JPH0516497B2 - - Google Patents

Info

Publication number
JPH0516497B2
JPH0516497B2 JP7666986A JP7666986A JPH0516497B2 JP H0516497 B2 JPH0516497 B2 JP H0516497B2 JP 7666986 A JP7666986 A JP 7666986A JP 7666986 A JP7666986 A JP 7666986A JP H0516497 B2 JPH0516497 B2 JP H0516497B2
Authority
JP
Japan
Prior art keywords
hole
water
ground
injection hole
cement milk
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP7666986A
Other languages
Japanese (ja)
Other versions
JPS62233324A (en
Inventor
Moichi Horiie
Toshuki Takada
Kenji Kita
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kumagai Gumi Co Ltd
Original Assignee
Kumagai Gumi Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kumagai Gumi Co Ltd filed Critical Kumagai Gumi Co Ltd
Priority to JP7666986A priority Critical patent/JPS62233324A/en
Publication of JPS62233324A publication Critical patent/JPS62233324A/en
Publication of JPH0516497B2 publication Critical patent/JPH0516497B2/ja
Granted legal-status Critical Current

Links

Description

【発明の詳細な説明】 (技術分野) 本発明は、セメントミルクを用いるグラウチン
グ方法に関し、特に砂層、砂礫層、シルト層、軟
岩層等の地盤の改良に適したグラウチング方法お
よび装置に関する。
DETAILED DESCRIPTION OF THE INVENTION (Technical Field) The present invention relates to a grouting method using cement milk, and particularly to a grouting method and apparatus suitable for improving ground such as sand layers, gravel layers, silt layers, and soft rock layers.

(従来技術) 砂層、砂礫層、シルト層、軟岩層等の比較的軟
らかい地盤の改良においては、2種類以上の液体
を反応させる溶液タイプのグラウト材を用いる方
法があるが、廉価で耐久性に優れたセメントミル
クをグラウト材として用いるグラウチング方法が
多く採用されている。
(Prior art) When improving relatively soft ground such as sand layers, gravel layers, silt layers, soft rock layers, etc., there is a method of using a solution type grout that reacts two or more types of liquids, but this method is inexpensive and durable. A grouting method using superior cement milk as a grouting material is widely adopted.

この種のグラウチング方法の一つとして、ボー
リング機械により地盤に開けた穴に噴出パイプを
配置し、セメントミルクから成るグラウト材を前
記噴出パイプから前記穴に供給することにより地
盤にグラウト材を圧入する方法がある。しかし、
この方法は、セメントミルクの注入抵抗が溶液タ
イプのグラウト材のそれに比べて大きいため、透
水係数の小さい地盤の場合、地盤に開けた前記穴
の近傍の薄い層のみにグラウト材が浸透するにす
ぎず、止水効果が低い。
One of these types of grouting methods involves placing a spouting pipe in a hole drilled in the ground by a boring machine, and supplying grouting material made of cement milk into the hole from the spouting pipe, thereby press-fitting the grouting material into the ground. There is a way. but,
In this method, the injection resistance of cement milk is greater than that of solution-type grout, so in the case of ground with a low permeability coefficient, the grout penetrates only into a thin layer near the hole drilled in the ground. However, the water stopping effect is low.

グラウチング方法の他の一つとして、前記穴に
圧縮空気を吹き込んで地盤中の水を排除した後、
グラウト材を注入する方法がある。しかし、この
方法では、前記穴の周囲の極限られた範囲の地盤
空隙にセメントミルクが注入されるだけであり、
セメントミルクを広い範囲にわたつて注入するこ
とができない。これは、前記穴に空気を吹き込む
ことにより前記穴の周囲の地盤空隙が乾燥され、
この結果その後に注入されるセメントミルクがそ
の水分を穴の周囲の地盤空隙壁に吸収されて穴周
囲の極限られた範囲で凝結するためと考えられ
る。
Another grouting method is to blow compressed air into the hole to remove water in the ground, and then
There is a method of injecting grouting material. However, with this method, cement milk is only injected into the ground voids in an extremely limited range around the hole;
Cement milk cannot be injected over a wide area. This is done by blowing air into the hole to dry the ground voids around the hole,
As a result, it is thought that the water content of the cement milk injected afterwards is absorbed by the ground cavity walls around the hole and condenses in a very limited area around the hole.

(発明の目的) 本発明は、セメントミルクから成るグラウト材
を広い範囲にわたつて効果的に注入することがで
きるグラウチング方法を提供することを目的とす
る。
(Objective of the Invention) An object of the present invention is to provide a grouting method that can effectively inject grouting material made of cement milk over a wide range.

(発明の構成) 本発明のグラウチング方法は、地盤に穴を穿
ち、該穴に圧縮空気のような圧縮気体を吹き込ん
で前記穴の周囲の地盤に送気した後、前記穴に水
を注入し、その後セメントミルクを前記穴に供給
して送気領域に前記セメントミルクを注入するこ
とを特徴とする。
(Structure of the Invention) The grouting method of the present invention involves drilling a hole in the ground, blowing compressed gas such as compressed air into the hole to supply air to the ground around the hole, and then injecting water into the hole. , and then supplying cement milk to the hole to inject the cement milk into the air supply area.

本発明のグラウチング方法は、また、地盤に第
1および第2の穴を穿ち、該第2の穴内の水また
は空気を排出しつつ前記第1の穴に圧縮空気のよ
うな圧縮気体を吹き込んで該第1の穴の周囲の地
盤に送気した後、前記第1の穴に水を注入し、そ
の後前記第2の穴内の水または空気を排出しつつ
前記第1の穴にセメントミルクを供給して送気領
域に前記セメントミルクを注入することを特徴と
する。
The grouting method of the present invention also includes drilling first and second holes in the ground, and blowing compressed gas such as compressed air into the first hole while draining water or air in the second holes. After supplying air to the ground around the first hole, water is injected into the first hole, and then cement milk is supplied to the first hole while discharging the water or air in the second hole. The method is characterized in that the cement milk is injected into the air supply area.

(発明の作用効果) 本発明は、地盤に穿たれた穴に圧縮気体を吹き
込むことにより、その優れた透過性と膨張性とに
起因する注入障害物の優れた除去能力により、前
記穴の周囲の広い範囲にわたつて地盤空隙の浸透
性が改善される。この地中の送気領域の空隙は、
吹き込まれた圧縮気体により乾燥されても、次に
前記穴に注入される水により前記地盤空隙の回り
の壁すなわち地盤空隙壁が湿気を有することにな
る。
(Operations and Effects of the Invention) By blowing compressed gas into a hole drilled in the ground, the present invention has an excellent ability to remove injection obstructions due to its excellent permeability and expandability, thereby improving the ability to remove injection obstacles around the hole. The permeability of ground voids is improved over a wide range of areas. The voids in this underground air supply area are
Even if it is dried by the blown compressed gas, the walls around the ground void, ie, the ground void walls, will have moisture due to the water that is then injected into the hole.

このため、本発明によれば、水を穴に注入した
後にセメントミルクを穴に注入するから、該セメ
ントミルクの水分が地盤空隙壁に吸収されず、従
つて注入されたセメントミルクは、穴の周囲で凝
結することなく、送気領域を経て穴の周囲の広い
範囲の地盤空隙にまで達し、穴の周囲の広い範囲
にわたつて注入される。
Therefore, according to the present invention, since cement milk is injected into the hole after water is injected into the hole, the moisture in the cement milk is not absorbed by the ground cavity wall, and therefore the injected cement milk is absorbed into the hole. Without condensation in the surrounding area, the gas passes through the air delivery area into the ground voids in a wide area around the hole, and is injected over a wide area around the hole.

また、本発明は、第1の穴への圧縮気体の吹き
込み時あるいはまたセメントミルクの注入時に第
2の穴内の水または気体の排出を連続的または間
欠的に行うため、短時間で前記送気の効果を得る
ことができ、セメントミルクを第1の穴の周囲の
より広い地盤にわたつて注入することができる。
Further, the present invention continuously or intermittently discharges the water or gas in the second hole when blowing compressed gas into the first hole or when pouring cement milk, so that the air supply is completed in a short time. effect can be obtained, and the cement milk can be injected over a wider ground area around the first hole.

さらに、グラウト材を注入すべき領域の境界に
沿つて複数の第2の穴を設けると、圧縮気体がグ
ラウト材の注入範囲を制限することができるの
で、好ましい。
Furthermore, it is preferable to provide a plurality of second holes along the boundaries of the area in which the grouting material is to be injected, since this allows the compressed gas to limit the area in which the grouting material is to be injected.

(実施例) 以下、図面に示す本発明の実施例について説明
する。
(Example) Hereinafter, an example of the present invention shown in the drawings will be described.

図に示す実施例では、地盤10に縦方向へ伸び
る複数の穴12,14,16を穿ち、これらのう
ちの少なくとも一つを圧縮空気およびセメントミ
ルクのための注入穴12とし、残りの穴を水また
は空気のための排出穴14,16として使用す
る。
In the embodiment shown in the figure, a plurality of longitudinally extending holes 12, 14, 16 are drilled in the ground 10, at least one of which serves as an injection hole 12 for compressed air and cement milk, and the remaining holes Used as drainage holes 14, 16 for water or air.

地上に設置されたグラウチング装置18は、コ
ンプレツサ20を含む。コンプレツサ20は該コ
ンプレツサに接続された送風ホース22と、注入
穴12に接続された注入パイプ24とを経て注入
穴12に圧縮空気を供給する。送風ホース22に
は、流量調節弁26が設けられており、該弁26
によりコンプレツサ20から注入穴12へ供給す
る圧縮空気の圧力を調節することができる。注入
パイプ24には、注入穴12内の圧力を指示する
圧力計28が設けられている。
The grouting device 18 installed on the ground includes a compressor 20. The compressor 20 supplies compressed air to the injection hole 12 through a blowing hose 22 connected to the compressor and an injection pipe 24 connected to the injection hole 12. The blowing hose 22 is provided with a flow control valve 26, and the valve 26
This allows the pressure of compressed air supplied from the compressor 20 to the injection hole 12 to be adjusted. The injection pipe 24 is provided with a pressure gauge 28 that indicates the pressure within the injection hole 12.

グラウチング装置18は、また、グラウトミキ
サ・アジテータ30を含む。該グラウトミキサ・
アジテータ30は、セメントおよび水を混練して
セメントミルクを作るミキサと、これを溜て撹拌
するアジテータとを備える。
Grouting apparatus 18 also includes a grout mixer agitator 30 . The grout mixer
The agitator 30 includes a mixer that mixes cement and water to produce cement milk, and an agitator that collects and stirs the cement milk.

グラウトミキサ・アジテータ30は、ホース3
2を経て注入ポンプ34に接続されているととも
にホース36を経て流量圧力自動調節器38に接
続されている。注入ポンプ34はホース40を経
て流量圧力自動調節器38に接続され、流量圧力
自動調節器38およびホース42を経て注入パイ
プ24に接続されている。パイプ42には、停止
弁44が設けられている。
The grout mixer/agitator 30 has a hose 3
2 to an injection pump 34, and a hose 36 to an automatic flow rate and pressure regulator 38. The injection pump 34 is connected to a flow pressure regulator 38 via a hose 40 and to the injection pipe 24 via a flow pressure regulator 38 and a hose 42 . The pipe 42 is provided with a stop valve 44 .

排出穴14,16には、それぞれ排水および排
気パイプ46,48が配置されている。排水パイ
プ46は、パイプ50を経て排水設備54に接続
されている。排気パイプ48には、二つの停止弁
56と圧力計58とが設けられている。
Drain and exhaust pipes 46, 48 are arranged in the discharge holes 14, 16, respectively. Drainage pipe 46 is connected to drainage equipment 54 via pipe 50. The exhaust pipe 48 is provided with two stop valves 56 and a pressure gauge 58.

グラウチング時、グラウチング装置18は、排
出設備54により排出穴14より水60を排水
し、また排出穴16より水および空気62を排出
しつつコンプレツサ20により注入穴12に圧縮
空気を供給する。このように排出穴14より排水
し、排水穴16より排水および排気しつつ圧縮空
気を注入穴12に供給すると、送気の効果を短時
間で効果的に得ることができる。しかし、注入穴
12への圧縮空気の供給時に排出穴14,16よ
り排水および排気を継続しなくてもよい。圧縮空
気の圧力および送風時間は、地盤の浮き上がり、
亀裂の発生等により地盤が破壊しない値に設定す
る。
During grouting, the grouting device 18 discharges water 60 from the discharge hole 14 using the discharge facility 54, and supplies compressed air to the injection hole 12 using the compressor 20 while discharging water and air 62 from the discharge hole 16. By supplying compressed air to the injection hole 12 while draining water from the discharge hole 14 and draining and exhausting water from the drain hole 16 in this manner, the effect of air supply can be effectively obtained in a short time. However, when compressed air is supplied to the injection hole 12, drainage and exhaust from the discharge holes 14 and 16 need not be continued. The compressed air pressure and blowing time are determined by the lifting of the ground,
Set to a value that will prevent the ground from being destroyed due to the occurrence of cracks, etc.

次に、送気された領域内の地盤空隙壁を湿らせ
るべく、注入ポンプ34によりグラウトミキサ・
アジテータ30内の水を流量圧力自動調節器38
を経て注入穴12へ供給する。これにより、注入
穴12の周囲の広い範囲にわたる地盤空隙が湿
る。このときの水の圧力および供給時間は、送気
された領域内の土粒子を湿らせる程度でよいか
ら、僅かでよい。
The grout mixer is then injected by injection pump 34 to moisten the ground cavity walls within the insulated area.
The flow rate pressure automatic regulator 38 controls the water in the agitator 30.
It is supplied to the injection hole 12 through the. This wets the ground void over a wide area around the injection hole 12. The water pressure and supply time at this time may be small enough to moisten the soil particles in the area to which the air is blown.

次いで、注入ポンプ34により、グラウトミキ
サ・アジテータ30内のミキサにより作られたセ
メントミルクを注入穴12に注入する。これによ
り、セメントミルクは、前記の送気領域を経て穴
12の周囲の広い範囲に注入され、それによりそ
の範囲の地盤粒子と結合して止水層を形成する。
このとき、排水設備54を稼動させて排水穴14
内の排水を継続すれば、セメントミルクをより広
い範囲に注入することができる。
Then, the cement milk produced by the mixer in the grout mixer agitator 30 is injected into the injection hole 12 by the injection pump 34 . Thereby, the cement milk is injected into a wide area around the hole 12 through the air supply area, thereby combining with ground particles in that area to form a water stop layer.
At this time, the drainage equipment 54 is operated to drain the drainage hole 14.
If the drainage continues, cement milk can be injected over a wider area.

施工例 1 地下水位面が地表面下5mの砂礫層(粒径が
0.04mm〜20mm、透水係数が8×10-2cm/s、乾燥
密度が約1.7gr/cm3)に、下端5m間はストレーナ
状の加工をした直径60mmのパイプを深度25mmまで
鉛直に設置して注入穴とし、該注入穴を中心とす
る直径12mの範囲に前記注入穴と同様のパイプで
同深度の4つの排出穴を設けた。各排出穴から排
水しつつ注入穴に圧縮空気をゲージ圧で3Kg/cm2
で30分間吹き込み、次いで注入穴に水を0.5Kg
f/cm2で5分間注入し、その後各排出穴から排水
することなく注入穴にセメントミルクをゲージ圧
1Kgf/cm2で40分間注入し、3日間養生させた。
セメントミルクは、平均粒径が4ミクロン程度の
超微粒子セメントを1/3のセメント−水比(c/
w)とした。
Construction example 1 A gravel layer with a groundwater level 5m below the ground surface (grain size
0.04mm to 20mm, coefficient of permeability 8 x 10 -2 cm/s, dry density approximately 1.7gr/cm 3 ), and a 60mm diameter pipe with a strainer-like finish for 5m at the bottom is installed vertically to a depth of 25mm. An injection hole was formed, and four discharge holes with the same depth and the same pipe as the injection hole were provided in a range of 12 m in diameter around the injection hole. While draining water from each discharge hole, compressed air is applied to the injection hole at a gauge pressure of 3Kg/cm 2
for 30 minutes, then add 0.5Kg of water to the injection hole.
Cement milk was injected into the injection holes at a gauge pressure of 1 Kgf/cm 2 for 40 minutes without draining water from each discharge hole, and allowed to cure for 3 days.
Cement milk is made by mixing ultrafine cement with an average particle size of about 4 microns at a cement-water ratio of 1/3 (c/
w).

この結果、注入穴の周りの直径約2mの範囲の
地盤に当初の1/1900の透水性の止水層が形成され
た。
As a result, a water stop layer with 1/1900 of the original water permeability was formed in the ground area around the injection hole with a diameter of approximately 2 m.

施工例 2 施工例1を実施した現場付近の砂礫層に、施工
例1と同じ条件で中心の1つの注入穴とその周り
の4つの排出穴を設けた。各排出穴から排水しつ
つ中心の穴に圧縮空気をゲージ圧3Kgf/cm2で30
分間吹き込み、次いで注入穴に水を0.5Kgf/cm2
で5分間注入し、その後各排出穴から排水しつつ
注入穴に施工例1で用いたセメントミルクと同一
条件のセメントミルクをゲージ圧1Kgf/cm2で40
分間注入し、3日間養生させた。
Construction Example 2 In the gravel layer near the site where Construction Example 1 was carried out, one central injection hole and four discharge holes around it were provided under the same conditions as Construction Example 1. While draining water from each discharge hole, compressed air is supplied to the center hole at a gauge pressure of 3Kgf/ cm2 .
Blow water into the injection hole for 0.5Kgf/ cm2.
After that, while draining water from each discharge hole, pour cement milk under the same conditions as the cement milk used in construction example 1 into the injection hole at a gauge pressure of 1 Kgf/cm 2 at a gauge pressure of 1 kgf/cm 2.
It was injected for 3 minutes and allowed to cure for 3 days.

この結果、注入穴の周りの直径約2mの範囲の
地盤に当初の1/2000の透水性の止水層が形成され
た。
As a result, a water stop layer with 1/2000 of the original water permeability was formed in the ground area around the injection hole with a diameter of approximately 2 m.

比較例 1 施工例1を実施した現場付近の砂礫層に施工例
1と同一条件で中心の注入穴とその周りの4つの
排出穴を設けた。各排出穴から排出しつつ注入穴
に圧縮空気をゲージ圧で3Kgf/cm2で30分間吹き
込み、次いで各排出穴から排水しつつ注入穴に施
工例1で用いたセメントミルクを施工例1と同じ
条件で注入し、3日間養生させた。
Comparative Example 1 A central injection hole and four discharge holes around it were provided in a gravel layer near the site where Construction Example 1 was carried out under the same conditions as Construction Example 1. Blow compressed air into the injection hole at a gauge pressure of 3 kgf/cm 2 for 30 minutes while discharging from each discharge hole, then apply the cement milk used in Construction Example 1 to the injection hole while draining from each discharge hole. The cells were injected under the following conditions and allowed to cure for 3 days.

この結果、注入穴の周りの直径約1.5mの範囲
の地盤に当初の1/250の透水性の止水層が形成さ
れたにすぎなかつた。
As a result, a water stop layer with only 1/250 of the original water permeability was formed in the ground around the injection hole in an area of approximately 1.5 m in diameter.

比較例 2 施工例1を実施した現場付近の砂礫層に施工例
1と同一条件で中心の注入穴とその周りの4つの
排出穴を設けた。各排出穴から排水した後、注入
穴に水を0.5Kgf/cm2のゲージ圧で5分間注入し、
次いで各排出穴から排水しつつ注入穴に施工例1
で用いたセメントミルクを施工例1と同じ条件で
注入し、3日間養生させた。
Comparative Example 2 A central injection hole and four discharge holes around it were provided under the same conditions as in Construction Example 1 in a gravel layer near the site where Construction Example 1 was carried out. After draining water from each discharge hole, water was injected into the injection hole at a gauge pressure of 0.5Kgf/ cm2 for 5 minutes.
Next, while draining water from each discharge hole, apply construction example 1 to the injection hole.
The cement milk used in Example 1 was injected under the same conditions as in Construction Example 1, and allowed to cure for 3 days.

この結果、注入穴の周りの直径約1.5mの範囲
の地盤に当初の1/200の透水性の止水層が形成さ
れたにすぎなかつた。
As a result, a water stop layer with only 1/200 of the original water permeability was formed in the ground around the injection hole in an area of approximately 1.5 m in diameter.

施工例 3 地下水位が非常に低い砂礫層(粒径、透水係
数、乾燥密度等は施工例1の場合とほぼ同じ)に
施工例1と同一条件の1つの注入穴を穿ち、該注
入穴に圧縮空気を3Kgf/cm2のゲージ圧で30分間
吹き込み、次いで注入穴に水を0.5Kgf/cm2のゲ
ージ圧で5分間注入し、その後注入穴に施工例1
で用いたセメントミルクを施工例1と同じ条件で
注入し、3日間養生させた。
Construction example 3 One injection hole with the same conditions as construction example 1 was drilled in a gravel layer with a very low groundwater level (grain size, hydraulic conductivity, dry density, etc. are almost the same as construction example 1), and the injection hole was Compressed air was blown into the injection hole at a gauge pressure of 3 kgf/cm 2 for 30 minutes, then water was injected into the injection hole at a gauge pressure of 0.5 kgf/cm 2 for 5 minutes, and then the injection hole was filled with construction example 1.
The cement milk used in Example 1 was injected under the same conditions as in Construction Example 1, and allowed to cure for 3 days.

この結果、注入穴の周りの直径約2mの範囲の
地盤に当初の1/1800の透水性の止水層が形成され
た。
As a result, a water stop layer with 1/1800 of the original water permeability was formed in the ground area around the injection hole with a diameter of approximately 2 m.

比較例 3 施工例3を実施した現場付近の砂礫層に施工例
3と同じ条件の1つの注入穴を穿ち、該注入穴に
施工例3と同じ条件で圧縮空気を吹き込み、次い
で施工例3で用いたセメントミルクを施工例3と
同じ条件で注入し、3日間養生させた。
Comparative Example 3 One injection hole under the same conditions as Construction Example 3 was drilled in the gravel layer near the site where Construction Example 3 was carried out, compressed air was blown into the injection hole under the same conditions as Construction Example 3, and then The used cement milk was injected under the same conditions as in Construction Example 3 and allowed to cure for 3 days.

この結果、注入穴の周りの直径約1.5mの範囲
の地盤に当初の1/200の透水性の止水層が形成さ
れたにすぎなかつた。
As a result, a water stop layer with only 1/200 of the original water permeability was formed in the ground around the injection hole in an area of approximately 1.5 m in diameter.

比較例 4 施工例3を実施した現場付近の砂礫層に施工例
3と同じ条件の1つの注入穴を穿ち、該注入穴に
水を0.5Kgf/cm2のゲージ圧で5分間注入し、次
いで施工例3で用いたセメントミルクを施工例3
と同じ条件で注入し、3日間養生させた。
Comparative Example 4 One injection hole under the same conditions as Construction Example 3 was drilled in the gravel layer near the site where Construction Example 3 was carried out, water was injected into the injection hole at a gauge pressure of 0.5 kgf/cm 2 for 5 minutes, and then The cement milk used in Construction Example 3 was used in Construction Example 3.
The cells were injected under the same conditions as above and allowed to cure for 3 days.

この結果、注入穴の周りの直径約1.5mの範囲
の地盤に当初の1/200の透水性の止水層が形成さ
れたにすぎなかつた。
As a result, a water stop layer with only 1/200 of the original water permeability was formed in the ground around the injection hole in an area of approximately 1.5 m in diameter.

比較例 5 施工例3を実施した現場付近の砂礫層に施工例
3と同じ条件の1つの注入穴を穿ち、該注入穴に
水を3Kgf/cm2のゲージ圧で10分間注入し、次い
で施工例3で用いたセメントミルクを施工例3と
同じ条件で注入し、3日間養生させた。
Comparative Example 5 One injection hole under the same conditions as Construction Example 3 was drilled in the sand and gravel layer near the site where Construction Example 3 was carried out, water was injected into the injection hole at a gauge pressure of 3 kgf/cm 2 for 10 minutes, and then construction was carried out. The cement milk used in Example 3 was injected under the same conditions as in Construction Example 3, and allowed to cure for 3 days.

この結果、注入穴の周りの直径約0.2mの範囲
の地盤が固結したにすぎず、止水層の目的は達せ
られなかつた。
As a result, the ground within a diameter of approximately 0.2 m around the injection hole was only consolidated, and the purpose of the water stop layer was not achieved.

施工例 4 地下水位が非常に低い軟岩層(透水係数が2×
10-4cm/s、間隙率が0.34)に直径が700mm、深
さが30mの注入穴を垂直に穿ち、該注入穴を中心
とする直径6mの範囲に注入穴と同様の4つの排
出穴を垂直に穿ち、各排出穴から間欠的に排気し
つつ、注入穴の深さ25mの位置にパツカーを設置
したパイプを用いて下端5mの区間から圧縮空気
をゲージ圧3Kgf/cm2で40分間吹き込んだ。次い
で、注入穴に水をゲージ圧0.5Kgf/cm2で5分間
注入し、その後注入穴にセメントミルクをゲージ
圧2Kgf/cm2で60分間注入し、3日間養生させ
た。セメントミルクは、施工例1と同じ超微粒子
セメントを1/10のセメント−水比(c/w)とし
た。
Construction example 4 Soft rock layer with very low groundwater level (permeability coefficient is 2×
An injection hole with a diameter of 700 mm and a depth of 30 m is perpendicularly drilled in the hole (10 -4 cm/s, porosity is 0.34), and four discharge holes similar to the injection hole are formed within a 6 m diameter area around the injection hole. was drilled vertically, and while exhausting intermittently from each discharge hole, compressed air was pumped in from a 5m section at the lower end at a gauge pressure of 3Kgf/ cm2 for 40 minutes using a pipe with a police car installed at a depth of 25m from the injection hole. I blew it. Next, water was injected into the injection hole at a gauge pressure of 0.5 Kgf/cm 2 for 5 minutes, and then cement milk was injected into the injection hole at a gauge pressure of 2 Kgf/cm 2 for 60 minutes, followed by curing for 3 days. The cement milk used was the same ultrafine particle cement as in Construction Example 1, with a cement-water ratio (c/w) of 1/10.

この結果、注入穴の周りの直径1mの範囲の地
盤に当初の1/10の透水性の止水層が形成された。
As a result, a water stop layer with 1/10 the original water permeability was formed in the ground within a 1m diameter area around the injection hole.

比較例 6 施工例4を実施した現場付近の軟岩層に施工例
4と同一の条件で1つの注入穴を穿ち、25mの位
置にパツカーを設置したパイプを用いて下端5m
の区間から0.5Kgf/cm2のゲージ圧で水を5分間
注入し、次いで施工例4で用いたセメントミルク
を施工例4と同一条件で注入し、3日間養生させ
た。
Comparative example 6 One injection hole was drilled in the soft rock layer near the site where construction example 4 was carried out under the same conditions as construction example 4, and a pipe with a patch car installed at a position of 25 m was used to extend the lower end 5 m.
Water was injected from the section at a gauge pressure of 0.5 Kgf/cm 2 for 5 minutes, then the cement milk used in Construction Example 4 was injected under the same conditions as in Construction Example 4, and the mixture was allowed to cure for 3 days.

この結果、注入穴の周りの直径約0.5mの範囲
の地盤の固結度がわずかに増したが、透水性の低
下はほとんど見られなかつた。
As a result, the degree of consolidation of the ground in an area of approximately 0.5 m in diameter around the injection hole increased slightly, but there was almost no decrease in permeability.

施工例 5 施工例4を実施した現場付近の軟岩層に施工例
4と同一の条件で1つの注入穴とその周りの4つ
の排出穴を穿ち、前記注入穴以外の穴から排気し
つつ注入穴から施工例4と同一条件で圧縮窒素ガ
スを吹き込んだ。次いで、注入穴に水をゲージ圧
0.5Kgf/cm2で5分間注入し、その後注入穴に施
工例4で用いたセメントミルクを施工例4と同一
条件で注入し、3日間養生させた。
Construction Example 5 One injection hole and four discharge holes around it were drilled under the same conditions as Construction Example 4 in a soft rock layer near the site where Construction Example 4 was carried out, and the injection hole was closed while exhausting air from holes other than the injection hole. Compressed nitrogen gas was blown in under the same conditions as in Construction Example 4. Then add water to the injection hole at gauge pressure
It was injected for 5 minutes at 0.5 kgf/cm 2 , and then the cement milk used in Construction Example 4 was injected into the injection hole under the same conditions as Construction Example 4, and allowed to cure for 3 days.

この結果、施工例4とほぼ同じ程度の止水層が
形成された。
As a result, a water stop layer of approximately the same level as in Construction Example 4 was formed.

【図面の簡単な説明】[Brief explanation of the drawing]

図は本発明の実施に用いるグラウチング装置の
一実施例を示す概略図である。 10:地盤、12,14,16:縦穴、20:
コンプレツサ、30:グラウトミキサ・アジテー
タ、34:注入ポンプ、38:流量圧力自動調節
器、54:排水設備。
The figure is a schematic diagram showing one embodiment of a grouting device used for carrying out the present invention. 10: Ground, 12, 14, 16: Vertical hole, 20:
Compressor, 30: Grout mixer/agitator, 34: Injection pump, 38: Automatic flow rate pressure regulator, 54: Drainage equipment.

Claims (1)

【特許請求の範囲】 1 地盤に穴を穿ち、該穴に圧縮気体を吹き込ん
で前記穴の周囲の地盤に送気した後、前記穴に水
を注入し、その後セメントミルクを前記穴に供給
して送気領域に前記セメントミルクを注入するこ
とを特徴とする、グラウチング方法。 2 地盤に第1および第2の穴を穿ち、該第2の
穴内の水または気体を排出しつつ前記第1の穴に
圧縮気体を吹き込んで該第1の穴の周囲の地盤に
送気した後、前記第1の穴に水を注入し、その後
前記第2の穴内の水または気体を排出しつつ前記
第1の穴にセメントミルクを供給して送気領域に
前記セメントミルクを注入することを特徴とす
る、グラウチング方法。 3 前記第2の穴を複数穿ち、各第2の穴から水
または気体を排出する、特許請求の範囲第2項に
記載のグラウチング方法。
[Claims] 1. A hole is drilled in the ground, compressed gas is blown into the hole to supply the ground around the hole, water is injected into the hole, and then cement milk is supplied to the hole. A grouting method, characterized in that the cement milk is injected into the air supply area. 2. First and second holes were drilled in the ground, and while the water or gas in the second hole was discharged, compressed gas was blown into the first hole and into the ground around the first hole. and then injecting water into the first hole, and then supplying cement milk to the first hole while discharging the water or gas in the second hole to inject the cement milk into the air supply area. A grouting method characterized by: 3. The grouting method according to claim 2, wherein a plurality of second holes are bored and water or gas is discharged from each second hole.
JP7666986A 1986-04-04 1986-04-04 Grouting method Granted JPS62233324A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP7666986A JPS62233324A (en) 1986-04-04 1986-04-04 Grouting method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP7666986A JPS62233324A (en) 1986-04-04 1986-04-04 Grouting method

Publications (2)

Publication Number Publication Date
JPS62233324A JPS62233324A (en) 1987-10-13
JPH0516497B2 true JPH0516497B2 (en) 1993-03-04

Family

ID=13611821

Family Applications (1)

Application Number Title Priority Date Filing Date
JP7666986A Granted JPS62233324A (en) 1986-04-04 1986-04-04 Grouting method

Country Status (1)

Country Link
JP (1) JPS62233324A (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2760754B2 (en) * 1994-09-16 1998-06-04 日産建設株式会社 Method of protruding installation of grounding rod from underground conduit for cable and grounding rod used in this method
JP2014181484A (en) * 2013-03-19 2014-09-29 Nishimatsu Constr Co Ltd Ground improvement method
JP6330560B2 (en) * 2014-08-05 2018-05-30 株式会社大林組 Groundwater neutralization method and groundwater neutralization system
CN111622207B (en) * 2020-06-09 2021-04-27 广西路桥工程集团有限公司 Induced grouting method

Also Published As

Publication number Publication date
JPS62233324A (en) 1987-10-13

Similar Documents

Publication Publication Date Title
CN101245600B (en) Construction method for generating horizontal reinforcing body by high-pressure-double-liquid rotary spray technique
CN106759297A (en) A kind of construction method of support pile and three pipe high-pressure rotary jet grouting pile deep basal pits
CN108442358A (en) Pervious concrete grouting behind shaft or drift lining foundation consolidation process and transition stake and composite pile pile system
US8470406B2 (en) Method of spray application, and spray apparatus, for bentonite material
CN105350585B (en) The model test apparatus and model test of flocculant are injected in barged-in fill work progress
KR20090002833A (en) Sand pore fill construction apparatus
CN106480878A (en) A kind of upper and lower part expansion type soil cement is combined pile tube
JPH0516497B2 (en)
JPH0469251B2 (en)
US3180098A (en) Soil solidification process
CN104005416A (en) Method for processing major-diameter hole pile collapsed holes under high and steep slope plain fill back-pressing condition
CN103774645B (en) The construction method of a kind of soil cement and the stake of Combined concrete material
CN108867709A (en) A kind of waterproofing for basement method
JPH0656015B2 (en) Pile inside digging method
JPH0771183A (en) Frozen construction method
CN107975027A (en) The construction method that shield launching is reinforced with reaching end soil body
JPS60138112A (en) Pneumatic grouting method
KR100463104B1 (en) Pillar-shaped hardening structure formation equipment and the formation method of leading cement milk pressure injection
JP3515014B2 (en) Filling method for cavity
CN111270672A (en) High-pressure jet grouting pile construction method for water-rich round gravel stratum
JPS5810529B2 (en) How to strengthen weathered rock
RU2804093C1 (en) Method for producing horizontal and oblique ground-clay element by jetting
JPS6360169B2 (en)
CN106761823A (en) Exempt from wall for grouting segmentation cleaning bottom of hole retrusive controlling grouting method
JPH0548809B2 (en)

Legal Events

Date Code Title Description
LAPS Cancellation because of no payment of annual fees