JPH0459439B2 - - Google Patents
Info
- Publication number
- JPH0459439B2 JPH0459439B2 JP60070761A JP7076185A JPH0459439B2 JP H0459439 B2 JPH0459439 B2 JP H0459439B2 JP 60070761 A JP60070761 A JP 60070761A JP 7076185 A JP7076185 A JP 7076185A JP H0459439 B2 JPH0459439 B2 JP H0459439B2
- Authority
- JP
- Japan
- Prior art keywords
- arch center
- tunnel
- arch
- center
- internal stress
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
- 238000010276 construction Methods 0.000 claims description 28
- 238000000034 method Methods 0.000 description 15
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 8
- 230000035882 stress Effects 0.000 description 7
- 238000010586 diagram Methods 0.000 description 6
- 238000009415 formwork Methods 0.000 description 4
- 238000005516 engineering process Methods 0.000 description 2
- 229910000831 Steel Inorganic materials 0.000 description 1
- 230000032683 aging Effects 0.000 description 1
- 238000006243 chemical reaction Methods 0.000 description 1
- 238000007796 conventional method Methods 0.000 description 1
- 238000006073 displacement reaction Methods 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 239000003673 groundwater Substances 0.000 description 1
- 239000000463 material Substances 0.000 description 1
- 238000012856 packing Methods 0.000 description 1
- 230000003014 reinforcing effect Effects 0.000 description 1
- 239000004576 sand Substances 0.000 description 1
- 238000000926 separation method Methods 0.000 description 1
- 239000002689 soil Substances 0.000 description 1
- 239000007787 solid Substances 0.000 description 1
- 239000010959 steel Substances 0.000 description 1
- 239000011800 void material Substances 0.000 description 1
- 238000003466 welding Methods 0.000 description 1
Landscapes
- Lining And Supports For Tunnels (AREA)
Description
本発明は、強制変形により内部応力をかけたア
ーチセントル(アーチ型の覆工打設用型枠)を用
いて能率良く且つ経済的にトンネルを構築又は改
修する方法に関するものである。
The present invention relates to a method for efficiently and economically constructing or repairing tunnels using an arch center (arch-shaped formwork for pouring lining) to which internal stress is applied through forced deformation.
従来、トンネルを新築する場合や休線下の既設
トンネルの老朽化に対する修繕補強あるいは複線
化・電化等によるトンネル内空断面の拡大に対し
ての改築を行うトンネル施工時には、セントルと
スキンプレートとを一体化した移動式や組立・解
体を繰り返し行う組立式の型枠を使用し、支保工
もトンネル内に任意に設けることができた。
一方、活線下におけるトンネルの修繕や改築を
行う場合には、トンネル内を列車や車輛が通過す
る空間を確保できる建築限界内においてコンパク
トで且つ充分な剛性を有する堅固な型枠を使用し
てトンネルの覆工を行わねばならないために特殊
なトンネル施工方法が要求され、その代表的な方
法としてはタイバツクアンカーを地山に打ち込ん
で打設したコンクリートの荷重に対してセントル
を固定保持する方法が実施されていた。
Conventionally, when constructing a new tunnel, repairing and reinforcing an aging existing tunnel that is currently closed, or renovating a tunnel to expand the cross-section of the tunnel due to double tracking or electrification, center and skin plates were used. By using integrated movable formwork or prefabricated formwork that can be repeatedly assembled and dismantled, it was possible to install shoring as desired within the tunnel. On the other hand, when repairing or renovating tunnels under live lines, it is necessary to use solid formwork that is compact and has sufficient rigidity within the construction limits to ensure space for trains and vehicles to pass through the tunnel. Because the tunnel must be lined, a special tunnel construction method is required, and a typical method is to drive tieback anchors into the ground to secure and hold the center against the load of the poured concrete. was being carried out.
しかしながらこの従来方法では、地山にタイバ
ツクアンカーを打ち込まなければならないため湧
水の問題がしばしば発生してその止水対策に莫大
な費用を要したり、大きな事故が発生する危険性
を有していた。特に山岳トンネルが施工されてい
る山間部においては、地下水の大部分が地層内に
発達する亀裂、節理、破砕帯等の地質的分離面に
関連して存在しているのでこのような亀裂等を通
る水の流動は土砂の粒子間隙を通過する水の流動
よりも流速が大きく且つ不連続でしかも局所的で
あることが多いため湧水が集中的・突発的に発生
するので、セントルを固定するのにトンネル周辺
の地山に数多くのタイバツクアンカーを打ち込む
方法では湧水に対する止水・危険防止対策に莫大
な費用を要するばかりでなく、工期も大幅に遅れ
るという問題点を有しており、またたとえ湧水の
発生がない場合でも多数のタイバツクアンカーを
打ち込まなければならないのでコスト高な施工方
法であるという問題点があつた。
However, with this conventional method, tieback anchors must be driven into the ground, which often causes problems with spring water, which requires a huge amount of money to stop the water, and has the risk of causing a major accident. was. Particularly in mountainous areas where mountain tunnels are constructed, most of the groundwater exists in connection with geological separation surfaces such as cracks, joints, and fracture zones that develop within the strata. The flow of water passing through the soil is faster than the flow of water passing through the gaps between the grains of the earth and sand, and is often discontinuous and localized, resulting in concentrated and sudden occurrence of spring water, so fix the center. However, the method of driving a large number of tieback anchors into the ground around the tunnel not only requires a huge amount of money to stop the spring water and take measures to prevent danger, but also has the problem of significantly delaying the construction period. Furthermore, even if there is no spring water, a large number of tieback anchors must be driven, resulting in an expensive construction method.
本発明者等は上記従来技術の問題点を解決すべ
く鋭意研究を行つた結果、強制変形により内部応
力をかけてトンネル覆工断面に合わせた所定の形
状を維持させたアーチセントルを利用し、このア
ーチセントルの外側にトンネル面に沿つて取り付
けてられたスキンプレートとトンネル面との空隙
部に剰次コンクリートを打設してトンネルを構築
又は改修すれば上記従来の問題点を完全に解決で
きることを究明して本発明を完成したのである。
すなわち、本発明はトンネル覆工断面より曲率半
径の大きなアーチセントルを製作し、このアーチ
セントルの両端部を強制的に索引してトンネル覆
工断面より曲率半径の小さな曲率半径の外形状に
変形せしめた状態で所望の場所に所要の間隔で元
の形に戻らないように施工トンネル内にくさびを
介して建込んだ後に両端部の索引を解放して該ア
ーチセントルに内部応力をかけた状態として固定
し、次いで該アーチセントルの外側にトンネル面
に沿つてスキンプレートを取り付けてトンネル面
と該スキンプレートとの空隙部に順次コンクリー
トを打設してトンネルを構築又は改修することを
特徴とする強制変形により内部応力をかけたアー
チセントルを利用するトンネル施工方法に関する
ものである。
The present inventors conducted intensive research to solve the problems of the above-mentioned conventional technology, and as a result, they utilized an arch center that maintains a predetermined shape that matches the cross section of the tunnel lining by applying internal stress through forced deformation. The above conventional problems can be completely solved by constructing or renovating a tunnel by pouring surplus concrete into the gap between the tunnel surface and the skin plate attached to the outside of the arch center along the tunnel surface. They investigated this and completed the present invention.
That is, the present invention manufactures an arch center with a radius of curvature larger than the tunnel lining cross section, and forcibly indexes both ends of this arch center to deform the outer shape into an outer shape with a smaller radius of curvature than the tunnel lining cross section. After erecting the arch at the desired location at the required intervals through a wedge in the construction tunnel so that it does not return to its original shape, the indexes at both ends are released and internal stress is applied to the arch center. A method of constructing or repairing a tunnel by fixing the arch center, then attaching a skin plate to the outside of the arch center along the tunnel surface, and sequentially pouring concrete into the gap between the tunnel surface and the skin plate. This invention relates to a tunnel construction method that uses an arch center that is subjected to internal stress due to deformation.
以下、図面に基づいて本発明に係る強制変形に
より内部応力をかけたアーチセントルを利用する
トンネル施工方法について詳細に説明する。
第1図〜第3図はアーチセントルとしてトンネ
ル覆工断面の上部アーチ部のみにアーチセントル
を使用する場合の本発明方法の施工過程の説明
図、第4図はアーチセントルとしてトンネル覆工
断面の上部アーチ部及び側壁部にアーチセントル
を使用する場合の本発明方法の施工状態の説明
図、第5図及び第6図はそれぞれ本発明方法を実
施するために使用するくさびの形状を示す説明図
である。
本発明方法を実施するには、先ず第1図に示す
如くH形鋼等によりトンネル覆工断面より曲率半
径の大きなアーチセントル1を工場において予め
製作し、このアーチセントル1の両端部にチエン
ブロツク、ターンバツクルあるいはレバーブロツ
ク(以下、ターンバツクル等と言う)3を取り付
けておき、このアーチセントル1をトンネル施工
現場に搬入してアーチセントル1の両端部をター
ンバツクル等3を用いて強制的に牽引して第2図
に示す如くトンネル覆工断面より曲率半径の小さ
な曲率半径の所望の外形状に変形せしめた状態で
所望の場所に所要の間隔で元の形に戻らないよう
に施工トンネル内にくさび4を介して建込むので
ある。この建込みを行うに際してアーチセントル
1が上部アーチ部のみを構成する場合には第2図
及び第3図に示す如くその両端部に側壁セントル
2を固定すればよいが、アーチセントル1が第4
図に示す如く上部アーチ部と側壁部とを成すよう
に予め一体に形成されている場合にはその必要は
ない。またこの建込み時に使用するくさび4は、
打設するコンクリートの巻厚を確保すると共にア
ーチセントル1の両端部の牽引を解放した時にア
ーチセントル1と側壁セントル2を使用する場合
にはアーチセントル1と側壁セントル2の地山側
への変位を拘束するためのものであるから、アー
チセントル1の両端部の解放された牽引力がくさ
び4を介して伝達された際にトンネル面を構成す
る地山又は既設のトンネル覆工が充分な強度を有
する場合にはアーチセントル1に螺合されている
先端の尖つたボルトであればよいが、地山又は既
設のトンネル覆工が充分の強度を有しない場合は
ボルトの先端にプレート4aを溶接により固定し
このプレート4aと地山又は既設のトンネル覆工
との間に生ずる間隙にドライパツキング4b等を
充填して荷重を有効に伝達できるものを使用すれ
ばよい。かくして施工トンネル内にくさび4を介
してアーチセントル1を建込んだら、アーチセン
トル1の両端部を強制的に索引しているターンバ
ツクル等3を操作してアーチセントル1の両端部
の索引を解放してアーチセントル1に内部応力を
かけた状態としてアーチセントル1を施工トンネ
ル内にくさび4を介して固定し、次いでアーチセ
ントル1の外側及び側壁セントル2が存在する場
合にはアーチセントル1と側壁セントル2の外側
にそれぞれトンネル面に沿つてスキンプレート5
を取り付けてトンネル面とスキンプレート5との
空隙部6に順次コンクリートを打設してトンネル
を構築又は改修すればよいのである。
Hereinafter, a tunnel construction method using an arch center to which internal stress is applied by forced deformation according to the present invention will be explained in detail based on the drawings. Figures 1 to 3 are explanatory diagrams of the construction process of the method of the present invention when an arch center is used only in the upper arch section of the tunnel lining cross section, and Figure 4 is an illustration of the construction process of the tunnel lining cross section as an arch center. An explanatory diagram of the construction state of the method of the present invention when arch centers are used in the upper arch portion and side wall portions, and FIGS. 5 and 6 are explanatory diagrams showing the shape of the wedge used to implement the method of the present invention, respectively. It is. To carry out the method of the present invention, first, as shown in FIG. 1, an arch center 1 made of H-beam steel or the like having a radius of curvature larger than the cross section of the tunnel lining is manufactured in advance in a factory, and chain blocks are attached to both ends of this arch center 1. , turnbuckles or lever blocks (hereinafter referred to as turnbuckles, etc.) 3 are attached, the arch center 1 is carried to the tunnel construction site, and both ends of the arch center 1 are forcibly pulled using the turnbuckles, etc. 3. As shown in Fig. 2, wedges 4 are placed inside the tunnel to prevent it from returning to its original shape at the desired locations and at the required intervals while the tunnel lining is deformed into a desired external shape with a radius of curvature smaller than the cross section of the tunnel lining. It is built through. When performing this construction, if the arch center 1 constitutes only the upper arch part, it is sufficient to fix the side wall centers 2 to both ends as shown in FIGS. 2 and 3.
This is not necessary if the upper arch part and the side wall part are integrally formed in advance as shown in the figure. Also, the wedge 4 used during construction is
In addition to ensuring the thickness of the concrete to be poured, when using arch center 1 and side wall center 2 when the traction at both ends of arch center 1 is released, the displacement of arch center 1 and side wall center 2 toward the ground should be avoided. Since it is used for restraint, the ground or existing tunnel lining that constitutes the tunnel surface has sufficient strength when the released traction force at both ends of the arch center 1 is transmitted through the wedge 4. In this case, a bolt with a sharp tip screwed onto the arch center 1 may be sufficient, but if the ground or existing tunnel lining does not have sufficient strength, a plate 4a may be fixed to the tip of the bolt by welding. It is sufficient to use dry packing 4b or the like which can be used to effectively transmit the load by filling the gap between the plate 4a and the ground or the existing tunnel lining. After the arch center 1 is thus erected in the construction tunnel via the wedge 4, the indexes at both ends of the arch center 1 are released by operating the turnbuckles etc. 3 that forcibly index both ends of the arch center 1. The arch center 1 is fixed in the construction tunnel via the wedge 4 with internal stress applied to the arch center 1, and then the outside of the arch center 1 and the side wall center 2 are fixed when the arch center 1 and the side wall center 2 are present. 2 along the tunnel surface on the outside of each skin plate 5.
The tunnel can be constructed or repaired by attaching the skin plate and pouring concrete into the gap 6 between the tunnel surface and the skin plate 5 one after another.
【効果】
以上詳述した強制変形により内部応力をかけた
アーチセントル1を利用するトンネル施工方法
は、スキンプレート5を取り付けられるアーチセ
ントル1が施工トンネル内にくさび4を介して建
込まれて固定された状態においてその両端部の索
引を解放されて内部反応力をかけられた状態とな
つているため、タイバツクアンカーを打ち込んだ
り支保工を用いて補強する必要がないので使用部
材の大幅な削減が可能であり、セントルを固定す
るのにトンネル周辺の地山に数多くのタイバツク
アンカーを打ち込む必要がないので湧水の止水対
策に莫大な費用を要したり大きな事故が発生する
危険性がないと共に施工費用が安価で且つ工期も
大幅に短縮できるものであり、特に活性下におけ
るトンネルの修繕や改築を行う場合にトンネル内
を列車や車輛が通過する空間を充分に確保できる
利点も有しており、その工業的価値は非常に大き
なものがある。[Effect] In the tunnel construction method using the arch center 1 to which internal stress is applied through forced deformation as detailed above, the arch center 1 to which the skin plate 5 can be attached is built and fixed in the construction tunnel via the wedge 4. In this state, the indexes at both ends are released and internal reaction force is applied, so there is no need to drive tieback anchors or use shoring to reinforce the structure, resulting in a significant reduction in the number of materials used. This eliminates the need to drive numerous tieback anchors into the ground around the tunnel to secure the center, so there is no need to spend a huge amount of money to stop the spring water, or there is a risk of a major accident occurring. In addition, the construction cost is low and the construction period can be significantly shortened, and it also has the advantage of ensuring sufficient space for trains and vehicles to pass through the tunnel, especially when repairing or renovating the tunnel under active conditions. Its industrial value is extremely large.
第1図〜第3図はアーチセントルとしてトンネ
ル覆工断面の上部アーチ部のみにアーチセントル
を使用する場合の本発明方法の施工過程の説明
図、第4図はアーチセントルとしてトンネル覆工
断面の上部アーチ部及び側壁部にアーチセントル
を使用する場合の本発明方法の施工状態の説明
図、第5図及び第6図はそれぞれ本発明方法を実
施するために使用するくさびの形状を示す説明図
である。
1……アーチセントル、2……側壁セントル、
3……ターンバツクル等、4……くさび、4a…
…プレート、4b……ドライパツキング、5……
スキンプレート、6……空隙部。
Figures 1 to 3 are explanatory diagrams of the construction process of the method of the present invention when an arch center is used only in the upper arch section of the tunnel lining cross section, and Figure 4 is an illustration of the construction process of the tunnel lining cross section as an arch center. An explanatory diagram of the construction state of the method of the present invention when arch centers are used in the upper arch portion and side wall portions, and FIGS. 5 and 6 are explanatory diagrams showing the shape of the wedge used to implement the method of the present invention, respectively. It is. 1... Arch center, 2... Side wall center,
3...Turnbuckle etc., 4...Wedge, 4a...
...Plate, 4b...Dry patching, 5...
Skin plate, 6... void section.
Claims (1)
チセントルを製作し、このアーチセントルの両端
部を強制的に索引してトンネル覆工断面より曲率
半径の小さな曲率半径の外形状に変形せしめた状
態で所望の場所に所要の間隔で元の形に戻らない
ように施工トンネル内にくさびを介して建込んだ
後に両端部の索引を解放して該アーチセントルに
内部応力をかけた状態として固定し、次いで該ア
ーチセントルの外側にトンネル面に沿つてスキン
プレートを取り付けてトンネル面と該スキンプレ
ートとの空隙部に順次コンクリートを打設してト
ンネルを構築又は改修することを特徴とする強制
変形により内部応力をかけたアーチセントルを利
用するトンネル施工方法。 2 アーチセントルとしてトンネル覆工断面の上
部アーチのみに対応するアーチセントルを使用す
る特許請求の範囲第1項に記載の強制変形により
内部応力をかけたアーチセントルを利用するトン
ネル施工方法。 3 アーチセントルとしてトンネル覆工断面の上
部アーチ及び側壁部に対応するアーチセントルを
使用する特許請求の範囲第1項に記載の強制変形
により内部応力をかけたアーチセントルを利用す
るトンネル施工方法。 4 アーチセントルの両端部を強制的に索引する
部材としてチエンブロツクを使用する特許請求の
範囲第1項から第3項までのいずれか1項に記載
の強制変形により内部応力をかけたアーチセント
ルを利用するトンネル施工方法。 5 アーチセントルの両端部を強制的に索引する
部材としてターンバツクルを使用する特許請求の
範囲第1項から第3項までのいずれか1項に記載
の強制変形により内部応力をかけたアーチセント
ルを利用するトンネル施工方法。 6 アーチセントルの両端部を強制的に索引する
部材としてレバーブロツクを使用する特許請求の
範囲第1項から第3項までのいずれか1項に記載
の強制変形により内部応力をかけたアーチセント
ルを利用するトンネル施工方法。[Claims] 1. An arch center with a radius of curvature larger than the cross section of the tunnel lining is manufactured, and both ends of this arch center are forcibly indexed to form an outer shape with a radius of curvature smaller than the cross section of the tunnel lining. In the deformed state, the arch center was erected at the desired location at the required intervals through a wedge in order to prevent it from returning to its original shape, and then the indexes at both ends were released to apply internal stress to the arch center. The tunnel is constructed or repaired by fixing the arch center in a fixed state, then attaching a skin plate along the tunnel surface to the outside of the arch center, and sequentially pouring concrete into the gap between the tunnel surface and the skin plate. A tunnel construction method that uses an arch center that applies internal stress through forced deformation. 2. A tunnel construction method using an arch center to which internal stress is applied by forced deformation as set forth in claim 1, in which an arch center corresponding only to the upper arch of a tunnel lining cross section is used as an arch center. 3. A tunnel construction method using an arch center to which internal stress is applied by forced deformation as set forth in claim 1, which uses an arch center corresponding to the upper arch and side wall portion of the tunnel lining cross section as the arch center. 4. An arch center to which internal stress is applied by forced deformation according to any one of claims 1 to 3, in which a chain block is used as a member for forcibly indexing both ends of the arch center. Tunnel construction method to be used. 5 Utilizing an arch center to which internal stress is applied by forced deformation according to any one of claims 1 to 3, in which a turnbuckle is used as a member for forcibly indexing both ends of the arch center. tunnel construction method. 6. An arch center to which internal stress is applied by forced deformation according to any one of claims 1 to 3, in which a lever block is used as a member for forcibly indexing both ends of the arch center. Tunnel construction method to be used.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP60070761A JPS61229099A (en) | 1985-04-03 | 1985-04-03 | Tunnel construction method utilizing arch centrle to which internal stress was applied by forcible deformation |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP60070761A JPS61229099A (en) | 1985-04-03 | 1985-04-03 | Tunnel construction method utilizing arch centrle to which internal stress was applied by forcible deformation |
Publications (2)
Publication Number | Publication Date |
---|---|
JPS61229099A JPS61229099A (en) | 1986-10-13 |
JPH0459439B2 true JPH0459439B2 (en) | 1992-09-22 |
Family
ID=13440812
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP60070761A Granted JPS61229099A (en) | 1985-04-03 | 1985-04-03 | Tunnel construction method utilizing arch centrle to which internal stress was applied by forcible deformation |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPS61229099A (en) |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP7231434B2 (en) * | 2019-02-18 | 2023-03-01 | 株式会社フジタ | Installation method of reinforcing bar assembly for tunnel secondary lining |
-
1985
- 1985-04-03 JP JP60070761A patent/JPS61229099A/en active Granted
Also Published As
Publication number | Publication date |
---|---|
JPS61229099A (en) | 1986-10-13 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
KR101671123B1 (en) | Tunnel construction method by using pre-support and post-support, and suitable device therefor | |
US4405260A (en) | Method of constructing underpass across railway and highway without affecting normal traffic thereof | |
RU2375523C1 (en) | Formwork for constructing reinforcing covering of construction made from corrugated steel plates | |
KR20170061061A (en) | Tunnel construction method by using pre-support and post-support, and suitable device therefor | |
KR101167511B1 (en) | Underpass using precast concrete pile and method for constructing the same | |
KR20170061060A (en) | Tunnel construction method by using pre-support and post-support, and suitable device therefor | |
US4112694A (en) | Tunnel-lagging element and system | |
JPH0459439B2 (en) | ||
US20210363711A1 (en) | Jacking Force Transfer System for Bridges with Prefabricated Deck Units | |
JPH08193330A (en) | Construction method of strut/beam material in underground structure | |
FREYSSINET | LECTURE ON PRE-STRESSED CONCRETE: PRINCIPLES & APPLICATIONS. JOINT MEETING WITH SOCIETE DES INGENIEURS CIVILS DE FRANCE (BRITISH SECTION). 17 NOVEMBER 1949. | |
JP2831934B2 (en) | How to build substructure | |
JP3446640B2 (en) | Flexible submerged tunnel and its construction method | |
JPS584094A (en) | Method of constructing low road cross | |
JP2021188354A (en) | Precast prestressed concrete foundation structure and its construction method | |
GB2101177A (en) | Method of constructing underpass across railway and highway without affecting normal traffic thereof | |
CN110318372B (en) | Anchor rod butt joint method | |
JPH07310365A (en) | Synthetic retaining wall structure and building method thereof | |
JPH0454037B2 (en) | ||
JPH09184303A (en) | Lining steel plate and reinforcing method for existing columnar body | |
JPS6135359B2 (en) | ||
JPH06117052A (en) | Precast horizontal central pillar | |
JP2560483B2 (en) | Construction method of annular girder in underground wall. | |
JPH0649675Y2 (en) | Tunnel lining structure | |
JPS6241898A (en) | Lining method in method of shielding type tunnel construction |