JPH05186161A - Lower portion centering device for elevator installation - Google Patents

Lower portion centering device for elevator installation

Info

Publication number
JPH05186161A
JPH05186161A JP477892A JP477892A JPH05186161A JP H05186161 A JPH05186161 A JP H05186161A JP 477892 A JP477892 A JP 477892A JP 477892 A JP477892 A JP 477892A JP H05186161 A JPH05186161 A JP H05186161A
Authority
JP
Japan
Prior art keywords
centering
frame
piano wire
hoistway
lower centering
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP477892A
Other languages
Japanese (ja)
Other versions
JP2606512B2 (en
Inventor
Mitsugi Adachi
貢 足立
Shusuke Ishii
秀典 石井
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Mitsubishi Electric Corp
Original Assignee
Mitsubishi Electric Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Mitsubishi Electric Corp filed Critical Mitsubishi Electric Corp
Priority to JP4004778A priority Critical patent/JP2606512B2/en
Publication of JPH05186161A publication Critical patent/JPH05186161A/en
Application granted granted Critical
Publication of JP2606512B2 publication Critical patent/JP2606512B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66BELEVATORS; ESCALATORS OR MOVING WALKWAYS
    • B66B5/00Applications of checking, fault-correcting, or safety devices in elevators
    • B66B5/0087Devices facilitating maintenance, repair or inspection tasks
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66BELEVATORS; ESCALATORS OR MOVING WALKWAYS
    • B66B19/00Mining-hoist operation

Landscapes

  • Maintenance And Inspection Apparatuses For Elevators (AREA)
  • Lift-Guide Devices, And Elevator Ropes And Cables (AREA)

Abstract

PURPOSE:To enable highly accurate centering with high safety and economicity without interference with other working scaffold and efficiently perform centering work in a short time. CONSTITUTION:A damper mount 11, 12 on which a centering position is indicated and a centering member 13 are joined together at predetermined intervals by fittings 14 and the centering member is fixed as a lower centering frame to the floor of an elevator shaft bottom portion 1 and piano wires 16, 20, 21 are hung down into the elevator shaft toward the lower centering frame and predetermined tension is applied to the piano wires 16, 20, 21 by respective springs 23, 25, 27 and the piano wires 16, 20, 21 are connected to the hole 22 of the lower centering frame and fittings 24, 26, respectively.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明は、エレベータ据付用下部
芯出装置に関するものであり、特に、かごレール、釣合
錘レール、エレベータ乗場等の据付の際に使用されるエ
レベータ据付用下部芯出装置に関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to an elevator installation lower centering device, and more particularly to an elevator installation lower centering device used for installation of a car rail, a counterweight rail, an elevator landing and the like. It relates to the device.

【0002】[0002]

【従来の技術】従来のエレベータ据付の際の芯出作業
は、昇降路の上部に或いは昇降路頂部の機械室床面に設
けた上部芯出枠から所定の各芯出位置毎に錘を付けた基
準ピアノ線を降ろし、昇降路底部の所定高さに設定した
下部芯出枠の対応する位置に同基準ピアノ線を各々固定
することにより、必要とする関連寸法を各々得ている。
即ち、従来は図3及び図4のようなエレベータ据付用下
部芯出装置を利用して、芯出しを行なっている。
2. Description of the Related Art Conventional centering work during elevator installation involves attaching weights at predetermined centering positions from an upper centering frame provided at the top of the hoistway or on the floor of the machine room at the top of the hoistway. The required reference dimensions are obtained by lowering the reference piano wire and fixing the reference piano wire to the corresponding positions of the lower centering frame set at a predetermined height at the bottom of the hoistway.
That is, conventionally, the lower centering device for elevator installation as shown in FIGS. 3 and 4 is used to perform the centering.

【0003】図3は従来のエレベータ据付用下部芯出装
置を示す平面図、図4は従来のエレベータ据付用下部芯
出装置を示す側面図である。
FIG. 3 is a plan view showing a conventional elevator installation lower centering apparatus, and FIG. 4 is a side view showing a conventional elevator installation lower centering apparatus.

【0004】図において、1は昇降路底部、2は昇降路
壁、3は昇降路壁2の所定の高さ位置に取付けられた固
定部材、4は固定部材3を昇降路壁2に固定するアンカ
ーボルト、5は固定部材3間に架設された受台、6は昇
降路の上部或いは頂部の上部芯出枠(図示せず)から所
定の各芯出位置毎に垂下されたピアノ線、7はピアノ線
6の先端に吊下げられた錘、8,8a,8bは受台5の
上面に配設された位置決部材であり、9はかご側ガイド
レールの芯出用のピアノ線、10は錘側ガイドレールの
芯出用のピアノ線である。
In the figure, 1 is a hoistway bottom portion, 2 is a hoistway wall, 3 is a fixing member mounted at a predetermined height position of the hoistway wall 2, and 4 is a fixing member 3 fixed to the hoistway wall 2. Anchor bolts, 5 are pedestals installed between the fixing members 3, 6 are piano wires hung at predetermined centering positions from an upper centering frame (not shown) at the top or top of the hoistway, 7 Is a weight suspended at the tip of the piano wire 6, 8a, 8b are positioning members arranged on the upper surface of the pedestal 5, and 9 is a piano wire for centering the car-side guide rail. Is a piano wire for centering the weight side guide rail.

【0005】次に、この構成のエレベータ据付用下部芯
出装置の設置動作について述べる。まず、昇降路底部1
から約1m程度上方の対向する昇降路壁2に埋設したア
ンカーボルト4を用いて固定部材3を固定する。この固
定部材3は昇降路底部1から角材等を用いて固定される
こともある。そして、これらの固定部材3間に受台5を
架け渡して、水平調整を行なった後に固定する。続い
て、上部芯出枠(図示せず)から前面位置決用のピアノ
線6に錘7を付けて降ろし、その静止を待ってから位置
決部材8をその前縁がピアノ線6に接する位置を定め、
前記受台5に釘止め固定を行なう。即ち、このピアノ線
6が乗場側機器の芯出用の基準線となる。更に、同様に
して、各位置決部材8a,8bの前縁にかご側ガイドレ
ールの芯出用のピアノ線9及び錘側ガイドレールの芯出
用のピアノ線10を垂下し、その位置をけがき、上部芯
出枠(図示せず)と対応する位置にエレベータ据付用の
下部芯出枠を設置する。こうして設置された下部芯出枠
と各ピアノ線6,9,10を結合し、この各ピアノ線
6,9,10を基準にしてエレベータ据付に必要な芯出
しを行なう。
Next, the installation operation of the lower centering device for elevator installation of this configuration will be described. First, the bottom of the hoistway 1
The fixing member 3 is fixed using the anchor bolts 4 embedded in the hoistway wall 2 facing each other at about 1 m above. The fixing member 3 may be fixed from the hoistway bottom portion 1 using a square member or the like. Then, the pedestal 5 is bridged between these fixing members 3 to perform horizontal adjustment and then fixed. Subsequently, a weight 7 is attached to the piano wire 6 for positioning the front surface from the upper centering frame (not shown), and the weight is lowered, and after waiting for the stationary, the positioning member 8 is brought into contact with the piano wire 6 at its front edge. ,
The pedestal 5 is fixed by nailing. That is, the piano wire 6 serves as a reference line for centering the hall side equipment. Further, similarly, a piano wire 9 for centering the car-side guide rail and a piano wire 10 for centering the weight-side guide rail are hung on the front edges of the respective positioning members 8a and 8b, and the positions thereof are marked. A lower centering frame for installing an elevator is installed at a position corresponding to a postcard and an upper centering frame (not shown). The lower centering frame installed in this way and the respective piano wires 6, 9 and 10 are connected, and the centering necessary for elevator installation is performed with reference to these piano wires 6, 9 and 10.

【0006】[0006]

【発明が解決しようとする課題】上記のような従来のエ
レベータ据付用下部芯出装置では、下部芯出枠が昇降路
底部1から約1m程上方に設けられているため、他の作
業足場と干渉することがあった。また、エレベータ据付
用下部芯出装置の設置は、環境の悪い建築現場での作業
を伴なうために、精度の高い芯出しが困難であり、且
つ、作業者の安全性の点でも好ましくなく、その設置方
法にも問題があった。しかも、従来のエレベータ据付用
下部芯出装置は工事毎に使い捨てとなっており、極めて
不経済であった。このため、実公昭57−28852号
公報に掲載のエレベータ据付用下部芯出装置が提案され
ていた。
In the conventional lower centering device for installing an elevator as described above, since the lower centering frame is provided about 1 m above the bottom 1 of the hoistway, the lower centering frame is different from other work scaffolds. There was interference. In addition, since installation of the lower centering device for elevator installation involves work at a construction site where the environment is poor, accurate centering is difficult, and it is not preferable in terms of worker safety. There was also a problem with the installation method. Moreover, the conventional lower centering device for installing an elevator is disposable after each construction, which is extremely uneconomical. For this reason, a lower centering device for elevator installation disclosed in Japanese Utility Model Publication No. 57-28852 has been proposed.

【0007】しかし、この公報のエレベータ据付用下部
芯出装置においても、各ピアノ線の先端に各々錘を付け
て降ろし、その静止を待ってから下部芯出枠の位置決め
を行なうために、ピアノ線が静止するのに長時間かか
り、この結果、芯出作業時間が長くなっていた。
However, in the lower centering device for elevator installation of this publication, too, a weight is attached to the tip of each piano wire to lower it, and after waiting for it to stand, the piano wire is positioned in order to position the lower centering frame. It took a long time to stand still, resulting in a long centering work time.

【0008】そこで、この発明は、昇降路底部に配設さ
れる緩衝器台を利用して、他の作業足場と干渉すること
がなく、精度の高い芯出しができ、且つ、安全性が高
く、しかも経済的であり、芯出作業が短時間で効率よく
できるエレベータ据付用下部芯出装置の提供を課題とす
るものである。
Therefore, the present invention utilizes the shock absorber base arranged at the bottom of the hoistway to perform accurate centering without interfering with other work scaffolds and high safety. Moreover, it is an object of the present invention to provide an elevator installation lower centering device that is economical and that can perform centering work efficiently in a short time.

【0009】[0009]

【課題を解決するための手段】請求項1の発明にかかる
エレベータ据付用下部芯出装置は、各々の芯出位置を表
示した緩衝器台、乗場側用の芯出部材を結合金具で各々
所定の間隔をおいて結合し、昇降路底部の床に固定して
なる下部芯出枠と、前記下部芯出枠に向って昇降路内に
垂下されたピアノ線と、前記ピアノ線に所定の張力を付
加して前記下部芯出枠の所定の位置に接続された張力付
加接続手段とを具備するものである。
In the lower centering device for elevator installation according to the invention of claim 1, a shock absorber stand displaying the respective centering positions and a centering member for the landing side are predetermined by connecting fittings. A lower centering frame that is fixed to the floor at the bottom of the hoistway, a piano wire hung in the hoistway toward the lower centering frame, and a predetermined tension applied to the piano wire. And a tension applying connection means connected to a predetermined position of the lower centering frame.

【0010】請求項2の発明にかかるエレベータ据付用
下部芯出装置は、上記請求項1と同様の下部芯出枠と、
ピアノ線とを有し、前記ピアノ線に所定の張力を付加し
て前記下部芯出枠の所定の位置に移動可能な状態で接続
された張力付加接続手段を具備するものである。
An elevator installation lower centering device according to a second aspect of the present invention includes a lower centering frame similar to that of the first aspect.
And a piano wire, which is provided with a tension applying connection means which is connected to the piano wire in a movable state at a predetermined position of the lower centering frame by applying a predetermined tension to the piano wire.

【0011】[0011]

【作用】請求項1の発明のエレベータ据付用下部芯出装
置においては、各々の芯出位置を表示した緩衝器台、芯
出部材を結合金具で各々所定の間隔をおいて結合し、下
部芯出枠として昇降路底部の床に固定し、下部芯出枠に
向って昇降路内にピアノ線を垂下し、このピアノ線に所
定の張力を付加して前記下部芯出枠の所定の位置に接続
されたものであるから、昇降路底部に実際に配設される
緩衝器台を利用した下部芯出枠となり、しかもピアノ線
の振れを短時間で静止できる。
In the lower centering device for elevator installation according to the first aspect of the present invention, the shock absorber base and the centering member, which indicate the respective centering positions, are joined with the fittings at predetermined intervals, and the lower center is attached. It is fixed to the floor at the bottom of the hoistway as an exit frame, a piano wire is hung in the hoistway toward the lower centering frame, and a predetermined tension is applied to this piano wire to the predetermined position of the lower centering frame. Since it is connected, it becomes a lower centering frame utilizing a shock absorber base actually arranged at the bottom of the hoistway, and the swing of the piano wire can be stopped in a short time.

【0012】請求項2の発明のエレベータ据付用下部芯
出装置においては、上記請求項1と同様の下部芯出枠を
昇降路底部の床に固定し、下部芯出枠に向って昇降路内
にピアノ線を垂下し、このピアノ線に所定の張力を付加
して前記下部芯出枠の所定の位置に移動可能な状態で接
続されたものであるから、昇降路底部に実際に配設され
る緩衝器台を利用した下部芯出枠となり、しかもピアノ
線の振れを短時間で静止できるだけでなく、各ピアノ線
間の寸法の調整ができる。
In the lower centering device for elevator installation according to a second aspect of the present invention, the lower centering frame similar to that of the above-mentioned first aspect is fixed to the floor at the bottom of the hoistway and the hoistway is oriented toward the lower centering frame. Since the piano wire is hung down and is connected to the piano wire so as to be movable to a predetermined position of the lower centering frame by applying a predetermined tension to the piano wire, the piano wire is actually disposed at the bottom of the hoistway. It is a lower centering frame that uses a shock absorber base, and not only can the swing of the piano wire be stopped in a short time, but the dimensions between the piano wires can be adjusted.

【0013】[0013]

【実施例】以下、本発明の各実施例について説明をす
る。
Embodiments of the present invention will be described below.

【0014】〈第一実施例〉図1は本発明の第一実施例
であるエレベータ据付用下部芯出装置を示す斜視図であ
る。図中、上記実施例と同一符号及び記号は上記実施例
の構成部分と同一または相当する構成部分を示す。
<First Embodiment> FIG. 1 is a perspective view showing a lower centering device for elevator installation according to a first embodiment of the present invention. In the figure, the same reference numerals and symbols as those of the above-mentioned embodiment indicate the same or corresponding components as those of the above-mentioned embodiment.

【0015】図において、11はエレベータかご用の緩
衝器台、12は釣合錘用の緩衝器台、13はエレベータ
乗場用の芯出部材、14は前記緩衝器台11,12及び
芯出部材13を連結する結合金具、15はその結合ボル
ト、16は昇降路の上部或いは頂部の上部芯出枠(図示
せず)の所定の芯出位置から垂下されたピアノ線、17
〜19は緩衝器台11,12及び芯出部材13を昇降路
底部1の床面へ固定するための固定具、20はかご側ガ
イドレールの芯出用のピアノ線、21は錘側ガイドレー
ルの芯出用のピアノ線である。22は芯出部材13の所
定の位置に予め穿設された孔、23はピアノ線16に所
定の張力を付加するバネ、24は緩衝器台11の所定の
位置に予め取付けられた取付金具、25はピアノ線20
に所定の張力を付加するバネ、26は緩衝器台12の所
定の位置に予め取付けられた取付金具、27はピアノ線
21に所定の張力を付加するバネである。
In the figure, 11 is a shock absorber stand for an elevator car, 12 is a shock absorber stand for a counterweight, 13 is a centering member for an elevator landing, and 14 is the shock absorber stands 11, 12 and the centering member. A connecting metal fitting for connecting 13; 15 a connecting bolt thereof; 16 a piano wire suspended from a predetermined centering position of an upper centering frame (not shown) at the top or the top of the hoistway;
˜19 are fixtures for fixing the shock absorber bases 11 and 12 and the centering member 13 to the floor surface of the hoistway bottom portion 1, 20 is a piano wire for centering the car side guide rail, and 21 is a weight side guide rail. It is a piano wire for centering. Reference numeral 22 is a hole preliminarily formed at a predetermined position of the centering member 13, 23 is a spring for applying a predetermined tension to the piano wire 16, and 24 is a mounting bracket previously attached at a predetermined position of the shock absorber base 11. 25 is a piano wire 20
Is a spring for applying a predetermined tension to, a mounting metal fitting 26 that is previously attached to a predetermined position of the shock absorber base 12, and a spring for applying a predetermined tension to the piano wire 21.

【0016】次に、この構成のエレベータ据付用下部芯
出装置の設置動作について述べる。まず、エレベータか
ご用の緩衝器台11、釣合錘用の緩衝器台12、乗場側
用の芯出部材13を相互間の間隔寸法を調整できる結合
金具14に所要寸法を確認して結合し、下部芯出枠とし
て一体化する。こうして結合された下部芯出枠を移動さ
せながら、上部芯出枠(図示せず)から垂下したピアノ
線16の先端を予め穿設した孔22にバネ23を介して
接続する。そして、基準階の墨(図示せず)にピアノ線
16を合わせて位置決めを行ない、芯出部材13、緩衝
器台11,12の各固定具17〜19を利用して昇降路
底部1の床に、コンクリート釘、樹脂アンカーボルト等
を取付けて固定する。また、こうして固定した後に、前
記上部芯出枠(図示せず)から別途垂下されているかご
側ガイドレール芯出用のピアノ線20と錘側ガイドレー
ル芯出用のピアノ線21を、かご側緩衝器台11と錘側
緩衝器台12に各々予め電気溶接等により取付けられた
取付金具24,26にバネ25、バネ27を介して止着
し、これらの各ピアノ線16,20,21から必要な関
係寸法を得る。こうして設置された下部芯出枠に連結さ
れた各ピアノ線16,20,21を基準にしてエレベー
タ据付に必要な芯出しを行なう。
Next, the installation operation of the lower centering device for elevator installation of this construction will be described. First, the elevator car shock absorber stand 11, the counterweight shock absorber stand 12, and the landing side centering member 13 are connected to a joint fitting 14 capable of adjusting the distance between them by confirming the required dimensions. , Integrated as a lower centering frame. While moving the lower centering frame coupled in this way, the tip of the piano wire 16 hanging from the upper centering frame (not shown) is connected to a pre-drilled hole 22 via a spring 23. Then, the piano wire 16 is aligned with the black ink (not shown) on the standard floor, and the positioning is performed. Using the fixing members 17 to 19 of the centering member 13 and the shock absorber bases 11 and 12, the floor of the hoistway bottom 1 is used. Then, attach concrete nails, resin anchor bolts, etc., and fix. Also, after fixing in this way, the car-side guide rail centering piano wire 20 and the weight-side guide rail centering piano wire 21 which are separately hung from the upper centering frame (not shown) are mounted on the car side. From the respective piano wires 16, 20, 21 to the mounting brackets 24, 26 previously mounted on the shock absorber base 11 and the weight side shock absorber base 12 by electric welding or the like via springs 25, 27, respectively. Get the required relational dimensions. The centering necessary for elevator installation is performed on the basis of the respective piano wires 16, 20, 21 connected to the lower centering frame thus installed.

【0017】このように、本実施例のエレベータ据付用
下部芯出装置は、各々の芯出位置を表示したかご側ガイ
ドレール用の緩衝器台11、釣合錘側ガイドレール用の
緩衝器台12、乗場側用の芯出部材13を結合金具14
で各々所定の間隔をおいて結合し、昇降路底部1の床に
固定してなる下部芯出枠と、前記下部芯出枠に向って上
部芯出枠(図示せず)から昇降路内に垂下されたピアノ
線16,20,21と、前記ピアノ線16,20,21
に所定の張力を付加して前記下部芯出枠の孔22、取付
金具24,26に接続する張力付加接続手段であるバネ
23,25,27とを備えている。
As described above, the lower centering device for elevator installation according to the present embodiment has the buffer stand 11 for the guide rails on the car side and the shock absorber stand for the guide rails on the counterweight side that indicate the respective centering positions. 12, the centering member 13 for the landing side, the fitting 14
At a predetermined distance from each other and fixed to the floor of the hoistway bottom 1, and from the upper centering frame (not shown) toward the lower centering frame into the hoistway. The suspended piano wires 16, 20, 21 and the piano wires 16, 20, 21
Is provided with springs 23, 25 and 27 which are tension applying connecting means for connecting a predetermined tension to the hole 22 of the lower centering frame and the fittings 24 and 26.

【0018】即ち、本実施例のエレベータ据付用下部芯
出装置は、各々の芯出位置を表示した緩衝器台11,1
2、芯出部材13を結合金具14で各々所定の間隔をお
いて結合し、下部芯出枠として昇降路底部1の床に固定
し、下部芯出枠に向って昇降路内にピアノ線16,2
0,21を垂下し、このピアノ線16,20,21にバ
ネ23,25,27で所定の張力を付加して下部芯出枠
の孔22、取付金具24,26に接続するものである。
That is, in the lower centering device for elevator installation according to the present embodiment, the shock absorber bases 11 and 1 displaying the respective centering positions are shown.
2. The centering members 13 are joined together with the fittings 14 at predetermined intervals, and fixed to the floor of the hoistway bottom 1 as a lower centering frame, and the piano wire 16 is inserted into the hoistway toward the lower centering frame. , 2
0, 21 are hung, and a predetermined tension is applied to the piano wires 16, 20, 21 by springs 23, 25, 27 to connect them to the hole 22 of the lower centering frame and the fittings 24, 26.

【0019】したがって、本実施例のエレベータ据付用
下部芯出装置は、昇降路底部1に実際に配設される緩衝
器台11,12を利用した下部芯出枠となるので、下部
芯出枠が他の作業足場と干渉することがない。また、下
部芯出枠の孔22、取付金具24,26を利用して芯出
しを行なうために、精度の高い芯出しが可能になり、且
つ、作業者に対する安全性も高い。しかも、従来のよう
に工事毎の使い捨てでなく経済的である。
Therefore, the lower centering device for elevator installation according to the present embodiment is a lower centering frame that utilizes the shock absorber bases 11 and 12 that are actually arranged on the bottom 1 of the hoistway. Does not interfere with other work scaffolds. Further, since the centering is performed by using the hole 22 of the lower centering frame and the mounting fittings 24 and 26, the centering can be performed with high accuracy, and the safety for the worker is also high. Moreover, it is economical rather than being disposable for each work as in the past.

【0020】また、バネ23,25,27によりピアノ
線16,20,21の振れを短時間で静止できるので、
従来のように錘を使用する場合に比べ芯出作業を短時間
で効率よくできる。更に、バネ23,25,27のバネ
定数を任意に選択することにより、ピアノ線16,2
0,21を略瞬時に静止させることもできる。
Further, since the springs 23, 25, 27 can stop the swing of the piano wires 16, 20, 21 in a short time,
The centering work can be performed efficiently in a short time as compared with the case where the weight is used as in the past. Further, by selecting the spring constants of the springs 23, 25, 27 arbitrarily, the piano wires 16, 2
It is also possible to make 0 and 21 stand still almost instantaneously.

【0021】〈第二実施例〉図2は本発明の第二実施例
であるエレベータ据付用下部芯出装置の要部を示す拡大
斜視図である。図中、第一実施例と同一符号及び記号は
第一実施例の構成部分と同一または相当する構成部分を
示す。
<Second Embodiment> FIG. 2 is an enlarged perspective view showing a main part of an elevator installation lower centering apparatus according to a second embodiment of the present invention. In the figure, the same reference numerals and symbols as those in the first embodiment denote the same or corresponding components as those of the first embodiment.

【0022】図において、28は緩衝器台11,12の
所定の位置に取付けられた取付金具であり、29は取付
金具28の取付片に穿設された長孔である。なお、この
取付金具28は長孔29を介してネジ止め等により緩衝
器台11,12に取付けられている。
In the figure, 28 is a mounting member attached to a predetermined position of the shock absorber bases 11 and 12, and 29 is an elongated hole formed in the mounting piece of the mounting member 28. The mounting member 28 is attached to the shock absorber bases 11 and 12 by screwing or the like through the long hole 29.

【0023】本実施例では、ピアノ線20,21に所定
の張力を付加するバネ25,27を接合する取付金具
を、上記第一実施例のように電気溶接等により固定する
ことなく着脱式にしたものである。即ち、この構成の取
付金具28は緩衝器台11,12に電気溶接等により固
定されておらず、着脱が可能であり、しかも、この取付
金具28を長孔29に沿って移動させることにより、ピ
アノ線20間の寸法の調整ができる。
In this embodiment, the fittings for joining the springs 25 and 27 for applying a predetermined tension to the piano wires 20 and 21 are detachable without fixing them by electric welding as in the first embodiment. It was done. That is, the mounting bracket 28 having this configuration is not fixed to the shock absorber bases 11 and 12 by electric welding or the like, and can be attached and detached. Moreover, by moving the mounting bracket 28 along the long hole 29, The dimensions between the piano wires 20 can be adjusted.

【0024】このように、本実施例のエレベータ据付用
下部芯出装置は、各々の芯出位置を表示したかご側ガイ
ドレール用の緩衝器台11、釣合錘側ガイドレール用の
緩衝器台12、乗場側用の芯出部材13を結合金具14
で各々所定の間隔をおいて結合し、昇降路底部1の床に
固定してなる下部芯出枠と、前記下部芯出枠に向って上
部芯出枠(図示せず)から昇降路内に垂下されたピアノ
線16,20,21と、前記ピアノ線16,20,21
に所定の張力を付加して前記下部芯出枠の孔22、長孔
29を有する移動可能な取付金具28に接続する張力付
加接続手段であるバネ23,25,27とを備えてい
る。
As described above, the lower centering device for elevator installation according to the present embodiment is provided with the buffer stand 11 for the car-side guide rail and the shock absorber stand for the counterweight-side guide rail that indicate the respective centering positions. 12, the centering member 13 for the landing side, the fitting 14
At a predetermined distance from each other and fixed to the floor of the hoistway bottom 1, and from the upper centering frame (not shown) toward the lower centering frame into the hoistway. The suspended piano wires 16, 20, 21 and the piano wires 16, 20, 21
Is provided with springs 23, 25 and 27 which are tension applying connecting means for applying a predetermined tension to the movable core fitting 28 having the hole 22 and the elongated hole 29 of the lower centering frame.

【0025】即ち、本実施例のエレベータ据付用下部芯
出装置は、上記第一実施例の取付金具24,26を長孔
29を有する移動可能な取付金具28にしたものであ
る。
That is, in the lower centering device for elevator installation of this embodiment, the mounting fittings 24 and 26 of the first embodiment are replaced by a movable mounting fitting 28 having an elongated hole 29.

【0026】したがって、本実施例のエレベータ据付用
下部芯出装置は、上記第一実施例と同様に、昇降路底部
1に実際に配設される緩衝器台11,12を利用した下
部芯出枠となるので、下部芯出枠が他の作業足場と干渉
することがない。また、下部芯出枠の孔22、取付金具
28を利用して芯出しを行なうために、精度の高い芯出
しが可能になり、且つ、作業者に対する安全性も高い。
しかも、従来のように工事毎の使い捨てでなく経済的で
ある。
Therefore, the lower centering device for elevator installation according to the present embodiment is similar to the first embodiment described above in that the lower centering using the shock absorber bases 11 and 12 actually arranged on the bottom 1 of the hoistway. Since it becomes a frame, the lower centering frame does not interfere with other work scaffolds. Further, since the centering is performed by using the hole 22 of the lower centering frame and the mounting metal fitting 28, the centering can be performed with high accuracy and the safety for the operator is also high.
Moreover, it is economical rather than being disposable for each work as in the past.

【0027】また、バネ23,25,27によりピアノ
線16,20,21の振れを短時間で静止できるので、
従来のように錘を使用する場合に比べ芯出作業を短時間
で効率よくできる。更に、バネ23,25,27のバネ
定数を任意に選択することにより、ピアノ線16,2
0,21を略瞬時に静止させることもできる。
Since the springs 23, 25, 27 can stop the swing of the piano wires 16, 20, 21 in a short time,
The centering work can be performed efficiently in a short time as compared with the case where the weight is used as in the past. Further, by selecting the spring constants of the springs 23, 25, 27 arbitrarily, the piano wires 16, 2
It is also possible to make 0 and 21 stand still almost instantaneously.

【0028】更に、取付金具28を長孔29に沿って移
動させることにより、ピアノ線20間の寸法の調整がで
きるので、微調整が可能になり、位置決め及び芯出しの
精度が増す。
Further, by moving the mounting member 28 along the long hole 29, the dimension between the piano wires 20 can be adjusted, so that fine adjustment is possible and the positioning and centering accuracy is increased.

【0029】[0029]

【発明の効果】以上説明したように、請求項1の発明の
エレベータ据付用下部芯出装置は、下部芯出枠と、ピア
ノ線と、張力付加接続手段とを備え、各々の芯出位置を
表示した緩衝器台、芯出部材を結合金具で各々所定の間
隔をおいて結合し、下部芯出枠として昇降路底部の床に
固定し、下部芯出枠に向って昇降路内にピアノ線を垂下
し、このピアノ線に所定の張力を付加して前記下部芯出
枠の所定の位置に接続することにより、昇降路底部に実
際に配設される緩衝器台を利用した下部芯出枠となるの
で、他の作業足場と干渉することがなく、精度の高い芯
出しができ、且つ、安全性が高く、経済的となり、しか
もピアノ線の振れを短時間で静止できるので、芯出作業
を短時間で効率よくできる。
As described above, the elevator installation lower centering apparatus of the invention of claim 1 is provided with the lower centering frame, the piano wire, and the tension applying connecting means, and the respective centering positions are provided. The shock absorber base and the centering member shown are connected with the fittings at predetermined intervals, and fixed to the floor of the bottom of the hoistway as a lower centering frame, and the piano wire is placed in the hoistway toward the lower centering frame. A lower centering frame using a shock absorber base that is actually arranged at the bottom of the hoistway by connecting the piano wire to the predetermined position by applying a predetermined tension to the piano wire. Since it does not interfere with other work scaffolding, it can be centered with high accuracy, and it is highly safe and economical, and the swing of the piano wire can be stopped in a short time, so centering work Can be done efficiently in a short time.

【0030】請求項2の発明のエレベータ据付用下部芯
出装置は、下部芯出枠と、ピアノ線と、張力付加接続手
段とを備え、上記請求項1と同様の下部芯出枠を昇降路
底部の床に固定し、下部芯出枠に向って昇降路内にピア
ノ線を垂下し、このピアノ線に所定の張力を付加して前
記下部芯出枠の所定の位置に移動可能な状態で接続する
ことにより、昇降路底部に実際に配設される緩衝器台を
利用した下部芯出枠となるので、他の作業足場と干渉す
ることがなく、精度の高い芯出しができ、且つ、安全性
が高く、経済的となり、しかもピアノ線の振れを短時間
で静止できるので、芯出作業を短時間で効率よくでき、
更に、各ピアノ線間の寸法の調整ができるので、微調整
が可能になり、位置決め及び芯出しの精度が増す。
A lower centering device for elevator installation according to a second aspect of the present invention comprises a lower centering frame, a piano wire, and a tension applying connecting means, and a lower centering frame similar to that of the above-mentioned claim 1 is used for a hoistway. Fixed on the floor of the bottom part, hanging a piano wire in the hoistway toward the lower centering frame, applying a predetermined tension to this piano wire and being movable to a predetermined position of the lower centering frame. By connecting, it becomes a lower centering frame that utilizes a shock absorber base that is actually arranged at the bottom of the hoistway, so it does not interfere with other work scaffolds, and highly accurate centering is possible, and It is highly safe and economical, and because the swing of the piano wire can be stopped in a short time, centering work can be done efficiently in a short time,
Furthermore, since the size of each piano wire can be adjusted, fine adjustment is possible, and the positioning and centering accuracy is increased.

【図面の簡単な説明】[Brief description of drawings]

【図1】図1は本発明の第一実施例であるエレベータ据
付用下部芯出装置を示す斜視図である。
FIG. 1 is a perspective view showing an elevator installation lower centering device according to a first embodiment of the present invention.

【図2】図2は本発明の第二実施例であるエレベータ据
付用下部芯出装置の要部を示す拡大斜視図である。
FIG. 2 is an enlarged perspective view showing a main part of a lower centering device for elevator installation according to a second embodiment of the present invention.

【図3】図3は従来のエレベータ据付用下部芯出装置を
示す平面図である。
FIG. 3 is a plan view showing a conventional lower centering device for elevator installation.

【図4】図4は従来のエレベータ据付用下部芯出装置を
示す側面図である。
FIG. 4 is a side view showing a conventional lower centering device for elevator installation.

【符号の説明】[Explanation of symbols]

1 昇降路底部 11,12 緩衝器台 13 芯出部材 14 結合金具 15 結合ボルト 16,20,21 ピアノ線 17〜19 固定具 22 孔 23,25,27 バネ 24,26,28 取付金具 29 長孔 1 Bottom of hoistway 11,12 Shock absorber base 13 Centering member 14 Coupling metal fitting 15 Coupling bolt 16,20,21 Piano wire 17-19 Fixing tool 22 hole 23,25,27 Spring 24,26,28 Mounting metal fitting 29 Long hole

Claims (2)

【特許請求の範囲】[Claims] 【請求項1】 各々の芯出位置を表示した緩衝器台、乗
場側用の芯出部材を結合金具で各々所定の間隔をおいて
結合し、昇降路底部の床に固定してなる下部芯出枠と、 前記下部芯出枠に向って昇降路内に垂下されたピアノ線
と、 前記ピアノ線に所定の張力を付加して前記下部芯出枠の
所定の位置に接続された張力付加接続手段とを具備する
ことを特徴とするエレベータ据付用下部芯出装置。
1. A lower core formed by connecting a shock absorber stand displaying the respective centering positions and a centering member for the landing side with coupling fittings at predetermined intervals, and fixing them to the floor at the bottom of the hoistway. Outer frame, a piano wire hanging in the hoistway toward the lower centering frame, and a tension-applying connection connected to a predetermined position of the lower centering frame by applying a predetermined tension to the piano wire. A lower centering device for elevator installation, comprising:
【請求項2】 各々の芯出位置を表示した緩衝器台、乗
場側用の芯出部材を結合金具で各々所定の間隔をおいて
結合し、昇降路底部の床に固定してなる下部芯出枠と、 前記下部芯出枠に向って昇降路内に垂下されたピアノ線
と、 前記ピアノ線に所定の張力を付加して前記下部芯出枠の
所定の位置に移動可能な状態で接続された張力付加接続
手段とを具備することを特徴とするエレベータ据付用下
部芯出装置。
2. A lower core obtained by connecting a shock absorber stand displaying the respective centering positions and a centering member for the landing side with connecting fittings at predetermined intervals, and fixing them to the floor at the bottom of the hoistway. An outlet frame, a piano wire hung in the hoistway toward the lower centering frame, and a predetermined tension applied to the piano wire to be connected to the lower centering frame in a movable state. Lower centering device for elevator installation, comprising:
JP4004778A 1992-01-14 1992-01-14 Lower centering device for elevator installation Expired - Lifetime JP2606512B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP4004778A JP2606512B2 (en) 1992-01-14 1992-01-14 Lower centering device for elevator installation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP4004778A JP2606512B2 (en) 1992-01-14 1992-01-14 Lower centering device for elevator installation

Publications (2)

Publication Number Publication Date
JPH05186161A true JPH05186161A (en) 1993-07-27
JP2606512B2 JP2606512B2 (en) 1997-05-07

Family

ID=11593286

Family Applications (1)

Application Number Title Priority Date Filing Date
JP4004778A Expired - Lifetime JP2606512B2 (en) 1992-01-14 1992-01-14 Lower centering device for elevator installation

Country Status (1)

Country Link
JP (1) JP2606512B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2021191146A1 (en) 2020-03-27 2021-09-30 Inventio Ag Universal console and pit assembly for a rail vehicle of an elevator system, rail system, and method for aligning the rail system

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2021191146A1 (en) 2020-03-27 2021-09-30 Inventio Ag Universal console and pit assembly for a rail vehicle of an elevator system, rail system, and method for aligning the rail system

Also Published As

Publication number Publication date
JP2606512B2 (en) 1997-05-07

Similar Documents

Publication Publication Date Title
US7559409B2 (en) Procedure and apparatus for the installation of an elevator
JPH05105362A (en) Working device in hoistway
JPH05186161A (en) Lower portion centering device for elevator installation
JPH0829905B2 (en) Hoistway scaffolding equipment
JPH05246649A (en) Lower part centering device for installing elevator
JPH05213562A (en) Hydraulic elevator lower part centering method and device therefor
JPH08245116A (en) Installation engineering of elevator
JP2692525B2 (en) Lower centering method for elevator installation
JP4454100B2 (en) Elevator guide rail centering template and elevator guide rail centering method
JPH09227056A (en) Car frame for elevator
JP2507636B2 (en) Mechanical platform support device for temporary elevator
JPH05246650A (en) Shock absorber board connecting device for elevator
JPH10167613A (en) Installation device for elevator guide rail
JP2002060158A (en) Installation method for elevator
JPS634049Y2 (en)
JPS6348763Y2 (en)
JP4857970B2 (en) Elevator fall prevention curtain mounting device and mounting method
JP2004250198A (en) Damper stand installation device of elevator
JP3347968B2 (en) Hydraulic elevator installation method
JP2674392B2 (en) Hydraulic elevator installation method
JPH04317978A (en) Guide rail mounting device
JPH0442301Y2 (en)
JPH07157235A (en) Elevator installation scaffolding device
JPH08217357A (en) Reset action confirming fitting mounting method of plunger in oil buffer
JPH02305785A (en) Elevator installation process and working floor device for elevator installation

Legal Events

Date Code Title Description
FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20080213

Year of fee payment: 11

FPAY Renewal fee payment (prs date is renewal date of database)

Year of fee payment: 12

Free format text: PAYMENT UNTIL: 20090213

FPAY Renewal fee payment (prs date is renewal date of database)

Year of fee payment: 13

Free format text: PAYMENT UNTIL: 20100213

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100213

Year of fee payment: 13

FPAY Renewal fee payment (prs date is renewal date of database)

Year of fee payment: 14

Free format text: PAYMENT UNTIL: 20110213

FPAY Renewal fee payment (prs date is renewal date of database)

Year of fee payment: 15

Free format text: PAYMENT UNTIL: 20120213

EXPY Cancellation because of completion of term