JPH0471196B2 - - Google Patents

Info

Publication number
JPH0471196B2
JPH0471196B2 JP58104039A JP10403983A JPH0471196B2 JP H0471196 B2 JPH0471196 B2 JP H0471196B2 JP 58104039 A JP58104039 A JP 58104039A JP 10403983 A JP10403983 A JP 10403983A JP H0471196 B2 JPH0471196 B2 JP H0471196B2
Authority
JP
Japan
Prior art keywords
construction
ground
building
foundation
work
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP58104039A
Other languages
Japanese (ja)
Other versions
JPS59228532A (en
Inventor
Tadao Suzuki
Suetsugi Ishii
Shinji Hashida
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hitachi Ltd
Logisteed Ltd
Original Assignee
Hitachi Ltd
Hitachi Transport System Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hitachi Ltd, Hitachi Transport System Ltd filed Critical Hitachi Ltd
Priority to JP58104039A priority Critical patent/JPS59228532A/en
Publication of JPS59228532A publication Critical patent/JPS59228532A/en
Publication of JPH0471196B2 publication Critical patent/JPH0471196B2/ja
Granted legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes

Description

【発明の詳細な説明】 〔発明の利用分野〕 本発明は、半地下式の原子力発電プラントを建
設する現場において、主に移動クレーンの走行等
に好適な作業表面を提供する建設用基礎台に関す
るものである。
[Detailed Description of the Invention] [Field of Application of the Invention] The present invention relates to a construction foundation that provides a suitable working surface for the movement of a mobile crane, etc., mainly at a site where a semi-underground nuclear power plant is constructed. It is something.

〔発明の背景〕[Background of the invention]

一般に、原子力発電プラントの建設工事には、
固定式の大型クレーンを用いることが多く行なわ
れ、その吊り能力は、吊り荷重と吊り作業半径に
密接な関係を有していて、特に吊り荷重が同一で
ある場合には作業半径の距離に比例してその吊り
能力が低減する関係にあるから、前記大型クレー
ンの設置は出来るだけ吊り作業半径を短かくした
位置とすることが望ましいとされている。このた
めに、前記大型クレーンを原子炉建屋躯体内に設
置する例さえも知られているが、この場合には、
クレーンが解体されるまで建屋建設の工事等と干
渉することが避け難いので、建設工期の短縮は得
られないという難点がある。
In general, construction work for nuclear power plants includes:
Fixed large cranes are often used, and their lifting capacity is closely related to the lifting load and the lifting work radius, and especially when the lifting load is the same, the lifting capacity is proportional to the distance of the work radius. Therefore, it is desirable to install the large crane at a position where the lifting radius is as short as possible. For this purpose, it is even known that the large crane is installed inside the reactor building, but in this case,
Since it is difficult to avoid interfering with building construction work until the crane is dismantled, there is a drawback that the construction period cannot be shortened.

そこで一般には、前記建屋内の工事等と干渉し
ない建屋屋外であつて、この建屋と出来るだけ近
接した位置の工事用仮設作業地面に基盤を設け、
この上に固定式の大型クレーンを設置するのが普
通である。
Therefore, in general, a base is installed on a temporary work ground for construction outside the building that does not interfere with the construction work inside the building, and as close as possible to the building.
A large fixed crane is usually installed on top of this.

なお前記の場合、半地下式の原子力発電プラン
トの建設にあたつては、建屋構築エリアである基
礎部と同様に地表面から掘削されて建屋外近傍の
工事用仮設地面として形成されたエリアの一部
に、前記大型クレーン設置用の基盤を岩盤から構
築するものであるから、この大型クレーンの稼動
範囲内まで、建屋内に搬入すべき所定の機器等を
運び込むことが必要となるのは言うまでもない。
In the above case, when constructing a semi-underground nuclear power plant, the area excavated from the ground surface and formed as temporary ground for construction near the outside of the building, as well as the foundation, which is the building construction area, must be In part, because the foundation for installing the large crane is constructed from bedrock, it goes without saying that it is necessary to carry certain equipment into the building within the operating range of the large crane. stomach.

第1図は、このような従来知られる代表的な半
地下式原子力発電プラントのプロツトプランを示
したものであり、地表面4から掘削された建設現
場の略中央には、原子力発電設備、その機器を収
容する原子炉建屋1と、タービン建屋2(なおそ
の他の建屋等の図示は省略している)が位置して
いる。またこれら建屋1,2の周囲には、地表面
からの掘削によつて地表面よりも低いエレベーシ
ヨンの工事用仮設地面3が設けられ、更に地表面
4と前記工事用仮設作業地面3の間には、これら
の間を連絡する通路としての比較的急傾斜なアク
セス路、および土砂崩れ防止のための斜視がつい
た法面が設けられている。
Figure 1 shows the prototype of a typical semi-underground nuclear power plant known in the art. At approximately the center of the construction site excavated from the ground surface 4, there is a nuclear power generation facility, A reactor building 1 and a turbine building 2 (other buildings and the like are not shown) are located, which house the equipment. Further, around these buildings 1 and 2, a temporary construction ground 3 with an elevation lower than the ground surface is provided by excavation from the ground surface, and further between the ground surface 4 and the temporary construction work ground 3. A relatively steeply sloping access road is provided to connect these areas, and a beveled slope is provided to prevent landslides.

なお第1図の従来例では、別の地表面からこれ
と同じエレベーシヨンで水平に延設設置された仮
設架構台8が設けられているが、この点について
は後記する。
In the conventional example shown in FIG. 1, a temporary frame base 8 is provided which extends horizontally from another ground surface with the same elevation as this, but this point will be described later.

以上の形式をなす半地下式原子力発電プラント
の建設においては、工事用仮設作業地面3の建屋
1,2近傍に固定式の大型クレーン7を設置して
いるのが普通であるのは前述した通りであり、し
たがつて搬入機器等をこのクレーン近くまで運ぶ
場合は、前記した急傾斜でかつ幅の狭いアクセス
路を通つて車輌等によりこれを運ぶことが必要と
なり、それ故に形状、寸法、重量等の点から大型
吊り込み品については別途の方法に頼らざるを得
なくなつている。このことから一般に大型吊り込
み品の場合は、前記大型クレーンの稼動範囲内に
大型化地組作業用定盤エリア50と、部材吊り上
げエリア51とをそれぞれ確保することが必要に
なり、その結果として工事の初期における膨大な
土量の掘削、その後の埋め戻しに多大な作業・時
間・費用を要することになつてしまつている。更
に部材吊り上げエリア51は、一般に埋め戻し部
分に位置するために埋め戻し工事と干渉するとい
う難点もある。
As mentioned above, in the construction of a semi-underground nuclear power plant of the above type, it is normal to install a large fixed crane 7 near the buildings 1 and 2 on the temporary work ground 3 for construction. Therefore, when transporting equipment, etc. to the vicinity of this crane, it is necessary to transport it by vehicle etc. through the steeply sloping and narrow access road mentioned above. For these reasons, it is becoming necessary to rely on separate methods for large suspended items. For this reason, in the case of large-sized items to be lifted, it is generally necessary to secure a surface plate area 50 for large-sized ground assembly work and a member lifting area 51 within the operating range of the large crane, and as a result, Excavation of a huge amount of earth at the beginning of construction and backfilling afterwards requires a great deal of work, time, and cost. Furthermore, since the member lifting area 51 is generally located in the backfilling area, there is also the problem that it interferes with the backfilling work.

そこで、これらの難点を解消するものとして前
記した仮設架構台8を用いることも提案されてお
り、これにより地表面から同じ高さで前記大型ク
レーンの稼動範囲内まで吊り込み部材を運び込む
ことを可能としているのであるが、これも埋戻し
工事期間中の部材吊り上げエリア確保の点での利
点はあるにしても、反面、架構台の構築のために
莫大な作業・費用を要するという難点もある。
Therefore, as a solution to these difficulties, it has been proposed to use the above-mentioned temporary frame platform 8, which makes it possible to carry the suspended member within the operating range of the large crane at the same height from the ground surface. Although this method has the advantage of securing an area for lifting parts during the backfilling period, it also has the disadvantage of requiring a huge amount of work and cost to construct the frame base.

なお第2図は、前記第1図A−A線の断面を示
しており、これにより建設現場の垂直的構造が理
解されよう。図中20は建屋1の外壁を示してい
る。
Note that FIG. 2 shows a cross section taken along line A--A in FIG. 1, which will help understand the vertical structure of the construction site. In the figure, 20 indicates the outer wall of the building 1.

以上の如く、従来法による半地下式原子力発電
プラントの建設においては、種々の問題があり、
また前記大型クレーンが固定式であることについ
ても、これが建屋屋外近傍の工事用仮設作業地面
に設置されるために、建屋工事の施行と干渉する
という問題もある別に指摘されるところとなつて
いる。
As mentioned above, there are various problems in the construction of semi-underground nuclear power plants using conventional methods.
Furthermore, the fact that the large crane is of a fixed type has also been pointed out as a problem in that it interferes with the execution of building construction work because it is installed on the temporary construction work ground near the outside of the building. .

〔発明の目的〕[Purpose of the invention]

本発明の目的は、前記した半地下式原子力発電
プラントの建設工事において移動式クレーンを好
適に使用できるようにすることと、掘削エリアを
出来るだけ減少して掘削・埋設しの作業に伴う難
点を軽減させ、合わせて建設作業・土木作業と不
干渉の状態で部品の吊り込み作業が行なえるよう
にすることにある。
The purpose of the present invention is to enable the use of a mobile crane in the construction work of the above-mentioned semi-underground nuclear power plant, and to reduce the excavation area as much as possible to eliminate the difficulties associated with excavation and burying work. The purpose is to reduce the amount of noise and allow parts to be lifted without interfering with construction and civil engineering work.

〔発明の概要〕[Summary of the invention]

本発明は、原子炉圧力容器、原子炉格納容器、
熱交換器、タービン発電機の機器を収容する半地
下式建屋を構築するため地表面から掘削して形成
される建屋用基礎部と、この建屋用基礎部の周囲
作業地面として前記地表面から若干浅く掘削され
る工事用仮設作業地面と、前記地表面から工事用
仮設作業地面に至るよう傾斜して形成されるアク
セス路を設けてなる半地下式原子力発電プラント
の建設現場において、前記地表面から同一のエレ
ベーシヨンにて前記建屋用基礎部の近傍まで続
き、かつ垂直側壁により前記工事用仮設作業地面
に対し段差をもつて隔離された台状をなして移動
式クレーンの走行・旋回・作業表面を提供するよ
うに構築されたことを特徴とするものである。
The present invention provides a reactor pressure vessel, a reactor containment vessel,
In order to construct a semi-underground building to house equipment such as heat exchangers and turbine generators, there is a building foundation that is excavated from the ground surface and a working ground that is slightly above the ground surface surrounding this building foundation. At the construction site of a semi-underground nuclear power plant, which has a shallowly excavated temporary work ground for construction and an access road formed at an angle from the ground surface to the temporary work ground for construction, The same elevation extends to the vicinity of the building foundation, and forms a platform separated from the temporary work ground by a vertical side wall with a step, allowing the mobile crane to travel, turn, and work on the surface. It is characterized by being constructed to provide.

〔発明の実施例とその効果〕[Embodiments of the invention and their effects]

以下本発明を図面に示す実施例に基づいて説明
する。
The present invention will be described below based on embodiments shown in the drawings.

第3図は、本発明を適用した半地下式原子力発
電プラントの建設現場の一例を示す平面図であ
り、第4図は第3図B−B線の断面図を示してい
る。
FIG. 3 is a plan view showing an example of a construction site of a semi-underground nuclear power plant to which the present invention is applied, and FIG. 4 is a sectional view taken along line BB in FIG. 3.

本実施例において前記第1図および第2図に示
したものと異なるのは、地表面と同じエレベーシ
ヨンをなす建設用基礎台9が、原子炉圧力容器、
原子炉格納容器、熱交換器、タービン発電機の機
器を収容する半地下式建屋1,2を構築するため
の建屋用基礎部1Aの近傍まで近接して設けられ
ていること、したがつてこの建設用基礎台9上に
移動式クレーン10が位置するために、大型化地
組作業用定盤エリア50および部材吊り上げエリ
ア51もこの建設用基礎台9上に在ることの点に
あり、その他の点は前記第1図の例と同じである
ので共通する部分には同一の符号を付して説明を
省略する。
The difference in this embodiment from those shown in FIGS. 1 and 2 is that the construction foundation 9, which has the same elevation as the ground surface,
It must be located close to the building foundation 1A for constructing the semi-underground buildings 1 and 2 that house the equipment of the reactor containment vessel, heat exchanger, and turbine generator; Since the mobile crane 10 is located on the construction foundation 9, the enlarged ground assembly work surface plate area 50 and the member lifting area 51 are also located on this construction foundation 9, and other Since these points are the same as those in the example shown in FIG. 1, common parts are given the same reference numerals and their explanation will be omitted.

本実施例における建設用基礎台9は、前記の如
く地表面4と同じエレベーシヨンで建屋用基礎部
1Aの近傍まで位置する如く設けられて、その表
面が移動式クレーン10の走行・旋回・作業表面
を提供するものであるから、建屋建設のための作
業空間を作り出すように地表から掘削形成された
工事用仮設作業地面3とは、垂直的に段差を生ず
ることになる。このため前記建設用基礎台9の周
囲は、工事用仮設作業地面3およびこれに付随し
て設けられるアクセス路6、法面5との間で、隔
離用山留め垂直側壁11によつて囲まれている。
The construction foundation 9 in this embodiment is provided so as to be located near the building foundation 1A at the same elevation as the ground surface 4 as described above, and its surface is used for traveling, turning, and operation of the mobile crane 10. Since it provides a surface, there will be a vertical difference in level from the temporary construction work ground 3 that is excavated from the ground surface to create a work space for building construction. For this reason, the periphery of the construction foundation 9 is surrounded by isolation vertical side walls 11 between the temporary work ground 3 for construction, the access road 6 provided incidentally thereto, and the slope 5. There is.

この側壁11は、建設用基礎台9を構成する地
盤41の土質および土質構造等により支配される
前記移動式クレーンの接地圧に基づく側圧に充分
耐え得る構成にする必要があり、例えば擁壁形
式、矢板形式等にて垂直壁構造を構築し、更に必
要に応じてアンカー(図示せず)などの補強を施
せばよい。
This side wall 11 needs to have a structure that can sufficiently withstand the lateral pressure based on the ground pressure of the mobile crane, which is controlled by the soil quality and soil structure of the ground 41 constituting the construction foundation 9. For example, it is in the form of a retaining wall. , a vertical wall structure may be constructed in the form of sheet piles, etc., and further reinforced with anchors (not shown) or the like as necessary.

またこの建設用基礎台9は、移動式クレーン1
0の接地圧以上の地耐力を必要とされ、通常の地
盤であれば地山のまま利用してもよいが、場合に
よつて地盤41に杭打ちして地盤強化を図り、あ
るいは鉄板、鉄筋コンクリート等による養生層4
2を形成させて、地盤への荷重分散を図ることを
行なえばよい。
This construction foundation 9 also includes a mobile crane 1.
If it is a normal ground, it may be used as it is, but in some cases, it may be necessary to strengthen the ground by driving piles into the ground 41, or by using steel plates or reinforced concrete. Curing layer 4 by etc.
2 to distribute the load to the ground.

このように建設用基礎台9は、地山をそのまま
あるいは前記のような地盤強化を図つて利用され
るものであるが、地表面から掘削をしない部分で
あるからこの分の掘削・埋戻しがいらないのは言
うまでもない。
In this way, the construction foundation 9 is used as it is or to strengthen the ground as described above, but since it is a part that is not excavated from the ground surface, excavation and backfilling are necessary. Needless to say, I don't need it.

また本実施例は、このような位置・構造を持つ
た建設用基礎台9により、原子炉建屋等への屋内
に所定の機器等を移動式クレーンにより吊り込み
するのに好適な作業面を提供するものであるか
ら、吊り込みを行なう移動式クレーンは、その機
能に基づき、負荷時・無負荷時を問わず走行・旋
回・起伏が可能であると共に、これによつて固定
式クレーンの場合のような稼動範囲内への部材等
の運び込みの必要はなく、第3図に示す如く例え
ば大型化地組作業用定盤エリア50の位置等を任
意に設定できるという利点がある。更にこのよう
な利点から、建設工事において種々の作業等が輻
輳するクレーン近傍のエリアを効果的にかつ多目
的に活用できるという利益も得られることになる
のである。
Furthermore, in this embodiment, the construction foundation 9 having such a position and structure provides a work surface suitable for lifting predetermined equipment into a reactor building or the like using a mobile crane. Therefore, based on its functions, a mobile crane that performs lifting is capable of traveling, turning, and raising and lowering regardless of whether it is loaded or unloaded. There is no need to carry members and the like into the operating range, and there is an advantage that, as shown in FIG. 3, the position of, for example, the surface plate area 50 for large-scale earth assembly work can be arbitrarily set. Further, due to these advantages, the area near the crane, where various operations are congested during construction work, can be used effectively and for multiple purposes.

なお第3図中の符号60は、部材吊り上げエリ
ア51へのアクセス路を示している。
Note that the reference numeral 60 in FIG. 3 indicates an access path to the member lifting area 51.

第5図〜は、前記建設用基礎台9上におい
て移動式クレーン10により行なわれる部材吊り
込み作業の手順一例を示したものであり、車輌7
0により適宜の位置まで運ばれてきた対象機器
は、その付近まで走行してきた移動式クレーン1
0により吊り上げされ(第5図参照)、次いで
旋回した後吊り込みすべき建屋1の方向に走行し
て建設用基礎台9の縁付近に至る(第5図,
参照)。
FIGS. 5 to 5 show an example of a procedure for lifting a member onto the construction foundation 9 using the mobile crane 10, and show an example of the procedure for lifting a member onto the construction foundation 9.
The target equipment that has been transported to the appropriate location by the mobile crane 1 that has traveled to the vicinity
0 (see Fig. 5), then rotates and travels in the direction of the building 1 to be lifted, reaching near the edge of the construction foundation 9 (see Fig. 5,
reference).

次いでブームを倒して位置合せしながら前記機
器を建屋1内の所定部に吊り下し(第5図参
照)、作業を終了する。
Next, the equipment is suspended from a predetermined part in the building 1 while the boom is brought down and aligned (see Fig. 5), and the work is completed.

吊り上げする部材が大型化地組作業定盤エリア
50に在る場合も同様に行なえばよく、このよう
に移動式クレーン10の機能を充分発揮させるこ
とで好適な部材吊り込み作業が行なうことができ
る。
The same procedure can be performed even when the member to be lifted is located in the large-sized ground assembly work surface plate area 50, and by fully utilizing the functions of the mobile crane 10 in this way, suitable member lifting work can be performed. .

なお、吊り込み作業は前記の例に限定されるも
のではない。すなわちクレーンの一作業に要する
時間はその走行・起伏・旋回等の動作回数に比例
するから、作業所要時間を出来るだけ短縮させる
という観点からはクレーンの動作回数を出来るだ
け少なくした搬入作業が望まれるのであり、この
ために、例えば建設用基礎台9の出来るだけ建屋
側の位置まで対象機器を車輌等で運び込みし、移
動式クレーン10は第5図の姿勢で該機器を吊
り上げするものとすれば、旋回動作の省略が行な
えるのである。更にまた、第3図で示しているア
クセス路6、工事用仮設作業地面3は、建屋建設
の進捗状況に応じて逐次埋戻しされるが、工期の
かなりの間は利用可能であるから、これを利用す
ることでより動作回数を減らした搬入作業を行な
えることになる。第6図,はこの場合の作業
状況を示しており、アクセス路6上まで車輌70
にて対象機器を運び込み、建設用基礎台9上で停
止している移動式クレーン10のブームの起伏動
作・吊り上げ、吊り下げ動作で搬入を行なうよう
にしているのである。この作業によれば、クレー
ンは旋回のみならず更に走行を行なうことを要し
ないという利点が得られることになる。
Note that the lifting work is not limited to the above example. In other words, since the time required for one crane operation is proportional to the number of operations such as traveling, raising and lowering, and turning, etc., from the viewpoint of shortening the required operation time as much as possible, it is desirable to perform loading operations with as few crane operations as possible. For this purpose, for example, if the target equipment is carried by a vehicle or the like to a position on the construction foundation 9 as close to the building as possible, and the mobile crane 10 lifts the equipment in the attitude shown in FIG. , the turning operation can be omitted. Furthermore, the access road 6 and temporary work ground 3 shown in Figure 3 will be backfilled in stages according to the progress of building construction, but since they will be available for a considerable period of the construction period, By using this, it is possible to carry out loading operations with fewer operations. Figure 6 shows the work situation in this case.
The target equipment is carried in by the lifting, lifting and hanging operations of the boom of the mobile crane 10 which is stopped on the construction foundation 9. This operation has the advantage that the crane does not have to travel in addition to turning.

第7図,は、本実施例における建設用基礎
台9が地表面と同じエレベーシヨンにあることの
利点を、地表面より掘削した工事用仮設作業面3
上に移動式クレーン10を配置した場合と対比し
て説明するための図である。
FIG. 7 shows the advantage of having the construction foundation 9 in this embodiment at the same elevation as the ground surface, on a temporary construction work surface 3 excavated from the ground surface.
It is a figure for demonstrating in comparison with the case where the mobile crane 10 is arrange|positioned above.

この図から明らかであるように、工事用仮設作
業地面に移動式クレーン10を配置させた場合
(第7図の場合)には、建屋1の外壁20に干
渉されてクレーンの作業半径は大きな制約を受け
るが、本実施例の場合(第7図の場合)には移
動式クレーン10が地表面の高さにあるため、建
屋外壁20による干渉が大幅に緩和されるという
利益が得られているのが理解されよう。
As is clear from this figure, when the mobile crane 10 is placed on the temporary work ground for construction (as in the case of Fig. 7), the working radius of the crane is severely restricted due to interference with the outer wall 20 of the building 1. However, in the case of this embodiment (the case shown in FIG. 7), since the mobile crane 10 is located at the height of the ground surface, there is an advantage that interference by the building outer wall 20 is significantly alleviated. It will be understood that

次ぎに、以上の構造をなす建設用基礎台9を構
築するための施行手順の一例を説明する。
Next, an example of the procedure for constructing the construction foundation 9 having the above structure will be explained.

第8図〜は、半地下式原子力発電プラント
を建設する場合の作業概要を簡単に示したもので
あり、まず一般的に、原子炉建屋、タービン建屋
を囲む所定のエリアを岩盤12に達するまで掘削
機72により法面付のオープンカツト工法によつ
て掘削する。そして前記建屋は、通常、前記基礎
岩盤上に構築されたマンメイドロツク(人造岩)
13の上に、配筋を備えた外壁を順次下から立ち
上げ構築する。なお14はマツトである。
Figures 8 to 8 show a simple outline of the work when constructing a semi-underground nuclear power plant. Generally speaking, a predetermined area surrounding the reactor building and turbine building is constructed until bedrock 12 is reached. Excavation is carried out using an excavator 72 using the open cut method with a slope. The building is usually a man-made rock (artificial rock) built on the foundation rock.
On top of No. 13, an outer wall with reinforcement is built up sequentially from below. Note that 14 is pine.

建屋回りの埋戻し、建屋の構築、建屋内への種
種の機器の吊り込み搬入は、前記建屋外壁20の
構築に応じて行なわれるのである。
Backfilling around the building, construction of the building, and loading and carrying of various types of equipment into the building are performed in accordance with the construction of the building exterior wall 20.

以上の一般的な建設作業において、本実施例の
建設用基礎台9はその計画エリアについては掘削
を行なわず、掘削されるエリアとは側壁により隔
離した状態で地表面と同じエレベーシヨンを保つ
ようにする。
In the general construction work described above, the construction foundation 9 of this embodiment does not excavate the planned area, but maintains the same elevation as the ground surface while separating the area from the excavated area by a side wall. Make it.

なお前記建屋等のエリアの掘削はオープンカツ
ト法の他、垂直直掘法によつてもよく、また第3
図で示したように建屋1,2と建設用基礎台9の
間にアクセス路6を設ける場合において施行をオ
ープンカツト法で行なうときは、アクセス路は埋
戻して行なえばよい。たどし本発明においてこの
ような位置のアクセス路は必ずしも必要なもので
はない。
In addition to the open cut method, the excavation of the area for the buildings etc. may be performed by the vertical direct excavation method, or by the third method.
As shown in the figure, when an access road 6 is provided between the buildings 1 and 2 and the construction foundation 9 and the construction is carried out using the open cut method, the access road may be backfilled. However, in the present invention, an access path in such a position is not necessarily required.

建設用基礎台9の垂直側壁を擁壁形式あるいは
矢板形式等によつて構築すればよいことは既に述
べているが、第8図に示す例ではこれを矢板形式
で行なつている。すなわち、第8図に示す如
く、建設用基礎台9の側壁位置となる位置に、ま
ずくい打ち機71によつて鋼矢板30を順次連設
打ち込みし、次いでこの鋼矢板30の建屋側だけ
を根切りする如く所定の掘削を行なつて、鋼矢板
30の反対側には地表面と同じエレベーシヨンの
ままの面を残すのである。この面が移動式クレー
ンの走行・作業表面を提供することになる。
It has already been stated that the vertical side walls of the construction foundation 9 may be constructed in the form of retaining walls or in the form of sheet piles, but in the example shown in FIG. 8, this is done in the form of sheet piles. That is, as shown in FIG. 8, the steel sheet piles 30 are successively driven into the positions that will become the side walls of the construction foundation 9 using a pile driver 71, and then only the building side of the steel sheet piles 30 is driven. A predetermined amount of excavation is carried out, similar to root cutting, and a surface with the same elevation as the ground surface is left on the opposite side of the steel sheet pile 30. This surface will provide the running and working surface for the mobile crane.

なお、矢板形式でアースアンカー31が必要で
あれば、鋼矢板30の内側を掘削して地盤41に
アンカーを打込み、地盤よりアースアンカー31
にて鋼矢板30を支え、この後埋戻しすればよい
し、掘削をしないアースアンカー工法によつても
よい。
If the earth anchor 31 is required in the sheet pile format, excavate the inside of the steel sheet pile 30 and drive the anchor into the ground 41, and then attach the earth anchor 31 from the ground.
The steel sheet pile 30 may be supported by the ground and then backfilled, or an earth anchor construction method that does not require excavation may be used.

次ぎに以上のようにして構築された建設用基礎
台9は、移動クレーンの接地圧に対する地耐力に
充分対応できる地盤であれば、整地機73による
転圧、整地および鉄板敷設程度の養生によればよ
く、更に土質等によつて地盤強化が必要となる場
合には適当な養成層42を設けることがよい。す
なわち、例えばくい打ち32、鉄鋼製あるいは鉄
筋コンクリート製の養生層を設けるのである。な
おここで説明した整地、転圧、くい打ち等の施工
法は通常のものでよく、前記垂直側壁の構築作業
と同時施工すれば工事の短縮化が図れる。また鉄
板敷設による表面養生は通常行なわれる最も簡易
な方法に属するものであり、鉄鋼製の養生は、例
えばH型鋼、I型鋼をボルト結合ないし溶接によ
つて結合したものであつて、大きな地耐力が得ら
れるものとして知られている。
Next, the construction foundation 9 constructed as described above can be constructed by compacting the ground with a ground leveling machine 73, leveling the ground, and curing it by laying iron plates, if the ground is sufficiently strong enough to withstand the ground pressure of the mobile crane. Furthermore, if ground reinforcement is required due to soil quality, etc., an appropriate cultivation layer 42 may be provided. That is, for example, pilings 32 and a curing layer made of steel or reinforced concrete are provided. Note that the construction methods described here, such as leveling, compaction, and piling, may be conventional methods, and if they are performed simultaneously with the construction of the vertical side walls, the construction period can be shortened. In addition, surface curing by laying iron plates belongs to the simplest method that is usually carried out, and curing made of steel is, for example, H-shaped steel and I-shaped steel joined by bolts or welding, and has a large soil bearing capacity. It is known that it can be obtained.

なお鉄筋コンクリートによる養生法は、その撤
去に手間がかかるが、施工が簡単で大きな地耐力
が得られるものであり、これらの各養生法は必要
に応じ、また目的に応じて選択すればよい。
Although the curing method using reinforced concrete takes time to remove, it is easy to construct and provides a large soil bearing capacity, and each of these curing methods can be selected according to necessity and purpose.

〔発明の変形例、応用例〕[Modifications and application examples of the invention]

本発明は、前記した実施例により説明される基
本的な特徴を持つものであるが、建設用基礎台と
しての広がり範囲を建屋建設に支障のない限りに
おいて拡大するも可能であり、このようにすれば
掘削・埋戻しの労力、費用等がより低減されるこ
とになる。
Although the present invention has the basic features explained in the embodiments described above, it is possible to expand the range of use as a construction foundation as long as it does not impede building construction. This will further reduce the labor and cost of excavation and backfilling.

また、建設用基礎台は移動式クレーンのための
好適な走行・旋回・作業表面を提供するものであ
るが、これと共に、あるいはこれに代えて固定式
の大型クレーンを基礎台上に設置することもでき
る。
Additionally, although construction foundations provide suitable running, turning, and working surfaces for mobile cranes, large fixed cranes may also be installed on the foundation. You can also do it.

更に建設用基礎台の周囲に設けられる垂直側壁
は、一般に10m以上のものとなるものであるか
ら、側圧等を考慮して適当な段階状の構造をなす
ものとしてもよい。すなわち、数m程度毎の1段
あるいは2段程度の若干の幅をもつた段差をつけ
て下部を建屋側に突出させた構造の垂直側壁とし
てもよいのであり、地盤の土質によつては好まし
いものとなる。
Furthermore, since the vertical side walls provided around the construction foundation are generally 10 m or more in length, they may be formed into an appropriate stepped structure in consideration of lateral pressure and the like. In other words, it may be a vertical side wall with a structure in which the lower part protrudes toward the building side with steps with a slight width of one or two steps every few meters, which is preferable depending on the soil quality of the ground. Become something.

〔発明の効果〕〔Effect of the invention〕

本発明は、以上述べた構造の建設用基礎台の構
築によつて移動式クレーンの好適な行・旋回・作
業表面を望ましい位置、高さに得ることができ、
建屋建設工事の作業、埋戻し作業が部材吊り込み
作業と干渉することなく行なえるという利点が得
られると共に、基礎台上の空間を種々の作業に有
効に利用でき、更に建設用基礎台部分は基本的に
掘削・埋戻しの作業が不要であるためそのための
作業労力、費用等の負担が軽減されるという効果
も得られるものである。
The present invention provides the construction of a construction foundation having the structure described above, thereby making it possible to obtain suitable rows, turns, and working surfaces for a mobile crane at desired positions and heights.
This has the advantage that building construction work and backfilling work can be performed without interfering with component lifting work, and the space on the foundation platform can be used effectively for various operations, and the construction foundation section can be Basically, there is no need for excavation and backfilling, so the effect of reducing the burden of work effort, cost, etc. can also be obtained.

【図面の簡単な説明】[Brief explanation of drawings]

第1図は、従来の代表的な半地下式原子力発電
プラントの建設現場概要を説明する平面図、第2
図は第1図A−A線の断面図、第3図は本発明を
適用した同建設現場概要を説明する平面図、第4
図は第3図B−B線断面図、第5図〜は本発
明実施例による部材吊り込み作業手順の一例を説
明する図、第6図,は同アクセス路からの吊
り込み作業手順を示す図、第7図,は、従来
例の場合と本発明の場合の移動式クレーンに与え
る影響を対比して示した図、第8図〜は本発
明の建設用基礎台を構築する作業手順を説明する
ための図である。 1……原子炉建屋、2……タービン建屋、3…
…工事用仮設作業地面、4……地表面、5……法
面、6……アクセス路、7……大型クレーン、8
……仮設架構台、9……建設用基礎台、10……
移動クレーン、12……岩盤、13……マンメイ
ドロツク(人造岩)、14……マツト、20……
建屋外壁、30……鋼矢板、31……アースアン
カー、32……くい、41……地盤、42……地
盤養生層、50……大型化地組作業用定盤エリ
ア、51……部材つり上げエリア、60……アク
セス路、71……くい打ち機、72……掘削機、
73……整地機。
Figure 1 is a plan view explaining the outline of the construction site of a typical conventional semi-underground nuclear power plant;
The figures are a sectional view taken along the line A-A in Figure 1, Figure 3 is a plan view illustrating an outline of the construction site to which the present invention is applied, and Figure 4 is a cross-sectional view taken along line A-A in Figure 1.
The figure is a sectional view taken along the line B-B in Figure 3, Figures 5 to 5 are diagrams for explaining an example of the work procedure for lifting a member according to an embodiment of the present invention, and Figure 6 shows the work procedure for lifting a member from the same access path. Figure 7 shows a comparison of the effects on mobile cranes in the case of the conventional example and in the case of the present invention, and Figures 8 to 8 show the work procedure for constructing the construction foundation of the present invention. It is a figure for explaining. 1...Reactor building, 2...Turbine building, 3...
...Temporary work ground for construction, 4...Ground surface, 5...Slope, 6...Access road, 7...Large crane, 8
...Temporary frame stand, 9...Construction foundation stand, 10...
Mobile crane, 12...Bedrock, 13...Manmade rock (artificial rock), 14...Matsuto, 20...
Building exterior wall, 30...Steel sheet pile, 31...Earth anchor, 32...Pile, 41...Soil, 42...Soil curing layer, 50...Surface plate area for large-sized ground assembly work, 51...Lifting of members Area, 60...access road, 71...pile driver, 72...excavator,
73... Earth leveling machine.

Claims (1)

【特許請求の範囲】[Claims] 1 原子炉圧力容器、原子炉格納容器、熱交換
器、タービン発電機の機器を収容する半地下式建
屋を構築するため地表面から掘削して形成される
建屋用基礎部と、この建屋用基礎部の周囲作業地
面として前記地表面から若干浅く掘削される工事
用仮設作業地面と、前記地表面から工事用仮設作
業地面に至るよう傾斜して形成されるアクセス路
を設けてなる半地下式原子力発電プラントの建設
現場において、前記地表面から同一のエレベーシ
ヨンにて前記建屋用基礎部の近傍まで続き、かつ
垂直側壁により前記工事用仮設作業地面に対し段
差をもつて隔離された台状をなして移動式クレー
ンの走行・旋回・作業表面を提供するように構築
されたことを特徴とする建設用基礎台。
1. A building foundation that is excavated from the ground surface to construct a semi-underground building that will house equipment for the reactor pressure vessel, reactor containment vessel, heat exchanger, and turbine generator, and the foundation for this building. A semi-underground nuclear power plant comprising a temporary work ground for construction excavated slightly shallowly from the ground surface as a work ground around the section, and an access road formed at an angle from the ground surface to the temporary work ground for construction. At the construction site of a power generation plant, a platform is formed that extends from the ground surface to the vicinity of the building foundation by the same elevation, and is separated by a step from the temporary work ground for construction by a vertical side wall. A construction foundation, characterized in that it is constructed to provide a running, turning, and working surface for a mobile crane.
JP58104039A 1983-06-10 1983-06-10 Foundation for construction work Granted JPS59228532A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP58104039A JPS59228532A (en) 1983-06-10 1983-06-10 Foundation for construction work

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP58104039A JPS59228532A (en) 1983-06-10 1983-06-10 Foundation for construction work

Publications (2)

Publication Number Publication Date
JPS59228532A JPS59228532A (en) 1984-12-21
JPH0471196B2 true JPH0471196B2 (en) 1992-11-13

Family

ID=14370077

Family Applications (1)

Application Number Title Priority Date Filing Date
JP58104039A Granted JPS59228532A (en) 1983-06-10 1983-06-10 Foundation for construction work

Country Status (1)

Country Link
JP (1) JPS59228532A (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP5717507B2 (en) * 2011-03-31 2015-05-13 株式会社東芝 Power plant construction method

Also Published As

Publication number Publication date
JPS59228532A (en) 1984-12-21

Similar Documents

Publication Publication Date Title
CN107035159B (en) A method of suitable for frame structure isolated footing building underground increasing layer
CN102434717B (en) Construction method of joist steel pipe-jacking work pit
CN105756091B (en) A kind of Metro station excavation construction method of control adjacent building composition deformation
CN209741877U (en) Cofferdam structure with concrete ring beam water stop additionally arranged at root of steel sheet pile
CN108867692A (en) The protection of city big cross section open trench tunnel Nearby Structure and tunnel foundation pit method for digging
CN206706783U (en) A kind of reusable foundation pit supporting construction
CN110468873A (en) Piles underpinning structure and application method under a kind of small space
CN111255462B (en) Pipe curtain cover excavation top-down construction method for subway station construction
JP2000352296A (en) Method o constructing passage just under underground structure
CN210195766U (en) Underground structure is built in same direction as digging to hunch lid
CN111549789A (en) Reinforcing structure for foundation pit support and construction method thereof
JP4226954B2 (en) Underpinning method and viaduct
CN207111094U (en) Ultra-deep shield launching in a kind of water/hang out well construction
JP2000291398A (en) Underground structure and construction method therefor
JPH0471196B2 (en)
CN211948552U (en) Construction platform for underground space development of dense existing building group
JPS62288269A (en) Method for extending underground stair of building
CN112942377A (en) Novel support shear-resistant structure and construction method thereof
CN113322976A (en) Independent small-space excavation supporting method
JPH0559728A (en) Sheathing work above underground structure
JPH06341154A (en) Construction of underground building frame
JP3511145B2 (en) How to build underground structures
JPH02300422A (en) Construction of underground structure
CN214784063U (en) Combined cofferdam structure
CN113847062B (en) Subway station construction method combining small-diameter jacking pipes with double-layer six-hole piles