JPH05263529A - Supply method of building member for prefabricated structure - Google Patents

Supply method of building member for prefabricated structure

Info

Publication number
JPH05263529A
JPH05263529A JP6267092A JP6267092A JPH05263529A JP H05263529 A JPH05263529 A JP H05263529A JP 6267092 A JP6267092 A JP 6267092A JP 6267092 A JP6267092 A JP 6267092A JP H05263529 A JPH05263529 A JP H05263529A
Authority
JP
Japan
Prior art keywords
floor
site
building
wall
panels
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP6267092A
Other languages
Japanese (ja)
Inventor
Shiyuuji Ooashi
修次 大芦
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Misawa Homes Co Ltd
Original Assignee
Misawa Homes Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Misawa Homes Co Ltd filed Critical Misawa Homes Co Ltd
Priority to JP6267092A priority Critical patent/JPH05263529A/en
Publication of JPH05263529A publication Critical patent/JPH05263529A/en
Pending legal-status Critical Current

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

PURPOSE:To promote work efficiency in a construction site, to reduce execution misses as low as possible and to enable the control of the site. CONSTITUTION:When building members for a prefabricated structure are supplied to a construction site, and the building members are divided into a plurality of blocks in order of assembly in advance. The blocks of the building members are subsequently supplied to a construction site (Y) in accordance with the progress of work.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明はプレハブ用建築部材を現
場へ供給する供給方法に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for supplying prefabricated building members to a site.

【0002】[0002]

【従来の技術】プレハブ住宅は、例えば床あるいは壁用
のパネル等の建築部材の大部分を予め工場で製作加工し
ておき、それらを現場まで搬送して互いに連結させて組
み立てることで所望の建築物を得ようとするものであ
る。したがって、通常、建築現場には、床パネルや壁パ
ネル、屋根パネル等の種々の建築部材が運び込まれてお
り、作業員はこれら建築部材から工程順に合わせて必要
な部材を選び出して基礎上の所定箇所等まで運んで組み
立てていた。
2. Description of the Related Art In a prefabricated house, most of building members such as floor or wall panels are manufactured and processed in a factory in advance, and they are transported to a site and connected to each other to be assembled into a desired building. It is about trying to get things. Therefore, various building members such as floor panels, wall panels, roof panels, etc. are usually brought into the construction site, and the worker selects the necessary members from these building members according to the order of the process, and selects them on the foundation. I was carrying it to places and assembling it.

【0003】[0003]

【発明が解決しようとする課題】しかしながら、上記し
た建築部材の供給方法では、作業員が、雑多に置かれた
多数の建築部材から現在の工程に必要な部材のみを選び
出す作業を行わなければならず、これら近似するものが
多数ある建築部材の中から必要な部材のみを選び出す作
業は非常に面倒であり、これがために現場の作業効率が
悪く工期が遅れる、施工ミスを引き起こす等の不具合が
生じがちであった。
However, in the above-mentioned method of supplying building members, the worker must perform the work of selecting only the members necessary for the current process from a large number of the building members placed in various ways. However, it is very troublesome to select only the necessary members from the building members that have many similar ones, and this causes inconvenience such as poor work efficiency at the site, delay of construction period, and construction errors. It was apt.

【0004】本発明は上記事情に鑑みてなされたもの
で、現場の作業効率の向上が図れかつ施工ミスの発生を
極力低減することができ、しかも現場管理が容易になる
プレハブ用建築部材の供給方法を提供することを目的と
するものである。
The present invention has been made in view of the above circumstances, and is to supply a prefabricated building member capable of improving work efficiency on site, minimizing the occurrence of construction errors, and facilitating site management. It is intended to provide a method.

【0005】[0005]

【課題を解決するための手段】本発明では、係る目的を
達成するために、プレハブ用建築部材を現場へ供給する
に際し、それら建築部材を組立順にしたがい予め複数組
みに分けてブロック化しておき、それらブロック化した
建築部材を工程に合わせて順に現場へ供給することを特
徴としている。
According to the present invention, in order to achieve the above object, when supplying prefabricated building members to a site, the building members are divided into a plurality of groups in advance according to the assembling order, and are divided into blocks. The feature is that these block-shaped building materials are sequentially supplied to the site according to the process.

【0006】[0006]

【作用】本発明では、現場の各工程に応じてその工程で
必要な建築部材のみを、予めブロック化した建築部材か
ら選んで供給することができ、したがって、多数ある建
築部材から必要な部材のみを選んで一々取り出す面倒な
作業を行う必要はなくなり、現場での作業効率が向上す
る。
According to the present invention, only the building members required in the process can be selected and supplied from the pre-blocked building members according to each process at the site, and therefore, only the necessary members can be selected from a large number of building members. It is no longer necessary to select and pick up one by one, and the work efficiency in the field improves.

【0007】また、上記のように各工程に必要な建築部
材が予めブロック化されて供給されるため、現場での作
業ミスが少なくなり、質の向上および現場管理が容易に
なる。
Further, as described above, since the building members necessary for each process are pre-blocked and supplied, work mistakes at the site are reduced, quality is improved and site management is facilitated.

【0008】[0008]

【実施例】以下、本発明の一実施例を図1ないし図14
を参照して説明する。図1は、本発明の概要を示すもの
で、現場が狭く、近くに仮置場を設けなければならない
ような施工現場に本発明を適用した例を示すものであ
る。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENT An embodiment of the present invention will be described below with reference to FIGS.
Will be described. FIG. 1 shows an outline of the present invention, and shows an example in which the present invention is applied to a construction site where the site is small and a temporary storage site must be provided nearby.

【0009】工場等で予め製作加工された床パネル等の
建築部材は、トラックT1に荷積みされて仮置場Xまで
搬送される。建築部材はトラックT1に荷積みされる時
点で、既に組立順にしたがい複数組みに分けてブロック
化されている。この実施例では、図10にも示すよう
に、4つに大ブロック化され、それら大ブロック化され
たものはさらにそれぞれ4個あるいは6個に小ブロック
化[イ]〜[ソ]されている。そして小ブロック化され
たものが個々に防水シートSによって梱包されている。
Building members such as floor panels, which have been manufactured and processed in advance in a factory or the like, are loaded onto a truck T1 and transported to a temporary storage space X. When the building members are loaded on the truck T1, the building members are already divided into a plurality of sets according to the assembling order and are divided into blocks. In this embodiment, as shown in FIG. 10, four large blocks are formed, and the large blocks are further divided into four or six small blocks [a] to [so]. .. The small blocks are individually packaged in the waterproof sheet S.

【0010】なお、小ブロック化された建築部材はここ
では防水シートSで梱包されているが、コンテナ等の防
水機能を有する函に個々に収納させてもよい。
Although the building members made into small blocks are packed with the waterproof sheet S here, they may be individually stored in a box having a waterproof function such as a container.

【0011】図10は上記のように大ブロック化された
建築部材が、パレットP上に積み上げられてトラックT
1によって搬送される状態を示している。図1の仮置場
Xでは、上記のような形態で搬送された建築部材が荷降
ろしされた状態を示す。この仮置場Xでは、トラックT
1の荷台から順に荷降ろしされる関係上、各小ブロック
化されたものは、図10で示す状態に対して上下逆にな
る。
In FIG. 10, the building members, which have been made into large blocks as described above, are piled up on a pallet P, and the truck T is used.
1 shows a state of being transported by 1. In the temporary storage area X in FIG. 1, the building members conveyed in the above-described form are unloaded. In this temporary storage area X, the truck T
Due to the fact that the loading platform is unloaded from the first loading platform, each of the small blocks is turned upside down with respect to the state shown in FIG.

【0012】すなわち、図1の仮置場Xにおける最も左
側に位置する大ブロックで見てみると、トラックT1上
では、上側に[ヨ]〜[ソ]で示す軸組材等がまた下側
に1階の床パネル[イ],[ロ]がそれぞれ位置してい
るが、仮置場Xで荷降ろしされた段階では、上側に床パ
ネル[イ],[ロ]がまた下側に軸組材[ヨ]〜[ソ]
が位置するように逆に配置される。
That is, when looking at the large block located on the leftmost side in the temporary storage area X in FIG. 1, on the track T1, the frame members and the like indicated by [Yo] to [So] are on the upper side and on the lower side. The floor panels [a] and [b] on the first floor are respectively located, but when unloaded at the temporary storage area X, the floor panels [a] and [b] are on the upper side and the frame members are on the lower side. [Yo]-[So]
Are placed in reverse so that they are located.

【0013】このように、仮置場Xでの荷降ろし段階で
上下逆になるので、トラックT1に荷積みするときには
これを予め考慮し、先に使用する建築部材が下側に来る
ように荷積みする。なお、図1において[ネ],[ナ]
はそれぞれ小物部品を収納する函を示す。
As described above, since the cargo is unloaded at the temporary storage area X, it is turned upside down. Therefore, when loading on the truck T1, this should be taken into consideration in advance so that the building member used first comes to the lower side. To do. In addition, in FIG. 1, [ne], [na]
Shows boxes for storing small parts.

【0014】そして、この仮置場Xから、現場Yの工程
に合わせて、前記各ブロック化された建築部材[イ]〜
[ナ]が、小トラックT2を介して順に現場Yへ供給さ
れる。すなわち、小ブロック化された建築部材[イ]〜
[ソ]は、[イ],[ロ],[ハ]…の順で現場Yへ供
給される。
From the temporary storage area X, the building members [a] to
[Na] is sequentially supplied to the site Y via the small truck T2. That is, building blocks [a]
[SO] is supplied to the site Y in the order of [A], [B], [C] ....

【0015】上記小ブロック化した建築部材の分類分け
の理由について、現場Yでの作業順にしたがい具体的に
説明する。
The reason for classifying the building blocks into the small blocks will be specifically described in the order of work at the site Y.

【0016】図2はこれから構築しようとする建物の1
階の床パネルの配置図ある。この工程では、Aー1〜A
ー28で示す合計28個の床パネルが使用されるとも
に、それらパネルの外周に配置される半土台、あるいは
パネルを使用されない箇所に配置される土台を構成する
角材100等が使用される。
FIG. 2 shows one of the buildings to be constructed.
It is a layout drawing of the floor panel of the floor. In this process, A-1 to A
A total of 28 floor panels indicated by -28 are used, and a semi-base which is arranged on the outer periphery of these panels, or a square timber 100 which constitutes a base where the panels are not used is used.

【0017】1階で使用される床パネルAー1〜Aー2
8は、図11および図12中[イ],[ロ]で示す如
く、施工順であってかつ先に使用するものが上側に来る
ように、予め積み上げられて梱包されている。また、こ
のように積み上げられた床パネルの間に形成される隙間
(上下の床パネルどうしの大きさが異なる場合に隙間が
形成される)には、前記土台あるいは半土台を構成する
角材100や台輪102等が適宜嵌め込まれている。こ
れは、搬送中等において、梱包された荷自体がガタつか
ないようにするためである。
Floor panels A-1 to A-2 used on the first floor
As shown by [a] and [b] in FIGS. 11 and 12, 8 is pre-stacked and packaged so that the one to be used in the order of construction and the one to be used first is on the upper side. In addition, in the gap formed between the floor panels stacked in this way (a gap is formed when the upper and lower floor panels have different sizes), the timber 100 that constitutes the base or the semi-base is The pedestal wheel 102 and the like are properly fitted. This is to prevent the packed load itself from rattling during transportation or the like.

【0018】現場Yでは、予め基礎ができ上がる前に、
これら小ブロック化された建築部材[イ],[ロ]が現
場Yに運び込まれ荷が解かれる。また、小物部品を収納
されている函[ネ],[ナ]も予め現場Yに運び込まれ
ている。
At site Y, before the foundation is completed,
These building blocks [a] and [b], which are made into small blocks, are carried to the site Y and unloaded. In addition, boxes [n] and [na] containing small parts are also carried in advance to the site Y.

【0019】そして、基礎が構築された後、上記床パネ
ルAー1,Aー2…は順に該基礎の上部に運び込まれそ
こに固定されて組み付けられる。このとき、上記したよ
うに、床パネルが施工順に予め積み上げられているか
ら、現場Yでの作業員は床パネルを順に取り出して図2
に示すように配置して固定するだけでよく、床パネルを
捜す手間が省けることから作業効率の向上が図れかつ施
工ミスが生じるのを防止できる。
After the foundation is constructed, the floor panels A-1, A-2, ... Are sequentially carried to the upper portion of the foundation and fixed and assembled there. At this time, as described above, since the floor panels are stacked in advance in the order of construction, the worker at the site Y takes out the floor panels in order and
Since it is only necessary to arrange and fix the floor panel as shown in (3), it is possible to save the trouble of searching for the floor panel, so that the working efficiency can be improved and the construction error can be prevented.

【0020】1階の床パネルの敷き工程が終わると、次
に1階の壁パネルを組み付ける。したがって、この1階
の床パネルの敷き工程が完了する前に、壁パネル等を小
ブロック化してなる梱包物[ハ],[ニ],[ホ],
[ヘ]を予め現場Yへ運んでおく。このとき、1階の壁
パネルは数が多いので、現場Yのスペースが少ない場合
には、壁の施工工程に合わせて[ハ],[ニ]…の順に
分割して運んでもよい。
After the process of laying the floor panel on the first floor is completed, the wall panel on the first floor is assembled next. Therefore, before the floor panel laying process on the first floor is completed, the packaged product [C], [D], [E],
[F] is carried to the site Y in advance. At this time, since the number of wall panels on the first floor is large, if the space at the site Y is small, the panels may be divided into [c], [d] ... in accordance with the wall construction process.

【0021】図3は1階の壁となる壁パネル割りの平面
図である。図中符号Bー1,Bー2…Bー19はそれぞ
れ壁の一ブロックを示しており、Bーの後の番号は施工
順を示す。図4および図5は1階の壁のパネルエレメン
ト図であり、これらの図においてBー1,Bー2…Bー
19は、前記図3に示した壁のブロックに相当する。
FIG. 3 is a plan view of a wall panel divided into walls on the first floor. Reference numerals B-1, B-2, ..., B-19 in the drawing each indicate one block of the wall, and the numbers after B- indicate the order of construction. 4 and 5 are panel element diagrams of the wall on the first floor, and B-1, B-2, ... B-19 in these figures correspond to the block of the wall shown in FIG.

【0022】例えばBー1で示す壁ブロックについて説
明すると、この壁ブロックは8個の壁パネルBー1ー
1,Bー1ー2…Bー1ー8からなっていて、それらは
1階の床面等フラットな箇所で、互いの壁パネルの端面
どうしを接着材および釘等の接着手段で連結されること
によって予め組まれる。そして、このように組まれた状
態で前記施工された1階の床パネルが敷積められてなる
床面上の縁部所定箇所まで運ばれ、そこで立てかけられ
て固定される。次いで、他の壁ブロックBー2,Bー3
…についても同様な手順で、1階の床面上に固定され
る。
For example, the wall block indicated by B-1 will be described. This wall block is composed of eight wall panels B-1-1, B1-2, ... B-1-8, which are on the first floor. It is assembled in advance by connecting the end surfaces of the wall panels to each other at a flat portion such as the floor surface by an adhesive means such as an adhesive and nails. Then, in the assembled state as described above, the constructed floor panel of the first floor is carried to a predetermined edge portion on the floor where the floor panel is laid, and is leaned and fixed there. Next, other wall blocks B-2, B-3
... is fixed on the floor of the first floor by the same procedure.

【0023】これらの作業を行うときも、図13および
図14で示すように、1階で使用する壁パネルは、各ブ
ロック[ハ]〜[ヘ]内で施工順に予め積み上げられて
いるから、これらを運び出して所定箇所で互いに連結す
れば所望の壁ブロックが得られ、壁パネルを捜す手間が
省けかつ施工ミスが生じるのを防ぐことができる。な
お、それらの図で示すように、積み上げられた壁パネル
の間に形成される隙間にも、適宜角材角材100等が適
宜嵌め込まれている。
Also when performing these operations, as shown in FIGS. 13 and 14, the wall panels used on the first floor are pre-stacked in the order of construction in each block [C] to [F]. If these are carried out and connected to each other at a predetermined location, a desired wall block can be obtained, the labor for searching for the wall panel can be saved, and a construction error can be prevented. In addition, as shown in these drawings, the square bars 100 and the like are appropriately fitted into the gaps formed between the stacked wall panels.

【0024】次いで、1階の壁パネルの組付工程が終わ
ると、次に2階の床パネルを敷積める。したがって、1
階の壁パネルの組付工程が完了する前に、予め2階の床
パネル等を小ブロック化してなる梱包物[リ],[チ]
を現場Yへ運んでおく。
Next, when the assembly process of the first floor wall panel is completed, the second floor floor panel is laid next. Therefore, 1
Before the assembly process of the floor panel on the second floor is completed, the packaged items are made by dividing the floor panel on the second floor into small blocks in advance.
To the site Y.

【0025】図6は2階の床パネルの配置図ある。ここ
では、Cー1〜Cー20で示す合計20個のパネルが使
用される。この2階で使用される床パネルCー1〜Cー
20も、図10中[リ],[チ]で示す如く、施工順で
あってかつ先に使用するものが上側に来るように積み上
げられて梱包されている。
FIG. 6 is a layout view of the floor panel on the second floor. Here, a total of 20 panels indicated by C-1 to C-20 are used. The floor panels C-1 to C-20 used on the second floor are also piled up in the order of construction and the one to be used first comes to the upper side, as shown by [li] and [h] in FIG. It is packed and packed.

【0026】そして、前記のように1階の壁が組み付ら
れた後、上記床パネルCー1,Cー2…は順に該壁の上
部に運び込まれ、そこに固定される。このとき、上記し
たように、床パネルが予め施工順に積み上げられている
から、前記同様、床パネルを捜す手間が省けかつ施工ミ
スが生じるのを防止できる利点が得られる。
After the wall on the first floor is assembled as described above, the floor panels C-1, C-2, ... Are successively carried to the upper part of the wall and fixed there. At this time, as described above, since the floor panels are stacked in the order of construction in advance, there is an advantage that the labor of searching for the floor panels can be saved and construction errors can be prevented as in the above.

【0027】2階の床パネルの敷き工程が終わると、次
に2階の壁パネルを組み付ける。したがって、2階の床
パネルの敷き工程が完了する前に、2階の壁パネル等を
ブロック化してなる梱包物[ヌ]〜[カ]を予め現場Y
へ運んでおく。
When the process of laying the floor panel on the second floor is completed, the wall panel on the second floor is assembled next. Therefore, before the laying process of the floor panel on the second floor is completed, the packing items [nu] to [mosquito] made by blocking the wall panel on the second floor are pre-assembled on the site Y.
Carry on.

【0028】図7は2階の壁となるパネル割りの平面図
である。図中符号Dー1,Dー2…Dー17はそれぞれ
壁の一ブロックを示す。ここでは、壁のブロックを構成
するパネルエレメント図は省略してあるが、この場合
も、前記1階の壁を組み立てたときと同様に、一つの壁
ブロックを構成するパネルどうしを適宜フラットな箇所
で予め連結して組付け、そして、このように予め組付け
た態で前記施工された2階の床面上の縁部所定箇所に固
定する。
FIG. 7 is a plan view of a panel division which becomes a wall on the second floor. Reference numerals D-1, D-2, ... D-17 in the drawing each denote one block of the wall. Here, the panel element diagram that constitutes the block of the wall is omitted, but in this case as well, as in the case of assembling the wall on the first floor, the panels constituting one wall block are appropriately flat parts. And preliminarily connect and assemble, and then, in the preassembled state, it is fixed to a predetermined edge portion on the floor surface of the second floor constructed above.

【0029】これらの作業を行うときも、図10で示す
ように、2階で使用する壁パネルは施工順に予め積み上
げられているから、壁パネルを捜す手間が省けかつ施工
ミスが生じるのを防ぐことができる利点が得られる。
Even when performing these operations, as shown in FIG. 10, since the wall panels used on the second floor are pre-stacked in the order of construction, the labor for searching for the wall panels can be saved and construction errors can be prevented. The advantage that can be obtained is obtained.

【0030】次に、軸組材の他、梁、垂木等を寄せ集め
た梱包物[ヨ]、合板の梱包物[タ]、屋根切りパネ
ル、屋根パネル、屋根金物、内装材、仕上げ材、外装材
等を集めた梱包物[レ]および[ソ]を、2階の壁パネ
ルを組み付ける前に現場Yに予め運び込み、2階の壁パ
ネルを組み込んだ後に、屋根の組立構造や内装工事等を
行う。
Next, in addition to the frame members, beams, rafters, and other packages [Yo], plywood packages [Ta], roofing panels, roof panels, roof metal fittings, interior materials, finishing materials, The packages [LE] and [SO] in which the exterior materials are collected are carried in advance to the site Y before the second-floor wall panel is assembled, and after the second-floor wall panel is assembled, the roof assembly structure, interior work, etc. I do.

【0031】なお、本発明を実施する場合には、工場等
で梱包する段階で、建築部材を工程順に並べて梱包する
作業が必要となるが、このような作業は、現場において
多数ある建築部材から必要な部材を取り出す作業に比べ
て、作業場所が広い工場内であること、各建築部材が整
理された状態で配置されていることから、はるかに容易
である。
When the present invention is carried out, it is necessary to arrange the building members in the order of process at the stage of packing in a factory or the like, and such a work is performed from a large number of building members on site. Compared with the work of taking out the necessary members, it is much easier because the work place is in a large factory and each building member is arranged in an organized state.

【0032】また、上記実施例において示した各施工方
法およびそれを実施するのに用いる部品等は一例であ
り、用いるプレハブ用建築部材によって適宜変更可能で
ある。
Further, the respective construction methods shown in the above-mentioned embodiments and the parts and the like used for implementing them are merely examples, and can be appropriately changed depending on the prefabricated building member used.

【0033】例えば、上記実施例では、2階建の建物を
例にとって説明したがこれに限られることなく、平屋あ
るいは3階以上の建物を構築する場合でも本発明は適用
可能であり、また施工方法としても、実施例のようにパ
ネルを主体とした建物に限られることなく軽量鉄骨を骨
組みとしたプレハブ住宅あるいはALC板を利用した工
法等にも適用可能である。
For example, in the above embodiment, a two-story building has been described as an example, but the present invention is not limited to this, and the present invention can be applied to the case of building a one-story building or a building with three or more floors. The method is not limited to the panel-based building as in the embodiment, but can be applied to a prefabricated house having a lightweight steel frame or a construction method using an ALC plate.

【0034】また、上記実施例では、工場から搬送する
建築部材を一旦仮置場に配置して、そこから現場へ供給
しているが、これに限られることなく、工場等あるいは
倉庫等にストックしておき、そこから直接現場へ供給す
るようにしてもよい。
Further, in the above-mentioned embodiment, the building members conveyed from the factory are once placed in the temporary storage area and then supplied to the site, but the present invention is not limited to this, and they are stocked in the factory or warehouse. Alternatively, it may be directly supplied to the site from there.

【0035】[0035]

【発明の効果】以上説明したように本発明によれば、プ
レハブ用建築部材を現場へ供給するに際し、それら建築
部材を組立順にしたがい予め複数組みに分けてブロック
化しておき、それらブロック化した建築部材を工程に合
わせて順に現場へ供給する方法であるから、現場の各工
程に応じてその工程で必要な建築部材のみを、予めブロ
ック化した建築部材から選んで供給することができ、し
たがって、多数ある建築部材から必要な部材のみを選ん
で一々取り出す面倒な作業を行う必要はなくなり、現場
での作業効率が向上する。また、現場での作業ミスが少
なくなり、質の向上および現場管理が容易になる等の優
れた効果を奏する。
As described above, according to the present invention, when the prefabricated building members are supplied to the site, the building members are divided into a plurality of sets in advance according to the assembling order, and the blocks are constructed. Since it is a method of supplying members to the site in order according to the process, only the building members required in the process according to each process of the site can be selected from the pre-blocked building members and supplied, therefore, It is no longer necessary to select the necessary members from a large number of building members and take them out one by one, which improves the work efficiency on site. In addition, it is possible to reduce work mistakes on the site, improve quality, and easily manage the site.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明にかかるプレハブ用建築部材の供給方法
の一例を示す説明図。
FIG. 1 is an explanatory view showing an example of a method for supplying a prefabricated building member according to the present invention.

【図2】1階で使用する床パネルエレメントを説明する
平面図である。
FIG. 2 is a plan view illustrating a floor panel element used on the first floor.

【図3】1階の壁パネル割りを示す平面図である。FIG. 3 is a plan view showing a wall panel division on the first floor.

【図4】1階で使用する壁パネルエレメントを説明する
正面図である。
FIG. 4 is a front view illustrating a wall panel element used on the first floor.

【図5】1階で使用する壁パネルエレメントを説明する
正面図である。
FIG. 5 is a front view illustrating a wall panel element used on the first floor.

【図6】2階で使用する床パネルエレメントを説明する
平面図である。
FIG. 6 is a plan view illustrating a floor panel element used on the second floor.

【図7】2階の壁パネル割りを示す平面図である。FIG. 7 is a plan view showing a wall panel division on the second floor.

【図8】2階で使用する壁パネルエレメントを説明する
正面図である。
FIG. 8 is a front view illustrating a wall panel element used on the second floor.

【図9】2階で使用する壁パネルエレメントを説明する
正面図である。
FIG. 9 is a front view illustrating a wall panel element used on the second floor.

【図10】工場から仮置きスペースまでプレハブ用建築
部材を運ぶトラックの荷積み状態を説明する正面図であ
る。
FIG. 10 is a front view illustrating a loaded state of a truck that carries a prefabricated building member from a factory to a temporary storage space.

【図11】ブロック化された建築部材を説明する正面図
である。
FIG. 11 is a front view illustrating a block-shaped building member.

【図12】ブロック化された建築部材を説明する正面図
である。
FIG. 12 is a front view illustrating a block-shaped building member.

【図13】ブロック化された建築部材を説明する正面図
である。
FIG. 13 is a front view illustrating a block-shaped building member.

【図14】ブロック化された建築部材を説明する正面図
である。
FIG. 14 is a front view illustrating a block-shaped building member.

【符号の説明】[Explanation of symbols]

[イ] ブロック化された建築部材 [ロ] ブロック化された建築部材 … … [ソ] ブロック化された建築部材 T1 トラック T2 トラック Y 現場 [A] Blocked building member [b] Blocked building member ……… [so] Blocked building member T1 truck T2 truck Y Site

Claims (1)

【特許請求の範囲】[Claims] 【請求項1】 プレハブ用建築部材を現場へ供給するに
際し、それら建築部材を組立順にしたがい予め複数組み
に分けてブロック化しておき、それらブロック化した建
築部材を工程に合わせて順に現場へ供給することを特徴
とするプレハブ用建築部材の供給方法。
1. When supplying prefabricated building members to a site, the building members are divided into a plurality of sets in advance according to the order of assembling, and the blocked building members are sequentially supplied to the site according to the process. A method for supplying a prefabricated building member, comprising:
JP6267092A 1992-03-18 1992-03-18 Supply method of building member for prefabricated structure Pending JPH05263529A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP6267092A JPH05263529A (en) 1992-03-18 1992-03-18 Supply method of building member for prefabricated structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP6267092A JPH05263529A (en) 1992-03-18 1992-03-18 Supply method of building member for prefabricated structure

Publications (1)

Publication Number Publication Date
JPH05263529A true JPH05263529A (en) 1993-10-12

Family

ID=13206964

Family Applications (1)

Application Number Title Priority Date Filing Date
JP6267092A Pending JPH05263529A (en) 1992-03-18 1992-03-18 Supply method of building member for prefabricated structure

Country Status (1)

Country Link
JP (1) JPH05263529A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6000192A (en) * 1995-07-14 1999-12-14 Cohen Brothers Homes, Llc Method of production of standard size dwellings
US6253504B1 (en) * 1995-07-14 2001-07-03 Cohen Brothers Homes, Llc Manufacturing facility for production of standard size dwellings
US8418411B2 (en) * 2005-12-16 2013-04-16 Velez Y Cortazar Carlos Garcia Integral, industrialized modular dwelling system

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH02183050A (en) * 1988-12-30 1990-07-17 Dai Ichi Horm Co Ltd Building material unit body

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH02183050A (en) * 1988-12-30 1990-07-17 Dai Ichi Horm Co Ltd Building material unit body

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6000192A (en) * 1995-07-14 1999-12-14 Cohen Brothers Homes, Llc Method of production of standard size dwellings
US6253504B1 (en) * 1995-07-14 2001-07-03 Cohen Brothers Homes, Llc Manufacturing facility for production of standard size dwellings
US8418411B2 (en) * 2005-12-16 2013-04-16 Velez Y Cortazar Carlos Garcia Integral, industrialized modular dwelling system

Similar Documents

Publication Publication Date Title
US6253504B1 (en) Manufacturing facility for production of standard size dwellings
US6000192A (en) Method of production of standard size dwellings
CA2182242C (en) Pre-insulated prefab wall panel
US20020007605A1 (en) Manufactured standard size dwellings having an integral base frame
JPH05263529A (en) Supply method of building member for prefabricated structure
JPH05263528A (en) Supply method of building member for prefabricated structure
JPH05261634A (en) Manufacture of prefab panel
JPH0642179A (en) Feed method of prefabricated building member
EP0435934B1 (en) Prefabricated building kit
Yano et al. Packing optimization for cargo containers
JP2793662B2 (en) Housing unit loading rack
JP2000170307A (en) Manufacture of roof panel and designing device of roof panel
JPS60199166A (en) Feeding method of construction member
JP2506536B2 (en) How to construct an attic
JP2521370B2 (en) Roof structure
JP4340402B2 (en) Building roof structure and roof construction method
JP3501478B2 (en) How to transport building materials
KR20230087115A (en) Automatic method of precast concrete component allocation plan
JPH06227539A (en) Pallet
JPH10273144A (en) Tool for pallet, and loading and unloading method by using the pallet
Jones et al. Time and Cost Studies on Five Floor Systems
JPH06108575A (en) Mansard roof structure and construction thereof
JPH0531637A (en) Operation method for panel-framework wooden-frame supply truck
JP4364223B2 (en) Wooden building siding precut method and pallet suitable for it
JPH0673796A (en) Construction of unit house

Legal Events

Date Code Title Description
A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 19951114