JPH059922A - Off-shore foundation structure construction method - Google Patents
Off-shore foundation structure construction methodInfo
- Publication number
- JPH059922A JPH059922A JP18543591A JP18543591A JPH059922A JP H059922 A JPH059922 A JP H059922A JP 18543591 A JP18543591 A JP 18543591A JP 18543591 A JP18543591 A JP 18543591A JP H059922 A JPH059922 A JP H059922A
- Authority
- JP
- Japan
- Prior art keywords
- frames
- sea
- foundation structure
- frame
- foundation
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Landscapes
- Foundations (AREA)
- Bridges Or Land Bridges (AREA)
Abstract
Description
【0001】[0001]
【産業上の利用分野】本発明は、海洋に設置される構造
物、例えば、橋梁やシーバース等の基礎構造物の建造方
法に関するものである。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method of constructing a structure installed in the ocean, for example, a basic structure such as a bridge or a sea berth.
【0002】[0002]
【従来の技術】近年、我国では比較的水深の深い海域に
橋梁やシーバースを建設する事例が増えつつある。例え
ば、1988年に開通した本州四国連絡橋備讃瀬戸大橋
は、造船所等において基礎部分となる大型の鋼製ケーソ
ンを製作し、これを浮かべて設置場所まで海上曳航し、
水深50mの支持地盤上に沈設した後、現場で不足分の
上部を継ぎ足していくという建造方法が採用された。2. Description of the Related Art In recent years, in Japan, the number of cases of constructing bridges and sea berths in relatively deep water is increasing. For example, the Honshu-Shikoku Connecting Bridge, Bisan Seto Ohashi, which opened in 1988, made a large steel caisson that is the foundation of a shipyard, and floats it on the sea to the installation site.
A construction method was adopted in which, after sunk on a supporting ground at a water depth of 50 m, the top of the shortage was replenished on site.
【0003】また、シーバースの基礎構造物として、鋼
製のジャケット式構造物が採用されている。この構造物
は工場製作した立体トラスであるジャケット本体を運搬
し、海底に据え付け、ジャケットの支柱内を貫通して地
盤に杭を打設し、杭頭部に上部工を架設固定して施工さ
れる。A steel jacket type structure is used as a basic structure of the seaverse. This structure is constructed by transporting the jacket body, which is a three-dimensional truss produced by the factory, and installing it on the seabed, penetrating the inside of the pillars of the jacket, driving a pile into the ground, and erection and fixing a superstructure on the pile head. It
【0004】[0004]
【発明が解決しようとする課題】しかしながら、前記橋
梁の基礎部分となる大型ケーソンの設置作業では、基礎
の底面が大きいので海底面の掘削・均し作業を広い面積
に対して行う必要があり、また、シーバースにおけるジ
ャケットの設置作業では、杭の打設作業を伴うなど、作
業船および機材に対する費用が高価とならざるを得な
い。更に、上記海洋構造物の現場施工期間が一般に長い
ことから、構造物が不安定な状態で長期間にわたり外力
にさらされるため、防護工として周辺の仮設備が大きく
なるという欠点を有している。However, in the installation work of the large caisson which is the foundation part of the bridge, since the bottom surface of the foundation is large, it is necessary to excavate and level the sea floor over a large area. In addition, the installation work of the jacket in the sea berth is inevitably expensive due to the work of placing the piles and the like for the work boat and the equipment. Further, since the construction period of the offshore structure is generally long, the structure is exposed to external force for a long period of time in an unstable state, and there is a drawback that temporary facilities around the protective work become large. ..
【0005】本発明は前記課題を解決しようとするもの
であり、その目的は、海洋基礎構造物を構成する支持部
材を簡易な構造とし、これを組み立てて、海洋基礎構造
物を建造する方法を提供することにある。The present invention is intended to solve the above-mentioned problems, and an object thereof is to provide a method for constructing a marine foundation structure by assembling a supporting member constituting the marine foundation structure into a simple structure. To provide.
【0006】[0006]
【課題を解決するための手段】上記目的を達成するため
に、本発明に係る海洋基礎構造物の建造方法は、海洋構
造物の基礎を構成する複数の支持部材を組立場所以外で
製作し、これを最終設置場所へ洋上曳航し、該支持部材
の下端部を海底地盤に着底させた後、二以上の支持部材
の頂部を連結し、かつ、各支持部材の下端部を海底地盤
に固定することによって課題を解決したものである。In order to achieve the above-mentioned object, a method of constructing an offshore foundation structure according to the present invention comprises manufacturing a plurality of support members constituting a foundation of an offshore structure at a place other than an assembly place, This is towed to the final installation location, the lower end of the supporting member is set on the seabed, the tops of two or more supporting members are connected, and the lower end of each supporting member is fixed to the seabed. The problem is solved by doing.
【0007】[0007]
【実施例】以下、海洋基礎構造物として橋梁の橋脚を例
に取り、その建造方法の好適な実施例を、図1に基づい
て説明する。橋脚部材の製作 予め、ドライドックで橋脚を構成するフレーム3を製作
する。フレーム3は、図2(A)に示すような、2本の
脚柱3a間に桁3bを渡した梯子形状をした一対のトラ
ス状フレーム3、3′によって構成する。各フレーム
3、3′の大きさは、設置される海域の水深によって定
まるが、橋脚の高さが数十m〜数百mの範囲内で可能で
ある。DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENT A preferred embodiment of a construction method of a bridge pier will be described below as an example of a marine foundation structure with reference to FIG. Manufacture of pier member The frame 3 that constitutes the pier is manufactured in advance by dry dock. The frame 3 is constituted by a pair of truss-shaped frames 3 and 3'in the shape of a ladder in which a girder 3b is arranged between two pedestals 3a as shown in FIG. 2 (A). The size of each frame 3, 3'is determined depending on the water depth of the installed sea area, but the height of the pier can be within the range of several tens m to several hundred m.
【0008】例えば、100mの水深に設置される橋脚
であれば、外径10mのコンクリート管で、高さ120
m、頂部幅50m、脚柱間の開脚幅100mといった寸
法に製作される。また、脚柱3aの内部には、数m間隔
で鋼板製の隔壁を設けて内部を区画し、後記するバラス
ト材が注入される空室と、同バラスト材の給排水を行う
ポンプを設置するポンプ室として利用できるように構成
する。For example, for a pier installed at a water depth of 100 m, a concrete pipe having an outer diameter of 10 m and a height of 120 m
m, top width 50 m, open leg width 100 m between pedestals. Further, inside the pedestal 3a, partition walls made of steel plates are provided at intervals of several meters to partition the interior, and a vacant chamber into which a ballast material is injected, which will be described later, and a pump for supplying and draining the ballast material are installed. It is configured so that it can be used as a room.
【0009】海底地盤の掘削 始めに、フレーム3、3′を着底する部分の海底地盤を
予め掘削し、レベル調整を行う(工程)。また、この
際に、海底地盤の地耐力を調査した上で、必要があれ
ば、掘削孔1内にプレキャスト製コンクリート版等を設
置するか、或いは、水中コンクリートを打設して、海底
基礎2を造成する(工程)。[0009] At the beginning of excavation of the seabed, the seabed of the portion where the frames 3, 3'are bottomed is excavated in advance and the level is adjusted (step). In addition, at this time, after investigating the ground bearing capacity of the seabed ground, if necessary, a precast concrete plate or the like is installed in the excavation hole 1, or underwater concrete is placed to form the seabed foundation 2 To create (process).
【0010】曳航 フレーム3をドライドックから曳き出して洋上に浮か
べ、設置する海域まで浮上曳航する。なお、小規模なド
ライドックで製作する場合には、フレーム3を複数部分
に分割して製作し、これをドライドックから曳き出して
静穏な洋上で接合した後、最終設置場所へ曳航してもよ
い。The towing frame 3 is towed from the dry dock, floated on the sea, and levitated to the sea area to be installed. In addition, when manufacturing with a small dry dock, even if the frame 3 is divided into multiple parts, it is towed out from the dry dock and joined on a calm ocean, and then towed to the final installation location. Good.
【0011】フレームの着底 先ず、洋上に横たわっているフレーム3の基底部から海
水等のバラスト材を注入していき、フレーム3を洋上で
鉛直に起立させる(工程)。その後、更にバラスト材
を注水して、そのまま前記造成した基礎2上に着底させ
る(工程)。同じ操作をもう一つのフレーム3′につ
いても行う。[0011] bottom landing of the frame first, we will inject the ballast material such as seawater from the base of the frame 3 lying offshore, is vertically upright frame 3 at sea (step). After that, water is further poured into the ballast material, and the bottom of the foundation 2 is formed as it is (step). The same operation is performed for the other frame 3 '.
【0012】橋脚の組立 各フレーム3、3′にバラスト材を加え、両者の頂部を
徐々に引き寄せる。引き寄せ作業は、クレーン船、曳
船、ウィンチ等の設備により行う。この際に、注水量と
注水速度を調整することにより、フレーム3、3′の傾
きと橋脚の姿勢を制御することができる。その後、両フ
レーム3、3′の頂部を適当な金具で結合する(工程
)。 Assembling the bridge pier Ballast material is added to each frame 3, 3 ', and the tops of both are gradually pulled. The pulling work will be performed using equipment such as a crane ship, tugboat and winch. At this time, the inclinations of the frames 3 and 3'and the attitude of the pier can be controlled by adjusting the water injection amount and the water injection speed. After that, the tops of the two frames 3 and 3'are joined with an appropriate metal fitting (step).
【0013】橋脚の固定 フレーム3、3′の脚柱3aが着底している掘削孔1内
を、土砂、ソイルセメントまたはコンクリート4等で埋
め戻して、脚柱3aの下端部を海底地盤に固定する(工
程)。The inside of the excavation hole 1 in which the pedestal 3a of the fixed frame 3 or 3'of the pier is bottomed is backfilled with earth, sand cement, concrete 4 or the like, and the lower end of the pedestal 3a becomes the seabed ground. Fix (process).
【0014】最後に、両フレーム3、3′の洋上に突出
している頂部に所定の大きさの頂版5を載置し、橋脚の
高さ、姿勢を最終的に調整する(工程)。Finally, a top plate 5 of a predetermined size is placed on the tops of the two frames 3, 3'protruding on the sea, and the height and posture of the piers are finally adjusted (step).
【0015】上部工 通常の橋梁施工法と同様にして、主塔等の上部構造物6
を前記頂版5上に設置する(工程)。[0015] in the same manner as in the superstructure normal bridge construction methods, upper structure of the main tower, etc. 6
Is installed on the top plate 5 (step).
【0016】以上の実施例では、一対のフレーム3、
3′をもって橋脚を構成したが、本発明は、これ以外に
も、図2(B)に示すような中空のコンクリート製また
は鋼製の支柱7を用いて橋脚を構成する支持部材とする
こともできる。即ち、当該支柱7と前記フレーム3との
組合せ、または、複数本の支柱7、7′による組合せが
可能である。更に、フレーム3または支柱7を組み合せ
て、図2(C)に示すような櫓形の基礎構造物8とする
ことも可能である。In the above embodiment, the pair of frames 3,
Although the bridge pier is configured with 3 ', the present invention may also be used as a supporting member for configuring the bridge pier using a hollow concrete or steel strut 7 as shown in FIG. 2 (B). it can. That is, a combination of the support column 7 and the frame 3 or a combination of a plurality of support columns 7 and 7'is possible. Further, it is possible to combine the frame 3 or the columns 7 to form a tower-shaped substructure 8 as shown in FIG. 2 (C).
【0017】[0017]
【発明の効果】本発明の海洋基礎構造物の建造方法は、
支持部材を簡易な構造の支柱をもって構成したので、構
造物を極めて簡易な方法により建造することができる。
また、支持部材の製作が全てドライドック内で行えるか
ら、洋上作業の多い従来法と比べて、工期を短縮するこ
とができ、品質管理も行き届くという優れた効果を有す
る。The method of constructing a marine foundation structure of the present invention comprises:
Since the supporting member is composed of the columns having a simple structure, the structure can be constructed by an extremely simple method.
In addition, since all the supporting members can be manufactured in the dry dock, the construction period can be shortened and quality control can be performed well, as compared with the conventional method in which many offshore operations are performed.
【図1】橋脚の組立施工順序を示す説明図である。FIG. 1 is an explanatory diagram showing the order of assembling and constructing a pier.
【図2】橋脚を構成する支持部材の変形例を示した図で
ある。FIG. 2 is a diagram showing a modified example of a support member that constitutes a pier.
1 掘削孔 2 海底基礎 3、3′ フレーム 4 埋戻し 5 頂版 6 上部構造物 1 drill hole 2 seabed foundation 3, 3'frame 4 backfill 5 top plate 6 superstructure
Claims (1)
部材を組立場所以外で製作し、これを最終設置場所へ洋
上曳航し、該支持部材の下端部を海底地盤に着底させた
後、二以上の支持部材の頂部を連結し、かつ、各支持部
材の下端部を海底地盤に固定することを特徴とする海洋
基礎構造物の建造方法。Claims: 1. A plurality of support members that form the foundation of an offshore structure are manufactured at a place other than the assembly site, and these are towed to the final installation site, and the lower end of the support members is at the bottom of the seabed. A method for constructing a marine foundation structure, comprising the steps of connecting the tops of two or more support members to each other and fixing the bottom ends of the support members to the seabed ground after the bottoms are attached to the bottom.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP18543591A JP2953823B2 (en) | 1991-06-29 | 1991-06-29 | Construction method of offshore substructure |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP18543591A JP2953823B2 (en) | 1991-06-29 | 1991-06-29 | Construction method of offshore substructure |
Publications (2)
Publication Number | Publication Date |
---|---|
JPH059922A true JPH059922A (en) | 1993-01-19 |
JP2953823B2 JP2953823B2 (en) | 1999-09-27 |
Family
ID=16170745
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP18543591A Expired - Fee Related JP2953823B2 (en) | 1991-06-29 | 1991-06-29 | Construction method of offshore substructure |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP2953823B2 (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2007204992A (en) * | 2006-01-31 | 2007-08-16 | Nippon Steel Engineering Co Ltd | Up welling current-generating submarine artificial levee and its construction method |
JP2017089097A (en) * | 2015-11-02 | 2017-05-25 | 三井住友建設株式会社 | Construction method of main tower or bridge pier |
-
1991
- 1991-06-29 JP JP18543591A patent/JP2953823B2/en not_active Expired - Fee Related
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2007204992A (en) * | 2006-01-31 | 2007-08-16 | Nippon Steel Engineering Co Ltd | Up welling current-generating submarine artificial levee and its construction method |
JP4539989B2 (en) * | 2006-01-31 | 2010-09-08 | 日鉄トピーブリッジ株式会社 | Artificial seabed with upwelling flow and its construction method |
JP2017089097A (en) * | 2015-11-02 | 2017-05-25 | 三井住友建設株式会社 | Construction method of main tower or bridge pier |
Also Published As
Publication number | Publication date |
---|---|
JP2953823B2 (en) | 1999-09-27 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US9567720B2 (en) | Offshore platform for a marine environment | |
JP2643049B2 (en) | Floating structure | |
US4266887A (en) | Self-elevating fixed platform | |
US3528254A (en) | Offshore platform structure and construction method | |
GB2202494A (en) | Deep water support assembly for a jack-up platform structure | |
JP6105044B2 (en) | Partially floating offshore platform for offshore wind power, bridges and offshore structures, and construction method | |
CN101392521A (en) | Rock-socketed steel dock structure and construction method thereof | |
US4080916A (en) | Maritime platform assemblies | |
US4767238A (en) | Method of accurately positioning a prefabricated structure on the sea bed or on a river bed by grounding, and a sea or a river construction obtained by said method | |
RU2310721C1 (en) | Protection device to protect self-elevating floating drilling installation for exploratory well drilling in ice conditions and method for protection device construction | |
CN202969333U (en) | Steel truss rock-socketed wharf structure | |
US3115013A (en) | Artificial island and method of constructing the same | |
CN109518674B (en) | Artificial island segment, assembled artificial island and construction method of assembled artificial island | |
US3091937A (en) | Underwater foundation structure and method therefor | |
JPH06146305A (en) | Underwater foundation and installation method thereof | |
JP3075179B2 (en) | Bridge pier foundation structure and its construction method | |
JP2953823B2 (en) | Construction method of offshore substructure | |
US2935854A (en) | Offshore drilling platform | |
JP2822873B2 (en) | Construction method of deep water foundation structure and its structure | |
JPH0930487A (en) | Artificial island having half-floating structure | |
JP2953818B2 (en) | Construction method for deep water structures | |
JP2000265450A (en) | Artificial ground consisting of porous housing and construction method therefor | |
JP2669317B2 (en) | Construction method of gravity type offshore structure and its structure | |
JPS6237172B2 (en) | ||
US20240217629A1 (en) | Offshore submergible platform |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 19990622 |
|
LAPS | Cancellation because of no payment of annual fees |