JPH04238911A - Construction of underground continuous wall - Google Patents

Construction of underground continuous wall

Info

Publication number
JPH04238911A
JPH04238911A JP106991A JP106991A JPH04238911A JP H04238911 A JPH04238911 A JP H04238911A JP 106991 A JP106991 A JP 106991A JP 106991 A JP106991 A JP 106991A JP H04238911 A JPH04238911 A JP H04238911A
Authority
JP
Japan
Prior art keywords
drilling
groups
group
continuous wall
pit
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP106991A
Other languages
Japanese (ja)
Other versions
JP2971587B2 (en
Inventor
Takatoyo Fujita
孝豊 藤田
Kazuharu Fujito
藤戸 一治
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to JP106991A priority Critical patent/JP2971587B2/en
Publication of JPH04238911A publication Critical patent/JPH04238911A/en
Application granted granted Critical
Publication of JP2971587B2 publication Critical patent/JP2971587B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Bulkheads Adapted To Foundation Construction (AREA)

Abstract

PURPOSE:To raise the accuracy of construction as well as the efficiency of operation by a method in which following pit groups are formed by lapping one ends of one-side pit groups in the non-connected part of the preceding pit group. CONSTITUTION:The ground is vertically excavated by using a multispindle excavator 8 having excavating rods 7 whose axes are arranged in parallel on the same plane. A hardening agent is injected to mix it with excavated soil with stirring to form connected preceding pit groups 2-1 and 2-2 with nonconnected portions, The nonconnected portion 3 between the pit groups 2-1 and 2-2 is excavated to forum following pit groups 2'-3 to construct an underground continuous wall consisting of the pit groups 2-1, 2'-3, and 2-2 which are connected to each other. At the pit 1 on one end of the one-side pit groups in the preceding pit groups 2-1 and 2-2, the pits on one ends of the following pit groups 2'-3 are overlapped for excavation.

Description

【発明の詳細な説明】[Detailed description of the invention]

【0001】0001

【産業上の利用分野】この発明は多軸掘削機を用いた地
下連続壁の施工方法に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method of constructing an underground continuous wall using a multi-axis excavator.

【0002】0002

【発明が解決しようとする課題】軸心が一平面をなし並
列する複数本の掘削ロッドを有する多軸掘削機を用いて
地下連続壁を構築する施工方法は、一般に掘削機が有す
る複数本の掘削ロッドで地盤を垂直に掘削し、掘削ロッ
ドの先端から固化材を吐出して、掘削土と撹拌混合し、
連続する複数の削孔からなる削孔群を形成し、この削孔
群を連続して固化材と掘削土との混合物の固結体からな
る地下連続壁を構築していた。
[Problems to be Solved by the Invention] A construction method for constructing an underground continuous wall using a multi-shaft excavator having a plurality of parallel drilling rods whose axes lie in one plane is generally The ground is excavated vertically with a drilling rod, and solidified material is discharged from the tip of the drilling rod and mixed with the excavated soil.
A drill group consisting of a plurality of continuous drill holes was formed, and this drill group was successively used to construct an underground continuous wall made of a solidified mixture of solidified material and excavated soil.

【0003】上記従来の施工方法では連続する複数の削
孔からなる削孔群を一方向から順次連続して形成し構築
する連続方式、および削孔群を不連続に形成した後、不
連続部分を後行の削孔群で連続して構築する断続方式と
があった。
[0003] The conventional construction methods described above include a continuous method in which a drill hole group consisting of a plurality of continuous drill holes is sequentially formed and constructed from one direction, and a continuous method in which a drill hole group is formed discontinuously and then a discontinuous portion is constructed. There was an intermittent method in which holes were constructed in succession with subsequent drilling groups.

【0004】すなわち、3軸の掘削機を用い断続方式で
施工するには図4のごとく、先ず連続する3個の削孔1
からなる2つの削孔群2−1,2−2を不連続に先行し
形成した後先行の削孔群2,2間の不連続部分3を、3
軸の掘削機を用い、両端側の2つの掘削ロッドをそれぞ
れ先行削孔群2の2つの削孔1において重複して掘削し
後行削孔群2’−3を形成し先行した削孔群2,2間を
連続させていた。
In other words, in order to perform intermittent construction using a three-axis excavator, first drill three consecutive holes 1 as shown in Figure 4.
After forming the two drilling groups 2-1 and 2-2 discontinuously, the discontinuous portion 3 between the preceding drilling groups 2 and 2 is
Using an axial drilling machine, the two drilling rods on both ends are used to overlap the two holes 1 of the preceding drilling group 2 to form a trailing drilling group 2'-3, which is the preceding drilling group. There were 2,2 intervals in a row.

【0005】上記のごとく従来の施工方法では隣接する
削孔群間では、固化体の品質の均質化および連続性を高
めるために、1つの削孔を重複して掘削し、掘削土と固
化材との撹拌、混合が行なわれていた。しかし、掘削土
と固化材との混合が一旦完了した削孔内の混合物は実質
的に十分な強度を有し、再度固化材を混入して混合する
必要性は乏しかった。
[0005] As mentioned above, in the conventional construction method, in order to homogenize the quality of the solidified material and improve continuity, one hole is repeatedly excavated between adjacent drilling groups, and the excavated soil and the solidified material are separated. Stirring and mixing were performed. However, once the mixing of the excavated soil and the solidification material has been completed, the mixture in the borehole has substantially sufficient strength, and there is little need to mix the soil and solidification material again.

【0006】この発明は上記問題点に着目しなされたも
のである。その目的は断続方式で地下連続壁を構築する
に際し、重複し掘削する削孔の数を減じることにより、
作業能率の向上、材料コストの低減を図ることができ、
同時に連続壁の連続性を確保できる地下連続壁の施工方
法を提案するにある。
[0006] The present invention has been made in view of the above-mentioned problems. The purpose is to reduce the number of duplicate drilling holes when constructing an underground continuous wall using the intermittent method.
It is possible to improve work efficiency and reduce material costs.
At the same time, we propose a construction method for underground continuous walls that can ensure the continuity of continuous walls.

【0007】[0007]

【課題を解決するための手段】この地下連続壁の施工方
法は、軸心が一平面をなし並列する複数本の掘削ロッド
を有する多軸掘削機を用いて地盤を垂直に掘削し、固化
材を吐出して掘削土と固化材とを撹拌混合してなる連続
する複数の削孔からなる削孔群を複数不連続に先行して
形成した後、2つの先行削孔群間の不連続部分を掘削し
後行削孔群を形成し、2つの先行削孔群間を連続させる
地下連続壁の施工方法において、前記2つの先行削孔群
の片方の削孔群一端の削孔において重複し後発削孔群を
形成することを特徴とする。
[Means for solving the problem] This underground continuous wall construction method involves excavating the ground vertically using a multi-axis excavator that has multiple parallel drilling rods whose axes lie on one plane. After discharging and stirring and mixing excavated soil and solidification material to form a plurality of discontinuous drilling groups consisting of a plurality of continuous drilling holes, a discontinuous portion between the two preceding drilling groups is formed. In the method of constructing an underground continuous wall that connects two preceding drilling groups by excavating a trailing hole group and connecting two preceding drilling groups, there is overlap in drilling at one end of one of the two preceding drilling groups. It is characterized by forming a group of subsequent drilling holes.

【0008】[0008]

【実施例】以下、図示する実施例により説明する。この
実施例は3本の掘削ロッドを有する掘削機を用い、直線
をなし連続する3個の削孔からなる削孔群を単位として
構築する。削孔群形成の手順は図1(a) のごとく、
平面視一直線をなす地下連続壁を構築すべき位置に沿い
3個の削孔1からなる2つの先行削孔群2−1,2−2
を所定の間隔をあけ不連続に形成する。その後、先行削
孔群2−1,2−2間の不連続部分3を掘削して後行削
孔群2’−3を形成し、先行削孔群間を連続させる。こ
の際に片方の先行削孔群2−1の一端側の削孔1を重複
して掘削する。同様に先行削孔群2−2との間に所定の
間隔をあけ、先行削孔群2−4を形成し、その一端側の
削孔1を重複して不連続部分3を掘削して後行削孔群2
’−5を形成して、先行削孔群間を連続させる。これを
繰返して地下連続壁4を構築する。第2図は、先端に掘
削ビット5、軸のまわりに撹拌翼6があり、先端から固
化材液を吐出する3本の掘削ロッド7を備えた3軸掘削
機8を用い地盤を掘削し、3個の削孔1が連続する2つ
の先行削孔群2−1,2−2を形成し、削孔1内の掘削
土と固化材との混合物9が未硬化の時点で、不連続部3
を掘削して後行削孔群2’−3を形成する状態を示す。
[Embodiments] The following will explain the embodiments shown in the drawings. In this embodiment, an excavator having three drilling rods is used to construct a hole group consisting of three consecutive straight holes as a unit. The procedure for forming drill hole groups is shown in Figure 1(a).
Two preliminary drilling groups 2-1, 2-2 consisting of three drilling holes 1 along the position where an underground continuous wall is to be constructed, which are in a straight line in plan view.
are formed discontinuously at predetermined intervals. Thereafter, the discontinuous portion 3 between the preceding drilling groups 2-1 and 2-2 is excavated to form a subsequent drilling group 2'-3, thereby making the preceding drilling groups continuous. At this time, the holes 1 on one end side of one of the preceding hole group 2-1 are drilled redundantly. Similarly, a pre-drilling group 2-4 is formed with a predetermined interval between the pre-drilling group 2-2, and the discontinuous portion 3 is excavated by overlapping the drilled holes 1 at one end of the pre-drilling group 2-4. Row drilling group 2
'-5 is formed to connect the preceding drilling groups. This process is repeated to construct the underground continuous wall 4. FIG. 2 shows a three-shaft excavator 8 equipped with a drilling bit 5 at the tip, a stirring blade 6 around the shaft, and three drilling rods 7 that discharge solidified material liquid from the tips. The three drilling holes 1 form two continuous preceding drilling groups 2-1 and 2-2, and when the mixture 9 of excavated soil and solidification material in the drilling holes 1 is unhardened, a discontinuous part is formed. 3
This shows the state in which the trailing hole group 2'-3 is formed by drilling the hole group 2'-3.

【0009】3軸掘削機8の一端の掘削ロッド7の位置
は先行削孔群2−1の一端の削孔1を重複して掘削し後
行削孔群2’−3を形成し、先行削孔群2−1,2−2
を連続させる。
The position of the drilling rod 7 at one end of the 3-axis excavator 8 is such that the drilling rod 7 at one end of the preceding drilling group 2-1 is redundantly drilled to form a trailing drilling group 2'-3. Drilling group 2-1, 2-2
Continuing.

【0010】第3図は2本の掘削ロッドを有する2軸掘
削機を用いた2個の削孔からなる削孔群を単位とする実
施例である。この実施例は2個の連続する削孔1からな
る先行削孔群2−1,2−2間の不連続部分3を、片方
の先行削孔群2−1の一端の削孔1を重複して掘削して
後行削孔群2’−3を形成し、先行削孔群2−1,2−
2間を連続せしめ、これを繰返し地下連続壁を構築する
FIG. 3 shows an embodiment in which a drilling group consisting of two holes is used as a unit using a two-shaft excavator having two drilling rods. In this example, the discontinuous portion 3 between the preceding drilling groups 2-1 and 2-2 consisting of two consecutive drilling holes 1 is overlapped with the drilling 1 at one end of one of the preceding drilling groups 2-1. drilling to form the trailing hole group 2'-3, and the preceding hole group 2-1, 2-
The two rooms are made continuous, and this process is repeated to construct an underground continuous wall.

【0011】[0011]

【作用】この発明は以上の構成からなる。この方法によ
ると、先行削孔群と後行削孔群との間は、1つの削孔を
重複して掘削するのみであるので、従来の2つの削孔に
おいて重複する方法に比べ、作業能率の向上、固化材の
節減を図ることができる。
[Operation] This invention consists of the above structure. According to this method, only one hole is redundantly drilled between the preceding drilling group and the following drilling group, so the work efficiency is higher than the conventional method of drilling two holes redundantly. It is possible to improve this and reduce the amount of solidifying material used.

【0012】また、先行削孔群の一端の削孔を重複して
掘削して後行削孔群を形成するので施工の精度が高く、
削孔群間を密に連続させ、連続壁の高い連続性を確保す
ることができる。また、多軸の掘削機を用いるので堅い
地盤や石塊等があっても複数の掘削ロッドが相互に拘束
し合い、軸の曲りを防止できる。
[0012] Furthermore, since the holes at one end of the preceding drilling group are drilled redundantly to form the subsequent drilling group, the accuracy of construction is high;
It is possible to closely connect drill holes and ensure high continuity of the continuous wall. Moreover, since a multi-axis excavator is used, even if there is hard ground or rock blocks, the plurality of excavation rods are mutually restrained and the axes can be prevented from bending.

【0013】[0013]

【発明の効果】この地下連続壁の施工方法によると、多
軸掘削機を用い、作業能率の向上、材料費の低減を図り
、同時に連続壁の高い連続性を確保できる。
[Effects of the Invention] According to this method of constructing an underground continuous wall, using a multi-axis excavator, it is possible to improve work efficiency and reduce material costs, while at the same time ensuring high continuity of the continuous wall.

【図面の簡単な説明】[Brief explanation of the drawing]

【図1】(a) は3軸掘削機を用い形成した削孔群を
単位として地下連続壁を構築する手順を示す平面視の説
明図である。(b) は構築した地下連続壁の平面図で
ある。
FIG. 1(a) is an explanatory plan view showing a procedure for constructing an underground continuous wall using a group of drilled holes formed using a three-axis excavator as a unit. (b) is a plan view of the constructed underground continuous wall.

【図2】(a) は先行削孔群間に後行削孔群を形成す
る状態を示す縦断面図である。(b)は(a) の横断
面図である。
FIG. 2(a) is a longitudinal sectional view showing a state in which a trailing hole group is formed between a preceding hole group. (b) is a cross-sectional view of (a).

【図3】(a) は2軸掘削機を用い形成した削孔群を
単位として地下連続壁を構築する手順を示す平面視の説
明図である。(b) は構築した地下連続壁の平面図で
ある。
FIG. 3(a) is an explanatory plan view showing a procedure for constructing an underground continuous wall using a group of drilled holes formed using a two-shaft excavator as a unit. (b) is a plan view of the constructed underground continuous wall.

【図4】従来の3軸掘削機を用い形成した削孔群を単位
として地下連続壁を構築する手順を示す平面視の説明図
である。
FIG. 4 is an explanatory plan view showing a procedure for constructing an underground continuous wall using a group of drilled holes formed using a conventional three-axis excavator.

【符号の説明】[Explanation of symbols]

1…、削孔、2…削孔群、3…不連続部分、4…地下連
続壁、5…掘削ビット、6…撹拌翼、7…掘削ロッド、
8…3軸掘削機、9…混合物。
1... Drilling hole, 2... Drilling group, 3... Discontinuous part, 4... Underground continuous wall, 5... Drilling bit, 6... Stirring blade, 7... Drilling rod,
8...3-shaft excavator, 9...mixture.

Claims (1)

【特許請求の範囲】[Claims] 【請求項1】  軸心が一平面をなし並列する複数本の
掘削ロッドを有する多軸掘削機を用いて地盤を垂直に掘
削し、固化材を吐出して掘削土と固化材とを撹拌混合し
てなる連続する複数の削孔からなる削孔群を複数不連続
に先行して形成した後、2つの先行削孔群間の不連続部
分を掘削し後行削孔群を形成し、2つの先行削孔群間を
連続させる地下連続壁の施工方法において、前記2つの
先行削孔群の片方の削孔群一端の削孔において重複し後
発削孔群を形成することを特徴とする地下連続壁の施工
方法。
Claim 1: Vertically excavating the ground using a multi-axis excavator having a plurality of parallel drilling rods whose axes are in one plane, discharging a solidification material, and stirring and mixing the excavated soil and the solidification material. After forming a plurality of discontinuous drilling groups consisting of a plurality of continuous drilling holes, drilling a discontinuous portion between the two preceding drilling groups to form a subsequent drilling group, A method for constructing an underground continuous wall that connects two preceding drilling groups, characterized in that the drilling at one end of one of the two preceding drilling groups overlaps to form a subsequent drilling hole group. Continuous wall construction method.
JP106991A 1991-01-09 1991-01-09 Construction method of underground continuous wall Expired - Fee Related JP2971587B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP106991A JP2971587B2 (en) 1991-01-09 1991-01-09 Construction method of underground continuous wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP106991A JP2971587B2 (en) 1991-01-09 1991-01-09 Construction method of underground continuous wall

Publications (2)

Publication Number Publication Date
JPH04238911A true JPH04238911A (en) 1992-08-26
JP2971587B2 JP2971587B2 (en) 1999-11-08

Family

ID=11491239

Family Applications (1)

Application Number Title Priority Date Filing Date
JP106991A Expired - Fee Related JP2971587B2 (en) 1991-01-09 1991-01-09 Construction method of underground continuous wall

Country Status (1)

Country Link
JP (1) JP2971587B2 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104612141B (en) * 2015-02-28 2016-11-30 机械科学研究总院青岛分院 T-shaped agitation driller

Also Published As

Publication number Publication date
JP2971587B2 (en) 1999-11-08

Similar Documents

Publication Publication Date Title
JP5043731B2 (en) Construction method of impermeable walls
US5118223A (en) Multi-shaft auger apparatus and process for forming soilcrete columns and walls and grids in situ in soil
JPS60199112A (en) Ground improvement work by deep layer mixing treatment of cement
JPH04238911A (en) Construction of underground continuous wall
JP3224435B2 (en) Construction method of underground continuous wall
JP4550792B2 (en) Construction method of underground wall
JP2000265797A (en) Construction of tunnel
DE2937009A1 (en) METHOD FOR PRODUCING A TUNNEL BETWEEN TWO TUBES AT DIFFERENT HEIGHTS, E.g. A START IN MINING
JP2000104245A (en) Execution method of diaphragm wall and device thereof
JPH0827775A (en) Three shaft type soil continuous wall construction method
JP2659612B2 (en) Column type continuous underground wall construction method
JPH09119131A (en) Construction method of column row type underground continuous wall and guide plate structure of multishaft auger machine used therefor
JPH11222849A (en) Structure of diaphragm wall and excavating method
JP2960139B2 (en) Construction method of underground continuous wall
JP3058135U (en) Continuous underground wall construction equipment
JP2553991B2 (en) Construction method of continuous wall
JPH07238538A (en) Continuous underground wall construction method
JPH083980A (en) Method for constructing underground wall
JPH07238537A (en) Continuous underground wall construction method
JPH018587Y2 (en)
JP2001241063A (en) Excavator and method for constructing underground column continuous wall using the same
JPH05222721A (en) Connected wall and continuously combined wall having drilling method
JPS6078018A (en) Method and apparatus for constructing rectangular column line type sheathing wall
JPH10306438A (en) Widened wing type ground improving equipment and ground improving method using the equipment
JPH06158646A (en) Method for constructing underground continuous wall

Legal Events

Date Code Title Description
R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

LAPS Cancellation because of no payment of annual fees