JPH042753B2 - - Google Patents

Info

Publication number
JPH042753B2
JPH042753B2 JP11158685A JP11158685A JPH042753B2 JP H042753 B2 JPH042753 B2 JP H042753B2 JP 11158685 A JP11158685 A JP 11158685A JP 11158685 A JP11158685 A JP 11158685A JP H042753 B2 JPH042753 B2 JP H042753B2
Authority
JP
Japan
Prior art keywords
crane
girder
sides
structures
assembled
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP11158685A
Other languages
Japanese (ja)
Other versions
JPS61270461A (en
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed filed Critical
Priority to JP11158685A priority Critical patent/JPS61270461A/en
Publication of JPS61270461A publication Critical patent/JPS61270461A/en
Publication of JPH042753B2 publication Critical patent/JPH042753B2/ja
Granted legal-status Critical Current

Links

Description

【発明の詳細な説明】 〔産業上の利用分野〕 この発明は超高層建物等における建築物の構築
方法に関するものである。
[Detailed Description of the Invention] [Industrial Application Field] This invention relates to a method of constructing a building such as a super high-rise building.

〔従来の技術〕[Conventional technology]

従来の建築工事においては、一般に標準的なモ
ジユールを用いて設計するものが多く、特に張間
方向に大梁等の中間の架構体を架設する場合は最
上階に設ける場合が多い。
In conventional construction work, standard modules are generally used in many designs, and in particular, when an intermediate frame such as a girder is to be erected in the span direction, it is often installed on the top floor.

しかし、最近の建築工事の動向として、低層部
分の有効利用のためあるいは意匠的な面から中間
階にも大梁等の中間の架構体を架設する建築物の
設計が行なわれてきている。
However, as a recent trend in construction work, buildings are being designed in which intermediate frames such as girders are erected even on intermediate floors in order to make effective use of lower-rise areas or from a design perspective.

従来工法でこれら大梁等の中間の架構体を建築
するには一般的に用いるステージング工法、ベン
ト工法、スライデイング工法等、クレーンの性能
に合わせた組立作業を採用することとなる。
In order to construct intermediate structures such as these girders using conventional construction methods, commonly used assembly methods such as staging methods, venting methods, and sliding methods are employed that are tailored to the performance of the crane.

第7図はステージング工法を示したもので、作
業用のステージ31を先行作業で作成し、その上
に順次大梁2を組み立てて行き、大梁2の仕上げ
作業が完了した時点で下部のステージ31を徹去
する。
Figure 7 shows the staging method, in which a work stage 31 is created in advance, girders 2 are assembled on top of it in sequence, and when the finishing work of girders 2 is completed, the lower stage 31 is assembled. Completely eliminate.

第8図はベント工法を示したもので、ベント3
3部分を先行作業で立ち上げ、その上に大梁2を
組み立てて行き、大梁2の組立完了後、順次ベン
ト31を解体して行く。
Figure 8 shows the vent construction method.
The three parts are set up in advance, the girder 2 is assembled on top of them, and after the assembly of the girder 2 is completed, the vents 31 are sequentially dismantled.

第9図はスライデイング工法を示したもので、
所定の場所にクレーンで組立てができない場合、
まず組立可能な場所の足場34上で大梁2を組み
立て、その後、スライドガーダー35に沿つて大
梁2を移動させる。
Figure 9 shows the sliding method.
If it is not possible to assemble at the designated location using a crane,
First, the girder 2 is assembled on a scaffold 34 at a location where it can be assembled, and then the girder 2 is moved along the slide girder 35.

〔発明が解決しようとする問題点〕[Problem that the invention seeks to solve]

しかし、上記従来工法で大梁等の中間の架構体
の架設を行なうとすると、次のような問題点があ
る。
However, when constructing an intermediate frame such as a girder using the conventional method described above, the following problems arise.

大梁架設に手間を要し、工程が遅延する。 Erection of girders takes time and the process is delayed.

溶接工事、本締工事等、条件の悪い場所での
作業となる。
Welding work, final tightening work, etc. will be performed in locations with poor conditions.

高所での作業工数が増え、安全作業対策に困
難をきたす。
The number of man-hours required to work at height increases, making it difficult to implement safety measures.

揚重機が大型化する。 Lifting machines become larger.

この発明の方法はこのような問題点の解決を図
つたもので、大梁等中間の架構体の架設方法の簡
素化、安全性および建築物全体の品質の確保、工
期短縮を目的としている。
The method of the present invention is intended to solve these problems, and aims to simplify the method of constructing intermediate frames such as girders, ensure safety and quality of the entire building, and shorten the construction period.

〔問題点を解決するための手段〕[Means for solving problems]

この発明の要旨は建物のコア部1等の両側の構
造体の建方を先行させ、昇降装置15を備えたク
レーン10を前記両側の構造体間に架け渡すよう
にして組立て、地組してユニツト化した大梁2等
の架構体を前記クレーン10により所定高さまで
吊上げ、前記両側の構造体間に架設するととも
に、前記両側の構造体の建方の所定高さまで先行
させて行ない、前記クレーン10を前記両側の構
造体に沿つて所定高さまで上昇させる作業を繰り
返すことを特徴とする建築物の構築方法であり、
クレーン10の昇降装置15としては、コア部1
等の両側の構造体の建方完了後の鉄骨および躯体
を直接利用してクライミングするもの、先行する
コア部1よりワイヤー等で吊下げ、巻上装置で巻
上げるもの、先行するコア部1に沿つて設けた昇
降用ラツク装置等が考えられる。
The gist of the invention is to first erect the structures on both sides, such as the core part 1 of the building, and then assemble and assemble a crane 10 equipped with a lifting device 15 so as to span between the structures on both sides. The unitized frame structure such as the girder 2 is hoisted to a predetermined height by the crane 10, and is erected between the structures on both sides, and is carried out in advance of the erection of the structures on both sides to a predetermined height. A method of constructing a building, characterized by repeating the work of raising the structure to a predetermined height along the structures on both sides,
As the elevating device 15 of the crane 10, the core portion 1
Climbing by directly using the steel frame and skeleton after the erection of the structure on both sides of the structure is completed, etc. A rack device for lifting and lowering, etc. installed along the line can be considered.

クレーン10としては、例えば天井走行クレー
ン式のもの等が利用でき、昇降装置15によつて
支持される縦けた11と、縦けた11のレール上
を走行する横けた12および横けた上に取り付け
た巻上装置13とからなるもの等が考えられる
が、必ずしもこの形式に限らない。
As the crane 10, for example, an overhead traveling crane type can be used, and there is a vertical crane 11 supported by a lifting device 15, a horizontal beam 12 running on the rail of the vertical beam 11, and a horizontal crane mounted on the horizontal beam. A configuration including a hoisting device 13 is conceivable, but it is not necessarily limited to this type.

また吊上げる架構体は大梁2その他、これに付
属するブロツク化またはユニツト化された大重量
のものである。
Further, the frame structure to be lifted is the girder 2 and other heavy objects attached thereto, which are made into blocks or units.

〔実施例〕〔Example〕

第5図および第6図は、この発明の大梁2等の
架構体の架設方法を適用する建物の一例を示した
もので、この建物はフロア面積を大きくとつた低
層部3と上層部4の間に大断面の水平方向の吹抜
け5を形成してある。
Figures 5 and 6 show an example of a building to which the method of constructing a frame such as a girder 2 of the present invention is applied. A horizontal atrium 5 with a large cross section is formed in between.

この吹抜け5は建物に向かう風を通過させるこ
とにより、超高層ビル等の周辺で発生する風害を
防止するためのものである。このような大断面の
吹抜け5を設けるため、エレベーター、その他の
設備室を集中させたコア部1は前記吹抜け5の両
側に設け、両コア部1間に一般の部屋あるいはフ
ロア部分等を形成してある。
This atrium 5 is intended to prevent wind damage occurring around skyscrapers and the like by allowing wind toward the building to pass through. In order to provide the atrium 5 with such a large cross section, the core part 1 in which the elevator and other equipment rooms are concentrated is provided on both sides of the atrium 5, and a general room or floor part is formed between both core parts 1. There is.

この実施例では上述のような設計において、吹
抜け5の直上位置およびその上の複数の高さに大
梁2を設けることを想定しており、第1図〜第4
図はこの発明による大梁2の架設方法を示したも
のである。
In this embodiment, in the above-mentioned design, it is assumed that the girder 2 is provided directly above the atrium 5 and at multiple heights above it.
The figure shows a method of constructing a girder 2 according to the present invention.

以下、第1図〜第4図に基づき、その施工手順
を説明する。
Hereinafter, the construction procedure will be explained based on FIGS. 1 to 4.

(1) まず、第1図に示すように、低層部3および
両側の先行コア部1の建方を所定高さまで行な
つた後、先行コア部1間にクレーン10を組立
てる。クレーン10は上面にレールを設けた縦
けた11と、縦けた11間に架け渡した横けた
12と、横けた12上に取り付けた巻上装置1
3からなり、縦けた11を先行コア部1に支持
させてある。
(1) First, as shown in FIG. 1, after the lower part 3 and the leading core parts 1 on both sides are erected to a predetermined height, the crane 10 is assembled between the leading core parts 1. The crane 10 has a vertical girder 11 with a rail on the upper surface, a horizontal girder 12 spanning between the vertical girders 11, and a hoisting device 1 attached to the horizontal girder 12.
3, with a vertical support 11 supported by the preceding core part 1.

これと並行して、現場内で大梁2の鉄骨を地
組し、ユニツト化しておく。
At the same time, the steel frame of girder 2 will be assembled into a unit on site.

次に、上述のように組立てたクレーン10を
利用して地組した大梁2を吊上げ、所定位置に
セツトし、先行コア部1と結合させる。
Next, using the crane 10 assembled as described above, the girder 2 assembled on the ground is lifted, set at a predetermined position, and connected to the preceding core section 1.

(2) 次に、第2図に示すように、コア部1のタワ
ークレーン20を上昇させ、コア部1の先行建
方例えば柱、梁鉄骨の溶接等を行なう。なおタ
ワークレーン20によるコア部1の建方は、例
えば特公昭45−23776号のクライミング工法等
により、ベースクライミングさせて行なうこと
ができる。
(2) Next, as shown in FIG. 2, the tower crane 20 of the core section 1 is raised, and preliminary erection of the core section 1, such as welding of columns and beam steel frames, is performed. The core portion 1 can be erected using the tower crane 20 by base climbing, for example, using the climbing method disclosed in Japanese Patent Publication No. 45-23776.

(3) その後、第3図に示すように、先行させたコ
ア部1の頂部に設置した巻上装置およびワイヤ
ー等からなる昇降装置15を利用して、クレー
ン10の縦けた11部分をクレーン10の動力
および他の動力、油圧機構を用いて所定の高さ
に設置し直す。
(3) After that, as shown in FIG. It is reinstalled at a predetermined height using power, other power, and hydraulic mechanisms.

この位置で、再び地組した大梁2を吊上げ、
所定位置にセツトする。また、これと並行して
既に取付の完了した大梁2上に柱および梁の鉄
骨建方を行ない、コア部1間をつないで行く。
At this position, hoist girder 2 which has been assembled into the ground again,
Set it in place. In addition, in parallel with this, the steel frames of columns and beams are erected on the girder 2 which has already been installed, and the core parts 1 are connected.

(4) 以上の作業を繰り返し、第4図に示すように
順次上方の大梁2の設置および大梁2間の鉄骨
建方を行なう。
(4) Repeat the above operations to install the upper girder 2 and erect the steel frame between the girders 2 in sequence as shown in Figure 4.

最終の大梁2の建方完了後、クレーン10は
解体し、コア部1のタワークレーン20で残り
の鉄骨他、揚重工事を行なう。
After the erection of the final girder 2 is completed, the crane 10 is dismantled, and the remaining steel frame and other parts are lifted by the tower crane 20 of the core section 1.

〔発明の効果〕 大梁等ユニツト化した中間の架構体の架設に
おいて、ステージ、支保工等、仮設部材の組立
て、解体の手間が大幅に削減され、高所での作
業工数も少なくなるため、工期短縮および安全
性の向上が図れる。
[Effects of the invention] When constructing unitized intermediate structures such as girders, the labor required for assembling and dismantling temporary members such as stages and shoring is greatly reduced, and the number of man-hours required for work at high places is also reduced. It is possible to shorten the time and improve safety.

中間の架構体は場内加工場で組立作業を行な
うことができるため品質管理がしやすい。
The intermediate frame structure can be assembled at an on-site processing facility, making quality control easier.

先行した両側の構造体に沿つてセルフクライ
ミングするクレーンを用い、地組した架構体を
直ちに吊上げ、複数の所定の位置に安全に、効
率良く架設することができる。
Using a crane that self-climbs along the preceding structures on both sides, the assembled frame can be immediately lifted up and erected at multiple predetermined positions safely and efficiently.

【図面の簡単な説明】[Brief explanation of drawings]

第1図〜第4図はこの発明の実施例における施
工手順を示す斜視図、第5図は適用する建物の一
例を示す正面図、第6図はその側面図、第7図、
第8図は従来例の正面図、第9図は従来例の斜視
図である。 1……コア部、2……大梁、3……低層部、4
……上層部、5……吹抜け、10……クレーン、
11……縦けた、12……横けた、13……巻上
装置、14……フツク、15……昇降装置、20
……タワークレーン、31……ステージ、32…
…支柱、33……ベント、34……足場、35…
…スライドガーダー。
1 to 4 are perspective views showing construction procedures in an embodiment of the present invention, FIG. 5 is a front view showing an example of a building to which the invention is applied, FIG. 6 is a side view thereof, and FIG.
FIG. 8 is a front view of the conventional example, and FIG. 9 is a perspective view of the conventional example. 1... Core part, 2... Main beam, 3... Low-rise part, 4
... Upper floor, 5... Atrium, 10... Crane,
11... Vertical, 12... Horizontal, 13... Hoisting device, 14... Hook, 15... Lifting device, 20
...Tower crane, 31...Stage, 32...
...Strut, 33...Vent, 34...Scaffolding, 35...
...Slide girder.

Claims (1)

【特許請求の範囲】[Claims] 1 建物の両側の構造体の建方を先行させ、昇降
装置を備えたクレーンを前記両側の構造体間に架
け渡すようにして組立て、地組してユニツト化し
た架構体を前記クレーンにより所定高さまで吊上
げ、前記両側の構造体間に架設するとともに、前
記両側の構造体の建方を所定高さまで先行させて
行ない、前記クレーンを前記両側の構造体に沿つ
て所定高さまで上昇させる作業を繰り返すことを
特徴とする建築物の構築方法。
1. The structures on both sides of the building are erected in advance, and a crane equipped with a lifting device is assembled to span the structures on both sides, and the crane is used to raise the frame structure, which has been assembled into a unit, to a predetermined height. The crane is hoisted up and erected between the structures on both sides, the structures on both sides are erected in advance to a predetermined height, and the crane is repeatedly raised along the structures on both sides to a predetermined height. A method of constructing a building characterized by:
JP11158685A 1985-05-24 1985-05-24 Construction of large beam Granted JPS61270461A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP11158685A JPS61270461A (en) 1985-05-24 1985-05-24 Construction of large beam

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP11158685A JPS61270461A (en) 1985-05-24 1985-05-24 Construction of large beam

Publications (2)

Publication Number Publication Date
JPS61270461A JPS61270461A (en) 1986-11-29
JPH042753B2 true JPH042753B2 (en) 1992-01-20

Family

ID=14565123

Family Applications (1)

Application Number Title Priority Date Filing Date
JP11158685A Granted JPS61270461A (en) 1985-05-24 1985-05-24 Construction of large beam

Country Status (1)

Country Link
JP (1) JPS61270461A (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2600489B2 (en) * 1990-05-18 1997-04-16 鹿島建設株式会社 Super high-rise building

Also Published As

Publication number Publication date
JPS61270461A (en) 1986-11-29

Similar Documents

Publication Publication Date Title
EP0487516B1 (en) Construction apparatus and construction method
JPH04111829A (en) Method for constructing large-span roof
WO2022252829A1 (en) Liftable scaffold, lifting and installation methods thereof, and construction method for prefabricated building
JP2957328B2 (en) Peripheral holding self-elevating construction method
JPH042753B2 (en)
JPH1061193A (en) Method of building steel frame structure and device therefor
JP3453181B2 (en) Working steel stand and method of assembling tower-like structure using the working steel stand
JP2678403B2 (en) Construction method of building structure and connection method of pillar members
JP3841242B2 (en) Elevator parking elevating work table and construction method using it
CN209942195U (en) Construction operation platform of high-rise hollow area
JP3185122B2 (en) All-weather construction method
CN214462403U (en) Elevator shaft tool type steel platform
CN211313314U (en) Steel elevator shaft main structure construction operation platform frame
JP2876991B2 (en) Steel frame method for high-rise buildings
JP2779258B2 (en) Roof lift-up method
JP3002054U (en) Tower crane with multiple main columns as tower mast
JP2796448B2 (en) Building construction method and building construction equipment used for the construction method
JP3439545B2 (en) Construction method of multi-story parking lot
JPH0430213Y2 (en)
JP2766769B2 (en) How to bring in air conditioning equipment
JP2690822B2 (en) Steel construction method for low-rise buildings
JPH0518132A (en) Jack-up type construction method for steel structure such as tower type stereoscopic parking lot
JP2934567B2 (en) Work gondola for multi-story parking lot construction
JP2776128B2 (en) Lifting device for building frame
JPH0317356A (en) Construction of multi-story building

Legal Events

Date Code Title Description
LAPS Cancellation because of no payment of annual fees