JPH05290054A - Management system at workshop - Google Patents
Management system at workshopInfo
- Publication number
- JPH05290054A JPH05290054A JP9405092A JP9405092A JPH05290054A JP H05290054 A JPH05290054 A JP H05290054A JP 9405092 A JP9405092 A JP 9405092A JP 9405092 A JP9405092 A JP 9405092A JP H05290054 A JPH05290054 A JP H05290054A
- Authority
- JP
- Japan
- Prior art keywords
- plan
- instruction
- management system
- information
- management
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02P—CLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
- Y02P90/00—Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
- Y02P90/30—Computing systems specially adapted for manufacturing
Landscapes
- Multi-Process Working Machines And Systems (AREA)
- General Factory Administration (AREA)
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Abstract
Description
【0001】[0001]
【産業上の利用分野】本発明は、生産情報管理システム
に利用し、その下位階層に位置づけられて作業計画管理
における負荷計画と実行計画の非同期を解消する製造現
場管理システムに関する。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a manufacturing site management system which is used in a production information management system and which is positioned in a lower hierarchy thereof to eliminate the asynchronism between load plans and execution plans in work plan management.
【0002】[0002]
【従来の技術】従来、工場などの製造現場管理システム
では、その作業計画あるいは作業指示を生産管理担当
者、製造ショップの職長等の専従者の人手不足の管理に
委ねている。2. Description of the Related Art Conventionally, in a manufacturing site management system of a factory or the like, the work plan or work instruction is entrusted to the management of labor shortage of a production management person in charge and a full-time person such as a foreman of a manufacturing shop.
【0003】図2に示すように、生産管理担当者〔M〕
は、いつまでに何をどれだけ生産するかの生産計画〔2
A〕の週計画表〔2B〕と、製造オーダに対する使用部
品の充足補充である解除予定をもとに解除オーダを決定
し、そして、納期に間に合うように解除要求書〔2C〕
を作成し、倉庫管理システム〔2D〕に対して、解除指
示を行う。As shown in FIG. 2, a person in charge of production management [M]
Is the production plan [2]
The release order is determined based on the weekly schedule [2B] of [A] and the release schedule that is the supplement of the used parts to the production order, and the release request [2C] in time for the delivery date.
Is created and a cancellation instruction is given to the warehouse management system [2D].
【0004】3日後には倉庫より部品と出庫リスト〔2
E〕が送付され、製造部では週計画表〔2F〕と照合の
上、又、保有工数を考慮して2〜3日先の作業予定を立
案する。After 3 days, the parts and shipping list [2
E] will be sent, and the manufacturing department will collate it with the weekly schedule [2F] and, in consideration of the number of man-hours possessed, will make a work schedule 2-3 days ahead.
【0005】[0005]
【発明が解決しようとする課題】このように従来の人手
中心の製造現場管理システムでは、週計画の総量を複数
回に分け、解除予定表〔2G〕をもとに解除オーダを決
定し、さらに、決定した解除オーダに基づく解除要求書
〔2C〕の作成と、倉庫管理システム〔2D〕に対する
解除指示を行う。又、製造ショップに対する製造指示を
行う必要がある。これらを実施しても結果的にみると、
日単位に負荷のアンバランスが生じ、製造ショップにて
作業の再段取、すなわち、再計画が必要となる問題があ
る。As described above, in the conventional man-made manufacturing site management system, the total amount of the weekly plan is divided into a plurality of times, the release order is determined based on the release schedule [2G], and , Creates a release request [2C] based on the determined release order, and issues a release instruction to the warehouse management system [2D]. It is also necessary to give manufacturing instructions to the manufacturing shop. As a result of implementing these,
There is a problem that the load is unbalanced on a daily basis, and the work shop needs to be re-planned, that is, re-planned.
【0006】本発明は、このような課題を解決するもの
であり、負荷計画と実行計画の非同期を解消し、日別実
行計画立案工数、管理工数の削減とともに、情報精度及
び情報活用が効果的に向上する製造現場管理システムを
提供することを目的とする。The present invention solves such a problem, eliminates the asynchronization of the load plan and the execution plan, reduces the daily execution plan drafting man-hours, management man-hours, and is effective in information accuracy and information utilization. It is intended to provide a manufacturing site management system that is improved.
【0007】[0007]
【課題を解決するための手段】この目的を達成するため
に、本発明の製造現場管理システムは、週単位計画に基
づいて所要工数を明示したワークショップ単位の山積表
を作成する第1の処理と、部品充足状態と保有工数を加
味した日別実行計画を立案する第2の処理と、オンライ
ン処理による着手日調整処理と自動処理を行う第3の処
理とを含み、負荷計画と実行計画の非同期を解消する構
成としている。In order to achieve this object, the manufacturing site management system of the present invention is a first process for creating a mountain table for each workshop in which the required man-hours are specified based on a weekly plan. Of the load plan and execution plan, including a second process for formulating a daily execution plan that takes into account the component satisfaction state and the number of man-hours held, and a third process for performing the start date adjustment process by online process and the automatic process. It has a configuration that eliminates asynchrony.
【0008】[0008]
【実施例】以下、本発明の製造現場管理システムの実施
例について図面をもとに説明する。図1は実施例の構成
を示している。DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS An embodiment of the manufacturing site management system of the present invention will be described below with reference to the drawings. FIG. 1 shows the configuration of the embodiment.
【0009】図1において、この例は生産管理システム
〔A〕と製造現場管理システム〔B〕で概略構成されて
いる。In FIG. 1, this example is roughly constituted by a production management system [A] and a manufacturing site management system [B].
【0010】製造現場管理システム〔B〕にあって、山
積作成表〔1〕は、負荷管理機能であり、生産管理シス
テム〔A〕より、4〜8週先の計画情報を受けて蓄積す
る。又、変更情報発生の都度更新を行う。In the manufacturing site management system [B], the pile creation table [1] is a load management function and receives and stores plan information for 4 to 8 weeks ahead from the production management system [A]. Also, it is updated each time change information is generated.
【0011】この計画情報をもとにCAMデータベース
を参照し、着手の2〜3週前に山積表を出力する。この
山積表により、何をいくつ生産するかの総量の把握、そ
れに要す所要工数、図面の有無、NC情報の有無及び設
計変化情報等の表示により製造リソースの確保、準備を
行う。Based on this plan information, the CAM database is referred to, and a mountain table is output 2-3 weeks before the start. Based on this pile table, the total amount of what is produced and what is to be produced is grasped, the required man-hours required, presence / absence of drawings, presence / absence of NC information, design change information, and the like are secured and manufacturing resources are secured and prepared.
【0012】図1中、日単位計画立案〔2〕は、日別実
行計画立案機構であり、計画情報と部品充足情報及び保
有工数テーブルを入力し、現在日+2日先、すなわち、
出庫リードタイムより先1週間分について、日単位計画
を自動的に作成する。In FIG. 1, a daily unit plan [2] is a daily execution plan planning mechanism, which inputs plan information, parts sufficiency information, and a possessed man-hour table, and the present date + 2 days ahead, that is,
Daily plan will be automatically created for one week after the delivery lead time.
【0013】その実案ロジックは、第1に対象データの
抽出、すなわち、計画情報より完了予定日≦日単位計画
立案最終日のものを抜き出す。第2に欠品のオーダも含
む抽出されたデータについての所要工数をサマリーす
る。第3にサマリーした所要工数と保有工数テーブル上
の保有工数を比較する。この比較は、保有に見合う分だ
けの日単位に均等割付る所要工数≧保有工数であり、さ
らに、計画立案開始日より保有に見合う分だけ前倒し割
付の所要工数<保有工数である。Firstly, the actual draft logic extracts target data, that is, extracts from the plan information the date of planned completion date ≦ day unit plan final date. Secondly, the required man-hours for the extracted data including the order of missing items are summarized. Thirdly, the required man-hours summarized and the man-hours possessed on the possessed man-hour table are compared. In this comparison, the required number of man-hours that are evenly allocated on a daily basis to the extent commensurate with the possession is equal to or greater than the required man-hours, and the required man-hours for the forward allocation corresponding to the possession from the start date of the planning are less than the required man-hours.
【0014】但し、いずれも割付方式を決定するまで
は、欠品オーダもその処理対象とするが、実際の割付処
理では欠品分は除き割り付ける。However, in all cases, the shortage product order is subject to processing until the allocation method is determined, but in the actual allocation processing, the shortage product is excluded and allocated.
【0015】着手日の設定である日単位の割付が完了
後、オーダ単位の着手日変更の微調整が必要であれば実
施する。すなわち、優先順又は欠品対応を行う。After the completion of the allocation on a daily basis, which is the setting of the commencement date, if necessary, a fine adjustment of the change of the initiation date on an order basis is performed. That is, the priority order or the lack-of-item correspondence is performed.
【0016】図1中、解除/製造指示〔3〕は、日単位
計画立案〔2〕により、日単位の計画が決定した場合、
現在日+2日先の計画立案開始日を、今日の解除指示分
とし、倉庫管理へ磁気ベースで自動解除機能を利用して
リンクし、さらに、製造指示表により製造ショップへの
作業指示を行う。In FIG. 1, the release / manufacturing instruction [3] indicates that the daily unit plan is determined by the daily unit planning [2].
The planning start date of the current date + 2 days ahead is used as the cancellation instruction for today, and it is linked to the warehouse management by using the magnetically-based automatic cancellation function, and the work instruction is given to the manufacturing shop by the manufacturing instruction table.
【0017】このように、この実施例では、部品充足状
況と保有工数を加味した日別実行計画立案工数、例え
ば、1日当たり3時間の時間削除ができる。さらに、日
別実行計画に基づく自動解除指示と製造指示による管理
工数、例えば、1日当たり2時間の削減ができる。As described above, in this embodiment, it is possible to delete the number of man-hours for formulating a daily execution plan, which takes into consideration the condition of parts satisfaction and the number of man-hours, for example, 3 hours per day. Further, it is possible to reduce the management man-hours by the automatic release instruction based on the daily execution plan and the production instruction, for example, 2 hours per day.
【0018】[0018]
【発明の効果】以上の説明から明らかなように、本発明
の製造現場管理システムは、従来の人手中心の管理から
EDP中心に移行し、負荷計画と実行計画の非同期を解
消するため、部品充足状況と保有工数を加味した日別実
行計画立案工数の削減及び日別実行計画に基づく自動解
除指示と製造指示による管理工数の削減ができるという
効果を有する。As is apparent from the above description, the manufacturing site management system of the present invention shifts from the conventional manual-centered management to the EDP-based management and eliminates the asynchronism between the load plan and the execution plan. This has the effect of reducing the number of man-hours for formulating a daily execution plan in consideration of the situation and the number of man-hours, and reducing the man-hours required for management by an automatic cancellation instruction and a manufacturing instruction based on the daily execution plan.
【0019】さらに、情報の磁気化及び一元管理を行う
ようにしているため、情報精度及び情報活用が効果的に
向上するという効果を有する。Further, since the information is magnetized and the information is centrally managed, there is an effect that the information accuracy and the information utilization are effectively improved.
【図1】本発明の製造現場管理システムの実施例におけ
る処理内容を示すブロック図である。FIG. 1 is a block diagram showing processing contents in an embodiment of a manufacturing site management system of the present invention.
【図2】従来の製造現場管理システムの処理内容を示す
ブロック図である。FIG. 2 is a block diagram showing the processing contents of a conventional manufacturing site management system.
〔A〕 生産管理システム 〔B〕 製造現場管理システム 〔1〕 山積表作成 〔2〕 日単位計画立案 〔3〕 解除/製造指示 [A] Production management system [B] Manufacturing site management system [1] Mountain table creation [2] Daily planning [3] Cancellation / manufacturing instruction
Claims (1)
ワークショップ単位の山積表を作成する第1の処理と、 部品充足状況と保有工数を加味した日別実行計画を立案
する第2の処理と、 オンライン処理による着手日調整処理と自動処理を行う
第3の処理と、とを含み、負荷計画と実行計画の非同期
を解消することを特徴とする製造現場管理システム。1. A first process of creating a pile table for each workshop in which the required man-hours are specified based on a weekly plan, and a second execution plan for preparing a daily execution plan that considers the part satisfaction status and man-hours held. A manufacturing site management system, characterized by including processing, and a third processing for performing an on-boarding date adjustment processing and an automatic processing by an online processing, and eliminating the asynchronism between a load plan and an execution plan.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP9405092A JPH05290054A (en) | 1992-04-14 | 1992-04-14 | Management system at workshop |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP9405092A JPH05290054A (en) | 1992-04-14 | 1992-04-14 | Management system at workshop |
Publications (1)
Publication Number | Publication Date |
---|---|
JPH05290054A true JPH05290054A (en) | 1993-11-05 |
Family
ID=14099731
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP9405092A Pending JPH05290054A (en) | 1992-04-14 | 1992-04-14 | Management system at workshop |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPH05290054A (en) |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS5815650A (en) * | 1981-07-22 | 1983-01-29 | Hitachi Ltd | Job-shop type production system |
JPH0271960A (en) * | 1988-09-01 | 1990-03-12 | Hokuriku Nippon Denki Software Kk | Heaping method for limited load in production control |
JPH03281154A (en) * | 1990-03-30 | 1991-12-11 | Nec Corp | Production load levelling system |
JPH0453657A (en) * | 1990-06-18 | 1992-02-21 | Sekisui Chem Co Ltd | Simulation method for multiple kind mixed production line |
-
1992
- 1992-04-14 JP JP9405092A patent/JPH05290054A/en active Pending
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS5815650A (en) * | 1981-07-22 | 1983-01-29 | Hitachi Ltd | Job-shop type production system |
JPH0271960A (en) * | 1988-09-01 | 1990-03-12 | Hokuriku Nippon Denki Software Kk | Heaping method for limited load in production control |
JPH03281154A (en) * | 1990-03-30 | 1991-12-11 | Nec Corp | Production load levelling system |
JPH0453657A (en) * | 1990-06-18 | 1992-02-21 | Sekisui Chem Co Ltd | Simulation method for multiple kind mixed production line |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP2789801B2 (en) | Production plan creation method | |
JP2828526B2 (en) | Automatic generation of production line control information | |
DE4222755B4 (en) | Numerical control unit | |
Timpe | Solving planning and scheduling problems with combined integer and constraint programming | |
JPH09153090A (en) | Method and device for forming working process production plan | |
CN101794147A (en) | Shop operation dynamic dispatching method based on disturbance event driving | |
Olsmats et al. | Industrial dynamics model building of a close-coupled production-distribution system | |
CN112818189B (en) | Visual processing procedure list scheduling method, system and platform | |
CN114299764A (en) | Linkage change consistency method for civil aviation flight time plan and advance flight plan | |
Połoński et al. | Impact of baseline terms on the course of critical paths and time buffers in the modified Goldratt’s method | |
JPH05290054A (en) | Management system at workshop | |
JP2004054678A (en) | Method and system for managing production | |
Henseler | Reaktion: a system for event independent reactive scheduling | |
CN114862122B (en) | Workshop scheduling method, system and equipment based on APS | |
CN115700638A (en) | Workshop scheduling optimization method | |
US20040193299A1 (en) | System and method for scheduling production of molds | |
JPH05174030A (en) | Job shop scheduling expert system | |
JP4318162B2 (en) | Production schedule planning management method and production schedule planning management program | |
DE19911699A1 (en) | Process sequences monitoring and control method, includes capacity planning for use of human resource and performance of production devices and machines, especially robots | |
JPH11156679A (en) | Production scheduling device and recording medium recording production scheduling program | |
Miles et al. | Scheduling of a manufacturing cell with simulation | |
DE102012202802A1 (en) | Method for selecting proposed solution for predetermined process for dynamic optimization function for e.g. production control in industrial enterprise, involves selecting proposed solution based on rating of fragments of current solution | |
JPH0724706A (en) | Production order control system | |
JP2859402B2 (en) | How to make a casting schedule | |
Smith et al. | A comparison of two intelligent scheduling systems for flexible manufacturing systems |