JPH0473499B2 - - Google Patents

Info

Publication number
JPH0473499B2
JPH0473499B2 JP61312531A JP31253186A JPH0473499B2 JP H0473499 B2 JPH0473499 B2 JP H0473499B2 JP 61312531 A JP61312531 A JP 61312531A JP 31253186 A JP31253186 A JP 31253186A JP H0473499 B2 JPH0473499 B2 JP H0473499B2
Authority
JP
Japan
Prior art keywords
frame
building
truss
center
ground
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP61312531A
Other languages
Japanese (ja)
Other versions
JPS63167828A (en
Inventor
Eiji Matsushita
Keiji Inoe
Toshuki Yamanaka
Kozaburo Sato
Takao Inoe
Junichiro Ootsubo
Hajime Saito
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kajima Corp
Original Assignee
Kajima Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kajima Corp filed Critical Kajima Corp
Priority to JP31253186A priority Critical patent/JPS63167828A/en
Publication of JPS63167828A publication Critical patent/JPS63167828A/en
Publication of JPH0473499B2 publication Critical patent/JPH0473499B2/ja
Granted legal-status Critical Current

Links

Landscapes

  • Rod-Shaped Construction Members (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Description

【発明の詳細な説明】 〔産業上の利用分野〕 この発明は大空間の架構を構成する大規模建物
の構築方法に関するものである。
DETAILED DESCRIPTION OF THE INVENTION [Field of Industrial Application] The present invention relates to a method of constructing a large-scale building that constitutes a frame of a large space.

〔発明が解決しようとする問題点〕[Problem that the invention seeks to solve]

大空間を覆う架構として立体トラス構造を用い
ることが多いが、この架構は通常柱を建てた後
に、地上10数mの高所において柱頭部の周囲に順
次トラスを組み立てて構成されるものであるため
従来の構築方法では足場およびサポート等の支保
工が必要となる等仮設工事が大がかりとなり、工
期の長期化は避けられないのが実情である。
A three-dimensional truss structure is often used as a frame to cover a large space, but this frame is usually constructed by erecting columns and then sequentially assembling trusses around the column heads at a height of more than 10 meters above the ground. Therefore, conventional construction methods require extensive temporary construction work such as scaffolding and supports, and the reality is that the construction period is unavoidably prolonged.

またトラス架構を地表面上で組立ててジヤツキ
アツプあるいはリフトアツプする工法があるが大
規模建物では重量が過大で施工は著しく困難であ
る。
There is also a method of assembling a truss frame on the ground surface and jacking it up or lifting it up, but this is extremely difficult to construct in large-scale buildings due to its excessive weight.

この発明はこうしたトラス架構構築方法の実情
を踏まえてなされたもので、建物中央部はトラス
を地組みして全体を上昇させる方法を採り建物周
辺では移動足場を利用する方法を採ることにより
施工の省力化、工期の短縮化を実現しようとする
ものである。
This invention was made based on the actual situation of the truss frame construction method, and the construction was made by using a method in which the central part of the building is assembled with trusses and the entire structure is raised, and a method in which moving scaffolding is used around the building. The aim is to save labor and shorten the construction period.

〔問題点を解決するための手段〕[Means for solving problems]

この発明では建物の中央部のトラス架構を地上
で組み立てる方法を採用し、建物周辺部では移動
足場を利用することにより短期間に大空間架構を
建設することを可能にする。
This invention uses a method of assembling the truss frame in the center of the building on the ground, and uses movable scaffolding around the building, making it possible to construct a large space frame in a short period of time.

地上で組み立てられた建物中央部のトラス架構
はジヤツキアツプ、またはリフトアツプによつて
所定の高さまで上昇させられる。
The truss frame in the center of the building, assembled on the ground, is raised to a predetermined height by a jack-up or lift-up.

前者の場合には所定位置の地中に形成された削
孔内に柱を挿入し、その頭部にトラスを接合して
トラス架構を形成し、全体をジヤツキアツプし
て、一方後者の場合には所定位置に柱を設置し、
その基部の周囲にトラス架構を形成し、これを柱
頭部の位置までリフトアツプしてそれぞれ建物中
央部の架構を構築する。
In the former case, a pillar is inserted into a hole formed in the ground at a predetermined location, a truss is connected to the head of the pillar to form a truss frame, and the whole is jacked up. Install the pillar in the designated position,
A truss frame is formed around the base, and this is lifted up to the position of the column head to construct the frame for each central part of the building.

さらにこうしてジヤツキアツプ、もしくはリフ
トアツプによつて構築する建物中央部の架構の周
辺部では中央部の架構に沿つてレールを敷設し、
この上方にレール上を移動可能な仮設足場を設置
し、仮設足場を移動させながらこの仮設足場を利
用して中央部のトラス架構の周辺にトラスを連続
して組み立てて架構を構築する。
Furthermore, in the area around the central frame of the building constructed by jack-up or lift-up, rails are laid along the central frame.
A temporary scaffold that can move on rails is installed above this, and while the temporary scaffold is being moved, the structure is constructed by continuously assembling trusses around the central truss frame using this temporary scaffold.

〔実施例〕〔Example〕

以下この発明を一実施例を示す図面に基づいて
説明する。
The present invention will be explained below based on the drawings showing one embodiment.

初めに第一の発明の図面により説明する。 First, the first invention will be explained with reference to the drawings.

この発明は地上で組み立てた柱aとトラス架構
b全体をジヤツキアツプして建物架構A0を構築
する方法である。
This invention is a method of constructing a building frame A0 by jacking up the entire column a and truss frame b assembled on the ground.

第1図に従つて施工手順を説明する。 The construction procedure will be explained according to Fig. 1.

まず所定位置にケーシング1を埋設して削孔2
を形成する()。この場合ケーシング1を杭と
して利用することもできる。
First, bury casing 1 in a predetermined position and drill hole 2.
form(). In this case, the casing 1 can also be used as a stake.

続いてこの削孔2に柱aを頭部の下まで挿入す
るとともに、地上にトラス3の組み立てのための
盤木4を設置し、柱aの頭部下にジヤツキ5をセ
ツトして頭部にトラス3を組み立てる()。
Next, insert the column a into the drilled hole 2 to the bottom of the head, set up a board 4 on the ground for assembling the truss 3, and set the jack 5 under the head of the column a to remove the head. Assemble truss 3 ().

トラス架構bの組み立て終了後、必要な屋根仕
上げ、設備配管等を施し()、柱aおよびトラ
ス架構b全体をジヤツキアツプする。なお柱aの
下端外周にはローラまたはジヤツキを突設して柱
の上昇の安定度を確保する()。
After completing the assembly of truss frame b, necessary roof finishing, equipment piping, etc. are applied (), and column a and the entire truss frame b are jacked up. A roller or jack is provided protruding from the outer periphery of the lower end of column a to ensure stability in the upward movement of the column ().

柱aおよびトラス架構bを所定の高さまでジヤ
ツキアツプした後、削孔2内にコンクリート6等
を充填して柱aを定着させ()、建物の架構A0
が構築される。このとき必要に応じて柱aとケー
シング1と金物等によつて連結する。
After jacking up column a and truss frame b to a predetermined height, concrete 6, etc. is filled into drilled hole 2 to fix column a (), and building frame A 0
is constructed. At this time, the column a and the casing 1 are connected by hardware or the like, if necessary.

第2図はジヤツキアツプ開始から終了までの架
構A0の構築の様子を示したものである。
Figure 2 shows the construction of the frame A0 from the start to the end of the jack-up.

また第3図はジヤツキアツプの様子の詳細を例
示したものである。は上昇開始時の、〜は
上昇時の様子を示す。
Further, FIG. 3 shows a detailed example of the state of the jack up. indicates the state at the start of the ascent, and ~ indicates the state at the time of the ascent.

に示すように削孔2の周囲には基礎7が形成
され、この基礎7上にジヤツキ5をセツトするた
めの架台8が据え付けられる。基礎7下には基礎
杭9が打ち込まれている。図では架台8およびジ
ヤツキ5を地下部分に設置しているが、地上に設
置しても勿論差し支えない。
As shown in FIG. 2, a foundation 7 is formed around the drilled hole 2, and a pedestal 8 for setting the jack 5 is installed on this foundation 7. Foundation piles 9 are driven under the foundation 7. In the figure, the frame 8 and jack 5 are installed underground, but they may of course be installed above ground.

ジヤツキ5はその基部において架台8に取り付
けられ、その上方にはロツドの上下動に従つて昇
降する昇降架台10が設置されている。
The jack 5 is attached to a pedestal 8 at its base, and above it is installed an elevating pedestal 10 that moves up and down as the rod moves up and down.

柱aは架台8、もしくは昇降架台10の位置に
おいてジヤツキ5を貫通して柱aの側面に設けら
れた溝a−1にピン11を差し込むことによつて
ジヤツキ5に固定されるようにしてある。
The column a is fixed to the jack 5 by penetrating the jack 5 at the position of the pedestal 8 or the elevating frame 10 and inserting a pin 11 into a groove a-1 provided on the side surface of the column a. .

柱aの上昇は、まず昇降架台10において溝a
−1にピン11を差し込んでジヤツキアツプし
()、その状態で架台8のピン11を差し込むと
ともに、昇降架台10のピン11を抜いてジヤツ
キダウンする()、という手順で行われる。,
はさらに柱aをストローク上昇させた様子を示
している。
The raising of the column a is first carried out in the groove a in the elevating frame 10.
-1 to jack it up (), then insert the pin 11 of the pedestal 8 in this state, and pull out the pin 11 of the elevating pedestal 10 to jack it down (). ,
2 shows a state in which the column a is further raised by a stroke.

この周辺部の架構Bの構築は建物中央部の架構
Aの構築と平行して、または構築後に第4図のよ
うにレール12上を移動自在とされた仮設足場1
3によりトラス架構b′を組み立てて行われる。
The construction of the frame B in the peripheral area can be carried out in parallel with the construction of the frame A in the central part of the building, or after construction, the temporary scaffolding 1 is movable on the rails 12 as shown in Fig. 4.
3, the truss frame b' is assembled.

この施工方法は、図示するように中央部の架構
Aに沿つてレール12を敷設した後、レール12
の端部に組み立てられた仮設足場13を設置し
()、仮設足場13を移動させながら中央部のト
ラス架構Aの周辺にこれに連続してトラス3を組
み立てていく()、という要領で行われる。
This construction method involves laying the rails 12 along the frame A in the center as shown in the figure, and then
The assembled temporary scaffolding 13 is installed at the end of the building (), and the truss 3 is successively assembled around the truss frame A in the center while moving the temporary scaffolding 13 (). be exposed.

図示した実施例では中央部の架構Aの周辺を周
回して架構Bを構築しているが、この架構Bは中
央部の架構A周辺部の一部だけの場合もある。
In the illustrated embodiment, the frame B is constructed by going around the frame A in the center, but the frame B may be only a part of the periphery of the frame A in the center.

続いて第5図乃至第7図に基づいて第二の発明
による中央部の架構Aの構築方法を説明する。
Next, a method of constructing the central frame A according to the second invention will be explained based on FIGS. 5 to 7.

この発明は柱aを地上に設置し、地組みされた
トラス架構bを柱a頭部までリフトアツプして建
物中央部の架構Aを構成する方法である。
This invention is a method of constructing a frame A in the center of a building by installing a column a on the ground and lifting up a truss frame b assembled on the ground to the head of the column a.

中央部の施工手順を第5図により説明する。 The construction procedure for the central part will be explained with reference to FIG.

まず所定の位置に柱aを建込んで設置するとと
もに、盤木4を設置してトラス3を組み立てる
()。
First, the pillar a is erected and installed at a predetermined position, and the board 4 is installed to assemble the truss 3 ().

トラス架構bの組み立て後、柱a頭部にジヤツ
キ14を、柱a頭部、トラス架構b間にロツド1
5を設置する()。第6図はジヤツキ14およ
びロツド15を設置した様子を示したものである
が、ジヤツキ14は柱a頭部の周囲に配置される
上部架台16と下部架台17間に据え付けられ、
ロツド15は上下架台16,17を貫通し、トラ
ス架構bの下面に受梁18を介してそれぞれナツ
ト19により接続される。
After assembling truss frame b, put a jack 14 on the head of column a, and a rod 1 between the head of column a and truss frame b.
Set 5(). FIG. 6 shows how the jack 14 and rod 15 are installed, and the jack 14 is installed between the upper frame 16 and the lower frame 17 arranged around the head of column a.
The rod 15 passes through the upper and lower frames 16 and 17, and is connected to the lower surface of the truss frame b via a support beam 18 with a nut 19, respectively.

ここでトラス架構b全体を柱a頭部の下までジ
ヤツキ14によりリフトアツプし()、柱aと
トラス架構bとを接続する()。そしてジヤツ
キ14、ロツド15、架台16,17等を撤去し
て中央部の架構Aが形成される()。
Here, the entire truss frame b is lifted up by the jack 14 to below the head of column a (), and column a and truss frame b are connected (). Then, the jack 14, rod 15, frames 16, 17, etc. are removed to form the central frame A ().

トラス架構bのリフトアツプは、第7図に示す
ように初めに上部架台16上のナツト19を締め
付け()、この状態で上部架台16をジヤツキ
アツプすることによつてロツド15を引き上げ
()、続いて下部架台17上のナツト19を締め
()、上部架台16をジヤツキダウンする()、
という手順を繰り返して行われる。
To lift up the truss frame b, as shown in FIG. Tighten the nut 19 on the lower pedestal 17 (), and jack down the upper pedestal 16 ();
This procedure is repeated.

周辺部の架構Bの構築は第一の発明の方法と全
く同様に行われる。
Construction of the peripheral frame B is performed in exactly the same manner as the method of the first invention.

〔発明の効果〕〔Effect of the invention〕

この発明は以上の通りであり、建物を中央部と
周辺部とに別けて施工し、建物の中央部をトラス
架構のジヤツキアツプまたはリフトアツプによる
上昇により、さらに周辺部では移動仮設足場を利
用して構築を行うものであるため、支保工が大幅
に削減され、全体的に施工の省力化、工期の短縮
化を実現することができ、特に大規模建物を安全
に施工できる。
This invention is as described above, and a building is constructed separately into a central part and a peripheral part, and the central part of the building is raised by jack-up or lift-up of a truss frame, and the peripheral part is constructed by using movable temporary scaffolding. Because it performs this, the need for shoring is significantly reduced, making it possible to save labor and shorten the construction period overall, making it possible to safely construct large-scale buildings in particular.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図は中央部の構築手順を示した概要図、第
2図はその一部斜視図、第3図はジヤツキアツプ
の様子を示した手順図、第4図は周辺部の構築の
様子を示した斜視図である。第5図は中央部の構
築手順を示した概要図、第6図はジヤツキおよび
ロツドの設置状態を示した詳細図、第7図はリフ
トアツプの様子を示した手順図である。 A0……主要部の架構、A……中央部の架構、
B……周辺部の架構、a……柱、a−1……溝、
b,b′……トラス架構、1……ケーシング、2…
…削孔、3……トラス、4……盤木、5……ジヤ
ツキ、6……コンクリート、7……基礎、8……
架台、9……基礎杭、10……昇降架台、11…
…ピン、12……レール、13……仮設足場、1
4……ジヤツキ、15……ロツド、16……上部
架台、17……下部架台、18……受梁、19…
…ナツト。
Figure 1 is a schematic diagram showing the construction procedure for the central part, Figure 2 is a partial perspective view, Figure 3 is a procedure diagram showing the jack up, and Figure 4 is a diagram showing the construction of the peripheral part. FIG. FIG. 5 is a schematic diagram showing the construction procedure of the central part, FIG. 6 is a detailed diagram showing the installation state of the jack and rod, and FIG. 7 is a procedural diagram showing the state of lift-up. A 0 ...Main part frame, A...Central part frame,
B...Peripheral frame, a...Column, a-1...Groove,
b, b′...Truss frame, 1...Casing, 2...
...drilling, 3...truss, 4...board, 5...jacketing, 6...concrete, 7...foundation, 8...
Frame, 9...Foundation pile, 10...Elevating frame, 11...
...Pin, 12...Rail, 13...Temporary scaffolding, 1
4... Jacket, 15... Rod, 16... Upper frame, 17... Lower frame, 18... Support beam, 19...
...Natsuto.

Claims (1)

【特許請求の範囲】 1 建物中央部の所定位置の地中に形成された削
孔内にケーシングを埋設し、そのケーシング内に
一定長の柱を挿入し、地上において柱頭部にトラ
ス部材を接合してトラス架構を形成した後、柱お
よびトラス架構全体をジヤツキアツプして建物中
央部の架構を構築するとともに、建物中央部の周
辺部の地上にその中央部の架構に沿つてレールを
敷設し、この上方にレール上を移動可能な仮設足
場を設置し、この仮設足場を移動させながらこの
仮設足場を利用して建物中央部のトラス架構の周
辺に、これに連続してトラス部材を組み立てて建
物周辺部の架構を構築する大規模建物の構築方
法。 2 建物中央部の所定位置の地上に柱を建込んで
設置し、地上において柱基部の周囲にトラス部材
を組み立ててトラス架構を形成した後、トラス架
構全体を柱頭部の位置までリフトアツプして建物
中央部の架構を構築するとともに、建物中央部の
周辺部の地上にその中央部の架構に沿つてレール
を敷設し、この上方にレール上を移動可能な仮設
足場を設置し、この仮設足場を移動させながらこ
の仮設足場を利用して建物中央部のトラス架構の
周辺にこれに連続してトラス部材を組み立てて建
物周辺部の架構を構築するトラス大規模建物の構
築方法。
[Claims] 1. A casing is buried in a hole formed in the ground at a predetermined location in the center of a building, a column of a certain length is inserted into the casing, and a truss member is joined to the column head above ground. After forming a truss frame, the pillars and the entire truss frame are jacked up to construct a frame in the center of the building, and rails are laid along the center frame on the ground around the center of the building. A temporary scaffold that can move on rails is installed above this, and while the temporary scaffold is moved, truss members are assembled around the truss frame in the center of the building in succession, using this temporary scaffold to assemble the building. A method of constructing a large-scale building that constructs a frame around the periphery. 2. After erecting and installing columns on the ground at a predetermined location in the center of the building, assembling truss members around the base of the column on the ground to form a truss frame, the entire truss frame is lifted up to the position of the column head and the building is completed. In addition to constructing a central frame, rails are laid on the ground around the center of the building along the central frame, and above this a temporary scaffold that can move on the rails is installed. This is a method of constructing a large-scale truss building, in which the temporary scaffolding is moved while being moved, and truss members are continuously assembled around the truss frame in the center of the building to construct a frame around the building's periphery.
JP31253186A 1986-12-29 1986-12-29 Construction of large-scaled building Granted JPS63167828A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP31253186A JPS63167828A (en) 1986-12-29 1986-12-29 Construction of large-scaled building

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP31253186A JPS63167828A (en) 1986-12-29 1986-12-29 Construction of large-scaled building

Publications (2)

Publication Number Publication Date
JPS63167828A JPS63167828A (en) 1988-07-11
JPH0473499B2 true JPH0473499B2 (en) 1992-11-20

Family

ID=18030345

Family Applications (1)

Application Number Title Priority Date Filing Date
JP31253186A Granted JPS63167828A (en) 1986-12-29 1986-12-29 Construction of large-scaled building

Country Status (1)

Country Link
JP (1) JPS63167828A (en)

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5214016A (en) * 1975-06-16 1977-02-02 Takenaka Komuten Co Construction method of ground building

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5214016A (en) * 1975-06-16 1977-02-02 Takenaka Komuten Co Construction method of ground building

Also Published As

Publication number Publication date
JPS63167828A (en) 1988-07-11

Similar Documents

Publication Publication Date Title
US5839239A (en) Apparatus and method for building construction
JP3732586B2 (en) Method and apparatus for constructing steel structure
JP2000291031A (en) Construction method for base isolation structure
JPH0473499B2 (en)
JPH0932120A (en) Method of construction of structure
JP2723431B2 (en) Construction method of steel framed house
JP3066460B2 (en) How to build a tower
CN112681525B (en) Jacking and supporting system and method for large-span steel structure
JP2871468B2 (en) How to build a building
JP2684956B2 (en) Steel erection in a structure
JPH0742179A (en) Modified inversion placing construction method
JP3038076B2 (en) Jack device for construction work
JPH0874278A (en) Construction method for large underground space
JP3416759B2 (en) Underground structure frame building equipment
JPH0657769A (en) Underground concrete structure and working method thereof
JP2696486B2 (en) Building construction method
JPH0347375A (en) Space truss erection method and push-up device
JPH056621B2 (en)
JP2946372B2 (en) Construction method of structure
JPH01214619A (en) Construction method for subsurface structure
JPH0387439A (en) Construction method
JP2884398B2 (en) Construction method of building structure and lifting device of building structure
JP2704447B2 (en) Lift-up method using permanent columns
SU1726702A1 (en) Method of construction skeleton of a building
SU920112A1 (en) Method of erecting a stationary platform