JPH0511169B2 - - Google Patents

Info

Publication number
JPH0511169B2
JPH0511169B2 JP1106287A JP1106287A JPH0511169B2 JP H0511169 B2 JPH0511169 B2 JP H0511169B2 JP 1106287 A JP1106287 A JP 1106287A JP 1106287 A JP1106287 A JP 1106287A JP H0511169 B2 JPH0511169 B2 JP H0511169B2
Authority
JP
Japan
Prior art keywords
steel plate
steel plates
concrete
steel
underground beam
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP1106287A
Other languages
Japanese (ja)
Other versions
JPS63181816A (en
Inventor
Satoru Kusaka
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Takenaka Komuten Co Ltd
Original Assignee
Takenaka Komuten Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Takenaka Komuten Co Ltd filed Critical Takenaka Komuten Co Ltd
Priority to JP1106287A priority Critical patent/JPS63181816A/en
Publication of JPS63181816A publication Critical patent/JPS63181816A/en
Publication of JPH0511169B2 publication Critical patent/JPH0511169B2/ja
Granted legal-status Critical Current

Links

Landscapes

  • Foundations (AREA)

Description

【発明の詳細な説明】 (産業上の利用分野) 本発明は、建物基礎における地中梁を構成する
地中梁構成材に関する。
DETAILED DESCRIPTION OF THE INVENTION (Industrial Field of Application) The present invention relates to underground beam constituent materials that constitute underground beams in building foundations.

(従来の技術) 梁を構成するものとしては、従来一般に、例え
ば、特公昭54−3527号公報や実公昭58−53363号
公報に示されるように、U形にプレスした鋼板を
型枠兼用の構造体として使用し、そのU形鋼板の
開口上部に梁の上端鉄筋を配筋するとともに、そ
の上端鉄筋に逆U形差し筋を配筋し、それらの鉄
筋を埋設するようにコンクリートを充填するよう
に構成したものが知られている。
(Prior Art) Beams have generally been constructed using steel plates pressed into a U-shape that also serves as formwork, as shown in Japanese Patent Publication No. 54-3527 and Utility Model Publication No. 58-53363, for example. Used as a structure, the upper end reinforcing bars of the beam are placed above the opening of the U-shaped steel plate, and the inverted U-shaped reinforcing bars are placed on the upper end reinforcing bars, and concrete is filled to bury these reinforcing bars. It is known that the structure is as follows.

また、特開昭61−165452号公報に示されるよう
に、2個のH形鋼を、そのウエブが対向するよう
に間隔を置いて配置するとともに、その所定箇所
に型枠を取り付け、その型枠、フランジおよびウ
エブで囲まれた空間内にコンクリートを充填する
ように構成したものが知られている。
In addition, as shown in Japanese Patent Application Laid-Open No. 61-165452, two H-shaped steels are placed at a distance so that their webs face each other, and a formwork is attached to a predetermined location of the H-shaped steel. A structure is known in which a space surrounded by a frame, a flange, and a web is filled with concrete.

(発明が解決しようとする問題点) しかしながら、このような構成を有する従来例
の場合、前者にあつては、U形プレス鋼板内に鉄
筋を配筋しなければならず、その配筋作業に手間
を要して工期が増大する欠点があつた。
(Problems to be Solved by the Invention) However, in the case of the conventional example having such a configuration, in the case of the former, reinforcing bars must be arranged within the U-shaped pressed steel plate, and the reinforcing work requires The disadvantage was that it required time and effort and increased the construction period.

一方、後者にあつては、2個のH形鋼それぞれ
を、互いに所定間隔を隔てて配置しなければなら
ない上に、小さいとはいうものの型枠ならびにそ
の取り付けを必要とし、前述の場合と同様に工期
が増大する欠点があつた。
On the other hand, in the latter case, two H-beams must be placed at a predetermined distance from each other, and a formwork and its installation are required, although the size is small. The disadvantage was that the construction period increased.

本発明は、このような事情に鑑みてなされたも
のであつて、構造的に十分な耐力と粘りを有する
ものでありながら、現場施工における型枠工事な
らびに配筋工事を簡略化して工期を大幅に低減で
きるようにすることを目的とする。
The present invention was developed in view of these circumstances, and while having sufficient structural strength and tenacity, it simplifies form work and reinforcement work during on-site construction, significantly shortening the construction period. The aim is to reduce the

(問題点を解決するための手段) 本発明の地中梁構成材は、このような目的を達
成するために、 上下方向で対向するとともに対向面側にせん断
力伝達部を備えた第1鋼板それぞれに、左右方向
で対向して前記第1鋼板それぞれの端縁どうしを
連結する第2鋼板それぞれを一体化して縦断面形
状四角形に構成し、 前記上側の第1鋼板または第2鋼板の上端側
に、コンクリートの注入穴と、コンクリートの充
填状態を確認する覗き穴とを形成して構成する。
(Means for Solving the Problems) In order to achieve the above object, the underground beam component of the present invention includes first steel plates facing each other in the vertical direction and having a shear force transmitting portion on the opposing surface side. Second steel plates facing each other in the left and right direction and connecting the edges of the first steel plates are integrated to have a rectangular vertical cross section, and the upper end side of the upper first steel plate or the second steel plate is integrated. It is constructed by forming a concrete injection hole and a peephole for checking the filling state of concrete.

(作用) 上記構成によれば、工場段階において、それぞ
れ一対の第1鋼板と第2鋼板とを溶接やボルトに
よる接合などにより一体化して縦断面形状四角形
の箱形筒状の地中梁構成材を生産し、その地中梁
構成材を現場に搬入し、柱などに溶接やボルトな
どによつて接合し、ベースへの配筋を施した後
に、注入穴を通じてコンクリートを充填するとと
もに、覗き穴から充填状態を確認し、一対の第1
鋼板が主筋として作用するとともに、一対の第2
鋼板がフープ筋やスターラツプ筋として作用しな
がら、充填コンクリートにより大きな剛性を発揮
できる地中梁を得ることができる。
(Function) According to the above configuration, at the factory stage, each pair of the first steel plate and the second steel plate are integrated by welding, bolting, etc. to form a box-shaped cylindrical underground beam component with a rectangular vertical cross section. After producing the underground beam components and transporting them to the site, joining them to columns etc. by welding or bolting, and providing reinforcement to the base, concrete is filled through the injection hole, and the peephole is Check the filling status from the
The steel plate acts as the main reinforcement, and a pair of second
While the steel plates act as hoop reinforcements and stirrup reinforcements, it is possible to obtain an underground beam that can exhibit greater rigidity due to the concrete filling.

(実施例) 以下、本発明の実施例を図面に基づいて詳細に
説明する。
(Example) Hereinafter, an example of the present invention will be described in detail based on the drawings.

<第1実施例> 第1図は、本発明の実施例に係る地中梁構成材
の第1実施例を示す全体斜視図、第2図は第1実
施例の縦断面図である。
<First Example> FIG. 1 is an overall perspective view showing a first example of an underground beam component according to an example of the present invention, and FIG. 2 is a longitudinal sectional view of the first example.

これらの図において、1,1は第1鋼板、2,
2は第2鋼板であり、第1鋼板1,1それぞれが
上下方向に対向されるとともに、第2鋼板2,2
が左右方向に対向され、第1鋼板1,1と第2鋼
板2,2との両端縁どうしが溶接され、全体とし
て縦断面形状が四角形で筒状に地中梁構成材Aが
構成されている。
In these figures, 1, 1 is the first steel plate, 2,
2 is a second steel plate, and the first steel plates 1, 1 are vertically opposed to each other, and the second steel plates 2, 2 are opposite to each other in the vertical direction.
are opposed in the left-right direction, and both edges of the first steel plates 1, 1 and the second steel plates 2, 2 are welded together, and the underground beam component A is constructed in a cylindrical shape with a rectangular vertical cross section as a whole. There is.

前記第1鋼板1,1それぞれの対向面側には、
長手方向に沿つて突条3…が突設され、内部にコ
ンクリートを充填したときに、そのコンクリート
との間にせん断力を伝達するように構成されてい
る。このせん断力を伝達する構成としては、例え
ば、第1鋼板1,1の外面から内方に突出するよ
うにボルトを突設しても良く、それらをしてせん
断力伝達部と称する。
On the opposing surfaces of each of the first steel plates 1, 1,
Projections 3 are provided to protrude along the longitudinal direction, and when the inside is filled with concrete, it is configured to transmit shear force to the concrete. As a structure for transmitting this shear force, for example, bolts may be provided so as to protrude inwardly from the outer surfaces of the first steel plates 1, 1, and these are referred to as shear force transmitting parts.

前記第1鋼板1,1の内、上側のものの上面の
所定箇所には、床スラブのコンクリートと一体化
するためのスタツドボルト4が溶接によつて連接
されている。
A stud bolt 4 for integrating with the concrete of the floor slab is connected by welding to a predetermined location on the upper surface of the upper one of the first steel plates 1,1.

また、上側の第1鋼板1には、その長手方向に
所定間隔を隔てて、コンクリートの充填状態を確
認するための覗き穴5…が形成されている。
Furthermore, peep holes 5 are formed in the upper first steel plate 1 at predetermined intervals in the longitudinal direction thereof, for checking the filling state of concrete.

第2鋼板2,2それぞれは、第1鋼板1よりも
肉厚が小に(例えば、第1鋼板1の1/10程度)構
成され、そして、第2鋼板2,2それぞれの長手
方向両端それぞれの下端側には、矩形状の切欠部
2aが形成され、柱や梁などと突き合わせ溶接を
する場合にこの切欠部2a…を通じて溶接作業を
行なうように構成されている。
Each of the second steel plates 2 and 2 has a wall thickness smaller than that of the first steel plate 1 (for example, about 1/10 of the first steel plate 1), and both longitudinal ends of each of the second steel plates 2 and 2 are A rectangular notch 2a is formed on the lower end side of the welding member 2, and the welding operation is performed through this notch 2a when butt welding is to be performed on a pillar, a beam, or the like.

また、第2鋼板2,2のそれぞれの上端側所定
箇所には、コンクリートの注入穴6が形成され、
この注入穴6に、薄鋼板や木材、プラスチツク等
で形成された漏斗7を係止によつて取り付け、内
部にコンクリートを充填できるようになつてい
る。前記注入穴6としては、例えば、1mおきに
10cm程度の開口幅を有するように形成しておけば
良い。
Further, a concrete injection hole 6 is formed at a predetermined location on the upper end side of each of the second steel plates 2, 2,
A funnel 7 made of a thin steel plate, wood, plastic, or the like is attached to the injection hole 6 by a lock, so that the inside can be filled with concrete. For example, the injection holes 6 are arranged at intervals of 1 m.
It may be formed to have an opening width of about 10 cm.

更には、第2鋼板2,2それぞれの下端側に
は、鉄筋の差し込み穴8…が形成されている。
Furthermore, insertion holes 8 for reinforcing bars are formed at the lower end sides of each of the second steel plates 2, 2.

また、図示しないが、第2鋼板2,2それぞれ
において、後述するベースコンクリートCや床ス
ラブコンクリートDの打設後に外気と接触する箇
所には、錆の発生を防止するために、亜鉛鍍金が
施されるか、例えば、エポキシ樹脂等の耐候性樹
脂が塗装されている。
In addition, although not shown, in each of the second steel plates 2 and 2, the parts that come into contact with the outside air after the base concrete C and floor slab concrete D, which will be described later, are placed are galvanized to prevent rust from forming. For example, it may be coated with a weather-resistant resin such as epoxy resin.

更には、建築物の性状に応じ、必要があれば、
第2図に示すように、応力の大きい箇所に、その
座屈を防止するために、第2鋼板2,2どうしを
長ボルト9で止める。この座屈を防止する構成と
しては、例えば、第2鋼板2,2それぞれの対向
面側に上下方向に向かうリブを突設しても良い。
Furthermore, depending on the characteristics of the building, if necessary,
As shown in FIG. 2, the second steel plates 2, 2 are fastened to each other with long bolts 9 at locations where stress is large to prevent buckling. As a structure for preventing this buckling, for example, ribs extending in the vertical direction may be provided on the opposing surfaces of each of the second steel plates 2, 2.

以上の構成により、第3図aに示すように、捨
てコンクリートB上に墨出しして、隣合う柱1
0,10…間に地中梁構成材A…を配置し、適
宜、それらの下部にフイラー(図示せず)を介在
してレベルを調整し、しかる後に、第3図bおよ
び第4図の要部の拡大図それぞれに示すように、
地中梁構成材Aと構成が同じで長尺の地中梁構成
材A1の下側の第1鋼板1の端面を地中梁構成材
Aの下側の第1鋼板1の横側端面に突き合わせ、
前記切欠部2a…を通じて突き合わせ溶接により
連接するとともに、同様にして地中梁構成材A1
の上側の第1鋼板1の端面を地中梁構成材Aの上
側の第1鋼板1の横側端面に突き合わせ溶接によ
つて連接し、かつ、地中梁構成材A1の第2鋼板
2,2、の長手方向の端縁を地中梁構成材Aの第
2鋼板2,2の板面に隅肉溶接により連接し、更
に、これらの地中梁構成材Aと柱10とを、同様
の溶接により連接する。
With the above configuration, as shown in FIG.
Place the underground beam component A between 0 and 10, adjust the level by interposing a filler (not shown) under them as appropriate, and then As shown in each enlarged view of the main parts,
The end face of the first steel plate 1 on the lower side of the long underground beam member A 1, which has the same configuration as the underground beam member A, is the lateral end face of the first steel plate 1 on the lower side of the underground beam member A. Match it to,
They are connected by butt welding through the notches 2a, and in the same way, the underground beam component A 1
The end face of the upper first steel plate 1 is connected to the side end face of the upper first steel plate 1 of the underground beam component A by butt welding, and the second steel plate 2 of the underground beam component A 1 . Connected by similar welding.

そして、第3図bおよび第5図の要部の拡大図
それぞれに示すように、鉄筋差し込み穴8…に鉄
筋11…を差し込み、その状態で、ベースに対し
て、上端筋12…ならびに下端筋13…を配筋す
る。
Then, as shown in the enlarged views of the main parts in FIG. 3b and FIG. 13. Arrange reinforcement.

その後に、第3図cに示すように、ベースコン
クリートCを打設するとともに、前記注入穴6…
を通じて地中梁構成材A…,A1…それぞれの内
部にコンクリートを打設し、覗き穴5から充填状
態を確認して、内部に〓間があれば、高強度モル
タルを注入しておく。
After that, as shown in Fig. 3c, base concrete C is poured and the injection holes 6...
Concrete is poured inside each of the underground beam components A..., A1 ... through the holes, and the filling status is checked through the peephole 5. If there are gaps inside, high-strength mortar is injected.

しかる後に、第3図dに示すように、地中梁構
成材A,A…にわたつてデツキプレート14を架
設するとともに、上端筋12a…ならびに下端筋
13a…を配筋する。
Thereafter, as shown in FIG. 3d, the deck plate 14 is erected across the underground beam components A, A, etc., and the upper end reinforcements 12a... and the lower end reinforcements 13a... are arranged.

それらの上部に、第3図eに示すように、最下
階の床スラブコンクリートDを打設して地下躯体
を構築する。このとき、上部の鉄骨性の建て方を
行なつても良い。
Above these, as shown in Figure 3e, a concrete floor slab D for the lowest floor is poured to construct an underground framework. At this time, the upper part may be constructed with a steel frame.

なお、上述の地中梁構成材A,A1内へのコン
クリートの打設に先立ち、第2鋼板2,2とその
内部のコンクリートとの間でのせん断力の伝達を
良好に行なうために、第2鋼板2,2の外面から
釘を打ち込んでおいても良い。
In addition, prior to placing concrete into the above-mentioned underground beam components A and A1 , in order to ensure good transmission of shear force between the second steel plates 2 and the concrete inside them, Nails may be driven from the outer surfaces of the second steel plates 2, 2.

<第2実施例> 第6図は、第2実施例の斜視図であり、この第
2実施例の特徴とするところは次の点にある。
<Second Embodiment> FIG. 6 is a perspective view of the second embodiment, and the second embodiment is characterized by the following points.

即ち、第1実施例において鉄筋11を差し込む
構成に代えて、第1鋼板1,1それぞれの両側縁
(または第2鋼板2,2それぞれの下端側)にく
し板15を溶接により連接し、ベースコンクリー
トCとの連結強度を高めている。他の構成は第1
実施例と同様であり、説明を省略する。
That is, instead of inserting the reinforcing bars 11 in the first embodiment, the comb plates 15 are connected by welding to both side edges of the first steel plates 1, 1 (or to the lower end sides of the second steel plates 2, 2), and the base The strength of the connection with concrete C is increased. Other configurations are first
This is the same as the embodiment, and the explanation will be omitted.

<第3実施例> 第7図は、第3実施例の一部分を示す斜視図で
あり、この第3実施例の特徴とするところは次の
点にある。
<Third Embodiment> FIG. 7 is a perspective view showing a part of the third embodiment, and the third embodiment is characterized by the following points.

即ち、第1鋼板1,1の長手方向長さを第2鋼
板2,2よりも大にし、その長手方向両端それぞ
れにおいて、第1ボルト孔16…を備えたフラン
ジ部17を形成するとともに、第2鋼板2,2そ
れぞれの両端側に第2ボルト孔18…を形成し、
第8図に示すように、柱10の四面それぞれに予
め溶接によつて連接したフランジ部材19と接合
できるように構成されている。
That is, the length in the longitudinal direction of the first steel plates 1, 1 is made larger than that of the second steel plates 2, 2, and a flange portion 17 with first bolt holes 16 is formed at each of the longitudinal ends thereof. 2. Forming second bolt holes 18 on both end sides of each of the two steel plates 2, 2,
As shown in FIG. 8, it is constructed so that it can be joined to flange members 19 that are connected to each of the four sides of the pillar 10 by welding in advance.

その接合状態について詳述すれば、第9図に示
すように、下側の第1鋼板1のフランジ部17と
それに対接するフランジ部材19の端縁どうしを
突き合わせ溶接し、一方、上側の第1鋼板1のフ
ランジ部17とフランジ部材19とを、一対のプ
レート20,20によつて挟むとともに、第1ボ
ルト孔16…を介して高力ボルト21…により連
結し、更に、第2鋼板2,2それぞれの外面側に
プレート22,22を配置し、それらプレート2
2,22を第2ボルト孔18…を介して高力ボル
ト23…により第2鋼板2,2に連結するととも
に、そのプレート22,22の他端側をフランジ
部材19に高力ボルト24…により連結し、4枚
のプレート20,20,22,22と高力ボルト
21…,23…,24…、ならびに、突き合わせ
溶接を介して地中梁構成材Aと柱10とが連結さ
れている。このとき、プレート22,22の上端
と上側の第1鋼板1のフランジ部17との間にお
ける〓間は、例えば、鋼板、木材、プラスチツク
等の適当な材質の板を接着して閉塞すれば良い。
To explain the joining state in detail, as shown in FIG. The flange portion 17 of the steel plate 1 and the flange member 19 are sandwiched between a pair of plates 20, 20, and are connected by high-strength bolts 21 through the first bolt holes 16. 2 Plates 22, 22 are arranged on the outer surface side of each plate 2.
2, 22 are connected to the second steel plates 2, 2 by high-strength bolts 23 through the second bolt holes 18, and the other ends of the plates 22, 22 are connected to the flange member 19 by high-strength bolts 24. The underground beam component A and the column 10 are connected through four plates 20, 20, 22, 22, high-strength bolts 21..., 23..., 24..., and butt welding. At this time, the gap between the upper ends of the plates 22, 22 and the flange portion 17 of the upper first steel plate 1 may be closed by gluing a plate made of a suitable material such as a steel plate, wood, or plastic. .

上記実施例では、地中梁構成材A,A1それぞ
れを第1鋼板1,1と第2鋼板2,2とを溶接に
より一体化して構成しているが、本発明として
は、それらをボルト連結により一体化して構成す
るものでも良い。
In the above embodiment, each of the underground beam components A, A 1 is constructed by integrating the first steel plates 1, 1 and the second steel plates 2, 2 by welding, but in the present invention, they are connected by bolts. It may be configured by being integrated by connection.

また、上記実施例では、第2鋼板2の肉厚を第
1鋼板1よりもかなり薄くして、材料を軽減しな
がら必要強度を確保できるようにしているが、本
発明としては、第1鋼板1と同じ肉厚に構成して
も良い。
Further, in the above embodiment, the wall thickness of the second steel plate 2 is made considerably thinner than that of the first steel plate 1, so that the required strength can be secured while reducing the amount of material used. It may be configured to have the same wall thickness as 1.

(効果) 以上のように、本発明によれば、第1鋼板と第
2鋼板とを互いに一体化し、第1鋼板の対向面側
にせん断力伝達部を備えるから、従来にあつて配
筋を必要としていた主筋の機能を第1鋼板に、そ
して、フープ筋やスターラツプ筋の機能を第2鋼
板に発揮させることができ、かつ、内部に充填す
るコンクリートによつて大きな剛性を発揮させる
ことができる上に、第1および第2鋼板により閉
断面を構成してねじれ剛性を高めることができる
から、全体として構造的に十分な耐力と粘りを有
するものでありながら、地中梁周囲の型枠工事を
不要にできるとともにその内部への配筋をせずに
済み、現場施工における型枠工事ならびに配筋工
事を簡略化でき、工期を大幅に低減できるように
なつた。
(Effects) As described above, according to the present invention, the first steel plate and the second steel plate are integrated with each other, and the shear force transmitting portion is provided on the opposing surface side of the first steel plate, so that the reinforcement arrangement is not required in the conventional case. The function of the required main reinforcement can be applied to the first steel plate, and the functions of hoop and stirrup reinforcement can be applied to the second steel plate, and the concrete filled inside can provide great rigidity. Moreover, since the first and second steel plates can form a closed section and increase torsional rigidity, the structure as a whole has sufficient structural strength and tenacity, yet is suitable for formwork work around underground beams. This eliminates the need for reinforcing inside the structure, simplifying formwork work and reinforcing work during on-site construction, and significantly reducing the construction period.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図は、本発明の実施例に係る地中梁構成材
の第1実施例を示す全体斜視図、第2図は第1実
施例の縦断面図、第3図は、施工工程を示す要部
の概略図、第4図および第5図は、それぞれ要部
の拡大図、第6図は、第2実施例の全体斜視図、
第7図は、第3実施例の一部分を示す斜視図、第
8図は、第3実施例を適用する場合の柱の斜視
図、第9図は、第3実施例の柱との接合状態を示
す側面図である。 1……第1鋼板、2……第2鋼板、3……せん
断力伝達部としての突条、5……覗き穴、6……
注入穴。
Fig. 1 is an overall perspective view showing a first embodiment of an underground beam component according to an embodiment of the present invention, Fig. 2 is a longitudinal cross-sectional view of the first embodiment, and Fig. 3 shows a construction process. A schematic diagram of the main parts, FIGS. 4 and 5 are enlarged views of the main parts, respectively, and FIG. 6 is an overall perspective view of the second embodiment.
FIG. 7 is a perspective view showing a part of the third embodiment, FIG. 8 is a perspective view of a column when the third embodiment is applied, and FIG. 9 is a state of connection with the column of the third embodiment. FIG. DESCRIPTION OF SYMBOLS 1...First steel plate, 2...Second steel plate, 3...Protrusion as a shear force transmission part, 5...Peep hole, 6...
injection hole.

Claims (1)

【特許請求の範囲】 1 上下方向で対向するとともに対向面側にせん
断力伝達部を備えた第1鋼板それぞれに、左右方
向で対向して前記第1鋼板それぞれの端縁どうし
を連結する第2鋼板それぞれを一体化して縦断面
形状四角形に構成し、 前記上側の第1鋼板または第2鋼板の上端側
に、コンクリートの注入穴と、コンクリートの充
填状態を確認する覗き穴とを形成してあることを
特徴とする地中梁構成材。
[Scope of Claims] 1. First steel plates facing each other in the vertical direction and having a shear force transmitting portion on the opposing surface side, and a second steel plate facing in the left and right direction and connecting the edges of each of the first steel plates to each other. Each of the steel plates is integrated to have a rectangular vertical cross-section, and a concrete injection hole and a peephole for checking the filling state of concrete are formed on the upper end side of the first steel plate or the second steel plate. An underground beam component material characterized by:
JP1106287A 1987-01-19 1987-01-19 Constituent material for underground beam Granted JPS63181816A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP1106287A JPS63181816A (en) 1987-01-19 1987-01-19 Constituent material for underground beam

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP1106287A JPS63181816A (en) 1987-01-19 1987-01-19 Constituent material for underground beam

Publications (2)

Publication Number Publication Date
JPS63181816A JPS63181816A (en) 1988-07-27
JPH0511169B2 true JPH0511169B2 (en) 1993-02-12

Family

ID=11767514

Family Applications (1)

Application Number Title Priority Date Filing Date
JP1106287A Granted JPS63181816A (en) 1987-01-19 1987-01-19 Constituent material for underground beam

Country Status (1)

Country Link
JP (1) JPS63181816A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US11342206B2 (en) 2009-12-29 2022-05-24 Nikon Corporation Substrate case and substrate accommodation apparatus

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2824374B2 (en) * 1992-12-25 1998-11-11 株式会社赤城商会 Concrete block for foundation, manufacturing method thereof, and foundation construction method using the same
WO2004092543A2 (en) * 2003-04-11 2004-10-28 Adler, Richard, S. Blast and anti-ramming walls
DE102011087022A1 (en) * 2011-11-24 2013-05-29 Wobben Properties Gmbh Device and method for anchoring a wind energy plant

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US11342206B2 (en) 2009-12-29 2022-05-24 Nikon Corporation Substrate case and substrate accommodation apparatus

Also Published As

Publication number Publication date
JPS63181816A (en) 1988-07-27

Similar Documents

Publication Publication Date Title
JPH09221717A (en) Steel-concrete composite floor-slab bridge and construction method thereof
EP0418216B1 (en) Frame-work for structural walls in multy-storey buildings
JP3690437B2 (en) Seismic reinforcement structure for existing buildings
JPH0511169B2 (en)
JP4095534B2 (en) Joint structure of column and beam in ramen structure and its construction method
JPH11100900A (en) Joint part structure between reinforced concrete column and steel beam
JPH07252891A (en) Junction structure of steel member and concrete member
JP6839921B2 (en) Column-beam joint structure
JPH06173343A (en) Column and beam joint structure for laminated wood sturtcture
JP2004346568A (en) Seismic-response controlled structure
JPH09100576A (en) Method for joining end section of column for wooden framework technique
JP2566701Y2 (en) Joint structure between reinforced concrete columns and steel beams
JP3870871B2 (en) Reinforcement structure of frame
JP3685830B2 (en) Steel-concrete composite beam structure
JPS63268834A (en) Method for constructing body of multi-storied building and reinforcing bar connected cylinder used therein
JP4045502B2 (en) Structure
KR102569266B1 (en) Assembly type concrete filled steel column
JPH10184031A (en) Method of earthquake-proof reinforcing for already constructed pillar beam construction
JPH0270850A (en) Pc coupled beam and execution of construction using same
JP3218297B2 (en) Buildings with parallel multistory shear walls
JPH0868113A (en) Connecting structure for steel beam and reinforced concrete beam
JPH0762740A (en) Joint method for precast steel framed reinforced concrete construction pillar and beam
JP3160730B2 (en) Connecting columns and beams
JP3018968B2 (en) Bending reinforcement method for existing columns
JP3041433B2 (en) Joint structure between reinforced concrete columns and steel beams