JPH05321281A - Bar arranging method for steel foundation column and underground beam - Google Patents
Bar arranging method for steel foundation column and underground beamInfo
- Publication number
- JPH05321281A JPH05321281A JP16817792A JP16817792A JPH05321281A JP H05321281 A JPH05321281 A JP H05321281A JP 16817792 A JP16817792 A JP 16817792A JP 16817792 A JP16817792 A JP 16817792A JP H05321281 A JPH05321281 A JP H05321281A
- Authority
- JP
- Japan
- Prior art keywords
- column
- underground beam
- hole
- steel
- steel foundation
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Landscapes
- Foundations (AREA)
Abstract
Description
【0001】[0001]
【産業上の利用分野】この発明は、鉄骨基礎柱と基礎の
地中ばりの鉄筋配筋工法に関する。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a reinforcing bar arranging method for steel foundation columns and foundation underground beams.
【0002】[0002]
【従来の技術】従来、鉄骨基礎柱を使用した基礎構造は
なかった。2. Description of the Related Art Conventionally, there has been no foundation structure using steel foundation columns.
【0003】[0003]
【発明が解決しようとする課題】鉄骨基礎柱A(1)と
地中ばりの主筋(3)との容易かつ経済的な主筋の配筋
接続方法がなかったSUMMARY OF THE INVENTION There has been no easy and economical connection method for the reinforcing bar of the steel foundation column A (1) and the reinforcing bar (3) of the underground beam.
【0004】[0004]
【課題を解決するための手段】鉄骨基礎柱A(1)に縦
長の貫通穴(2)を設ける。そして、地中ばりの主筋
(3)を貫通穴(2)に入れ、配筋をする。本発明は、
以上の構成よりなる地中ばりの鉄筋配筋方法である。Means for Solving the Problems A vertically long through hole (2) is provided in a steel foundation column A (1). Then, the main bar (3) of the underground beam is put into the through hole (2) to arrange the bar. The present invention is
This is a method of arranging reinforcing bars in the underground beam having the above configuration.
【0005】[0005]
【作 用】地中ばりの主筋(3)が鉄骨基礎柱A(1)
を貫通するので鉄筋配筋が容易化し、地中ばりと基礎柱
とを一体化構造にできる。[Operation] The main bar (3) of the underground beam is the steel foundation column A (1)
Since it penetrates through, the reinforcing bar arrangement is facilitated, and the underground beam and the foundation pillar can be integrated.
【0006】[0006]
【実施例】以下、木発明の実施例について説明する。 (イ)縦長の貫通穴(2)を設けた鉄骨基礎柱A(1)
を鉄骨柱の中心となる位置に安定した状態で据え付け
る。 (ロ)次に、地中ばりの主筋(3)を貫通穴(2)に挿
入して配筋をする。 (ハ)そして、地中ばりのあばら筋(7).柱の主筋
(5).柱の帯筋(6)などの鉄筋類を配筋すれば鉄筋
工事が完了する。Embodiments of the invention will be described below. (A) Steel-framed foundation pillar A (1) provided with a vertically long through hole (2)
Install in a stable position at the center of the steel column. (B) Next, the main bar (3) of the underground beam is inserted into the through hole (2) to arrange the bar. (C) And the stirrups in the underground (7). Pillar main line (5). Reinforcement work is completed by arranging the reinforcements such as the strips (6) of the columns.
【0007】[0007]
【考案の効果】(イ)地中ばりにハンチを設ける事なく
基礎柱と地中ばりとを接続できる。 (ロ)鉄骨柱の応力を理想的に地中ばりに伝達できる。[Advantages of the Invention] (a) The foundation pillar and the underground beam can be connected without providing a haunch on the underground beam. (B) The stress of the steel column can be ideally transmitted to the underground beam.
【図1】本発明の配筋後の立面図であるFIG. 1 is an elevational view of the present invention after reinforcement.
【図2】本発明の配筋後のA〜A断面平面図である。FIG. 2 is a cross-sectional plan view taken along line AA of the present invention after bar arrangement.
1.鉄骨基礎柱A 2.貫通穴 3.地中ばりの主筋 4.位置出し棒 5.柱の主筋 6.柱の帯筋 7.あばら筋 1. Steel foundation column A 2. Through hole 3. Underground beam main line 4. Positioning stick 5. Pillars of pillar 6. Pillar stirrup 7. Stirrups
Claims (1)
する鉄骨基礎柱Aと地中ばりの配筋工法に関する。The present invention relates to a method for arranging steel foundation columns A and underground beams used in application number Japanese Patent Application No. 3-259940.
け、貫通穴(2)に地中ばりの主筋(3)を貫通させた
鉄筋配筋工法。1. A reinforcing bar arranging method in which a through hole (2) is provided in a steel foundation column A (1) and a main bar (3) of an underground beam is passed through the through hole (2).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP16817792A JPH05321281A (en) | 1992-05-18 | 1992-05-18 | Bar arranging method for steel foundation column and underground beam |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP16817792A JPH05321281A (en) | 1992-05-18 | 1992-05-18 | Bar arranging method for steel foundation column and underground beam |
Publications (1)
Publication Number | Publication Date |
---|---|
JPH05321281A true JPH05321281A (en) | 1993-12-07 |
Family
ID=15863223
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP16817792A Pending JPH05321281A (en) | 1992-05-18 | 1992-05-18 | Bar arranging method for steel foundation column and underground beam |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPH05321281A (en) |
-
1992
- 1992-05-18 JP JP16817792A patent/JPH05321281A/en active Pending
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JPH05321281A (en) | Bar arranging method for steel foundation column and underground beam | |
JPH0726624A (en) | Joint method of steel encased reinforced concrete column in precast method | |
JPH05346039A (en) | Column-beam joint structure | |
JP2000320057A (en) | Flat slab using steel pipe concrete column and construction for the slab | |
JPH06272311A (en) | Connecting structure of precast concrete column and steel framed beam | |
JP2000073448A (en) | Connection method and structure for precast concrete beam and column | |
JP2976255B2 (en) | Column and beam joint structure | |
JP2635872B2 (en) | How to build a composite structure | |
JPH047435A (en) | Steel framed reinforced concrete rigid-framed structure using partially precast beam | |
JPS62260967A (en) | Method for assembling reinforcement for reinforced concrete structure | |
JPH0525886A (en) | Composite beam | |
JPS6111399Y2 (en) | ||
JPH01137032A (en) | Method of lap joint construction of main reinforcement in post and beam joining section | |
JPS62178634A (en) | Framework construction method of structure | |
JPH056336Y2 (en) | ||
JPH07113260A (en) | Method for connecting column and beam | |
JPH0715183B2 (en) | Connection structure of precast steel concrete columns | |
JPH10299260A (en) | Earthquake-resistant improving method for existing building by square type frame | |
JPS6351529A (en) | Construction of reinforced concrete underground beam and slab | |
JPS62228551A (en) | Pc half pillar | |
JPH06257226A (en) | Joint construction of square steel pipe post or square steel pipe concrete post | |
JPS62121250A (en) | Pillar/beam connection structure | |
JP2556757B2 (en) | Reinforcement structure of column / beam connection and its construction method | |
JPS58204246A (en) | Construction of reinforced concrete structure | |
JPH04221149A (en) | Joint structure of steel pipe pillar and slab in flat slab structure |