a. body
It is a combination of those provided with 20. The horizontal streaks 8a are bent to a position where the ring bodies 20 are overlapped with each other and attracted to each other, and the overlapping ring bodies 20 are vertically penetrated by a rod member 21 such as round steel. With this configuration, the multi-stage linear members in the vertical direction of the horizontal stripe 8a
All 15 can be locked at the center with a single rod 21.
【0018】先行エレメント1側で掘削孔に前記仕切板
3付きの鉄筋カゴ4を吊り降ろし、コンクリート6を打
設して先行パネルを形成するが打設するコンクリートは
仕切板3で止められる。先行エレメント1のコンクリー
ト6を打設した後で、後行エレメント2の鉄筋カゴ9を
掘削孔10内に配設するが、前記のごとく該鉄筋カゴ9の
鉄筋継手8は水平筋8aが線状部材15で緊張されて幅狭
となっているので、鉄筋継手5の水平筋5a間に容易に
差し入れることができる。On the side of the preceding element 1, the reinforcing bar basket 4 with the partition plate 3 is hung in the excavation hole, and the concrete 6 is cast to form the preceding panel. The cast concrete is stopped by the partition plate 3. After the concrete 6 of the preceding element 1 is placed, the reinforcing bar basket 9 of the trailing element 2 is arranged in the excavation hole 10. As described above, the reinforcing bar joint 8 of the reinforcing bar basket 9 has a horizontal bar 8a having a linear shape. Since the member 15 is strained and narrowed, it can be easily inserted between the horizontal bars 5a of the reinforcing bar joint 5.
【0019】このようにしてから地上で棒材21の上端を
つかみ、これを上方向に引き抜けば、重なる環体20が分
離可能となり各線状部材15を切断状態とすることができ
る。該線状部材15での緊張が無くなるので、図3に示す
ように左右の水平筋8aは弾性により直状に戻り、先行
エレメント1側の鉄筋継手5の水平筋5aに接合する。By thus grasping the upper end of the bar 21 on the ground and pulling it upward, the overlapping ring members 20 can be separated and the linear members 15 can be cut. Since the tension in the linear member 15 is eliminated, the left and right horizontal streaks 8a return to a straight shape by elasticity and are joined to the horizontal streaks 5a of the reinforcing bar joint 5 on the side of the preceding element 1 as shown in FIG.
【0020】以上のように水平筋5aと水平筋8aとを
可能な限り近接させて重ね継手としてから、図示は省略
するが後行エレメント2側にコンクリートを打設して後
行パネルを形成すればラップする鉄筋継手5と鉄筋継手
8で接合がなされる。As described above, the horizontal streaks 5a and the horizontal streaks 8a are made as close as possible to each other to form a lap joint, and although not shown, concrete is placed on the side of the following element 2 to form the following panel. For example, the reinforcing bar joint 5 and the reinforcing bar joint 8 which are overlapped are joined.
【0021】水平重ね継手部が面外力を受ける場合、先
行エレメント1の鉄筋継手5の水平筋5aと後行エレメ
ント2の鉄筋継手8の水平筋8aとが水平方向で離れよ
うとする動きをするが、本発明では水平筋5aと8aの
水平方向の隙間を予め無くして1本の棒状に近い重ね継
手としたので、離れにくいものとなり割裂破壊耐力の増
大が期待できる。When the horizontal lap joint portion receives an out-of-plane force, the horizontal bar 5a of the reinforcing bar joint 5 of the preceding element 1 and the horizontal bar 8a of the reinforcing bar joint 8 of the trailing element 2 move so as to separate from each other in the horizontal direction. However, in the present invention, since the horizontal gap between the horizontal streaks 5a and 8a is eliminated in advance to form a single lap joint close to a rod shape, it becomes difficult to separate, and an increase in split fracture resistance can be expected.
【0022】さらに、水平筋5aと水平筋8aとが水平
方向で離れようとする動きをした時に全体がH形である
仕切板3の曲げモーメントが働き、仕切板3端のフラン
ジ板3aがこの継手部を外側から拘束して抑えとして作
用する。その結果、より割裂破壊耐力の増大が期待でき
る。Further, when the horizontal streaks 5a and the horizontal streaks 8a move so as to separate from each other in the horizontal direction, the bending moment of the partition plate 3, which is H-shaped as a whole, acts to cause the flange plate 3a at the end of the partition plate 3 to move. It acts as a restraint by restraining the joint from the outside. As a result, it can be expected that the split fracture proof stress will increase.
【0023】また、他の実施例として、先行エレメント
1側の鉄筋継手5の水平筋5aに補強部材11を添設して
もよい。この補強部材11は図4に示すように縦軸材12に
楕円形のフープ筋13を上下間隔を存してタラップ状に取
付けたもので、該縦軸材12はフープ筋13内を貫通し、そ
の端に寄せて溶接で固定して取付ける。また、縦軸材12
は補強部材11の全体の軽量化を図るためにパイプを使用
して内部を中空とすることが望ましい。As another embodiment, a reinforcing member 11 may be attached to the horizontal bar 5a of the reinforcing bar joint 5 on the side of the preceding element 1. As shown in FIG. 4, the reinforcing member 11 is formed by attaching elliptical hoop muscles 13 to a vertical axis member 12 in a trapezoidal shape with a vertical interval, and the vertical axis material 12 penetrates the inside of the hoop muscle 13. , Weld it close to the end and fix it by welding. Also, vertical axis material 12
In order to reduce the weight of the reinforcing member 11 as a whole, it is desirable to use a pipe to make the inside hollow.
【0024】補強部材11を水平筋5aに添設するに際
し、縦軸材12は水平筋5aに直交する向きに配設され、
フープ筋13はその横長方向が水平筋5aの長さ方向と平
行するよう向かせる。この縦軸材12は番線等で鉄筋継手
5に回動可能に取付けておくものである。When the reinforcing member 11 is attached to the horizontal bar 5a, the vertical axis member 12 is arranged in a direction orthogonal to the horizontal bar 5a,
The hoop muscle 13 is oriented so that its lateral direction is parallel to the longitudinal direction of the horizontal muscle 5a. The vertical axis member 12 is rotatably attached to the reinforcing bar joint 5 with a wire or the like.
【0025】先行エレメント1のコンクリート6を打設
した後で、後行エレメント2の鉄筋カゴ9を掘削溝10内
に配設し、前記のごとく鉄筋カゴ9の鉄筋継手8の水平
筋8aを鉄筋継手5の水平筋5aに重ねて重ね継手とす
るが、このようにしてから縦軸材12の上端をつかんでこ
れを回せば、縦軸材12を中心にフープ筋13が回動して図
3に示すようにフープ筋13は水平筋5aと水平筋8aの
相互に跨がって直交方向に交差するように配設される。
なお、フープ筋13の上下位置は水平筋5aや水平筋8a
の位置とずらせて上下段の水平筋5a、水平筋8aの間
になるようにし、また、フープ筋13の横長間隔分は鉄筋
継手5や鉄筋継手8に縦筋5b、8bを配設せずにフー
プ筋13が回り込める間隔を確保しておく。After placing the concrete 6 of the preceding element 1, the reinforcing bar basket 9 of the trailing element 2 is arranged in the excavation groove 10, and the horizontal bar 8a of the reinforcing bar joint 8 of the reinforcing bar basket 9 is reinforced as described above. The lap joint is formed by overlapping the horizontal streak 5a of the joint 5, and if the upper end of the vertical axis member 12 is grasped and turned in this way, the hoop streak 13 rotates about the vertical axis member 12 As shown in FIG. 3, the hoop muscles 13 are arranged so as to straddle the horizontal muscles 5a and 8a and intersect each other in the orthogonal direction.
The vertical position of the hoop muscle 13 is the horizontal muscle 5a and the horizontal muscle 8a.
The vertical streaks 5b and 8b are not provided in the reinforcing bar joint 5 or the reinforcing bar joint 8 for the horizontally long intervals of the hoop reinforcing bars 13 so that they are displaced between the horizontal bars 5a and the horizontal bars 8a in the upper and lower stages. Keep a space around which the hoop muscle 13 can wrap around.
【0026】このフープ筋13は幅止め筋として作用する
もので、縦軸材12の内部にはモルタルを充填する場合も
ある。The hoop muscle 13 acts as a width stop muscle, and the ordinate member 12 may be filled with mortar.
【0027】[0027]
【発明の効果】以上述べたように本発明の地下連続壁の
接合方法は、先行エレメントの鉄筋カゴ端の鉄筋継手と
後行エレメントの鉄筋カゴ端の鉄筋継手を重ね継手で配
設する地下連続壁の接合方法において、鉄筋継手相互の
水平筋の水平方向の隙間を予め無くしておくことにより
水平筋相互が離れて外側に弾けることを防止でき、接合
部の耐力を向上させることができるものである。As described above, the method of joining underground continuous walls of the present invention is an underground continuation in which the reinforcing bar joint at the end of the reinforcing bar of the preceding element and the reinforcing bar joint at the end of the reinforcing bar of the trailing element are arranged in a lap joint. In the wall joining method, by eliminating the horizontal gap between the horizontal bars of the reinforcing bar joints in advance, it is possible to prevent the horizontal bars from separating and popping outward, and it is possible to improve the yield strength of the joint. is there.
【図面の簡単な説明】[Brief description of drawings]
【図1】本発明の地下連続壁の接合方法の1実施例を示
す接合前の横断平面図である。FIG. 1 is a cross-sectional plan view before joining showing an embodiment of a joining method for underground continuous walls of the present invention.
【図2】本発明の地下連続壁の接合方法の1実施例を示
す配筋終了後の横断平面図である。FIG. 2 is a horizontal cross-sectional plan view showing an embodiment of a method for joining underground continuous walls of the present invention after completion of reinforcement.
【図3】本発明の地下連続壁の接合方法の1実施例を示
す接合後の横断平面図である。FIG. 3 is a cross-sectional plan view after joining showing one embodiment of the method for joining underground continuous walls of the present invention.
【図4】補強部材の正面図である。FIG. 4 is a front view of a reinforcing member.
【図5】従来例を示す横断平面図である。FIG. 5 is a cross-sectional plan view showing a conventional example.
【図6】従来例を示す縦断側面面である。FIG. 6 is a longitudinal side surface showing a conventional example.
1…先行エレメント 2…後行エレメント 3…仕切板 3a…フランジ板 4…鉄筋カゴ 4a…絞り部 5…鉄筋継手 5a…水平筋 5b…縦筋 6…コンクリート 8…鉄筋継手 8a…水平筋 8b…縦筋 9…鉄筋カゴ 10…掘削孔 11…補強部材 12…縦軸材 13…フープ筋 15…線状部材 16,17 …割裂防止筋 18…ガイド 19…番線 20…環体 21…棒材 22…剪断補強筋 1 ... Leading element 2 ... Trailing element 3 ... Partition plate 3a ... Flange plate 4 ... Reinforcing bar basket 4a ... Drawing part 5 ... Reinforcing bar joint 5a ... Horizontal bar 5b ... Vertical stripes 6 ... Concrete 8 ... Reinforcing bar joint 8a ... horizontal streak 8b ... vertical streak 9 ... Rebar cage 10 ... Drilling hole 11 ... Reinforcement member 12 ... Vertical axis material 13 ... hoop muscle 15… Linear member 16,17… Split prevention muscle 18… Guide 19… Track 20 ... Ring 21 ... Bar 22 ... Shear reinforcement
Claims (2)
の水平筋間に後行エレメントの鉄筋カゴ端の鉄筋継手の
水平筋を差し入れ、重ね継手で接合する地下連続壁の接
合方法において、後行エレメント側の鉄筋カゴの鉄筋継
手の左右の水平筋は先端部またはその近傍を線状部材で
緊張して該水平筋の弾性に抗して先端が相互に近接する
ように撓ませ、このように幅狭とした後行エレメント側
の鉄筋継手を先行エレメント側の鉄筋継手の水平筋間に
差し入れた後、前記線状部材を切断して後行エレメント
側の鉄筋継手の左右の水平筋を弾性により直状として先
行エレメント側の鉄筋継手の水平筋に近接させることを
特徴とする地下連続壁の接合方法。1. A method for joining an underground continuous wall in which a horizontal bar of a reinforcing bar joint of a rear element of a trailing element is inserted between horizontal bars of a reinforcing bar joint of a leading element of a preceding element, and is joined by a lap joint. The horizontal bars on the left and right of the reinforcing bar joint of the element side reinforcing bar basket are strained by a linear member at the tip or in the vicinity thereof to bend the tips against each other against the elasticity of the horizontal bar. After inserting the narrow rebar joint on the trailing element side between the horizontal bars of the rebar joint on the preceding element side, cut the linear member to elastically resize the left and right horizontal bars of the rebar joint on the trailing element side. A method for joining underground continuous walls, which is characterized in that a straight shape is brought close to the horizontal bar of the reinforcing bar joint on the side of the preceding element.
の他端に環体を設け、この環体を重合させて棒材で縦方
向に貫き、該棒材を上方向に引き抜くことで環体相互を
分離して切断状態とする請求項1記載の地下連続壁の接
合方法。2. A linear member is provided with a ring body at the other end of a wire which is connected to a horizontal streak at one end, and the ring body is polymerized and vertically penetrated by a rod member, and the rod member is pulled out upward. The method for joining underground continuous walls according to claim 1, wherein the ring bodies are separated from each other to be in a cut state.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP3189399A JPH0823144B2 (en) | 1991-07-03 | 1991-07-03 | Method of joining underground continuous walls |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP3189399A JPH0823144B2 (en) | 1991-07-03 | 1991-07-03 | Method of joining underground continuous walls |
Publications (2)
Publication Number | Publication Date |
---|---|
JPH059931A true JPH059931A (en) | 1993-01-19 |
JPH0823144B2 JPH0823144B2 (en) | 1996-03-06 |
Family
ID=16240647
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP3189399A Expired - Lifetime JPH0823144B2 (en) | 1991-07-03 | 1991-07-03 | Method of joining underground continuous walls |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPH0823144B2 (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2017186832A (en) * | 2016-04-07 | 2017-10-12 | 旭化成建材株式会社 | Reinforced cage and connection method of reinforced cage |
Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS62280414A (en) * | 1986-05-28 | 1987-12-05 | Kajima Corp | Construction work of underground continuous wall |
-
1991
- 1991-07-03 JP JP3189399A patent/JPH0823144B2/en not_active Expired - Lifetime
Patent Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS62280414A (en) * | 1986-05-28 | 1987-12-05 | Kajima Corp | Construction work of underground continuous wall |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2017186832A (en) * | 2016-04-07 | 2017-10-12 | 旭化成建材株式会社 | Reinforced cage and connection method of reinforced cage |
Also Published As
Publication number | Publication date |
---|---|
JPH0823144B2 (en) | 1996-03-06 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CA2292117C (en) | Mine stopping, method of constructing same and panels thereof | |
US20160177533A1 (en) | Geosynthetic connection systems and methods for mechanically stablized earth walls | |
JP2016514222A (en) | Reinforcement, structure and method for subway reinforced concrete buildings | |
JPH059931A (en) | Joining method for underground continuous wall | |
JP3457294B2 (en) | Reinforced concrete joint structure | |
JPH08199989A (en) | Construction of large section tunnel | |
JPH0794726B2 (en) | Method of joining underground continuous walls | |
JPH055306A (en) | Connection of underground continuous wall | |
JP2516498B2 (en) | Connection structure of underground continuous wall | |
JPS62280414A (en) | Construction work of underground continuous wall | |
JPH11209967A (en) | Joint structure of underground continuous wall | |
JPS63184610A (en) | Joint for continuous underground wall | |
JP2918762B2 (en) | Rebar joint structure | |
JPH0544215A (en) | Connection of underground continuous wall | |
JP2545310B2 (en) | Connection structure of underground continuous wall | |
JPH10237860A (en) | Mehtod for joining underground continuous wall | |
JP2516509B2 (en) | Joint structure of underground wall | |
JP2694715B2 (en) | Joint structure of underground wall | |
JPH04353115A (en) | Joint structure for underground continuous wall | |
JPH05112932A (en) | Joining method of underground continuous wall | |
AU622469B2 (en) | Improvements in and relating to the prestressing of concrete articles or structures | |
JPS6039835B2 (en) | Reinforced steel construction method | |
JP2545319B2 (en) | Joint structure of underground wall | |
JPS6340520Y2 (en) | ||
JPH07107268B2 (en) | Joint structure of underground continuous wall |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20051221 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20060124 |
|
A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20060327 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20060523 |
|
A521 | Written amendment |
Effective date: 20060724 Free format text: JAPANESE INTERMEDIATE CODE: A523 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20060822 |
|
A02 | Decision of refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A02 Effective date: 20061219 |