JPH0475356B2 - - Google Patents

Info

Publication number
JPH0475356B2
JPH0475356B2 JP60032447A JP3244785A JPH0475356B2 JP H0475356 B2 JPH0475356 B2 JP H0475356B2 JP 60032447 A JP60032447 A JP 60032447A JP 3244785 A JP3244785 A JP 3244785A JP H0475356 B2 JPH0475356 B2 JP H0475356B2
Authority
JP
Japan
Prior art keywords
pipe
underground
buried
buried pipe
casing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP60032447A
Other languages
Japanese (ja)
Other versions
JPS61191798A (en
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed filed Critical
Priority to JP60032447A priority Critical patent/JPS61191798A/en
Publication of JPS61191798A publication Critical patent/JPS61191798A/en
Publication of JPH0475356B2 publication Critical patent/JPH0475356B2/ja
Granted legal-status Critical Current

Links

Description

【発明の詳細な説明】 〔産業上の利用分野〕 本発明は、ヒユーム管など地中に埋設された地
下推進管の到達位置にマンホール等の立坑を構築
するための工法に関する。
DETAILED DESCRIPTION OF THE INVENTION [Industrial Application Field] The present invention relates to a construction method for constructing a vertical shaft such as a manhole at the destination of an underground propulsion pipe buried underground, such as a hump pipe.

〔従来の技術〕[Conventional technology]

従来かかる到達立坑の形成の工法としては、例
えば第6図に示すように鋼矢板aを地中に打ち込
んで鋼矢板aによつて囲繞される空間を地下推進
管の到達深さまで掘削してシールド空間sを作り
出し、同空間s内に複数段に支保工cを取付け、
底部にはコンクリート製底板dを設け、この上に
地下推進管受けのマンホールを構築する方式があ
る。
Conventionally, as shown in Fig. 6, the conventional construction method for forming a reaching shaft is to drive steel sheet piles a into the ground and excavate the space surrounded by the steel sheet piles a to the depth reached by the underground propulsion pipe to create a shield. Create a space s, install shoring c in multiple stages within the space s,
There is a method in which a concrete bottom plate d is provided at the bottom and a manhole for receiving the underground propulsion pipe is constructed on top of this.

また、他の方式として、第7図に示すように、
予めケーシングgを用意し、地下推進管の到達位
置に至る空間hを掘削して同空間h内にケーシン
グgを設置し、ケーシングgと空間hとの空隙に
土砂を埋め戻して同ケーシングgを固定したのち
同様に支保工cを設け、その空間内にマンホール
を構築する方式がある。
In addition, as another method, as shown in Fig. 7,
Prepare a casing g in advance, excavate a space h to reach the underground propulsion pipe, install the casing g in the space h, and backfill the gap between the casing g and the space h with earth and sand to replace the casing g. There is a method in which a support c is similarly provided after it is fixed, and a manhole is constructed within that space.

〔発明が解決しようとする問題点〕[Problem that the invention seeks to solve]

上記の従来の工法においては、シールド部形成
のためにケーシングスペース以上の土砂の掘削後
の埋め戻し、各補強部材を設置する必要があるこ
とから作業効率が低く、またコストも高くなると
いう問題があつた。
In the conventional construction method described above, it is necessary to backfill earth and sand beyond the casing space after excavating it and install various reinforcing members to form the shield, resulting in low work efficiency and high costs. It was hot.

本発明は従来工法における効率の低さと作業の
無駄を解消し、しかも低コストで安全に到達立坑
を形成するための工法を提供するものである。
The present invention eliminates the low efficiency and waste of work in conventional construction methods, and provides a construction method for safely forming a reaching shaft at low cost.

〔問題点を解決するための手段〕[Means for solving problems]

本発明は、円筒状鋼管をケーシングとし、同ケ
ーシングを圧入しながら内部の土を掘削して埋設
する工法を採用し、この筒状鋼管をそのまま埋設
管とし、この埋設管を地中を推進してきたヒユー
ム管のような地下推進管の受け部とし、この上に
マンホール枠を構築することによつて上記課題を
解決したものである。
The present invention adopts a construction method in which a cylindrical steel pipe is used as a casing, the soil inside is excavated and buried while the casing is press-fitted, the cylindrical steel pipe is used as a buried pipe, and this buried pipe is propelled underground. The above problem was solved by using this as a receiving part for an underground propulsion pipe such as a humid pipe, and by constructing a manhole frame on top of this.

以下、添付の図面に示す実施例に基づいて本発
明を説明する。
The present invention will be described below based on embodiments shown in the accompanying drawings.

第1図に本発明の工法過程を示す。 Figure 1 shows the process of the construction method of the present invention.

第1図1において、1は地下推進管の受け部と
して埋設される通常断面が円形の鋼管製の埋設管
を示し、予め設定された所定の位置において、例
えば第1図3に示すパワージヨベルAの先端に設
けた圧入引抜具Cと回動具Dを用いて回動させな
がら地中に圧入される。
In FIG. 1, reference numeral 1 indicates a buried pipe made of steel pipe with a generally circular cross section, which is buried as a receiving part of an underground propulsion pipe. It is press-fitted into the ground while being rotated using a press-in/extraction tool C and a rotating tool D provided at the tip.

埋設管1は第3図に一部断面によつて示す構造
を有する。同図を参照して、埋設管1の下方側面
には地下推進管を取付けるための取付口2が設け
られ、同取付口2は盲板3を内周面から取り外し
可能にボルト止めすることによつて埋設管1の圧
入が終了するまで閉鎖されている。4は先端部を
焼入れした硬質鋼からなる刃先5と取付け基部6
とからなる掘削部材であつて、埋設管1の先端内
周部に複数個所、通常は8個所に、取り外し可能
にボルト止めされている。7は後述の連結ケーシ
ングとの連結部ねじ孔を示す。
The buried pipe 1 has a structure shown partially in cross section in FIG. Referring to the figure, a mounting port 2 for installing an underground propulsion pipe is provided on the lower side surface of a buried pipe 1, and a blind plate 3 is removably bolted to the mounting port 2 from the inner peripheral surface. Therefore, it remains closed until the press-fitting of the buried pipe 1 is completed. 4 is a cutting edge 5 made of hard steel with a hardened tip and a mounting base 6
This excavation member is removably bolted to the inner periphery of the tip of the buried pipe 1 at a plurality of locations, usually eight locations. Reference numeral 7 indicates a screw hole for connection with a connection casing, which will be described later.

第1図2は埋設管1を或る深さまで地中に圧入
した状態を断面によつて示す。同図において、8
は例えば第1図3に示すパワーシヨベルAの作業
アームBに吊り下げられたロープ9に取付けられ
た掘削機であつて、埋設管1内の土砂を掘削する
とともに掘削した土砂を埋設管1外に搬出する機
能を有する。
FIG. 1 and 2 show, in cross section, the state in which the underground pipe 1 is press-fitted into the ground to a certain depth. In the same figure, 8
For example, the excavator is attached to a rope 9 suspended from the work arm B of the power shovel A shown in FIG. It has the function of carrying out.

埋設管1内の土砂を掘削しつつ埋設管1の圧入
を進行せしめ、ほぼ第1図2に示す深さまで到達
したとき、埋設管1の上端に第1図3に示す連結
ケーシング10を連結して刃先5と掘削機8によ
る埋設管1の圧入を続ける。
The buried pipe 1 is press-fitted while excavating the earth and sand inside the buried pipe 1, and when the depth approximately shown in FIG. 1 is reached, the connecting casing 10 shown in FIG. 1 is connected to the upper end of the buried pipe 1. Press-fitting of the buried pipe 1 by the cutting edge 5 and the excavator 8 is continued.

第4図は連結ケーシング10の構造を一部断面
によつて示す図である。同連結ケーシング10は
二重の鋼管101と102から構成され、その上
下端に連結部材11,12を溶接によつて取付け
てなるものである。同連結部材11は第5図に示
すような断面形状を有し、二重の鋼管101と1
02との間に挿入して溶接によつて両管を結合し
て中空の二重管を形成するとともに、その端部の
外周に段部を設け、同段部に上記埋設管1の上方
先端部と嵌合し内方から埋設管1の連結部ねじ孔
7にボルト止めして埋設管1と取り外し可能に連
結できる構造になつている。また、同連結ケーシ
ング10の上端には同様の他の連結部材12が取
付けられ、第2の連結ケーシング13と連結でき
る構造になつている。
FIG. 4 is a partially cross-sectional view showing the structure of the connection casing 10. The connecting casing 10 is composed of double steel pipes 101 and 102, and connecting members 11 and 12 are attached to the upper and lower ends of the pipes by welding. The connecting member 11 has a cross-sectional shape as shown in FIG.
02 and join the two pipes by welding to form a hollow double pipe.A step is provided on the outer periphery of the end of the pipe, and the upper tip of the buried pipe 1 is provided at the step. The structure is such that it can be removably connected to the buried pipe 1 by fitting into the connecting part and bolting from the inside to the connecting part screw hole 7 of the buried pipe 1. Further, another similar connecting member 12 is attached to the upper end of the connecting casing 10, and has a structure that can be connected to a second connecting casing 13.

第1図3は埋設管1に連結ケーシング10を連
結してさらにケーシング内の土砂を掘削しつつ地
中に圧入した状態を示す。同連結ケーシング10
の長さにまで圧入が進行した時点で、その上から
パワーシヨベルAの前方に設けた回動具Dに保持
された第2の連結ケーシング13を第1の連結部
材12に連結して先端の埋設管1を盲板が地下推
進管16の推進レベルLに合致するまで圧入す
る。
FIG. 1 and 3 show a state in which the connecting casing 10 is connected to the buried pipe 1, and the earth and sand inside the casing are further excavated and press-fitted into the ground. Connected casing 10
When the press-fitting has progressed to the length of , the second connecting casing 13 held by the rotating tool D provided in front of the power shovel A is connected to the first connecting member 12 from above, and the tip is buried. The pipe 1 is press-fitted until the blind plate matches the propulsion level L of the underground propulsion pipe 16.

このようにして、第1図4に示すように、埋設
管1に設けた地下推進管の推進埋設位置に到達す
ると、前記埋設管1の先端に取りつけた前述の刃
先5を有する掘削部材4を取り外し、土質の状態
により埋設管1の周囲の土砂に薬液14を注入し
て固化し埋設管1を固定するとともに、埋設管の
底にコンクリートを流して底面15を形成する。
In this way, as shown in FIG. 1, when the buried position of the underground propulsion pipe provided in the buried pipe 1 is reached, the excavating member 4 having the aforementioned cutting edge 5 attached to the tip of the buried pipe 1 is removed. After removal, a chemical solution 14 is injected into the earth and sand around the buried pipe 1 to solidify it depending on the soil condition to fix the buried pipe 1, and concrete is poured at the bottom of the buried pipe to form a bottom surface 15.

さらに、第1図5に示すように、埋設管1の取
付口2を閉鎖している盲板3を取り外して、ヒユ
ーム管等の地下推進管16を同取付口2に導入す
る。
Furthermore, as shown in FIG. 1, the blind plate 3 closing the attachment port 2 of the buried pipe 1 is removed, and an underground propulsion pipe 16 such as a Huum pipe is introduced into the attachment port 2.

そして、埋設管1を外部型枠としたマンホール
立上がり部17をコンクリートにて製作する。
Then, a manhole rising portion 17 is made of concrete using the buried pipe 1 as an external form.

次ぎに、第1図6に示すように、埋設管1と第
1の連結ケーシング10との連結ボルトと取り外
してマンホール立上がり部17の上にマンホール
枠18を構築しつつ、第1図3に示すパワーシヨ
ベルAの先端に設けた圧入引抜具Cと回動具Dを
利用して、連結ケーシング10,13を引き上げ
るとともに、マンホール枠と地山の空間にコンク
リート19を流し込みながら道路面上まで上げ、
マンホールの蓋枠を設置して、マンホールの構築
を終了する。
Next, as shown in FIG. 16, the connecting bolts between the buried pipe 1 and the first connecting casing 10 are removed and a manhole frame 18 is constructed on the manhole rising portion 17, while the manhole frame 18 is constructed as shown in FIG. Using the press-in/extraction tool C and rotating tool D provided at the tip of the power shovel A, pull up the connecting casings 10 and 13, and while pouring concrete 19 into the space between the manhole frame and the ground, raise it above the road surface.
Install the manhole cover frame and complete the manhole construction.

〔発明の効果〕〔Effect of the invention〕

本発明は、マンホール構築に必要な最小限の断
面積の空間の土砂を掘削するのみで、地下推進管
の到達立坑を作ることができるので、マンホール
を構築する面積よりも僅かに広い面積があれば工
事を行なうことができる。土砂掘削に使用した埋
設管をそのまま地下推進管の受け部及びマンホー
ル立上がり部のコンクリート外枠として使用する
ので、作業効率が格段に向上する。
The present invention makes it possible to create a vertical shaft for an underground propulsion pipe by simply excavating earth and sand in a space with the minimum cross-sectional area required for constructing a manhole. construction work can be carried out. Since the buried pipe used for earth and sand excavation is used as it is as the receiving part of the underground propulsion pipe and the concrete outer frame of the rising part of the manhole, work efficiency is greatly improved.

立坑周囲は埋め戻していないので陥没の心配が
なく、マンホールの土台となる鋼管そのものの周
囲も埋め戻しのない土砂を使用し、しかも薬剤に
よつて強化できるので、極めて安定した地下推進
管のマンホールを形成することができるという効
果を奏する。
The area around the shaft is not backfilled, so there is no risk of it collapsing, and the area around the steel pipe itself, which forms the base of the manhole, is made of earth and sand without backfilling, and it can be strengthened with chemicals, making it an extremely stable underground propulsion pipe manhole. This has the effect of being able to form a

【図面の簡単な説明】[Brief explanation of drawings]

第1図は本発明の工法の各工程を示す図であ
り、第2図は本発明の工法を行なうために使用さ
れる移動クレーンとその付属設備を示す図であ
り、第3図は本発明に係る埋設管の構造を示し、
第4図は連結ケーシングの構造を示し、第5図は
連結ケーシングの連結部材の構造を示す図であ
る。また第6図および第7図は従来の工法を示す
図である。 1……埋設管、2……取付口、3……盲板、4
……掘削部材、5……刃先、6……取付け基部、
7……連結部ねじ孔、8……掘削機、9……ロー
プ、10,13……連結ケーシング、11……連
結部材、12……連結部材、14……薬液、15
……底面、16……地下推進管、17……マンホ
ール立上がり部、18……マンホール枠、19…
…コンクリート。
Figure 1 is a diagram showing each step of the construction method of the present invention, Figure 2 is a diagram showing a mobile crane and its attached equipment used to carry out the construction method of the present invention, and Figure 3 is a diagram showing the construction method of the present invention. It shows the structure of the buried pipe related to
FIG. 4 shows the structure of the connecting casing, and FIG. 5 shows the structure of the connecting member of the connecting casing. Further, FIGS. 6 and 7 are diagrams showing the conventional construction method. 1... Buried pipe, 2... Installation port, 3... Blind plate, 4
...Drilling member, 5...Blade tip, 6...Mounting base,
7... Connection screw hole, 8... Excavator, 9... Rope, 10, 13... Connection casing, 11... Connection member, 12... Connection member, 14... Chemical solution, 15
... Bottom surface, 16 ... Underground propulsion pipe, 17 ... Manhole rising part, 18 ... Manhole frame, 19 ...
…concrete.

Claims (1)

【特許請求の範囲】[Claims] 1 側面に地下推進管の取付口を有し且つ同取付
口に盲板を取り外し可能に当てがつて閉鎖した埋
設管を同埋設管内の土砂を掘削しつつ地中に圧入
し、次いで連結ケーシングを前記埋設管に取り外
し自在に連結して同様に土砂を掘削しつつ圧入し
同埋設管を地下推進管の到達位置に達しせしめた
のち、同埋設管を同地下推進管の到達位置に固定
し、前記盲板を除去して到達地下推進管を前記埋
設管の地下推進管取付口に取付け、次いで、同埋
設管から前記連結ケーシングを切り離して同埋設
管を地中に残留したまま前記連結ケーシングを上
方に引き上げつつ、前記残留埋設管上にマンホー
ル枠体を構築することを特徴とする到達立坑の形
成方法。
1. A buried pipe that has an underground propulsion pipe installation port on its side and is closed by removably applying a blind plate to the installation port is press-fitted into the ground while excavating the earth and sand inside the buried pipe, and then the connecting casing is removed. After removably connecting to the buried pipe and press-fitting it while similarly excavating earth and sand to make the buried pipe reach the reaching position of the underground propulsion pipe, fixing the buried pipe at the reaching position of the underground propulsion pipe, The blind plate is removed and the reaching underground propulsion pipe is attached to the underground propulsion pipe installation port of the underground pipe, and then the connecting casing is separated from the underground pipe and the connecting casing is removed while the underground pipe remains underground. A method for forming a reaching shaft, which comprises constructing a manhole frame on the remaining buried pipe while pulling it upward.
JP60032447A 1985-02-19 1985-02-19 Formation of arrival vertical pit Granted JPS61191798A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP60032447A JPS61191798A (en) 1985-02-19 1985-02-19 Formation of arrival vertical pit

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP60032447A JPS61191798A (en) 1985-02-19 1985-02-19 Formation of arrival vertical pit

Publications (2)

Publication Number Publication Date
JPS61191798A JPS61191798A (en) 1986-08-26
JPH0475356B2 true JPH0475356B2 (en) 1992-11-30

Family

ID=12359217

Family Applications (1)

Application Number Title Priority Date Filing Date
JP60032447A Granted JPS61191798A (en) 1985-02-19 1985-02-19 Formation of arrival vertical pit

Country Status (1)

Country Link
JP (1) JPS61191798A (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2741387B2 (en) * 1988-10-24 1998-04-15 羽田ヒューム管 株式会社 Construction manhole construction method
JP3075736B2 (en) * 1990-08-29 2000-08-14 三菱重工業株式会社 Shaft construction method

Also Published As

Publication number Publication date
JPS61191798A (en) 1986-08-26

Similar Documents

Publication Publication Date Title
JP3453664B2 (en) Shaft construction method
JPH10168880A (en) Removing device for obstacle to underground structure and removing method for the obstacle
JPH0475356B2 (en)
JP3776987B2 (en) Vertical shaft construction method using a manhole wall combined tubular body
JP2741387B2 (en) Construction manhole construction method
JPS58153818A (en) Drawing of existing steel tubular pile
CN114319444B (en) Shaft construction method and device
JP4086400B2 (en) Propulsion shaft, its construction method and propulsion method
JP6009294B2 (en) Manhole construction method using steel circular casing
JP3794097B2 (en) Construction method for underground structures
JP2812041B2 (en) Construction method of underground diaphragm wall and excavator used in the method
JP2876265B2 (en) Sheet pile for underground continuous wall and underground continuous wall method
JP2693028B2 (en) Construction method of human hole in middle of pipeline
JP2000104482A (en) Shaft construction method and earth retaining plate
JPH0759873B2 (en) Pile hole excavation method and device
JP3075736B2 (en) Shaft construction method
JPH0742478A (en) Steel cutting edge and construction method of liner plate catchment well with the steel cutting edge
JPH05287983A (en) Construction of underground space having long and large diametral dimension
JP2828786B2 (en) Casing shaft
JP2840024B2 (en) Vertical hole forming method
JPH08177048A (en) Removing method of pile and excavator used for removing method
JPH1150447A (en) Formation method of steel pipe column continuous wall and device therefor
JPH03206213A (en) Construction method of earth support
JPH11247591A (en) Connection method of underground structure using jacking device
JP2554826B2 (en) True pipe type large diameter cast pile device