JPH0577454U - Temporary roof structure for all-weather construction - Google Patents

Temporary roof structure for all-weather construction

Info

Publication number
JPH0577454U
JPH0577454U JP1489492U JP1489492U JPH0577454U JP H0577454 U JPH0577454 U JP H0577454U JP 1489492 U JP1489492 U JP 1489492U JP 1489492 U JP1489492 U JP 1489492U JP H0577454 U JPH0577454 U JP H0577454U
Authority
JP
Japan
Prior art keywords
roof
construction
skeleton
roofs
frame
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP1489492U
Other languages
Japanese (ja)
Other versions
JP2534580Y2 (en
Inventor
五郎 森口
晋 谷沢
建治 木村
Original Assignee
株式会社淺沼組
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 株式会社淺沼組 filed Critical 株式会社淺沼組
Priority to JP1489492U priority Critical patent/JP2534580Y2/en
Publication of JPH0577454U publication Critical patent/JPH0577454U/en
Application granted granted Critical
Publication of JP2534580Y2 publication Critical patent/JP2534580Y2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Abstract

(57)【要約】 【目的】 RC造躯体の施工時にその上部を屋根で覆
い、降雨、降雪でも施工を可能にすると共に、作業環境
を改善する。 【構成】 構築せんとする躯体Aの外側に多数の支柱1
を立設し、複数で躯体Aの上部を覆う上部屋根3と下部
屋根4を、支柱1へ着脱自在に固定して配置し、躯体A
の上部を覆うことによって雨天でも施工を可能にすると
共に、夏期や冬期における作業環境を改善する。また、
下部屋根4は開閉自在になっているので、資材の取り込
みが支障なく行なえ、躯体Aの施工が進行すると、両屋
根3、4はクレーンによる吊上げによって順次上昇させ
る。
(57) [Summary] [Purpose] The top of the RC structure is covered with a roof during construction to enable construction even in the event of rain or snow and improve the work environment. [Structure] A large number of struts 1 on the outside of the building A to be constructed
And a plurality of upper roofs 3 and lower roofs 4 covering the upper part of the skeleton A are detachably fixed to the support columns 1 and
By covering the upper part of the building, construction can be performed even in rainy weather, and the working environment in summer and winter is improved. Also,
Since the lower roof 4 is openable and closable, the material can be taken in without trouble, and when the construction of the frame A progresses, both roofs 3 and 4 are sequentially lifted by hoisting by a crane.

Description

【考案の詳細な説明】[Detailed description of the device]

【0001】[0001]

【産業上の利用分野】[Industrial applications]

この考案は、RC造の建物を構築するとき、建物の上部を覆い天候の影響を受 けることなく施工を可能にする全天候施工用仮設屋根構造に関する。 The present invention relates to a temporary roof structure for all-weather construction that covers the upper part of the building when constructing an RC structure and enables construction without being affected by the weather.

【0002】[0002]

【従来の技術】[Prior Art]

建築工事は降雨、降雪や暑さ、寒さなど天候の影響を受ける作業が多く、特に RC造の躯体工事においては降雨、降雪時に工事の中断を余儀なくされ、工期遅 延の大きな要因になっている。 Many construction works are affected by the weather such as rainfall, snowfall, heat, and cold. Especially, in the RC structure work, it is necessary to suspend the work during rain or snow, which is a major cause of delay in construction period. ..

【0003】 このため、残業や休日出勤が増加し、週休二日制の定着が困難となり、若年層 の建築業離れの大きな原因の一つになっている。For this reason, overtime work and holiday work increase, making it difficult to establish a two-day work week, which is one of the major causes for the youth to leave the construction industry.

【0004】 そこで、近年建築工事の作業環境を改善する目的で、躯体の上部を屋根で覆い 、降雨時でも施工を可能にすると共に、夏期や冬期の厳しい作業環境を緩和する 仮設屋根の提案がなされている。Therefore, in order to improve the working environment of construction work in recent years, a proposal of a temporary roof has been proposed in which the upper part of the skeleton is covered with a roof so that construction can be performed even during rainfall and the severe working environment in summer and winter is alleviated. Has been done.

【0005】[0005]

【考案が解決しようとする課題】[Problems to be solved by the device]

ところで、上記のような仮設屋根は、躯体の周囲に立設した支柱に電動式のク ライミング装置を取付け、躯体を覆う屋根をクライミング装置に固定し、躯体施 工の進行と共にクライミング装置で屋根を上昇動させるようになっているため、 設備コストが高くつくと共に、各クライミング装置を同調させて屋根を上昇させ るにはタイミング的に困難性があり、屋根の円滑な上昇が得られないという問題 がある。 By the way, in the above-mentioned temporary roof, an electric climbing device is attached to the pillars erected around the skeleton, the roof covering the skeleton is fixed to the climbing device, and the roof is climbed with the climbing device as the skeleton work progresses. Since it is designed to raise the roof, the equipment cost is high, and it is difficult to raise the roof in synchronization with each climbing device, which makes it difficult to raise the roof smoothly. There is.

【0006】 そこでこの考案は、RC造の構築に殆んどといっていいほどクレーンが使用さ れる点に着目し、屋根の上昇にクレーンを用いることにより、屋根の上昇が円滑 に行なえ、構造の簡略化と設備のコストダウンを図ることができる全天候施工用 仮設屋根構造を提供することを課題としている。In view of this, the present invention focuses on the fact that almost all cranes are used in the construction of RC structures, and by using the crane to raise the roof, the roof can be raised smoothly and the structure can be improved. The challenge is to provide a temporary roof structure for all-weather construction that can be simplified and the cost of equipment can be reduced.

【0007】[0007]

【課題を解決するための手段】[Means for Solving the Problems]

上記のような課題を解決するため、この考案は、構築せんとする躯体を囲む外 側の位置に複数の支柱を所定の間隔で立設し、複数で躯体の上部を覆う屋根を、 隣接する屋根間に高低差を設けた配置で個々に独立させて支柱に着脱自在となる よう固定し、少なくとも一つの屋根を開閉可能とした構成を採用したものである 。 In order to solve the above-mentioned problems, the present invention has a plurality of struts standing at an outer position surrounding a skeleton to be constructed at predetermined intervals, and a plurality of roofs covering the upper part of the skeleton are adjacent to each other. It has a structure in which at least one roof can be opened and closed by fixing it to the columns so that they can be detached from each other, with the height difference between the roofs being set independently.

【0008】[0008]

【作用】[Action]

構築せんとする躯体の外側を囲むように立設した支柱に躯体の上部を覆う屋根 を着脱自在に取付け、躯体構築部分の環境を改善し、降雨時にも工事を可能にし て工期の短縮を図る。 The roof that covers the upper part of the skeleton is detachably attached to the pillars that stand upright to surround the outside of the skeleton to be constructed, improve the environment of the skeleton construction part, and enable construction even in the case of rain to shorten the construction period. ..

【0009】 躯体の工事が進行するごとに、クレーンで屋根を吊持し、支柱への固定部分を 外した後、高い方の屋根から順に所要ストロークだけ引上げ、再び支柱に対して 固定する操作を繰返し行なう。[0009] Every time the construction of the frame progresses, the roof is hung by a crane, the part fixed to the pillar is removed, and then the roof is pulled up by the required stroke in order from the taller roof, and then the pillar is fixed again. Repeat.

【0010】 また、躯体部分の上部からの資材の搬入は開閉可能な屋根を開き、この部分か ら資材を入れる。In addition, when the material is loaded from the upper part of the skeleton part, the openable roof is opened and the material is loaded from this part.

【0011】[0011]

【実施例】【Example】

以下、この考案の実施例を添付図面に基づいて説明する。 An embodiment of the present invention will be described below with reference to the accompanying drawings.

【0012】 図1と図2のように、構築せんとするRC造躯体Aの外側でこの躯体Aを挾む 両側の位置に多数の支柱1を立設する。 この支柱1は躯体Aの外側を囲むように仮設する外部足場2と同列に組込まれ 、躯体1の長さ方向に一定の間隔で配置されている。As shown in FIGS. 1 and 2, a large number of struts 1 are erected on the outside of the RC skeleton A to be constructed and at both sides of the skeleton A. The columns 1 are incorporated in the same row as the external scaffolds 2 that are temporarily installed so as to surround the outside of the frame A, and are arranged at regular intervals in the length direction of the frame 1.

【0013】 上記躯体Aの上部を覆う屋根は、各支柱1のスパン毎に独立し、四隅を支柱1 に対して着脱自在に固定して躯体A上を覆う上部屋根3と、同じく四隅を支柱1 に着脱自在となるよう固定して躯体A上を覆い、上部屋根3よりも少し下方の位 置に設ける下部屋根4とからなり、これらを躯体Aの長さ方向へ交互に配置し、 躯体Aの全面を覆うようになっている。The roof covering the upper part of the skeleton A is independent for each span of each strut 1, and the four corners are detachably fixed to the strut 1 to cover the skeleton A and the upper roof 3 and the same four corners. 1 and a lower roof 4 which is fixed so as to be detachably fixed to cover the upper part of the structure A and which is provided at a position slightly lower than the upper roof 3, and these are alternately arranged in the longitudinal direction of the structure A. It covers the entire surface of A.

【0014】 上部屋根3は、両端を両側の支柱1に取付機構5を介して固定する一対の梁材 6、6を複数の横桟7で結合したフレーム8の上面に防災加工を施したシート9 を張設し、中央棟部から両側に下り勾配を設けた構造になっている。The upper roof 3 is a sheet having an upper surface of a frame 8 in which a pair of beam members 6, 6 whose both ends are fixed to the columns 1 on both sides via a mounting mechanism 5 are connected by a plurality of horizontal rails 7 and which has been subjected to a disaster prevention process. 9 is stretched and the structure has a downward slope on both sides from the central ridge.

【0015】 また、下部屋根4も同様に、両端を支柱1に取付機構5を介して固定する一対 の梁材10、10を複数の横桟11で結合したフレーム12上にシート13を張 設し、中央の棟部から両側に下り勾配を設けた構造になっている。Similarly, in the lower roof 4, a seat 13 is stretched on a frame 12 in which a pair of beam members 10 and 10 whose both ends are fixed to a support 1 via a mounting mechanism 5 are connected by a plurality of horizontal rails 11. However, it has a structure with a downward slope on both sides from the central ridge.

【0016】 上部屋根3の下部屋根4上に臨む側縁は、図5に示すように梁材6に固定した アーム14で支持してシート9の延長部9aを設け、この延長部9aが下部屋根 4上にラップして臨むようになっている。As shown in FIG. 5, the side edge of the upper roof 3 facing the lower roof 4 is supported by an arm 14 fixed to the beam member 6 to provide an extension 9a of the seat 9, and the extension 9a is a lower portion. It is designed to be wrapped on the roof 4.

【0017】 図示の場合、下部屋根4は、シート13を躯体Aの長さ方向にジグザグ状の折 り畳みと引延しが自在となるよう横桟11で保持し、梁材10、10間の上部に 張設したワイヤ15で手動もしくは電動によりシート13を開閉自在とし、上部 屋根3間を開くことにより、この部分から躯体A上に対する資材の出し入れが行 なえるようにしている。In the case shown in the figure, the lower roof 4 holds the sheet 13 with a cross rail 11 so that it can be folded and stretched in a zigzag shape in the length direction of the skeleton A. The sheet 15 can be opened and closed manually or electrically with a wire 15 stretched over the upper part of the roof, and by opening the upper roof 3, the material can be taken in and out of the frame A from this part.

【0018】 上記した上部及び下部屋根3、4を支柱1に対して固定する取付機構5は共に 等しく、下部屋根4の場合を図4で例示するように、支柱1を構成するアングル 材1aに取付孔16を設け、このアングル材1aと梁材10の端部に固定したブ ラケット17とを複数のボルト18で着脱自在に結合し、ボルト18の締め緩め により取付孔16の間隔でブラケット17の固定位置を上方へ順次変更できるよ うにしている。The above-mentioned attachment mechanisms 5 for fixing the upper and lower roofs 3 and 4 to the pillar 1 are the same, and as shown in FIG. 4 for the case of the lower roof 4, the angle member 1a that constitutes the pillar 1 is attached. A mounting hole 16 is provided, and the angle member 1a and a bracket 17 fixed to the end of the beam member 10 are detachably coupled with a plurality of bolts 18, and the brackets 17 are spaced at intervals of the mounting holes 16 by tightening and loosening the bolts 18. The fixed position of the can be changed upwards.

【0019】 取付機構5は図示に限定されるものではなく、例えばピンの打込式等支柱1に 対してブラケット17を着脱自在に固定化できかつ上下に位置調整できるものや 、上下に長いブラケット17を支柱1に緊結しておき、梁材10の端部を着脱自 在に固定できるようにしてもよい。The mounting mechanism 5 is not limited to the one shown in the figure. For example, a pin-placing type mountable bracket 5 can be removably fixed to the column 1, and the vertical position of the bracket 17 can be adjusted. 17 may be tightly connected to the column 1 so that the end of the beam 10 can be detachably fixed.

【0020】 この考案の仮設屋根構造は上記のような構成であり、RC造躯体Aを構築せん とする部分の周囲に外部足場2と支柱1の組立てを行なうと共に、地上において 1スパン毎の上部及び下部屋根3、4を地組する。The temporary roof structure of the present invention has the above-described structure, and the outer scaffold 2 and the pillars 1 are assembled around the portion where the RC structure A is constructed, and the upper part of each span is set on the ground. And the lower roofs 3 and 4 are assembled.

【0021】 次に、クレーンBを用い、先ず下部屋根4を吊上げ、これを対応する支柱1間 の所望高さ位置に建込み、梁材10の両端を取付機構5で支柱1に固定する。Next, using the crane B, first, the lower roof 4 is hoisted, and the lower roof 4 is erected at a desired height position between the corresponding columns 1, and both ends of the beam member 10 are fixed to the columns 1 by the attachment mechanism 5.

【0022】 この後、上部屋根3をクレーンBで吊上げて対応する支柱1間に建込み、梁材 6の両端を取付機構5で支柱1に固定する。After that, the upper roof 3 is hoisted by the crane B and installed between the corresponding columns 1, and both ends of the beam member 6 are fixed to the columns 1 by the attachment mechanism 5.

【0023】 上部屋根3は図5のように延長部9aが下部屋根4上に臨み、上部及び下部屋 根3、4を順次建込むことによって躯体Aの上面全体を覆うことができ、これに よって降雨時においても躯体Aの工事が行なえると共に、夏期や冬期における作 業環境を改善することができる。As shown in FIG. 5, the extension 3a of the upper roof 3 faces the lower roof 4, and the upper and lower chamber roots 3 and 4 are sequentially installed to cover the entire upper surface of the skeleton A. Therefore, it is possible to carry out the construction of the frame A even when it is raining, and it is possible to improve the working environment in the summer and winter.

【0024】 図5において、上部屋根3と下部屋根4間の隙間Hは、夏期は広く、冬期は狭 くなるように設定することにより、作業環境を緩和する。In FIG. 5, the gap H between the upper roof 3 and the lower roof 4 is set to be wide in the summer and narrow in the winter to relax the working environment.

【0025】 また、躯体Aに対する資材の取込み時は、所望位置の下部屋根4におけるシー ト13を折り畳んで開き、開口部分からクレーンで資材を搬入すればよい。Further, when the material is taken into the skeleton A, the sheet 13 on the lower roof 4 at a desired position may be folded and opened, and the material may be carried in by a crane from the opening portion.

【0026】 躯体Aが施工により高くなると、外部足場2及び支柱1を上方に継足して組立 てた後、先ず図1のように、上部屋根3をクレーンBで吊持した状態で取付機構 5を外し、この上部屋根3を所定階高だけ吊上げ、四隅を支柱1に対して固定す る。When the skeleton A becomes higher due to the construction, after the outer scaffold 2 and the pillar 1 are added upward to assemble, first, as shown in FIG. 1, the upper roof 3 is hung by the crane B, and the mounting mechanism 5 The upper roof 3 is lifted up by a predetermined floor height, and the four corners are fixed to the pillar 1.

【0027】 この後、下部屋根4も同様にクレーンBで吊上げて支柱1に固定し、躯体Aの 施工を行なうものであり、躯体Aが所定階高分だけ施工されるごとに、外部足場 2と支柱1の継足しと、上部及び下部屋根3、4の引上げを繰返して行ない、躯 体Aの完成後は、上部及び下部屋根3、4の取外しを行う。外部足場2と支柱1 の解体は、従来通り外壁の仕上げが完了後に行う。Thereafter, the lower roof 4 is also similarly lifted by the crane B and fixed to the pillar 1, and the construction of the frame A is performed. Every time the frame A is constructed by a predetermined floor height, the external scaffold 2 Repeating the addition of the pillar 1 and pulling up the upper and lower roofs 3 and 4, after the completion of the skeleton A, the upper and lower roofs 3 and 4 are removed. The dismantling of the outer scaffold 2 and the pillar 1 is performed after finishing the outer wall as usual.

【0028】[0028]

【効果】【effect】

以上のように、この考案によると、RC造躯体の施工時にその上部を屋根で覆 うようにしたので、降雨、降雪時においても躯体の施工が可能になり、工期の短 縮が図れると共に、直射日光や寒風を和らげ、作業環境を快適にして作業能率を 向上させることができ、作業員の確保や労働条件の改善が可能になる。 As described above, according to this invention, since the upper part of the RC structure is covered with the roof when the RC structure is constructed, the structure can be constructed even during rain or snow, and the construction period can be shortened. It can mitigate direct sunlight and cold winds, make the work environment comfortable and improve work efficiency, and can secure workers and improve working conditions.

【0029】 また、屋根は躯体施工に使用するクレーンを用いて上昇動させるようにしたの で、構造的に複雑なクライミング装置等の採用が不要になり、仮設屋根構造のコ スト低減が可能になる。Further, since the roof is moved up and down by using the crane used for the construction of the skeleton, it is not necessary to employ a structurally complicated climbing device or the like, and the cost of the temporary roof structure can be reduced. Become.

【0030】 更に、少なくとも一つの屋根を開閉自在としたので、躯体への資材搬入が支障 なく行なえる。Further, since at least one roof can be freely opened and closed, the material can be carried into the frame without any trouble.

【図面の簡単な説明】[Brief description of drawings]

【図1】仮設屋根構造の使用状態を示す斜視図FIG. 1 is a perspective view showing a usage state of a temporary roof structure.

【図2】同上の平面図FIG. 2 is a plan view of the same as above.

【図3】同じく縦断側面図[Figure 3] Similarly, a vertical side view

【図4】下部屋根と支柱の関係を示す斜視図FIG. 4 is a perspective view showing the relationship between the lower roof and the columns.

【図5】上部及び下部屋根の関係を示す縦断正面図FIG. 5 is a vertical sectional front view showing the relationship between the upper and lower roofs.

【符号の説明】[Explanation of symbols]

1 支柱 2 外部足場 3 上部屋根 4 下部屋根 5 取付機構 9、13 シート A 躯体 B クレーン 1 Support 2 External scaffolding 3 Upper roof 4 Lower roof 5 Mounting mechanism 9, 13 Seat A Body B Crane

Claims (1)

【実用新案登録請求の範囲】[Scope of utility model registration request] 【請求項1】 構築せんとする躯体を囲む外側の位置に
複数の支柱を所定の間隔で立設し、複数で躯体の上部を
覆う屋根を、隣接する屋根間に高低差を設けた配置で個
々に独立させて支柱に着脱自在となるよう固定し、少な
くとも一つの屋根を開閉可能としたことを特徴とする全
天候施工用仮設屋根構造。
1. A plurality of columns are erected at predetermined intervals at an outer position surrounding a frame to be constructed, and a roof covering the upper part of the frame is provided with a height difference between adjacent roofs. Temporary roof structure for all-weather construction, characterized in that it is individually and independently fixed to a pillar so that at least one roof can be opened and closed.
JP1489492U 1992-03-19 1992-03-19 Temporary roof structure for all-weather construction Expired - Fee Related JP2534580Y2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP1489492U JP2534580Y2 (en) 1992-03-19 1992-03-19 Temporary roof structure for all-weather construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP1489492U JP2534580Y2 (en) 1992-03-19 1992-03-19 Temporary roof structure for all-weather construction

Publications (2)

Publication Number Publication Date
JPH0577454U true JPH0577454U (en) 1993-10-22
JP2534580Y2 JP2534580Y2 (en) 1997-04-30

Family

ID=11873709

Family Applications (1)

Application Number Title Priority Date Filing Date
JP1489492U Expired - Fee Related JP2534580Y2 (en) 1992-03-19 1992-03-19 Temporary roof structure for all-weather construction

Country Status (1)

Country Link
JP (1) JP2534580Y2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2017533365A (en) * 2014-10-30 2017-11-09 ベトカット オーワイ Method of assembling roof truss with rain shield and roof truss bundle with rain guard

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2017533365A (en) * 2014-10-30 2017-11-09 ベトカット オーワイ Method of assembling roof truss with rain shield and roof truss bundle with rain guard

Also Published As

Publication number Publication date
JP2534580Y2 (en) 1997-04-30

Similar Documents

Publication Publication Date Title
JPH0577454U (en) Temporary roof structure for all-weather construction
JP3950800B2 (en) Suspension scaffold
JP3585460B2 (en) Awning building
JP2550477Y2 (en) All-weather temporary roof system
JP2661750B2 (en) Construction site tent
CN216406098U (en) Movable construction platform for workshop construction of factory building
JP3381090B2 (en) Temporary roof of building site
JPH0458866B2 (en)
JP2592980B2 (en) Construction method of steel frame material for high-rise structure
JP2871468B2 (en) How to build a building
JPH0791076A (en) Lift-up device of all weather type temporary roof
JP2779258B2 (en) Roof lift-up method
JP2764363B2 (en) Lifting hardware for temporary tents
JP2552986Y2 (en) Lifting piece for lifting temporary tent
JP3111446B2 (en) Gas station canopy manufacturing method
JP3231511B2 (en) Lift-up device for all-weather temporary roof
JP2575796Y2 (en) External curing frame
JPH04297668A (en) Climbing type all-weather roof for construction work
JPH10219629A (en) Windproof and snowproof fence with spike and its folding and erecting method
JP2764366B2 (en) Temporary tent with opening and closing mechanism
JP2634271B2 (en) Jack-up method and device
JP3954945B2 (en) Roof construction method and building construction method
JPH0135887Y2 (en)
JPS6236918Y2 (en)
JP2002121896A (en) Sunshade structure for roofing work

Legal Events

Date Code Title Description
R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

LAPS Cancellation because of no payment of annual fees