JPH0454769B2 - - Google Patents

Info

Publication number
JPH0454769B2
JPH0454769B2 JP16112585A JP16112585A JPH0454769B2 JP H0454769 B2 JPH0454769 B2 JP H0454769B2 JP 16112585 A JP16112585 A JP 16112585A JP 16112585 A JP16112585 A JP 16112585A JP H0454769 B2 JPH0454769 B2 JP H0454769B2
Authority
JP
Japan
Prior art keywords
excavation
flange
band
shaped
frame
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP16112585A
Other languages
Japanese (ja)
Other versions
JPS6221927A (en
Inventor
Koichiro Konishi
Hidekazu Sato
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tokyu Construction Co Ltd
Original Assignee
Tokyu Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tokyu Construction Co Ltd filed Critical Tokyu Construction Co Ltd
Priority to JP16112585A priority Critical patent/JPS6221927A/en
Publication of JPS6221927A publication Critical patent/JPS6221927A/en
Publication of JPH0454769B2 publication Critical patent/JPH0454769B2/ja
Granted legal-status Critical Current

Links

Landscapes

  • Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)

Description

【発明の詳細な説明】 <産業上の利用分野> 本発明は土留壁を構築するのに際し、所定の間
隔で地中に打設したH形鋼のフランジ面の裏側に
残存する土砂およびフランジの裏面間を結ぶ側壁
面を機械的に掘削する、土留工における掘削装置
に関するものである。
[Detailed Description of the Invention] <Industrial Field of Application> When constructing an earth retaining wall, the present invention is designed to remove soil and sand remaining on the back side of the flange surface of H-beams cast into the ground at predetermined intervals. This invention relates to an excavation device for earth retaining works that mechanically excavates the side wall surface connecting the back surfaces.

<従来の技術> 一般に簡易な土留壁の構築技術として親杭横矢
板工法が存在する。
<Conventional technology> Generally speaking, the main pile horizontal sheet pile method exists as a simple construction technology for earth retaining walls.

この工法は、あらかじめH形鋼等からなる親杭
を所定の間隔で地中に打ち込んでおき、掘削と並
行して木製等の横矢板を親杭間に差し込んで土留
壁を構築する工法である。
In this construction method, parent piles made of H-shaped steel etc. are driven into the ground at predetermined intervals in advance, and horizontal piles made of wood or other material are inserted between the parent piles in parallel with excavation to construct an earth retaining wall. .

<本発明が解決しようとする問題点> 上記した土留壁の構築技術には、次のような問
題点が存在する。
<Problems to be Solved by the Present Invention> The above-described earth retaining wall construction technology has the following problems.

(イ) 横矢板を親杭内に差し込むためには、各親杭
のフランジの前面を結んだ平面より後退させて
掘削する必要がある。
(b) In order to insert the horizontal sheet piles into the main piles, it is necessary to dig back from the plane connecting the front surfaces of the flanges of each main pile.

この作業は、バツクホー等のバスケツトで親
杭に衝突しないでギリギリまで接近して掘削し
なければならず、バツクホー等の操縦者に高い
操作技術が要求される。
This work requires excavating as close as possible to the parent pile without colliding with a basket hoe, etc., and requires high operating skills from the operator of the bucket hoe.

(ロ) フランジの裏側に残存する土砂は、バツクホ
ー等の掘削機気では掘削できないため、作業員
がスコツプで掘削して除去しなければならな
い。
(b) Earth and sand remaining on the back side of the flange cannot be excavated with excavators such as a box hoe, so workers must excavate and remove it with a shovel.

しかし、スコツプで掘削する作業は多大の労
力と作業時間を必要とするため非能率的であ
る。
However, excavating with a scoop requires a lot of labor and time, and is therefore inefficient.

(ハ) フランジの裏側に残存する土砂を作業員がス
コツプ等で手掘りするといつても、フランジの
隅部まできれいに掘削することは非常に困難で
あり、掘削残しが残存する場合が多い。
(c) Even when workers manually dig the soil remaining on the back side of the flange with a scoop, etc., it is extremely difficult to excavate cleanly to the corners of the flange, and excavation remains often remain.

土砂の掘削残しが残存すると、横矢板の差し
込みに手数がかかる。
If excavated earth and sand remains, it will take time to insert the horizontal sheet piles.

(ニ) 高所でフランジの裏側に残存する土砂を掘削
する場合には、脚立等が使用される。
(d) When excavating soil remaining behind the flange at high places, a stepladder, etc. is used.

しかし、高所での掘削作業は転落事故により
人命を失う場合もあり、大変危険な作業であ
る。
However, excavation work at high places is extremely dangerous work, with people sometimes losing their lives due to falling accidents.

(ホ) フランジの裏側に残存する土砂の掘削作業
は、バツクホー等による機械掘削の終了を待つ
て行われる。
(e) Excavation work for the remaining earth and sand on the back side of the flange will be carried out after waiting for the completion of mechanical excavation using excavators such as box hoes.

そのため全体の作業工程を計画する際、バツ
クホー等の機械掘削の掘削速度にあまり遅れな
いように手掘りを行う人員を計画しなければな
らない。
Therefore, when planning the entire work process, it is necessary to plan the number of people who will carry out manual digging so as not to lag too much behind the excavation speed of machine excavators such as excavators.

しかし、高価な人件費を考慮すると、余分に
人員を確保する事は不経済であり、作業工程を
たてにくい。
However, considering the high labor costs, it is uneconomical to secure extra personnel and it is difficult to plan the work process.

<本発明の目的> 本発明は上記の問題点を解決するためになされ
たもので、各親杭のフランジの裏側およびフラン
ジの裏側間を結ぶ側壁面を一定の深さで効率良く
掘削でき、かつ、これらの掘削作業を安全に行え
る、土留工における掘削装置を提供することを目
的とする。
<Object of the present invention> The present invention was made in order to solve the above problems, and it is possible to efficiently excavate the back side of the flange of each parent pile and the side wall surface connecting the back sides of the flanges to a constant depth, Another object of the present invention is to provide an excavation device for earth retaining works that can safely perform these excavation operations.

<実施例> 以下、図面を参照しながら本発明に係る掘削装
置について説明する。
<Example> Hereinafter, an excavation device according to the present invention will be described with reference to the drawings.

<イ> 掘削装置全体の構成(第1図) 掘削装置1は、エンドレス帯の外周に多数の
掘削刃を有する帯状掘削体2と、この帯状掘削
体2を張架してバツクホー等のアームの先端に
接続するフレーム3で構成する。
<B> Overall construction of excavation equipment (Fig. 1) The excavation equipment 1 includes a belt-shaped excavation body 2 having a large number of excavation blades on the outer periphery of an endless belt, and a belt-shaped excavation body 2 that is stretched over an arm such as a backhoe. It consists of a frame 3 connected to the tip.

<ロ> 帯状掘削体 帯状掘削体2は、各親杭のフランジAの裏側
と各フランジAの裏側を結ぶ側壁面を同時に掘
削する掘削具である。
<B> Band-shaped excavation body The band-shaped excavation body 2 is an excavation tool that simultaneously excavates the side wall surface connecting the back side of the flange A of each parent pile and the back side of each flange A.

帯状掘削体2としては、例えば第2,3図に
示すようにエンドレス状の帯の外周に多数の掘
削刃21を植設したものを使用できる。
As the band-shaped excavation body 2, for example, as shown in FIGS. 2 and 3, an endless band with a large number of excavation blades 21 planted around the outer periphery can be used.

エンドレス状の帯には、公知の鋼製チエーン
等を採用できる。
A known steel chain or the like can be used as the endless band.

掘削刃21の掘削巾は、親杭に差し込む1枚
の横矢板の板厚と等しいか多少厚く掘削できる
寸法とする。
The excavation width of the excavation blade 21 is set to a size that allows excavation to be equal to or somewhat thicker than the thickness of one horizontal sheet pile inserted into the parent pile.

<ハ> フレーム フレーム3は帯状掘削体2の内周側に位置
し、かつ、帯状掘削体2が隣り合うフランジA
の距離の変化に追随して回転掘削を行えるよう
な伸縮機能を持たせて形成する。
<C> Frame The frame 3 is located on the inner circumferential side of the band-shaped excavated body 2, and the flange A where the band-shaped excavated body 2 is adjacent to each other.
It is formed with a telescoping function that enables rotary excavation to follow changes in the distance between the two.

例えばフレーム3の両端には、スプロケツト
31,32を回転自在に設ける。
For example, sprockets 31 and 32 are rotatably provided at both ends of the frame 3.

水平方向に設置したフレーム3の途上には、
伸縮性のバネ等の伸縮材4を鉛直方向に配置し
て取り付ける。
In the middle of frame 3 installed horizontally,
An elastic member 4 such as an elastic spring is arranged and attached in the vertical direction.

この伸縮材4の最下端にはスプロケツト41
を回転自在に設ける。
A sprocket 41 is installed at the bottom end of this elastic material 4.
is provided rotatably.

そして各スプロケツト31,32,41に帯
状掘削体2を巻き掛ける。
Then, the band-shaped excavated body 2 is wrapped around each sprocket 31, 32, 41.

さらにフレーム3の途上にはフレーム3の全
長の伸縮を調節できるように、圧縮状態の調整
バネ33を介在させておく。
Furthermore, an adjustment spring 33 in a compressed state is interposed in the middle of the frame 3 so that the entire length of the frame 3 can be adjusted.

調整バネ33を設けたことにより、親杭の打
設間隔が変化した場合にフレーム3の全長が変
化して確実に追随できる。
By providing the adjustment spring 33, when the driving interval of the parent piles changes, the overall length of the frame 3 changes and can reliably follow the change.

さらに、伸縮材4を設けたことにより、フレ
ーム3が例えば伸長したときは伸縮材4が伸縮
し、また逆にフレーム3が収縮したときには伸
縮材4が伸長するといつた具合に、フレーム3
の伸縮動作に連動して伸縮材4が全長を変化す
るので、帯状掘削体2に一定の緊力を付与でき
る。
Furthermore, by providing the elastic material 4, the elastic material 4 expands and contracts when the frame 3 is expanded, and conversely, when the frame 3 contracts, the elastic material 4 expands.
Since the elastic material 4 changes its entire length in conjunction with the expansion and contraction movement of the belt-shaped excavated body 2, a certain tension can be applied to the band-shaped excavation body 2.

フレーム3の途上には、帯状掘削体2に回転
力を与えられるようにモータ7を配備する。
A motor 7 is disposed in the middle of the frame 3 so as to apply rotational force to the band-shaped excavation body 2.

<ニ> 係合手段 フレーム3の両端近くには、係合輪5を回転
自在に設ける。
<D> Engagement means Engagement wheels 5 are rotatably provided near both ends of the frame 3.

係合輪5は、フランジAの縁部に走行可能に
係合させる目的の部材である。
The engagement ring 5 is a member intended to be engaged with the edge of the flange A so that it can travel.

係合輪5の取り付け位置は、係合輪5がフラ
ンジAの縁部に係合したときに、掘削刃21が
親杭のリブBに接触しない位置とする。
The attachment position of the engagement ring 5 is such that when the engagement ring 5 engages with the edge of the flange A, the excavation blade 21 does not come into contact with the rib B of the parent pile.

なお本実施例では、フランジAに1つだけ係
合輪5を係合させる場合について説明するが、
フランジAの両縁部に抱き合わせるようにして
2つ配置する事も勿論可能である。
In this embodiment, a case will be described in which only one engagement ring 5 is engaged with the flange A.
Of course, it is also possible to arrange two of them so that they are hugged at both edges of the flange A.

<ホ> 昇降手段 掘削装置1は、バツクホー8等のアーム81
に接続して使用する。
<E> Lifting means The excavation device 1 is equipped with an arm 81 such as a backhoe
Use by connecting to.

掘削装置1をアーム81に接続するには、例
えばフレーム3上に吊り下げ用のブラケツト3
4を突設する。
To connect the drilling equipment 1 to the arm 81, for example, a hanging bracket 3 is attached on the frame 3.
4 is installed protrudingly.

このブラケツト34と、アーム81の先端と
をピン等で軸支して着脱自在に構成する。
This bracket 34 and the tip of the arm 81 are pivotally supported by a pin or the like so that they can be attached and detached.

また、アーム81との連結に際して、掘削装
置1の水平度や水平方向における旋回角度を調
節できるよう構成することも可能である。
Further, when connecting with the arm 81, it is also possible to configure the excavation device 1 so that its levelness and the turning angle in the horizontal direction can be adjusted.

次に掘削方法について説明する。 Next, the excavation method will be explained.

<1> バツクホーによる掘削 地中に打設した親杭のフランジAにギリギ
リに接近させてバツクホー8等で掘削する。
<1> Excavation with a backhoe Excavate with a backhoe 8 etc. as close as possible to flange A of the parent pile driven into the ground.

バツクホー8では、フランジAの裏側や、
このフランジAの裏側間を結ぶ側壁面までは
掘削できないので、そのまま土砂が残存して
いる。
In Backhoe 8, the back side of flange A,
Since it is not possible to excavate up to the side wall surface connecting the back sides of this flange A, the earth and sand remains as it is.

<2> 掘削装置のセツト バツクホー8のアーム81の先端に前記構
造の掘削装置1を連結する。
<2> Setting up the excavation rig The excavation rig 1 having the above structure is connected to the tip of the arm 81 of the backhoe 8.

掘削装置1をセツトするバツクホー8は、
開削作業に使用しているものとは別のバツク
ホー8に接続しても良く、また場合によつて
は開削作業に使用しているバツクホー8のバ
ケツトと交換して使用することも可能であ
る。
The backhoe 8 that sets the drilling rig 1 is
It may be connected to a different excavator 8 than the one used for excavation work, and in some cases, it can be used in exchange for the bucket of the excavator 8 used for excavation work.

掘削装置1をアーム81の先端に連結した
ら、アーム81を移動操作して、掘削装置1
を側壁面の掘削を予定する親杭の真上に位置
させる。
After connecting the excavation device 1 to the tip of the arm 81, move the arm 81 to remove the excavation device 1.
Position it directly above the parent pile where the side wall surface will be excavated.

<3> 掘削開始 掘削装置1の帯状掘削体2を回転させなが
ら、掘削装置1を徐々に降下させる。
<3> Start of excavation While rotating the band-shaped excavation body 2 of the excavation device 1, the excavation device 1 is gradually lowered.

このとき、掘削装置1の係合輪5を両親杭
のフランジAに係合させる。
At this time, the engagement ring 5 of the excavation device 1 is engaged with the flange A of the parent pile.

その結果、回転する帯状掘削体2によつて
フランジAの裏側に残存する土砂、および両
フランジAの裏側間を直線で結んだ平面より
後退した側壁面の掘削が進行する。
As a result, the rotating belt-shaped excavation body 2 excavates the earth and sand remaining on the back side of the flange A and the side wall surface receding from the plane connecting the back sides of both flanges A with a straight line.

掘削された土砂は、自然落下して排土され
る。
The excavated earth and sand will fall naturally and be removed.

掘削装置1を降下させる際、フランジAの
縁部間の距離が変化している場合でも、フレ
ーム3がその変化に対応して伸縮するので、
係合輪5がフランジAの縁部から外れる心配
はなく、安定した掘削作業を行える。
When lowering the excavation rig 1, even if the distance between the edges of the flanges A changes, the frame 3 expands and contracts in response to the change.
There is no fear that the engagement ring 5 will come off the edge of the flange A, and stable excavation work can be performed.

<4> 横矢板の設置 掘削装置1による掘削を完了した直後、横
矢板9を掘削済みのフランジAの裏側に差し
込み、擁壁を形成する。
<4> Installation of horizontal sheet piles Immediately after completing the excavation by the excavation device 1, the horizontal sheet piles 9 are inserted into the back side of the excavated flange A to form a retaining wall.

横矢板9の差し込み作業は、少なくとも一
枚以上の横矢板9の差し込み幅分の掘削が終
了した直後に行う。
The insertion work of the horizontal sheet piles 9 is performed immediately after the excavation for the insertion width of at least one horizontal sheet pile 9 is completed.

以上のようにして隣り合う親杭のフランジ
A間に横矢板9を差し込みながら、露出する
地山の全域を被覆して、土留め作業を行う。
As described above, the earth retaining work is performed by inserting the horizontal sheet piles 9 between the flanges A of adjacent parent piles, covering the entire area of the exposed ground.

<5> 掘削装置の撤去 掘削装置1を最下端まで降下させたら、フ
レーム3を強制的に収縮して親杭から撤去し
て、次の掘削予定の親杭間へ移動する。
<5> Removal of excavation rig When the excavation rig 1 is lowered to the lowest point, the frame 3 is forcibly contracted, removed from the parent pile, and moved to the next place between the parent piles scheduled for excavation.

以上の作業を繰り返しながら、順次開削直
後の地山に土留壁を構築していく。
By repeating the above operations, retaining walls are successively constructed on the ground immediately after excavation.

<効果> 本発明は以上説明したようになるから、次のよ
うな効果が得られる。
<Effects> Since the present invention is as explained above, the following effects can be obtained.

(イ) 従来手作業に頼つていたフランジの裏側に残
存する土砂の掘削作業と、隣り合うフランジの
裏側間を結ぶ壁面間の掘削作業を、人力によら
ず機械的に掘削できる。
(b) Excavation of the remaining soil on the back side of flanges, which conventionally relied on manual labor, and excavation between the walls connecting the back sides of adjacent flanges can be done mechanically without manual labor.

従つて、掘削効果が著しく向上し、擁壁の構
築に要する工期を大幅に短縮できる。
Therefore, the excavation effect is significantly improved, and the construction period required for constructing the retaining wall can be significantly shortened.

(ロ) 掘削装置をバツクホー等のアームの先端に取
り付けて掘削できる。
(b) Excavating equipment can be attached to the tip of the arm of a batshoe, etc. for excavation.

従つて、高所であつても人員に頼ることなく
機械的に掘削できるため、作業の安全性が著し
く向上する。
Therefore, even in high places, excavation can be done mechanically without relying on human resources, which significantly improves work safety.

(ハ) 帯状掘削体を選択するだけで、横矢板の板厚
に応じた掘削ができる。
(c) Just by selecting the belt-shaped excavation body, excavation can be performed according to the thickness of the horizontal sheet pile.

そのうえ掘削残しもなく、フランジの裏側の
隅部まで確実に掘削できるので横矢板の差し込
みをスムーズに行える。
Furthermore, there is no excavation left behind, and the back corner of the flange can be reliably excavated, allowing for smooth insertion of horizontal sheet piles.

(ニ) フランジの裏側およびフランジの裏側間に残
存する土砂を機械的に掘削できるので、従来の
ように掘削作業のための作業員の確保や、工程
を熟案する必要から開放された。
(d) Since the earth and sand remaining on the back side of the flange and between the back sides of the flange can be mechanically excavated, it is no longer necessary to secure workers for excavation work or to carefully plan the process as in the past.

(ホ) 掘削装置は、バツクホーの各種建設機械のア
ームの先端にピン等で連結できる構造であるか
ら、着脱作業が容易である。
(E) The excavation equipment has a structure that allows it to be connected to the end of the arm of various types of construction machinery, such as a backhoe, with pins, etc., so it is easy to attach and detach.

(ヘ) 掘削装置はバツクホーの他各種の建設機械の
アームに連結して使用することができ、汎用性
が広い。
(F) The excavation equipment can be used by connecting it to the arm of various construction machines other than Batsukuho, and has a wide range of versatility.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図:掘削装置を使つた土留工の説明図、第
2図:掘削装置の一実施例の説明図、第3図:親
杭周辺の掘削状態の説明図。 1:掘削装置、2:帯状掘削体、3:フレー
ム、4:伸縮材、5:係合輪、8:バツクホー、
31,32,41:スプロケツト。
Fig. 1: An explanatory diagram of earth retaining work using an excavating device, Fig. 2: An explanatory diagram of an embodiment of the excavating device, and Fig. 3: An explanatory diagram of the state of excavation around the main pile. 1: Excavation equipment, 2: Strip excavation body, 3: Frame, 4: Expandable material, 5: Engagement ring, 8: Backhoe,
31, 32, 41: Sprocket.

Claims (1)

【特許請求の範囲】 1 エンドレス状の帯の外周に掘削刃を多数形成
した帯状掘削体と、 前記帯状掘削体の内周側で帯状掘削体に一定の
張力を与えて支持する部材であつて、 バツクホー等のアームとの連結手段及び、 断面H形の親杭のフランジに上下方向に走行可
能に係合する係合輪を有するフレームとからな
り、 地中に打設した前記親杭に沿つて昇降自在に構
成したことを特徴とする、 土留工における掘削装置。
[Scope of Claims] 1. A band-shaped excavation body in which a large number of excavation blades are formed on the outer periphery of an endless band, and a member that supports the band-shaped excavation body by applying a constant tension to the band-shaped excavation body on the inner circumferential side of the band-shaped excavation body. , a connecting means with an arm such as a backhoe, and a frame having an engaging ring that engages with the flange of a main pile with an H-shaped cross section so as to be able to run in the vertical direction. An excavation device for earth retaining works, characterized by being configured to be able to be raised and lowered freely.
JP16112585A 1985-07-23 1985-07-23 Excavator for sheathing work Granted JPS6221927A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP16112585A JPS6221927A (en) 1985-07-23 1985-07-23 Excavator for sheathing work

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP16112585A JPS6221927A (en) 1985-07-23 1985-07-23 Excavator for sheathing work

Publications (2)

Publication Number Publication Date
JPS6221927A JPS6221927A (en) 1987-01-30
JPH0454769B2 true JPH0454769B2 (en) 1992-09-01

Family

ID=15729076

Family Applications (1)

Application Number Title Priority Date Filing Date
JP16112585A Granted JPS6221927A (en) 1985-07-23 1985-07-23 Excavator for sheathing work

Country Status (1)

Country Link
JP (1) JPS6221927A (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4645438B2 (en) * 2005-12-26 2011-03-09 コベルコクレーン株式会社 Continuous groove drilling method

Also Published As

Publication number Publication date
JPS6221927A (en) 1987-01-30

Similar Documents

Publication Publication Date Title
JPH07180154A (en) Endless chain cutter of underground continuous wall excavator
JPH0454769B2 (en)
JP3205485B2 (en) Civil engineering method and device and earth retaining device
JP3867197B2 (en) Method for constructing joint part of underground wall and removal device for joint part forming tool of underground wall
JPH0454768B2 (en)
JPH023706Y2 (en)
US3538629A (en) Method of digging manholes
JPH0454767B2 (en)
JPS61270419A (en) Automatic excavator in sheathing construction
JPS5849653B2 (en) Simple steel sheet pile punching method using an excavator
JPH07119866A (en) Laying construction method of underground buried pipe
JPH04111808A (en) Construction work of sheathing wall for undeground tank
JPH04179731A (en) Simplified underground continuous wall construction method
JP3377444B2 (en) How to build underground side walls
JPH0352816Y2 (en)
JPH0343412B2 (en)
JPH05156639A (en) Method and apparatus for forming digging hole for constructing thin film wall
JPH072734Y2 (en) Detachable bucket
JPH03180614A (en) Construction of retaining wall for underground structure
JPH0434209Y2 (en)
JPH04120319A (en) Work method for slope surface and work machine for slope surface
JP2878784B2 (en) Drilling rig for slope construction
JP2788343B2 (en) Tunnel excavation method and equipment
JPH0633462A (en) Soldier beam horizontal lagging method
JPH05156641A (en) Digging hole forming apparatus for constructing thin film wall