JPH0598708A - Installation method and device for floor slab of unit building - Google Patents

Installation method and device for floor slab of unit building

Info

Publication number
JPH0598708A
JPH0598708A JP26212491A JP26212491A JPH0598708A JP H0598708 A JPH0598708 A JP H0598708A JP 26212491 A JP26212491 A JP 26212491A JP 26212491 A JP26212491 A JP 26212491A JP H0598708 A JPH0598708 A JP H0598708A
Authority
JP
Japan
Prior art keywords
unit
floor
slab
concrete
column
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP26212491A
Other languages
Japanese (ja)
Other versions
JP3045839B2 (en
Inventor
Chika Iri
知香 伊理
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sekisui Chemical Co Ltd
Original Assignee
Sekisui Chemical Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sekisui Chemical Co Ltd filed Critical Sekisui Chemical Co Ltd
Priority to JP3262124A priority Critical patent/JP3045839B2/en
Publication of JPH0598708A publication Critical patent/JPH0598708A/en
Application granted granted Critical
Publication of JP3045839B2 publication Critical patent/JP3045839B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Abstract

PURPOSE:To make it possible to support a floor slab directly by a concrete beam without lowering productivity when a unit building having a construction of reinforcing bar or steel framed reinforced concrete is constructed by adding a concrete beam to a floor beam of a building unit. CONSTITUTION:In an installation method of a floor slab of a unit building 10 wherein a concrete beam 14A is placed along a floor beam 23 of an inner unit 11 and a floor slab 26 is installed on said concrete beam 14A, the floor slab 26 is supported by the floor beam 23 until the beam 14A is cured. And when the beam 14A has been cured, the floor slab 26 is supported by the concrete beam 14A.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明は、鉄筋又は鉄骨鉄筋コン
クリート構造の高層ユニット建物を構築するに好適な、
ユニット建物の床スラブ据付方法及び装置に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention is suitable for constructing a high-rise unit building having a reinforced concrete structure or a reinforced concrete structure,
A floor slab installation method and apparatus for a unit building.

【0002】[0002]

【従来の技術】従来、鉄筋又は鉄骨鉄筋コンクリート構
造のユニット建物として、特公昭55-14217号公報に記載
のものがある。このユニット建物は、隣接配置された建
物ユニットの側壁間領域に鉄筋を吊込み設置した後、該
側壁間領域にコンクリートを打設する工程を、各階にわ
たり繰り返すことにて構築されるものである。
2. Description of the Related Art Conventionally, as a unit building having a reinforcing bar or a steel frame reinforced concrete structure, there is one described in JP-B-55-14217. This unit building is constructed by repeating the steps of suspending and installing reinforcing bars in the region between the side walls of adjacently arranged building units and then placing concrete in the region between the side walls over each floor.

【0003】[0003]

【発明が解決しようとする課題】然るに、従来技術で
は、コンクリート壁を構造耐力上有効に配置する必要が
あり、建物内部空間のプラン制約となる。
However, in the prior art, it is necessary to effectively dispose the concrete wall in terms of structural strength, which becomes a plan constraint for the internal space of the building.

【0004】そこで、鉄筋又は鉄骨鉄筋コンクリート構
造のユニット建物を構築するに際し、建物内部空間のプ
ラン自由度を高めるため、建物ユニットの柱や梁に沿っ
てコンクリート柱やコンクリート梁を打設し、このコン
クリート柱やコンクリート梁によって構造耐力を確保す
ることが考えられる。
Therefore, when constructing a unit building having a reinforced concrete structure or a steel reinforced concrete structure, concrete columns or concrete beams are laid along the columns or beams of the building unit in order to increase the degree of freedom in the plan of the interior space of the building. It is conceivable to secure structural strength with columns and concrete beams.

【0005】然しながら、建物ユニットの床梁に床スラ
ブを支持させた状態下で、該床梁にコンクリート梁を添
設した場合には、床スラブに作用する床荷重が床梁を介
してコンクリート梁に伝わることになる。即ち、床スラ
ブをコンクリート梁に直接的に支持させることができ
ず、十分な構造強度の確保に困難がある。また、床梁
は、コンクリート打設後にも十分な断面強度を具備する
必要があり、材料経済性が悪い。
However, when a floor slab is supported by a floor beam of a building unit and a concrete beam is attached to the floor beam, the floor load acting on the floor slab is applied to the floor beam through the floor beam. Will be transmitted to. That is, the floor slab cannot be directly supported by the concrete beam, and it is difficult to secure sufficient structural strength. In addition, the floor beam needs to have a sufficient cross-sectional strength even after the concrete is placed, and the material economy is poor.

【0006】尚、建物ユニットの床梁にコンクリート梁
を添設した後、該コンクリート梁上に床スラブを載置す
るものとすれば、床スラブをコンクリート梁に直接的に
一体化することができるが、この場合には、床スラブを
工場段階で予めユニット化することができず、生産性を
阻害する。
If a concrete beam is attached to the floor beam of the building unit and then the floor slab is placed on the concrete beam, the floor slab can be directly integrated with the concrete beam. However, in this case, the floor slab cannot be unitized in advance at the factory stage, which impedes productivity.

【0007】本発明は、建物ユニットの床梁にコンクリ
ート梁を添設し、鉄筋又は鉄骨鉄筋コンクリート構造の
ユニット建物を構築するに際し、生産性を阻害すること
なく、床スラブをコンクリート梁に直接的に支持可能と
することを目的とする。
According to the present invention, when a concrete beam is attached to a floor beam of a building unit to construct a unit building having a reinforcing bar or a steel reinforced concrete structure, the floor slab is directly attached to the concrete beam without impairing productivity. The purpose is to be supportable.

【0008】[0008]

【課題を解決するための手段】請求項1に記載の本発明
は、建物ユニットの床梁に沿ってコンクリート梁を打設
し、該コンクリート梁に床スラブを据付けるユニット建
物の床スラブ据付方法において、コンクリート梁の硬化
前には、床スラブを床梁に支持し、コンクリート梁の硬
化後には、床スラブをコンクリート梁に支持するように
したものである。
The present invention according to claim 1 is a method for installing a floor slab of a unit building, in which a concrete beam is placed along a floor beam of a building unit and the floor slab is installed on the concrete beam. In the above, the floor slab is supported by the floor beam before hardening of the concrete beam, and the floor slab is supported by the concrete beam after hardening of the concrete beam.

【0009】請求項2に記載の本発明は、請求項1に記
載の本発明において更に、前記建物ユニットの床梁が、
コンクリート梁打設のための捨型枠を構成するようにし
たものである。
According to a second aspect of the present invention, in addition to the first aspect of the present invention, the floor beam of the building unit further comprises:
It is designed to form a scrap frame for placing concrete beams.

【0010】請求項3に記載の本発明は、建物ユニット
の床梁に沿ってコンクリート梁を打設し、該コンクリー
ト梁に床スラブを据付けるユニット建物の床スラブ据付
装置において、床梁に嵌着されると共に、スラブ受部を
備えたスラブ支持ボルトを有し、スラブ支持ボルトは、
スラブ支持レベルに設定されてスラブ受部に床スラブを
支持し、スラブ非支持レベルに設定されてスラブ受部を
床スラブの下方に離間せしめ得るように構成されるよう
にしたものである。
According to a third aspect of the present invention, in a floor slab installation device of a unit building, a concrete beam is placed along a floor beam of a building unit, and a floor slab is installed on the concrete beam. Wearing and having a slab support bolt with a slab support, the slab support bolt,
The floor slab is set to the slab support level to support the floor slab, and the slab non-support level is set to allow the slab support to be spaced below the floor slab.

【0011】[0011]

【作用】本発明によれば、下記〜の作用がある。 打設されたコンクリート梁が硬化して必要強度が出る
までは、床スラブに作用する荷重は床梁に支持される。
そして、コンクリート梁の硬化後、床スラブは床梁と縁
を切り、床スラブに作用する荷重を全てコンクリート梁
へ伝えることになる。即ち、床スラブをコンクリート梁
に直接的に支持されることができ、十分な構造強度を確
保できる。また、床梁は、コンクリート打設前の最低限
の断面強度を有するものであれば足り、材料経済性が良
い。
According to the present invention, there are the following actions. The load acting on the floor slab is supported by the floor beam until the cast concrete beam hardens and the required strength appears.
Then, after the concrete beam is hardened, the floor slab is cut off from the floor beam to transfer all the load acting on the floor slab to the concrete beam. That is, the floor slab can be directly supported by the concrete beam, and sufficient structural strength can be secured. Further, the floor beam is sufficient as long as it has the minimum cross-sectional strength before placing concrete, and the material economy is good.

【0012】床スラブは、工場段階で、床梁に嵌着し
てあるスラブ支持ボルトに支持された状態で予めユニッ
ト化され、生産性を阻害することがない。
The floor slab is unitized in advance in a state of being supported by the slab support bolt fitted to the floor beam at the factory stage, so that productivity is not impaired.

【0013】床梁がコンクリート梁打設のための捨型
枠として機能するから、コンクリート梁打設のための構
成を著しく簡素とし、かつコンクリート梁打設ための作
業工数を著しく低減でき、生産性を向上できる。
Since the floor beam functions as a scrap frame for placing concrete beams, the structure for placing concrete beams can be remarkably simplified, and the man-hours for placing concrete beams can be remarkably reduced. Can be improved.

【0014】[0014]

【実施例】図1は高層ユニット建物の施工手順を示す模
式図、図2はインナユニットを示す模式図、図3はアウ
タユニットを示す模式図、図4はコラムユニットを示す
模式図、図5はガーダーユニットを示す模式図、図6は
柱梁接合ユニットを示す模式図、図7は高層ユニット建
物のユニット配置状態を示す平面図、図8はスラブ支持
ボルトの設置状態を示す模式図、図9はスラブ支持ボル
トの使用手順を示す模式図である。
EXAMPLE FIG. 1 is a schematic diagram showing a construction procedure of a high-rise unit building, FIG. 2 is a schematic diagram showing an inner unit, FIG. 3 is a schematic diagram showing an outer unit, FIG. 4 is a schematic diagram showing a column unit, and FIG. Is a schematic diagram showing a girder unit, FIG. 6 is a schematic diagram showing a beam-column joining unit, FIG. 7 is a plan view showing a unit arrangement state of a high-rise unit building, and FIG. 8 is a schematic diagram showing an installation state of slab support bolts. 9 is a schematic view showing a procedure of using the slab support bolt.

【0015】ユニット建物10は、図1(A)〜(E)
に示す如く、基礎上に、複数の建物ユニットとしての、
建物内部空間を形成するインナユニット11、建物外周
部を形成するアウタユニット12を水平及び鉛直方向に
隣接配置して構築される。そして、ユニット建物10
は、後に詳述するように、隣接するインナユニット1
1、アウタユニット12の柱間領域に配置されるコラム
ユニット13と、梁間領域に配置されるガーダーユニッ
ト14と、コラムユニット13とガーダーユニット14
の交差領域に配置される柱梁接合ユニット15のそれぞ
れに、コンクリートを打設することにて、コンクリート
柱13Aとコンクリート梁14Aとを具備するRCラー
メンを構成するものである。
The unit building 10 is shown in FIGS. 1 (A) to 1 (E).
As shown in the figure, on the foundation, as a plurality of building units,
The inner unit 11 forming the interior space of the building and the outer unit 12 forming the outer peripheral portion of the building are adjacently arranged in the horizontal and vertical directions. And the unit building 10
As described later in detail, the adjacent inner units 1
1. The column unit 13 arranged in the inter-column region of the outer unit 12, the girder unit 14 arranged in the inter-beam region, the column unit 13 and the girder unit 14.
By concrete is poured into each of the beam-column joining units 15 arranged in the intersection region, the RC rigid frame including the concrete column 13A and the concrete beam 14A is configured.

【0016】インナユニット11は、図2(A)〜
(E)に示す如く、4本の鋼板製柱21と、柱21の下
端部にボルト22により接合される4本の鋼板製床梁2
3と、柱21の上端部にボルト24により接合される4
本の鋼板製天井梁25とを有して構成された箱形骨組体
である。尚、インナユニット11は、床スラブ26、床
下地27、天井根太28、天井ボード29、更には給排
水、光熱配線、配管通信設備等の内装を工場で施された
後、建築現場に搬入され、据付けられる。
The inner unit 11 is shown in FIG.
As shown in (E), four steel plate columns 21 and four steel plate floor beams 2 joined to the lower ends of the columns 21 by bolts 22.
3 and 4 which are joined to the upper ends of the pillars 21 by bolts 4
It is a box-shaped frame body configured by including a steel plate ceiling beam 25 of a book. In addition, the inner unit 11 is carried into the construction site after the floor slab 26, the floor base 27, the ceiling joist 28, the ceiling board 29, the interior of the water supply / drainage, the photothermal wiring, the piping communication equipment, etc. are applied in the factory. Installed.

【0017】アウタユニット12は、図3に示す如く、
鋼板製柱31と、鋼板製梁32とを有して構成された骨
組体であり、外壁33、開口部34等の外装を工場で施
された後、建築現場に搬入され、据付けられる。
The outer unit 12 is, as shown in FIG.
It is a skeleton body having a steel plate column 31 and a steel plate beam 32, and is exteriorized such as an outer wall 33 and an opening 34 in a factory, and then carried into a construction site and installed.

【0018】ここで、インナユニット11、アウタユニ
ット12の柱21、31は、柱間領域に対して凹状をな
すL型断面材にて構成されている。尚、柱21、31の
L型断面の両端部は、コラムユニット13の後述する補
助型枠43の両端折り曲げ係合部43Aと係合し得る折
り曲げ係合部21Aを備えている。
Here, the columns 21 and 31 of the inner unit 11 and the outer unit 12 are made of L-shaped cross-section members which are concave with respect to the inter-column region. Both ends of the L-shaped cross sections of the columns 21 and 31 are provided with bending engaging portions 21A that can engage with both-end bending engaging portions 43A of an auxiliary mold 43 of the column unit 13 described later.

【0019】コラムユニット13は、図4(A)、
(B)に示す如く、横断面中心部を貫通する鋼管製パイ
プ41を備えるとともに、コンクリートを打設可能とさ
れる柱配筋42を上記パイプ41回りに備える。また、
コラムユニット13は、隣接するインナユニット11、
アウタユニット12の柱間領域回りの、複数の柱間隙に
設置される鋼板製補助型枠43を備えており、相対する
補助型枠43、43を互いに継なぎ筋44にて連結して
いる。尚、継なぎ筋44は、各補助型枠43に溶接され
ている棒鋼製補強リブ45に溶接されている。
The column unit 13 is shown in FIG.
As shown in (B), a pipe 41 made of steel pipe that penetrates through the central portion of the cross section is provided, and column reinforcements 42 that allow concrete to be placed are provided around the pipe 41. Also,
The column unit 13 includes the adjacent inner units 11 and
The outer unit 12 is provided with a steel plate auxiliary mold 43 installed in a plurality of pillar gaps around the inter-columnar region, and the opposing auxiliary molds 43, 43 are connected to each other by a splice 44. The joint bar 44 is welded to a steel bar reinforcing rib 45 which is welded to each auxiliary form 43.

【0020】ここで、コラムユニット13の柱配筋42
は、柱長手方向に延びる柱主筋46と、各柱主筋46を
囲む如くに配設される補強筋47と、上述の継なぎ筋4
4とから構成されている。尚、補助型枠43は両端部に
折り曲げ係合部43Aを備えており、柱21、31の折
り曲げ係合部21Aと係合し得るようになっている。
Here, the column reinforcements 42 of the column unit 13
Is a column main bar 46 extending in the column longitudinal direction, a reinforcing bar 47 arranged so as to surround each column main bar 46, and the above-mentioned joint bar 4.
4 and. The auxiliary mold 43 is provided with bending engaging portions 43A at both ends so that it can be engaged with the bending engaging portions 21A of the columns 21 and 31.

【0021】即ち、ユニット建物10にあっては、隣接
するインナユニット11、アウタユニット12の柱2
1、31と、それら柱間隙に設置される補助型枠43と
が、コラムユニット13へのコンクリート柱13A打設
のための捨型枠を構成するようになっている。
That is, in the unit building 10, the pillar 2 of the inner unit 11 and the outer unit 12 which are adjacent to each other.
1, 31 and the auxiliary formwork 43 installed in the space between the columns form a scrap formwork for placing the concrete column 13A on the column unit 13.

【0022】ガーダーユニット14は図5(A)、
(B)に示す如く、コンクリートを打設可能とされる梁
配筋51を備える。また ガーダーユニット14は、隣
接するインナユニット11、アウタユニット12の梁間
領域回りの、複数の梁間隙に設置される鋼板製補助型枠
52、53を備えており、相対する両側面の補助型枠5
2、52を互いに通線パイプ54にて連結し、底面の補
助型枠53を梁配筋51の継なぎ筋55により支持して
いる。補助型枠52は上階インナユニット11の床梁2
3と下階インナユニット11の天井梁25との梁間隙に
設置され、補助型枠53は左右のインナユニット11の
天井梁25の梁間隙に設置される。尚、通線パイプ5
4、継なぎ筋55は、各補助型枠52、53に溶接され
ている。
The girder unit 14 is shown in FIG.
As shown in (B), it is provided with a beam reinforcement 51 capable of placing concrete. Further, the girder unit 14 includes steel plate auxiliary molds 52 and 53 installed in a plurality of beam gaps around the inter-beam regions of the adjacent inner unit 11 and outer unit 12, and the auxiliary molds on the opposite side surfaces are opposed to each other. 5
The two and 52 are connected to each other by a conduit pipe 54, and the auxiliary formwork 53 on the bottom surface is supported by the splice lines 55 of the beam arrangement 51. The auxiliary formwork 52 is the floor beam 2 of the upper floor inner unit 11.
3 and the ceiling beam 25 of the lower inner unit 11 are installed in the beam gap, and the auxiliary formwork 53 is installed in the beam gap of the ceiling beams 25 of the left and right inner units 11. In addition, line pipe 5
4. The joint line 55 is welded to each auxiliary formwork 52, 53.

【0023】ここで、ガーダーユニット14の梁配筋5
1は、梁長手方向に延びる梁主筋56と、各梁主筋56
を囲む如くの補強筋57と、上述の継なぎ筋55とから
構成されている。尚、補助型枠52は下端部に下階イン
ナユニット11の天井梁25に載る折り曲げ部52Aを
備え、上端部に上階インナユニット11の床梁23を支
える折り曲げ部52Bを備えている。また、補助型枠5
3は両端部に折り曲げ係合部53Aを備えており、天井
梁25の折り曲げ係合部25Aと係合し得るようになっ
ている。
Here, the beam reinforcement 5 of the girder unit 14
1 is a beam main bar 56 extending in the beam longitudinal direction and each beam main bar 56
It is composed of a reinforcing bar 57 that surrounds the above and the above-mentioned connecting bar 55. The auxiliary form 52 has a bent portion 52A on the ceiling beam 25 of the lower inner unit 11 at the lower end, and a bent portion 52B that supports the floor beam 23 of the upper inner unit 11 at the upper end. Also, the auxiliary formwork 5
3 is provided with bending engaging portions 53A at both ends, and can be engaged with the bending engaging portions 25A of the ceiling beam 25.

【0024】即ち、ユニット建物10にあっては、隣接
するインナユニット11、アウタユニット12の床梁2
3、天井梁25、梁32と、それら梁間隙に設置される
補助型枠52、53とが、ガーダーユニット14へのコ
ンクリート梁14A打設のための捨型枠を構成するよう
になっている。
That is, in the unit building 10, the floor beams 2 of the inner unit 11 and the outer unit 12 which are adjacent to each other.
3, the ceiling beam 25, the beam 32, and the auxiliary formwork 52, 53 installed in the beam gap constitute a scrap formwork for placing the concrete beam 14A on the girder unit 14. ..

【0025】柱梁接合ユニット15は、図6(A)、
(B)に示す如く、横断面中心部を貫通する鋼管製中間
パイプ61を備えるとともに、コンクリートを打設可能
とされる柱配筋62と梁配筋63とを備える。
The column-beam joining unit 15 is shown in FIG.
As shown in (B), a steel pipe intermediate pipe 61 that penetrates through the central portion of the cross section is provided, and a column reinforcement 62 and a beam reinforcement 63 that allow concrete to be placed are provided.

【0026】ここで、柱梁接合ユニット15の柱配筋6
2は、柱長手方向に延びる柱主筋64と、各柱主筋64
を囲む如くに配設される補強筋65とから構成されてい
る。また、柱梁接合ユニット15の梁配筋63は、梁長
手方向に延びる梁主筋66と、各梁主筋66を囲む如く
に配設される補強筋67とから構成されている。
Here, the column reinforcement 6 of the column-beam joining unit 15
2 is a column main bar 64 extending in the column longitudinal direction, and each column main bar 64
And a reinforcing bar 65 arranged so as to surround the. The beam reinforcement 63 of the beam-column joining unit 15 is composed of a beam main reinforcement 66 extending in the beam longitudinal direction and a reinforcing reinforcement 67 arranged so as to surround each beam main reinforcement 66.

【0027】尚、上下に隣接するインナユニット11、
アウタユニット12のコラムユニット13を柱梁接合ユ
ニット15により接合するに際し、上下階のコラムユニ
ット13のパイプ41は、図4(C)に示す如く、柱梁
接合ユニット15のパイプ61を介して互いに連通せし
められる。このとき、パイプ41、61の上端部はスト
レート状であるのに対し、それらの下端部は受口部68
を備えており、後述する如くにパイプ41、61内を圧
送されるコンクリートが付着残留しにくいパイプ41、
61の上端部ストレート形状を備えるとともに、下階側
のパイプ41、61の上端部に対して嵌合し易いパイプ
41、61の下端部受口形状を備えることとしている。
The inner units 11, which are vertically adjacent to each other,
When the column unit 13 of the outer unit 12 is joined by the beam-column joining unit 15, the pipes 41 of the column units 13 on the upper and lower floors are mutually connected via the pipe 61 of the column-beam joining unit 15 as shown in FIG. 4C. Can communicate. At this time, the upper ends of the pipes 41 and 61 are straight, whereas the lower ends of the pipes 41 and 61 are in the receiving portion 68.
As will be described later, the pipe 41, 61 is less likely to adhere and remain with the concrete to be pumped in the pipe 41, 61,
In addition to the straight shape of the upper end portion of 61, the lower end portion of the pipes 41 and 61 that are easily fitted to the upper end portions of the pipes 41 and 61 on the lower floor side are provided.

【0028】以下、ユニット建物10の構築方法につい
て説明する。 (1) 複数のインナユニット11、アウタユニット12を
基礎上に吊り込み、1階層を構成するインナユニット1
1、アウタユニット12を水平方向に隣接配置する(図
1(A)、図7参照)。
A method of constructing the unit building 10 will be described below. (1) An inner unit 1 in which a plurality of inner units 11 and outer units 12 are suspended on a foundation to form one layer
1. The outer unit 12 is horizontally adjacently arranged (see FIG. 1A and FIG. 7).

【0029】(2) コラムユニット13を隣接配置された
インナユニット11、アウタユニット12のL型断面材
からなる柱21、31の、柱間領域に差し込む如くに配
置する(図1(B)参照)。
(2) The column unit 13 is arranged so as to be inserted into the inter-column region of the columns 21 and 31 made of the L-shaped cross-section material of the inner unit 11 and the outer unit 12 which are arranged adjacent to each other (see FIG. 1B). ).

【0030】(3) ガーダーユニット14を隣接配置され
たインナユニット11、アウタユニット12の天井梁2
5、32の梁間領域に配置する(図1(C)参照)。
(3) Ceiling beam 2 of inner unit 11 and outer unit 12 in which girder units 14 are arranged adjacent to each other
5 and 32 are arranged in the inter-beam region (see FIG. 1C).

【0031】(4) 柱梁接合ユニット15をコラムユニッ
ト13とガーダーユニット14の交差領域に配置する。
このとき、コラムユニット13のパイプ41上端ストレ
ート部に柱梁接合ユニット15のパイプ61下端受口部
68を嵌合せしめる。また、コラムユニット13の柱主
筋46と柱梁接合ユニット15の柱主筋64とを溶接、
特殊継手にて接合し、ガーダーユニット14の梁主筋5
6と柱梁接合ユニット15の梁主筋66とを溶接、特殊
継手にて接合する。
(4) The column-beam joint unit 15 is arranged in the intersection region of the column unit 13 and the girder unit 14.
At this time, the pipe 61 lower end receiving portion 68 of the column-beam joining unit 15 is fitted into the upper straight portion of the pipe 41 of the column unit 13. In addition, the column main bar 46 of the column unit 13 and the column main bar 64 of the column-beam joining unit 15 are welded,
Beam main bar 5 of girder unit 14 joined with a special joint
6 and the beam main reinforcement 66 of the beam-column joining unit 15 are welded and joined by a special joint.

【0032】(5) 上階層を構成するインナユニット1
1、アウタユニット12を上述(1) の下階層となるイン
ナユニット11、アウタユニット12の上部に隣接配置
する。
(5) Inner unit 1 constituting the upper layer
1. The outer unit 12 is arranged adjacent to the upper part of the inner unit 11 and the outer unit 12 which are lower layers of the above (1).

【0033】(6) 隣接配置されたインナユニット11、
アウタユニット12の柱21、31と、下階天井梁2
5、32と、上階床梁23、32を捨型枠とするととも
に、コラムユニット13、ガーダーユニット14に設け
た補助型枠43、52、53を捨型枠とし、1階層分の
コラムユニット13とガーダーユニット14にコンクリ
ートを打設し、コンクリート柱13A、コンクリート梁
14Aを形成する。このとき、上下階のコラムユニット
13のパイプ41は、上述(4) の柱梁接合ユニット15
のパイプ61を介して互いに連通せしめられており、コ
ンクリートは最下層のコラムユニット13のパイプ41
下部から充填され、今回打設階となっているコラムユニ
ット13のパイプ41回り、ガーダーユニット14、及
び柱梁接合ユニット15に打設される(図1(D)参
照)。
(6) Inner units 11 arranged adjacent to each other,
The pillars 21 and 31 of the outer unit 12 and the ceiling beam 2 on the lower floor
5 and 32 and upper floor floor beams 23 and 32 are scrap frames, and auxiliary molds 43, 52 and 53 provided in the column unit 13 and the girder unit 14 are scrap frames, and a column unit for one layer 13 and the girder unit 14 are poured with concrete to form concrete columns 13A and concrete beams 14A. At this time, the pipe 41 of the column unit 13 on the upper and lower floors is connected to the column-beam joining unit 15 of (4) above.
Are connected to each other through a pipe 61 of the pipe, and the concrete is the pipe 41 of the column unit 13 in the lowermost layer.
It is filled from the lower part and is placed around the pipe 41 of the column unit 13 which is the placement floor this time, the girder unit 14, and the beam-column joining unit 15 (see FIG. 1D).

【0034】尚、上述(6) のコンクリート打設の前又は
後工程で、ガーダーユニット14に設けられている通線
パイプ54にダクト69を接続する(図1(E)参
照)。 (7) ユニット建物10の各階について、上述(1) 〜(6)
を繰り返す。
The duct 69 is connected to the conduit pipe 54 provided in the girder unit 14 before or after the concrete pouring in (6) above (see FIG. 1 (E)). (7) For each floor of the unit building 10, above (1) to (6)
repeat.

【0035】然るに、インナユニット11は、図8に示
す如く、床梁23に嵌着されるスラブ支持ボルト80を
有しており、(a) 上述(6) のコンクリート梁14Aの硬
化前には、スラブ支持レベルに設定されて、スラブ受部
81に床スラブ26を支持し、(b) コンクリート梁14
Aの硬化後には、スラブ非支持レベルに設定されて、ス
ラブ受部81を床スラブ26の下方に離間せしめ、結果
として床スラブ26をコンクリート梁14Aに直接的に
支持せしめる。
However, the inner unit 11 has a slab support bolt 80 fitted to the floor beam 23 as shown in FIG. 8, and (a) before the concrete beam 14A of (6) above is hardened. , The slab support level is set, the floor slab 26 is supported by the slab receiving portion 81, and (b) the concrete beam 14
After the curing of A, it is set to the slab non-supporting level so that the slab receiving portion 81 is spaced below the floor slab 26, and as a result, the floor slab 26 is directly supported by the concrete beam 14A.

【0036】尚、上述(6) のガーダーユニット14への
コンクリート打設時、捨型枠となる両側インナユニット
11の床梁23の上部フランジ上には、当該捨型枠の上
端部を構成することとなるスペーサ100が設置される
(図5(A)、図8参照)。
When placing concrete on the girder unit 14 in the above (6), the upper end of the scrap frame is formed on the upper flange of the floor beam 23 of the inner unit 11 on both sides, which is a scrap frame. A different spacer 100 is installed (see FIG. 5A and FIG. 8).

【0037】以下、スラブ支持ボルト80の設置構造及
び使用手順について説明する。即ち、床梁23の上部フ
ランジ裏面にはナット82が溶接されており、スラブ支
持ボルト80の中間部には上述のスラブ受部81が設け
られ、スラブ支持ボルト80の下端ねじ部はナット82
に嵌着され、スラブ支持ボルト80の上端ねじ部に嵌着
されるナット83はスラブ受部81との間に床スラブ2
6を挟圧保持できる。そして、スラブ支持ボルト80
は、下記(1) 、(2) により使用される。
The installation structure and usage procedure of the slab support bolt 80 will be described below. That is, the nut 82 is welded to the back surface of the upper flange of the floor beam 23, the above-mentioned slab receiving portion 81 is provided in the middle portion of the slab support bolt 80, and the lower end screw portion of the slab support bolt 80 is the nut 82.
The nut 83 fitted to the slab support bolt 80 and the nut 83 fitted to the upper end screw part of the slab support bolt 80 is provided between the slab support part 81 and the floor slab 2
6 can be held with a pinching force. And the slab support bolt 80
Is used according to (1) and (2) below.

【0038】(1) スラブ支持レベルへのスラブ支持ボル
ト80の設定作業 スラブ支持ボルト80の下端ねじ部を床梁23に設け
てあるナット82に螺合する(図9(A)参照)。この
とき、スラブ支持ボルト80は上述(a) のスラブ支持レ
ベルに設定される。
(1) Setting work of the slab support bolt 80 on the slab support level The lower end thread portion of the slab support bolt 80 is screwed into the nut 82 provided on the floor beam 23 (see FIG. 9A). At this time, the slab support bolt 80 is set to the slab support level described in (a) above.

【0039】スラブ支持ボルト80のスラブ受部81
より上部に床スラブ26の支持孔26Aを嵌合し、床ス
ラブ26をスラブ受部81に支持する(図9(B)参
照)。スラブ支持ボルト80の上端面十字孔を工具にて
固定し、スラブ支持ボルト80の上端ねじ部にナット8
3を締結することにて、ナット83とスラブ受部81と
の間に床スラブ26を保持する(図9(C)参照)。
Slab support 81 of slab support bolt 80
The support hole 26A of the floor slab 26 is fitted to the upper portion to support the floor slab 26 on the slab receiving portion 81 (see FIG. 9 (B)). Fix the upper cross hole of the slab support bolt 80 with a tool, and attach the nut 8 to the upper screw part of the slab support bolt 80.
By fastening No. 3, the floor slab 26 is held between the nut 83 and the slab receiving portion 81 (see FIG. 9C).

【0040】(2) スラブ非支持レベルへのスラブ支持ボ
ルト80の設定作業 スラブ支持ボルト80の上端面十字孔を工具にて固定
し、ナット83をスラブ支持ボルト80の上端ねじ部か
ら緩め、ナット83を取り外す(図9(D)参照)。
(2) Setting work of the slab support bolt 80 to the slab non-support level Fix the upper end cross hole of the slab support bolt 80 with a tool, loosen the nut 83 from the upper screw part of the slab support bolt 80, and tighten the nut. 83 is removed (see FIG. 9 (D)).

【0041】スラブ支持ボルト80の上端面十字孔に
係合せしめた工具により、スラブ支持ボルト80をナッ
ト82に対して螺動し、スラブ支持ボルト80を上述
(b) のスラブ非支持レベルに設定する(図9(E)参
照)。
The slab support bolt 80 is screwed with respect to the nut 82 by a tool engaged with the upper end surface cross hole of the slab support bolt 80, and the slab support bolt 80 is moved to the above-mentioned position.
Set to the slab non-support level in (b) (see Fig. 9 (E)).

【0042】尚、ユニット建物10にあっては、隣接す
るインナユニット11、アウタユニット12の全ての柱
間領域にコラムユニット13を配置することを必須とせ
ず、一部の柱間領域(図7に破線で示す柱21間領域)
については、コラムユニット13を配置しないこともで
きる。その場合には、各階のコンクリート打設完了によ
り、各階層の構造耐力を確保した段階で、コラムユニッ
ト13の柱21を撤去し、広い居室空間等を得ることが
できる。尚、柱21は、床梁23、天井梁25との接合
部からボルト22、24を取外すことにて撤去できる。
In the unit building 10, it is not essential to dispose the column units 13 in all the inter-pillar regions of the inner unit 11 and the outer unit 12 which are adjacent to each other. (Area between columns 21 indicated by a broken line at)
For, it is possible not to arrange the column unit 13. In that case, the pillar 21 of the column unit 13 can be removed at the stage where the structural strength of each floor is secured by the completion of the concrete pouring on each floor, and a large living room space or the like can be obtained. The pillar 21 can be removed by removing the bolts 22 and 24 from the joint between the floor beam 23 and the ceiling beam 25.

【0043】また、ユニット建物10にあっては、1階
層分づつコンクリートを打設することを必須とせず、複
数階層分(全階層分であっても良い)のコラムユニット
13とガーダーユニット14に、一度にコンクリートを
打設するものとしても良い。
In addition, in the unit building 10, it is not essential to pour concrete for each floor, and the column unit 13 and the girder unit 14 for a plurality of floors (all floors may be used). , It is also possible to place concrete at once.

【0044】次に、本実施例の作用について説明する。 打設されたコンクリート梁14Aが硬化して必要強度
が出るまでは、床スラブ26に作用する荷重は床梁23
に支持される。そして、コンクリート梁14Aの硬化
後、床スラブ26は床梁23と縁を切り、床スラブ26
に作用する荷重を全てコンクリート梁14Aへ伝えるこ
とになる。即ち、床スラブ26をコンクリート梁14A
に直接的に支持されることができ、十分な構造強度を確
保できる。また、床梁23は、コンクリート打設前の最
低限の断面強度を有するものであれば足り、材料経済性
が良い。
Next, the operation of this embodiment will be described. Until the cast concrete beam 14A hardens and the required strength is obtained, the load acting on the floor slab 26 is the floor beam 23.
Supported by. Then, after the concrete beam 14A is hardened, the floor slab 26 is cut off from the floor beam 23, and the floor slab 26 is cut.
All the load acting on the concrete beam will be transmitted to the concrete beam 14A. That is, the floor slab 26 is replaced by the concrete beam 14A.
It can be directly supported by and can secure sufficient structural strength. Further, the floor beam 23 is sufficient as long as it has the minimum cross-sectional strength before placing concrete, and the material economy is good.

【0045】床スラブ26は、工場段階で、床梁23
に嵌着してあるスラブ支持ボルト80に支持された状態
で予めユニット化され、生産性を阻害することがない。
The floor slab 26 is the floor beam 23 at the factory stage.
The unit is preliminarily united in a state of being supported by the slab support bolt 80 fitted to the slab and does not hinder productivity.

【0046】床梁23がコンクリート梁14A打設の
ための捨型枠として機能するから、コンクリート梁14
A打設のための構成を著しく簡素とし、かつコンクリー
ト梁14A打設ための作業工数を著しく低減でき、生産
性を向上できる。
Since the floor beam 23 functions as a scrap frame for placing the concrete beam 14A, the concrete beam 14
The construction for placing A can be remarkably simplified, and the number of working steps for placing the concrete beam 14A can be significantly reduced, so that productivity can be improved.

【0047】尚、本発明の実施において、ユニット建物
10は、柱梁接合ユニット15を用いることを必須とし
ない。柱梁接合ユニット15を用いない場合には、図4
(D)に示す如く、コラムユニット13の柱配筋42内
に、互いに交差するコラムユニット13の柱主筋46と
接合される柱主筋71を備え、且つ互いに交差するガー
ダーユニット14の梁主筋56と接合される梁主筋72
とを備えることとなる。
In the practice of the present invention, the unit building 10 does not necessarily use the beam-column joining unit 15. When the column-beam joining unit 15 is not used, the structure shown in FIG.
As shown in (D), the column reinforcements 42 of the column unit 13 are provided with the column reinforcements 71 that are joined to the column reinforcements 46 of the column units 13 that intersect with each other, and the beam reinforcements 56 of the girder unit 14 that intersect with each other. Beam main bar 72 to be joined
And will be equipped.

【0048】[0048]

【発明の効果】以上のように本発明によれば、建物ユニ
ットの床梁にコンクリート梁を添設し、鉄筋又は鉄骨鉄
筋コンクリート構造のユニット建物を構築するに際し、
生産性を阻害することなく、床スラブをコンクリート梁
に直接的に支持可能とすることができる。
As described above, according to the present invention, when a concrete beam is added to a floor beam of a building unit to construct a unit building having a reinforcing bar or a steel frame reinforced concrete structure,
The floor slab can be directly supported by the concrete beam without impeding productivity.

【図面の簡単な説明】[Brief description of drawings]

【図1】図1は高層ユニット建物の施工手順を示す模式
図である。
FIG. 1 is a schematic diagram showing a construction procedure of a high-rise unit building.

【図2】図2はインナユニットを示す模式図である。FIG. 2 is a schematic diagram showing an inner unit.

【図3】図3はアウタユニットを示す模式図である。FIG. 3 is a schematic diagram showing an outer unit.

【図4】図4はコラムユニットを示す模式図である。FIG. 4 is a schematic view showing a column unit.

【図5】図5はガーダーユニットを示す模式図である。FIG. 5 is a schematic view showing a girder unit.

【図6】図6は柱梁接合ユニットを示す模式図である。FIG. 6 is a schematic view showing a beam-column joining unit.

【図7】図7は高層ユニット建物のユニット配置状態を
示す平面図である。
FIG. 7 is a plan view showing a unit arrangement state of a high-rise unit building.

【図8】図8はスラブ支持ボルトの設置状態を示す模式
図である。
FIG. 8 is a schematic view showing an installed state of slab support bolts.

【図9】図9はスラブ支持ボルトの使用手順を示す模式
図である。
FIG. 9 is a schematic view showing a procedure of using the slab support bolt.

【符号の説明】[Explanation of symbols]

10 ユニット建物 11 インナユニット(建物ユニット) 14A コンクリート梁 23 床梁 26 床スラブ 80 スラブ支持ボルト 81 スラブ受部 10 unit building 11 inner unit (building unit) 14A concrete beam 23 floor beam 26 floor slab 80 slab support bolt 81 slab receiving part

Claims (3)

【特許請求の範囲】[Claims] 【請求項1】 建物ユニットの床梁に沿ってコンクリー
ト梁を打設し、該コンクリート梁に床スラブを据付ける
ユニット建物の床スラブ据付方法において、コンクリー
ト梁の硬化前には、床スラブを床梁に支持し、コンクリ
ート梁の硬化後には、床スラブをコンクリート梁に支持
することを特徴とするユニット建物の床スラブ据付方
法。
1. A floor slab installation method for a unit building, in which a concrete beam is cast along a floor beam of a building unit, and the floor slab is installed on the concrete beam. A method for installing a floor slab in a unit building, which comprises supporting the beam on a beam and, after hardening the concrete beam, supporting the floor slab on the beam.
【請求項2】 前記建物ユニットの床梁が、コンクリー
ト梁打設のための捨型枠を構成する請求項1記載のユニ
ット建物の床スラブ据付方法。
2. The floor slab installation method for a unit building according to claim 1, wherein the floor beam of the building unit constitutes a scrap frame for placing a concrete beam.
【請求項3】 建物ユニットの床梁に沿ってコンクリー
ト梁を打設し、該コンクリート梁に床スラブを据付ける
ユニット建物の床スラブ据付装置において、床梁に嵌着
されると共に、スラブ受部を備えたスラブ支持ボルトを
有し、スラブ支持ボルトは、スラブ支持レベルに設定さ
れてスラブ受部に床スラブを支持し、スラブ非支持レベ
ルに設定されてスラブ受部を床スラブの下方に離間せし
め得るように構成されることを特徴とするユニット建物
の床スラブ据付装置。
3. A floor slab installation device of a unit building in which a concrete beam is placed along a floor beam of a building unit and a floor slab is installed on the concrete beam, and the slab receiving portion is fitted to the floor beam. Having a slab support bolt, the slab support bolt being set to a slab support level to support the floor slab to the slab support, and set to a slab non-support level to space the slab support below the floor slab. A floor slab installation device for a unit building, which is constructed so that it can be pressed.
JP3262124A 1991-10-09 1991-10-09 Method and apparatus for installing floor slab in unit building Expired - Lifetime JP3045839B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP3262124A JP3045839B2 (en) 1991-10-09 1991-10-09 Method and apparatus for installing floor slab in unit building

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP3262124A JP3045839B2 (en) 1991-10-09 1991-10-09 Method and apparatus for installing floor slab in unit building

Publications (2)

Publication Number Publication Date
JPH0598708A true JPH0598708A (en) 1993-04-20
JP3045839B2 JP3045839B2 (en) 2000-05-29

Family

ID=17371385

Family Applications (1)

Application Number Title Priority Date Filing Date
JP3262124A Expired - Lifetime JP3045839B2 (en) 1991-10-09 1991-10-09 Method and apparatus for installing floor slab in unit building

Country Status (1)

Country Link
JP (1) JP3045839B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20200010981A (en) * 2018-12-19 2020-01-31 한국건설기술연구원 Prestressing anchorage apparatus for strengthening flexural capacity of slab, and method using the same

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20200010981A (en) * 2018-12-19 2020-01-31 한국건설기술연구원 Prestressing anchorage apparatus for strengthening flexural capacity of slab, and method using the same

Also Published As

Publication number Publication date
JP3045839B2 (en) 2000-05-29

Similar Documents

Publication Publication Date Title
KR19980080404A (en) Method of construction of plant buildings and modular structures used in the construction thereof
JP3045839B2 (en) Method and apparatus for installing floor slab in unit building
JP2928002B2 (en) Column formwork structure
JPS6137692Y2 (en)
JP3105044B2 (en) How to build a unit building
JP3045841B2 (en) Beam formwork structure for unit building
JPH0480444A (en) Connection unit of reinforced concrete pole and steel framed beam
JP3586121B2 (en) Mixed structure of reinforced concrete column and steel beam and its construction method
JP3045840B2 (en) Column formwork for unit buildings
JP3207276B2 (en) How to build a unit building
JP3045838B2 (en) Unit building and its construction method
JP3045837B2 (en) Unit building and its construction method
JP3045836B2 (en) Unit building and its construction method
JP3045835B2 (en) Unit building and its construction method
JPH02311639A (en) Construction of composite floor
JPH05141044A (en) Bar arrangement unit
JP3105038B2 (en) Unit building
JPH06299718A (en) Construction of wall, floor in atomic power plant and wall slab thereof
JPH05125831A (en) Post for constructing concrete beam
JP2972956B2 (en) Column and beam joining method and its structure
JPS63165634A (en) Construction of wall type building
JP2023016370A (en) Construction method of structure
JPH02140339A (en) Structure of composite pc member
JP2020180442A (en) Double floor construction method
JPH0790972A (en) Construction of building and lightweight floor slab