JPH0517327B2 - - Google Patents

Info

Publication number
JPH0517327B2
JPH0517327B2 JP60098037A JP9803785A JPH0517327B2 JP H0517327 B2 JPH0517327 B2 JP H0517327B2 JP 60098037 A JP60098037 A JP 60098037A JP 9803785 A JP9803785 A JP 9803785A JP H0517327 B2 JPH0517327 B2 JP H0517327B2
Authority
JP
Japan
Prior art keywords
partition plate
plate
pulled out
reinforcing bar
excavation hole
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP60098037A
Other languages
Japanese (ja)
Other versions
JPS61257530A (en
Inventor
Yasushi Nakamura
Masaya Hirai
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Obayashi Corp
Original Assignee
Obayashi Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Obayashi Corp filed Critical Obayashi Corp
Priority to JP9803785A priority Critical patent/JPS61257530A/en
Publication of JPS61257530A publication Critical patent/JPS61257530A/en
Publication of JPH0517327B2 publication Critical patent/JPH0517327B2/ja
Granted legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/18Bulkheads or similar walls made solely of concrete in situ

Description

【発明の詳細な説明】 ≪産業上の利用分野≫ この発明は地中連続壁工法に関し、特にジヨイ
ントボツクスの仕切板の抜取性の向上に関する。
DETAILED DESCRIPTION OF THE INVENTION <<Industrial Application Field>> The present invention relates to an underground continuous wall construction method, and particularly to improving the ease of extracting partition plates from joint boxes.

≪従来技術≫ 地中を掘削しつつ連続的な地中壁を形成する工
法の一つとして、従来より第3図、第4図に示す
地中連続壁工法がある。
<<Prior Art>> As one of the construction methods for forming a continuous underground wall while excavating underground, there is a conventional underground continuous wall construction method shown in FIGS. 3 and 4.

図において、1aは先行掘削孔であり、この掘
削孔1に一端部に中空状のジヨイントボツクス2
を設けた鉄筋篭3を挿入し、該掘削孔1a内にコ
ンクリートを打設することにより、ジヨイントボ
ツクス2を除く部分に先行壁体7を形成する。
In the figure, reference numeral 1a indicates a preliminary drilling hole, and a hollow joint box 2 is installed at one end of this drilling hole 1.
By inserting a reinforcing bar cage 3 provided with a steel bar and pouring concrete into the excavated hole 1a, a leading wall body 7 is formed in a portion excluding the joint box 2.

ジヨイントボツクス2は、一対の側板4と、接
合板5と、図示しない底面板およびジヨントボツ
クス2の側端側にあつてアングル4aに支持され
た仕切板6とからなつている。仕切板6は鉛直方
向に引抜き可能であり、先行壁の形成作業が終了
の後、新たな後行掘削孔1bを仕切板6の側端側
に連続的に掘削した後に引抜かれ、完成した掘削
孔1b内に前記と同じく先端側にジヨイントボツ
クスを一体化した鉄筋篭3′を挿入する。そして、
ジヨイントボツクス2内で鉄筋篭3,3′の端部
をオーバーラツプさせた状態で配置し、この状態
で新たなコンクリートを打設することにより先行
壁体7と連結した後行壁体8を連続して形成する
ものである。
The joint box 2 is composed of a pair of side plates 4, a joint plate 5, a bottom plate (not shown), and a partition plate 6 located at the side end of the joint box 2 and supported by an angle 4a. The partition plate 6 can be pulled out in the vertical direction, and after the formation work of the preceding wall is completed, a new trailing excavation hole 1b is continuously excavated to the side end side of the partition plate 6, and then pulled out, and the completed excavation is completed. A reinforcing bar cage 3' having a joint box integrated at its tip end is inserted into the hole 1b in the same manner as described above. and,
The ends of the reinforcing bar cages 3 and 3' are placed in an overlapping state within the joint box 2, and new concrete is poured in this state to create a continuous trailing wall 8 that is connected to the leading wall 7. It is formed by

≪発明が解決しようとする問題点≫ この工法における問題点は、掘削孔1の深さが
深い場合に、仕切板6の長さが極めて長くなつて
しまうため、引抜きや挿入が難しいものとなる。
例えば掘削孔1の深度は現在のところ最大45m程
度であり、また今度は60〜80mとなる可能性もあ
りこれに応じて仕切板6の鉛直方向の長さもこれ
と同様な長さとなりさらにこの操作が困難にな
る。
<<Problems to be solved by the invention>> The problem with this construction method is that when the depth of the excavation hole 1 is deep, the length of the partition plate 6 becomes extremely long, making it difficult to pull out or insert it. .
For example, the maximum depth of the excavation hole 1 is currently about 45 m, and there is a possibility that it will become 60 to 80 m in the future. Operation becomes difficult.

一方、挿入あるいは引抜き操作を容易にするた
め、アングル4aと仕切板6の間隔を大きくした
場合には、仕切板6でのシール性が充分でなくな
り、例えば後行掘削孔1bの掘削作業に際し、仕
切板6とアングル4aとの隙間から土が入りこん
だり、あるいは先行掘削孔1aと側板2との間に
充填されるコンクリートが仕切板6とアングル4
aとの隙間に入りこみ、仕切板6を固着してしま
う惧れもあつた。
On the other hand, if the distance between the angle 4a and the partition plate 6 is increased in order to facilitate insertion or withdrawal, the sealing performance of the partition plate 6 will not be sufficient. Soil may enter through the gap between the partition plate 6 and the angle 4a, or concrete filled between the preceding excavation hole 1a and the side plate 2 may enter the partition plate 6 and the angle 4.
There was also a risk that it would get into the gap between a and the partition plate 6 and fix the partition plate 6.

この発明は、上述した問題を鑑みてなされたも
のであつて、仕切板の挿入および引抜き作業が容
易にできる地中連続壁工法を提供することを目的
とする。
The present invention was made in view of the above-mentioned problems, and an object of the present invention is to provide an underground continuous wall construction method that allows easy insertion and removal of partition plates.

≪発明の構成≫ 前記目的を達成するため、この発明は、一端に
中空状のジヨイントボツクスが設けられた鉄筋篭
を掘削する孔内に建込み鉄筋篭の端部同志をオー
バーラツプさせて先・後行壁を順次連結形成する
地中連続壁工法において、該ジヨイントボツクス
の接合板を埋設する一方、仕切板と側板とをそれ
ぞれ引抜き可能となし、該仕切板と該掘削孔との
間に砕石などの充填材を充填した後、打設コンク
リートの半硬化状態で該側板を引抜き、該充填材
の側方に該後行掘削孔を形成した後に該仕切板を
引抜くことを特徴とする。
<<Structure of the Invention>> In order to achieve the above-mentioned object, the present invention provides a structure in which the ends of the built-in reinforcing bar cage are overlapped with each other in a hole for excavating a reinforcing bar cage provided with a hollow joint box at one end. In the underground continuous wall construction method in which the trailing wall is sequentially connected, the joint plate of the joint box is buried, and the partition plate and side plate are each removable, and between the partition plate and the excavation hole. After filling with a filler such as crushed stone, the side plate is pulled out while the poured concrete is in a semi-hardened state, and the partition plate is pulled out after the trailing excavation hole is formed on the side of the filler. .

≪作用≫ 充填材は打設されたコンクリートがジヨイント
ボツクスの仕切板側へ廻り込みを防止し、仕切板
の引抜き容易性を確保する。
<<Function>> The filler prevents the poured concrete from going around to the partition plate side of the joint box and ensures ease of pulling out the partition plate.

また、側板は打設コンクリートの半硬化状態で
引抜くため、比較的容易に行なえる。
Furthermore, since the side plates are pulled out from the cast concrete in a semi-hardened state, this process is relatively easy.

≪実施例≫ 以下、この発明の好適な実施例について添附図
面を参照にして詳細に説明する。
<<Example>> Hereinafter, preferred embodiments of the present invention will be described in detail with reference to the accompanying drawings.

第1図はこの発明に係る地中連続壁工法の一実
施例を工程順に示す平面図である。
FIG. 1 is a plan view showing one embodiment of the underground continuous wall construction method according to the present invention in the order of steps.

同図に示す工法は、上述した従来工法と同じよ
うに、先行掘削孔1aを掘削し、連結側の端部に
ジヨイントボツクス10を取付けた鉄筋篭3を建
込み挿入し、コンクリートを打設して先行壁体7
を形成した後に、ジヨイントボツクス10の側方
に後行掘削孔1bを形成し、他の鉄筋篭3′を鉄
筋篭3,3′の端部同志がオーバーラツプするよ
うに挿入した後、コンクリートを打設して後行壁
体8を順次連結形成するものであつて、これらの
構成は同じである。
The construction method shown in the figure is similar to the conventional construction method described above, in which a preliminary excavation hole 1a is excavated, a reinforcing bar cage 3 with a joint box 10 attached to the connecting end is inserted, and concrete is poured. Leading wall 7
After forming, a trailing excavation hole 1b is formed on the side of the joint box 10, and another reinforcing bar cage 3' is inserted so that the ends of the reinforcing bar cages 3 and 3' overlap, and then concrete is poured. The trailing wall bodies 8 are sequentially connected and formed by pouring, and these structures are the same.

そして、同図に示す工法は以下に説明する点に
特徴がある。
The construction method shown in the figure is characterized by the following points.

すなわち、先行掘削孔1a内に鉄筋篭3を建込
んだ後、ジヨイントボツクス10の外側端と先行
掘削孔1aの側端間に砕石などの比較的粗い充填
材11を充填する。
That is, after the reinforcing bar cage 3 is erected in the pre-excavation hole 1a, a relatively coarse filler 11 such as crushed stone is filled between the outer end of the joint box 10 and the side end of the pre-excavation hole 1a.

ここで、本発明のジヨイントボツクス10は、
連結形成される壁体7,8間に介在する接合板1
2と、掘削孔1a,1bの側面に位置する一対の
側板14,14と後行掘削孔1bの形成後に引抜
かれる仕切板16とから構成されている。
Here, the joint box 10 of the present invention includes:
Joint plate 1 interposed between wall bodies 7 and 8 to be connected
2, a pair of side plates 14, 14 located on the side surfaces of the drilling holes 1a, 1b, and a partition plate 16 that is pulled out after the trailing drilling hole 1b is formed.

接合板12は、格子状に編組した水平筋3aと
垂直筋3bからなる鉄筋篭3の、水平筋3aが貫
通した状態で鉛直に取付けられ、接合板12から
所定の間隔をおいて細幅な挾持板18,18が水
平筋3aを貫通して取付けられており、接合板1
2と各挾持板18,18とは、鉛直方向に適宜間
隔で配設された繋ぎ材20で間隔を保持されてい
る。
The joint plate 12 is attached vertically to a reinforcing bar cage 3 consisting of horizontal reinforcements 3a and vertical reinforcements 3b braided in a lattice shape, with the horizontal reinforcements 3a penetrating through it. The clamping plates 18, 18 are attached to pass through the horizontal reinforcement 3a, and the joint plate 1
2 and the respective clamping plates 18, 18 are maintained at intervals by connecting members 20 disposed at appropriate intervals in the vertical direction.

一方、仕切板16は平板状の基部16aの両端
に、これと直交する一対の側部16bを高剛性材
で一体形成した断面がコ字形をなし、両端部16
b,16bは、側板14,14の内側面に沿つて
延び、それぞれの端部が挾持板18,18に当接
するように配置される。
On the other hand, the partition plate 16 has a U-shaped cross section, with a pair of side parts 16b perpendicular to the flat base part 16a integrally formed with a high-rigidity material at both ends of the flat base part 16a.
b, 16b extend along the inner surfaces of the side plates 14, 14, and are arranged such that their respective ends abut against the clamping plates 18, 18.

そして、側板14は両端部に一対の突起14
a,14aが形成された凹状断面をなし、一方の
突起14aを接合板12と挾持板18との間に嵌
合し、他方の突起14aを仕切板16の外側面に
係合して、仕切板16の側部16bを抱き込むよ
うにして引抜き可能に装着されている。
The side plate 14 has a pair of protrusions 14 at both ends.
a, 14a are formed, one protrusion 14a is fitted between the joint plate 12 and the clamping plate 18, and the other protrusion 14a is engaged with the outer surface of the partition plate 16 to form a partition. It is attached so that it can be pulled out so as to embrace the side portion 16b of the plate 16.

鉄筋篭3の建込が終わると、ジヨイントボツク
ス10内を除きコンクリートの打設が行なわれ
る。
Once the reinforcing bar cage 3 has been erected, concrete is poured except for inside the joint box 10.

打設されたコンクリートは、側板14と掘削孔
1aとの間隙から仕切板16側に廻り込もうとす
るが、ここには上記充填材11があるため、これ
によつて廻り込みが阻止される。
The poured concrete tries to go around to the partition plate 16 side from the gap between the side plate 14 and the excavated hole 1a, but since the above-mentioned filler material 11 is present here, this prevents it from going around. .

コンクリートの打設後、セメントの硬化が進行
し、半硬化状態、すなわちそれ自体じ自立状態が
確保される程度の硬度が発現されると、上記側板
14,14の引抜きが行なわれる。
After the concrete is placed, the cement hardens and becomes semi-hardened, that is, hard enough to maintain its own self-supporting state, and then the side plates 14, 14 are pulled out.

引抜きは打設コンクリートの半硬化状態で行な
われるため、比較的簡単に行なえるとともに、引
抜き後には側板14,14のあつた位置に第1図
Bに示すように空隙22が形成される。
Since the drawing is carried out while the cast concrete is in a semi-hardened state, it can be carried out relatively easily, and after drawing, a void 22 is formed at the position where the side plates 14, 14 were located, as shown in FIG. 1B.

次いで、仕切板16の側方に後行掘削孔1bが
掘削される。
Next, a trailing excavation hole 1b is drilled on the side of the partition plate 16.

この場合、充填材11は掘削とともに破壊し、
仕切板16が徐々に露出し、後行掘削孔1bの形
成によつて充填材11の除去も行なわれる。
In this case, the filler material 11 is destroyed during excavation,
The partition plate 16 is gradually exposed, and the filler 11 is also removed by forming the trailing excavation hole 1b.

後行掘削孔1bの形成が終了すると、上記仕切
板16の引抜きが行なわれるが、仕切板16は、
その周りが空隙22と充填材11の除去によつて
拘束されておらず、先行壁体7中に埋没していな
いので容易に引抜ける。
When the formation of the trailing excavation hole 1b is completed, the partition plate 16 is pulled out.
The surrounding area is not restricted by the void 22 and the removal of the filler 11, and it is not buried in the preceding wall 7, so it can be easily pulled out.

しかる後、他端にジヨイントボツクス10を取
付けた他の鉄筋篭3′を後行掘削孔1b内に挿入
し、鉄筋篭3と3′の端部同志をオーバーラツプ
させて(第1図C参照)、コンクリートの打設を
行ない後行壁体8を連結形成する。
After that, another reinforcing bar cage 3' with a joint box 10 attached to the other end is inserted into the trailing excavation hole 1b, and the ends of the reinforcing bar cages 3 and 3' are overlapped (see Fig. 1C). ), concrete is placed and the trailing wall 8 is connected and formed.

以後、上記工程を順に繰り返すことで所定の地
中連続壁が形成される。
Thereafter, by repeating the above steps in order, a predetermined underground continuous wall is formed.

なお、上記実施例では鉄筋篭3,3′に予めジ
ヨイントボツクス10の各構成板を、それぞれ取
付けて掘削孔1a,1b内に建込む場合で説明し
たが、例えば掘削孔1a,1bが比較的浅い時に
は、接合板12、側板14などは鉄筋篭3,3′
の建込み後に取付けてもよい。
In the above embodiment, each component plate of the joint box 10 is attached to the reinforcing bar baskets 3 and 3' in advance and is constructed in the excavated holes 1a and 1b. However, for example, the excavated holes 1a and 1b are compared. When the target is shallow, the joint plate 12, side plate 14, etc.
It may be installed after construction.

また、後行壁体8のコンクリート打設に先立つ
て、ジヨイントボツクス10のあつた位置を洗
浄、スライム処理して施工してもよい。
Furthermore, prior to concrete pouring of the trailing wall 8, the hot position of the joint box 10 may be cleaned and treated with slime.

≪発明の効果≫ 以上、実施例で詳細に説明したように、本発明
の地中連続壁工法によれば、ジヨイントボツクス
の側板の引抜きは、打設コンクリートの半硬化状
態で行なわれるため容易になされるとともに、打
設コンクリートの廻り込みが充填材で防止され、
且つ側板も前もつて引抜かれているため仕切板も
容易に引抜け、工期の短縮を可能にする。
≪Effects of the Invention≫ As explained above in detail in the examples, according to the underground continuous wall construction method of the present invention, the side plates of the joint box can be easily pulled out while the poured concrete is in a semi-hardened state. At the same time, the poured concrete is prevented from going around by the filling material,
In addition, since the side plates are also pulled out from the front, the partition plates can also be easily pulled out, making it possible to shorten the construction period.

【図面の簡単な説明】[Brief explanation of drawings]

第1図A,B,Cは本発明工法の一実施例を工
程順に示す要部平面図、第2図は鉄筋篭の側面
図、第3図、第4図は従来工法の工程を順に示す
それぞれの平面図である。 10……ジヨイントボツクス、11……充填
材、12……接合板、14……側板、16……仕
切板、18……挾持板。
Figures 1A, B, and C are plan views of essential parts showing an example of the method of the present invention in the order of steps, Figure 2 is a side view of a reinforcing bar basket, and Figures 3 and 4 show the steps of the conventional method in order. FIG. 3 is a plan view of each. 10... Joint box, 11... Filler, 12... Joining plate, 14... Side plate, 16... Partition plate, 18... Holding plate.

Claims (1)

【特許請求の範囲】[Claims] 1 一端に中空状のジヨイントボツクスが設けら
れた鉄筋篭を掘削孔内に建込み鉄筋篭の端部同志
をオーバーラツプさせて先・後行壁を順次連結形
成する地中連続壁工法において、該ジヨイントボ
ツクスの接合板を埋設する一方、仕切板と側板と
をそれぞれ引抜き可能となし、該仕切板と該掘削
孔との間に砕石などの充填材を充填した後、打設
コンクリートの半硬化状態で該側板を引抜き、該
充填材の側方に該後行掘削孔を形成した後に該仕
切板を引抜くことを特徴とする地中連続壁工法。
1. In the underground continuous wall construction method, a reinforcing bar cage with a hollow joint box provided at one end is built into the excavation hole, and the ends of the reinforcing bar cages are overlapped to sequentially connect the leading and trailing walls. While the joint board of the joint box is buried, the partition board and side board are made removable, and after filling the space between the partition board and the excavation hole with filler such as crushed stone, the poured concrete is semi-hardened. An underground continuous wall construction method characterized in that the side plate is pulled out in a state where the partition plate is pulled out, and the partition plate is pulled out after forming the trailing excavation hole on the side of the filler.
JP9803785A 1985-05-10 1985-05-10 Underground continuous wall construction wall Granted JPS61257530A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP9803785A JPS61257530A (en) 1985-05-10 1985-05-10 Underground continuous wall construction wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP9803785A JPS61257530A (en) 1985-05-10 1985-05-10 Underground continuous wall construction wall

Publications (2)

Publication Number Publication Date
JPS61257530A JPS61257530A (en) 1986-11-15
JPH0517327B2 true JPH0517327B2 (en) 1993-03-08

Family

ID=14208853

Family Applications (1)

Application Number Title Priority Date Filing Date
JP9803785A Granted JPS61257530A (en) 1985-05-10 1985-05-10 Underground continuous wall construction wall

Country Status (1)

Country Link
JP (1) JPS61257530A (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2791072B1 (en) 1999-03-19 2001-06-15 Cie Du Sol DEVICE FOR AIDING FORMWORK

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS55116922A (en) * 1979-03-02 1980-09-08 Ohbayashigumi Ltd Jointing method of continuous underground wall
JPS57130622A (en) * 1981-02-06 1982-08-13 Taisei Corp Construction of continuous underground wall

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS55116922A (en) * 1979-03-02 1980-09-08 Ohbayashigumi Ltd Jointing method of continuous underground wall
JPS57130622A (en) * 1981-02-06 1982-08-13 Taisei Corp Construction of continuous underground wall

Also Published As

Publication number Publication date
JPS61257530A (en) 1986-11-15

Similar Documents

Publication Publication Date Title
KR100850028B1 (en) Construction method using concrete mould for concrete piles cast in position
JP4440497B2 (en) Construction method of underground continuous wall and construction method of underground structure
JPH0517327B2 (en)
JPS61122320A (en) Method of coupling continuous underground wall with underground structure
JPS61257529A (en) Underground continuous wall construction work
JPH09324422A (en) Cast-in-place compound pile and building method therefor
JPH041811B2 (en)
JP3586839B2 (en) In-situ formed concrete pile and its forming method
JPH0721196B2 (en) Reverse construction method of underground structure
JPH0415878B2 (en)
JPS6248011B2 (en)
JPH01315520A (en) Underground outer wall constructing method for superstructure
JP2603307B2 (en) Retaining method for the upper part of the continuous underground wall
JP2663087B2 (en) How to build underground structures
JPH0370050B2 (en)
JPS6178915A (en) Formation work of underground continuous wall
KR960001455Y1 (en) A follow-devices for h-section steel pile
JP2689743B2 (en) How to build an underground structure
JPH0551727B2 (en)
JPH0310767B2 (en)
JPH10140557A (en) Construction method of cast-in-place diaphragm wall with hollow
JP2524892B2 (en) Building foundation method
JPH055970B2 (en)
JPH0310768B2 (en)
JPH042133B2 (en)