JPH05141006A - Anchor frame and its fixing jig - Google Patents

Anchor frame and its fixing jig

Info

Publication number
JPH05141006A
JPH05141006A JP32808191A JP32808191A JPH05141006A JP H05141006 A JPH05141006 A JP H05141006A JP 32808191 A JP32808191 A JP 32808191A JP 32808191 A JP32808191 A JP 32808191A JP H05141006 A JPH05141006 A JP H05141006A
Authority
JP
Japan
Prior art keywords
anchor
anchor bolt
frame
plate
fixing jig
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP32808191A
Other languages
Japanese (ja)
Other versions
JPH0733690B2 (en
Inventor
Tomoaki Konoue
友明 鴻上
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Daiwa House Industry Co Ltd
Original Assignee
Daiwa House Industry Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Daiwa House Industry Co Ltd filed Critical Daiwa House Industry Co Ltd
Priority to JP3328081A priority Critical patent/JPH0733690B2/en
Publication of JPH05141006A publication Critical patent/JPH05141006A/en
Publication of JPH0733690B2 publication Critical patent/JPH0733690B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Joining Of Building Structures In Genera (AREA)

Abstract

PURPOSE:To improve the assembling property of anchor frames and workability, and position respective anchor bolts firmly at the anchor frames, and cure male screw sections. CONSTITUTION:The work of anchor frames 1 is executed by using anchor bolt fixing jigs 2. The anchor frames 1 are composed of an anchor plate 3 having anchor bolt retaining devices 4 and fixing legs 5, and four anchor bolts 6, and are formed to have no top plate. The fixing legs 5 are provided with ground fixing holes for inserting hole-in anchors 21 through. The anchor bolt retaining devices 4 consist of bottom plates 4a with screw holes 8 formed on, and split-shell-shaped rise pieces 4b set vertically on the bottom plates 4a. The anchor bolt fixing jigs 2 are composed of a plurality of caps 19 for covering the respective upper ends of the respective anchor bolts 6 for composing the anchor frames 1, and a connecting frame 20 for connecting the caps 19 to each other with.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】この発明は、建物の柱脚等の固定
に使用されるアンカーフレームと、その施工に使用する
アンカーボルト固定治具とに関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to an anchor frame used for fixing a column base of a building and an anchor bolt fixing jig used for the construction.

【0002】[0002]

【従来の技術】従来、アンカーボルトにPC鋼棒を使用
し、このアンカーボルトに緊張力を与えることにより、
基礎コンクリートと柱脚部を圧着し一体化する露出型剛
接合柱脚構造が採用されている。
2. Description of the Related Art Conventionally, a PC steel rod has been used for an anchor bolt and a tension force has been applied to the anchor bolt.
An exposed type rigid joint column base structure is adopted in which the foundation concrete and the column base are crimped and integrated.

【0003】このような圧着工法におけるアンカーボル
トの固定構造として、図4に示すアンカーフレームが用
いられている。このアンカーフレーム41は、基礎コン
クリート40を挟み込むために下部に設けたアンカープ
レート42と、位置出し兼用の天プレート44と、PC
鋼棒からなる複数本のアンカーボルト43とでなり、こ
れら3者42〜44は分解状態で運搬されて現場組立て
される。
An anchor frame shown in FIG. 4 is used as a fixing structure for anchor bolts in such a crimping method. The anchor frame 41 includes an anchor plate 42 provided at a lower portion for sandwiching the basic concrete 40, a ceiling plate 44 also serving as a positioning member, and a PC.
It is composed of a plurality of anchor bolts 43 made of steel rods, and these three members 42 to 44 are transported in a disassembled state and assembled on site.

【0004】現場において、捨コンクリート45には打
設時にアングル46を予め埋設しておく。このアングル
46に、アンカープレート42の下面に設けられたアン
グル47を載せ、アンカーフレーム41の位置出しを行
った後、溶接部48で溶接し固定する。
At the site, an angle 46 is previously embedded in the waste concrete 45 at the time of pouring. An angle 47 provided on the lower surface of the anchor plate 42 is placed on the angle 46, the anchor frame 41 is positioned, and then welded and fixed at a welded portion 48.

【0005】[0005]

【発明が解決しようとする課題】この構成のアンカーフ
レーム41によると、固定に際して前記のように溶接部
48の現場溶接が必要であるため、現場作業性が悪いう
えに、熱的影響を与えてはいけないPC鋼棒のアンカー
ボルト41に熱が加わる可能性があり、強度低下の危険
性が高かった。また、捨コンクリート45の打設時に、
アングル46を埋設しておかなければならず、これによ
っても現場作業性が悪くなり、工期が長くなるという問
題点があった。
According to the anchor frame 41 of this structure, since the welding portion 48 needs to be welded on site as described above, the workability at the site is poor and a thermal influence is exerted. There is a possibility that heat will be applied to the anchor bolt 41 of the PC steel rod which should not be done, and there was a high risk of strength reduction. Also, when placing the waste concrete 45,
The angle 46 must be buried, which also deteriorates the workability on site and prolongs the construction period.

【0006】さらに、天プレート44を用いて各アンカ
ーボルト43の上端をナット止めする構成であるため、
ナット止め箇所が多くて組み立て作業性が悪いという問
題点がある。そこで、天プレート44を省略することを
考えたが、天プレート44を省略すると、アンカーボル
ト43を直立状態に固定することが難しく、また位置決
めが困難になる。
Further, since the upper plate 44 is used to nut-lock the upper ends of the anchor bolts 43,
There is a problem that assembly workability is poor because there are many places where nuts are fixed. Therefore, it is considered that the top plate 44 is omitted, but if the top plate 44 is omitted, it is difficult to fix the anchor bolt 43 in the upright state and the positioning becomes difficult.

【0007】この発明の目的は、現場溶接が不要で、組
み立ても簡単であり、また捨てコンクリートの打設時に
アングル材等を埋設することが不要で、作業性の向上お
よび工期の短縮が図れるアンカーフレームを提供するこ
とである。
An object of the present invention is that an on-site welding is unnecessary, assembly is simple, and an angle member or the like is not buried at the time of placing waste concrete, so that the workability can be improved and the construction period can be shortened. It is to provide a frame.

【0008】請求項2の発明の目的は、天プレートを省
略したアンカーフレームにつき、アンカーボルト上端の
固定の確実と、位置出しの容易とが図れ、かつアンカー
ボルト上端の雄ねじ部分の養生が図れるアンカーボルト
固定治具を提供することである。
It is an object of the present invention to provide an anchor frame which does not include a ceiling plate, in which the upper end of the anchor bolt can be securely fixed and easily positioned, and the male screw portion of the upper end of the anchor bolt can be cured. It is to provide a bolt fixing jig.

【0009】請求項3の発明の目的は、アンカーフレー
ムの位置出しのより一層の容易化が図れるアンカーボル
ト固定治具を提供することである。
An object of the invention of claim 3 is to provide an anchor bolt fixing jig capable of further facilitating positioning of the anchor frame.

【0010】[0010]

【課題を解決するための手段】この発明のアンカーフレ
ームは、アンカープレートの上面に複数のアンカーボル
ト保持具を設けると共に、接地板部に地盤固定孔を有す
る固定脚を前記アンカープレートに設けたものである。
アンカーボルト保持具は、立上り片でアンカーボルトの
下端を直立状態に保持するものである。
In the anchor frame of the present invention, a plurality of anchor bolt holders are provided on the upper surface of the anchor plate, and fixing legs having ground fixing holes are provided on the ground plate portion on the anchor plate. Is.
The anchor bolt holding tool holds the lower end of the anchor bolt in an upright state by a rising piece.

【0011】請求項2のアンカーボルト固定治具は、ア
ンカーフレームを構成する各アンカーボルトの上端に各
々被さる複数のキャップを設け、これらキャップを連結
フレームで相互に連結したものである。
According to a second aspect of the present invention, there is provided an anchor bolt fixing jig, wherein a plurality of caps respectively covering the upper ends of the anchor bolts constituting the anchor frame are provided, and these caps are connected to each other by a connecting frame.

【0012】請求項3のアンカーボルト固定治具は、請
求項2の構成において、連結フレームの4方に下げ振り
を取付けたものである。
According to a third aspect of the present invention, in the anchor bolt fixing jig according to the second aspect, a plumb bob is attached to four sides of the connecting frame.

【0013】[0013]

【作用】この構成のアンカーフレームによると、アンカ
ープレートにアンカーボルトを現場組み立てし、この組
み立てられたアンカーフレームを固定脚で地盤の捨てコ
ンクリート上に載せ、固定脚の地盤固定孔において、ホ
ールインアンカ等で捨てコンクリートに固定する。この
ように、現場溶接を必要とせずに、アンカーフレームの
固定が行える。アンカープレートに設けられたアンカー
ボルト保持具は、アンカーボルトの傾きを防止して、ア
ンカーボルトの上端の位置ずれを防止する。そのため、
従来の各アンカーボルトの上端を相互に固定する天プレ
ートを省略することが可能になる。なお、各アンカーボ
ルトの上端は、基礎コンクリートの打設まで、必要に応
じて適宜の治具で相互に連結しておいても良い。
[Operation] According to the anchor frame of this structure, the anchor bolt is assembled on the anchor plate in the field, and the assembled anchor frame is placed on the concrete scrap of the ground with the fixed leg, and the hole-in anchor is fixed at the ground fixing hole of the fixed leg. Discard it and fix it on concrete. In this way, the anchor frame can be fixed without the need for on-site welding. The anchor bolt holder provided on the anchor plate prevents the anchor bolt from tilting and prevents displacement of the upper end of the anchor bolt. for that reason,
It is possible to omit the conventional top plate for fixing the upper ends of the respective anchor bolts to each other. The upper ends of the anchor bolts may be connected to each other with an appropriate jig as needed until the foundation concrete is poured.

【0014】請求項2のアンカーボルト固定治具による
と、連結フレームで相互に連結されたキャップが各アン
カーボルトの上端に被さることにより、剛性を高めてア
ンカーボルトの傾きを防止し、アンカーボルトの上端位
置の固定の確実を図ることができ、またこの治具を介し
て位置出しが行える。さらに、キャップが被さることに
よって、アンカーボルトの上端の雄ねじ部の養生が図
れ、配筋時等におけるアンカーボルトの雄ねじ部の傷つ
きが防止できる。
According to the anchor bolt fixing jig of the second aspect, the caps interconnected by the connecting frame cover the upper ends of the anchor bolts to enhance the rigidity and prevent the inclination of the anchor bolts. The upper end position can be securely fixed, and positioning can be performed through this jig. Furthermore, by covering the cap, the male screw portion of the upper end of the anchor bolt can be cured, and the male screw portion of the anchor bolt can be prevented from being damaged when arranging.

【0015】請求項3のアンカーボルト固定治具による
と、4方の下げ振りによってアンカーフレームの捨てコ
ンクリート上における基準線に対する位置決めが行え
る。
According to the anchor bolt fixing jig of the third aspect, the anchor frame can be positioned with respect to the reference line on the discarded concrete by swinging down in four directions.

【0016】[0016]

【実施例】この発明の一実施例を図1および図2に基づ
いて説明する。図1はアンカーフレーム1にアンカーボ
ルト固定治具2をセットした状態の斜視図である。アン
カーフレーム1は、アンカープレート3の上面の4隅に
アンカーボルト保持具4を設けると共に、アンカープレ
ート3に一対の固定脚5,5を設け、前記各アンカーボ
ルト保持具4の設置箇所に4本のアンカーボルト6を立
設したものである。アンカーボルト6はPC鋼棒の上下
端に雄ねじ部6a,6b(図2)を加工したものであ
り、表面には基礎コンクリートとの付着性を低下させる
ためのアンボンドコーティングが施してある。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS An embodiment of the present invention will be described with reference to FIGS. FIG. 1 is a perspective view showing a state in which an anchor bolt fixing jig 2 is set on an anchor frame 1. The anchor frame 1 is provided with anchor bolt holders 4 at four corners of the upper surface of the anchor plate 3, and a pair of fixing legs 5 and 5 is provided on the anchor plate 3, and four anchor bolt holders 4 are provided at the installation locations of the anchor bolt holders 4. The anchor bolts 6 are erected. The anchor bolt 6 is formed by processing male screw portions 6a and 6b (FIG. 2) on the upper and lower ends of a PC steel rod, and the surface thereof is provided with an unbond coating for reducing the adhesion to the basic concrete.

【0017】アンカープレート3は鉄板等の厚板からな
り、中央に空気抜き孔7を設けると共に、各アンカーボ
ルト保持具4の取付位置にアンカーボルト6の挿通孔
(図示せず)を設けてある。アンカーボルト保持具4
は、ねじ孔8の加工された丸プレートからなる底板4a
と、底板4a上に立設されてアンカーボルト6を嵌合す
る割り筒状の立上り片4bとで構成され、ねじ孔8をア
ンカープレート3のアンカーボルト挿通孔に整合させて
アンカープレート3に溶接される。アンカーボルト6
は、下端の雄ねじ部6bをアンカーボルト保持具4のね
じ孔8に螺合させてアンカープレート3の下面に突出さ
せ、その突出部分に丸座金9(図2)と共にPCナット
10を螺着して締めつけることにより、アンカープレー
ト3に立設される。
The anchor plate 3 is made of a thick plate such as an iron plate, has an air vent hole 7 in the center, and an insertion hole (not shown) for the anchor bolt 6 at the mounting position of each anchor bolt holder 4. Anchor bolt holder 4
Is a bottom plate 4a made of a round plate having screw holes 8
And a split tubular rising piece 4b which is erected on the bottom plate 4a and into which the anchor bolt 6 is fitted. The screw hole 8 is aligned with the anchor bolt insertion hole of the anchor plate 3 and welded to the anchor plate 3. To be done. Anchor bolt 6
Screw the male screw portion 6b at the lower end into the screw hole 8 of the anchor bolt holder 4 to project it to the lower surface of the anchor plate 3, and screw the PC washer 10 together with the round washer 9 (FIG. 2) to the projecting portion. It is erected on the anchor plate 3 by tightening.

【0018】各固定脚5は、アンカープレート3の隣合
う角部に溶接されたアングル材からなる一対の縦脚材1
1,11と、両縦脚材11,11間に渡って取付けられ
る接地部材12とからなる。接地部材12はアングル材
からなり、その横向きフランジからなる接地板部12a
に、複数の地盤固定孔13(図2)が設けられている。
接地部材12の縦脚材11への取付けは、縦脚材11に
設けられた上下方向の長孔14と接地部材12の貫通孔
15とに渡って挿通される高さ調整ボルト16により高
さ調整自在に行われる。17,18は、各々高さ調整ボ
ルト16に用いられる座金およびナットである。
Each fixed leg 5 is a pair of vertical leg members 1 made of angle members welded to adjacent corners of the anchor plate 3.
1, 11 and a grounding member 12 mounted across both vertical leg members 11, 11. The grounding member 12 is made of an angle material, and the grounding plate portion 12a is made of its lateral flange.
, A plurality of ground fixing holes 13 (Fig. 2) are provided.
The grounding member 12 is attached to the vertical leg member 11 by a height adjusting bolt 16 which is inserted through a vertically elongated hole 14 provided in the vertical leg member 11 and a through hole 15 of the grounding member 12. Adjustable. Reference numerals 17 and 18 denote washers and nuts used for the height adjusting bolt 16, respectively.

【0019】アンカーボルト固定治具2は、アンカーフ
レーム1の各アンカーボルト6の上端に被せられる蓋付
円筒からなる4個のキャップ19と、これらキャップ1
9を相互に連結した十字状の連結フレーム20とで構成
される。キャップ19と連結フレーム20とは溶接等で
固定してある。
The anchor bolt fixing jig 2 includes four caps 19 each of which is a cylinder with a lid and covers the upper ends of the anchor bolts 6 of the anchor frame 1, and these caps 1.
And a cross-shaped connecting frame 20 in which 9 are connected to each other. The cap 19 and the connecting frame 20 are fixed by welding or the like.

【0020】次に、施工方法を説明する。アンカーフレ
ーム1は、図2に示すようにアンカープレート3と、4
本のアンカーボルト6(図2には1本のみ図示)と、固
定脚5の構成部材となる2本の接地部材12とに分解し
た状態で現場に運搬される。現場において、アンカーフ
レーム1の各部材3,6,12の組み立てと、アンカー
ボルト固定治具2の取付けとが行われる。
Next, the construction method will be described. The anchor frame 1 includes anchor plates 3 and 4 as shown in FIG.
The anchor bolt 6 (only one is shown in FIG. 2) and the two grounding members 12, which are the constituent members of the fixed leg 5, are disassembled and transported to the site. At the site, the members 3, 6, 12 of the anchor frame 1 are assembled and the anchor bolt fixing jig 2 is attached.

【0021】この組み立ての後、アンカーフレーム1を
地盤の捨てコンクリート上に位置決めし、固定脚12の
地盤固定孔13において、ホールインアンカ21(図
1)によりアンカーフレーム1の据え付けを行う。ホー
ルインアンカ21は、捨コンクリートに設けた孔内に挿
入されて、上方からの引っ張り操作等により孔内で一部
が広がって固定されるものであり、ウェジット形式のも
のや、内面が雌ねじ部に形成されたスリーブ形式のもの
等が用いられる。ホールインアンカ21は、孔を明けな
がら挿入される自穿式のものであっても良い。アンカー
フレーム1の据え付けの後、基礎の配筋を行い、アンカ
ーボルト6の上端近傍の所定レベルまで基礎コンクリー
トを打設する。硬化後に、柱脚のベースプレート(図示
せず)を各アンカーボルト6に締付け固定する。
After this assembly, the anchor frame 1 is positioned on the waste concrete of the ground, and the anchor frame 1 is installed in the ground fixing hole 13 of the fixing leg 12 by the hole-in anchor 21 (FIG. 1). The hole-in anchor 21 is inserted into a hole provided in abandoned concrete and partly spreads and is fixed in the hole by pulling operation from above. A sleeve type or the like formed in the above is used. The hole-in anchor 21 may be a self-piercing type one that is inserted while making a hole. After the anchor frame 1 is installed, the reinforcement of the foundation is performed, and the foundation concrete is poured to a predetermined level near the upper end of the anchor bolt 6. After curing, the base plate (not shown) of the column base is tightened and fixed to each anchor bolt 6.

【0022】このアンカーフレーム1は、このように現
場溶接を行うことなく地盤に据え付けることができる。
そのため、PC鋼棒からなるアンカーボルト6を溶接熱
で劣化させて引っ張り耐力を低下させる恐れがなく、安
定した施工品質が得られる。また、現場施工性も向上す
る。しかも、固定脚5の地盤固定孔13でホールインア
ンカ21により地盤に固定することができ、従来のよう
に捨コンクリートにアンカーフレーム固定用のアングル
材等を予め埋設する必要がない。そのため、より一層現
場作業性が向上する。また、固定脚5が高さ調整ボルト
16と長孔14とで高さ調整自在であるため、アンカー
ボルト6のレベル出しが容易に行える。
The anchor frame 1 can be installed on the ground without performing the on-site welding in this way.
Therefore, there is no fear that the anchor bolt 6 made of a PC steel rod is deteriorated by welding heat and the tensile strength is lowered, and stable construction quality can be obtained. In addition, on-site workability is also improved. Moreover, the hole can be fixed to the ground by the hole fixing anchor 21 in the ground fixing hole 13 of the fixed leg 5, and it is not necessary to previously bury an angle member or the like for fixing the anchor frame in the waste concrete unlike the conventional case. Therefore, workability on site is further improved. Further, since the height of the fixed leg 5 can be freely adjusted by the height adjusting bolt 16 and the long hole 14, the anchor bolt 6 can be easily leveled.

【0023】また、このアンカーフレーム1は、従来の
天プレート44(図4)の代わりに、アンカーボルト固
定治具2を用いてアンカーボルト6の傾き防止と位置出
しを行うようにしており、アンカーボルト固定治具2は
各キャップ19をアンカーボルト6に被せるだけで取付
けられるため、従来の天プレートをナット止めするもの
に比べて、現場におけるアンカーフレーム1の組み立て
が簡単になる。しかも、アンカーボルト6の上端の雄ね
じ部6aがアンカーボルト固定治具2のキャップ19で
養生されるため、配筋時に雄ねじ部6を傷めることが防
止される。このように、アンカーフレーム1の組み立て
が簡単となり、またアンカーフレーム1の地盤への据え
付けが簡単になるため、工期の短縮、および施工コスト
の低減が図れる。
Further, in this anchor frame 1, instead of the conventional top plate 44 (FIG. 4), an anchor bolt fixing jig 2 is used to prevent the anchor bolt 6 from tilting and to position it. Since the bolt fixing jig 2 is attached only by covering the anchor bolts 6 with the caps 19, the assembly of the anchor frame 1 in the field is easier than in the conventional method in which the ceiling plate is fixed with nuts. Moreover, since the male screw portion 6a at the upper end of the anchor bolt 6 is cured by the cap 19 of the anchor bolt fixing jig 2, it is possible to prevent the male screw portion 6 from being damaged during bar arrangement. As described above, the anchor frame 1 is easily assembled and the anchor frame 1 is easily installed on the ground, so that the construction period can be shortened and the construction cost can be reduced.

【0024】アンカーボルト固定治具2は、単にキャッ
プ19をアンカーボルト6に被せるものであるため、従
来のナットで天プレートを固定するものに比べてアンカ
ーボルト6の固定の確実性が低下することが懸念される
が、各アンカーボルト6はアンカーボルト保持具4の立
上り片4bで直立状態に保持されるため、アンカーボル
ト6の固定の確実性低下が防止される。なお、前記実施
例におけるアンカーフレーム1では、アンカーボルト6
にPC鋼棒を使用したが、鉄筋等に用いられている異形
鋼棒を使用しても良い。
Since the anchor bolt fixing jig 2 simply covers the anchor bolt 6 with the cap 19, the reliability of fixing the anchor bolt 6 is lower than that of the conventional one in which the ceiling plate is fixed with a nut. However, since the anchor bolts 6 are held upright by the rising pieces 4b of the anchor bolt holder 4, it is possible to prevent the anchor bolts 6 from being reliably fixed. In the anchor frame 1 in the above-mentioned embodiment, the anchor bolt 6
Although the PC steel rod was used for the above, a deformed steel rod used for a reinforcing bar or the like may be used.

【0025】図3は、アンカーボルト固定治具の変形例
を示す。このアンカーボルト固定治具22は、各キャッ
プ19を連結した連結フレーム23を矩形の枠状とし、
連結フレーム23の4方にアーム24を突設して、その
先端に下げ振り25を取付けたものである。下げ振り2
5は、アーム24の先端に形成したスリットからなる取
付部26に、糸部25aを取付けてある。キャップ19
は前記実施例のものと同様である。
FIG. 3 shows a modification of the anchor bolt fixing jig. In this anchor bolt fixing jig 22, a connecting frame 23 connecting the caps 19 has a rectangular frame shape,
An arm 24 is projectingly provided on four sides of the connecting frame 23, and a plumbing 25 is attached to the tip thereof. Plumb bob 2
In No. 5, the thread portion 25a is attached to the attachment portion 26 formed of a slit formed at the tip of the arm 24. Cap 19
Is the same as that of the above embodiment.

【0026】この構成の場合、次のようにアンカーフレ
ーム1の位置決めが行える。すなわち、アンカーボルト
固定治具22から垂らされた各下げ振り25が、捨てコ
ンクリート上に予め墨打ちされた基準線La,Lbに一
致するように、アンカーフレーム1の位置を調整する。
このように、アンカーボルト固定治具22を位置決め治
具として兼用することができ、下げ振り25がアンカー
ボルト固定治具22に取付けられていて、作業者が支え
る必要がないため、位置決め作業が容易に行える。しか
も、アンカーフレーム1の4方向の位置決めが同時に行
えるため、位置決め作業がより一層簡単に行える。
In this structure, the anchor frame 1 can be positioned as follows. That is, the position of the anchor frame 1 is adjusted such that each plumb bob 25 hung from the anchor bolt fixing jig 22 matches the reference lines La and Lb pre-inked on the discarded concrete.
In this way, the anchor bolt fixing jig 22 can also be used as a positioning jig, and since the plumb bob 25 is attached to the anchor bolt fixing jig 22, it is not necessary for the operator to support, so that the positioning work is easy. You can do it. Moreover, since the anchor frame 1 can be positioned in four directions at the same time, the positioning work can be performed more easily.

【0027】[0027]

【発明の効果】この発明のアンカーフレームは、地盤固
定孔を有する固定脚をアンカープレートに設けたため、
ホールインアンカ等を用いて直接に地盤に固定でき、そ
のため現場溶接が不要で、また捨コンクリート等に予め
アングル等を埋設する必要がなく、現場作業性が向上す
る。また、立上り片でアンカーボルトを直立状態に保持
するアンカーボルト保持具をアンカープレートに設けた
ため、天プレートを設けることが不要で、アンカーフレ
ームの組み立てが簡単になる。これらにより、工期が短
縮され、施工コストが低減される。
According to the anchor frame of the present invention, since the anchor leg having the ground fixing hole is provided on the anchor plate,
Since it can be directly fixed to the ground by using a hole-in anchor, there is no need for on-site welding, and there is no need to bury an angle or the like beforehand in waste concrete or the like, improving on-site workability. Further, since the anchor plate is provided with the anchor bolt holder that holds the anchor bolt in the upright state by the rising piece, it is not necessary to provide the top plate, and the assembly of the anchor frame is simplified. As a result, the construction period is shortened and the construction cost is reduced.

【0028】請求項2のアンカーボルト固定治具は、各
アンカーボルトの上端に被さるキャップを連結フレーム
で相互に連結したものであるため、天プレートを省略し
たアンカーフレームにおいて、アンカーボルトの傾きを
防止して確実な位置決めを図ることができる。また、キ
ャップによってアンカーボルトの上端の雄ねじ部の養生
が図れ、配筋時等におけるアンカーボルト雄ねじ部の傷
つきが防止できる。
In the anchor bolt fixing jig according to the second aspect of the present invention, since the caps covering the upper ends of the anchor bolts are connected to each other by the connecting frame, the anchor bolts are prevented from tilting in the anchor frame without the top plate. It is possible to achieve reliable positioning. Further, the cap allows the male screw portion at the upper end of the anchor bolt to be cured, so that the male screw portion of the anchor bolt can be prevented from being damaged when the reinforcement is arranged.

【0029】請求項3のアンカーボルト固定治具は、4
方に下げ振りを設けたため、捨てコンクリート上に墨打
ちされた基準線に対してアンカーフレームを位置決めす
るにつき、下げ振りを作業者が支持する必要がなくて、
一人の作業者で容易に位置決め作業が行える。しかも4
方の位置決めが同時に行える。
The anchor bolt fixing jig of claim 3 is 4
Since the plumb bob was provided on the one side, the operator did not have to support the plumb bob when positioning the anchor frame with respect to the reference line stamped on the discarded concrete,
Positioning work can be easily performed by one worker. Moreover, 4
One can be positioned at the same time.

【図面の簡単な説明】[Brief description of drawings]

【図1】この発明の一実施例にかかるアンカーフレーム
とアンカーボルト固定治具との関係を示す組み立て状態
の斜視図である。
FIG. 1 is a perspective view of an assembled state showing a relationship between an anchor frame and an anchor bolt fixing jig according to an embodiment of the present invention.

【図2】そのアンカーフレームとアンカーボルト固定治
具の分解状態の斜視図である。
FIG. 2 is a perspective view of the anchor frame and an anchor bolt fixing jig in an exploded state.

【図3】アンカーボルト固定治具の変形例とアンカーフ
レームとの関係を示す組み立て状態の斜視図である。
FIG. 3 is a perspective view of an assembled state showing a relationship between a modified example of an anchor bolt fixing jig and an anchor frame.

【図4】従来例の正面図である。FIG. 4 is a front view of a conventional example.

【符号の説明】[Explanation of symbols]

1…アンカーフレーム、2…アンカーボルト固定治具、
3…アンカープレート、4…アンカーボルト保持具、4
a…底板、4b…立上り片、5…固定脚、6…アンカー
ボルト、8…ねじ孔、12a…接地板部、13…地盤固
定孔、19…キャップ、20…連結フレーム、21…ホ
ールインアンカ、22…アンカーボルト固定治具、25
…下げ振り
1 ... anchor frame, 2 ... anchor bolt fixing jig,
3 ... Anchor plate, 4 ... Anchor bolt holder, 4
a ... bottom plate, 4b ... rising piece, 5 ... fixed leg, 6 ... anchor bolt, 8 ... screw hole, 12a ... ground plate part, 13 ... ground fixing hole, 19 ... cap, 20 ... connecting frame, 21 ... hole-in anchor , 22 ... Anchor bolt fixing jig, 25
... plumb bob

Claims (3)

【特許請求の範囲】[Claims] 【請求項1】 アンカープレートと、このアンカープレ
ートの上面に各々固定されてアンカーボルトの下部を立
上り片で直立状態に保持する複数のアンカーボルト保持
具と、これらアンカーボルト保持具に保持されて前記ア
ンカープレートに立設される複数本のアンカーボルト
と、前記アンカープレートに設けられて接地板部に地盤
固定孔を有する複数の固定脚とを備えたアンカーフレー
ム。
1. An anchor plate, a plurality of anchor bolt holders each fixed to an upper surface of the anchor plate and holding a lower portion of the anchor bolt in an upright state by a rising piece, and the anchor bolt holders held by the anchor bolt holders. An anchor frame provided with a plurality of anchor bolts standing on an anchor plate and a plurality of fixing legs provided on the anchor plate and having ground fixing holes in a ground plate portion.
【請求項2】 アンカーフレームを構成する各アンカー
ボルトの上端に各々被さる複数のキャップと、これらキ
ャップを相互に連結した連結フレームとを備えたアンカ
ーボルト固定治具。
2. An anchor bolt fixing jig comprising a plurality of caps respectively covering the upper ends of the anchor bolts constituting the anchor frame, and a connecting frame connecting the caps to each other.
【請求項3】 連結フレームの4方に下げ振りを取付け
た請求項2記載のアンカーボルト固定治具。
3. An anchor bolt fixing jig according to claim 2, wherein plumb bobs are attached to four sides of the connecting frame.
JP3328081A 1991-11-15 1991-11-15 Anchor frame and its fixing jig Expired - Lifetime JPH0733690B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP3328081A JPH0733690B2 (en) 1991-11-15 1991-11-15 Anchor frame and its fixing jig

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP3328081A JPH0733690B2 (en) 1991-11-15 1991-11-15 Anchor frame and its fixing jig

Publications (2)

Publication Number Publication Date
JPH05141006A true JPH05141006A (en) 1993-06-08
JPH0733690B2 JPH0733690B2 (en) 1995-04-12

Family

ID=18206304

Family Applications (1)

Application Number Title Priority Date Filing Date
JP3328081A Expired - Lifetime JPH0733690B2 (en) 1991-11-15 1991-11-15 Anchor frame and its fixing jig

Country Status (1)

Country Link
JP (1) JPH0733690B2 (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2015055079A (en) * 2013-09-11 2015-03-23 株式会社淺沼組 Anchor frame, and method for constructing anchor structure using the anchor frame
JP2018040132A (en) * 2016-09-06 2018-03-15 鹿島建設株式会社 Structure and method for fixing anchor
CN108253243A (en) * 2018-03-14 2018-07-06 山西宏厦建筑工程第三有限公司 Pre-buried high-strength foundation bolt overlength casing detent mechanism and localization method
KR20210016812A (en) * 2019-08-05 2021-02-17 주식회사 지음피씨이 Reinforcing rod fixing system for pricast concrete column
JP2021042621A (en) * 2019-09-13 2021-03-18 フルサト工業株式会社 Anchor bolt fixing implement and anchor frame
CN112881163A (en) * 2021-01-26 2021-06-01 郑州大学 FRP (fiber reinforced plastic) rod end anchoring and fixing device with telescopic butterfly-shaped clamp and method

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH04118465A (en) * 1990-09-07 1992-04-20 Misawa Homes Co Ltd Positioning jig

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH04118465A (en) * 1990-09-07 1992-04-20 Misawa Homes Co Ltd Positioning jig

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2015055079A (en) * 2013-09-11 2015-03-23 株式会社淺沼組 Anchor frame, and method for constructing anchor structure using the anchor frame
JP2018040132A (en) * 2016-09-06 2018-03-15 鹿島建設株式会社 Structure and method for fixing anchor
CN108253243A (en) * 2018-03-14 2018-07-06 山西宏厦建筑工程第三有限公司 Pre-buried high-strength foundation bolt overlength casing detent mechanism and localization method
CN108253243B (en) * 2018-03-14 2024-01-23 山西宏厦建筑工程第三有限公司 Positioning mechanism and positioning method for pre-buried high-strength anchor bolt ultra-long sleeve
KR20210016812A (en) * 2019-08-05 2021-02-17 주식회사 지음피씨이 Reinforcing rod fixing system for pricast concrete column
JP2021042621A (en) * 2019-09-13 2021-03-18 フルサト工業株式会社 Anchor bolt fixing implement and anchor frame
CN112881163A (en) * 2021-01-26 2021-06-01 郑州大学 FRP (fiber reinforced plastic) rod end anchoring and fixing device with telescopic butterfly-shaped clamp and method

Also Published As

Publication number Publication date
JPH0733690B2 (en) 1995-04-12

Similar Documents

Publication Publication Date Title
JPH0713416B2 (en) Anchor frame positioning tool
JPH05141006A (en) Anchor frame and its fixing jig
JP2630623B2 (en) Anchor bolt installation method and anchor bolt support device used for it
JP3032104B2 (en) Fixing method of pillar lower end
JPH0514061B2 (en)
JP2015055079A (en) Anchor frame, and method for constructing anchor structure using the anchor frame
JP2694431B2 (en) Construction method of anchor bolt
JPH11200511A (en) Column leg fitting and wooden through column fixing method using the same
JP2537475B2 (en) Strut reinforcement method
JP4774268B2 (en) Column base hardware
JP3453487B2 (en) Anchor bolt mounting device for steel reinforced concrete structures
JPH0410282Y2 (en)
JP4038086B2 (en) Bracing unit mounting structure
JPH10184011A (en) Metal tool set for installing anchor bolt
JP2825150B2 (en) Fixing method of column base in steel frame building
JPS6315478Y2 (en)
JPH0540335U (en) Anchor frame
JPH0721627Y2 (en) Anchor bolt fixing device
JPH09217357A (en) Anchor frame
JPS62107132A (en) House anchoring apparatus
JPH09165753A (en) Anchor bolt set up device of structure
JPH07109100B2 (en) Anchor bolt construction method
JPH10325178A (en) Connecting hardware for steel pedestal and fixing method of steel pedestal
JPH0327166Y2 (en)
JPH0540336U (en) Anchor frame