JPH04182501A - Precast floor plate supporting method - Google Patents
Precast floor plate supporting methodInfo
- Publication number
- JPH04182501A JPH04182501A JP31149190A JP31149190A JPH04182501A JP H04182501 A JPH04182501 A JP H04182501A JP 31149190 A JP31149190 A JP 31149190A JP 31149190 A JP31149190 A JP 31149190A JP H04182501 A JPH04182501 A JP H04182501A
- Authority
- JP
- Japan
- Prior art keywords
- resin
- floor plates
- height
- girder
- load
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 238000000034 method Methods 0.000 title claims description 13
- 229920005989 resin Polymers 0.000 claims abstract description 17
- 239000011347 resin Substances 0.000 claims abstract description 17
- 125000006850 spacer group Chemical group 0.000 claims abstract description 16
- 239000003795 chemical substances by application Substances 0.000 abstract description 7
- 239000000463 material Substances 0.000 abstract description 5
- 238000009434 installation Methods 0.000 abstract description 3
- 239000003566 sealing material Substances 0.000 abstract description 3
- 230000007547 defect Effects 0.000 abstract description 2
- 229910000831 Steel Inorganic materials 0.000 abstract 1
- 239000010959 steel Substances 0.000 abstract 1
- 238000010276 construction Methods 0.000 description 3
- 230000000694 effects Effects 0.000 description 2
- 239000013013 elastic material Substances 0.000 description 1
- 239000000945 filler Substances 0.000 description 1
- 239000004033 plastic Substances 0.000 description 1
- 229920001225 polyester resin Polymers 0.000 description 1
- 239000004645 polyester resin Substances 0.000 description 1
Landscapes
- Bridges Or Land Bridges (AREA)
Abstract
Description
【発明の詳細な説明】
〔発明の目的〕
(産業上の利用分野)
本発明は、FM梁梁構動物床版の支持方法、特に既設床
版を取り壊し、プレキャスト床版の設置を行なう場合の
床版支持方法に関する。[Detailed Description of the Invention] [Objective of the Invention] (Industrial Field of Application) The present invention provides a method for supporting a FM beam structure slab, particularly when an existing floor slab is demolished and a precast floor slab is installed. Relating to a floor slab support method.
(従来の技術)
従来、既設床版を取り壊し、プレキャスト床版を設置す
る方法としては、交通規制をしたのち、既設床版を取り
壊し、撤去し、桁上を清掃したのち、プレ羊ヤスト床版
を桁上に戴置する方法が知られている。(Prior art) Conventionally, the method of demolishing an existing floor slab and installing a precast floor slab was to restrict traffic, demolish and remove the existing floor slab, clean the girder, and then install a precast floor slab. There is a known method of placing the
この方法は、第5図に示すよう1.:折1−上に戴置さ
れたプレキャスト床版2′内に予め埋め込まれた高さ調
整ボルト3−を使用し、プレキャスト床版2′の設置高
さを基準高さになるよう調節し、ついで第6図に示すよ
うにプレキャスト床版2′と桁り′上面との間にテーパ
ー状のプラスチック製のくさび4′を打ち込み、床版支
持終了後高さ511!ボルト3′を撤去し、ボルト穴及
びプレキャスト床版2′と桁1′の空隙を閤澗材やシー
ル材で充填するというものである。This method consists of 1. as shown in FIG. :Fold 1- Adjust the installation height of the precast floor slab 2' to the reference height using the height adjustment bolts 3- embedded in advance in the precast floor slab 2' placed above, Next, as shown in Fig. 6, a tapered plastic wedge 4' is driven between the precast floor slab 2' and the upper surface of the girder, and the height is 511 mm after the floor slab is supported. The bolts 3' are removed, and the bolt holes and the gaps between the precast slab 2' and the girder 1' are filled with filler material or sealing material.
(発明が解決しようとする課題)
しかしながら、かかる方法はプレキャスト床版の荷重や
通過車輛等の活荷重は、くさびを介して、点で桁上部の
7ランジの端部に伝達されうため、フランジ部分のI%
傷をきたしたり、くさびの形状がテーパー状であるため
、通過車輛の振動で緩みを起し、抜は落ちることもある
。また、くさびは数多く設M1jるが、荷重を点で受け
ているため、必ずしも均一に?7i(を受けることはむ
つかしい。(Problem to be Solved by the Invention) However, in this method, the load of the precast deck slab and the live load of passing vehicles, etc. are transmitted to the end of the 7 langes at the top of the girder at a point through the wedge, so the flange Part I%
Because the wedges are tapered, vibrations from passing vehicles can cause them to loosen, causing them to fall off. Also, although there are many wedges M1j, the load is received at points, so it is not necessarily uniform. 7i (It is difficult to receive.
このような状況で支点間隔が広くなった場合には、床版
にクラック等を発生させるおそれがある。また、桁上面
とプレキャスト床版の下面との高さは必ずしも一定でな
いので、時にはくさびを何枚も重ねて使用することもあ
り、常に安定した状態で上部の荷重を受けることがむつ
かしい。If the fulcrum spacing becomes wide in such a situation, there is a risk that cracks will occur in the floor slab. In addition, the height between the top surface of the girder and the bottom surface of the precast slab is not necessarily constant, so sometimes multiple wedges are used, making it difficult to receive the load from the top in a stable manner at all times.
本発明は、このような問題点を以下述べるところにより
除去せんとするものである。The present invention aims to eliminate such problems as described below.
(発明の構成)
(課題を解決するための手段)
上記目的を達成するため、本発明のプレキャスト床版の
支持方法においては、荷重に対してほぼ同じ容積を維持
しながら変形可能な弾力性を有する容器に主剤・硬化剤
を混合した樹脂を封入してなるスペーサーを桁上に適当
な間隙で配置したのち、その上に高さ調整ボルトを下面
に突出させたプレキャスト床版を#!置することにより
変形させ、このスペーサーを(?して荷重を桁へと伝達
させるものである。(Structure of the Invention) (Means for Solving the Problems) In order to achieve the above object, in the method for supporting a precast deck slab of the present invention, elasticity that can be deformed while maintaining approximately the same volume under load is provided. After placing a spacer made of a container filled with a resin mixed with a base resin and a hardening agent at an appropriate gap on the girder, a precast floor slab with height adjustment bolts protruding from the bottom is placed on top of the spacer. The spacer is deformed by placing the spacer in place, and the load is transmitted to the girder.
く作用)
スペーサーB荷重に対して、はぼ同じ容積を維持しなが
ら、変形可能な弾力性を有する容器に主剤・硬化剤を混
合したのち、樹脂を封入してなるので、桁とプレキャス
ト床版との間にあって、プレキャスト床版の荷重に対し
て、もとに戻ろうとしながらも平に変形し、樹脂の硬化
とともにその変形を維持する。Spacer B: The base material and curing agent are mixed in an elastic container that can be deformed while maintaining approximately the same volume under the load, and then the resin is sealed, so the girders and precast slabs are Under the load of the precast slab, it deforms into a flat shape while attempting to return to its original shape, and maintains its deformation as the resin hardens.
(実施例〉 つぎに本発明の実施例を図面に基いて説明する。(Example> Next, embodiments of the present invention will be described based on the drawings.
第1図は本発明の実施例を示す概略斜視図、第2図は乃
至第4図は施工過程を示すための要部の断面図で、第2
図は第3図のA−A断面図、第3図は第2図のB−B断
面図、第4図はプレキャスト床版の荷重によりスペーサ
ーが変形した状態を示す第3図におけるC−C断面相当
図である。FIG. 1 is a schematic perspective view showing an embodiment of the present invention, and FIGS. 2 to 4 are sectional views of main parts to show the construction process.
The figure is a cross-sectional view taken along line A-A in Figure 3, Figure 3 is a cross-sectional view taken along line B-B in Figure 2, and Figure 4 is a cross-sectional view taken along line C-C in Figure 3 showing the state in which the spacer has been deformed due to the load of the precast slab. It is a cross-sectional equivalent view.
まず、第1図乃至第3図において、術1のフランジ1a
の上面にほぼ同じ容積を維持しながら変形可能な弾力性
を有する素材の容器5a、たとえば、ゴム風船の中に主
剤・硬化剤を混合、封入したl!iI脂5b、たとえば
、樹脂としてポリエステル系樹脂を封入してなるスペー
サー5を適宜の間隔をもって配lし、その上に高さ:I
41!ボルト3を下面に概略設計高さ程度突出させたプ
レ訓せスト床版2をaE31する。ここで1桁1のフラ
ンジ1aの上に配Sされるスペーサー5はプレキャスト
床版2の下面に突出する高さ調整ボルト3を避けて配置
される。First, in FIGS. 1 to 3, the flange 1a of technique 1
A container 5a made of an elastic material that can be deformed while maintaining approximately the same volume on the upper surface of the l! iI resin 5b, for example, a spacer 5 made of a polyester resin sealed therein is arranged at appropriate intervals, and a height: I
41! AE31 is made of a pre-drilled floor slab 2 with bolts 3 protruding from the lower surface to approximately the approximate design height. Here, the spacer 5 disposed on the flange 1a of the single digit 1 is disposed so as to avoid the height adjustment bolt 3 protruding from the lower surface of the precast floor slab 2.
ついで、高さ調整ボルト3を使用し、プレキャスト床版
2の設置f高さを唾1!高さになるよう調整する。この
とき、スペーサー5は桁1とプレ主ヤス]・床版2との
間にあって、プレキャスト床版の押圧に対してもとに戻
ろうとしながらもほぼ同じ容積を111持しながら平伏
に変形し、樹脂の硬化とともに変形を11持する。l!
!脂の硬化に要する時間は、プレキャスト床版をII後
2〜3時間程度が作業性からみて好ましい。Next, use the height adjustment bolts 3 to adjust the installation height of the precast floor slab 2 to 1! Adjust to the desired height. At this time, the spacer 5 is located between the girder 1 and the precast floor slab 2, and although it tries to return to its original shape under the pressure of the precast floor slab, it deforms into a flat state while maintaining approximately the same volume 111. , the deformation remains as the resin hardens. l!
! From the viewpoint of workability, it is preferable that the time required for the hardening of the fat is about 2 to 3 hours after the precast slab is finished II.
樹脂硬化後は高さ調整ボルト3を撤去し、プレキャスト
床版相互間は必要によってPCJI材で緊張し、ボルト
穴及び桁1とプレキャスト床版2との2隙には従来工法
と同様にIll詰材やシール材を充填する。After the resin hardens, the height adjustment bolts 3 are removed, the precast slabs are tensioned with PCJI material as necessary, and the bolt holes and the gaps between the girder 1 and the precast slab 2 are filled with Ill as in the conventional construction method. Fill with material and sealing material.
〔発明の効果]
本発明は、上述のようにしてなるので、っぎの効果を有
する。[Effects of the Invention] Since the present invention is made as described above, it has the following effects.
スペーサーが荷重に対してほぼ同じ容積を維持しながら
変形可能な弾力性を有する容器に主剤・硬化剤を混合し
た樹脂を封入してなるので、桁とプレキャスト床版との
間にあって、プレキャスト床版の荷重に対して、もとに
戻ろうとしながらも空隙に従って、平に変形し、樹脂の
硬化とともにその変形を維持する。The spacer is made of a container with elasticity that can be deformed while maintaining almost the same volume against the load, and is filled with a resin mixed with a main resin and a hardening agent. Although it tries to return to its original shape under the load, it deforms flat according to the gap, and maintains its deformation as the resin hardens.
そのため、上部の荷重は平たい板状の物を介して桁に伝
達されるから、これまでのくさびを用いての支持方法に
おける欠点、すなわち、桁のクラック部分の損傷、床版
のクラックの発生、くさびの抜は落ら等の欠点を除去す
ることができる。Therefore, the load on the upper part is transmitted to the girder through the flat plate-like object, so the drawbacks of the conventional support method using wedges, such as damage to the cracked part of the girder, cracks in the deck slab, etc. Wedge removal can eliminate defects such as falling.
第1図は本発明の実施例を示す概略斜視図、第2図乃至
第4図は施工過程を示すための要部の断面図で、第2図
は第3図のA−A断面図、第3図は第2図のB−8断面
図、第4図はプレキャスト床版の荷重によりスペーサー
が変形した状態を示す第3図におけるC−C断面相当図
、第5図及び第6図は従来例を説明する要部断面図であ
る。
図面において、1は桁、2はプレキャスト床版、3は高
さ調整ボルト、5はスペーサーである。
特許出願人 ショーボンド建設株式会社代理人弁理士
宇 野 晴 高
弟1図
B
第3図
第4図
ノ
第5図
第6図Fig. 1 is a schematic perspective view showing an embodiment of the present invention, Figs. 2 to 4 are sectional views of main parts to show the construction process, Fig. 2 is a sectional view taken along line A-A in Fig. 3, Figure 3 is a cross-sectional view taken along line B-8 in Figure 2, Figure 4 is a cross-sectional view equivalent to line C-C in Figure 3 showing the state in which the spacer has been deformed due to the load of the precast slab, and Figures 5 and 6 are FIG. 2 is a sectional view of a main part explaining a conventional example. In the drawings, 1 is a girder, 2 is a precast floor slab, 3 is a height adjustment bolt, and 5 is a spacer. Patent applicant Shobond Construction Co., Ltd. Patent attorney
Haru Uno Senior disciple Figure 1 B Figure 3 Figure 4 Figure 5 Figure 6
Claims (1)
力性を有する容器に主剤・硬化剤を混合した樹脂を封入
してなるスペーサーを、桁上に適当な間隔で配置したの
ち、その上に、高さ調整ボルトを下面に突出させたプレ
キャスト床版を載置し、上記スペーサーを介して桁に荷
重を伝達することを特徴とするプレキャスト床版の支持
方法。After placing spacers at appropriate intervals on the girders, which are made by filling a resin mixed with a base resin and hardening agent in an elastic container that can be deformed while maintaining almost the same volume under the load, A method for supporting a precast floor slab, comprising placing a precast floor slab with height adjustment bolts protruding from the bottom surface, and transmitting the load to the girder via the spacer.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP31149190A JPH0684608B2 (en) | 1990-11-19 | 1990-11-19 | Precast floor slab support method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP31149190A JPH0684608B2 (en) | 1990-11-19 | 1990-11-19 | Precast floor slab support method |
Publications (2)
Publication Number | Publication Date |
---|---|
JPH04182501A true JPH04182501A (en) | 1992-06-30 |
JPH0684608B2 JPH0684608B2 (en) | 1994-10-26 |
Family
ID=18017875
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP31149190A Expired - Fee Related JPH0684608B2 (en) | 1990-11-19 | 1990-11-19 | Precast floor slab support method |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPH0684608B2 (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US5802652A (en) * | 1995-05-19 | 1998-09-08 | Fomico International | Bridge deck panel installation system and method |
JP2008240347A (en) * | 2007-03-27 | 2008-10-09 | Ihi Corp | Method of stretching precast slab |
JP2014020137A (en) * | 2012-07-19 | 2014-02-03 | Oriental Shiraishi Corp | Precast floor slab and erection method of precast floor slab |
JP2014105457A (en) * | 2012-11-27 | 2014-06-09 | Jfe Steel Corp | Rapid construction bridge, and construction method thereof |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP6372703B2 (en) * | 2014-12-26 | 2018-08-15 | 清水建設株式会社 | Bonding structure and bonding method for precast concrete floorboard |
-
1990
- 1990-11-19 JP JP31149190A patent/JPH0684608B2/en not_active Expired - Fee Related
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US5802652A (en) * | 1995-05-19 | 1998-09-08 | Fomico International | Bridge deck panel installation system and method |
JP2008240347A (en) * | 2007-03-27 | 2008-10-09 | Ihi Corp | Method of stretching precast slab |
JP2014020137A (en) * | 2012-07-19 | 2014-02-03 | Oriental Shiraishi Corp | Precast floor slab and erection method of precast floor slab |
JP2014105457A (en) * | 2012-11-27 | 2014-06-09 | Jfe Steel Corp | Rapid construction bridge, and construction method thereof |
Also Published As
Publication number | Publication date |
---|---|
JPH0684608B2 (en) | 1994-10-26 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
KR100802336B1 (en) | The use of the bearing installation is involved the precast block and it for construction method of the bearing installation and the replacing methodof bearing installation | |
US5826290A (en) | Reusable composite bridge structure and method of constructing and attaching the same | |
JP2004124617A (en) | Bearing replacement method for existing bearing device, and bearing device | |
CN106996190A (en) | Alter-pouring strips mould plate and post-cast strip casting method | |
JP2994222B2 (en) | Construction method of cast-in-place slab of precast concrete girder and its formwork | |
EP1809810B9 (en) | Railway track construction shim and method of constructing railway track | |
JPH04182501A (en) | Precast floor plate supporting method | |
JPH08151675A (en) | Oblique prestressed box culvert and its prestress introducing method | |
JPH1060913A (en) | Installation method for machine equipment | |
EP1114904B1 (en) | Fixing structure and method for the installation thereof | |
JPS59185230A (en) | Installation work for large-size machinery equipment | |
KR101728161B1 (en) | Flatness pad for installation truss girder type deck panels and ceiling mold structure using there of | |
JP2980567B2 (en) | How to replace the bearing device | |
JP3450054B2 (en) | Installation method of floor slab on bridge girder and slab cradle | |
JP7371315B2 (en) | Precast floor slab construction method | |
JPH07138901A (en) | Track structure | |
JP7290940B2 (en) | Seismic isolation device installation member, seismic isolation device stand structure, and construction method for seismic isolation device stand | |
JPH0913383A (en) | Execution method of face of slope | |
JP2022142330A (en) | Method for replacing telescopic device | |
JPH1086113A (en) | Manufacture of slate-cast precast concrete plate | |
JP2002294631A (en) | Structure for mounting horizontal force damping device of structural body and its installation method | |
JPS5824969Y2 (en) | Bearing leveling device | |
JPH06173220A (en) | Installing method for elastic bearing body for structure | |
JPH0571108A (en) | Execution method for multi diameter continuous beam having rc floor plate | |
KR200351731Y1 (en) | Concrete sheeting apparatus For steel box girder bridge |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
LAPS | Cancellation because of no payment of annual fees |