JPH0571291A - Detachable drill-boom - Google Patents

Detachable drill-boom

Info

Publication number
JPH0571291A
JPH0571291A JP16381091A JP16381091A JPH0571291A JP H0571291 A JPH0571291 A JP H0571291A JP 16381091 A JP16381091 A JP 16381091A JP 16381091 A JP16381091 A JP 16381091A JP H0571291 A JPH0571291 A JP H0571291A
Authority
JP
Japan
Prior art keywords
boom
cutter
drill
excavator
directions
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP16381091A
Other languages
Japanese (ja)
Inventor
Masataka Uozumi
雅孝 魚住
Sueo Kajiwara
末男 梶原
Tatsuo Usui
龍男 臼井
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Mitsui Construction Co Ltd
Original Assignee
Mitsui Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Mitsui Construction Co Ltd filed Critical Mitsui Construction Co Ltd
Priority to JP16381091A priority Critical patent/JPH0571291A/en
Publication of JPH0571291A publication Critical patent/JPH0571291A/en
Pending legal-status Critical Current

Links

Abstract

PURPOSE:To bore a blasting hole without carrying a boom cutter type excavator from a tunnel during the construction thereof. CONSTITUTION:A main boom 46 is provided to a chuck 42 capable of holding a boom cutter 9 of an excavator 6 so that it is capable of oscillating through a main jack 45. A sub-boom 47 having a drill 50 is provided to the main boom 46 so that it is capable of bending through a sub-jack 48.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明は、トンネルを構築する際
に、地山を掘削するために用いられる着脱式ドリルブー
ムに関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a removable drill boom used for excavating the natural ground when constructing a tunnel.

【0002】[0002]

【従来の技術】従来、トンネルを構築する際に、地山を
掘削するために地山の地質条件等に合わせて掘削機は選
択される。例えば、軟岩質の地山では、ブームカッタ式
掘削機を使用して掘進する。ところが、掘進中に硬岩等
の該掘削機で掘削不可能な地質に遭遇した場合、発破等
を用いて掘削することになる。この場合、一旦、該ブー
ムカッタ式掘削機を構築中のトンネルから出して、新た
に、ドリルジャンボを搬入して発破用のダイナマイト等
を装填するせん孔を開ける必要があった。
2. Description of the Related Art Conventionally, when constructing a tunnel, an excavator is selected according to the geological conditions of the natural ground for excavating the natural ground. For example, in soft rocky ground, a boom cutter type excavator is used for excavation. However, when a geological feature such as hard rock that cannot be excavated by the excavator is encountered during excavation, blasting or the like is used for excavation. In this case, it was necessary to once take out the boom cutter type excavator from the tunnel under construction, carry in a new drill jumbo, and open a hole for loading blasting dynamite and the like.

【0003】[0003]

【発明が解決しようとする課題】しかし、これでは、ブ
ームカッタ式掘削機を使用して軟岩質の地山を掘進する
際に、硬岩質の地山に遭遇する度に、ブームカッタ式掘
削機を構築中のトンネルから搬出してドリルジャンボを
搬入する等の掘削機の入れ替えといった無駄な工程を要
することになる。
However, with the boom cutter type excavator, the boom cutter type excavator is used every time a hard rock type ground is encountered when excavating the soft rock type ground. The wasteful process of exchanging the excavator, such as carrying out the machine from the tunnel under construction and carrying in the drill jumbo, is required.

【0004】そこで、本発明は、上記事情に鑑み、ブー
ムカッタ式掘削機を構築中のトンネルから搬出しなくて
も、発破用のダイナマイト等を装填するせん孔を開ける
ことができる着脱式ドリルブームを提供することを目的
とする。
Therefore, in view of the above circumstances, the present invention provides a detachable drill boom capable of forming a hole for loading blasting dynamite or the like without carrying out the boom cutter type excavator from the tunnel under construction. The purpose is to provide.

【0005】[0005]

【課題を解決するための手段】即ち、本発明は、本体
(46、47)を有し、前記本体(46、47)の一端
に、カッタ装着部(41)を掘削機(6)のカッタ(9
a)に対して着脱自在に設け、また、前記本体(46、
47)に、削岩機(50)を設けて構成される。
That is, the present invention has a main body (46, 47), and a cutter mounting portion (41) is provided at one end of the main body (46, 47) for a cutter of an excavator (6). (9
a) is detachably attached to the main body (46,
47) is provided with a rock drilling machine (50).

【0006】なお、括弧内の番号等は、図面における対
応する要素を示す便宜的なものであり、従って、本記述
は図面上の記載に限定拘束されるものではない。以下の
「作用」の欄についても同様である。
The numbers in parentheses are for convenience of showing the corresponding elements in the drawings, and the present description is not limited to the description in the drawings. The same applies to the column of "action" below.

【0007】[0007]

【作用】上記した構成により、本発明は、カッタ装着部
(41)をカッタ(9a)に装着することにより、削岩
機(50)を掘削機(6)に装着できるように作用す
る。
With the above-described structure, the present invention acts so that the rock drilling machine (50) can be mounted on the excavator (6) by mounting the cutter mounting portion (41) on the cutter (9a).

【0008】[0008]

【実施例】以下、本発明の実施例を図面に基づき説明す
る。図1は、本発明によるドリルブームをトンネル掘進
装置に装着したところの一実施例を示した側面図、図2
は、図1に示したドリルブームのカッタ把持装置の一実
施例を示す斜視図、図3は、図1に示したドリルブーム
を搭載し得るトンネル掘進装置の一実施例を示す破断平
面図、図4は、図3に示したトンネル掘進装置の破断側
面図である。
Embodiments of the present invention will be described below with reference to the drawings. 1 is a side view showing an embodiment in which a drill boom according to the present invention is attached to a tunnel excavation device, FIG.
1 is a perspective view showing an embodiment of the cutter holding device for the drill boom shown in FIG. 1, and FIG. 3 is a cutaway plan view showing an embodiment of a tunnel excavation device capable of mounting the drill boom shown in FIG. FIG. 4 is a cutaway side view of the tunnel excavation device shown in FIG. 3.

【0009】本発明によるドリルブーム40は、図1に
示すように、カッタ把持装置41を有しており、カッタ
把持装置41には、円錐台形状のチャック42が軸心C
T2を中心として矢印R、S方向に屈折自在に設けられ
ている。即ち、図2に示すように、チャック42には、
本体42e、42eが円錐台形状を分割部42f、42
fで2分割する形で設けられており、本体42eの分割
部42fの円錐状部分には、フランジ42d、42dが
分割部42fの円錐状部分の母称に沿う形でそれぞれ設
けられている。フランジ42dには、ボルト等から成る
把持ピン53が図中上下方向に貫通し得るような穴が穿
設されており、本体42e、42eは、フランジ42
d、42dの該穴に図中上方より把持ピン53を挿入し
ナット54で締め付けることによりフランジ42d、4
2d同志を接合する形で結合できる。また、チャック4
2の本体42eの平面部分には、板状のブラケット43
が該平面部分に垂直にそれぞれ設けられており、ブラケ
ット43には、円筒状のピン44が軸心CT2を形成す
る形で摺動自在に設けられている。即ち、チャック42
は、軸心CT2を中心として矢印R’、S’方向に屈折
することにより開口し、矢印R”、S”方向に屈折する
ことにより閉口する。また、ピン44は、図1に示すよ
うに、該ピン44が形成する軸心CT2を後述する掘削
機6のカッタ9aの回転中心CT1と図1紙面垂直方向
に直交する形で設けられている。また、チャック42に
は、図1に示すように、内面42cが略台形断面を形成
するカッタ9aの外周面9dに沿う形で設けられてお
り、更に、チャック42には、爪状の把持部42bがカ
ッタ9aの台形断面の下底端部に掛ける形で設けられて
おり、更に、チャック42の外周面42aには、油圧ジ
ャッキ等から成るメインジャッキ45が矢印K、L方向
に突出後退自在に設けられている。メインジャッキ45
の他端には、くの字型屈折した棒状のメインブーム46
が該メインブーム46の屈折部近傍に枢着して設けられ
ており、メインブーム46の一端は、前記ピン44を介
してカッタ把持装置41に軸心CT2を中心として矢印
R、S方向に揺動自在な形で設けられている。即ち、図
2に示すように、メインブーム46(図中破線で示す)
の一端をブラケット43、43が挾む形でピン44が嵌
入され、該ピン44が形成する軸心CT2を中心として
矢印R、S方向に揺動する。また、メインブーム46に
は、油圧ジャッキ等から成るサブジャッキ48(図中二
点鎖線で図示)が矢印M、N方向に突出後退自在に設け
られており、サブジャッキ48の他端には、棒状のサブ
ブーム47が枢着して設けられている。サブブーム47
の一端は、メインブーム46の他端に軸心CT3を中心
として矢印T、U方向に揺動自在に設けられており、サ
ブブーム47の上面47aには、削岩機50が設けられ
ている。削岩機50の先端(図中最左方)には、発破用
のせん孔を開けるためのドリル51が設けられており、
ドリル51は、削岩軸CT4を中心として矢印V、W方
向に回転駆動して削岩する。削岩軸CT4は、メインブ
ーム46及びサブブーム47を折畳んだ状態で水平方向
(矢印A、B方向に平行な方向)に保持した際に、掘削
機6のカッタ9aの回転中心CT1と一致する形で設け
ている。
As shown in FIG. 1, the drill boom 40 according to the present invention has a cutter gripping device 41. The cutter gripping device 41 has a truncated cone-shaped chuck 42 as an axial center C.
It is provided so that it can be bent in the directions of arrows R and S centering on T2. That is, as shown in FIG.
The main body 42e, 42e has a truncated cone shape, and the divided portions 42f, 42e
It is provided in a form of being divided into two by f, and flanges 42d and 42d are respectively provided on the conical portion of the divided portion 42f of the main body 42e in a shape that follows the mother name of the conical portion of the divided portion 42f. The flange 42d is provided with a hole through which the gripping pin 53 made of a bolt or the like can penetrate in the vertical direction in the figure, and the main bodies 42e and 42e are formed in the flange 42d.
The grip pins 53 are inserted into the holes of d and 42d from the upper side in the drawing, and the nuts 54 are tightened to tighten the flanges 42d and 4d.
2d can be joined by joining each other. Also, the chuck 4
The plate-like bracket 43 is provided on the plane portion of the second main body 42e.
Are provided perpendicularly to the plane portion, and a cylindrical pin 44 is slidably provided on the bracket 43 so as to form the axial center CT2. That is, the chuck 42
Opens by bending in the directions of arrows R ′ and S ′ around the axis CT2, and closes by bending in the directions of arrows R ″ and S ″. Further, as shown in FIG. 1, the pin 44 is provided such that the axial center CT2 formed by the pin 44 is orthogonal to the rotation center CT1 of the cutter 9a of the excavator 6 described later in the direction perpendicular to the plane of FIG. .. Further, as shown in FIG. 1, the chuck 42 is provided with an inner surface 42c along the outer peripheral surface 9d of the cutter 9a forming a substantially trapezoidal cross section. 42b is provided so as to hang on the lower bottom end of the trapezoidal cross section of the cutter 9a, and further, a main jack 45 composed of a hydraulic jack or the like is projected and retractable in the directions of arrows K and L on the outer peripheral surface 42a of the chuck 42. It is provided in. Main jack 45
The other end of the main boom 46 is bent in a dogleg shape.
Is pivotally provided near the bending portion of the main boom 46, and one end of the main boom 46 swings to the cutter gripping device 41 via the pin 44 in the directions R and S about the axis CT2. It is provided in a freely movable form. That is, as shown in FIG. 2, the main boom 46 (shown by a broken line in the figure)
A pin 44 is fitted in such a manner that the brackets 43, 43 are sandwiched at one end thereof and is swung in the directions of arrows R and S about the axial center CT2 formed by the pin 44. Further, the main boom 46 is provided with a sub jack 48 (illustrated by a chain double-dashed line in the drawing) composed of a hydraulic jack or the like so as to project and retract in the directions of arrows M and N, and at the other end of the sub jack 48, A rod-shaped sub-boom 47 is pivotally mounted. Sub boom 47
Is provided at the other end of the main boom 46 so as to be swingable in the directions of arrows T and U about the axis CT3, and a rock drill 50 is provided on the upper surface 47a of the sub boom 47. A drill 51 is provided at the tip of the rock drilling machine 50 (on the leftmost side in the figure) to open a hole for blasting,
The drill 51 rotationally drives in the directions of arrows V and W around the rock drilling axis CT4 to drill rocks. The rock drilling axis CT4 coincides with the rotation center CT1 of the cutter 9a of the excavator 6 when the main boom 46 and the sub boom 47 are folded and held in the horizontal direction (direction parallel to the arrow A and B directions). It is provided in the shape.

【0010】ところで、トンネル掘進装置1は、図3及
び図4に示すように、胴型状に形成された外殻2を有し
ており、外殻2は掘進方向、即ち矢印A、B方向に近接
遠退自在に接続された前胴2A及び後胴2Bにより構成
されている。即ち、図4に示すように、後胴2Bの先端
部分には中継胴2Cが、前胴2A後端部分に入り込む形
で形成されており、中継胴2Cには、後胴2Bの内周に
沿う形で複数外殻ジャッキ2Dが矢印A、B方向に突出
後退自在に設けられている。そして、外殻ジャッキ2D
を押出し駆動することにより後胴2Bは、既設のリング
16に反力を取る形で外殻ジャッキ2Dのピッチ分だけ
矢印A方向に移動することが出来る。また、前胴2A及
び後胴2Bの下方にはインバート25bが、地山20が
切り開かれることにより岩盤が露出した形で形成されて
おり、インバート25bは切羽20aからトンネル後方
へ、即ち矢印A方向から矢印B方向に伸延する形で、連
続的に形成されている。前胴2Aは、インバート25b
に向かって開口する形で無底状に形成されており、後胴
2Bには、下側に底部2B1が、インバート25bとの
間を遮蔽される形で形成されている。前胴2A及び後胴
2Bの左右内側面には外殻レッグ3が、矢印A、B方向
に複数並んで該前胴2A及び後胴2Bの下端部分から下
方に突出する形で昇降自在に設けられており、従って、
後胴2Bに設けられた外殻ジャッキ3は底部2B1を貫
通している。そして、各外殻レッグ3はインバート25
bに支持されており、外殻レッグ3にはレッグジャッキ
3Aが、前胴2A及び後胴2Bを上下、即ち矢印C、D
方向に移動自在に支持する形で、設けられている。
As shown in FIGS. 3 and 4, the tunnel excavation device 1 has a shell-shaped outer shell 2, and the outer shell 2 is in the excavating direction, that is, in the directions of arrows A and B. The front torso 2A and the rear torso 2B are connected to each other so as to be able to move back and forth. That is, as shown in FIG. 4, a relay barrel 2C is formed at the tip of the rear barrel 2B so as to fit into the rear end of the front barrel 2A. A plurality of outer shell jacks 2D are provided along the shape so as to project and retract in the directions of arrows A and B. And outer shell jack 2D
By pushing out, the rear body 2B can move in the direction of arrow A by the pitch of the outer shell jack 2D in such a manner that a reaction force is applied to the existing ring 16. In addition, an invert 25b is formed below the front body 2A and the rear body 2B in a form in which the rock mass is exposed by the ground 20 being cut open. The invert 25b extends from the face 20a toward the rear of the tunnel, that is, in the direction of arrow A. Is continuously formed in the form of extending in the direction of arrow B from. Front torso 2A is Invert 25b
The bottom portion 2B 1 is formed at the lower side of the rear body 2B so as to be shielded from the invert 25b. A plurality of outer shell legs 3 are arranged on the left and right inner side surfaces of the front body 2A and the rear body 2B in a line in the directions of arrows A and B so as to be vertically movable so as to project downward from the lower end portions of the front body 2A and the rear body 2B. And therefore,
The outer shell jack 3 provided on the rear body 2B penetrates the bottom portion 2B 1 . And each outer shell leg 3 is invert 25
The outer shell leg 3 is supported by b, and the leg jack 3A moves up and down the front torso 2A and the rear torso 2B, that is, arrows C and D.
It is provided so that it can be moved in any direction.

【0011】前胴2Aの前端部分には、図4に示すよう
に、切羽20aのアーチ部分を仮支保するための先受矢
板5が、該前胴2Aの内周に沿った形で、且つ矢印A、
B方向に油圧ジャッキ等により突出後退自在に複数枚設
けられており、前胴2Aの内側には掘削機6が設置され
ている。掘削機6は機体6aを有しており、図4に示す
ように、機体6aの後部には掘削機6を操作駆動する為
の油圧ユニット61、制御盤62等が内蔵されている。
機体6aの後方には、トグルジャッキ13が、支持押圧
すべき重量に対応する形で適宜選択されて設けられてい
る。機体6aの底部には該機体6aを矢印A方向に推進
させるためのスライドシュー機構7が設けられており、
スライドシュー機構7は、固定シュー7A、駆動シュー
7B、スライドジャッキ7C等により構成されている。
固定シュー7Aは機体6aを支持する形でスキー板状に
形成されており、固定シュー7Aは、機体6aに対して
は矢印A、B方向に移動しない形で接続されている。ま
た、駆動シュー7Bは、固定シュー7Aと同様にスキー
板状に形成されており、駆動シュー7Bは機体6aに対
して、スライドジャッキ7Cを介して矢印A方向に先行
移動し得る形になっている。機体6aの前端にはブーム
カッタ9が、図4中回転軸CT5を中心として矢印C、
D方向に、及び、図3中回転軸CT6を中心として矢印
E、F方向に揺動駆動自在及び矢印A、B方向に進退駆
動自在で且つ旋回駆動自在な形で設けられており、ブー
ムカッタ9の先端には、地山20等の岩盤を破砕掘削し
得るカッタ9aが、円錐台状に形成されてブームカッタ
軸部9bに固定された形で設けられている。図4に示す
ように、ブームカッタ軸部9bの外周にはスクリューブ
レード9cが、ずり、即ちカッタ9aにより破砕された
切羽20aの岩を、矢印B方向である後方へ搬送する形
で回転軸CT1を中心として矢印P、Q方向に回転自在
に設けられており、スクリューブレード9cの後方には
ずり回収用のギャザリング10が、ブームカッタ軸部9
bの基部に装着される形で設けられている。ギャザリン
グ10に回収されたずりは、機体6aの側方に設けられ
たコンベヤ11を介して、さらに後方へ搬送されて、適
当なるずり搬送手段によりトンネル25の抗外へ運び出
される。
As shown in FIG. 4, at the front end portion of the front body 2A, there is provided a front receiving sheet pile 5 for temporarily supporting the arch portion of the face 20a along the inner circumference of the front body 2A. Arrow A,
A plurality of hydraulic jacks are provided so as to project and retract in the B direction, and an excavator 6 is installed inside the front body 2A. The excavator 6 has a machine body 6a, and as shown in FIG. 4, a hydraulic unit 61 for operating and driving the excavator 6 and a control panel 62 are built in the rear portion of the machine body 6a.
To the rear of the machine body 6a, a toggle jack 13 is appropriately selected and provided in a form corresponding to the weight to be supported and pressed. A slide shoe mechanism 7 for propelling the machine body 6a in the direction of arrow A is provided at the bottom of the machine body 6a.
The slide shoe mechanism 7 is composed of a fixed shoe 7A, a drive shoe 7B, a slide jack 7C and the like.
The fixed shoe 7A is formed in a ski shape so as to support the machine body 6a, and the fixed shoe 7A is connected to the machine body 6a so as not to move in the directions of arrows A and B. Further, the drive shoe 7B is formed in a ski shape like the fixed shoe 7A, and the drive shoe 7B is configured to be able to move in advance in the arrow A direction with respect to the machine body 6a via the slide jack 7C. There is. At the front end of the machine body 6a, a boom cutter 9 is provided with an arrow C about the rotation axis CT5 in FIG.
The boom cutter is provided so as to be swingable in the directions D and F in the directions E and F around the rotation axis CT6 in FIG. At the tip of 9, a cutter 9a capable of crushing and excavating rocks such as natural ground 20 is provided in a shape of a truncated cone and fixed to a boom cutter shaft portion 9b. As shown in FIG. 4, a screw blade 9c is provided on the outer circumference of the boom cutter shaft portion 9b so as to convey the rock, that is, the rock of the cutting face 20a crushed by the cutter 9a to the rear in the direction of arrow B. Is provided rotatably in the directions of arrows P and Q around the center of the boom cutter shaft portion 9 as a gathering ring 10 for slipping recovery at the rear of the screw blade 9c.
It is provided so as to be attached to the base of b. The shear collected in the gathering 10 is further transported to the rear via the conveyor 11 provided on the side of the machine body 6a, and is transported to the outside of the tunnel 25 by an appropriate shear transport means.

【0012】ところで、前記機体6aの上部には矢印
A、B方向に並ぶ2体のキャノピージャッキ12、12
が、シリンダ12a部分が連立する形で装着されてお
り、各キャノピージャッキ12の上部には、前記前胴2
Aの天蓋部分内周面に沿う形で蒲鉾片状に形成されたキ
ャノピー12bが、シリンダ12aを介して矢印C、D
方向である上下方向に移動駆動自在な形で、設けられて
いる。また、機体6aの矢印E、F方向両側部には、図
3に示すように、サイドジャッキ15、15が、機体6
aを前胴2Aの内側面に支持させる形で装着されてお
り、即ち機体6aと前胴2Aとは、キャノピージャッキ
12、12及びサイドジャッキ15、15を介して、坑
道内周方向に対して接合分離自在な形に構成されてい
る。
By the way, on the upper portion of the machine body 6a, two canopy jacks 12, 12 arranged in the directions of arrows A and B are arranged.
However, the cylinders 12a are mounted in a lined manner, and the front body 2 is attached to the upper portion of each canopy jack 12.
A canopy 12b formed in the shape of a kamaboko along the inner peripheral surface of the canopy portion of A has arrows C and D through a cylinder 12a.
It is provided so that it can be moved and driven in the vertical direction, which is the direction. As shown in FIG. 3, side jacks 15 and 15 are provided on both sides of the machine body 6a in the directions of arrows E and F, respectively.
It is mounted in such a manner that a is supported on the inner surface of the front body 2A, that is, the machine body 6a and the front body 2A are connected to the inner circumferential direction of the tunnel through the canopy jacks 12 and 12 and the side jacks 15 and 15. It is configured so that it can be joined and separated.

【0013】そしていま、図4に示すように、後胴2B
の後方には、エレクタ30により覆工建て込みされた長
円環状の楕円型リング16が、矢印A、B方向に隙間な
く並ぶ形で複数接続されており、隣接する楕円型リング
16、16間には止水板、締結ボルト等が、該複数接続
される楕円型リング16を密に構造一体化する形で、適
宜構築されている。エレクタ30により既に覆工建て込
みされて構造一体化した楕円型リング16の構築方向最
先端部分、即ち、図中左方に敷設されている敷設楕円型
リング16Aは、後胴2Bの内部に該後胴2Bの後方
(図中右方)から入り込む形で配置されている。該最先
端部分に配置された敷設済の敷設楕円型リング16Aの
矢印A方向下端部分には、該構築済の既設楕円型リング
16Aと新たに敷設される搬入楕円型リング16Bを接
合するためのセグメント支持手段29が、底部2B1
固定される形で設けられている。楕円型リング16の円
周方向外側には、地山20が馬蹄形状断面に掘削される
ことにより長円状断面の楕円型リング16との間に空隙
が生じる形で、裏込め層21が形成されており、裏込め
層21には、グラウトポンプ23等を介してモルタル2
2等が充填される。従って、いま、モルタル22が硬化
することにより覆工が完了したものとすると、後胴2B
の後方には既に覆工済みのトンネル25が接続されてい
る。また、覆工済みのトンネル25と切羽20aの間に
は、掘削機6を介して掘削される地山20に余掘りが避
けがたく形成される形で、外殻2と地山20の間に仮空
隙21’が生じており、仮空隙21’には砂、発砲スチ
ロールビーズ等の一次裏込材26が充填されている。
Now, as shown in FIG. 4, the rear body 2B
A plurality of elliptical elliptical rings 16 erected by erectors 30 are connected to the rear of the so as to line up in the directions of arrows A and B without gaps between adjacent elliptical rings 16 and 16. A water stop plate, fastening bolts, etc. are appropriately constructed in such a manner that the plurality of connected elliptical rings 16 are densely integrated with each other. The erected elliptical ring 16A, which is laid on the left side in the drawing, of the elliptical ring 16 that has already been lining-built by the erector 30 and is structurally integrated, that is, the laid elliptical ring 16A is laid inside the rear torso 2B. It is arranged so as to enter from the rear (right side in the figure) of the rear body 2B. At the lower end portion in the arrow A direction of the installed elliptical ring 16A arranged at the most distal end, the already-constructed existing elliptical ring 16A and the newly installed carry-in elliptical ring 16B are joined together. The segment supporting means 29 is provided so as to be fixed to the bottom portion 2B 1 . The backfill layer 21 is formed on the outer side in the circumferential direction of the elliptical ring 16 in such a manner that the ground 20 is excavated in a horseshoe-shaped cross section so that a gap is formed between the rock 20 and the elliptical ring 16 having the oval cross section. The mortar 2 is provided on the backfill layer 21 via a grout pump 23 or the like.
2 etc. are filled. Therefore, assuming that the mortar 22 is now hardened and the lining is completed, the rear body 2B
A tunnel 25 that has already been lined is connected to the rear of the. Moreover, between the outer shell 2 and the natural ground 20 in such a manner that the overburden is unavoidably formed in the natural ground 20 excavated by the excavator 6 between the lining tunnel 25 and the face 20a. A temporary void 21 'is formed in the inner wall of the inner wall 21. The temporary void 21' is filled with a primary backing material 26 such as sand and foam polystyrene beads.

【0014】本発明は以上のような構成を有するので、
トンネルを構築する際は、まず、トンネル掘進装置1を
用いて、軟岩質の地山20を掘削する。即ち、先受矢板
5により切羽20a部分の岩が崩落し得ないように支持
し、レッグジャッキ3Aを突出させて外殻レッグ3を介
して外殻2を矢印C方向に押し上げ地山20を支持す
る。また、キャノピージャッキ12を加圧負荷してラム
12cを矢印C方向に押し出すことにより前胴2Aの天
蓋部分にキャノピー12bを押しつける。更に、サイド
ジャッキ15、15を加圧負荷してラム15c、15c
を矢印E、F方向に押しだすことにより、機体6aを前
胴2Aとを一体化させる。すると、機体6aは前胴2A
の周面全体の面圧により支持される形になるので、機体
6aが、ブームカッタ9に生じる掘削抵抗や振動に十分
抗して前胴2A内を移動し得ないように堅固に固定支持
される。こうして、機体6aが前胴2Aに堅固に支持さ
れたところで、切羽20aにカッタ9aを当接する形で
掘削機6を駆動し、ブームカッタ9を、矢印C、D、
E、F方向に揺動させつつ回転駆動することにより、岩
を破砕して掘削断面形状が馬蹄形を呈するように切羽2
0aを掘削しつつ掘削機6を掘削ストローク分だけ矢印
A方向に掘進させる。また、切羽20aを掘削すると同
時に乃至先立ち、仮空隙21’には、発砲スチロールビ
ーズ等の一次裏込材26を圧送パイプ27を介してアー
チ25a部分から適宜圧力を以って注入する形で充填す
る。これにより、一次裏込材26は地山20の変形をあ
る程度許容しつつ余掘り部分からの肌落ちを防止すると
共に、外殻2から外側周面に沿った形で外方へ作用する
応力を、一次裏込材26を介して地山20に分散支持さ
せことができる。
Since the present invention has the above configuration,
When constructing a tunnel, first, the tunnel excavation device 1 is used to excavate the soft rocky ground 20. That is, the front sheet pile 5 supports the rocks of the face 20a so that they cannot fall, and the leg jack 3A is projected to push the outer shell 2 through the outer shell leg 3 in the direction of arrow C to support the natural ground 20. To do. Further, the canopy jack 12 is pressed and loaded, and the ram 12c is pushed out in the direction of the arrow C to push the canopy 12b against the canopy portion of the front body 2A. Further, the side jacks 15 and 15 are loaded under pressure to the rams 15c and 15c.
Is pushed out in the directions of arrows E and F to integrate the machine body 6a with the front body 2A. Then, the fuselage 6a has a front body 2A.
Since it is supported by the surface pressure of the entire peripheral surface of the machine body 6, the machine body 6a is firmly fixed and supported so as not to move in the front body 2A sufficiently against excavation resistance and vibration generated in the boom cutter 9. It In this way, when the machine body 6a is firmly supported by the front body 2A, the excavator 6 is driven so that the cutter 9a abuts on the face 20a, and the boom cutter 9 is moved to the arrows C, D ,.
The rock face 2 is crushed by rocking in the E and F directions while being rotated so that the excavated cross section has a horseshoe shape.
While excavating 0a, the excavator 6 is advanced in the direction of arrow A by the excavation stroke. Simultaneously with or before the excavation of the face 20a, the temporary void 21 'is filled with a primary backing material 26 such as foamed polystyrene beads by a suitable pressure from the arch 25a through the pressure feed pipe 27. To do. As a result, the primary backing material 26 allows the deformation of the natural ground 20 to some extent while preventing skin from falling off from the overburdened portion, and also exerts a stress acting outward from the outer shell 2 along the outer peripheral surface. It is possible to dispersively support the natural ground 20 through the primary backing material 26.

【0015】ところで、上述のように、ブームカッタ9
を用いて軟岩質の地山20を掘進中に硬岩質の地山20
に遭遇した際は、発破により硬岩層を破壊して掘進す
る。そこで、発破用のせん孔を硬岩層に開けるために、
図1に示すように、本発明によるドリルブーム40をブ
ームカッタ9に装着して使用する。まず、ドリルブーム
40のカッタ把持装置41をブームカッタ9のカッタ9
aに取付ける。即ち、図2に示すように、チャック42
の本体42e、42eをピン44の軸心CT2を中心と
して矢印R’、S’方向にカッタ9aの幅以上に屈折さ
せて開口させる。そして、軸心CT2を回転中心CT1
に直交させるような形で、チャック42の内面42c
が、カッタ9aの外周面9dに接するまでチャック42
を挿入する。挿入後、チャック42の本体42e、42
eをピン44の軸心CT2を中心として矢印R”、S”
方向に屈折させて閉口させて把持部42bでカッタ9a
を掴む。その状態で、チャック42のブラケット42
d、42dの穴に把持ピン53を挿入しブラケット42
d、42d同志をナット54で適宜締め付けることによ
り、図1に示すように、掘削機6のブームカッタ9のカ
ッタ9aに対してドリルブーム40を固定することがで
きる。次に、発破用のせん孔位置に合わせて、削岩機5
0のドリル51を位置決めする。即ち、まず、切羽表面
への位置決めとして、メインジャッキ45を矢印K、L
方向に適宜突出後退させることにより、メインブーム4
6が矢印R、S方向に揺動するので、半径方向(図1の
二点鎖線で示した例では、矢印C、D方向)の位置決め
ができる。また、ブームカッタ9を回転軸CT1を中心
として矢印P、Q方向に適宜回転させることにより、メ
インブーム46が矢印P、Q方向に回転するので、円周
方向(紙面垂直方向)の位置決めができる。従って、メ
インジャッキ45による半径方向の動きとブームカッタ
9による円周方向の動きを組合せることにより、任意の
位置に削岩機50を移動させることができる。また、必
要に応じてブームカッタ9を軸心CT5、CT6回りに
上下左右方向(矢印C、D方向及び図3中矢印E、F方
向)に揺動させても良い。次に、削岩機50のドリル5
1の切羽表面への位置決め後、該ドリル51の削岩軸C
T4を発破用のせん孔の穿孔方向と一致するように位置
決めする。即ち、サブジャッキ48を矢印M、N方向に
適宜突出後退させることにより、サブブーム47が矢印
T、U方向に揺動するので、サブブーム47の上面47
aに取付けられた削岩機50のドリル51の削岩軸CT
4を発破用のせん孔の穿孔方向に位置決めできる。この
ようにして、位置決めが完了したら、削岩機50のドリ
ル51を駆動させてせん孔を開ける。以上のように、ブ
ームカッタ9、メインブーム46、サブブーム47を動
かすことにより、発破用のせん孔を必要な個所に設け、
また、該せん孔に爆薬を装填して、発破を掛けることに
より、硬岩質の地山を掘削する。硬岩質の地山の掘削が
完了した後、チャック42を軸心CT2を中心に矢印
R’、S’方向にカッタ9aの幅以上に開放してドリル
ブーム40を掘削機6のカッタ9aから取り外して、掘
削機6により掘削できる状態に復帰する。そして、掘削
機6を用いて、再び軟岩質の地山を掘削する。
By the way, as described above, the boom cutter 9
Using hard rock to excavate soft rocky ground 20
When you encounter, you will blast and destroy the hard rock layer and proceed. Therefore, in order to open a hole for blasting in the hard rock layer,
As shown in FIG. 1, a drill boom 40 according to the present invention is attached to a boom cutter 9 for use. First, the cutter grasping device 41 of the drill boom 40 is attached to the cutter 9 of the boom cutter 9.
Attach to a. That is, as shown in FIG.
The main bodies 42e and 42e are bent and opened in the directions of arrows R'and S'with the center of the axis CT2 of the pin 44 as the center to be wider than the width of the cutter 9a. Then, the axial center CT2 is set to the rotation center CT1.
The inner surface 42c of the chuck 42 so as to be orthogonal to
The chuck 42 until it contacts the outer peripheral surface 9d of the cutter 9a.
Insert. After insertion, the main bodies 42e, 42 of the chuck 42
e is an arrow R ", S" centered on the axial center CT2 of the pin 44
It is bent in the direction to be closed, and the grasping portion 42b is used to cut the cutter 9a.
Grab In that state, the bracket 42 of the chuck 42
Insert the gripping pin 53 into the holes of d and 42d
As shown in FIG. 1, the drill boom 40 can be fixed to the cutter 9a of the boom cutter 9 of the excavator 6 by appropriately tightening the nuts 54 and 42d. Next, rock drill 5 according to the position of the blasting hole.
Position the 0 drill 51. That is, first, the main jack 45 is moved to the arrow K, L for positioning on the surface of the face.
By appropriately projecting and retracting in the direction, the main boom 4
Since 6 swings in the directions of arrows R and S, positioning in the radial direction (directions of arrows C and D in the example shown by the chain double-dashed line in FIG. 1) can be performed. Further, by appropriately rotating the boom cutter 9 in the directions of arrows P and Q about the rotation axis CT1, the main boom 46 rotates in the directions of arrows P and Q, so that positioning in the circumferential direction (direction perpendicular to the plane of the drawing) can be performed. .. Therefore, the rock drill 50 can be moved to an arbitrary position by combining the radial movement of the main jack 45 and the circumferential movement of the boom cutter 9. In addition, the boom cutter 9 may be swung in the vertical and horizontal directions (arrow C and D directions and arrow E and F directions in FIG. 3) around the axial centers CT5 and CT6 as necessary. Next, the drill 5 of the rock drill 50
After the positioning of No. 1 on the face of the face, rock drilling axis C of the drill 51
Position T4 to match the drilling direction of the blasting hole. That is, the sub-boom 47 swings in the directions of arrows T and U by appropriately retracting and retracting the sub-jack 48 in the directions of arrows M and N.
Rock drilling axis CT of drill 51 of rock drilling machine 50 attached to a
4 can be positioned in the drilling direction of the blasting hole. In this way, when the positioning is completed, the drill 51 of the rock drill 50 is driven to open a hole. As described above, by moving the boom cutter 9, the main boom 46, and the sub-boom 47, holes for blasting are provided at necessary locations,
In addition, a hard rock ground is excavated by loading an explosive into the hole and blasting. After the excavation of the hard rock ground is completed, the chuck 42 is opened in the arrow R'and S'directions about the axial center CT2 to the width of the cutter 9a or more to open the drill boom 40 from the cutter 9a of the excavator 6. It is removed and the excavator 6 returns to a state where it can be excavated. Then, the excavator 6 is used to excavate the soft rock ground again.

【0016】このようにして、軟岩質、硬岩質の地山2
0を掘削したら、次に、キャノピージャッキ12、12
及びサイドジャッキ15、15の加圧負荷状態で、スラ
イドジャッキ7Cを駆動することにより駆動シュー7B
を、機体6aに対して矢印A方向に移動ストローク分だ
け先行させる。そして、レッグジャッキ3Aを圧力開放
して外殻レッグ3を縮めて、外殻レッグ3をインバート
25bから浮上させると共に、キャノピージャッキ1
2、12を圧力開放して、キャノピー12b、12bと
共に前胴2Aを該前胴2Aの天蓋部分が一次裏込材26
と別離する形で矢印D方向に降下させる。こうして前胴
2Aを載戴支持した機体6aを、移動ストローク分だけ
先行した駆動シュー7Bに固定シュー7Aを追従させる
形で、矢印A方向に進行させる。次に、前胴2A及び機
体6aの前進時には、後胴2Bは前進せずに取り残され
て、中継胴2Cが前胴2Aの後端から抜け出す形で、前
胴2Aから遠退した状態になっている。そこで、切羽2
aが前進して、新たに切り開かれた部分の地山20が適
宜安定したところで、外殻ジャッキ2Dを駆動すること
により、既設リング16から反力を取る形で該外殻ジャ
ッキ2Dの駆動ストローク分だけ後胴2Bを前胴2A側
に引き寄せる形で、後胴2Bを矢印A方向に移動させ
る。
In this way, soft rocky and hard rocky ground 2
After drilling 0, then the canopy jack 12, 12
The drive shoe 7B is driven by driving the slide jack 7C while the side jacks 15 and 15 are under pressure load.
With respect to the machine body 6a in the direction of arrow A by a moving stroke. Then, the pressure of the leg jack 3A is released, the outer shell leg 3 is contracted, the outer shell leg 3 is floated from the invert 25b, and the canopy jack 1
2 and 12 are pressure-released so that the canopy 12b and 12b together with the front body 2A are attached to the canopy portion of the front body 2A by the primary backing material 26.
And separate it in the direction of arrow D. In this way, the machine body 6a on which the front body 2A is mounted and supported is advanced in the direction of arrow A such that the fixed shoe 7A follows the drive shoe 7B that precedes the moving stroke. Next, when the front torso 2A and the fuselage 6a move forward, the rear torso 2B is left behind without advancing, and the relay torso 2C exits from the rear end of the front torso 2A in a state of retreating from the front torso 2A. ing. Therefore, face 2
When a is moved forward and the ground 20 of the newly cut open portion is appropriately stabilized, by driving the outer shell jack 2D, the driving stroke of the outer shell jack 2D is obtained by taking a reaction force from the existing ring 16. The rear body 2B is moved in the direction of arrow A while pulling the rear body 2B toward the front body 2A side by an amount.

【0017】こうして、後胴2Bを掘進方向に外殻ジャ
ッキ2Dの駆動ストローク分だけ進行させると、構築済
の楕円型リング16のうち最先端、即ち、矢印A方向端
部に位置する敷設楕円型リング16Aと後胴2Bの後
端、即ち、矢印B方向端部分との間には、後胴2Bの前
進分だけ空隙が生じる。そこで、後胴2Bの前進と共
に、或いは先立つように、搬入楕円型リング16Bを、
図4に示すように、トンネル25の坑外より横長状に倒
した状態で搬送台車に搭載して後胴2B内に持ち込む。
そして、エレクタ30を用いて、楕円型リング16の敷
設状態に合うように反転して搬入楕円型リング16Bを
セグメント支持手段29上に設置する形で敷設楕円型リ
ング16Aに接続することにより、トンネル25を構築
していく。
In this way, when the rear body 2B is advanced in the excavation direction by the drive stroke of the outer shell jack 2D, the erected elliptical ring located at the extreme end of the constructed elliptical ring 16, that is, the end portion in the direction of arrow A. A gap is formed between the ring 16A and the rear end of the rear body 2B, that is, the end portion in the arrow B direction, by the amount of the forward movement of the rear body 2B. Therefore, the carry-in elliptical ring 16B is attached so as to move forward with the rear body 2B or in front of it.
As shown in FIG. 4, the tunnel 25 is placed in a horizontally long shape from the outside of the tunnel and mounted on a carrier truck and brought into the rear body 2B.
Then, the erector 30 is used to turn over the elliptical ring 16 so as to match the laid state of the elliptical ring 16 and connect the loaded elliptical ring 16B to the laid elliptical ring 16A so as to be installed on the segment support means 29. Build 25.

【0018】[0018]

【発明の効果】以上説明したように、本発明は、メイン
ブーム46及びサブブーム47等の本体を有し、前記本
体の一端に、カッタ把持装置41等のカッタ把持部を掘
削機6のカッタ9aに対して着脱自在に設け、また、前
記本体に、削岩機50を設けて構成されるので、カッタ
把持部を掘削機6のカッタ9aに対して固定することに
より、削岩機50を掘削機6のカッタ9aに装着できる
ので、掘削機6が削岩機50を支持し得る。また、削岩
機50を装着した状態でカッタ9aを移動させることに
より、カッタ9aと共に削岩機50を移動できるので、
削岩機50を切羽への位置決めすることができる。この
ように、削岩機50が、掘削機6を土台として位置決め
可能なので、ドリルジャンボの代用ができる。従って、
硬岩質の地山に遭遇した際は、搬入済みの軟岩質用の掘
削機6に着脱式ドリルブーム40を装着するだけで発破
用のダイナマイト等を装填するせん孔を開けることが可
能となり、軟岩質用の掘削機6を構築済みのトンネル外
へ搬出して、新たに、ドリルジャンボを搬入する等の掘
削機の入れ替えといった無駄な作業を無くすことが出来
る。
As described above, the present invention has the main body such as the main boom 46 and the sub boom 47, and the cutter gripping portion such as the cutter gripping device 41 is provided at one end of the main body with the cutter 9a of the excavator 6. The rock drill 50 is detachably provided to the main body, and the rock drill 50 is provided in the main body. Therefore, by fixing the cutter gripping portion to the cutter 9a of the drill machine 6, the rock drill 50 is drilled. Since the excavator 6 can be mounted on the cutter 9 a of the machine 6, the rock drill 50 can be supported. Further, since the rock drill 50 can be moved together with the cutter 9a by moving the cutter 9a with the rock drill 50 attached,
The rock drill 50 can be positioned on the face. In this way, the rock drill 50 can be positioned using the excavator 6 as a base, so that a drill jumbo can be substituted. Therefore,
When encountering hard rocky ground, it is possible to open a hole for loading blasting dynamite etc. just by mounting the removable drill boom 40 on the loaded soft rock excavator 6. The quality excavator 6 can be carried out of the constructed tunnel to eliminate wasteful work such as exchanging the excavator such as carrying a new drill jumbo.

【図面の簡単な説明】[Brief description of drawings]

【図1】図1は、本発明によるドリルブームをトンネル
掘進装置に装着したところの一実施例を示した側面図で
ある。
FIG. 1 is a side view showing an embodiment in which a drill boom according to the present invention is attached to a tunnel excavation device.

【図2】図2は、図1に示したドリルブームのカッタ把
持装置の一実施例を示す斜視図である。
FIG. 2 is a perspective view showing an embodiment of a cutter gripping device of the drill boom shown in FIG.

【図3】図3は、図1に示すドリルブームを搭載し得る
トンネル掘進装置の一実施例を示す破断平面図である。
FIG. 3 is a cutaway plan view showing an embodiment of a tunnel excavation device capable of mounting the drill boom shown in FIG.

【図4】図4は、図3に示すトンネル掘進装置の破断側
面図である。
FIG. 4 is a cutaway side view of the tunnel boring device shown in FIG. 3.

【符号の説明】[Explanation of symbols]

6……掘削機 9a……カッタ 41……カッタ把持部(カッタ把持装置) 46……メインブーム 47……サブブーム 50……削岩機 6 ... Excavator 9a ... Cutter 41 ... Cutter gripping part (cutter gripping device) 46 ... Main boom 47 ... Sub-boom 50 ... Rock drill

Claims (1)

【特許請求の範囲】[Claims] 【請求項1】 本体を有し、 前記本体の一端に、カッタ装着部を掘削機のカッタに対
して着脱自在に設け、 また、前記本体に、削岩機を設けて構成した着脱式ドリ
ルブーム。
1. A removable drill boom having a main body, a cutter mounting portion being detachably attached to one end of the main body with respect to a cutter of an excavator, and a rock drilling machine being provided in the main body. ..
JP16381091A 1991-06-07 1991-06-07 Detachable drill-boom Pending JPH0571291A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP16381091A JPH0571291A (en) 1991-06-07 1991-06-07 Detachable drill-boom

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP16381091A JPH0571291A (en) 1991-06-07 1991-06-07 Detachable drill-boom

Publications (1)

Publication Number Publication Date
JPH0571291A true JPH0571291A (en) 1993-03-23

Family

ID=15781143

Family Applications (1)

Application Number Title Priority Date Filing Date
JP16381091A Pending JPH0571291A (en) 1991-06-07 1991-06-07 Detachable drill-boom

Country Status (1)

Country Link
JP (1) JPH0571291A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003269066A (en) * 2002-03-15 2003-09-25 Maeda Corp Breaker arm device of excavator

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003269066A (en) * 2002-03-15 2003-09-25 Maeda Corp Breaker arm device of excavator

Similar Documents

Publication Publication Date Title
US3604754A (en) Apparatus for and method of driving a tunnel shaft
JP6685214B2 (en) Tunnel excavation method and tunnel excavator
JPH0571291A (en) Detachable drill-boom
JPH0642285A (en) Tunnelling machine for reaming
JP3250873B2 (en) Tunnel boring machine
JPH0579297A (en) Supporting method for elliptical ring
JP2940402B2 (en) Rock tunnel excavation method using arch machine
JPH09328999A (en) Method for excavating large scale underground cavity
JP3286728B2 (en) Excavation method for rock etc.
JPH04330194A (en) Excavating machine for modification of tunnel
JPH06102954B2 (en) Vertical shaft construction method
JP2879283B2 (en) Preparation method for pretreatment work such as ground improvement in tunnel excavation
JPH0633685A (en) Tunnel pilot excavation method and pilot excavation pipe anchor device
JP4318112B2 (en) Tunnel excavator
JPH05239997A (en) Eliptical ring inversion device
JPH05321573A (en) Tunnel excavator
JP3316373B2 (en) Tunnel excavator and excavation method
JPH11117683A (en) Method for discharging muck from tunnel boring machine and method for replacing muck-discharge means
JPH0571293A (en) Tunnel construction method
JPH07197770A (en) Tunnel construction method and shield device used therefor
JPH05263597A (en) Shielding device
JP2020101086A (en) Tunnel excavator and method for spraying concrete or mortar
JPH05239998A (en) Eliptical ring inversion device
JPH04347298A (en) Tunnel excavator
JPH06346685A (en) Reaction force bearing structure for inclined shaft excavator