JPH0460014A - Ground anchor method - Google Patents

Ground anchor method

Info

Publication number
JPH0460014A
JPH0460014A JP17057790A JP17057790A JPH0460014A JP H0460014 A JPH0460014 A JP H0460014A JP 17057790 A JP17057790 A JP 17057790A JP 17057790 A JP17057790 A JP 17057790A JP H0460014 A JPH0460014 A JP H0460014A
Authority
JP
Japan
Prior art keywords
load
anchor
anchor cable
bearing
cable
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP17057790A
Other languages
Japanese (ja)
Other versions
JPH0472009B2 (en
Inventor
Hideki Noguchi
英樹 野口
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kowa Sangyo KK
Original Assignee
Kowa Sangyo KK
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kowa Sangyo KK filed Critical Kowa Sangyo KK
Priority to JP17057790A priority Critical patent/JPH0460014A/en
Publication of JPH0460014A publication Critical patent/JPH0460014A/en
Publication of JPH0472009B2 publication Critical patent/JPH0472009B2/ja
Granted legal-status Critical Current

Links

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

PURPOSE:To uniform the tensile forces of cables and the loads to load-resisting bodies by engaging a set of anchor cable groups directly with a load-resisting body on the top end, and other cable groups to other load-resisting bodies through elastic bodies, respectively. CONSTITUTION:Twelve anchor cables 3, for example, to be inserted into an anchor hole 2 in the ground G are covered with a sheath tube 8, and four load- resisting bodies 9A-9D, for example, are installed thereto at fixed intervals. The cables 3 are divided into four sets of anchor cable groups 3A-3D as many as the load-resisting bodies 9, and the group 3A is directly engaged with the top end side load-resisting body 9A. Further, the groups 3B-3D are engaged with the load-resisting bodies 9B-9D through elastic bodies 16B-16D whose elastic deforming quantities are set to uniform the tensile forces, respectively, and each group 3A-3D is collectively strained. The elongation and tensile force of each cable 3 is uniformed to uniform the loads generated from the load- resisting bodies 9.

Description

【発明の詳細な説明】 !産業上の利用分野、。[Detailed description of the invention] ! Industrial applications,.

本発明は、地上構造物や山留壁等を地盤に定4する地盤
アノカー工法に関するしのである。
The present invention relates to a ground anode car construction method for fixing above-ground structures, mountain retaining walls, etc. to the ground.

[従来の技術] 地盤アンカーは、一般に、対象地盤の表面に土留め壁を
設けるとともに地盤中にアンカー孔を掘削し、このアン
カー孔に、複数本のアンカーケーブルを孔底ま゛て挿入
してからコンクリート等のグラウト材を注入し、養生期
間経過後、地盤外部に突出させである前記アンカーケー
ブルの端部を、ンヤノキにより緊張するとともにその状
態を保持して土留め壁に定着させることによりなされる
[Prior Art] Generally, a ground anchor is constructed by providing a retaining wall on the surface of the target ground, drilling an anchor hole in the ground, and inserting a plurality of anchor cables into the anchor hole, all the way to the bottom of the hole. Grout material such as concrete is injected into the ground, and after a curing period, the ends of the anchor cables that protrude outside the ground are tightened with a tree and held in that state to be anchored to the earth retaining wall. Ru.

ここで、寿命を2年程度とする仮設構造物はさておき、
永久構造物としての本設アンカーを構築する場合、アン
カーケーブルに対し長期にわたり安定した2重以上の防
錆処理を施すことか要求されており、そのため、アンカ
ーケーブルをシース管やチューブ等で被覆した地盤アン
カー構造かある。
Here, apart from temporary structures that have a lifespan of about two years,
When constructing a permanent anchor as a permanent structure, it is required that the anchor cable be treated with two or more layers of anti-corrosion treatment that is stable over a long period of time. There is a ground anchor structure.

その構造としては、大きく分けると、引張り型アンカー
構造と圧縮型アンカー構造とか知られている。
Broadly speaking, the structures are known as tension type anchor structure and compression type anchor structure.

前者は、アンカーケーブルの自由長部をシース管で、ま
た、定着長部を波状に成形されたフルケートチューブで
被覆し、このコルケートチューフ内にモルタル等のグラ
ウト材を充填・固化させて両者を一体化し、これらをア
ンカーケーブルによって引張る構造である。また、後者
は、アンカーケーブルをソース管で被覆するとともに、
アンカー孔に位置する部分のソース管の外周全体に防錆
被覆を兼ねる耐荷体と呼ばれる耐圧部材を装着し、さら
にこの耐荷体の地中端側にアンカーケーブルの端部を係
合させ、ソース管内にグラウト材を充填しない状態でア
ンカーケーブルを緊張することにより、耐荷体をアンカ
ー孔内のグラウト材内で圧縮させる構造である。この場
合アンカーケーブル全長が自由長部となる。
In the former method, the free length of the anchor cable is covered with a sheath tube, and the anchoring length is covered with a corrugated corrugated tube, and a grout material such as mortar is filled and solidified into the corrugated tube. It has a structure in which both are integrated and pulled together by an anchor cable. In addition, the latter covers the anchor cable with a source tube, and
A pressure-resistant member called a load-bearing body is attached to the entire outer periphery of the source pipe located in the anchor hole, which also serves as a rust-proof coating, and the end of the anchor cable is engaged with the underground end of this load-bearing body, and the inside of the source pipe is This structure compresses the load-bearing body within the grout in the anchor hole by tensioning the anchor cable without filling it with grout. In this case, the entire length of the anchor cable becomes the free length.

上記引張り型のアンカー構造では、フルケートチューブ
、およびこの内外のグラウト材によって、3重にアンカ
ーケーブルが防錆処理されているか、アンカー孔に充填
されたグラウト材に対する荷重分布か手前側(地盤表面
に近い方)に集中し、この部分のグラウト材にクラック
か入りやすい欠点かある。
In the above-mentioned tension-type anchor structure, the anchor cable is triple-rust-proofed by the full-coated tube and the grout material inside and outside, or the load distribution to the grout material filled in the anchor hole is affected by the near side (ground surface The grout material in this area tends to crack or form easily.

また、上記圧縮型のアンカー構造ては、ソース管、耐荷
体およびアンカー孔内のグラウト材による3重の防錆処
理が施されたものとなっている。
Furthermore, the above-mentioned compression type anchor structure is subjected to triple rust prevention treatment using grout material in the source pipe, the load-bearing body, and the anchor hole.

そして、グラウト材に対する荷重分布は、アンカー孔の
奥の方にかかるのでアンカー構造としては良好であるが
、ソース管に装着する前記耐荷体は長大なものとなり、
しかもこの耐荷体は一般にスチール製であるから、取り
扱いや施工性に難かある。
The load distribution on the grout material is applied toward the back of the anchor hole, which is good for the anchor structure, but the load-bearing body attached to the source pipe is long.
Moreover, since this load-bearing body is generally made of steel, it is difficult to handle and construct.

そこで、この圧縮型のアンカー構造の問題を解決したも
のとして、同様に圧縮型ではあるか、ソース管に装着す
る耐荷体を複数に分けて小型化し、複数本のアンカーケ
ーブルを耐荷体の数に対応させて複数組に分け、これら
アンカーケーブルの各組を、それぞれ各耐荷体に固定し
、この状態で全てのアンカーケーブルを緊張するアンカ
ー工法が開発されている。これによれば、1つの耐荷体
か受ける荷重が小さく、しかも耐荷体からアンカー孔内
のグラウト材に対して生しる荷重はおよそ均一に分布さ
せることかでき、取り扱いや施工性も向」ニするといっ
た利点かある。
Therefore, as a solution to the problem of this compression-type anchor structure, the load-bearing body attached to the source pipe is divided into multiple parts to reduce the size of the load-bearing body, and the number of anchor cables is reduced to the number of load-bearing bodies. An anchor construction method has been developed in which the anchor cables are divided into a plurality of corresponding sets, each set of anchor cables is fixed to each load-bearing body, and all the anchor cables are tensioned in this state. According to this, the load that each load-bearing body receives is small, and the load generated from the load-bearing body to the grout material in the anchor hole can be distributed approximately evenly, and handling and construction efficiency are also improved. There are some advantages to doing so.

[発明か解決しようとする課題] ところで、地盤アンカーの施工においては、アンカーケ
ーブルの緊張定着に先立って、アンカーケーブルの緊張
確認試験を行なう。この確認試験は、アンカーケーブル
を引張ったり緩めたりして除々に段階的にアンカーケー
ブルに対する緊張荷重を上げていき、アンカーケーブル
の地中端側の定着度を確認するものである。
[Problem to be Solved by the Invention] Incidentally, in the construction of a ground anchor, a tension confirmation test of the anchor cable is performed before tension fixation of the anchor cable. In this confirmation test, the tension load on the anchor cable is gradually increased by pulling and loosening the anchor cable, and the degree of anchorage of the underground end of the anchor cable is confirmed.

具体的には、アースアンカーの設計荷重を100%とし
たとき、まず最初に、初期荷重として設計荷重の10%
の荷重でアンカーケーブル3を引張する。
Specifically, when the design load of the earth anchor is 100%, first, 10% of the design load is set as the initial load.
The anchor cable 3 is pulled with a load of .

それから、次に所定時間毎に段階的に荷重を増やしなが
ら引張したり、緩めたりする。すなわち、第1段階は、
50%の荷重を加え、その状態を数分間保った後、荷重
を下げて再び10%まで緩める。
Then, at predetermined time intervals, the load is increased step by step while tensioning or loosening is performed. That is, the first stage is
After applying a 50% load and maintaining this state for several minutes, the load is lowered to 10% again.

次の段階では70%まで荷重を高めて数分後10−まで
緩める。次は、100Sまで荷重を高めて数分後lO%
まで緩める。このようにアンカーケーブル3の緊張・緩
和を繰り返し、最後は120%の荷重をかけた後、70
’vi前後の荷重まで下げ、これにより実際の定着を行
なう。
In the next step, the load is increased to 70%, and after a few minutes it is relaxed to 10-. Next, increase the load to 100S and after a few minutes lO%
Loosen until In this way, the anchor cable 3 is repeatedly tensed and relaxed, and finally, after applying a load of 120%,
The load is lowered to around 'vi' and actual fixing is performed.

そこで、上記のような複数の耐荷体にアンカーケーブル
をそれぞれ係合させた圧縮型の地盤アンカー構造の場合
、前述の如く、アンカーケーブルにおける各耐荷体への
係合部からジャ、牛までの長さ全体が自由長として働く
わけであるか、この自由長部は、各耐荷体に係合されて
いるアンカーケーブルごとに異なっているから、アンカ
ーケーブルの緊張時の伸び、および緊張力もそれぞれ異
なってくる。したがって、上記のような確認試験を行う
際にも、各アンカーケーブルおよび耐荷体に対して正確
な荷重を与えるには、各耐荷体に固定されているアンカ
ーケーブルごとに緊張管理を行っていかなければならな
い等、きわめて繁雑で、かつ時間がかかるという問題か
ある。
Therefore, in the case of a compression-type ground anchor structure in which anchor cables are engaged with multiple load-bearing bodies, as described above, the length of the anchor cable from the engagement part to each load-bearing body to the jar and cow is This free length is different for each anchor cable engaged with each load-bearing body, so the elongation and tension force of the anchor cable under tension are also different. come. Therefore, even when performing confirmation tests such as those mentioned above, in order to apply accurate loads to each anchor cable and load-bearing body, it is necessary to manage the tension of each anchor cable fixed to each load-bearing body. The problem is that it is extremely complicated and time-consuming.

この問題を解決するものとして、特公昭53−4326
号公報に示されるように、アンカーケーブル(PC鋼線
または鋼棒)にバネ機構を付帯した耐荷板を装着してア
ンカー管体を装着し、ハネ機構により全体の引抜き変位
を均等に分散させる技術かあるか、これによれば、上述
の確認試験を行った際に、緊張を繰り返すごとに耐荷体
に働く荷重を均一に保つことはてきない、このため、ア
ンカーケーブルにおける自由長部の長さを特定できない
から、確認試験に際しては正確な計測値を得ることか難
しいとともに、厳密な緊張管理を行うことかできないの
が現状である。
As a solution to this problem, the Special Publication No. 53-4326
As shown in the publication, a technology in which a load-bearing plate with a spring mechanism is attached to an anchor cable (PC steel wire or steel bar) and an anchor pipe body is attached, and the overall pulling displacement is evenly distributed by a spring mechanism. According to this, when carrying out the above-mentioned confirmation test, it was not possible to keep the load acting on the load-bearing body uniform each time the tension was repeated, and for this reason, the length of the free length of the anchor cable Because it is not possible to specify the actual strain, it is difficult to obtain accurate measurement values during confirmation tests, and it is currently impossible to strictly control tension.

本発明は、上述した事情に鑑みてなされたものであり、
前記のように複数の耐荷体に固定したアンカーケーブル
の緊張力と、耐荷体に対する荷重を均一にでき、なおか
つ確認試験の際にもその状態が保持できて確実な緊張管
理が行える地盤アンカー工法を提供することを目的とし
ている。
The present invention was made in view of the above-mentioned circumstances, and
As mentioned above, we developed a ground anchor construction method that can equalize the tension of anchor cables fixed to multiple load-bearing bodies and the load on the load-bearing bodies, and that can maintain this state even during confirmation tests, allowing reliable tension management. is intended to provide.

[問題点を解決するための手段] 本発明は、上記目的を達成するためになされたものてあ
って、アンカー孔内に挿入するff1l<本のアンカー
ケーブルをソース管によって被覆するとともに、このシ
ース管に、先端から前記アンカーケーブルの緊張方向に
一定間隔をおいて複数の耐荷体を装着し、前記複数本の
アンカーケーブルを、前記耐荷体と同数のアンカーケー
ブル群に分け、これらアンカーケーブル群のうちの1組
を最も地中端側に装着された耐荷体に直接係合するとと
もに、他のアンカーケーブル群を、全ての組のアンカー
ケーブル群の緊張力が均一になる如く弾性変形量がそれ
ぞれ設定された弾性体を介して他の前記各耐荷体に1組
ずつ係合し、次いで、各アンカーケーブル群をまとめて
緊張することを特徴としている。
[Means for Solving the Problems] The present invention has been made to achieve the above object, and includes covering the anchor cables inserted into the anchor hole with a source tube, and covering the anchor cables with a source tube. A plurality of load-bearing bodies are attached to the pipe at regular intervals in the direction of tension of the anchor cable from the tip, and the plurality of anchor cables are divided into anchor cable groups of the same number as the load-bearing bodies, and each of these anchor cable groups is One set of the anchor cables is directly engaged with the load-bearing body installed on the underground end side, and the other anchor cable groups are each elastically deformed so that the tension of all the anchor cable groups is uniform. The anchor cables are characterized in that one pair of anchor cables is engaged with each of the other load-bearing bodies via a set elastic body, and then each anchor cable group is tensioned together.

[作用] 本発明によれば、最も地中端側の耐荷体を除く他の耐荷
体に係合された各アンカーケーブル群におけるアンカー
ケーブルの伸びおよび緊張力は、各弾性体の作用により
それぞれ補償され、最も地中端側の耐荷体に直接係合さ
れたアンカーケーブルの伸びおよび緊張力と一致する。
[Function] According to the present invention, the elongation and tension of the anchor cables in each anchor cable group engaged with other load-bearing bodies except for the load-bearing body closest to the underground end are compensated for by the action of each elastic body. This corresponds to the elongation and tension of the anchor cable directly engaged with the load-bearing body closest to the underground end.

したかつて、全ての各アンカーケーブル群のアンカーケ
ーブルの伸ひおよび緊張力は均一になり、各耐荷体に発
生する荷重も均一となって良好なアンカー構造か得られ
る。また、定着前の確認試験を行う際には、アンカーケ
ーブルの自由長を最も地中端側の耐荷体からの距離とし
て特定できるため、きわめて正確な計測値を得ることが
できて厳密な緊張管理を行うことができる。
Once this is done, the extension and tension of the anchor cables in all the anchor cable groups will be uniform, and the loads generated on each load-bearing body will also be uniform, resulting in a good anchor structure. In addition, when performing confirmation tests before anchorage, the free length of the anchor cable can be determined as the distance from the load-bearing body closest to the underground end, allowing extremely accurate measurement values to be obtained and strict tension control. It can be performed.

[実施例] 以下、図面を参照して本発明の一実施例を説明する。[Example] Hereinafter, one embodiment of the present invention will be described with reference to the drawings.

第1図は、本実施例方法によって得られたアンカー構造
を示しており、符号Gは土留めを施す対象地盤、1が対
象地盤Gの表面に設けた土留め壁、2は対象地盤Gに掘
削されたアンカー孔、3はアンカー孔2にその孔底まで
挿入されたアンカーケーブルであり、これらアンカーケ
ーブル3・・の地表側の端部を、土留め壁1に当接させ
た台座4およびアンカーへノド5に通して図示せぬジヤ
ツキにて緊張し、その状態をアンカーケーブル3の突出
端外周に装着したくさひ6をアンカーへ、ト5に係合さ
せることにより定着されている。アンカーへノド5から
突出するアンカーケーブル3 の端部は、台座4に固定
されたオイルキャップ7によって覆われている。
Fig. 1 shows the anchor structure obtained by the method of this example, where G is the target ground to which earth retaining is applied, 1 is the earth retaining wall provided on the surface of the target ground G, and 2 is the earth retaining wall installed on the target ground G. Anchor cables 3 are inserted into the drilled anchor hole 2 to the bottom of the hole, and the ends of these anchor cables 3 on the ground side are placed on a pedestal 4 and a pedestal 4 in contact with the earth retaining wall 1. The cable is passed through the throat 5 to the anchor and tensioned with a jack (not shown), and this state is fixed by engaging the wedge 6 attached to the outer periphery of the protruding end of the anchor cable 3 with the jaw 5 of the anchor. The end of the anchor cable 3 protruding from the throat 5 to the anchor is covered by an oil cap 7 fixed to the base 4.

前記アンカーケーブル3は、PC鋼より線からなるアン
ホントPCストランドであり、表面には、ポリエチレン
チューブか被覆されて防錆処理かなされている。このア
ンカーケーブル3は、本実施例の場合12本用いられて
いる。
The anchor cable 3 is a true PC strand made of stranded PC steel, and its surface is coated with a polyethylene tube and subjected to anti-rust treatment. Twelve anchor cables 3 are used in this embodiment.

これらアンカーケーブル3・は、7−ス管8とこのソー
ス管8の途中に装着された複数の耐荷体9よりなる管体
10に挿入されることにより、この管体10によってそ
の全長か被覆されている。
These anchor cables 3 are inserted into a tube body 10 consisting of a source tube 8 and a plurality of load-bearing bodies 9 installed in the middle of the source tube 8, so that their entire length is covered by this tube body 10. ing.

前記耐荷体9は、地中側の先端からアンカーケーブル3
 の緊張方向に一定間隔をおいて、本実施例の場合4つ
装着されている。説明上これら耐荷体9を、先端側から
順に第1の耐荷体9A、第2の耐荷体9B、第3の耐荷
体9C1第4の耐荷体9Dとする。
The load-bearing body 9 is connected to the anchor cable 3 from the tip on the underground side.
In this embodiment, four are installed at regular intervals in the direction of tension. For the purpose of explanation, these load-bearing bodies 9 are referred to as a first load-bearing body 9A, a second load-bearing body 9B, a third load-bearing body 9C1, and a fourth load-bearing body 9D, in order from the tip side.

これら耐荷体9(9A、9B、9C19D)は、タフタ
イル鋳鉄製で表面に亜鉛メツキ処理か施されたものであ
って、第2図、第5図および第6図等に示すように、外
周面にンース管8よりも大径の環状の突条9aが軸方向
に間隔をおいて多数形成され、両端部の内径がシース管
8の外径と路間−に形成された円筒状をなしており、そ
の両端部に7−ス管8が嵌合されることにより、ンース
管8に装着されている。なお、地中端側の耐荷体9Aの
先端部には、開口を閉塞するパイロットキャップ11が
嵌められている。
These load-bearing bodies 9 (9A, 9B, 9C19D) are made of tufftile cast iron and have a galvanized surface, and as shown in FIGS. 2, 5, and 6, the outer peripheral surface A large number of annular protrusions 9a having a diameter larger than that of the sheath tube 8 are formed at intervals in the axial direction, and the inner diameter of both ends forms a cylindrical shape between the outer diameter of the sheath tube 8 and the path. It is attached to the first tube 8 by fitting the second tube 8 to both ends thereof. Note that a pilot cap 11 that closes the opening is fitted to the tip of the load-bearing body 9A on the underground end side.

耐荷体9の内部には、第2図〜第4図に示すように、ア
ンカーケーブル3を係合させるための係合部12が一体
に設けられ、この係合部12には、アンカーケーブル3
を挿通させると同時にその端部を係合させるための第1
の挿通孔】3と、単にアンカーケーブル3を挿通させる
第2の挿通孔14が耐荷体9の軸方向に沿って貫通形成
されている。
As shown in FIGS. 2 to 4, an engaging portion 12 for engaging the anchor cable 3 is integrally provided inside the load-bearing body 9.
The first
3 and a second insertion hole 14 through which the anchor cable 3 is simply inserted are formed through the load-bearing body 9 along the axial direction.

第1の挿通孔13は、係合部9の外岡部において周方向
を等分する3カ所に形成されている。この第1の挿通孔
13は、小径部+3aと地中端側の大径部13bとか連
続したもので、両者の間には、耐荷体9の軸方向に直交
する環状の係合面13cか形成されている。小径部13
aの内径はアンカーケーブル3の外径よりもやや大きく
、また大径部13bの内径は、アンカーケーブル3の端
部外周に固定された円筒状のコンブレノシコングリップ
15の外径よりもやや大きく設定されている。
The first insertion holes 13 are formed at three locations equally dividing the circumferential direction in the outer wall portion of the engaging portion 9 . This first insertion hole 13 is continuous with a small diameter part +3a and a large diameter part 13b on the underground end side, and there is an annular engagement surface 13c orthogonal to the axial direction of the load-bearing body 9 between them. It is formed. Small diameter part 13
The inner diameter of a is slightly larger than the outer diameter of the anchor cable 3, and the inner diameter of the large diameter portion 13b is slightly larger than the outer diameter of the cylindrical combination grip 15 fixed to the outer periphery of the end of the anchor cable 3. It is set.

第2の挿通孔14は、前記各第1の挿通孔13の間に、
断面クローバ状に形成されており、3つの先端部14a
、14b、14c内に、アンカーケーブル3が3本ずつ
挿通されるようになっている。
The second insertion hole 14 is located between each of the first insertion holes 13,
It is formed in a clover shape in cross section, and has three tip portions 14a.
, 14b, and 14c, three anchor cables 3 are inserted through each of them.

ところで、前記12本のアンカーケーブル3は、耐荷体
9と同数組、つまり3本ずつ4組に分けら−れている。
Incidentally, the 12 anchor cables 3 are divided into the same number of groups as the load-bearing bodies 9, that is, four groups each having three anchor cables.

これらアンカーケーブル3の各組を、第1のアンカーケ
ーブル群3A、第2のアンカーケーブル群3B、第3の
アンカーケーブルR3C。
Each set of these anchor cables 3 is a first anchor cable group 3A, a second anchor cable group 3B, and a third anchor cable R3C.

第4のアンカーケーブル群3Dとする。This is referred to as a fourth anchor cable group 3D.

そして、第2図および第6図〜第8図に示すように、第
1のアンカーケーブル群3Aは第1の耐荷体9Aに直接
係合され、第2のアンカーケーブル群3Bは第2の耐荷
体9Bに耐荷バネ16Bを介して係合され、第3のアン
カーケーブル群3Cは第3の耐荷体9Cに耐荷バネ16
Cを介して係合され、第4のアンカーケーブル群3Dは
第4の耐荷体9Dに耐荷バネ16Dを介して、それぞれ
係合されている。第9図はその状態を概略的に示してい
る。
As shown in FIGS. 2 and 6 to 8, the first anchor cable group 3A is directly engaged with the first load-bearing body 9A, and the second anchor cable group 3B is directly engaged with the second load-bearing body 9A. The third anchor cable group 3C is engaged with the body 9B via the load-bearing spring 16B, and the third anchor cable group 3C is engaged with the third load-bearing body 9C via the load-bearing spring 16.
The fourth anchor cable group 3D is engaged with the fourth load-bearing body 9D via the load-bearing spring 16D. FIG. 9 schematically shows the situation.

すなわち、第1のアンカーケーブル群3Aの各アンカー
ケーブル3は、第1の耐荷体9への第1の挿通孔13に
それぞれ通され、先端に固定されたコンブレノシコング
リップ15の一端面が第1の挿通孔13の係合面13c
に当接することにより第1の耐荷体9Aに係合されてい
る。そしてこれら第1のアンカーケーブル群3Aは、第
2の耐荷体3B、第3の耐荷体3Cおよび第4の耐荷体
3Dの各第2の挿通孔14における先端部14a内を通
され、前記アンカーへ、ト5に係合されている。
That is, each anchor cable 3 of the first anchor cable group 3A is passed through the first insertion hole 13 into the first load-bearing body 9, and one end surface of the combination grip 15 fixed to the tip is connected to the first insertion hole 13. Engagement surface 13c of insertion hole 13 of No. 1
By coming into contact with, it is engaged with the first load-bearing body 9A. These first anchor cable groups 3A are passed through the tip portions 14a of the second insertion holes 14 of the second load-bearing body 3B, the third load-bearing body 3C, and the fourth load-bearing body 3D, and 5 is engaged.

また、第2の耐荷体9Bの第1の挿通孔I3における大
径部13bには、円筒状の耐荷バネ16Bが係合面13
Cに当接する状態で挿入されており、第2のアンカーケ
ーブル群3Bの各アンカーケーブル3は、耐荷バネ16
Bおよび第1の挿通孔13にそれぞれ通され、コンプレ
、/ヨングリップ15の一端面が耐荷バネ16Bの一端
面に当接することにより、第2の耐荷体9Bに係合され
ている。これら第2のアンカーケーブル群3Bは、第3
の耐荷体3Cおよび第4の耐荷体3Dの各第2の挿通孔
14における各先端部14b内を通され、アンカーへノ
ド5に係合されている。
Further, a cylindrical load-bearing spring 16B is attached to the engagement surface 13 at the large diameter portion 13b of the first insertion hole I3 of the second load-bearing body 9B.
C, each anchor cable 3 of the second anchor cable group 3B is inserted in a state where it is in contact with the load-bearing spring 16.
B and the first insertion hole 13 respectively, and one end surface of the compressor/yong grip 15 abuts one end surface of the load-bearing spring 16B, thereby being engaged with the second load-bearing body 9B. These second anchor cable groups 3B
The load-bearing body 3C and the fourth load-bearing body 3D are passed through the tip portions 14b of the second insertion holes 14, and are engaged with the throats 5 of the anchors.

また、第3の耐荷体9Cの第1の挿通孔13における大
径部13bには、円筒状の耐荷バネI6Cが係合面13
Cに当接する状態で挿入されており、第3のアンカーケ
ーブル群3Cの各アンカーケーブル3は、耐荷バネ16
Cおよび第1の挿通孔13にそれぞれ通され、コンプレ
、ンヨングリ、ブ15の一端面が耐荷バネ16Cの一端
面に当接することにより、第3の耐荷体9Cに係合され
ている。これら第3のアンカーケーブル群3Cは、第4
の耐荷体3Dの各第2の挿通孔)4における各先端部1
4C内を通され、アンカーヘット5に係合されている。
Further, a cylindrical load-bearing spring I6C is attached to the engagement surface 13 in the large diameter portion 13b of the first insertion hole 13 of the third load-bearing body 9C.
C, and each anchor cable 3 of the third anchor cable group 3C is inserted into the load-bearing spring 16
C and the first insertion hole 13, and one end surface of the spring 15 is engaged with the third load-bearing body 9C by abutting one end surface of the load-bearing spring 16C. These third anchor cable groups 3C
Each tip part 1 in each second insertion hole) 4 of the load-bearing body 3D
4C and is engaged with the anchor head 5.

さらに、第4の耐荷体9Dの第1の挿通孔13における
大径部13bには、円筒状の耐荷ノ・不16Dが係合面
13cに当接する状態で挿入されており、第4のアンカ
ーケーブル群3Dの各アンカーケーブル3は、耐荷バネ
+6Dおよび第1の挿通孔13にそれぞれ通され、コン
ブレノンコングリノブ15の一端面が耐荷バネ+6Dの
一端面に当接することにより、第4の耐荷体9Dに係合
されている。これら第4のアンカーケーブル群3Dのア
ンカーケーブル3は、第4の耐荷体3Dの第1の挿通孔
13を通された後アンカーヘッド5に係合されている。
Further, a cylindrical load-bearing hole 16D is inserted into the large diameter portion 13b of the first insertion hole 13 of the fourth load-bearing body 9D in a state in contact with the engagement surface 13c, and the fourth anchor Each anchor cable 3 of the cable group 3D is passed through the load-bearing spring +6D and the first insertion hole 13, and when one end surface of the combination knob 15 comes into contact with the one end surface of the load-bearing spring +6D, the fourth It is engaged with the load bearing body 9D. The anchor cables 3 of the fourth anchor cable group 3D are engaged with the anchor head 5 after passing through the first insertion hole 13 of the fourth load-bearing body 3D.

第2の耐荷体9B、第2の耐荷体9Cおよび第3の耐荷
体9Dの各第1の挿通孔13の大径部13bに挿入され
た各ml荷ハネ16B、16c、16Dは、前述の如く
円筒状をなしその内部にアンカーケーブル3か通される
。これら各耐荷バネ16B、16C,16Dは、いずれ
も発泡N B Rコムで成形された弾性体であり、アン
カーケーブル3か緊張されると、アンカーケーブル3の
端部に固定されている各コンブレノノヨングリノブ15
によって押圧されることにより、弾性変形して軸方向に
収縮し、またその緊張力か解かれると、元の状態に復帰
する。
The ml load springs 16B, 16c, and 16D inserted into the large diameter portions 13b of the first insertion holes 13 of the second load-bearing body 9B, the second load-bearing body 9C, and the third load-bearing body 9D are the same as those described above. It has a cylindrical shape, and the anchor cable 3 is passed through it. Each of these load-bearing springs 16B, 16C, and 16D is an elastic body made of foamed NBR comb, and when the anchor cable 3 is tensioned, each of the combination springs fixed to the end of the anchor cable 3 Yonglinob 15
When pressed, it elastically deforms and contracts in the axial direction, and when the tension is released, it returns to its original state.

ところで、アンカーケーブル3・・における各アンカー
ケーブル群3A、3B、3C,3Dは、各耐荷体9A、
9B、9C19Dにその端部か係合されることにより、
緊張するンヤノキまでの長さすなわち自由長部の長さが
異なっている。したがって、各アンカーケーブル群3A
、3B、3C13Dを、耐荷バネ16B、16C116
Dを介在させない状態でまとめて1つのジ十ツキにより
緊張すると、アンカーケーブル3は単位長さ当たりの伸
び(伸び率)か一定であるから、その呻ひ、および緊張
力は各アンカーケーブル群3A、3B、3C13Dごと
に異なる。つまり、アンカーケーブル3の伸びはその長
さに比例し、緊張力は反比例する。
By the way, each anchor cable group 3A, 3B, 3C, 3D in the anchor cable 3... is connected to each load-bearing body 9A,
By engaging the ends of 9B and 9C19D,
The length up to the tension, that is, the length of the free length, is different. Therefore, each anchor cable group 3A
, 3B, 3C13D, load-bearing spring 16B, 16C116
When the anchor cables 3 are tensed by one tension without intervening D, the elongation (elongation rate) per unit length of the anchor cables 3 is constant. , 3B, 3C13D. That is, the elongation of the anchor cable 3 is proportional to its length, and the tension force is inversely proportional to its length.

そこで、アンカーケーブル群3B、3C,3Dにおける
アンカーケーブル3の伸ひと緊張力とが、アンカーケー
ブル群3Aにおけるアンカーケーブル3に揃うよう前記
各耐荷バネ16B、1.6 C116Dの軸方向の長さ
を異ならせることにより、その収縮量(弾性変形量)に
変化をもたせである。
Therefore, the length in the axial direction of each of the load-bearing springs 16B, 1.6 C116D is adjusted so that the tension and tension of the anchor cables 3 in the anchor cable groups 3B, 3C, and 3D are equal to those of the anchor cables 3 in the anchor cable group 3A. By making the difference, the amount of contraction (elastic deformation amount) can be changed.

たとえば、第1のアンカーケーブル群3Aのアンカーケ
ーブル3が、外径;12.7mm、長さ(自由長部);
30m、破断限、 18.7tf、降伏限: 15.7
tfの場合、14.3tfの荷重で緊張すると、伸びは
2+7+nm(理論値)とわかっており、よって、各耐
荷体9A、9B、9C19Dの相互の間隔(厳密に言う
と各コンプレッションリング15の地表側の端面間)が
1mであると、第2、第3、第4の各アンカーケーブル
群3B、3C,3Dの各アンカーケーブル3の伸びは、
それぞれ第1のアンカーケーブル群3Aのアンカーケー
ブル3に対して、それぞれ1/30(7,2mm)、2
/30(14,4mm)、3/30(21,8mm)ず
つ減少した値を示す。
For example, the anchor cable 3 of the first anchor cable group 3A has an outer diameter of 12.7 mm and a length (free length portion);
30m, breaking limit: 18.7tf, yield limit: 15.7
In the case of tf, when tensioned with a load of 14.3tf, the elongation is known to be 2+7+nm (theoretical value). When the length (between the front end faces) is 1 m, the elongation of each anchor cable 3 of the second, third, and fourth anchor cable groups 3B, 3C, and 3D is as follows:
1/30 (7.2 mm) and 2 mm, respectively, for the anchor cables 3 of the first anchor cable group 3A.
/30 (14.4 mm) and 3/30 (21.8 mm) are shown.

したかって、上記のアンカーケーブル3の条件て、各耐
荷体9A、9B、9C19Dの相互間隔か1mである場
合、第2の耐荷体9Bに設けた耐荷バネ16Bをその収
縮量か7.2mmに設定されたものとし、第3の耐荷体
9Cに設けた耐荷バネ16Cをその収縮量か14.4m
mに設定されたものとし、第4の耐荷体9Dに設けた耐
荷ハネ1.6 Dをその収縮量か21.6mmに設定さ
れたものとする。
Therefore, under the conditions of the anchor cable 3 described above, if the distance between the load bearing bodies 9A, 9B, 9C19D is 1 m, the contraction amount of the load bearing spring 16B provided on the second load bearing body 9B is 7.2 mm. It is assumed that the load-bearing spring 16C provided on the third load-bearing body 9C is contracted by 14.4 m.
It is assumed that the load-bearing spring 1.6D provided on the fourth load-bearing body 9D is set to a contraction amount of 21.6 mm.

これにより、各アンカーケーブル群3A、3B。As a result, each anchor cable group 3A, 3B.

3C,3Dをまとめて1つの/ヤノキにより緊張すると
、アンカーケーブル群3B、3C,3Dの各アンカーケ
ーブル3 ・の伸びは、各耐荷バネ16B、16C,+
6Dにそれぞれ補償され、いずれも第1のアンカーケー
ブル群3Aの伸ひに一致する。したがって、各アンカー
ケーブル群3A、3B、3C13Dの各アンカーケーブ
ル3・ に生じる緊張力は均一となり、この結果、各耐
荷体9A、9B、9C19Dからアンカー孔2内のグラ
ウト材に働く荷重も均一となって、良好なアンカー構造
か得られる。
When 3C and 3D are tensioned together by one rope, the elongation of each anchor cable 3 of anchor cable groups 3B, 3C, and 3D is equal to each load-bearing spring 16B, 16C, +
6D, and both correspond to the elongation of the first anchor cable group 3A. Therefore, the tension generated in each anchor cable 3 of each anchor cable group 3A, 3B, 3C13D becomes uniform, and as a result, the load acting on the grout material in the anchor hole 2 from each load-bearing body 9A, 9B, 9C19D is also uniform. As a result, a good anchor structure can be obtained.

なお、上記においては各耐荷体9A、9B、9C19D
相互の間隔を1mとした例を示したが、この間隔は任意
であり、それに応じて各耐荷バネ16B、16C116
Dの収縮量を異ならせる必要がある。
In addition, in the above, each load-bearing body 9A, 9B, 9C19D
Although an example is shown in which the mutual spacing is 1 m, this spacing is arbitrary, and each load-bearing spring 16B, 16C116
It is necessary to vary the amount of contraction of D.

たとえば、各耐荷体9A、9B、9C,9D相互の間隔
が1.5mである場合、上記の比率にもとつき、その収
縮量は、耐荷バネ16Bが1018mm、耐荷バネ16
Cが21.6mm、耐荷バネ16Dかが32.4mmに
設定されたものとする。
For example, when the distance between the load-bearing bodies 9A, 9B, 9C, and 9D is 1.5 m, based on the above ratio, the amount of contraction is 1018 mm for the load-bearing spring 16B, and 1018 mm for the load-bearing spring 16B.
It is assumed that C is set to 21.6 mm and load-bearing spring 16D is set to 32.4 mm.

また、[発明が解決しようとする課題]の項で述べたア
ンカーケーブル3を繰り返して緊張する確認試験を行う
際にも、各耐荷バネ16B、16C,16Dは、アンカ
ーケーブル3の緊張を解くと常に元の状態に戻るから、
アンカーケーブル3の長さ(自由長部)を各耐荷体9A
、9B、9C19Dからの長さと特定でき、したがって
、確認試験に際しては正確な計測値を得ることかできて
厳密な緊張管理を行うことかできる。
Furthermore, when conducting the confirmation test in which the anchor cable 3 is repeatedly tensioned as described in the [Problems to be Solved by the Invention] section, each load-bearing spring 16B, 16C, and 16D is Because it always returns to its original state,
The length (free length part) of anchor cable 3 is
, 9B, and 9C19D. Therefore, during confirmation tests, accurate measurement values can be obtained and strict tension management can be performed.

なお、以下に、上記工法を用いて行う確認試験方法の一
例を具体的に説明する。
In addition, below, an example of the confirmation test method performed using the said construction method is demonstrated concretely.

まず、この確認試験に用いる装置から説明する。First, the equipment used for this confirmation test will be explained.

第10図は、シャッターケートを備えたジャ。Figure 10 shows a jar equipped with a shutter cage.

牛17を施工置所にセットした状態を示している。A state in which the cow 17 is set at the construction site is shown.

5は前記アンカーヘッド、4は前記台座である。5 is the anchor head, and 4 is the pedestal.

ジヤツキ17は、筒状のジャッキ本体17a内部に、ア
ンカーケーブル3を緊張するための緊張シリンダ18と
、前記(さび6をアンカーへノド5に圧入するための押
し込みンリンダ20が、摺動自在に嵌装されたものであ
る。
The jack 17 includes a tension cylinder 18 for tensioning the anchor cable 3 and a push-in cylinder 20 for press-fitting the rust 6 into the throat 5 of the anchor, which are slidably fitted inside the cylindrical jack main body 17a. It is equipped.

緊張シリンダ18の上部開口にはプーリングへ2ド21
が嵌合されている。このプーリングへ。
At the upper opening of the tension cylinder 18, there is a 2 door 21 connected to the pooling ring.
are fitted. To this pooling.

ド21には、ケーブル挿通孔22が設けられ、この孔2
2の上部は、くさび状のグリッパ−23がはめ込まれる
グリッパ−孔24とされている。また、押し込み7リン
ダ20の先端には、ケーブル挿通孔25が設けられたイ
ンデックス阪26か設けられている。
The cable insertion hole 22 is provided in the card 21.
The upper part of 2 is a gripper hole 24 into which a wedge-shaped gripper 23 is fitted. Further, at the tip of the push-in cylinder 20, an index bell 26 in which a cable insertion hole 25 is provided is provided.

さらに、ジャッキ本体17a下部には、成文圧板である
筒状のラムチャー27が取り付けられている。このラム
チャー27は、第11図および第12図に示すように、
上縁にジヤツキ本体17aの下縁がはめ込まれる枠部2
8を有し、底部には、アンカーヘッド5が挿入される挿
入口29か形成されたものである。この内周面には、ア
ンカーヘッド5を押さえるための係止板30が突設され
ている。
Furthermore, a cylindrical ram char 27, which is a pressure plate, is attached to the lower part of the jack body 17a. As shown in FIGS. 11 and 12, this ramchar 27 is
Frame portion 2 into which the lower edge of the jack body 17a is fitted into the upper edge
8, and an insertion opening 29 into which the anchor head 5 is inserted is formed at the bottom. A locking plate 30 for holding down the anchor head 5 is protruded from the inner peripheral surface.

第10図において符号31で示すものは、前記シャッタ
ーゲートである。このシャッターゲート31は、第13
図および第14図に示すように、長尺な板状をなし、板
端部より縦方向に複数本、この場合4本の溝32が形成
されているものである。この溝32は、アンカーヘッド
5のケーブル挿通孔5aに対応して設けられており、シ
ャッターゲート31をアンカーへノド5に合わせて配置
した際、同一列に並ぶケーブル挿通孔5aがちようど1
本の溝32上に位置するようになっている。
What is indicated by the reference numeral 31 in FIG. 10 is the shutter gate. This shutter gate 31 is the thirteenth
As shown in the figure and FIG. 14, it has a long plate shape, and has a plurality of grooves 32 (four grooves in this case) formed in the longitudinal direction from the edge of the plate. This groove 32 is provided to correspond to the cable insertion hole 5a of the anchor head 5, and when the shutter gate 31 is placed on the anchor in alignment with the throat 5, the cable insertion holes 5a aligned in the same row are not aligned.
It is positioned above the groove 32 of the book.

また、溝幅は、アンカーケーブル3の径より若干大きく
、かつ、くさび6の先端の径より小さく形成され、アン
カーケーブル3は通過てきるものの、くさび6は通過て
きないようにされている。そして、このシャ、ターゲー
ト31か挿入された際、アンカーケーブル3の通る部分
かアンカーケーブル3の貫通部33とされ、この貫通部
33の周辺のシャッターゲート31の上面には、くさび
6が嵌まる嵌合凹部34か形成されている。
Further, the groove width is formed to be slightly larger than the diameter of the anchor cable 3 and smaller than the diameter of the tip of the wedge 6, so that the anchor cable 3 can pass through, but the wedge 6 cannot pass through. When the shutter gate 31 is inserted, the portion through which the anchor cable 3 passes is defined as the penetration portion 33 of the anchor cable 3, and the wedge 6 is fitted into the upper surface of the shutter gate 31 around the penetration portion 33. A fitting recess 34 is formed.

また、シャッターゲート31の他端には、ハンドル部3
5が形成されており、この部分をつかんでアンカーケー
ブル3に対してシャッターゲート31を抜き差しするこ
とにより、シャッターゲート31は、アンカーへノド5
の上面に取り外し自在に配置されるようになっている。
Further, a handle portion 3 is provided at the other end of the shutter gate 31.
5 is formed, and by grasping this part and inserting/removing the shutter gate 31 from/to the anchor cable 3, the shutter gate 31 connects to the anchor at the throat 5.
It is designed to be removably placed on the top surface of the .

なお、ラムチャー27の周壁には、第12図に示すよう
に、シャッターゲート31を挿入するためのゲート挿入
孔36が形成されている。
Note that, as shown in FIG. 12, a gate insertion hole 36 for inserting the shutter gate 31 is formed in the peripheral wall of the ram char 27.

次に、このように構成されたジヤツキ17の作用ととも
に、前述した確認試験方法を操作手順に従って説明する
Next, the operation of the jack 17 configured as described above and the confirmation test method described above will be explained according to the operating procedure.

まず、第10図に示すように、/ヤノ牛17を、地盤外
部に突出したアンカーケーブル3の端部に装着する。こ
の装着の仕方は、まず、アンカーケーブル3をアンカー
プレート土留め壁1のケーブル挿通孔1aに通し、アン
カーヘッド5のケーブル挿通孔5aから出す。
First, as shown in FIG. 10, the /yanogyu 17 is attached to the end of the anchor cable 3 that protrudes outside the ground. To do this, first, the anchor cable 3 is passed through the cable insertion hole 1a of the anchor plate retaining wall 1, and then taken out from the cable insertion hole 5a of the anchor head 5.

次に、くさび6を、先端かアンカーへノド5側に向くよ
うにしてアンカーケーブル3の端から通し、アンカーへ
ノド5近くてスプリング(図示時)を巻くことによりア
ンカーケーブル3に装着する。
Next, the wedge 6 is passed from the end of the anchor cable 3 into the anchor with the tip facing toward the throat 5, and is attached to the anchor cable 3 by winding a spring (as shown) near the throat 5 to the anchor.

それからアンカーケーブル3をインデックス板26のケ
ーブル挿通孔25に通し、緊張シリンダ18内部から、
プーリングヘッド21のケーブル挿通孔22を通して外
部に出す。そして、グリッパ−23を、プーリングヘッ
ド21のグリッパ−孔24に嵌入することにより、ジセ
ソキ17をアンカーケーブル3に固定する。
Then, pass the anchor cable 3 through the cable insertion hole 25 of the index plate 26, and from inside the tension cylinder 18,
The cable is passed through the cable insertion hole 22 of the pooling head 21 to the outside. Then, by fitting the gripper 23 into the gripper hole 24 of the pooling head 21, the gripper 17 is fixed to the anchor cable 3.

次いで、引張試験方法の操作手順を説明する。Next, the operating procedure of the tensile test method will be explained.

まず、/ヤ、ターケート31を、ラムチャー27のゲー
ト挿入孔36より挿入し、アンカーへ。
First, insert the target 31 through the gate insertion hole 36 of the ram chart 27 and attach it to the anchor.

ト5とくさび60間に位置させる。このとき、アンカー
ケーブル3はノセノターケート31の溝32に入る。こ
の状態で、先に説明した引張試験の升イクルて緊張/リ
ンク18を作動することによりアンカーケーブル3の緊
張・緩和を行なう。
5 and wedge 60. At this time, the anchor cable 3 enters the groove 32 of the nosenotarcate 31. In this state, the tension/relaxation of the anchor cable 3 is performed by operating the tension/link 18 every cycle of the tensile test described above.

このときのくさび6およびンヤノターケート31の動作
ならひに作用を説明する。まず、アンカーケーブル3を
緊張すると、くさひ6はアンカーケーブル3の伸ひに伴
って移動する。しかし、/ヤ、ターケート31とインテ
ックス板26間の距離か1回の引張りにおけるアンカー
ケーブル3の伸びより短く設定されているので、くさひ
6はある程度アンカーケーブル3とともに動くか、イン
デックス板26に当たって停止する。さらに、続けてア
ンカーケーブル3を緊張すると、アンカーケーブル3は
伸びるものの、くさび6はインデックス板26の手前に
留められる。
The operation of the wedge 6 and the turret 31 at this time will be explained. First, when the anchor cable 3 is tensioned, the wedge 6 moves as the anchor cable 3 is stretched. However, since the distance between the target plate 31 and the Intex plate 26 is set shorter than the extension of the anchor cable 3 in one pull, the wedge 6 either moves with the anchor cable 3 to some extent or stops when it hits the index plate 26. do. When the anchor cable 3 is further tightened, the anchor cable 3 stretches, but the wedge 6 remains in front of the index plate 26.

こうして所定の荷重を保持してアンカーケーブル3を引
張した後、荷重を下げる。そうすると、くさひ6は、ア
ンカーケーブル3か縮むのに伴ってアンカーへノド5側
に移動するか、その先端か、/キノターゲート31の貫
通部33に形成された凹部34にはまり、それ以上動か
なくなる。
After the anchor cable 3 is pulled while maintaining a predetermined load in this manner, the load is lowered. Then, as the anchor cable 3 shrinks, the wedge 6 moves toward the anchor throat 5, or its tip fits into the recess 34 formed in the penetration part 33 of the target gate 31, and it does not move any further. .

くさび6は、アンカーケーブル3の緊張・緩和の際には
以上のように動き、ンヤ、ターケート31によってアン
カーヘッド5の(さび孔5bには嵌入しない。すなわち
、試験中にはアンカーケーブル3は定着されることがな
い。
The wedge 6 moves as described above when tensioning and relaxing the anchor cable 3, and the wedge 6 does not fit into the wedge hole 5b of the anchor head 5 due to the turret 31. In other words, the anchor cable 3 is not fixed during the test. never be done.

このように、確認試験の際には、アンカーヘッド5の上
にシャッターゲート31が配置されていることにより、
くさび6はアンカーへノド5のくさび孔5bに嵌入され
ることなく、続けて緊張・緩和を行なうことができる。
In this way, during the confirmation test, by placing the shutter gate 31 on the anchor head 5,
The wedge 6 can be tensioned and relaxed continuously without being inserted into the wedge hole 5b of the throat 5 of the anchor.

なお、試験終了後、実際の定着を行なうには、試験にお
ける最後の緊張を行なった後、ラムチャー27のゲート
挿入孔36よりンヤ・ツタ−ゲート31を抜き取り、ア
ンカーケーブル3の緊張荷重を所定の定着荷重に戻し、
くさひ6を押し込みンリンク20によって、アンカーヘ
ット5のくさひ孔5bに圧入する。
In addition, in order to carry out actual anchoring after the test, after performing the final tension in the test, pull out the anchor gate 31 from the gate insertion hole 36 of the ram char 27, and apply the tension load of the anchor cable 3 to a predetermined value. Return to fixed load,
The wedge 6 is press-fitted into the wedge hole 5b of the anchor head 5 by the push-in link 20.

このような確認試験方法によれば、アンカーケーブル3
の緊張を緩和させたとき、くさひ6かンヤ、ターケート
31によってアンカーヘッド5のくさひ孔5bに嵌入ヒ
ないから、アンカーケーブル3にくさび6を装着したま
まの状態でアンカーケーブル3の緊張を行なえ、また、
試験終了後、アンカーケーブル3を実際に定着するとき
には、シャ、ターケート31を外し、くさび6をアンカ
ーへ、ト5のくさび孔5bに嵌入させればよい。
According to this confirmation test method, anchor cable 3
When the tension of the anchor cable 3 is relaxed, the tension of the anchor cable 3 is reduced with the wedge 6 still attached to the anchor cable 3, since the wedge 6 does not fit into the wedge hole 5b of the anchor head 5 due to the turret 31. Go on, again
After the test, when actually fixing the anchor cable 3, it is sufficient to remove the shaft and the turret 31, and insert the wedge 6 into the anchor into the wedge hole 5b of the anchor 5.

したかって、確認試験から実際の定着を行なうまで、−
貫して連続的に作業を行なうことかでき、地盤アンカー
施工の大幅な作業能率向上を図ることができる。そして
、上述の本実施例の地盤アンカー工法と組み合わせて行
うことにより、確認試験に際しては正確な計測値を得る
ことができ、かつ厳密な緊張管理を行うことができる。
However, from the confirmation test to the actual establishment, -
The work can be carried out continuously throughout the area, greatly improving the work efficiency of ground anchor construction. By performing this in combination with the ground anchor method of the present embodiment described above, accurate measurement values can be obtained during the confirmation test, and strict tension management can be performed.

[発明の効果] 以上説明したように、本発明の地盤アンカー工法によれ
ば、アンカー孔内に挿入する複数本のアンカーケーブル
を7−ス管によって波層するとともに、このシース管に
、先端から前記アンカーケーブルの緊張方向に一定間隔
をおいて複数の耐荷体を装着し、前記複数本のアンカー
ケーブルを、前記耐荷体と同数のアンカーケーブル群に
分け、これらアンカーケーブル群のうちの1組を最も地
中端側に装着された耐荷体に直接係合するとともに、他
のアンカーケーブル群を、全ての組のアンカーケーブル
群の緊張力が均一になる如く弾性変形量がそれぞれ設定
された弾性体を介して他の前記各耐荷体に1組ずつ係合
し、次いで、各アンカーケーブル群をまとめて緊張する
ことを特徴とすることから、各弾性体の作用により、複
数の耐荷体に係合した各アンカーケーブル群のアンカー
ケーブルの伸びおよび緊張力が均一になり、この結果、
耐荷体から発生する荷重も均一になって優れた地盤アン
カー構造を得ることができるとともに、アンカーケーブ
ルの緊張・緩和を繰り返す定着前の確認試験に際しても
、アンカーケーブルの伸びおよび緊張力を理論値に近似
させることかでき、確実な緊張管理か行えるといった効
果を奏する。
[Effects of the Invention] As explained above, according to the ground anchor construction method of the present invention, a plurality of anchor cables to be inserted into an anchor hole are wave layered by a 7-sheath pipe, and a wave layer is applied to the sheath pipe from the tip. A plurality of load bearing bodies are installed at regular intervals in the tension direction of the anchor cable, the plurality of anchor cables are divided into anchor cable groups of the same number as the load bearing bodies, and one set of these anchor cable groups is attached. An elastic body that directly engages with the load-bearing body installed closest to the underground end, and that also connects other anchor cable groups, with the amount of elastic deformation set so that the tension of all anchor cable groups is uniform. The method is characterized in that one pair of anchor cables is engaged with each of the other load-bearing bodies via the anchor cables, and then each group of anchor cables is tensed together, so that the anchor cables are engaged with a plurality of load-bearing bodies by the action of each elastic body. The elongation and tension of the anchor cables in each anchor cable group are uniform, and as a result,
The load generated from the load-bearing body becomes uniform, making it possible to obtain an excellent ground anchor structure.In addition, the elongation and tension of the anchor cable can be adjusted to theoretical values even during confirmation tests before anchorage, in which the anchor cable is repeatedly tensed and relaxed. It can be approximated and has the effect of ensuring reliable tension management.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図は本発明の一実施例によって施工された状態の地
盤アンカー構造の一部断面側面図、第2図は第1の耐荷
体の一部断面側面図、第3図は第2図のm−■線矢視図
、第4図は第2図の■−■線矢視図、第5図は第2図の
■−v線矢視図、第6図は第2の耐荷体の一部断面側面
図、第7図は第3の耐荷体の一部断面側面図、第8図は
第4の耐荷体の一部断面側面図、第9図はアンカー構造
の概略図、第10図〜第14図は確認試験を説明するた
めの図であって、第10図はジャ、キにてアンカーケー
ブルを施工箇所に定着している状態の側断面図、第11
図はラムチャーの平面図、第12図はラムチャーの左半
分を断面とした側面図、第13図はシャッターケートの
平面図、第14図は第13図におけるZ−Z線矢視図で
ある。 2・−アンカー孔、3 ・・・・アンカーケーブル、8
 ・・ンース管、9(9A、9B、9C19D)・・耐
荷体、16B、16C,16D ・・耐荷バネ(弾性体
)、G・・ 地盤。 第6図
FIG. 1 is a partially sectional side view of a ground anchor structure constructed according to an embodiment of the present invention, FIG. 2 is a partially sectional side view of the first load-bearing body, and FIG. Fig. 4 is a view taken along the ■-■ line in Fig. 2, Fig. 5 is a view taken along the -v line in Fig. 2, and Fig. 6 is a view taken along the line ■-v in Fig. 2. 7 is a partially sectional side view of the third load bearing body; FIG. 8 is a partially sectional side view of the fourth load bearing body; FIG. 9 is a schematic diagram of the anchor structure; Figures 1 to 14 are diagrams for explaining the confirmation test.
The figure is a plan view of the ram char, FIG. 12 is a side view of the left half of the ram char in cross section, FIG. 13 is a plan view of the shutter cage, and FIG. 14 is a view taken along the Z-Z line in FIG. 13. 2.-Anchor hole, 3 ... Anchor cable, 8
...Nose pipe, 9 (9A, 9B, 9C19D)...Load-bearing body, 16B, 16C, 16D...Load-bearing spring (elastic body), G... Ground. Figure 6

Claims (1)

【特許請求の範囲】[Claims] アンカー孔内に挿入する複数本のアンカーケーブルをシ
ース管によって被覆するとともに、このシース管に、先
端から前記アンカーケーブルの緊張方向に一定間隔をお
いて複数の耐荷体を装着し、前記複数本のアンカーケー
ブルを、前記耐荷体と同数のアンカーケーブル群に分け
、これらアンカーケーブル群のうちの1組を最も地中端
側に装着された耐荷体に直接係合するとともに、他のア
ンカーケーブル群を、全ての組のアンカーケーブル群の
緊張力が均一になる如く弾性変形量がそれぞれ設定され
た弾性体を介して他の前記各耐荷体に1組ずつ係合し、
次いで、各アンカーケーブル群をまとめて緊張すること
を特徴とする地盤アンカー工法。
A plurality of anchor cables to be inserted into the anchor hole are covered with a sheath tube, and a plurality of load-bearing bodies are attached to the sheath tube at regular intervals from the tip in the tension direction of the anchor cable, and the plurality of load bearing bodies are The anchor cables are divided into the same number of anchor cable groups as the load-bearing bodies, and one set of these anchor cable groups is directly engaged with the load-bearing body installed closest to the underground end, and the other anchor cable groups are , one pair of anchor cables is engaged with each of the other load-bearing bodies via elastic bodies each having a set amount of elastic deformation so that the tension force of all the sets of anchor cable groups is uniform;
Next is the ground anchor construction method, which is characterized by tensioning each anchor cable group together.
JP17057790A 1990-06-28 1990-06-28 Ground anchor method Granted JPH0460014A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP17057790A JPH0460014A (en) 1990-06-28 1990-06-28 Ground anchor method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP17057790A JPH0460014A (en) 1990-06-28 1990-06-28 Ground anchor method

Publications (2)

Publication Number Publication Date
JPH0460014A true JPH0460014A (en) 1992-02-26
JPH0472009B2 JPH0472009B2 (en) 1992-11-17

Family

ID=15907418

Family Applications (1)

Application Number Title Priority Date Filing Date
JP17057790A Granted JPH0460014A (en) 1990-06-28 1990-06-28 Ground anchor method

Country Status (1)

Country Link
JP (1) JPH0460014A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100413550B1 (en) * 2000-11-28 2003-12-31 김지호 Removable anchor fixing equipment
JP2012132220A (en) * 2010-12-22 2012-07-12 Okabe Co Ltd Tip cap for ground anchor and ground anchor

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006225884A (en) * 2005-02-15 2006-08-31 In-Kwi Lee Anchoring device for anchor

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS641824A (en) * 1987-06-24 1989-01-06 Kurosawa Kensetsu Kk Earth-anchor construction
JPH0270821A (en) * 1988-07-26 1990-03-09 Sanwa Doshitsu Kiso Kk Anchor tension member

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS641824A (en) * 1987-06-24 1989-01-06 Kurosawa Kensetsu Kk Earth-anchor construction
JPH0270821A (en) * 1988-07-26 1990-03-09 Sanwa Doshitsu Kiso Kk Anchor tension member

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100413550B1 (en) * 2000-11-28 2003-12-31 김지호 Removable anchor fixing equipment
JP2012132220A (en) * 2010-12-22 2012-07-12 Okabe Co Ltd Tip cap for ground anchor and ground anchor

Also Published As

Publication number Publication date
JPH0472009B2 (en) 1992-11-17

Similar Documents

Publication Publication Date Title
DE69918444T2 (en) ground anchor
US6216403B1 (en) Method, member, and tendon for constructing an anchoring device
EP0606820B1 (en) Anchoring device for at least one tension member in a sleeve and installation method for the anchoring device
US5289626A (en) Foundation anchor and method for securing same to a foundation
US2371882A (en) Tensioning and anchoring of cables in concrete or similar structures
EP3284865A1 (en) Cable anchorage with seal element and prestressing system comprising such anchorage
CN212376149U (en) Connector for connecting unbonded prestressed steel strands in post-cast strip
US7360342B2 (en) Anchor wedge for post tension anchor system and anchor system made therewith
US3559275A (en) Method of forming an anchorage for prestress reinforced structural members
JPH07189427A (en) Anchorage construction of end of frp reinforcing material
JPH0460014A (en) Ground anchor method
KR20210106367A (en) Compression grip with threaded rod and tendon including same
KR102021602B1 (en) Apparatus for re-providing tension for steel strand of ground anchor
EP3907331A1 (en) Hybrid anchor
KR101861142B1 (en) Pullout Behavior Analysis for Frictional Combined Ground Anchor
JP2753202B2 (en) Anchor method
KR102118120B1 (en) Anchorage apparatus for retensioning and anchorage method using the same
DE19626828C2 (en) Method for creating a removable anchor with a compression body and one or more connected tension members
US4486991A (en) Tie-anchor for reinforcing cable
JPS6342220B2 (en)
DE1634273C3 (en) Grouting anchor
US3488903A (en) Positive clamping and anchoring means for elongated metal members
DE2932809A1 (en) End anchorage for tensioning element in prestressed concrete - has compressible clamping elements tightened on to cables
US3072988A (en) Wedge anchors for gripping prestressing tendons
JP6779551B1 (en) Crimping grip and short anchor using it

Legal Events

Date Code Title Description
R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

LAPS Cancellation because of no payment of annual fees